Structure & Infrastructure Planning

Civil Engineer Perspective

Ir. Abdul Aziz Abas P.Eng, C.PEng, Int.PE


PREFACE STRUCTURE & INFRASTRUCTURE PLANNING

Preparation for life…

• As a module of the Integrated Design Project course for the Bachelor of


Civil Engineering programme, Faculty of Civil Engineering, UiTM, Shah
Alam

This program will provide basic overview of all aspects of Structure &
Infrastructure Planning from Civil Engineer’s prospective

Mar 2010 2
STRUCTURE & INFRASTRUCTURE PLANNING

Contents
Introduction
Overview of Civil engineering and facts
Project initiation, Professional Responsibility & Hierarchy
Challenge Faced By Engineers

Structure Plan
Brief discussion on Importance of Structure Plan
Role of Engineer

Infrastructure Plan
Engineer’s Responsibility, Approach & Methodology for infra & services
Planning for ultimate and phase development

Future Challenge
Dealing with new requirements & compliances

Q&A

Mar 2010 3
Introduction
INTRODUCTION STRUCTURE & INFRASTRUCTURE PLANNING

Overview
Civil engineering is a professional engineering discipline that deals with
the design, construction and maintenance of the physical and naturally
built environment.

FACTS

• Engineer deals with facts and figures

• Engineer’s responsibility & liability is for life (has no expiry date


except death)

• Engineer faces huge challenges to defend his works as


“anybody” has capability to query

• Engineer deals with safety of properties and lives

• Engineer converts ideas to reality

Mar 2010 5
INTRODUCTION STRUCTURE & INFRASTRUCTURE PLANNING

CIVIL ENGINEERS

A. SPECIALIST ENGINEERS B. GENERAL ENGINEERS

• Geotechnical Engineer • Planning Engineer


• Earthworks Engineer • Site Engineer
• Roads Engineer • Maintenance Engineer
• Drainage Engineer • Administrative Engineer
• Water Supply Engineer
• Sewerage Engineer Knowledgeable in many subjects but not
• Marine / Port Engineer an expert Of any subject
• Structural Engineer
• Specialist

Knowledgeable in less subjects but an expert


Of that subject(s)

Mar 2010 6
INTRODUCTION STRUCTURE & INFRASTRUCTURE PLANNING

CIVIL ENGINEERS

A. SPECIALIST ENGINEERS B. GENERAL ENGINEERS

• Geotechnical Engineer • Planning Engineer


• Earthworks Engineer • Site Engineer
• Roads Engineer • Maintenance Engineer
• Drainage Engineer • Administrative Engineer
• Water Supply Engineer
• Sewerage Engineer Knowledgeable in many subjects but not
• Marine / Port Engineer an expert Of any subject
• Structural Engineer
• Specialist

Knowledgeable in less subjects but an expert But, the Project Manager / Decision Maker
Of that subject(s) come under this category

Mar 2010 7
INTRODUCTION STRUCTURE & INFRASTRUCTURE PLANNING

Project Initiation

Early stage of a project, Engineer to…

• Appreciate project

• Confirm project’s expectation and milestones

• Conform responsibilities & scope of works

• Establish & confirm line of communication

• Establish Organisation Chart & Programme of works

Mar 2010 8
INTRODUCTION STRUCTURE & INFRASTRUCTURE PLANNING

Typical Organisation Chart

Mar 2010 9
INTRODUCTION STRUCTURE & INFRASTRUCTURE PLANNING

Professional Responsibility & Hierarchy


CLIENT / DEVELOPER

PMC

ARCHITECT / TOWN PLANNER (PSP)

ENGINEERS SURVEYORS Q.S. LANDSCAPE

SPECIALISTS (SP)

MasterplanStage
Design & Implementation Stage

BUILDING WORKS CIVIL & INFRASTRUCTURE WORKS

ARCHITECT (PSP) CIVIL ENGINEER (PSP)

ENGINEERS SURVEYORS Q.S. LANDSCAPE ARCHITECTS SURVEYORS Q.S. LANDSCAPE

SPECIALISTS (SP) SPECIALISTS (SP)

(PSP) Principal Submitting Person


(SP) Submitting Person Mar 2010 1
0
INTRODUCTION STRUCTURE & INFRASTRUCTURE PLANNING

Basic PMC’s / PSP’s Responsibility

• To establish Project’s Terms of Reference

• To establish & obtain approval of Development layout plan

• To obtain Development Order from Local Authority

• To establish Scope of works for Consultants / Contractors

• To establish and monitor implementation schedule

• To coordinate all stages of works

• To administer Tender exercise and award of Tender

• To secure Certificate of Completion & Compliance (CCC)

• To hand-over completed project to Client

Mar 2010 11
INTRODUCTION STRUCTURE & INFRASTRUCTURE PLANNING

Prior Requirement For Engineering Input

Letter Of Appointment (LOA)

Development Order

Development Masterplan Layout

Topographical Survey Plan

Landuse Table

Terms Of Reference / Scope of Works

Development Schedule / Phasing

Mar 2010 12
INTRODUCTION STRUCTURE & INFRASTRUCTURE PLANNING

Challenges faced by Engineers

Frequent Changes of Development Masterplan Layout

Frequent Changes of Landuse

Frequent Changes of Development Schedule / Phasing

• To suit budget constraints

• To suit business strategies

• To suit Authority’s requirement

• To suit crazy ideas

Engineers to attend to promptly, professionally & courteously


Mar 2010 13
Structure Plan
A PLANNING STRUCTURE & INFRASTRUCTURE PLANNING

Structure Plan

Structure Plan (SP) is a written statement that explains strategic policies


and actions concerning the land use development in urban and rural
areas, including steps to:-

Improve physical environment

Improve communications and traffic management

Improve socio-economic levels, encourage economic growth

Enhance rural planning

Facilitate sustainable development

Source : Department of Town and Country Planning, Peninsular Malaysia


Mar 2010 15
A PLANNING STRUCTURE & INFRASTRUCTURE PLANNING

Structure Plan

SP also contains graphs, pictures and sketches to explain policies or


suggestions brought forth

Engineers to provide Infrastructure & Utilities sector

Source : Department of Town and Country Planning, Peninsular Malaysia


Mar 2010 16
A PLANNING STRUCTURE & INFRASTRUCTURE PLANNING

Structure Plan

Structure Plan Functions

To interpret national and regional policies

To establish general objectives, policies and suggestions

To provide a framework for the preparation of local plans

To provide development control guidelines

To draw up decision-making guidelines

To draft a basic development guide

To expound on issues and decisions

Source : Department of Town and Country Planning, Peninsular Malaysia


Mar 2010 17
A PLANNING STRUCTURE & INFRASTRUCTURE PLANNING

Structure Plan

Source : Department of Town and Country Planning, Peninsular Malaysia


Mar 2010 18
Planning Approach
B PLANNING APPROACH STRUCTURE & INFRASTRUCTURE PLANNING

Req’d for Water Supply,


Sewerage, Solid Waste,
Telco & Power planning

DEVELOPMENT MASTERPLAN BY ARCHITECT / PLANNER Mar 2010 20


All Stages
B PLANNING APPROACH STRUCTURE & INFRASTRUCTURE PLANNING

Engineer’s Responsibility
• Engineer to advise on all aspects of engineering

Design Stage

• Engineer to perform all preliminary and detail design works


• Engineer to establish BQs and Engineer’s estimates
• Engineer to establish Specification for engineering works
• Engineer to obtain approvals for engineering works

Tender Stage

• Engineer to involve in Tender exercise

Construction Stage

• Engineer to supervise construction

Post Construction Stage

• Engineer to recommend / issue Certificate of Completion &


Compliance (CCC)

Mar 2010 21
B PLANNING APPROACH STRUCTURE & INFRASTRUCTURE PLANNING

Engineer’s Tasks

Upon obtaining the project,


Engineers to carry out….

Desktop Study

Preliminary Design

Detail Design

Construction Supervision

Mar 2010 22
B PLANNING APPROACH STRUCTURE & INFRASTRUCTURE PLANNING

Engineer’s Tasks

A. DESKTOP STUDY
• To Understand scope of works

• Mandatory site visit

• To confirm site location and


development boundaries

• To familiarize with the site


geographical condition

• To identify adjacent development,


Access, etc.

• To observe & assess site constraints

• To have general idea of existing &


future design system

• To gather information about historical


information

Mar 2010 23
B PLANNING APPROACH STRUCTURE & INFRASTRUCTURE PLANNING

B. PRELIMINARY DESIGN

• To establish conceptual design

• To obtain Client’s agreements

• To obtain planning approval from


respective Authority

Mar 2010 24
B PLANNING APPROACH STRUCTURE & INFRASTRUCTURE PLANNING

C. DETAIL DESIGN

• To establish detail design

• To obtain Client’s agreements

• To obtain design approval from


respective Authority

Mar 2010 25
B PLANNING APPROACH STRUCTURE & INFRASTRUCTURE PLANNING

D. CONSTRUCTION STAGE

• To participate in Tender Evaluation

• To supervise construction

• To control construction progress

• To recommend progress payments

• To comply statutory requirements

• To recommend / issue all Certificates

Mar 2010 26
Infrastructure Planning
INFRASTRUCTURE STRUCTURE & INFRASTRUCTURE PLANNING

A. Engineering Work
Earthworks

B. Infrastructure
Roads
Water Supply
Drainage
Sewerage
Solid Waste
Power Supply
Telecommunication Not Civil but M&E
Structures are part of Civil Engineering and existed in
Infrastructures and buildings works
Mar 2010 28
1 Earthworks
1 EARTHWORKS STRUCTURE & INFRASTRUCTURE PLANNING

Earthworks

Earthworks are engineering works


created through the moving of massive
quantities of soil or unformed rock

Earthworks are not infrastructure but


Engineering works required for civil
infrastructure works

Major Earthworks to provide sound


development’s Platform Levels with
sufficient gradients for engineering
infrastructure and building works

Proposed Implementation Agency :


Developer

Mar 2010 30
1 EARTHWORKS STRUCTURE & INFRASTRUCTURE PLANNING

Aim
Earthworks are crucial for all land development
• To have platform levels above Highest Flood Level

• To obtain balance cut & fill volumes (if possible)

• To have suitable platform levels / gradients for Sewerage & Drainage

• To minimise import of earth

• To suit development phases

• To abide all laws & Guidelines

Proposed Implementation Agency :


Developer

Mar 2010 31
1 EARTHWORKS STRUCTURE & INFRASTRUCTURE PLANNING

Proposed Masterplan On
Topography / Survey Map

Project’s boundary

Mar 2010 32
1 EARTHWORKS STRUCTURE & INFRASTRUCTURE PLANNING

Platform Levels

Max.
Proposed Platform Level Formation

Min.
Freeboard = +1m
Highest Flood Level

Water body

SCHEMATIC OF EARTHWORK CROSS-SECTION

Proposed Implementation Agency :


Developer

Mar 2010 33
1 EARTHWORKS STRUCTURE & INFRASTRUCTURE PLANNING

Balance Cut & Fill

Overall
Total Cut: 200 million cu.m. A
Cut & Fill Total Req’d Fill: 155 million cu.m. B

20% of total cut assumed to be spoilt i.e.


40 million cu.m. (Not suitable for fill) C

Access cut = 5 million cu.m.

A + B - C

LEGEND
Cut Area

Fill Area

Mar 2010 34
1 EARTHWORKS STRUCTURE & INFRASTRUCTURE PLANNING

Principle

• Too much access cut material – Difficult to dispose

• Too much fill material - Difficult to obtain borrow source & Cost

Proposed Implementation Agency :


Developer

Mar 2010 35
1 EARTHWORKS STRUCTURE & INFRASTRUCTURE PLANNING

Suit development phases


Phase 1A

Overall
Total Cut: 62.5 million cu.m.
Total Fill: 19.2 million cu.m.

Project description (Phase 1A)


To provide earthworks platforms for buildings
and utilities areas

Project brief
To carry out earthwork construction works to
form platform levels

To carry out ground treatment works

To dispose off excess and unsuitable


materials

Programme
To be developed in year 2011
Proposed Implementation Agency :
Developer

Mar 2010 36
1 EARTHWORKS STRUCTURE & INFRASTRUCTURE PLANNING

Typical Earthworks

Proposed Implementation Agency :


Developer

Mar 2010 37
2 Roads
2 ROADS STRUCTURE & INFRASTRUCTURE PLANNING

Roads

Definition:

Line of communication (travelled way) using a


stabilized base other than rails or air strips open
to public traffic, primarily for the use of road
motor vehicles running on their own wheels.

Context:

Included are bridges, tunnels, supporting


structures, junctions, crossings and
interchanges. Toll roads are also included.
Excluded are dedicated cycle paths.

Jurisdiction:

Federal Road Ministry of Work (KKR), PWD


State Road State PWD (JKR)
Local Road Local Council
Highways Malaysian Highway Authority

Mar 2010 39
2 ROADS STRUCTURE & INFRASTRUCTURE PLANNING

Aim
Proper roads networks enhance the development success
• To establish roads hierarchy

• To translate Traffic Impact Assessment into roads geometry

• To provide BOMBA access

• To provide sufficient roads widths (ROW)

• To provide roads safety

• To suit development phases

• To abide all laws & guidelines

Mar 2010 40
To Cherating / 2 ROADS STRUCTURE & INFRASTRUCTURE PLANNING

Kertih
Existing Road On
Proposed Masterplan
Layout
Timur

Sg. Ular
Interchange

FR3

LEGEND
Existing Road
Jabor – Jerangau
Gebeng Interchange
Interchange Expressway
Jabor Port Area
Interchange
To Kuantan
To Kuala Lumpur
Mar 2010 41
Future connection
To FR3 near Cherating
To Cherating / 2 ROADS STRUCTURE & INFRASTRUCTURE PLANNING

Kertih
Integration of
Existing And
Proposed Road
Network
FR3
Timur

Sg. Ular
Interchange

FR3 LEGEND
Existing Road
Proposed Road
Jabor – Jerangau Expressway
Gebeng Interchange
Interchange

Jabor
Interchange
To Kuantan
To Kuala Lumpur
Mar 2010 42
To FR3 near
Cherating
To Cherating /
Kertih
2 ROADS STRUCTURE & INFRASTRUCTURE PLANNING

Road Hierarchy

• Primary Road :
Connect Development to External Road

FR3 • Secondary Road :


Timur

Road terminating along Primary Road


Sg. Ular or between Secondary Roads
Interchange

FR3 LEGEND
Primary Road
Secondary Road
Gebeng
Jabor – Jerangau Expressway
Interchange
Interchange

Jabor
Interchange
To Kuantan
To Kuala Lumpur
Mar 2010 43
Higher speed limit
compared to urban 2 ROADS STRUCTURE & INFRASTRUCTURE PLANNING

Rural Abide laws : Road Design


Max design Minimum
Standard speed limit lane width Access control Application
(km/h) (m)
Expressways under
the administration of
JKR R6 120 3.5 Full
Malaysian Highway
Authority (MHA)
Primary roads and
partial access
JKR R5 100 3.5 Partial
highways for the
Federal JKR
Main / secondary
JKR R4 90 3.25 Partial
roads
JKR R3 70 3.0 Partial Secondary roads
Minor roads

Note: JKR R2 is the


JKR R2 60 2.75 None
minimum geometrical
standard for 2-lane
roads
Single-lane minor
JKR R1 40 (5.0)* None
roads (village roads)
Single-lane roads
(roads to restricted
JKR R1a 40 (4.5)* None
areas such as
quarries)

* - Total width of 2-way road Similar criteria as for urban


(Source: Arahan Teknik (Jalan) 8/86 - A Guide on Geometric Design of Roads, Jabatan Kerja Raya Malaysia)
Mar 2010 44
Lower speed limit
compared to rural 2 ROADS STRUCTURE & INFRASTRUCTURE PLANNING

Abide Laws : Road Design


Urban
Max design Minimum
Standard speed limit lane width Access control Application
(km/h) (m)
Expressways under
the administration of
JKR U6 100 3.5 Full
Malaysian Highway
Authority
Arterial roads and
JKR U5 80 3.5 Partial partial access
municipal highways
Arterial / collector
JKR U4 70 3.25 Partial
roads
Collector roads / Local
JKR U3 60 3.0 Partial
streets
Local streets

Note: JKR R2 is the


JKR U2 50 2.75 None
minimum geometrical
standard for 2-lane
roads
Single-lane street (in
JKR U1 40 (5.0)* None
towns)
Single-lane street (as
JKR U1a 40 (4.5)* None in low-cost housing
areas)

* - Total width of 2-way road


Similar criteria as for rural
(Source: Arahan Teknik (Jalan) 8/86 - A Guide on Geometric Design of Roads, Jabatan Kerja Raya Malaysia)
Mar 2010 45
2 ROADS STRUCTURE & INFRASTRUCTURE PLANNING

Suit development phases


Proposed
KPC Interchange

Sg. Ular
Interchange

FR3

by Developer
by Developer / Implementing Body
Gebeng Jabor – Jerangau
Interchange Interchange
Existing roads
Jabor
Expressway
Interchange

Mar 2010 46
2 ROADS STRUCTURE & INFRASTRUCTURE PLANNING

Typical Road Embankment

Note: Dotted line denotes road upgrading


Mar 2010 47
3 Water Supply
3 WATER SUPPLY STRUCTURE & INFRASTRUCTURE PLANNING

Water Supply

Definition:

A water supply system is a system of


engineered hydrologic and hydraulic
components which provide water supply

Context:

Included are water shed, raw water collection,


purification, reservoirs, storage tanks,
transmission and reticulation pipes, pumping
system and plumbing.

Jurisdiction:

Watershed State
Impounding Reservoirs State
Rivers State
Water Supply System SPAN, State Water Providers

Mar 2010 49
3 WATER SUPPLY STRUCTURE & INFRASTRUCTURE PLANNING

Aim
Shortage of Water Supply leads to crisis
• To provide ultimate water demand

• To provide 1-day storage requirement

• To adopt gravity supply system (priority)

• To adopt gravity – pumping – gravity supply system


(2nd priority)

• To identify and establish water supply reserves

• To provide reticulation system to meet dominant flow


condition

• To suit development phases

• To abide all laws & guidelines

Mar 2010 50
3 WATER SUPPLY STRUCTURE & INFRASTRUCTURE PLANNING

Water Supply
LEGEND
Main Pipelines (primary) System
Main Reticulation (Secondary)
External Storage (Primary) (Ultimate)
R7

R5
Timur

R6
6
R4
5
R2
R9 3
R8 1

R1 2
4
R3

Water Supply Zones


Jabor
Interchange
From Treatment
To Kuala Lumpur
Plant
Mar 2010 51
3 WATER SUPPLY STRUCTURE & INFRASTRUCTURE PLANNING

Establish Dedicated Reserves

Water reserve area


Mar 2010 52
3 WATER SUPPLY STRUCTURE & INFRASTRUCTURE PLANNING

To Cherating
Phase 1A
(2011-2015)
Project Description
R7 Pipeline from Semambu TW to R1,
Balancing Tank (R1) Stage 1, Service
Tanks R3, R4, R5 and R7, Main
R5 Pipelines & Main Reticulation Pipelines.
Timur

Project Brief
• To meet water demand & Storage
for Phase 1A.
R4
• 1800mm dia new pipeline, 10m
wide reserve from WTP to
Development.

• Land acquisition approx. 58 acres


R1 (including tank reserves).

Project Description
R3 R12
• Duration - 9 month (Land
Acquisition) and 4 years
(Construction)
Jabor LEGEND
Interchange Level 1 (Main Pipeline)
From Water Level 2 (Main Reticulation)
To Kuala Lumpur Level 1 (Storage Tank)
Treatment Plant Existing Tank
Existing Pipelines Mar 2010 53
3 WATER SUPPLY STRUCTURE & INFRASTRUCTURE PLANNING

Typical Water Storage System

Mar 2010 54
4 Drainage
4 DRAINAGE STRUCTURE & INFRASTRUCTURE PLANNING

Drainage

Definition:

A drainage system, the pattern formed by the


streams, rivers, drains and ponds in a particular
drainage basin (catchment).

Jurisdiction:

Watershed State DID


Impounding Reservoirs State DID
Rivers State DID
Main Drain System State DID
Local Drain Local Council

Mar 2010 56
4 DRAINAGE STRUCTURE & INFRASTRUCTURE PLANNING

Aim
Proper Drainage System guarantee safety of lives & property
• To provide development free from flood

• To control excess run-off water at source

• Not to affect (nuisance to) surrounding development

• To integrate with main established drainage system

• To complement earthwork platforming

• To establish drainage reserves

• To suit development phases

• To abide all laws & guidelines

Mar 2010 57
4 DRAINAGE STRUCTURE & INFRASTRUCTURE PLANNING

Development Free From Flood Threat

SCHEMATIC OF DEVELOPMENT CROSS-SECTION

Mar 2010 58
4 DRAINAGE STRUCTURE & INFRASTRUCTURE PLANNING

Observe Existing Drainage


System

Four main rivers form major drainage


artery

- Sg. Balok

- Sg. Ular

- Sg. Pengorak

- Sg. Baging.

Jabor
Interchange

Mar 2010 59
4 DRAINAGE STRUCTURE & INFRASTRUCTURE PLANNING

Integration of Existing
And Proposed
Sg. Baging
Drainage System

Sg. Ular
Timur

LEGEND
Existing Rivers And Drains
Proposed Drainage System
Proposed Detention Pond
Jabor
Interchange
Drainage reserve area Existing Drain (Upgrade)

Mar 2010 60
4 DRAINAGE STRUCTURE & INFRASTRUCTURE PLANNING

Drainage System
POND 10 (Ultimate)
Sg. Baging

POND 1 • To provide drainage system


to JPS guidelines
Sg. Ular
POND 2
POND 3
• Mainly laid along main roads
Timur

POND 9
POND 12 • Off main drain using berms
for maintenance
POND 11

• Drain reserves 8m, 10m &


12m
POND 4
POND 5
• 12 Detention Ponds
POND 7

POND 8
LEGEND
Main Drain (Primary)
POND 6
Main Drain (Secondary)
Detention Pond (Primary)
Jabor
Interchange Existing Drain (Upgrade)

Mar 2010 61
4 DRAINAGE STRUCTURE & INFRASTRUCTURE PLANNING

Control of Excess Run-Off Water

Detention Pond Size = 3% of Area


Mar 2010 62
To Cherating
4 DRAINAGE STRUCTURE & INFRASTRUCTURE PLANNING

Drainage Phase 1A
(2011 - 2015)
Sg. Baging

POND 1

Sg. Ular Project Description


POND 2
POND 3
Drainage system, detention
ponds and related works for
Timur

phase 1A.

Project Brief
• To provide drainage
system to JPS guidelines
POND 4 • Land acquisition ≈ 96 Ha
POND 5
Programme
• To be developed in year
2011
• Construction Duration 49
Months
POND 6

Jabor LEGEND
Interchange Main Drain (Primary)
To Kuala Lumpur
Main Drain (Secondary)
Detention Pond (Primary) Mar 2010 63
4 DRAINAGE STRUCTURE & INFRASTRUCTURE PLANNING

Typical Storm Water Drainage System

Mar 2010 64
5Sewerage
5 SEWERAGE STRUCTURE & INFRASTRUCTURE PLANNING

Sewerage

• A system for transporting sewage

• Connected sewerage systems comprise a network of underground sewer


pipes, pump stations, sewage treatment plants and sludge treatment
facilities.

• Generally operate by gravity.

• Sewage treatment plants located at lowest ground platform

development STP at lowest point


development
development of development

Gravity flow

Mar 2010 66
5 SEWERAGE STRUCTURE & INFRASTRUCTURE PLANNING

Aim
Proper Sewerage System leads to clean & fresh environment
• To provide centralised and sustainable sewerage
system

• To integrate with main established sewerage system

• To complement earthwork platforming

• To establish sewerage reserves

• To suit development phases

• To abide all laws & guidelines

Sewerage reserve area


Mar 2010 67
5 SEWERAGE STRUCTURE & INFRASTRUCTURE PLANNING

Old System
Individual Septic Tank

Mar 2010 68
5 SEWERAGE STRUCTURE & INFRASTRUCTURE PLANNING

Centralised System (Present Concept)


STANDARD ‘A’ - UPSTREAM STANDARD ‘B’ - DOWNSTREAM

Source : IWK
Mar 2010 69
5 SEWERAGE STRUCTURE & INFRASTRUCTURE PLANNING

Treatment Process

Source : IWK
Mar 2010 70
To Cherating
5 SEWERAGE STRUCTURE & INFRASTRUCTURE PLANNING

Sewerage
Masterplan
LS1
(Ultimate)
LS2

LS3 Catchment Area


STP1
• Catchment 1 approx. 230,000 PE
Timur

LS4 • Catchment 2 approx. 85,000 PE


• Catchment 3 approx. 50,000 PE

LS5
• Total Demand approximate 365,000
PE
STP2
Objectives
LS6
LS7
To avoid environmental degradation
STP3 To centralize system

LEGEND (All primary)


Sewerage Trunk Main

Jabor Sewerage Treatment Plant


STP
STP2
Interchange
Sewerage Lifting Station
LS
Sludge Treatment Facility
(by SPAN) Mar 2010 71
To Cherating
5 SEWERAGE STRUCTURE & INFRASTRUCTURE PLANNING

Sewerage to suit
Development Phases
Phase 1A

LS3 Project Description


STP1
Timur

To provide Sewage Treatment Facility to


SG. ULAR I/C Phase 1A development.

LS5 • 20 km Pipelines
• 3 STP (Modular construction)
• STP1 – 46,000PE x 2
STP2
• STP2 – 42,500PE x 1
• STP3 – 25,000PE x 1

STP3 • 2 Lifting Stations (LS 3 & 5)

LEGEND (All Level 1) Proposed Implementation Agency :


Sewerage Trunk Main SPAN
Jabor
Interchange Sewerage Treatment Plant
STP
STP2
To Kuala Lumpur Sewerage Lifting Station
LS
Phase 1A Mar 2010 72
5 SEWERAGE STRUCTURE & INFRASTRUCTURE PLANNING

Typical Sewerage Installation

Mar 2010 73
6 Solid Waste
6 SOLID WASTE STRUCTURE & INFRASTRUCTURE PLANNING

Solid Waste

Solid wastes are defined as wastes arising from human and animal
activities that are normally solid and unwanted

Municipal solid waste (MSW), also called urban solid waste, is a


waste type that includes predominantly household waste (domestic
waste

Main Waste Categories


1. Municipal Solid Waste
2. Harzardous Waste
3. Agricultural Waste
4. Industrial Waste

Mar 2010 75
6 SOLID WASTE STRUCTURE & INFRASTRUCTURE PLANNING

Aim

Proper disposal of solid wastes leads to safe & healthy living


• Prevent the creation of waste, or reduce the amount generated

• Reduce the toxicity or negative impacts of the waste that is generated

• Reuse in their current forms the materials recovered from the waste stream

• Recycle, compost, or recover materials for use as direct or indirect inputs to


new products

• Recover energy by incineration, anaerobic digestion, or similar processes

• Reduce the volume of waste prior to disposal

• Dispose off waste in an environmentally sound manner, generally in landfills

Mar 2010 76
6 SOLID WASTE STRUCTURE & INFRASTRUCTURE PLANNING

Solid Waste
Existing Situation
• 13 ha. existing Municipal Landfill
Jabor –Jerangau.
LPT2
• Serves Kuantan Area (un-scheduled
waste)
• Scheduled waste transfer to Bt.
Nenas

Existing landfill
Jalan Jabor Future Situation
Jerangau
• New centralised disposal site at
Pulau Manis

Jabor – Jerangau
Interchange
Jabor
Interchange

Mar 2010 77
Proposed Centralised
Solid Waste Disposal
(Jerantut)
6 SOLID WASTE STRUCTURE & INFRASTRUCTURE PLANNING

Solid Waste

Proposed Centralised
Solid Waste Disposal
(Pulau Manis)
Proposed Centralised
Solid Waste Disposal
(Raub)

Proposed Centralised
Solid Waste Disposal
(Temerloh)

Source : JPBD Pahang 2006 Mar 2010 78


6 SOLID WASTE STRUCTURE & INFRASTRUCTURE PLANNING

Typical Earthfill Disposal Site

Mar 2010 79
6 SOLID WASTE STRUCTURE & INFRASTRUCTURE PLANNING

Hazardous & Industrial Wastes


RECYCLABLE & RECOVERABLE WASTES

• Oil Waste
• Alkaline Waste
• Acid Waste
• Solvent Waste
• Paint Waste
• Metal Hydroxide Sludge
• Spent Photographic Waste
• Used Containers (Plastic & Metal)
• E-Waste
• Solder Dross

Managed by Kualiti Alam Sdn Bhd

A subsidiary of

Source : Kualiti Alam Mar 2010 80


KA undertakes the Privatisation of Malaysia's 1st
6 SOLID WASTE STRUCTURE & INFRASTRUCTURE PLANNING

Hazardous & Industrial Wastes


Integrated Hazardous Waste Management System on
18 December 1995

Bukit Nanas Waste Management Centre (“WMC”)


commenced operations in 1997

KA provides complete management of hazardous waste from “cradle to grave”,


commencing from collection of waste at the premises of waste generators,
transportation, treatment, to final disposal.

Source : Kualiti Alam Mar 2010 81


7 Power Supply
To Cherating
7 POWER SUPPLY STRUCTURE & INFRASTRUCTURE PLANNING

Existing Power Supply


System On Masterplan
Layout

Existing 132 kV line


Power Reliability & Quality
Timur

● Availability of reliable power supply


SG. ULAR I/C ● Quality i.e. Voltage Sag / Dip, etc

In planning

● To have clear Demarcation of


Utilities
1 2 Corridors to minimize fault.

LEGEND
1 Gebeng Industrial 275kV Substation
Jabor – Jerangau
Jabor Interchange
Interchange
2 Gebeng 132kV Substation
STP2
3 Sg Gelang 132kV Substation
To Kuala Lumpur
Mar 2010 83
7 POWER SUPPLY STRUCTURE & INFRASTRUCTURE PLANNING

Power Supply System

SS9
Distribution of Sub-Stations
And Coverage Areas

SS1
SS2
LPT2 SS8

SS3

SS12 SS11

SS5
SS10

SS7

SS6
OVERALL PHASE

COVERAGE AREA OF SS1 COVERAGE AREA OF SS9

COVERAGE AREA OF SS2 COVERAGE AREA OF SS10


Proposed 132 kV COVERAGE AREA OF SS3 COVERAGE AREA OF SS11
line COVERAGE AREA OF SS5 COVERAGE AREA OF SS12
Jabor COVERAGE AREA OF SS6 EXISTING 132Kv LINE
Interchange COVERAGE AREA OF SS7 EXISTING 275Kv LINE
COVERAGE AREA OF SS8 SS SUBSTATION (130M X
130M
Mar 2010 84
To Cherating
7 POWER SUPPLY STRUCTURE & INFRASTRUCTURE PLANNING

Power Supply to suit


Development phases
Phase 1A

Existing 132 kV line


Project Description
Timur

SS2
SS1 Construction of ;
SG. ULAR I/C
6 numbers of 132/33/11kV Substation
SS3
3 km of 132kV Transmission Line

Project Brief
SS5 To facilitate distribution of electricity
To meet eventual electrical demand
SS7
Programme
SS6 2009 to 2020

Proposed 132 kV
line
Jabor
Interchange

To Kuala Lumpur
Mar 2010 85
8 Telecommunication
To Cherating
8 TELECOMMUNICATION STRUCTURE & INFRASTRUCTURE PLANNING

Existing
Telecommunication On
Masterplan Layout
Timur

SG. ULAR I/C

Jabor – Jerangau
Interchange
LEGEND
Jabor
Interchange
EXISTING MAIN TRUNC ROUTING
To Kuala Lumpur
Mar 2010 87
To Cherating
8 TELECOMMUNICATION STRUCTURE & INFRASTRUCTURE PLANNING

Telecommunication
Phase 1A

Project Description
Rerouting of the Telecommunication
Main Trunk from FR3
Timur

SG. ULAR I/C Project Brief


Length 9.75km
Allow Expansion of Kuantan Port 2nd
Phase

Programme
2018 to 2019

Jabor – Jerangau
Interchange

LEGEND
Jabor
Interchange PROPOSED RELOCATION OF
MAIN TRUNK ROUTE
To Kuala Lumpur
Mar 2010 88
8 Typical Telecommunication Tower
TELECOMMUNICATION STRUCTURE & INFRASTRUCTURE PLANNING

Mar 2010 89
9
Services Coordination
To Cherating
9 SERVICE COORDINATION STRUCTURE & INFRASTRUCTURE PLANNING

Services Coordination
On Masterplan Layout
Sg. Baging

R7
POND 1
Phase 1A
Sg. Ular
LS3
R5 POND 2
POND 3
STP1
SS1 SS2

S2

LS5
R4

SS5
STP2
POND 4

POND 5 ESS
SS7 ESS
R1
SS6 STP3

R3 ESS

POND 6
Structure & Infrastructure planning
Jabor
Interchange
crucial for sustainable development
Mar 2010 91
9 SERVICE COORDINATION STRUCTURE & INFRASTRUCTURE PLANNING

Typical Services Coordination

Mar 2010 92
10
Future Challenge
10 LATEST REQUIREMENT STRUCTURE & INFRASTRUCTURE PLANNING

• Rain Water Harvesting

• Infiltration Drainage

• Water Recycling (Not yet implemented in Malaysia)

• Green Technology (Reducing carbon emission & safe of energy)

• Solar panel

• Broadband Technology

Mar 2010 94
Thank You
Terima Kasih
Questions & Answers