PML3_US_EHLV_01

Cutting Details
Section Road Footpath Embankment Total
Length Cutting Cutting in Cutting in HDD in Length
Sr.No. Section in meter in meter meter meter meter in meter
1 L1 440 0 0 440 0 440
2 L2 441 0 0 441 0 441

3 L3 450 0 0 288 132 420


4 L4 421 406 406
5 L5 431 260 171 431
6 L6 441 0 0 441 0 441
7 L7 441 427 0 14 0 441

8 L8 451 451 0 0 0 451


9 L9 462 100 249 113 462
10 L10 551 150 341 0 60 551
11 L11 561 80 481 0 0 561

12 L12 570 158 412 0 0 570

13 L13 562 151 0 0 0 151

14 L14 566 566 0 0 0 566

15 L15 526 526 0 0 0 526

16 L16 531 338 0 193 0 531

17 L17 541 541 0 0 0 541

18 L18 501 501 0 0 0 501


Total 8887 4249 1234 2643 305 8431
Remark
Width of trench up to 2meter
Width of trench up to 2meter
Width of trench up to 2meter
and Bridge length 30 meter
Bridge length 15 meter
Width of trench up to 2meter
Width of trench up to 2meter
Width of trench up to 2meter
road cutting length up to 251
meter , width 3 to 4meter
meter due to existing 220 KV
UG cable and metro rail pillar
and Road cutting length upto
200 meter width 2 meter
Width of trench up to 2meter

Road cutting permission for


this section is included under
permission from jambhulkar
chowk to wipro circle part of
L12 ,L13 ,L14,L15 and L16.

151 meter Road cutting


permission recevied but 411
meter length road cutting
permission required.

Road cutting permission


recevied

Road cutting permission


recevied
Road cutting permission
recevied
541 meter road cutting
permission required
501 meter road cutting
permission required