Professional Documents
Culture Documents
PLANNING
PREPARED BY
RAJASEKAR P K
PLANNING & TYPES
What is Planning?
- Process of formulating time based action for coordinating various
activities and resources to achieve specific objectives
- Process of developing Project Plan
Types of Construction Project Plan
1. Design & Drawings Plan PLANNING IS
2. Time Plan Decision making
3. Manpower Plan Information gathering
4. Material Plan Identifying/defining activities
5. Construction Equipment Plan Creativity
6. Finance Plan Flexibility
7. Quality Assurance Plan Inter relationships
8. Safety Plan
RAJASEKAR P K
DESIGN & DRAWINGS PLAN
Conceptual design – Conceptual sketches, Proposal analysis
Schematic design – Approval of schematic drawings, cost projections
Detailed design & drawings, BOQ, specifications, revised cost projections, mile stone completion
schedule
Drawing schedules, Shop drawings and specifications
Organising the drawings
* SPECIFICATIONS
Qualitative requirements for the products, materials and workmanship upon which the design is
based
Description in words about the work to be done, the quality of materials and workmanship, the
method of construction, the method of testing, etc.
Client’s developed Standards
RAJASEKAR P K
TIME PLAN – SHEDULING – the process of putting the Project
plan on a Calender time scale.
Drawings Schedule
Scheduling Benefits
Material schedule
Schedule simplifies Plan with Barchart, useful in
Staff Schedule Planning, coordination, Execution and control.
Labour Schedule Schedule Validates time objectives and verifies the
accomplishment of tasks on dates imposed for
Special Sub contractors schedule completion of project.
Plant & equipment schedule Schedule aids in the optimization of resources employed
and economical use of resources of men, materials and
Invoice schedule machinery
Financial schedules Schedule enables forecasting of input resources and
earned value in terms of investment, expenditure, output
Working Capital and income
Cash inflow and Outflow Scheduling brings out implications of time and resources
constraints.
Direct and Indirect Costs Monitoring of Projects against the scheduled baseline
RAJASEKAR P K
PROJECT PLANNING STEPS
Define Scope of work, method statement and FIVE LEVELS OF WBS
sequence of work
1. The entire Project
Generate the Work Breakdown Structure
2. Independent areas
(WBS) to produce a complete list of activities
3.Physically identifiable section fully contained in a
Develop Organisational Breakdown Structure
level 2 are, reflect construction strategy
(OBS) and link it with WBS to identify
responsibilities 4. Desciplines set up schedule
Determine relationship between activities 5. Master schedule activities, quantity, duration.
Estimate activities time duration, cost ACTIVITY
expenditure and resource requirement -Function in the project that consumes time, resources and
Develop the project network cost
- 3 types of activities
Production activity, procurement activity and
management activity
RAJASEKAR P K
A GOOD PROJECT PLAN
Involves advance thinking as to what is to be done, what are the activities, how it is to be
done, when it is to be done, where it is to be done, what is needed to do it and how to ensure
that it is done.
Provides the yardstick for measuring progress and evaluating resources performance
Provide the basis for coordinating the efforts of clients, consultants, architects, designers,
quantity surveyors, specialists, suppliers, contractors and the project staff
Has build in flexibility in the form of floats, to navigate changes in the planned path for
meeting fast changing environments
Creates healthy environment and make people time, cost and quality conscious
Well conceived Project Plan, developed before the commencement of Project execution stage -
can go a long way to prevent project collapse due to various aspects – making project
successful in scope and profit!
RAJASEKAR P K
THANK YOU
PREPARED BY
RAJASEKAR P K