CT411L-M CONSTRUCTION PLANNING &


SCHEDULING LAB

ACTIVITY NO.3

SUBMITTED BY:

Vicente, Hanz Leenard O.


TUPM-18-2446

SUBMITTED TO:

PROF. NESTOR D. MALAGAMBA

DATE SUBMITTED:
OCT. 17, 2021
TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES
College of Industrial Technology
Civil Engineering Technology Department
Manila

Name: Date:
Id#:
Course & Section:
Subject Code: CT411L – M
Problem:

1. Label the events and activities of the following networks in proper sequence.

Problem/Diagram and ANSWER:

2. Construct a Network Diagram from the following information:

Activity Precedes Estimated Time (weeks)


a b 15
b c, d 13
c e 8
d end 5
e end 3

Answer:
TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES
College of Industrial Technology
Civil Engineering Technology Department
Manila

3. Draw the network diagram of the following instructions.

A – is the first job of the project

O and N are the two final jobs for project completion

K – precedes O
N – follows L and M

J – restricts the start of K and M


C and B depends on the completion of A

D follows B and may go on in parallel with C and E

E follows C

I – restricts the start of J and L

H and G also restrict K and M

F must precede G and may go in parallel with H


E and D restrict H and I

C – must precede F.
Answer:
TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES
College of Industrial Technology
Civil Engineering Technology Department
Manila

4. Using the following information, perform the following:


a. Network diagram
b. Determine which activities are on the critical path
c. Compute the length of the critical path

Activity Estimated time (days)


1-2 5
2-3 6
2-4 4
3-6 10
6-7 3
4-5 5
4-7 16
5-7 10

Answer: