Outline
▪ Building Officials (Rule II of the IRR)
▪ Building Permits (Rule III of the IRR)
▪ Building Occupancy (Rule VII of the IRR)
▪ Lab Exercise (Homework 1)
2
Building Officials
Section 206. Qualifications Section 207. Duties
✓ Filipino
citizen and of good moral ✓ Primarily
responsible for the
character enforcement of the provisions of
the Code and its IRR
✓ Duly registered architect or civil engineer
✓ Member of good standing of an ✓ Overall administrative control
accredited professional organization for and/or supervision over all works
not less than 5 years (endorsed and pertinent to buildings/structures
recommended) ✓ Charged with processing and
✓ At least 5 years of diversified and issuance of all permit applications
professional experience in building design and certificates
and construction ✓ Undertake annual inspections of
✓ Attendedand completed a seminar all buildings/structures and keep
workshop on PD 1096 and its IRR by the an up-to-date record of their
DPWH status
Reference: Rule II of the IRR of the NBCP 3
Building Officials Section 213. Penal Provision
“Any person, firm or corporation who shall
violate any of the Provisions of the Code…
be punished by a fine of not more than
P20,000 or by imprisonment of not more
than 2 years or by both…”
(Figure III.3) 7
Reference: Rule III of the IRR of the NBCP
Building Permits
8
Reference: Rule III of the IRR of the NBCP
Building Permits
Section 304.5. Terms and Conditions of Permits
✓ That under Article 1732 of the Civil Code of the Philippines, the engineer or architect
who drew up the plans and specifications for a building/structure is liable for damages if
within 15 years from completion… (the structure collapses) due to defect in the plans or
specifications or defects in the ground. The engineer or architect who supervises the
construction shall be solidarily liable with the contractor should the edifice collapse due to
defect in the construction or the use of inferior materials.
✓ That the permit is accompanied by the applicable ancillary and accessory permits, plans
and specifications compliant to the Code and its IRR
✓ That no building/structure shall be used until the Building Official has issued a Certificate
of Occupancy (or partial Certificate of Occupancy)
✓ That the Owner/Permittee shall submit a duly accomplished prescribed “Notice of
Construction” to the OBO prior to any construction activity and shall put up a Building
Permit sign
9
Reference: Rule III of the IRR of the NBCP
Building Permits
10
Reference: Rule III of the IRR of the NBCP
Building Permits
✓ Full time inspection and supervision of the construction work shall be through the
services of a licensed architect or civil engineer (may or may not be the same as the
designer)
✓ There shall be kept at the jobsite at all times a logbook wherein the actual progress of
construction including tests conducted, weather conditions and other pertinent data are to
be recorded.
✓ Upon completion of the construction, the licensed architect or civil engineer shall submit
the logbook, duly signed and sealed, to the Building Official. A Certificate of
Completion stating that the construction of the building conforms to the provisions of the
Code as well as with the approved plans and specification shall also be submitted.
11
Reference: Rule III of the IRR of the NBCP
Building Permits
Section 309. Certificate of Occupancy
12
Reference: Rule VII of the IRR of the NBCP
Building Occupancy
Section 701. Occupancy Classified (10 groups, 25 divisions)
A B C D E
Group
F G H I J
Group
3: wood working
esablishments, highly 3: assembly building 3: stages, platforms,
combustible materials without stage and < sport courts, tombs,
are stored or 300 occupants in the zoo structures, banks
manuactures (loose building
combustible fibers or 4: stadia, reviewing
dust) stands, amusement
4: Repair garages parks not included in
5: aircraft repair Group I, H.1, H.2, H.3
hangars
14
Building Occupancy
15
Laboratory Exercise (Week 3)
STANDARD FORM FOR BUILDING PLANS/CONTRUCTION DRAWINGS
(Figure III.1 and Figure III.2, page 35 of the IRR of the NBCP)
16
Laboratory Exercise (Week 3)
STANDARD FORM FOR BUILDING PLANS/CONTRUCTION DRAWINGS
(Figure III.1 and Figure III.2, page 35 of the IRR of the NBCP)
17
Laboratory Exercise (Week 3)
Homework 1: Standard Building Plans Template
18
Laboratory Exercise (Week 3)
Homework 1: Standard Building Plans Template (DUE ON SEPT. 23, 10AM)
1 2 3
CAGANG, Ranul Marino ALAVANZA, Kristine Joy ASUM, Warda Hadji Usman
CASIÑO, Chevy ANUDE, Chrislyn GURO, Ayman
LIM, Isaiah Rasheed CAGALAWAN, Blessie SALVADOR, Crisgen
VILLAFLOR, Julieta ROA, Kirsten Danica SOTELO, Icom Genesis
VALDEVIESO, Alyssa Dominique
4 5 6
ABAO, Aikim CASTRO, Lorenz Klein ABELLA, Von Steven
COMISION, Markzenon DIMAAMPAO, Nabel ANDALEON, Jonmar
SABELLINA, John Christian ORAN, Trisha Anne EDULSA, Niña Freshella Kate
TOLO, Prince Jun Mhark PADUA, Roden Lorenz GARRIDO, Jan Mykel
REMOLE, Christian Lear
7 8
BELLO, Windy Lou AGURA, Jenny Mae
GENOSA, Adonis ALAAN, Kent
SIMENE, Al Laurence ANIÑON, Niño Lawrence
ZABALLERO, Kent Marwin FIOLA, Kent Winston
SUMALPONG, John Mard
19
THANK YOU
20