Professional Documents
Culture Documents
M Venkata Rao
DM(E) The case study is sharing the experience and learning while
E Purnachandar
implementing certain actions and modifying operating practices like
AM(O) converter positioning, methodology of addition of scrap and lime,
improvement in condition and availability of slag pot, increasing
periodicity of lance calibration and scanning of converter lining
conditions etc., to control the converter bottom build-up and
bringing it to a level below 0.4m.
Abstract :
Pig iron is converted into steel by oxidation of impurities in L D converters lined with Mgo-C refractory
bricks. Scrap& iron ore are added as primary and secondary coolants respectively. Refining process
takes around 18 min where fluxes are added to facilitate transport of impurities into slag. Of late
excessive converter bottom build up is causing concern to SMS because it is not only hampering
productivity but also causing threat to the safety of the employees and to the equipment.
This case study shares the learning and experience from the efforts made to control the excessive
converter bottom buildup by standardizing operating practices, increasing periodicity of converter
lining scanning, lance calibration etc.
Background:
After the previous heat is tapped and slag is drained, lining is inspected. Scrap and hot metal are
charged. Converter is tilted into the vertical position and the lance is lowered in the vessel to start the
blowing. Selection of the starting lance distance is such that the concentration of the force at the bath
level should not cause ejection of tiny iron particles (sparking) and at the same time maximum bath
surface area is covered by the oxygen jet. The starting lance distance (Xi) for specific oxygen blowing
rate Nm3/ (ton × min) can be calculated by
Xi = 0.541(db)1.04 where, db is bath diameter in meter.
Nevertheless, in all converters initial lance distance is such as to promote iron oxidation so that
dissolution of CaO commences. The idea is to create a basic and limy slag at the early part of the blow
to onset de-phosphorization. Shallow jet penetration covers the larger bath surface and is favorable
more for iron and silicon oxidation. Small amount of carbon may be removed. Once slag is formed,
lance is lowered. Oxygen jet penetrates into the bath and carbon reaction favours because oxygen is
available now deep into the bath. At the same time, force of the oxygen jet creates metal droplets and
as a consequence three phase dispersion of gas/slag /metal droplets are formed which enhance the
rate of decarburization.
At higher lance distance, oxygen jet penetration into bath is shallow and slag formation occurs. As the
lance distance decreases, jet penetrates deep into the bath, carbon reaction commences, CO forms,
droplets are produced which together leads to the formation of a three phase dispersion consisting of
gas bubbles, slag, metal droplets. In this state of blow, both carbon and phosphorus removal occur at
a faster rate. Formation of three phase dispersion is a characteristic feature of the top blown
steelmaking. Three phase dispersion creates conditions for faster removal rates of C and P. Foaming
of slag has to be controlled to avoid expulsion of slag, which can be controlled by controlling Carbon
reaction with FeO in slag. Reaction between C and FeO in slag will not allow CO bubbles to grow.
Smaller size gas bubbles can be trapped easily in slag as compared to larger sizes. Slag may foam and
may be expelled from the converter. Thick viscous slag and adherence of the retained slag to the
Excessive bottom built up in converter decreases the specific volume of the converter and also shift
the reaction zone of the converter to the top causing spillage of metal/slag, body jam formation and
track dozing, erosion of lip plates and also skull formation on the lance. Excessive bottom built up in
converter had directly reflected in productivity where converter -A had to be stopped due to skirt
movement problem for 241Hrs in the first campaign due to jam, later it was removed by O2 lancing
again this problem has repeated resulting declaring down for campaign repair. During the second
campaign also the same problem repeated resulting in a delay of 145Hrs.Apart from this, several other
problems faced are burning of SPTC & STC cables due to metal/slag overflow from mouth of the
converter, Lance tip failures, deformation of converter mouth, Umbrella plates deformation, Abnormal
change in blowing profile etc.,
11-Sep-…
13-Sep-…
15-Sep-…
17-Sep-…
19-Sep-…
23-Sep-…
25-Sep-…
27-Sep-…
29-Sep-…
22-Aug-…
24-Aug-…
26-Aug-…
28-Aug-…
1-Oct-15
3-Oct-15
5-Oct-15
7-Oct-15
9-Oct-15
11-Oct-15
13-Oct-15
15-Oct-15
17-Oct-15
19-Oct-15
21-Oct-15
23-Oct-15
25-Oct-15
27-Oct-15
29-Oct-15
31-Oct-15
1-Sep-15
3-Sep-15
5-Sep-15
7-Sep-15
9-Sep-15
In order to control the convertor bottom build up within the limits, a cross functional team has been
formed to study the above problem and to implement actions identified.
Implementation Methodology
Major Improvement Project
Team Members:
Sl.No. Name (S/Shri) Emp. No. Design. Dept.
1 J Anand Kumar 118874 AGM(O) SMS
2 M V Ramnarayana Rao 110805 AGM(O) SMS
3 K V M Nageswara Rao 111793 DM(M) SMS
4 M Venkata Rao 105536 DM(E) SMS
5 E Purnachandar 121783 AM(O) SMS
Sec. Metallurgy/
MM/CSD Ferro Alloys CCD
(required
Tapping
MM/CSD Petro Coke Liquid Steel parameters:
MM/CSD Aluminium
Then a detailed process map is made to study the process and to identify contributing factors and
existing controls to run the process within the permissible limits thereby to control excessive converter
bottom buildup.
Existing Control:
Periodical maintenance &
planning
ARS
Parameters No
Ok
Yes
Casting
Data collection was carried out and from the data, most recurring factors among the above identified
contributing factors are further funnelled down and Pareto analysis has been carried out to identify
vital few factors those are contributing for excessive bottom build up. The Pareto Analysis is shown
below:
100.00
90.00
80.00
70.00
60.00
50.00
40.00
30.00
20.00
30.95 27.38 22.62 10.00
9.52 5.95 3.57 0.00
SPTC Non- Low reactivity in STC Non-
HM Si content Slag Pot jam Slag Yard Prob.
Availability lime Availability
% Contribution 30.95 27.38 22.62 9.52 5.95 3.57
Cum. % 30.95 58.33 80.95 90.48 96.43 100.00
Further, various factors leading to the above are identified and a cause and effect diagram is made.
The cause and effect diagram is indicated below:
Why-Why Analysis:
Process / Eqpt/ Failure/ Major reason Root Cause Analysis *
Sl.
Assembly/ undesired / Contributing
No Cause Sub-Cause-1 Sub-Cause-2 Sub cause-3 Sub-Cause-4 Sub-Cause-5
sub-assembly event factor
1 Steel Making/ Increase in Slag drying SPTC Non- Field fault
Converter Bottom Availability Cable Problem Cable cut Position
Buildup Stuck up Jam
Re-termination Cable cut Position
BF Throttling Material
Si in HM non-
availability
Slag Pot Jam Slag Drying Improper Slag fluidity Si Content BF Issue
dumping in HM
Delay in Crane
dumping problem
STC Non- Stucking up Jam Spills on Jammed slag
availability track pot
Cable Spillage of hot Jammed Slag
burning material pot
Field fault
Car De- Jam Spills on Jammed slag
railment track pot
Poor LOI variation CRMP issue
Flux
Quality &reactivity
In addition to the above analysis, risk prioritisation is also done using FMEA methodology. Then the
action plan is made to eliminate root causes and causes with higher risk priority number (RPN).
1. Viscous slag:
The tapping in-charge closely monitors the condition of slag in
every heat during tapping and inform the blower regarding the
same and instruct the blower for specific addition of dolomite for
slag conditioning before slag splashing. In case the slag is viscous
a practice of dumping slag completely without slag splashing is
introduced so as not to allow the viscous slag to adhere at the
converter bottom and leading to buildup.
5. Poor productivity:
Any disruption in production causing idle time in Converter may lead to bottom buildup due to Lime added
in bottom will stick to the bottom and increase it. Hence whenever production clearance is withdrawn due
to machine closure .it is advised to keep the converter in nose down condition or inclined to 900 towards
charging side .Incase of minor maintenance schedules like mouth jam dropping, track dozing etc., bottom
lime should not be added.
Results
1) Converter bottom build up has been controlled through altering and ensuring certain operational
practices in the area of positioning converters, slag splashing and dumping, scrap and lime & other flux
materials charging practices, rescheduling/ increasing the periodicity of condition monitoring practices
etc.,
2) The bottom build up in all the three converters is controlled and kept below 0.5m level as targeted.
During Apr-May, 2017, the bottom buildup levels are varied below 0.4m.
20-Nov-16
25-Nov-16
30-Nov-16
31-Oct-16
5-Nov-16
15-Nov-16
5-Dec-16
10-Dec-16
15-Dec-16
20-Dec-16
25-Dec-16
30-Dec-16
4-Jan-17
9-Jan-17
5-Mar-17
16-Sep-15
30-Sep-15
15-Feb-16
26-Feb-16
13-Feb-17
18-Feb-17
23-Feb-17
28-Feb-17
22-Aug-15
3-Feb-17
8-Feb-17
10-Jan-16
26-Jan-16
14-Jan-17
19-Jan-17
24-Jan-17
29-Jan-17
10-Mar-17
15-Mar-17
20-Mar-17
25-Mar-17
30-Mar-17
0.4
0.3
0.2
0.1
The discontinuation of the trend during certain periods is due to campaign repairs of respective
converter during that period.
3) After implementation of various operational controls and continuing over a period of 6 months, the
FMEA is again carried out and indicated above. From the above FMEA it can be observed that there is
considerable reduction in RPN.
Schedule of Work
Conclusion
Several trials and studies have been conducted from the month of Aug-2016 to Mar-2017 to evaluate
root cause and the reasons for bottom build up were systematically screened. The solutions
implemented as described above yielded into controlling the converter bottom buildup below 0.4m
level from an average level of about 1.5m before taking up the project.
Whenever converter is planned for maintenance bottom lime should not be added soon after
slag dumping, it should be added only before charging of hot metal. In earlier practices the
bottom lime added used to stick and resulted to in converter bottom build up.
If slag is left over in the converter wait for another slag pot and dump the slag. During this waiting
period ensure converter is tilted towards charging side up to 900 or onto tapping side up to 900,
but should not be kept in in vertical position.
In case of poor lime quality (high LOI and low reactivity) 20% more than required quantity of lime
is to be added but in small batches within 5 min.
In case of low “Si” content <0.30 in hot metal, iron ore/sinter should be added as coolant in place
of steel scrap as addition of steel scrap further reduces the average “Si” content of the hot metal.
In case of high “Si” content in hot metal>0.70 intermediate de-slagging should be done without
fail to avoid left over of slag in the converter even after slag dumping.
In case bottom build up is above 1.0 met the following procedure to be followed to reduce it to
below 0.5m within 24hrs which was implemented successfully in this project and kept as control
measures.
a) After completely dumping the slag charge 3-5 ton of hot metal in the converter.
b) Blow oxygen at a rate of 450nm3/min till cumulative oxygen reaches 2000 nm3
c) After blowing, keep the converter in vertical position for 30 min
d) After 30 min dump the entire slag completely in jam pots so that it will not damage the slag
pots
e) Do lance calibration there will be reduction in bottom and further reduction in bottom is also
noticed during subsequent heats.