EBS1-FSFA00-SAEL-REEL-1003-D01
Date Sign
Code I Information only Submission - Accepted
Rejected – Major Comments – Data Provider to revise and re-submit. Work
Code R should NOT proceed in the affected areas until comments are resolved.
Comments Returned – Data provider to revise and re-submit for the further
Code C review.
Code A Accepted – Approved – No further submission required
D01 2020/09/04 IFP Wei Kai Wang Yonghao Yang Liandian Wan Kedong
D00 2020/08/30 IFE Wei Kai Wang Yonghao Yang Liandian Wan Kedong
Reason for Prepared Revised Checked Approved
REV Date
Issue By By By By
PROVISION OF EPCC SERVICE FOR
EARLY FSF CONSTRUCTION
PROJECT
TECHNICAL PROJECT SCOPE DISPL DOC SEQ REV
REQUISITION FOR Page 2 of 23
ACSR EBS1 FSFA00 SAEL REEL 1003 D01
REVISION
Rev DATE ISSUED UPDATE / AMENDMENT DETAILS
DESCRIPTION
D00 IFE 2020/08/30 Issued for Enquiry
D01 IFP 2020/09/04 Issued for Purchase
PROVISION OF EPCC SERVICE FOR
EARLY FSF CONSTRUCTION
PROJECT
TECHNICAL PROJECT SCOPE DISPL DOC SEQ REV
REQUISITION FOR Page 3 of 23
ACSR EBS1 FSFA00 SAEL REEL 1003 D01
CONTENTS
HOLDS .............................................................................................. 4
1.0 SCOPE OF SUPPLY ........................................................................ 5
2.0 ATTACHMENTS............................................................................. 6
3.0 DETAILED REQUIREMENTS ............................................................... 7
3.1 General .............................................................................................. 7
HOLDS
HOLD
Section Description
No.
No HOLDS
PROVISION OF EPCC SERVICE FOR
EARLY FSF CONSTRUCTION
PROJECT
TECHNICAL PROJECT SCOPE DISPL DOC SEQ REV
REQUISITION FOR Page 5 of 23
ACSR EBS1 FSFA00 SAEL REEL 1003 D01
ITEM
QTY DESCRIPTION
No.
1 38km ACSR-120/20
Data sheets EBS1-FSFA00-SAEL-DTEL-1003, SPECIFICATION EBS1-
FSFA00-SAEL-SPEL-1003.
2 3.8km ACSR-70/10
Data sheets EBS1-FSFA00-SAEL-DTEL-1003, SPECIFICATION EBS1-
FSFA00-SAEL-SPEL-1003.
PROVISION OF EPCC SERVICE FOR
EARLY FSF CONSTRUCTION
PROJECT
TECHNICAL PROJECT SCOPE DISPL DOC SEQ REV
REQUISITION FOR Page 6 of 23
ACSR EBS1 FSFA00 SAEL REEL 1003 D01
2.0 ATTACHMENTS
Project Specifications:
EBS1-FSFA00-SAEL-SPEL-1003 : SPECIFICATION FOR ACSR
CODES AND STANDARDS
The vendor shall meet or exceed the requirements of the latest edition of the following codes,
Regulations and standards, except as superseded herein. In case where more than one code,
regulations or standards apply to the same condition, the most stringent shall be following:
IEC61089: Round wire concentric lay overhead electrical stranded conductors
PROVISION OF EPCC SERVICE FOR
EARLY FSF CONSTRUCTION
PROJECT
TECHNICAL PROJECT SCOPE DISPL DOC SEQ REV
REQUISITION FOR Page 7 of 23
ACSR EBS1 FSFA00 SAEL REEL 1003 D01
accordance with IEC 61089. The extent of grease to be applied shall be Case 2 as
described in IEC 61089. After application of grease and before the outer layer of wires is
stranded the penultimate layer of wires shall be thoroughly wiped so that all remaining
visible grease on the conductor is between the wires of the penultimate layer. The
stranding of each layer of the conductor shall be as close and even as possible. The
outermost layer shall be right-handed. The aluminum shall be of the highest purity
commercially obtainable and the Contractor shall submit quality certificates of analyses
giving the percentage and nature of any impurities in the metal of which wires are made.
Precautions shall be taken during manufacture, storage and erection of ACSR conductors
to prevent the possibility of contamination by copper or other materials which may
adversely affect the aluminium.
PROVISION OF EPCC SERVICE FOR
EARLY FSF CONSTRUCTION
PROJECT
TECHNICAL PROJECT SCOPE DISPL DOC SEQ REV
REQUISITION FOR Page 9 of 23
ACSR EBS1 FSFA00 SAEL REEL 1003 D01
D = Delivery
- 1 = 1 Week Before
+1 = 1 Week After
RI = Review by Inspector at the VENDOR/BIDDER’s Works
(e.g. -2D = Required 2 weeks before delivery)
Submit with
Submit for
Include in
Include in
Document
Submit as
Review
Code
Final
MRB
IOM
Bid
Document Description
1 General
2 Sub-Orders
3 Concessions
PROVISION OF EPCC SERVICE FOR
EARLY FSF CONSTRUCTION
PROJECT
TECHNICAL PROJECT SCOPE DISPL DOC SEQ REV
REQUISITION FOR
Page 15 of
ACSR EBS1 FSFA00 SAEL REEL 1003 D01 23
Submit with
Submit for
Include in
Include in
Document
Submit as
Review
Code
Final
MRB
IOM
Bid
Document Description
4.8 Specific
. Project Quality Manual
4.12 Specific
S Project Internal and External Audit Schedule +4P
Submit with
Submit for
Include in
Include in
Document
Submit as
Review
Code
Final
MRB
IOM
Bid
Document Description
5 Interface Documents
Submit with
Submit for
Include in
Include in
Document
Submit as
Review
Code
Final
MRB
IOM
Bid
Document Description
6 Mechanical Documents
Submit with
Submit for
Include in
Include in
Document
Submit as
Review
Code
Final
MRB
IOM
Bid
Document Description
7 Electrical Documents
Submit with
Submit for
Include in
Include in
Document
Submit as
Review
Code
Final
MRB
IOM
Bid
Document Description
Weighing Procedure RI
Those documents required for submittal are shown on the document tables in Section 9.0.
The tables will indicate which documents are required with the bid, for review and those
required in data books in the form of a Manufacturing Record Book (MRB) and an
Installation-Operation-Maintenance Manual (IOM).
The VENDOR/BIDDER shall produce a document schedule to identify all the required
documents. The schedule will be used to track submittal dates, revision status and
approval status of individual documents. The schedule shall be continuously updated and
submitted periodically by the VENDOR/BIDDER to satisfy the project reporting procedures.
Quantities of documents required for review shall be as follows and confirmed by
COMPANY:
Submitted for: Review Certified Final (Native and PDF)
Drawings: 1 Soft Copy 6 Prints + 1 Soft Copy
Documents: 1 Soft Copy 6 Prints + 1 Soft Copy
Documents included in VENDOR/BIDDER data books shall be compiled in files with 4 ring
holes.
Files shall be identified on the front cover and spine with the Project name/number,
Purchase Order number, equipment description, tag number and titled Manufacturing
Record Book (MRB) or Installation-Operation-Maintenance Manual (IOM).
The IOM shall cover the following categories and contain the documents indicated in the
document tables in Section 9.0.
Sub-vendor data, together with their own indexes, shall be compiled as separate sections
of the VENDOR/BIDDER’s data book i.e. not integrated with VENDOR/BIDDER’s data.
Section 1 : Purchase Order, Change Orders
Section 2 : Sub-vendors names, addresses, contacts, telephone numbers.
Section 3 : Punch list, Concession Log, Concessions / Waivers.
Section 4 : Quality Documents
Section 5 : Interface Documents
Section 6 : Mechanical Documents
Section 7 : Electrical Documents
Section 8 : Manufacturing and Test Procedures
Section 9 : Certification/Records/Reports/Data
Sub-vendor 1 etc. : Index and Documentation to be compiled as a section of the
VENDOR/BIDDER’s MRB.
(N.B. Copies of Release Notes, Punch lists, Concessions, Handling procedures, Lifting
Gear Test Certification and preservation procedure/ instructions shall accompany the
equipment when shipped.)