You are on page 1of 6

21, rue d'Artois, F-75008 Paris Session 2000

http://www.cigre.org 12/23/34-05 © CIGRÉ

POWER TRANSFORMER ON-SITE CONDITION ASSESSMENT TESTING

TIM NOONAN*

ESB International

IRELAND

1. INTRODUCTION transformer’s condition and ensure its continuing


serviceability.
Medium and large power transformers are high capital
cost and critical plant items in the generation, Throughout the life of the transformer, a more extensive
transmission and distribution of electrical power. Their set of testing is performed at different stages to enable
expected lives can vary from thirty to fifty years. Cost decisions on its continuing serviceability. This tests are
of failure can be high not only due to high repair and generally known as condition assessment tests and are
replacement costs but also due to penalties arising from carried out (i) routinely to enable implementation of
loss of supply or costs associated with alternative condition based corrective maintenance tasks, (ii) after
supply / generation. a system incident, defect / fault on a transformer
A life management policy is essential in maintaining identified by monitoring / protection devices, (iii) prior
continued serviceability of these costly and critical to a change in operational requirements to determine if
plant items during their lifetimes and will also provide the transformer’s condition will permit this change i.e.
data that may enable the implementation of life increased loading / overloading, and (iv) towards the
extension programmes. Life management begins at the expected end of the transformers life to determine
specification stage i.e. quality of materials, good design continuing serviceability / cost of refurbishment to
and quality of construction are all vital elements in extend the transformer’s life.
maintaining the transformers serviceability throughout
its life. When the transformer is placed in service its
continued serviceability depends on its operational, 2. TRANSFORMER LIFE MANAGEMENT
maintenance and fault histories. Condition monitoring TESTS
tests are applied on several occasions throughout the
life of the transformer to provide data that enables the As already stated, there are three categories of
transformer’s life to be effectively managed. transformer life management tests i.e. fingerprint, low
cost routine / continuous monitoring, and condition
An initial set of tests is performed at the manufacturer’s assessment tests.
works or on site during commissioning. These are
called fingerprint tests and data generated act as a base 2.1 Fingerprint Tests
line set of test results with which subsequent tests
throughout the life of the transformer can be compared. Fingerprint tests are performed at the manufacturer’s
This initial set of tests also act as a quality assurance works / on-site during commissioning. Ideally a
check and ensures the transformer has been separate set of tests should be performed in both
manufactured and erected on site to an acceptable locations with the transformer fully erected. These tests
quality. not only provide a base line set of test data but also (i)
act as a quality assurance check after manufacture, (ii)
When the transformer is placed in service, low cost ensure no defects have been introduced during
routine / continuous monitoring is used to monitor the transportation to site and site erection and, (iii) act as a
quality insurance check after site erection.

* STEPHEN COURT, 18 / 21 ST STEPHEN’S GREEN, DUBLIN 2


MC/TN5234.REP

Some of the transformer acceptance tests performed at • Oil dissolved gas analysis.
the transformer manufacturer’s works may act as
fingerprint tests, i.e. partial discharge, winding • Oil furan analysis.
resistance, tan delta or % power factor and capacitance
measurements. • Paper sample degree of polymerisation
measurements [9].
Fingerprint tests performed by ESBI include the
following: • Paper sample moisture content test [10].

• Oil screen tests (breakdown voltage, moisture • Interwinding and winding to ground % power
content, neutralisation value, colour, resistivity, and factor measurements.
relative permittivity).
• Interwinding and winding to ground capacitance
• Oil dissolved gas analysis [1] [2]. measurements.

• Interwinding and winding to ground % power • Bushing main insulation and test tap insulation to
factor measurements [3]. ground % power factor and capacitance
measurements.
• Interwinding and winding to ground capacitance
measurements [3]. • Winding resistance.

• Bushing main insulation and test tap insulation to • Magnetising current measurements.
ground % power factor and capacitance
measurements [3]. • Leakage reactance measurements.

• Magnetising current measurements [3]. • Spectrum of polarisation measurements by


recovery voltage meter.
• Leakage reactance measurements [4].
• Frequency response analysis using the swept
• Spectrum of polarisation measurement by recovery frequency method.
voltage meter [5] [6].
• Infrared thermal vision.
• Frequency response analysis using the swept
frequency method [7] [8].
The paper sample degree of polymerisation
2.2 Low Cost Routine / Continuous Monitoring measurements and moisture content tests are carried out
on paper samples removed from leads / top of windings.
The low cost routine / continuous monitoring set of Paper samples are taken through bushing / inspection
tests to monitor the ongoing condition of the plate openings (or after untanking). This is done only
transformer, can vary considerably between utilities. In when an oil reconditioning, oil change out or a major
general, European utilities favour routine on-line oil refurbishment / repair is being carried out.
screen tests and dissolved gas analysis with continuous
on line gas in oil monitoring on strategic units. Other A transformer condition assessment also involves a
utilities, in particular in the U.S., include off-line detailed site inspection (external and diverter switch)
insulation % power factor testing as a routine test. and an assessment of the transformer’s operational,
ESBI recommend the following for ESB transformers: maintenance and fault histories as well as an assessment
(i) Routine on-line oil screen tests and dissolved gas of auxiliaries and spares availability.
analysis varying from 6 months to 2 yearly intervals
depending on the voltage rating and strategic
importance of the transformer and (ii) on-line 3. CASE HISTORIES
continuous gas in oil monitors (carbon monoxide and
hydrogen) depending on the voltage rating and strategic The following case histories are examples of the
importance / present condition of the transformer. effectiveness of fingerprint and condition assessment
testing in the transformer life management policy.
2.3 Condition Assessment Tests
Condition assessment tests performed by ESBI are as
follows:
• Oil screen tests.
MC/TN5234.REP

The following corrective maintenance was carried out


3.1 Case History 1 (New Transformer Quality on Unit 1:
Assurance)
• HV phase bushings changed out.
Fingerprint tests on two 110 / 20kV, 20 MVA • Transformer oil reconditioned.
transformers indicate % power factor values of
winding insulation as in Table I. The table The LV bushings on Unit 1 also had some deterioration.
headings CH, CHL, CL, CHT, CLT, and CT are These are being monitored on a routine basis.
respectively the high voltage winding to ground,
high to low voltage winding, low voltage winding
to ground, high to tertiary voltage winding, low to 3.3 Case History 3 (Repair Decision)
tertiary voltage winding and the tertiary voltage
winding to ground insulations. A 110 / 38kV, 63 MVA transformer tripped on
differential and Bucholz protection. A 38kV-system
Table I: % PF test values on main insulation. earth fault, which developed into a 38kV short circuit
on one of the 38kV circuits fed from the station
% PF immediately preceded the transformer trip. Bucholz gas
Unit and dissolved gas analysis indicated an internal fault
CH CHL CL CHT CLT CT had occurred in the transformer.
1 .32 .24 1.38 - .23 .38
Table IV shows the dissolved gas analysis results after
2 .42 .2 9.67 - .19 .39 the fault. Low values of CO indicate that paper
insulation was not involved in the fault.
Further investigation into the high value of CL
(acceptable values should be lee than 0.5) revealed Table IV: Dissolved gas analysis results.
cracking and moisture ingress on the LV bushings.
H2 CO CO2 CH4 C2H4 C2H6 C2H2
3.2 Case History 2 (Corrective Maintenance 329 250 1495 77 97 10 322
Decision)
The transformer was taken out of service. Condition
Condition assessment tests were carried out on two assessment tests were carried out. Condition
sister transformers in the same substation. Table II and assessment tests had previously been carried out on this
III indicate winding and bushing % PF tests from both transformer in 1996.
transformers.
Table V indicates results from both condition
Table II: % PF test values on main insulation. assessments.

% PF Condition assessment tests after the fault indicated:


Unit
CH CHL CL CHT CLT CT • An open circuit in the LV winding r phase near the
1 1.18 .22 .78 .22 .33 .26 r phase bushing.

2 .35 .22 .27 .23 .25 .26 • No other mechanical deformation in the
transformer.

Table III: % PF test values on HV bushing • Paper insulation was not involved in the fault.
insulation.
These results indicated the transformer could easily be
% PF repaired. The transformer was sent to a workshop,
Unit where it was untanked. The fault found was an open
R S T N circuit at a burnt connector to the LV r phase bushing.
1 1.91 2.8 3.51 .6 The transformer was repaired. Figure 1 shows the FRA
scans indicating the fault at the bushing end of the
2 .72 .74 .73 .70 winding. (Figure 3 shows FRA scans when the fault is
at the neutral end of the winding.) Figure 2 shows the
burnt connector at the LV winding r phase bushing.
The oil was also wet in Unit l i.e. moisture 30ppm and
breakdown voltage of 59kV / 2.5mm were recorded.
MC/TN5234.REP

Table V: Condition assessment results prior to and after the fault.

DP % PF / Capacitance (pF)
CH CL CT CHL CLT CHT
PREFAULT 662/601 .27/ .33/ .25/ .20/ .22/ -/
4537 1527 13874 8601 13509 74
POSTFAULT 781/893 .76/ .99/ .36/ .29/ .31/ -/
4567 1525 13925 8634 13562 75
Magnetising Currents (mA) Furan Analysis

HV Winding LV Winding
1 Furaldehyde 5 Methyl-2-Furfural
R-N S-N T-N r-n s-n t-n

PREFAULT 60 50 63.5 73 16
POSTFAULT 55 41.8 57.3 .048 319 439 33 4
HV Winding Resistance (m5) LV Winding Resistance (m5)
R–N S–N T-N r–n s–n t-n
PREFAULT 395 391 392 36 36 36
POSTFAULT 395 391 392 0 36.2 36.3
Frequency Response Analysis Leakage Reactance Measurements
Nameplate 22%
R–N S–N T-N
PREFAULT No defect indicated.

POSTFAULT Open circuit on LV winding r phase near the 1630 21.9 27.5
phase bushing end of the winding.

Figure 1: FRA scans showing open circuit at R phase


Bushing end of winding Figure 2: Burnt connector to phase bushing
MC/TN5234.REP

overloading guide based on the ransformer’s present


condition. Values of transformer interwinding % PF and
RVM data are given for the three categories of paper
insulation moisture levels.

Transformer overload rating guides and top oil and


winding hot spot temperature indicator trip and alarm
settings are also given.

%PF data ( INTER


8

WINDING)
6
4
2
Figure 3: Open circuit on T phase near neutral end of 0
winding 0 2
R V M data
4 6

3.4 Case History 4 (Transformer Operational Figure 4:Transform er R V M data V % P F


Decisions) data

Condition assessment tests are used to determine the


present condition of transformers so that overloading
guides determined by the transformer’s present Other data derived from the condition assessment i.e.
condition can be provided. Recovery voltage meter paper sample DP, oil screen tests, DGA, furan analysis,
(RVM) data and % power factors (%PF) of FRA, etc. is also used in applying the overloading
interwinding insulation are both used to allocate a rating if the data indicates a significant loss of paper life
wetness rating to the transformer’s paper insulation. / electrical-mechanical integrity.
Three categories are established in this way, i.e. dry,
medium and wet paper insulation. Figure 4 shows
transformer RVM test data versus % PF test data for in
service transformers. Table VI shows a transformer

Table VI: Transformer overloading guide based on condition assessment.

Transformer % PF RVM Reading Overloading Top Oil Winding Hot Spot


Category (Interwinding) Guide Temperature Temperature
Indicator Indicator
Alarm / Trip Alarm / Trip

Dry <.5 <2.5 IEC 354 90 / 1050C 120 / 1350C

Medium <1.5 3-4 1.25% limit 75 / 900C 105 / 1200C

Wet >1.5 >4 Do not overload 65 / 800C 85 / 1000C


MC/TN5234.REP

for a New Power Technology Inspection Policy”,


4. CONCLUSIONS Doble Client Conference Proceedings, April 1993.

Medium and large power transformers are high capital [6] Bognar, Kalocsai, Csepes, Nemeth, Schmidt:
cost and critical plant items in the generation, “Diagnostic tests of high voltage oil-paper
transmission and distribution of electrical power. To insulating systems (in particular transformer
ensure continued serviceability, a life management insulation) using DC dielectromectrics” CIGRE,
policy involving on site condition assessment testing is 1990 Session, paper 15/33-08
essential. This ensures:
[7] Dick, EP and Erven, CC: “Transformer Diagnostic
• The high quality of equipment being put into Testing by Frequency Response Analysis”, IEE
service. Trans, Vol. PAS-97, No. 6, PP.2144-2153,
November 1978.
• Continued effective monitoring of equipment in
service. [8] Noonan, TJ and Lapworth JA: “Mechanical
Condition Assessment of Power Transformers
• Present condition trending while in service. using Frequency Response Analysis”, Doble Client
Conference Proceedings, April 1995.
• Identification of required corrective maintenance
tasks for continued serviceability. [9] IEC Publication 450: “Measurement of the
Average Visiometric Degree of Polymerisation of
• Speedy repair and return of equipment to service New and Aged Electrical Papers”, 1974.
after fault.
[10] ASTM Designation: D3277: “Standard Test
• Generation of data to enable refurbishment and life Method for Moisture Content of Oil-Impregnated
extension decisions to be implemented. Cellulose Insulation”, 1992.

• Generation of data to enable operational changes,


relocation, retirement decisions to be implemented.

5. REFERENCES

[1] IEC Publication 567: “Guide for the Sampling of


Gases and Oil from Oil Filled Electrical Equipment
and for the Analysis of Free and Dissolved Gases”,
2nd Edition 1992.

[2] IEC Publication 599: “Interpretation of the


Analysis of Gases in Transformers and Other Oil-
Filled Electrical Equipment in Service”, 1978.

[3] Kopaczynski, D:“AC Dielectric-Loss, Power-


Factor and Capacitance Measurements as applied
to insulation systems of High-Voltage power
apparatus in the field. Part 1: Dielectric Theory.
Part 2: Practical Applications Doble Testing”,
Doble Client Conference Proceedings, April 1993.

[4] Lackman, MF:“Low-Voltage Single-Phase


Leakage Reactance Measurements on Transformers
– Significance and Application Part I” – Doble
Client Conference Proceedings, April 1994.

[5] Guuinic, P, Mauyean, J-M, Legrand, C, Sanches,


G, Luccion, P Patelli, J-P and Cohard, O, “The
EdF Diagnostic Method Evaluation: A Program

You might also like