Report of 20 PIAs

S. Particulars Number Remarks of Committee Members


No of
proposals
1 Applicants eligible for 09 1. Out of five PIAs who have completed
QA waive off and edit training program of the students, three
option may be provided PIAs conducted training in other trade
by MoRD which is not in the list of QA waive off
trades, considering trained students
welfare these trades may be
considered and closed on pro-rata
basis.
2. Four PIAs that have not conducted the
training did not get adequate time due
COVID Pandemic and one PIA was not
issued the PCO so these factors should
be taken into consideration.
3. All applicants may be given one more
chance for edit option for QA waive off
as fund had been released to all PIAs,
five PIAs already conducted training
programs and four PIAs could not get
sufficient time to complete training.

2 Initial Screening 06 1. As 4 projects had commenced the


Conducted but QA was training and placement had been done,
not conducted it may be calculated on pro rata basis
as per the achievement, for the
welfare of the students.
2. All six projects are recommended for
fresh QA process as fund had been
already released and four PIAs had
conducted training. MORD may provide
guidance on the same.

3 Applicants got rejected 03 1. One project which had commenced


during appraisal process training and placed the candidate may
be recommended for closure based on
prorata basis for the welfare of the
students.
2. It may be suggested that the project
may close as per closure notification.
MoRD may please provide the guidance
on the same.
4 Additional Target 01
It has been observed that PAC has given
conditional permission to the applicant for
additional target and at time of release of
first instalment, the applicant was eligible
but has not applied on the portal.
Considering trained students welfare, if
MoRD permits this project may be
continued.
5 Proposals not found 01 As fund has been released and training has
been conducted by PIA, Considering the
welfare of students who are trained,
project may be calculated and closed on
pro rata basis.

2. Internal Control measure and transparency in the system-

The committee suggests the key control measure to be followed strictly by SRLM/STSA
1. All the proposals to be verified & validated by SRLM/STSA in pre-PAC meetings.
2. Only that applications/proposal to be put for PAC approval which is approved in
pre-PAC Meeting.
3. Sanction orders, PCOs to be generated based on the application on ERPs portal
only.
4. It was observed that CTSA members were present as representative in PAC but the
agenda and list of applicants were not shared with them before in any of the PACs
for verification or super checks of appraisal process to be recorded on the ERP
Portal. It is proposed that CTSA members may be included to check the appraisal
process before placing the applicants in the PAC meeting. If there is any deviation,
then CTSA may indicate the same before PAC
5. SRLM/STSA to prepare robust monitoring mechanism at SRLM level to avoid
deviations in the processes in consultation with CTSA.

3. Self- Control of role of Central Technical Support Agency in the state of


Maharashtra- The committee members have observed that CTSA being extended arm of
MoRD may provide its technical support to MSRLM from time to time as and when required
by MSRLM. Further, MSRLM is requested to share the information with CTSA like PAC
agenda, PAC meetings, list of proposals placed for PAC from time to time so that CTSA
may be updated on the whole process. It is observed there is a lack of communication
between MSRLM and CTSA and, the sharing of information between the two is also not very
frequent. It is proposed that the dedicated team of CTSA members may be shifted to
MSRLM office permanently for close coordination.