Professional Documents
Culture Documents
1.0 INTRODUCTION
1
2 PRE-STRESSED CONCRETE FRAME
2
3 PRE-STRESSED CONCRETE FRAME
As reference to the related topic of pre-stressed concrete, there are 2 different types of
projects that were taken as case study for pre-stressed concrete. Next, both projects used
different type of pre-stressed concrete method that are pre-tensioning concrete and post-
tensioning concrete. The details for each project such as the location, type of project, the
parties involved for the project and others will be clarify in the table below;
3
4 PRE-STRESSED CONCRETE FRAME
The pre-stressed concrete has two primary classifications, namely pre-tensioned and
post-tensioned (Savani, 2015). The structural strengths of steel and concrete were used
for all of those approaches. Under these techniques, the concrete was shown to have a
strong compression strength but poor tension strength.
3.1 PRE-TENSIONING
Pre-tensioning method can be referred as the tension is applied to the tendons before
casting of the concrete. The pre-tensioned is transmitted from steel to concrete through
bond over the transmission length near the ends. This technique established a strong
connection between the tendon and the concrete, which both protects the tendon from
corrosion and enable stress to be transferred directly. The healed concrete adheres and
bonds to the bars, and when stress is released, it is transferred by static friction to the
concrete as compression. However, it needs stout anchoring points to stretch the tendon
between, at the tendons usually forms a straight line.
Regarding to the project, the infrastructure developed due to the bonding between the
concrete and steel tendons. The project used pre-tensioned method is cheaper because
the cost sheeting is not involved. Thus, this method used by the infrastructure project as it
is more reliable and easier to transport. Last but not least, the pre tensioning is proper to
be used in precast element.
4
5 PRE-STRESSED CONCRETE FRAME
Post-tensioning method is similar to the pre-tensioning but until after the concrete is
hardened, the steel does not get stretched. In general, ducts are shaped through thin-
walled steel shapes inside the unit. Those same steel tendons are inserted and extended
against the unit after the concrete extends to the proper length. According to Savani (2015),
the post tensioning is the method for strengthening concrete. In the shapes before the
concrete is set, the steel wire to be placed. Afterwards, the cables are pulled close and
anchored against the outer edges of the concrete until the concrete has gained strength.
The post tensioning system referred as the ducts for the tendons are placed along with
the reinforcement before the casting of concrete. The tendons are placed in the ducts after
the casting of concrete. The duct prevents contact between concrete and tendons during
the tensioning operation. Not same as pre-tensioning method, the tendons are pulled with
reaction acting against the hardened concrete. If the ducts are filled with the grout, it is
known as bonded post tensioning but if unbounded post tensioning, the ducts are never
grouted, and the tendon is held in tendon solely by the end anchorages.
The Perla Sentral Ara Damansara project is the residential building that have a basic
component which carparks within the basement. The carpark of the building mainly to be
focused within this study as it is using a post tensioning method. The post tensioning
method is a slab structure for this project thus the systems post tensioning help to place
and fixing, stressing and grouting.
The project used of post tensioning method as this method is decreasing or removes
shrinkage cracking, so no joints or fewer are needed. Forming of the cracks are kept closely
together, which allowing thinner slabs and other structural members to be thinner. The
method also allows to create slabs on expensive or soft soils, enabling to design longer
periods of elevated which if slab. Thus, it lead to have a high durability for used this method.
Post tensioning method for the project also improve seismic performance which an
execution of carpark building structure ability to sustain it due functions such as safety and
serviceability, at and after a particular earthquake. Other than that, this method also helps
to faster in construction cycle. Post tensioning on this project also have long economical
span which shallow structural depth. It also has minimum amount of non-prestressed
bonded reinforcement over supports of continuous post tensioned.
5
6 PRE-STRESSED CONCRETE FRAME
Both of the case study project used a different material. The infrastructure project
which used the pre-tensioned method apply precast concrete girder and pre tensioning of
pier cap and removal of bottom supports. The project has been designed using high-quality
materials that contribute to the expressway’s life and quality which have a high durability
performance. In lieu of the traditional Bentonite powder, polymer has been used, saving
20,000 cubic meters of soil from pile foundations (D'souza, 2020). In addition, the
improvised technique is high-grade RCC, M55 grade with micro silica and mixture, to obtain
an early strength of 45N per square millimetres, within four to five days, needed for de-
stressing of high tensile cables and early de-moulding.
Furthermore, regarding to an addition information, the shree cement have been used
in the project. The steel structure of the infrastructure project used is unknown as the
material steel is authority of India.
The residential building project which focused of carpark used bonded post tensioned
method which used the concrete slab structure. The concrete material used of grade35 as
the concrete is consider as high strength material. The material used in the project is an
inexpensive, quick and durable way to complete the project. Using of this material, the
shape of the slab is designing within the proposed shape and be used reliable.
This material also considers reinforced with steel, and having a high-quality tendon
applied. The repairs are easily done by spraying additional material onto the filling cracking
and divots with new material. The property of concrete to possess high compressive
strength, makes a concrete structure more economical.
6
7 PRE-STRESSED CONCRETE FRAME
The construction process from the case study 1 is using the pre-tensioned method
which is applied where stressing is carried out at factories. This method of precast pre-
tensioned girder process consists of firstly by preparing machine for pre-stressing, rebar
installation, tendon stressing, formwork (mould) installation, concreting, cutting, and lastly
removing formwork (mould). This method of pre-stressing in which the tendons are
tensioned before the concrete is placed, and the pre-stress is transferred to the concrete
when a suitable cube strength is reached.
Firstly, this construction process in Figure 1 shows the process is carried out by
preparing the machine for pre-stressing which is pre-stressing bed to start the pre-
tensioned construction process and high-tensile steel tendon are placed between the two
abutments. After that, the rebar installation is continued by placing all the reinforcement bar
at the pre-stressing bed. At this process, the tendon is been stretched up to 70 to 80 percent
with additional 10 percent of their ultimate strength using the jack types devices.
Next, the Figure 2 shows the installation of formwork which is mould is using for
constructed the girder. After stressing the wires (tendons), the side forms of the mould are
positioned and then the concrete is placed around the tensioned wires and allowed the
concrete to cure to the required initial strength.
7
8 PRE-STRESSED CONCRETE FRAME
Moreover, in Figure 3 shows after the concrete have been cured and hardened
sufficiently, the tendons are released slowly or cut, then the prestress will transfer from
steel to concrete through the bond. Thus, the bond between the stressed wires and
concrete will prevent the tendons from regaining their original lengths. The bond between
the stressed wires and concrete can also be improved by using crimped or indented wires.
After the stressed process is being secured from the workers and engineer requirements,
lastly as shows in Figure 4 where the formwork (mould) will be removed and ready for
delivered to the site.
For case study 2 the construction process is using the post-tensioned method which
is applied where stressing is carried out on site. The method of constructing the post-
tensioning slab in the case study project is conclude of firstly by formwork setup, rebar
installation, tendon installation, placing and fixing, concreting, tendon stressing, grouting
process, and lastly removing formwork. This method of prestressing in which the tendon is
tensioned after the concrete has reached a suitable strength.
8
9 PRE-STRESSED CONCRETE FRAME
Firstly, in Figure 5 shows the process is taken by installed the formwork platform as
the slab formwork and side formwork with 200mm of thickness to support the upper level
of the building. After installation of formwork setup, next process is a reinforcement bar
installation by placing the lower and beam reinforcement based on drawing to control
cracking from occurs in the anchorage zone. Thus, lower and punching shear
reinforcement were also be installed in column to increase the strength to transfer load.
The bar chair also been installed and be determined the position and placement by the
engineers followed to the profile height from the specified construction drawing.
Next, in Figure 6 shows the process is followed by installation of tendon by firstly pulling
the strand from the centre out coiled strand that fitted in a bri-pack coil with a minimum
effort. Then, the galvanised ducts are been placed into the required position before the
strands to be inserted and it must be free from any unnecessary particles like mud, sand
or others. The strand is then be cut with a high-speed friction cutter and the strand insertion
was on strand manner until the required number was reached. After the strand have been
cut and inserted, the process of placing and fixing is continued by installed the ducts based
on the construction drawing. It was adequately been sealed with tape on all the joints
between individual duct lengths to prevent ingress of cement grout during concreting and
then tied by bar chair. The grout vent was fixed by drilling the duct and attaching the
universal PSC Plastic Limpet Grout Vent and then the stressing anchorage castings were
also be fixed to the end of panel formwork using bolt and nuts, the strands also are fixed at
a maximum spacing of 35m as well as at each tendon ends before concreting.
9
10 PRE-STRESSED CONCRETE FRAME
Then, the Figure 7 shows the process of concreting is been continued by concreted
the slab with the concrete Grade 35 after the process have been confirmed to be installed
and also be inspected and completed. Slump test is also was be tested by the worker to
confirm that it achieved the range specified design of slump within 75mm and 125mm
before started casting. Thus, the concrete was been compacted using the vibrator and
ensure the concrete was work into the corner of structure member and kept away from the
tendon ducts.
10
11 PRE-STRESSED CONCRETE FRAME
The safety instalments that provided during the pre-stressing construction process in
these case studies first are included of placing the safety restraints (Figure 9). The wire
restraint was used for minimise the wire/strand movement when failure occurs and the
tension is released. It is also recommended that the stressing bed be equipped with
restraints along its length at approximately equal centres. Links, straps, bars, and bulk
heads can be used in restraints and should be at centres determined by risk assessment,
but usually not more than 10 m apart. All the wire restraints should remain in place
throughout the production process until casting occurs and only being removed when the
process ends.
Figure 10 Guarding
11
12 PRE-STRESSED CONCRETE FRAME
Figure 10 was shown a guarding system that also required for safety procedures to
ensure protection of the stressing operator during stressing and of all personnel after
stressing is complete. The independent checks on the load can be carried out after
stressing is complete for more secured for the pre-stressed concrete to be used. A paint
line also can be applied to avoid any lifting guards to check for slippage after stressing is
complete at close to the abutment before stressing that will allow slippage to be identified.
Figure 11 Signage
Lastly, a warning system is been produces for safety instalment to ensure awareness
for operating personnel and visitors when stressing is taking place suitable warning
systems should be installed; these could include lights, sirens, notices and signage. The
example of warning systems in Figure 11 shows that been used in this case studies project
is lights, sirens, and notices. The construction warning systems is delivery an important bit
of information to letting the workers, staff, and visitors to know about the hazards to watch
out for or requirements that must obey especially at site where it is an open construction
site.
12
13 PRE-STRESSED CONCRETE FRAME
Every construction will face problems whether before the construction starter or during
the construction period or after the construction process. The problems that arise will be
one of the challenges yet an experience especially for the consultant, engineer, architect,
quantity surveyor, contractor and all other parties that involved in that project. These are
the problem that arise during the construction process and the solutions to its problem of
both projects.
As the solution to this problem, the management parties have been discussed on the
construction methodology. They have come out with a plan to use massive of precast
element for this project. This is a great solution as it can maximize off-site and minimize
on-site activities. This idea has made the project complete within available space, time
frame and the most important part is minimized hindrance to traffic.
Besides, this project also has faced transportation problem to transport the material
from the factory to the site and erection of wide segment problems during the construction
process. As mentioned, the site is located at very congested area so it is difficult for to
transport the materials and to erect them due to moving traffic and also restricted space
availability.
To resolve the problems of transportation and erection of material, they have decided
to use conventional pre-tensioned girders for the viaduct. Use of precast pre-tensioned
girders has increased many folds in the last two decades. There are many benefits of
precast pre-tensioned girders, especially in long elevated road projects. The weight of a
pre-tensioned girder is significantly less as compared to a post- tensioned girder due to
reduced web thickness
13
14 PRE-STRESSED CONCRETE FRAME
Next, preparation of huge numbers of precast girders is one of the challenges for this
project as they did not have enough time to construction this long highways. There were a
total of 1107 numbers of precast girders for the entire project have to be prepared for which
a total of 12,000 sqm precast casting yard was prepared with 12 beds and 3 girder casting
facility on one bed. It is quite a lot to be completed and the clock is chasing them.
As they have not enough time to wait for it, they have decided to setting admixture
earlier and adopt steam curing. It is one of the best methods as they have reduced the time
cycle of girder casting from 10 days to 7 days. With that solution, they have successfully
produced 180 girders in a month. As the results, the yard was having a staking capacity of
220 nos. of precast girders and construction activities were planned accordingly. A steel
cutting bending and binding automatic yard of size 50m x 18m was commissioned to
accelerate the progress of project. Launching of such a huge number of precast girders
was a major task and was done with the help of two gantries instead of crane. Tracks for
gantry were placed 30m centre to centre near outer edge of ROW. Use of gantry reduced
the time involved in erection of girders substantially. Practically it took only 15 to 20 minutes
to erect a girder after lifting it from trailer, thereby reducing the stoppage time for traffic
drastically. With gantry, maximum of 14 girders were erected in a day, however average
erection of girders was 4 numbers per day.
As this project is still under construction, there are still many problems that did not yet
discovered. One of the main problems for this project is safety issues. This happened due
to lack of training, poor supervision, poor planning process and poor supervision. It is quite
worrying and very dangerous as well for the workers that close to stressing process area.
It is because of the stressing machine has a very high pressure.
As the solution to this problem, Department of Safety and Health have come out with
warning signage to the red zone area to avoid unwanted accident from happening. This
solution is very effective to make sure that area is safe especially during process of
stressing and grouting.
14
15 PRE-STRESSED CONCRETE FRAME
Good communication is one of the best ways to increase quality and can make the
problems solve directly with doing a meeting in site office to discuss about the problems
detected and solve it effectively. In site at Perla, the best solution of the problem is hired a
worker that can understand different language like Malay and the worker’s language from
their country. This solution can make the workers understand different language so that
they can do the job correctly.
Manpower is very important in the project as the more the manpower the fastest the
work can be finished. The shortage of labours may cause delay in project and cannot make
the work smoother. As for Perla Project, they are having lack of manpower as they involve
in a lot of works especially during pre-stressing steps.
15
16 PRE-STRESSED CONCRETE FRAME
Here is the comparison between two projects that use different method of pre-stressed
concrete which is project Delhi-Meerut Expressway that use pre-tensioned and Perla
Sentral Ara Damansara project that use post-tensioned.
IMAGE
16
17 PRE-STRESSED CONCRETE FRAME
17
18 PRE-STRESSED CONCRETE FRAME
18
19 PRE-STRESSED CONCRETE FRAME
19
20 PRE-STRESSED CONCRETE FRAME
9.0 CONCLUSION
Based on the case study, it can be concluded that the pre-stressed concrete have two
different method which are pre-tensioned and post-tensioned. The method used for the
construction of carpark at Project Perla Sentral Ara Damansara is using post-tensioned
meanwhile the construction of expressway at Delhi-Meerut is using pre-tensioned.
Post-tensioned method is one of the best method for support huge load such. This method
used for carpark and it also convey with theory and has proven that post-tensioned method
can be construct successfully with correct method statement, procedures and requirement.
Therefore, pre-tensioned also one of the best method use for highway as it can increases
the quality, strength and span of the structure. However, throughout the investigation there
were problems in the construction. The construction has problems such as site limitation,
transportation and erection, preparation of precast girders, safety issues, lack of
communication and shortage of labours. As results, it will risk the workers’ safety and has
affected the worker working time if they had an accident and cause them injured. It also
makes the construction’s quality will be affected. The solution for this problem is by use of
precast element, use of conventional pre-tensioned girders, early setting admixture,
warning signage, fix the communication and hired more labours. , it is the best for safety
supervisor to supervise the worker during stressing and grouting process effectively.
Hence, the problems should not take lightly. The problems occurred during construction
process has been acknowledge and the solutions have been taken
20
21 PRE-STRESSED CONCRETE FRAME
10.0 REFERENCES
Chin, S. (2 September, 2020). What Is Prestressed Concrete And How Does It Work? Retrieved From
Esub Constrution Software: Https://Esub.Com/Blog/What-Is-Prestressed-Concrete-And-
How-Does-It-Work/
D'souza, S. (July, 2020). Innovation Expressway. Retrieved From First Construction Council:
Https://Www.Firstconstructioncouncil.Com/Cement-Industry-News/117507/Innovation-
Expressway
Khandelwal, P. (3 September, 2019). Phase 3 Of Delhi-Meerut Expressway Now Open, Reach Hapur
From Dasna In 15 Mins. Retrieved From Hindustan Times:
Https://M.Hindustantimes.Com/Noida/Phase-3-Of-Delhi-Meerut-Expressway-Now-Open-
Reach-Hapur-From-Dasna-In-15-Mins/Story-U9slqcfocykcfghkvegidj.Html
Sigh. (6, 2020). Challenges In Design & Construction Of 4680m Elevated Viaduct At Pilkhuwa – A
Case Study. Retrieved From Infrastructure And Equipment Magazines:
Https://Www.Nbmcw.Com/Tech-Articles/Precast-Construction/41872-Challenges-In-
Design-Construction-Of-4680m-Elevated-Viaduct-At-Pilkhuwa-A-Case-Study.Html
21