Professional Documents
Culture Documents
Paper n° 0865
Paper n° 0865
components at decommissioning. These shall be analysed insulation damage and degradation, signs of overheating,
in conjunction with the full transformer oil analysis signs of partial discharge, signs of arcing, signs of
history where available to determine trends and leakage flux, loosening of clamping structure, loosening
developing faults. of electrical connections, deterioration of tap changer
contacts, and presence of sludge. The information
A complete suite of electrical testing shall be also gathered at this stage will allow the conditions indicated
performed with the aim of verifying at dismantling stage either by the oil and DGA analysis or the electrical
the adequacy of the available tests as asset condition testing (Figure 2) to be confirmed or discarded. It will
diagnostics tools (Figure 1). On the other hand, also highlight other conditions not indicated by any of the
underlying conditions not captured by the electrical diagnostics tools.
testing will be also made evident and will provide advice
on the level of caution to be applied when interpreting the
results of certain electrical tests. The following tests
should be performed as a minimum: power factor and
capacitance, polarisation index, dielectric frequency
response (DFR) and sweep frequency response analysis
(SFRA). Other tests may be suggested as indicated by oil
history. Electrical diagnostic testing of bushings should
be also considered. In the case of SPEN, electrical testing
on transformers in service is only performed as part of a
fault investigation exercise, but not as part of a routine
maintenance regime. Where historical test results are
available, they shall also be incorporated into the overall
final analysis to determine trends, deterioration rates and
developing faults. Figure 2 Cockenzie SGT2A 275/33kV 120MVA overheating
on a phase LV connector indicated by DGA analysis
On completion of the electrical testing, the transformer is Final stage of the process consists of analysis of all the
drained of insulating fluid, partially dismantled and gathered information and preparation of a report. In order
prepared for transportation to an authorised specialised to fully benefit from this process, a central database
scrap yard to undertake final dismantling and forensic should also be created to register the results of each
inspection. This inspection shall consist of a thorough individual transformer being evaluated so as that patterns,
internal visual inspection of all active part components trends and reoccurrences can be also analysed at fleet
(e.g. windings, core, insulation elements, clamping level.
system, electrical connections, etc.), transformer tank and
transformer accessories. The dismantling of the active ANALYSIS
part and de-nesting of the phase assemblies shall be The transformers evaluated to date by SPEN, forty in
carried out sequentially so each component can be total, have the following general characteristics: 10
assessed individually and in the required level of detail. supergrid transformers (275/33kV), 22 grid transformers
Areas of interest for the forensic inspection should (132/33kV) and 8 system transformers (33/11kV); built
include as a minimum: winding deformations and by different manufacturers although predominately Bruce
movements, core deformation and oxidation, solid
Paper n° 0865
Peebles (approx. 50%); average lifespan of 53 years and an abnormal measurement could not be exclusively
average residual life remaining at decommissioning of associated with this phenomenon.
27%, based on calculated DP value. All units were of a
separate cooler bank design and suitably protected free
breathing oil preservation system. All transformers but
three were decommissioned as part of a planned
replacement programme.
Paper n° 0865
indication of any change in the internal characteristics of Forensic inspections revealed that 61% of the evaluated
the active part construction, such as winding deformation transformers exhibited damage to core bolts or core bolts
or movement or loosening of clamping pressure, it insulation typically caused by excessive and prolonged
successfully identified the one transformer which was overheating (Figure 6). In order to prevent this
found to have experienced loosening of the winding occurrence, with consideration that core bolt insulation
clamping system on all phases at forensic inspection systems have moved from the use of paper insulation to
(Figure 5). On the other hand, the test indicated the fibre glass material, SPEN has evolved the transformer
potential existence of this condition on a number of units technical specification so that only banded or tapped
but evidence was not found at forensic inspection. This yokes and limbs are required in newly purchased
indicates the results of the SFRA test should be treated transformers.
with caution in cases where gain and frequency
deviations are not substantial as these may not be
conclusive.
Paper n° 0865