Professional Documents
Culture Documents
net/publication/3259204
CITATIONS READS
147 3,133
2 authors, including:
Ernst Gockenbach
Leibniz Universität Hannover
280 PUBLICATIONS 4,016 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Ernst Gockenbach on 02 April 2016.
Asset-Management of Transformers
Based on Condition Monitoring and
Standard Diagnosis
Key Words: asset management, condition monitoring, diagnosis, international test standard,
transformerdynamics, space environment, printed circuit boards, homocharge, heterocharge
Figure 2. Defective components of a transformer (LTC: load Figure 4. The importance of different diagnostic methods to
tap changer) [2]. estimate transformer conditions with color distinction.
1. Four IEEE® Conditions The measured parameters < 1. Overheating destroys oil insulation 1. The different measures are made
2. Duval Triangle Analysis recommended safety limits: and reduces life expectancy of according to conditions of transformers.
3. Rogers Ratio The most severe intensity of energy transformers. 2. Internal inspection should be
Analysis dissipation occurs with arcing, less with 2. The quality of oil is reflective of the considered.
4. Doernenberg Ratio Analysis heating, and least with corona. health of transformers.
to determine the most cost-effective alternative for operation, electrical or thermal stresses break down to liberate small quanti-
refurbishment, or replacement. ties of gases. The composition of these gases is dependent upon
To reliably assess the overall condition of a transformer, several the type of fault (Tables 1 and 2). The most important diagnostic
monitoring techniques are used or are under investigation. In ad- parameters are the individual and total dissolved combustible gas
dition to the traditional routine tests, there are some specialized
tests including partial discharge measurement, frequency response
analysis, infrared examination, vibration analysis, and degree of
polymerization. These monitoring tests may detect problems such
as local partial discharge, winding looseness and displacement,
mechanical faults, hot spot at connectors, moisture in paper and
aging of paper, as well as insulation degradation. The careful
recording and plotting of the test results makes it possible to get
the full information out of a test and to compare the values with
those of previously accomplished tests and international testing
standards.
Interpretive discussions are also included to provide guidance
on acceptance criteria. These activities may help identify existing
weaknesses or faults and also give some indication of expected
service reliability and remaining life.
concentrations (TDCG) and their generation rates [5]. By means The first step is to establish whether or not a fault exists by
of dissolved gas analysis (DGA), it is possible to distinguish fault using the IEEE method [5]. Only when these levels exceed some
types such as internal arcing, bad electrical contacts, hot spots, threshold value is a fault suspected. The second step is to deter-
partial discharge, or overheating in oil, cellulose paper, tank, or mine the type of fault. Three methods are most commonly used:
conductors, etc. Duval Triangle (Figure 5), Roger Ratio Criteria (Figure 6) and
M/DW 1. Moisture in presence of oxygen is 1. Paper insulation has a much greater 1. Transformer should have a dry out
(moisture/dry weight) > 2.5% extremely hazardous to insulation of affinity for water than oil does. with vacuum or do round-the-clock re-
paper and transformer. 2. Temperature is also a big factor in how circulation with a Bowser.
2. Moisture and oxygen form acids, metal water distributes itself between the oil 2. DGA and Doble tests should be
soaps and sludge, causing transformer and paper. examined.
cooling to be less efficient, 3. Each time the moisture is doubled in a
temperature to rise slowly over time and transformer, the life of
paper insulation to decay. insulation is cut by one-half.
3. Moisture reduces the dielectric 4. This is a vicious cycle of increasing
strength of oil. speed with deterioration forming more
4. Above 4% M/DW, it is in danger of acid and causing more decay.
flashover if temperature rises to 90°C.
Number of interfacial tension < 22 1. Oil is very contaminated and sludge 1. As oil ages, it is contaminated by Oil should be reclaimed to prevent sludge
dynes/cm is formed. oxidation products of oil and paper when it reaches 25 dynes/cm.
2. Sludge will settle on windings, insulation. These oxidation products will
insulation, cooling surfaces, and cause weaken the surface tension between oil
loading and cooling problem. This will and water and lower IFT number.
greatly shorten transformer life. 2. IFT and acid number together are an
excellent indication of when oil needs to
be reclaimed.
O2 concentration > 2000 ppm 1. High oxygen means a leakage in 1. Under the same temperature 1. Oil should be de-gassed and new
conservator. conditions, cellulose insulation in high- oxygen inhibitor installed when oxygen
2. Oxygen in oil greatly accelerates oxygen oil will last 10 times shorter than reaches 10000 ppm.
paper deterioration. insulation in low-oxygen oil. 2. DGA test must be done.
2. This becomes even more critical with
moisture above safe level.
Ditertiary Butyl Paracresol by total 1. Inhibitor is used up. 1. Oxygen inhibitor is a key to extend the 1. Inhibitor needs to be replaced.
weight of oil > 0.3% 2. Transformer ages. life of transformers. 2. Oil needs to be treated.
2. This works similarly to a sacrificial 3. DGA test must be done.
anode in grounding circuits. Oxygen
attacks inhibitor instead of cellulose
insulation.
Acid number > 0.4 mg KOH/gm 1. Oxidation of insulation and oil form 1. Acid attacks metals in tank and forms Oil should be reclaimed to prevent
acids and sludge. soaps. Acid also attacks cellulose and sludge when it reaches 0.2 mg KOH/gm.
2. Sludge will settle on windings, accelerates insulation degradation.
insulation, cooling surfaces and cause 2. IFT and acid number together are an
loading and cooling problems as excellent indication of when oil needs to
temperature rises slowly. This will greatly be reclaimed.
shorten transformer life.
Power factor > 1.0% (25 °C) 1. The insulation integrity of oil may be 1. The dielectric loss indicates 1. Replacement or reclaiming of oil is
broken down. deterioration or contamination of oil from required immediately.
2. The state of humidity of oil is by-products such as water, carbon, or 2. Internal inspection should be
determined. other conducting particles, including considered before re-energized.
3. Transformer failure is imminent when metal soaps and oxidation products. 3. Above 2%, oil should be removed
the power factor is above 2%. 2. A trend can be established as from service and replaced because oil
insulation system ages. cannot be longer reclaimed.
3. Test values are compared to previous
or factory tests.
1. Minimum oil breakdown voltage < It indicates the amount of contaminants This test is not extremely valuable since 1. Oil should be reclaimed.
20kV (for rated voltage < 288kV) (water and oxidation) in oil. moisture will destroy cellulose insulation 2. DGA test needs to be done.
2. Minimum oil breakdown voltage long before the dielectric strength of oil
<25kV (for rated voltage ≥ 287.5kV) has indicated.
Doernenberg Ratio. Interpretation of fault conditions associated significance are recommended for classification purposes and to
with gas concentration and combinations of these gases are also determine the suitability for use of reclaimed oils.
provided in [5].
C. Insulation Tests of Cellulose Paper
B. Physical and Chemical Tests of Oil Quality Furan analysis, degree of polymerization and CO2/CO ratio
An important part of the life extension of a transformer is the tests [5] may indicate a problem with the insulating paper (Tables
restoration of the insulating fluid quality in the transformer. Physi- 9–11), if the transformer is overheated, overloaded, aged, or after
cal and chemical tests such as moisture test, interfacial tension test, processing the oil (Table 9).
oxygen test, acidity test, power factor test, and dielectric strength The presence of these compounds is related to the strength
test [8], [9], [10] usually indicate oil conditions and operational of the paper as measured by its degree of polymerization (DP).
characteristics (Tables 3–8). DP is the average number of glucose molecules making the cel-
Moisture in a transformer decreases the dielectric strength of its lulose chains. The DP value decreases with time as the cellulose
insulation system (Figure 7). The combination of moisture, heat, molecules break and fragment. The paper is assumed to age at a
and oxygen is the key factor that affects the rate of cellulose deg- more rapid rate where the temperature of the paper and exposure
radation. The interfacial tension (IFT) between insulating fluids to oxygen are the highest. Figure 9 depicts the relation between
and water is a measure of the molecular attractive force between relative depolymerization velocity and the water content and
unlike molecules at the interface. This test provides a means of temperature. When the DP test reveals a value of 200 or less, the
detecting contaminants and products of deterioration (Figure 8). paper is considered to have lost almost all mechanical strength,
The oil conditions can be remedied through various reclamation and the transformer has reached its end of life. The distribution of
processes. Therefore, they are not indicative of overall transformer measured DP values in Figure 10 demonstrates that the technical
condition, which would lead to replacement. lifetime of generator transformers is limited to 25 years whereas
Additional tests such as color, visual appearance, flash point, transmission transformers can reach a technical lifetime up to 50
pour point, specific gravity, and viscosity [8], [9], [10] to detect years [13].
the presence of deleterious products of oxidation or contamination As paper degrades, a number of specific furanic compounds
in service-aged oils also seem appropriate. These tests and their are produced and dissolved in the oil. Furanic compounds are a
Furans > 250 ppb 1. Overheating, lightning, oxidation, 1. Furan is especially helpful in 1. Oil should be reclaimed.
acids and high moisture accelerate the estimating remaining life in paper 2. Use in conjunction with IFT and acid
destruction of cellulose insulation and insulation and transformer life. number.
form furanic compounds. 2. Test values are compared to previous 3. DGA is always required.
2. Paper insulation is being deteriorated or factory tests.
and transformer life reduced at a high
rate.
Degree of polymerization < 200 DP All mechanical strength of cellulose 1. The cellulose molecule is made up of 1. Transformer must be replaced.
insulation has been lost and paper a long chain of glucose rings which form 2. Internal inspection is required.
insulation has reached the end of life. the mechanical strength of molecule
and paper. DP is the average number of
these rings in molecule. As paper ages
or deteriorates from heat, acids, oxygen,
and water; bonds between the rings
begin to break, DP decreases.
2. DP is the most dependable means
of determining paper deterioration and
remaining life.
CO2/CO < 3 1. Imminent danger of failure. 1. Extreme overheating from loss of 1. If there is a sudden increase in H2
2. Severe and rapid deterioration of cooling or plugged oil passages will with CO2 and CO, this test is required.
cellulose is certainly occurring. produce a low CO2/CO ratio along with 2. De-energization and internal
3. The fault is probably caused by a increasing Furans. inspection is recommended.
bad connection on a bushing base or on 2. If H2, CH4, and C2H6 are increasing 3. DGA and Furans tests are taken
LTC, or a problem with a core ground. significantly as well as CO and CO2/ immediately to confirm the problem.
4. An excellent indication of abnormally CO<5, there is probably a problem.
high temperatures and rapidly 3. These problems are probably all
deteriorating cellulose insulation is a reparable in the field where a fault will
CO2/CO<5. not degrade cellulose insulation.
5. The large increase in CO2 could
mean an atmospheric leak when the
ratio is above 10.
family of molecules based on a furan ring structure. The most as blockages of cooling system, locating electrical connection
stable of these compounds is 2-furfuraldehyde, or 2-FAL. Ther- problems and hot spots (Figure 12).
mal degradation of insulating paper could be monitored by furan
analysis, especially when due to overheating conditions. Attempts
have been made to relate the furanic content (2-FAL) of oil to the
degree of polymerization (DP) of paper (Figure 11).
E. Power Factor Test as displaced wedging and support in winding and core (Table 14).
Power factor testing is important to determine the insulation The insulation condition of bushings can also be determined by
condition of transformers because it can detect the insulation measurement of capacitance [17]. About 90% of bushing failures
integrity in winding, bushing, arrester, tank, and oil (Table 13). may be attributed to moisture ingress.
The condition of bushings can also be determined by measure-
ment of capacitance. Increased power factor may be the result of G. Excitation Current Test
moisture or polar and ionic compounds in the oil [17]. The aging The purpose of this test is to detect short-circuited turns, poor
of bushings is caused by cracking of the resin-bonded paper and electrical connections, core delaminations, core lamination shorts,
inhomogeneous impregnation with insulating oil. The technical LTC problems, and other possible core and winding problems
life time has a great scatter and should not exceed more than 30 (Table 15). The excitation current test [9], [18] measures the
years (Figure 13). single-phase voltage, current, and phase angle between them,
typically on the high-voltage side with the terminals of the other
F. Capacitance Test winding left floating (with the exception of a grounded neutral).
As the transformer ages and events such as nearby lightning On three-phase transformers, results are also compared between
strikes or through faults occur, changes in the measured capaci- phases. The measured current magnetizes the core and generates
tances indicate winding deformation and structural problems such the magnetic fields in the windings.
Figure 11. Furan versus DP for thermally upgraded and non-thermally upgraded paper [13].
1. Hotspot: unusual thermal patterns 1. Circulating stray currents. 1. Abnormally high temperature can 1. Immediate de-energization and
2. Above ambient temperature 2. Blocked cooling. damage or destroy insulation systems replacement must be undertaken.
>75 °C 3. Bad tap changer contact. and thus reduce life expectancy. 2. Internal inspection need to be
4. High temperature may mean problems 2. An increasing temperature of only 8 investigated.
with winding, core, or connections. to 10 °C will reduce transformer life by 3. Doble test may show the problem.
5. Oil leakage. one-half.
6. Ingress of moisture and air. 3. Test values are compared to previous
7. Loose shields. or factory tests.
5. Catastrophic failure is imminent which
can destroy nearby equipment and be
hazardous to workers.
H. Frequency Response Analysis (FRA) previous tests, and similar units to detect deformation of the core
FRA [19] is used to help identify possible deformations and or windings due to shipping damage, through faults, or ground
movements in the transformer core and coil assembly as well faults (Table 19).
as other internal faults (Table 16). This test is also helpful if a
protective relay has tripped or a through fault, short-circuit, or L. Core-to-Ground Test
ground fault has occurred. The core-to-ground resistance test [21] can detect the default
The basis of the FRA technique is that the impedance of the if this connection is loose or indicate if a spurious, unintentional
transformer is related to the construction and geometry of the core ground is the problem (Table 20). It can also supplement
windings. Deformations and movements have an effect on both DGA test that shows the generation of hot metal gases. To check
inductance and capacitance that may be reflected in the resulting for unintentional core grounds, the intentional ground between the
frequency response. Therefore, a change in mechanical structure core and the grounded tank must be removed. If the intentional
results in a change of the resonance frequencies. A change in core ground is intact, the resultant resistance should be very low.
electrical performance due to partial discharges also results in a Experience can help locate the source of the problem.
larger damping of the resonance frequencies.
Different aging mechanisms can be detected and identified at M. Winding Resistance
their respective frequency ranges. Shorted turns, open circuits, or Careful measurement of winding resistance can detect broken
core grounds determine the dielectric loss in the low-frequency conductor strands, loose connections, and bad contacts in LTC
range; core movement or damage is the dominant contributor in [9] (Table 21). Results from these measurements may indicate
the medium-frequency range; and winding displacement or dam-
age is the mechanical defect in the high-frequency range.
I. Vibration Test
Vibration can result from loose core and coil segments, shield
problems, loose parts, or bad bearings on oil cooling pumps
or fans [20] of transformers (Table 17). If wedging has been
displaced due to paper deterioration or through faults, vibration
will increase markedly. It may also show if an internal inspec-
tion is necessary for transformers. Information gained from the
vibration test supplements ultrasonic or acoustic detection and
DGA tests.
Power factor > 0.5 % (20 °C) 1. The insulation integrity of windings, 1. The dielectric loss indicates 1. Internal inspection should be
bushings, and insulation systems may deterioration or contamination of considered before re-energized.
be lost. insulation systems from by-products 2. If the problem is severe, the unit may
2. The state of humidity of oil is such as water, carbon, or other have to be taken out of service.
determined. conducting particles.
3. Transformer failure is imminent when 2. A trend can be established as
the power factor is above 2%. insulation system ages.
3. Test values are compared to previous
or factory tests.
the need for an internal inspection. This information supplements This test can detect partial discharge (corona) and full discharge
DGA if DGA shows the generation of heat gases. When comparing (arcing) inside the transformer (Table 22). These devices also can
to factory tests, a temperature correction must be employed. detect loose parts inside the transformer that cause corona, spark-
ing, and arcing. Sonic testing can detect increased core or coil
N. Ultrasonic and Sonic Fault Detection Tests noise (looseness) and vibration, failing bearings in oil pumps and
Partial discharge occurs in an insulating system when a local fans, and nitrogen leaks in nitrogen-blanketed transformers. Infor-
breakdown of the insulating medium causes a redistribution of mation gained from these measurements supplements DGA test-
charge within the insulating system [9], [22]. There may also be ing, and provides additional support information for de-energized
changes to the original impulse (electrical, mechanical, acoustical, tests such as core ground and winding resistance tests.
and optical) due to the propagation characteristics in the insulat-
ing medium. The PD measurement systems principally depend O. Visible Inspection and Internal Inspection
on the bandwidth (narrow-, limited-wide, or wide-band system). If an internal inspection is absolutely necessary, it must be
With the knowledge of the impulse characteristic (spectrum and completed by an experienced person who knows exactly what to
waveform of the PD impulse) different measurement methods for look for and where to look. There are very few reasons for a visible
the apparent charge and the localization of failure are possible. inspection or an internal inspection as shown below [9]:
One technique consists of electrical measurements in millivolts, • corona in bushings, arresters, and all high voltage connec-
picocoulombs, or in microvolts of radio frequency. The other tions
method consists of acoustical measurements with an ultrasonic • incorrect mechanical connections in conservator, bladder,
transducer. breather, etc.
The diagnostic procedure is based on the evaluation of the • increasing C2H2, C2H4, and C2H6 in DGA tests
signal deformation of PD pulses within the transformer by • an additional core ground
mathematical algorithms. Figure 14 describes schematically the • loose windings
localization of failure in a transformer winding which is based on • low CO2/CO ratio
the comparison of the winding model with the transfer function • high furans
measured on the real transformer winding.
Changes in capacitances 1. Bushing loss and moisture ingress. 1. A trend can be established as 1. The test results are evidenced also by
2. Winding deformation, displaced insulation system ages. an increasing power factor.
wedging and winding support as some 2. Test values are compared to previous 2. Internal inspection should be
events occur, such as near-by lightning or factory tests. considered before re-energized.
strikes or through faults. 3. If the problem is severe, the unit may
have to be taken out of service.
1. Difference between two phase- 1. There are short-circuited turns, 1. When poor electrical connections 1. Other tests should also show
excitation currents >5% for a rated poor electrical connections, core de- occur, the reluctance through the abnormalities;
excitation current < 50mA laminations, core lamination shorts, and magnetic core changes, resulting in 2. Internal inspection should be
2. Difference between two phase- LTC problems. a change in the measured excitation considered before re-energized.
excitation currents >10% for a rated 2. There is an internal problem if the current. 3. If the problem is severe, the unit may
excitation current ≥ 50mA measured value > these limits. 2. The excitation current test relies on have to be taken out of service.
reluctance of core.
3. A trend can be established as
insulation system ages.
4. Test values are compared to previous
or factory tests.
Shape change 1. There is winding displacement or 1. By the winding transfer function in 1. This test should be conducted before
>3dB damage if frequency >10000Hz. trace form, this test shows that damage and after transformer has been moved
2. There is core movement or damage if has occurred during shipping or during a or after experiencing a through fault.
frequency <5000Hz. through fault. 2. This test can show the exact phase
3. There are shorted turns, open circuits, 2. Test values are compared to previous position of problem.
or core grounds after shipping or a or factory tests. 3. Internal inspection should be
through fault if frequency < 2000 Hz. considered before re-energized.
4. If the problem is severe, the unit may
have to be taken out of service.
The measured frequency is twice the 1. There is a good condition if the Test values are compared to previous or 1. Extreme care must be exercised in
line frequency. measured value is twice the line factory tests. evaluating the source of vibration.
frequency. 2. Internal inspection should be
2. Otherwise, loose parts, loose core, considered.
loose winding, bad bearings on oil
pumps can be detected.
3. If wedging has been displaced due
to paper deterioration or through faults,
vibration will increase markedly.
Change in turns ratio to the nameplate 1. False turns ratio indicates the shorted Test values are compared to previous or 1. Set the tap changer position on which
value > 0.5% turns which may result from short factory tests. the nameplate voltage is based.
circuits, open circuits, or insulation 2. Nameplate information for reclamation
failures for service-aged transformers. transformers is based on the tap 3
2. This value is above 0.1% for new position of the tap changer.
transformers. 3. DGA and Doble tests have been
performed.
Difference from the nameplate 1. These changes in impedance indicate 1. When winding distortion occurs, the 1. This test complements capacitance
Impedance: winding deformation, displaced wedging reluctance to the magnetic flux changes, and excitation current tests and they are
> 3% and winding support as some events resulting in a change in the measured used together.
occur, such as near-by lightning strikes, leakage reactance. 2. Internal inspection should be
through faults, or other surges. 2. The leakage reactance test relies on considered before re-energized.
2. Winding deformation can lead to reluctance of spaces. 3. If the problem is severe, the unit may
immediate transformer failure after 3. A trend can be established as have to be taken out of service.
a severe through fault or a small transformers age.
deformation can lead to a failure years 4. Test values are compared to previous
later. or factory tests.
Resistance A new transformer. A trend can be established as insulation 1. The unintentional core ground must
>1000 MΩ system ages. be corrected before energizing if below
10 MΩ.
Resistance A service-aged transformer. 2. This test is necessary if
> 100 MΩ C2H4, C2H6, and CH4 are present by DGA
test and all connections are good by
Resistance Deteriorating insulation between core winding resistance test.
10-100MΩ and ground.
Resistance change to the factory value 1. Loose connections on bushing, LTC, Test values are compared to previous 1. This test is necessary if C2H4, C2H6,
> 5% and arrester may be detected. or factory tests with the same reference and CH4 are present by DGA test.
2. Shorted winding turns or open temperature. 2. Turns ratio, frequency response, and
winding circuit. Doble tests may indicate that this test is
necessary.
Asset Management of Transformer In oil-impregnated transformers, much attention has been paid
Asset management of transformers has gained an increas- to the condition diagnosis of the cellulose insulating materials (pa-
ing acceptance in the past 15 to 20 years, due to economic and per and pressboard). The insulating paper around the conductors
technical reasons. The fundamental objective is to prolong the decays if it has been aged due to the heat dissipation of windings,
possible service life and to minimize operating costs. Operation, the loss induced by eddy-current, or the presence of water. Thus,
maintenance, and refurbishment of a transformer must all be the effects of temperature and water on the lifetime of insulating
considered together to determine the whole life-cycle cost for paper should be taken into consideration.
the transformer. Furthermore, load tap changers are aged by charged particles
The lifetime of a transformer is affected by the decrease in existing in insulating materials. If the electrical stress continues
electrical, thermal, or mechanical strength, related to the aging for a long time, partial discharges produce so much decomposi-
of windings, tanks, bushings, or load tap changers. The aging tion that conductive paths are formed in dielectric materials and
of windings depends strongly on the operating history of the the dielectric strength of insulating materials tends to decrease
transformer, particularly on the thermal stress due to an overload. with time.
Tanks are affected by corrosion which is related to operating The decrease of mechanical strength is the main cause of fail-
time and maintenance history. The aging of bushings due to ures. Transformers are aged typically due to wear-out processes
thermal stress depends on the operating load of the transformer. such as material fatigue under cyclic loading. This may occur
During the normal operation of load tap changers, the operat- when normal vibration causes failure or during the more severe
ing reliability is affected by the particles produced in insulating forces of through-fault conditions. When mechanical stress is
oils corresponding to the temperature as well as to the operating present, an empirical model based on a fatigue crack propagation
frequency. approach can be described.
Frequency: Audible 1. Partial discharges most often occur 1. Low energy discharges from partial 1. This test should be applied when
near the top of transformer in areas of discharge (corona) or full discharge H2 in DGA test increasing markedly.
high voltage stress which can readily (arcing) emit energy in the order 20 CH4, C2H4, C2H6, and C2H2 may also be
be located. kHz to 200 kHz. These frequencies increasing.
2. Partial discharges located deep within are above levels that can be detected 2. Internal inspection should be
windings may not be sensitive enough to audibly. considered.
detect and locate. 2. Remedying these defects can 3. This defect can be easily remedied.
3. Loose parts inside transformer can be sometimes extend transformer service
located through the test. life.
4. Sonic (audible ranges) fault detection 3. Test values are compared to previous
can find mechanical problems such as or factory tests.
noisy bearings, gas leaks, or other loose
parts.
& 2 / -
#/..%!54
5TILIZING ADVANCED TECHNIQUES IN WINDING POLYGLASS INSULATING YARNS #ONNEAUT )NDUSTRIES
IS NOW CUSTOM WINDING LARGER PRECISION SPOOLS FOR MAGNET WIRE MANUFACTURERS
4HESE #ONNEAUT SPOOLS PROCESS MORE YARDAGE AND CAPACITY THAN PREVIOUSLY POSSIBLE
! PROPRIETARY METHOD OF YARN LAYING ENSURES EVEN CONSISTENT AND UNIFORM PACKAGES
!N INNOVATIVE PLASTIC SPOOL IS AVAILABLE IN METERED LENGTHS UP TO ENDS
4HE RECOGNIZED INDUSTRY LEADER OF INSULATING YARNS AND FIBERS #ONNEAUT PRODUCES
SPECIALTY YARNS FOR A BROAD RANGE OF INDUSTRIAL APPLICATIONS BRAIDER PACKAGES SERVING SPOOLS
AND HIGH CAPACITY PAYOFF REELS OF FIBERGLASS ROVINGREINFORCEMENTS FOR IGNITION WIRES