Professional Documents
Culture Documents
Release 2.0
June 2013
OUM Cloud Application Services Implementation Approach Solution Delivery Guide, Release 2.0
Copyright © 2012, 2013, Oracle and/or its affiliates. All rights reserved. This document is provided for information
purposes only, and the contents hereof are subject to change without notice. This document is not warranted to be
error-free, nor subject to any other warranties or conditions, whether expressed orally or implied in law, including
implied warranties and conditions of merchantability or fitness for a particular purpose. We specifically disclaim any
liability with respect to this document, and no contractual obligations are formed either directly or indirectly by this
document. This document may not be reproduced or transmitted in any form or by any means, electronic or
mechanical, for any purpose, without our prior written permission. Oracle and Java are registered trademarks of
Oracle and/or its affiliates. Other names may be trademarks of their respective owners.
Scope .....................................................................................................2-2
Objectives ..............................................................................................2-3
Approach Overview................................................................................2-4
Contents ii OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Activity/Task Group .........................................................................4-8
Work Product...................................................................................4-8
Prerequisites....................................................................................4-8
Approach .........................................................................................4-8
Roles and Responsibilities ..............................................................4-9
WM.010 – Create Detailed Plan for Current Release (Core) ..............4-10
Activity/Task Group .......................................................................4-10
Work Product.................................................................................4-10
Prerequisites..................................................................................4-10
Approach .......................................................................................4-10
Roles and Responsibilities ............................................................4-11
RD.011.1 – Review In-Scope High-Level Business
Processes (Core) .................................................................................4-12
Activity/Task Group .......................................................................4-12
Work Product.................................................................................4-12
Prerequisites..................................................................................4-12
Approach .......................................................................................4-12
Roles and Responsibilities ............................................................4-12
MC.040.1 – Gather Setup Information (Core) .....................................4-13
Activity/Task Group .......................................................................4-13
Work Product.................................................................................4-13
Prerequisites..................................................................................4-13
Approach .......................................................................................4-13
Roles and Responsibilities ............................................................4-14
TA.030 – Conduct Integration Workshop (Core) .................................4-15
Activity/Task Group .......................................................................4-15
Work Product.................................................................................4-15
Prerequisites..................................................................................4-15
Approach .......................................................................................4-15
Roles and Responsibilities ............................................................4-16
CV.010 – Conduct Data Load Workshop (Core) .................................4-17
Activity/Task Group .......................................................................4-17
Work Product.................................................................................4-17
Prerequisites..................................................................................4-17
Approach .......................................................................................4-17
Roles and Responsibilities ............................................................4-18
DO.010 – Define Documentation Requirements and
Strategy (Optional)...............................................................................4-19
Activity/Task Group .......................................................................4-19
Work Product.................................................................................4-19
Prerequisites..................................................................................4-19
Approach .......................................................................................4-19
Roles and Responsibilities ............................................................4-20
OCM.015 – Identify Process Change Candidates (Optional)..............4-21
Activity/Task Group .......................................................................4-21
Work Product.................................................................................4-21
Prerequisites..................................................................................4-21
Approach .......................................................................................4-21
Roles and Responsibilities ............................................................4-21
Contents iv OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Work Product.................................................................................5-11
Prerequisites..................................................................................5-11
Approach .......................................................................................5-11
Roles and Responsibilities ............................................................5-12
MC.040.2 – Capture and Prioritize Additional Configurations (Core)..5-13
Activity/Task Group .......................................................................5-13
Work Product.................................................................................5-13
Prerequisites..................................................................................5-13
Approach .......................................................................................5-13
Roles and Responsibilities ............................................................5-13
MC.050.1 – Update Setup Documentation (Core)...............................5-14
Activity/Task Group .......................................................................5-14
Work Product.................................................................................5-14
Prerequisites..................................................................................5-14
Approach .......................................................................................5-14
Roles and Responsibilities ............................................................5-15
MC.063 – Conduct Configuration Familiarization Session (Core).......5-16
Activity/Task Group .......................................................................5-16
Work Product.................................................................................5-16
Prerequisites..................................................................................5-16
Approach .......................................................................................5-16
Roles and Responsibilities ............................................................5-17
DS.140.1 – Prepare Detailed Technical Specification –
Fusion (Optional) .................................................................................5-18
Activity/Task Group .......................................................................5-18
Work Product.................................................................................5-18
Prerequisites..................................................................................5-18
Approach .......................................................................................5-18
Roles and Responsibilities ............................................................5-19
DS.140.2 – Prepare Detailed Technical Specification – Client
Systems (Optional) ..............................................................................5-20
Activity/Task Group .......................................................................5-20
Work Product.................................................................................5-20
Prerequisites..................................................................................5-20
Approach .......................................................................................5-21
Roles and Responsibilities ............................................................5-21
CV.027.1 – Perform Data Mapping (Optional).....................................5-22
Activity/Task Group .......................................................................5-22
Work Product.................................................................................5-22
Prerequisites..................................................................................5-22
Approach .......................................................................................5-22
Roles and Responsibilities ............................................................5-22
CV.053 – Populate Data Load Templates with Client Data (Core) .....5-23
Activity/Task Group .......................................................................5-23
Work Product.................................................................................5-23
Prerequisites..................................................................................5-23
Approach .......................................................................................5-23
Roles and Responsibilities ............................................................5-23
MC.060.2 – Apply Setup Changes (Core) ...........................................5-24
Contents vi OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Work Product.................................................................................5-34
Prerequisites..................................................................................5-34
Approach .......................................................................................5-34
Roles and Responsibilities ............................................................5-34
MC.060.7 – Implement Localizations (Optional)..................................5-35
Activity/Task Group .......................................................................5-35
Work Product.................................................................................5-35
Prerequisites..................................................................................5-35
Approach .......................................................................................5-35
Roles and Responsibilities ............................................................5-35
MC.060.8 – Implement Composer Updates (Optional) .......................5-36
Activity/Task Group .......................................................................5-36
Work Product.................................................................................5-36
Prerequisites..................................................................................5-36
Approach .......................................................................................5-36
Roles and Responsibilities ............................................................5-36
MC.065.2 – Validate Setup Changes (Optional) .................................5-37
Activity/Task Group .......................................................................5-37
Work Product.................................................................................5-37
Prerequisites..................................................................................5-37
Approach .......................................................................................5-37
Roles and Responsibilities ............................................................5-37
RD.011.2 – Update Business Processes (Core) .................................5-38
Activity/Task Group .......................................................................5-38
Work Product.................................................................................5-38
Prerequisites..................................................................................5-38
Approach .......................................................................................5-38
Roles and Responsibilities ............................................................5-38
TE.027.1 – Update Validation Cases (Core) .......................................5-39
Activity/Task Group .......................................................................5-39
Work Product.................................................................................5-39
Prerequisites..................................................................................5-39
Approach .......................................................................................5-39
Roles and Responsibilities ............................................................5-39
IM.050.1 – Implement Integration Packages – Fusion (Optional) .......5-40
Activity/Task Group .......................................................................5-40
Work Product.................................................................................5-40
Prerequisites..................................................................................5-40
Approach .......................................................................................5-40
Roles and Responsibilities ............................................................5-41
IM.050.2 – Implement Integration Packages – Client
Systems (Optional) ..............................................................................5-42
Activity/Task Group .......................................................................5-42
Work Product.................................................................................5-42
Prerequisites..................................................................................5-42
Approach .......................................................................................5-42
Roles and Responsibilities ............................................................5-43
IM.050.3 – Load and Validate Data to Client Systems (Optional) .......5-44
Activity/Task Group .......................................................................5-44
Contents viii OUM Cloud Application Services Implementation Approach Solution Delivery Guide
CV.065.2 – Load, Reconcile and Validate Data (Core) .........................6-7
Activity/Task Group .........................................................................6-7
Work Product...................................................................................6-7
Prerequisites....................................................................................6-7
Approach .........................................................................................6-7
Roles and Responsibilities ..............................................................6-7
MC.060.9 – Apply Setup Changes (Core) .............................................6-8
Activity/Task Group .........................................................................6-8
Work Product...................................................................................6-8
Prerequisites....................................................................................6-8
Approach .........................................................................................6-8
Roles and Responsibilities ..............................................................6-8
MC.050.4 – Update Setup Documentation (Core).................................6-9
Activity/Task Group .........................................................................6-9
Work Product...................................................................................6-9
Prerequisites....................................................................................6-9
Approach .........................................................................................6-9
Roles and Responsibilities ..............................................................6-9
RD.011.3 – Update Business Processes (Core) .................................6-10
Activity/Task Group .......................................................................6-10
Work Product.................................................................................6-10
Prerequisites..................................................................................6-10
Approach .......................................................................................6-10
Roles and Responsibilities ............................................................6-10
TE.027.2 – Update Validation Cases (Core) .......................................6-11
Activity/Task Group .......................................................................6-11
Work Product.................................................................................6-11
Prerequisites..................................................................................6-11
Approach .......................................................................................6-11
Roles and Responsibilities ............................................................6-11
TE.105 – Prepare Users for Validation (Core).....................................6-12
Activity/Task Group .......................................................................6-12
Work Product.................................................................................6-12
Prerequisites..................................................................................6-12
Approach .......................................................................................6-12
Roles and Responsibilities ............................................................6-12
TE.070 – Conduct End-to-End Review (Core) ....................................6-13
Activity/Task Group .......................................................................6-13
Work Product.................................................................................6-13
Prerequisites..................................................................................6-13
Approach .......................................................................................6-13
Roles and Responsibilities ............................................................6-14
DO.070 – Publish User Guide (i.e., Job Aid) (Optional) ......................6-15
Activity/Task Group .......................................................................6-15
Work Product.................................................................................6-15
Prerequisites..................................................................................6-15
Approach .......................................................................................6-15
Roles and Responsibilities ............................................................6-16
DO.075 – Publish Admin Guide (Optional) ..........................................6-17
Contents x OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Roles and Responsibilities ..............................................................7-5
CV.065.3 – Load, Reconcile and Validate Data Loads in
Production (Core)...................................................................................7-6
Activity/Task Group .........................................................................7-6
Work Product...................................................................................7-6
Prerequisites....................................................................................7-6
Approach .........................................................................................7-6
Roles and Responsibilities ..............................................................7-6
TE.120 – Conduct Final Validation Review with Users and
Stakeholders (Core)...............................................................................7-7
Activity/Task Group .........................................................................7-7
Work Product...................................................................................7-7
Prerequisites....................................................................................7-7
Approach .........................................................................................7-7
Roles and Responsibilities ..............................................................7-7
TR.100 – Conduct End-User Training (Core) ........................................7-9
Activity/Task Group .........................................................................7-9
Work Product...................................................................................7-9
Prerequisites....................................................................................7-9
Approach .........................................................................................7-9
Roles and Responsibilities ..............................................................7-9
TS.052 – Implement Support Infrastructure (Core) .............................7-10
Activity/Task Group .......................................................................7-10
Work Product.................................................................................7-10
Prerequisites..................................................................................7-10
Approach .......................................................................................7-10
Roles and Responsibilities ............................................................7-10
TS.058 – Verify Production and Operational Readiness (Core)..........7-11
Activity/Task Group .......................................................................7-11
Work Product.................................................................................7-11
Prerequisites..................................................................................7-11
Approach .......................................................................................7-11
Roles and Responsibilities ............................................................7-11
TS.060 – Begin System Use (Core) ....................................................7-13
Activity/Task Group .......................................................................7-13
Work Product.................................................................................7-13
Prerequisites..................................................................................7-13
Approach .......................................................................................7-13
Roles and Responsibilities ............................................................7-13
D.PEC.TSK – Manage Project Execution (Core) ................................7-14
Activity/Task Group .......................................................................7-14
Work Product.................................................................................7-14
Prerequisites..................................................................................7-14
Approach .......................................................................................7-15
Roles and Responsibilities ............................................................7-15
D.PGM.TSK – Program Management (Optional) ................................7-16
Activity/Task Group .......................................................................7-16
Work Product.................................................................................7-16
Prerequisites..................................................................................7-16
Contents xii OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Prerequisites....................................................................................9-4
Approach .........................................................................................9-4
Roles and Responsibilities ..............................................................9-4
PS.ACT.CPC – Close Processes and Contract (Core) .........................9-5
Activity/Task Group .........................................................................9-5
Work Product...................................................................................9-5
Prerequisites....................................................................................9-5
Approach .........................................................................................9-5
Roles and Responsibilities ..............................................................9-6
PS.ACT.DLLAP – Document Lessons Learned and Archive
Project (Core).........................................................................................9-7
Activity/Task Group .........................................................................9-7
Work Product...................................................................................9-7
Prerequisites....................................................................................9-7
Approach .........................................................................................9-7
Roles and Responsibilities ..............................................................9-7
1 Introduction
Introduction 1 - 2 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
How to Use This Guide
The OUM Cloud Application Services Implementation Approach Solution Delivery Guide
contains general information about using this approach for Fusion Applications Cloud
implementation projects.
Contributors
Catherine Anderson, Steve Angelo, Anthony Bartolotto, Rob Boucher, David Burke, Terry
Chan, Bruce Dehner, Dave Edgecomb, Khaled Eldarawy, Mark Garlen, Peter Hammond,
Lieven Heymans, Sriram Krishnan, Jason Livingston, Linda Lowitz, Won Park, Tushar
Roy, Alok Sahay, Tim Sent, Tom Spitz, Ken Thompson, Louann Weaver, Marco van der
Peet, Eric Wendlandt
mailto:ominfo_us@oracle.com
2 Approach Overview
While the approach does not adhere to the work breakdown structure previously defined
for the OUM Implement Focus Area views, it does embody many of the principles on
which OUM is based.
While the focus of the approach is on the rapid implementation of the functionality within
the predefined boundaries of the Fusion fixed scope offerings, selected for
implementation, the approach also includes support for selected, additional services
(beyond the scope of the those offerings) including, additional configurations, additional
data loads, additional integrations, etc.
Approach Overview 2 - 2 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Objectives
The objectives of the OUM Cloud Application Services Implementation Approach follow:
The Plan phase is the first phase in the OUM Cloud Application Services Implementation
Approach and is critical for establishing a positive impression, and setting appropriate
expectations, with the client. During this phase, a kick-off meeting is held to orient the
entire project team to the project objectives and how the project will be conducted.
Workshops for gathering setup information and disseminate information regarding the
integrations and data loads are scheduled. A detailed plan for the current release is
prepared and applicable business processes reviewed. Previously scheduled workshops
to gather initial setup information are conducted, as well as workshops to communicate
Fusion integration concepts and data conversion options.
At the outset of the Prototype phase, the Staging Environment is configured using the
initial setup values collected during the Plan phase. An initial set of prototyping
workshops are then conducted with a focus on reviewing the standard functionality as
configured in the Staging Environment, collecting feedback, prototyping refinements and
capturing and prioritizing additional configuration settings.
Client personnel have responsibility for updating the Fusion Business Processes and
validation cases, as necessary, to reflect the resulting configuration.
If custom data loads, or integrations, are within the scope of the project, technical
specifications are also prepared, and the integrations built, during the Prototype phase.
Data load templates are populated with Client data and subsequently uploaded to the
Staging Environment.
Approach Overview 2 - 4 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
A second set of prototyping sessions conducted during the Prototype Phase is focused
on applying and validating configuration changes, which may include extensible items
such as workflows, notifications, FastFormulas, FlexFields, localizations and composer
updates, as well as validating required integrations and data loads.
Activities during the Validate phase include the entry of any additional configuration
changes in the Staging Environment and the validation of those values. If necessary,
business processes and test cases are again updated to reflect the resulting state of the
environment and sample client data is loaded in preparation for an end-to-end review.
The end-to-end review conducted in the Validate phase is intended to validate the final
configuration, which will be used to configure the Production Environment in the next
phase. During the end-to-end review, a series of validation cases are executed to
validate the proper functioning of the software solution. The test cases should also
exercise the client data that has been loaded to the Staging Environment using the data
load templates to validate that the data has been loaded properly.
A train-the-trainer event is also held in the Validate phase to prepare designated client
personnel to train end users during the next phase in preparation for the new system
being placed in use.
The Transition phase focuses on moving the new software system and the organization
to active use. The validated configuration is migrated to the Production Environment, the
client data is loaded, and a final review is conducted with users and stakeholders to help
ensure that the new environment is ready for use. A production and operational
readiness assessment is made as a final checkpoint and the Transition phase concludes
with the new system being placed in use.
The Production phase begins active use of the system and, during the phase, the
transition to steady-state operations is managed. A key activity in the Production phase
is planning for the next release and making provisions for the appropriate maintenance
and governance of the new system.
Core and Optional Tasks in the OUM Cloud Application Services Implementation Approach
The core tasks in the OUM Cloud Application Services Implementation Approach define
the minimum set of steps necessary to implement the functionality contained within the
predefined boundaries of Fusion Applications fixed scope offerings from Oracle
Consulting, or Oracle’s implementation partners. You may also need to include several
other tasks in your project depending on your specific circumstances. For example, if
your project includes custom integrations, or additional training or documentation
requirements, you may need to include several optional tasks that support those
additional services. A good test during project planning is to walk through the core tasks
and assess whether they will be sufficient to meet the project’s needs. If not, begin
considering optional tasks. This planning process should help create an efficient project
approach.
Approach Overview 2 - 6 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Important Concepts
There are several key concepts that are important to understand in order to fully
appreciate the OUM Cloud Application Services Implementation Approach. These
concepts include:
• Division of Responsibility
• Project Management
Division of Responsibility
Another key concept related to the OUM Cloud Application Services Implementation
Approach is the division of responsibility between Oracle and client resources. To help
achieve a lower implementation cost, a number of activities performed during the project
are shared between Oracle and client personnel. Where appropriate, some activities are
assigned solely to client resources, such as extracting data from client legacy systems.
Refer to the Responsibilities section of each phase chapter for a listing of the tasks by
responsibility. Each task description also contains a Roles and Responsibility section
delineating who is responsible for the completion of that task.
Project Management
The OUM Cloud Application Services Implementation Approach includes Project
Management Start Up, Execution and Control, and Project Closure tasks consistent with
the OUM Manage Focus area.
The above illustration demonstrates how the Project Management phases are integrated
with the OUM Cloud Application Services implementation phases to fully document the
OUM Cloud Application Services Approach. The Project Start Up phase typically begins
Because Cloud implementations tend to be smaller and less complex than the average
traditional OUM implementation, the OUM Cloud Application Services Approach Project
Management tasks are associated with the OUM Manage activity level to better scale to
the project management needs of an OUM Cloud implementation.
To simplify, and convey that the OUM Cloud Application Services Approach project
management tasks are not intended to be performed in a serial manner; activities are
included to group the project management tasks. These activities are unique to the OUM
Cloud Application Services Approach and do not relate to any structure in OUM Manage.
The activities and tasks generally associated with project management along with project
management leading practices; remain critical to any implementation project. The OUM
Cloud Application Services Approach draws upon this knowledge but also includes some
task steps and terms geared to Cloud implementations and not included in OUM
Manage. For example, the “Develop Workplan” task description includes references to a
high-level workplan and a release plan. Although OUM Manage does not use the term
release plan in its equivalent task guidance, the concept of creating an Implementation
Plan (i.e. high-level workplan) and an Iteration Plan (i.e. release plan) is described.
As with other OUM projects, managers should adhere to standard operating procedures
and customer-facing project management practices when executing an OUM Cloud
Application Services project, commensurate with the size and complexity of the
engagement.
During the iterative prototyping sessions, the full set of functionality selected for
implementation is partitioned into smaller subsets of that functionality. Each prototyping
workshop then concentrates on one or more of the smaller segments to refine and
validate that component of the overall solution, while taking into account any
dependencies inherent in other, related components. Each increment is considered in a
logical order until the overall solution has been reviewed, refined and validated.
Approach Overview 2 - 8 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
CHAPTER
T he goal of the Project Start Up phase is to review and agree on the scope of the
project with the client and to provide a clear framework for how the project will be
delivered.
A key output of the Project Start Up phase, the Project Management Plan, documents the
overall approach to the project including what needs to be done, who will do it and how
the project will be governed.
A critical success factor is a strong commitment to perform the project from the client. A
forum should be established to share the project status, risk and issues with the client
and obtain feedback.
• Project plan (including planned releases) is completed and base lined for project
planning and control
• Project is staffed
Project Start Up (PS) Phase 3 - 2 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Work Product Description
Validated Scope
The Validated Scope work product is a
result of validating that the contract
scope accurately reflects the contract
and the expectations of the client.
PS.ACT.RBC Review Bid and Contract Confirmed Bid and Contract Always
PS.ACT.RPAC Review Project Assets with Client Reviewed Project Assets Always
PS.ACT.DSPB Develop Staff Plan and Budget Staff Plan and Budget Always
The Oracle Implementation team and the client have a shared responsibility for the
following tasks in this phase:
Project Start Up (PS) Phase 3 - 4 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
PS.ACT.RBC – Review Bid and Contract (Core)
The Review Bid and Contract should be one of the first things that the project manager
will do after being assigned to the project. This task bridges the gap between the Bid
Preparation process and Project Start Up.
Activity/Task Group
Review Bid and Contract
Work Product
Confirmed Bid and Contract – The Confirmed Bid and Contract is the result of the
project manager reviewing the executed contract and related bid material and committing
to deliver the scope under the terms and budget included in the contract. The following
may be included components:
• Identified Stakeholders
• Reviewed Contract
Prerequisites
You need the following for this task:
Prerequisite Usage
Contract and associated Collective and ancillary documents such as vendor agreements, contract/labor
documentation agreements, system requirements documentation, Board-level directives and
communications, and requests for proposal. These documents assist in the
identification of the business drivers for the project and provide details on the
scope of the project; the modules purchased, the agreements, and so on.
• Review final contract and bid material by accessing internal bid system and/or by
obtaining material generated from the Cloud estimating tool.
• Review MSA/contract for terms and conditions and any exceptions which may
include special billing instructions, expense guidelines, receipt requirements
Project Start Up (PS) Phase 3 - 6 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
PS.ACT.RPAC – Review Project Assets with Client (Core)
As soon as feasible, the project manager will review the contract, project scope, key
project milestones and project approach with the client. This includes making any
necessary updates to the contract and project approach so it can be reflected in the
High-Level Project workplan and Project Management Plan prior to the project kickoff
Activity/Task Group
Review Project Assets with Client
Work Product
Reviewed Project Assets – The Reviewed Project Assets is a result of the contract and
project approach being reviewed with the client to arrive at a common understanding of
the project scope and objectives.
Prerequisites
You need the following for this task:
Prerequisite Usage
Confirmed Bid and Contract The Confirmed Bid and Contract is the result of the project manager reviewing
the executed contract and related bid material and committing to deliver the
scope under the terms and budget included in the contract. The contract,
including terms and conditions, assumptions and obligations should be reviewed
with the client.
Approach
When performing this task, consider the following:
• Set expectations regarding the project approach, planned releases and rollouts
Project Start Up (PS) Phase 3 - 8 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
PS.ACT.VSSOS – Validate Scope and Stakeholders (Core)
Most likely, the project manager will be validating the engagement scope in conjunction
with Reviewing the Bid and Contract and Developing the Workplan. This task should
reflect any detailed scoping items and requirements that may have been uncovered when
the contract assets were reviewed with the client. The goal of Validating the Scope and
Stakeholders is to ensure that all of these artifacts consistently and accurately represent
the contracted scope.
Additionally project scope needs to be validated and specified in detail. This is especially
critical where the scope has been vaguely written into the contract.
While the Review Bid and Contract task is primarily focused on having the project
manager understanding and accept the contracted project scope, this task focuses on
detailing the scope and validating that related project artifacts, particularly the project
workplan, reflect the accepted scope.
During this task, completeness of the stakeholder analysis conducted during the bid
cycle will be verified and refined. Having a complete list of key stakeholders will help to
further define the scope and will be a key input into the communication plan.
Activity/Task Group
Review Scope, Workplan and Budget
Work Product
Validated Scope – The Validated Scope work product is a result of validating that the
contract scope accurately reflects the contract and the expectations of the client.
Prerequisites
You need the following for this task:
Prerequisite Usage
Confirmed Bid and Contract The Confirmed Bid and Contract is the result of the project manager reviewing
the executed contract and related bid material and committing to deliver the
scope under the terms and budget included in the contract. The confirmed Bid
and Contract is referenced in order to validate that all other communication of
scope is in alignment with the contract scope.
Reviewed Project Assets The Reviewed Project Assets is a result of the contract and project approach
being reviewed with the client to arrive at a common understanding of the project
scope and objectives.
• Understand project scope and review generated project plan to make sure it is
consistent (i.e. optional scope items have associated tasks within plan)
Project Start Up (PS) Phase 3 - 10 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
PS.ACT.DW – Develop Workplan (Core)
In this task, the project manager completes the project workplan. The project workplan
denotes all the tasks and activities to be performed by the team in order to deliver on the
project scope and objectives. The project plan may include client activities or
placeholders to represent client activities in which the project is dependent on.
The baseline project workplan should identify planned releases, but may not detail the
tasks for each release at this time.
Activity/Task Group
Review Scope, Workplan and Budget
Work Product
High-Level Project Workplan – The High-Level Project Workplan depicts the high-level
tasks that need to be executed during the course of the project. The high-level workplan
identifies all planned releases, but may not contain the details of the releases at this time.
Prerequisites
You need the following for this task:
Prerequisite Usage
Validated Scope The Validated Scope work product is a result of validating that the contract
scope accurately reflects the contract and the expectations of the client.
Approach
When performing this task, consider the following:
Activity/Task Group
Review Scope, Workplan and Budget
Work Product
Staff Plan and Budget – The Staff Plan and Budget is developed in conjunction with
developing the High-Level Project Workplan. Using the High Level Project Workplan as
input, the project manager develops the staff plan and the project budget.
Prerequisites
You need the following for this task:
Prerequisite Usage
Confirmed Bid and Contract The Confirmed Bid and Contract is the result of the project manager reviewing
the executed contract and related bid material and committing to deliver the
scope under the terms and budget included in the contract. When the staff plan
and budget are created, the original contract budget and financial information
should be referenced and followed.
Validated Scope The Validated Scope work product is a result of validating that the contract
scope accurately reflects the contract and the expectations of the client.
High-Level Project Workplan The High-Level Project Workplan depicts the high-level tasks that need to be
executed during the course of the project. The high-level workplan identifies the
planned releases, but may not contain the details of the releases at this time.
Staffing is based on the tasks included in the project workplan and the project
budget is, in large part, a result of the staffing.
Approach
When performing this task, consider the following:
Project Start Up (PS) Phase 3 - 12 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
• If this is a fixed price contract, the budget is fixed and likely will not change. If
additional services are included (T&M), the project budget may need adjustments
based on assigning actual resources levels to the Project plan
The Project Management Plan (PMP) is not intended to be a large, complex plan.
Rather, it is meant to clearly and concisely explain how the project will be governed,
planned, executed and controlled.
The PMP should provide an overall project management roadmap or framework and may
reference the detailed project management process-level plans. For example, your
Project Workplan, may be managed using a scheduling tool (e.g., MS Project) and
referenced rather than included in the PMP
The PMP is often a conceptual work product meaning that each of its components may
be developed separately with the PMP only providing links or references to the various
plans corresponding to the Manage processes. The content of the PMP should be fit for
purpose -- appropriate for the size and complexity of the engagement.
Activity/Task Group
Create Project Governance, Policies and Supporting Infrastructure
Work Product
Project Management Plan – The Project Management Plan defines the governance
approach to project management by identifying how the critical, strategic areas of the
project will be planned, executed and controlled, and monitored and reported on.
Prerequisites
You need the following for this task:
Prerequisite Usage
Reviewed Project Assets The Reviewed Project Assets is a result of the contract and project approach
being reviewed with the client to arrive at a common understanding of the project
scope and objectives.
Validated Scope The Validated Scope work product is a result of validating that the contract
scope accurately reflects the contract and the expectations of the client.
High-Level Project Workplan The High-Level Project Workplan depicts the high-level tasks that need to be
executed during the course of the project. The high-level workplan identifies the
planned releases, but may not contain the details of the releases at this time.
Staff Plan and Budget The Staff Plan and Budget is developed in conjunction with developing the High-
Level Project Workplan. Using the High Level Project Workplan as input, the
project manager develops the staff plan and the project budget.
Project Start Up (PS) Phase 3 - 14 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Approach
When performing this task, consider the following:
o Change Control
o Financial Management
o Procurement process
Activity/Task Group
Create Project Governance, Policies and Supporting Infrastructure
Work Product
Project Infrastructure – The Project Infrastructure details the system and tools needed
to conduct the project.
Prerequisites
You need the following for this task:
Prerequisite Usage
Project Management Plan The Project Management Plan defines the governance approach to project
management by identifying how the critical, strategic areas of the project will be
planned, executed and controlled, and monitored and reported on.
Develop Staff Plan and Budget The Staff Plan and Budget is developed in conjunction with developing the High-
Level Project Workplan. Using the High Level Project Workplan as input, the
project manager develops the staff plan and the project budget.
Approach
When performing this task, consider the following:
• Establish procedure for procuring goods and contracted Services (if appropriate)
Project Start Up (PS) Phase 3 - 16 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Roles and Responsibilities
The Oracle Implementation team has primary responsibility for this task.
T he goal of the Plan phase is to align the project team with the project’s goals and
objectives, gather setup data, and prepare a detailed plan for the remainder of the
project.
Following confirmation of the project scope and objectives, and the preparation of a high-
level Project Workplan in the Project Start Up Phase, a kickoff meeting is held in the Plan
phase to orient the entire team to the project’s goals, objectives, and protocols to be
followed during the project.
During the Plan phase, a series of workshops are scheduled to gather initial setup
information and review the approach, or approaches, that will be employed to address
required integrations and the loading of legacy data. A detailed plan for the current
release is also prepared and shared with team members.
Plan (A) Phase 4 - 2 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Work Product Description
TR.050 Train Project Team Trained Project Team Project Team training has
been requested as an
additional service.
WM.010 Create Detailed Plan for Current Detailed Release Plan Always
Release
OCM.015 Identify Process Change Process Change Candidate List Cloud Adoption Services
Candidates have been requested as
an additional service.
OCM.035 Create Change Plan Change Enablement Plan Cloud Adoption Services
have been requested as
an additional service.
OCM.065 Provide Stakeholder / End User Stakeholder / End User Analysis Cloud Adoption Services
Analysis Guidance Tools and Techniques have been requested as
an additional service.
Responsibilities
The Oracle Implementation team has primary responsibility for the following tasks in this
phase:
The Oracle Implementation team and the client have a shared responsibility for the
following tasks in this phase:
Plan (A) Phase 4 - 4 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
• STM.050 Conduct Kick-Off Meeting
Work Product
Kick-Off Meeting – The Kick-Off Meeting is conducted to orient the project team and
communicate to them the project objectives and structure.
Activity/Task Group
Prepare Project Team
Prerequisites
You need the following for this task:
Prerequisite Usage
High-Level Project Workplan The High-Level Project Workplan depicts the high-level tasks that need to be
executed during the course of the project. The high-level workplan identifies the
planned releases, but may not contain the details of the releases at this time.
Approach
When performing this task, consider the following:
• Allow each team member to introduce themselves and the role they will play on
the project.
• Capture any issues and concerns that cannot be addressed during the meeting
and establish a plan to respond back to the team.
Plan (A) Phase 4 - 6 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
TR.050 – Train Project Team (Optional)
In this task, you conduct learning events for the project team. The scope of the training
should be determined by the pre-defined project team training developed for the fixed
scope offerings that are in-scope for the project (If available), or the project team training
specified in the contract.
Activity/Task Group
Prepare Project Team
Work Product
Trained Project Team – The Trained Project Team represents all members of the team
who have participated in the learning events intended to give them the knowledge and
skills they need to perform their roles on the team.
Prerequisites
You need the following for this task:
Prerequisite Usage
Contract and associated Collective and ancillary documents such as vendor agreements, contract/labor
documentation agreements, system requirements documentation, Board-level directives and
communications, and requests for proposal. These documents assist in the
identification of the business drivers for the project and provide details on the
scope of the project; the modules purchased, the agreements, and so on.
Approach
When performing this task, consider the following:
• Project team training should cover tools, applications, and all knowledge and skill
areas deemed necessary for the effective functioning of the team.
Activity/Task Group
Release Planning
Work Product
Workshop Schedule – The Workshop Schedule lists the workshops that are planned for
gathering setup information and addressing the integrations and data loads that are in-
scope for the project. It specifies the date, time, duration, objectives, and required
participants for each workshop.
Prerequisites
You need the following for this task:
Prerequisite Usage
High-Level Project Workplan The High-Level Project Workplan depicts the high-level tasks that need to be
executed during the course of the project. The high-level workplan identifies the
planned releases, but may not contain the details of the releases at this time.
Reviewed Business Processes The Reviewed Business Processes identifies the business processes in scope
for the project for which workshops must be scheduled.
Validated Scope The Validated Scope work product is a result of validating that the contract
scope accurately reflects the contract and the expectations of the client.
Approach
When performing this task, consider the following:
• Determine how many workshops will be required for each business process area
and how the work will be divided up across those workshops.
• Identify the client personnel required for each of the planned workshops and
obtain their availability.
• Prepare the schedule and have it reviewed and approved by the client.
Plan (A) Phase 4 - 8 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Roles and Responsibilities
The Oracle Implementation team has primary responsibility for this task.
Activity/Task Group
Release Planning
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
High-Level Project Workplan The High-Level Project Workplan depicts the high-level tasks that need to be
executed during the course of the project. The high-level workplan identifies the
planned releases, but may not contain the details of the releases at this time.
Validated Scope The Validated Scope work product is a result of validating that the contract
scope accurately reflects the contract and the expectations of the client.
Approach
When performing this task, consider the following:
• Have changes been identified during the implementation, which impact the
release plan?
Plan (A) Phase 4 - 10 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Roles and Responsibilities
The Oracle Implementation team has primary responsibility for this task.
Activity/Task Group
Gather Setup Information
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Validated Scope The Validated Scope work product is a result of validating that the contract
scope accurately reflects the contract and the expectations of the client.
Approach
When performing this task, consider the following:
• Use the standard Fusion Applications Process Models as the basis this review.
Plan (A) Phase 4 - 12 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
MC.040.1 – Gather Setup Information (Core)
In this task, you conduct scheduled workshops aimed at collecting input for the setup
questionnaires and wizards. Prior to these interviews, the implementation team should
have received the client documentation related to the procedures and processes within
the project’s scope. These are mainly used to confirm the teams’ understanding of the
client’s processes.
Activity/Task Group
Gather Setup Information
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Reviewed Business Processes The Reviewed Business Processes identifies the business processes in scope
for the project and determines the priority for implementation.
Workshop Schedule The Workshop Schedule lists the workshops that are planned for gathering setup
information and addressing the integrations and data loads that are in-scope for
the project. It specifies the date, time, duration, objectives, and required
participants for each workshop.
Approach
When performing this task, consider the following:
• Have setup questionnaires been forwarded to the client before the workshop?
Plan (A) Phase 4 - 14 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
TA.030 – Conduct Integration Workshop (Core)
In this task, you conduct a workshop to explain the Fusion integration concepts and
define an integration strategy to interface with legacy systems.
Activity/Task Group
Conduct Technical Workshops
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Validated Scope The Validated Scope work product is a result of validating that the contract
scope accurately reflects the contract and the expectations of the client.
Workshop Schedule The Workshop Schedule lists the workshops that are planned for gathering setup
information and addressing the integrations and data loads that are in-scope for
the project. It specifies the date, time, duration, objectives, and required
participants for each workshop.
Approach
When performing this task, consider the following:
• Which integrations are considered in-scope for the fixed scope offerings included
in the project?
• Are there any additional pre-built or custom integrations that have been
requested by the client?
Plan (A) Phase 4 - 16 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
CV.010 – Conduct Data Load Workshop (Core)
In this task, you conduct a workshop to explain the data conversion tools and functions
within Fusion and determine the data conversion options to be used for the data loads in
scope.
Activity/Task Group
Conduct Technical Workshops
Work Product
Data Load Strategy – The Data Load Strategy documents the high-level requirements
for each data load, and outlines the Fusion data load tools and functions, which will be
utilized to satisfy the data load requirements.
Prerequisites
You need the following for this task:
Prerequisite Usage
Validated Scope The Validated Scope work product is a result of validating that the contract
scope accurately reflects the contract and the expectations of the client.
Workshop Schedule The Workshop Schedule lists the workshops that are planned for gathering setup
information and addressing the integrations and data loads that are in-scope for
the project. It specifies the date, time, duration, objectives, and required
participants for each workshop.
Approach
When performing this task, consider the following:
• Which data loads are considered in-scope for the fixed scope offerings included
in the project?
• Are there any additional pre-built or custom data loads that have been requested
by the client?
• Which Fusion data load tools and options are appropriate for the data loads in
scope?
Plan (A) Phase 4 - 18 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
DO.010 – Define Documentation Requirements and Strategy (Optional)
In this task, you outline the overall requirements for creating user documentation and
specify the work products to be produced. You also identify the strategy you will use for
publishing project-specific documentation.
Activity/Task Group
Documentation
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Validated Scope The Validated Scope work product is a result of validating that the contract
scope accurately reflects the contract and the expectations of the client.
Approach
When performing this task, consider the following:
• Which process areas are included in the scope of the project and what priority
has been assigned to those process areas by the client?
• What strategy, tools, or techniques will be employed to develop and deploy the
required user documentation?
Plan (A) Phase 4 - 20 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
OCM.015 – Identify Process Change Candidates (Optional)
In this task, you Identify candidate processes/procedures for change based on the
documentation provided by client, catalog such candidate processes, and communicate
the change impact areas to the client.
Activity/Task Group
Cloud Adoption - Plan
Work Product
Process Change Candidate List – The Process Change Candidate List contains the
client’s current processes or procedures which have been identified as candidates for
change based on the standard functionality supported by the off-the-shelf products in
scope for the project.
Prerequisites
You need the following for this task:
Prerequisite Usage
Validated Scope The Validated Scope work product is a result of validating that the contract
scope accurately reflects the contract and the expectations of the client.
Reviewed Business Processes The Reviewed Business Processes identifies the business processes in scope
for the project and determines the priority for implementation.
Approach
This section is not yet available.
Activity/Task Group
Cloud Adoption - Plan
Work Product
Change Enablement Plan – The Change Enablement Plan outlines a plan of action,
which will enable the client organization to implement and adopt changes to their internal
processes, which are required in order to align those processes with those supported by
the off-the-shelf functionality of the software in scope for the project.
Prerequisites
You need the following for this task:
Prerequisite Usage
Process Change Candidate List The Process Change Candidate List contains the client’s current processes or
procedures which have been identified as candidates for change based on the
standard functionality supported by the off-the-shelf products in scope for the
project.
Approach
This section is not yet available.
Plan (A) Phase 4 - 22 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
OCM.065 – Provide Stakeholder / End User Analysis Guidance (Optional)
In this task, you conduct a change enablement kickoff and orientation workshop and
provide the client change lead with worksheets, sample PowerPoints for analysis output,
and guidance on integration to the overall implementation plan.
Activity/Task Group
Cloud Adoption - Plan
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Validated Scope The Validated Scope work product is a result of validating that the contract
scope accurately reflects the contract and the expectations of the client.
Approach
This section is not yet available.
Activity/Task Group
Executive Checkpoint
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Completed Setup Questionnaires The Completed Setup Questionnaires contain the configuration information for
the functionality that is in-scope for the project. The setup questionnaires are
used to configure the Staging Environment in preparation for the prototyping
workshops in the Prototype phase.
Integration Strategy The Integration Strategy documents the high-level requirements for each
integration point and outlines the Fusion integration concepts which will be
utilized to satisfy the integration requirements.
Data Load Strategy The Data Load Strategy documents the high-level requirements for each data
load and outlines the Fusion data load tools and functions, which will be utilized
to satisfy the data load requirements.
Approach
When performing this task, consider the following:
• Have the key work products for the phase been completed and reviewed?
• Have the objectives set out for the phase been achieved?
Plan (A) Phase 4 - 24 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Roles and Responsibilities
The Oracle Implementation team has primary responsibility for this task.
The Manage Project Execution is made up of many ongoing tasks. An ongoing task is
defined as a task that occurs continuously throughout a project, rather than at a specific
pre-defined time. The ongoing tasks occur as needed and do not include dependencies
among the tasks or with the execution method tasks.
Activity/Task Group
Project Management
Work Product
Managed Project Assets – Reviewed project progress, analyzed variances and updated
management plans and policies.
Prerequisites
You need the following for this task:
Prerequisite Usage
High-Level Project Workplan The High-Level Project Workplan depicts the high-level tasks that need to be
executed during the course of the project. The high-level workplan identifies all
planned releases, but may not contain the details of the releases at this time.
Project Management Plan The Project Management Plan defines the governance approach to project
management by identifying how the critical, strategic areas of the project will be
planned, executed and controlled, and monitored and reported on
Project Infrastructure The Project Infrastructure details the system and tools needed to conduct the
project.
Detailed Release Plan The Detailed Release Plan contains a network of interdependent tasks
representing all work, with staff work assignments and schedules for the current
release.
Plan (A) Phase 4 - 26 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Approach
When performing this task, consider the following:
• Review the key outputs for the phase with client and obtain agreement or
acceptance (for fixed price projects)
• Verify that phase objectives have been met and confirm next steps
Activity/Task Group
Project Management
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
High-Level Project Workplan The High-Level Project Workplan depicts the high-level tasks that need to be
executed during the course of the project. The high-level workplan identifies all
planned releases, but may not contain the details of the releases at this time. If
the implementation is part of a program, then project workplan may include
additional program related task and activities.
Project Management Plan The Project Management Plan defines the governance approach to project
management by identifying how the critical, strategic areas of the project will be
planned, executed and controlled, and monitored and reported on. If the
implementation is part of a program, then the project management plan may
reference how the program is executing, controlling, monitoring and reporting on
the progress of this implementation in the context of the entire program.
Approach
When Program Management is included in the project, it is recommended that you
reference the “Program Management Method (PGM) Handbook” which can be found in
the OUM Method Pack on the OUM Manage Homepage.
Plan (A) Phase 4 - 28 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Roles and Responsibilities
The Oracle Implementation team has primary responsibility for this task.
At the outset of the Prototype phase, the initial setup information, which was gathered
during the Plan phase, is used to configure the Staging Environment. An initial series of
workshops are then conducted to demonstrate the standard functionality (as configured
in the Staging Environment) and collect feedback on additional configurations and
refinements. Any additional configurations identified are prioritized and entered and
reviewed during the subsequent set of Prototype phase workshops.
Following the entry of any setup changes, a second series of prototyping workshops are
conducted to demonstrate and validate the functionality associated with extensible items,
integrations, and data loads. When additional services for pre-built or custom
integrations or data loads are in scope for the project, optional tasks related to data
mapping and preparation of technical specifications may also be executed. Custom
components associated with non-standard reports, data loads or custom integrations are
built and tested, and client legacy data is loaded and validated.
During the Prototype phase, client personnel may be tasked with cleaning and obtaining
legacy data in preparation for loading, as appropriate. The phase then culminates with
an implementation checkpoint to verify that phase objectives have been achieved and
approval to proceed obtained.
Prototype (B) Phase 5 - 2 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Work Product Description
DS.140.1 Prepare Detailed Technical Detailed Technical Specification - Custom reports, additional
Specifications - Fusion Fusion data loads, or custom
integrations are requested
as additional services.
DS.140.2 Prepare Detailed Technical Detailed Technical Specification – Custom reports, additional
Specifications - Client Legacy Client Systems data loads, or custom
Systems integrations are requested
as additional services.
CV.053 Populate Data Load Templates Populated Data Load Templates Always
With Client Data
MC.060.8 Implement Composer Updates Implemented Composer Updates Composer updates are
requested as an
additional service
Prototype (B) Phase 5 - 4 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
ID Task Name Work Product Required When
IM.050.3 Load and Validate Data to Client Validated Data Custom integrations are
Systems requested as an
additional service for your
project, which require
data to be loaded to client
systems.
TE.045 Validate Integration Packages Validated Integration Packages Custom integrations are
requested as additional
services.
OCM.145 Provide Change Impact Change Impact Assessment Cloud Adoption Services
Assessment Approach Approach have been requested as
an additional service for
your project.
Responsibilities
The Oracle Implementation team has primary responsibility for the following tasks in this
phase:
The client has primary responsibility for the following tasks in this phase:
The Oracle Implementation team and the client have a shared responsibility for the
following tasks in this phase:
Prototype (B) Phase 5 - 6 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
• CV.065.1 Load, Reconcile & Validate Data
Activity/Task Group
Prototype Configuration – Iteration 1
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Completed Setup Questionnaires The Completed Setup Questionnaires contain the configuration information for
the functionality that is in-scope for the project. The setup questionnaires are
used to configure the Staging Environment in preparation for the prototyping
workshops in the Prototype phase.
Approach
When performing this task, consider the following:
Prototype (B) Phase 5 - 8 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
TE.020 – Prepare Validation Scripts (Core)
In this task, you prepare demo scripts/test scripts for use in validating the setups, and
related functionality, during the prototyping workshops. If predefined scripts are available
for the functionality in question, update them as necessary instead of preparing new
scripts.
Activity/Task Group
Prototype Configuration – Iteration 1
Work Product
Validation Scripts – The Validation Scripts consist of the set of test scenarios, that each
includes a number of test steps, which will be executed during the configuration
prototyping workshops and end-to-end review.
Prerequisites
You need the following for this task:
Prerequisite Usage
Reviewed Business Processes The Reviewed Business Processes identifies the business processes in scope
for the project and determines the priority for implementation.
Completed Setup Questionnaires The Completed Setup Questionnaires contain the configuration information for
the functionality that is in-scope for the project. The setup questionnaires are
used to configure the Staging Environment in preparation for the prototyping
workshops in the Prototype phase.
Approach
When performing this task, consider the following:
• Collect any predefined demo scripts/test scripts available for the functionality in
question
• Verify that scripts are aligned with setup values contained in the Completed
Setup Questionnaires
Prototype (B) Phase 5 - 10 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
MC.070 – Conduct Workshops and Prototype Configuration (Core)
In this task, you conduct workshops to demonstrate the standard functionality as
configured in the prototype/Staging Environment.
Activity/Task Group
Prototype Configuration – Iteration 1
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Workshop Schedule The Workshop Schedule lists the workshops that are planned for gathering setup
information and addressing the integrations and data loads that are in-scope for
the project. It specifies the date, time, duration, objectives, and required
participants for each workshop.
Validation Scripts The Validation Scripts consist of the set of test scenarios, that each includes a
number of test steps, which will be executed during the configuration prototyping
workshops and end-to-end review.
Approach
When performing this task, consider the following:
• Determine how many iterations are required to prototype all functional areas
included in the project scope.
Prototype (B) Phase 5 - 12 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
MC.040.2 – Capture and Prioritize Additional Configurations (Core)
In this task, you document and prioritize any revised or additional configuration settings
required by the customer, which have been identified during the prototyping sessions.
Activity/Task Group
Prototype Configuration – Iteration 1
Work Product
MoSCoW List – The MoSCoW List is a prioritized list of the high-level requirements valid
for the application system that is being implemented, which contains the revised or
additional configuration requirements identified during the prototyping sessions.
Prerequisites
You need the following for this task:
Prerequisite Usage
Reviewed Prototype The Reviewed Prototype is the result of conducting a series of workshops
intended to demonstrate the standard functionality as configured in the
prototype/Staging Environment.
Approach
When performing this task, consider the following:
• Update the Setup Questionnaires to reflect the changes to the setup values.
Activity/Task Group
Prototype Configuration – Iteration 1
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Completed Setup Questionnaires The Completed Setup Questionnaires contain the configuration information for
the functionality that is in-scope for the project. The setup questionnaires are
used to configure the Staging Environment in preparation for the prototyping
workshops in the Prototype phase.
MoSCoW List The MoSCoW List is a prioritized list of the high-level requirements valid for the
application system that is being implemented, which contains the revised or
additional configuration requirements identified during the prototyping sessions.
Approach
When performing this task, consider the following:
• Does it include the impact of any setup changes in the course of the
implementation?
Prototype (B) Phase 5 - 14 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Roles and Responsibilities
The Oracle Implementation team has primary responsibility for this task.
Activity/Task Group
Prototype Configuration – Iteration 1
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Reviewed Prototype The Reviewed Prototype is the result of conducting a series of workshops
intended to demonstrate the standard functionality as configured in the
prototype/Staging Environment.
Setup Documentation The Setup Documentation defines the detailed setup parameters that have been
proven to support the future business processes.
Approach
When performing this task, consider the following:
• Are there appropriate controls in place regarding who is able to make changes to
the configuration?
Prototype (B) Phase 5 - 16 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Roles and Responsibilities
The Oracle Implementation team has primary responsibility for this task.
Activity/Task Group
Prepare Integration Details
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Integration Strategy The Integration Strategy documents the high-level requirements for each
integration point and outlines the Fusion integration concepts which will be
utilized to satisfy the integration requirements.
Data Load Strategy The Data Load Strategy documents the high-level requirements for each data
load and outlines the Fusion data load tools and functions, which will be utilized
to satisfy the data load requirements.
MoSCoW List The MoSCoW List is a prioritized list of the high-level requirements valid for the
application system that is being implemented, which contains the revised or
additional configuration requirements identified during the prototyping sessions.
Future Process Model The Future Process Model describes the future business process that the
business executes in response to triggering events as a set of one or more
activities.
Approach
When performing this task, consider the following:
Prototype (B) Phase 5 - 18 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
• Provide a technical overview.
Activity/Task Group
Prepare Integration Details
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Integration Strategy The Integration Strategy documents the high-level requirements for each
integration point and outlines the Fusion integration concepts which will be
utilized to satisfy the integration requirements.
Data Load Strategy The Data Load Strategy documents the high-level requirements for each data
load and outlines the Fusion data load tools and functions, which will be utilized
to satisfy the data load requirements.
MoSCoW List The MoSCoW List is a prioritized list of the high-level requirements valid for the
application system that is being implemented, which contains the revised or
additional configuration requirements identified during the prototyping sessions.
Future Process Model The Future Process Model describes the future business process that the
business executes in response to triggering events as a set of one or more
activities.
Prototype (B) Phase 5 - 20 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Approach
When performing this task, consider the following:
Activity/Task Group
Prepare for Data Loads
Work Product
Data Mapping – The Data Mapping defines the key assumptions, mapping between
source and target, and mapping rules and logic that is needed to create the conversions
and interfaces necessary to support the solution. It is intended to provide the developer
with the necessary information for writing accurate conversion, transformation and load
logic.
Prerequisites
You need the following for this task:
Prerequisite Usage
Data Load Strategy The Data Load Strategy documents the high-level requirements for each data
load and outlines the Fusion data load tools and functions, which will be utilized
to satisfy the data load requirements.
Approach
When performing this task, consider the following:
• The Conversion Mapping component provides a table that shows to which table
and column the legacy system data fields map in Oracle.
Prototype (B) Phase 5 - 22 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
CV.053 – Populate Data Load Templates with Client Data (Core)
In this task, you populate the specified data load templates with client data from legacy
systems and prepare the data for loading to the new Oracle system.
Activity/Task Group
Prepare for Data Loads
Work Product
Populated Data Load Templates – The Populated Data Load Templates contain the
client data that’s been obtained from the legacy systems and prepared for loading to the
new Oracle system.
Prerequisites
You need the following for this task:
Prerequisite Usage
Data Load Strategy The Data Load Strategy documents the high-level requirements for each data
load and outlines the Fusion data load tools and functions, which will be utilized
to satisfy the data load requirements.
Data Mapping The Data Mapping defines the key assumptions, mapping between source and
target, and mapping rules and logic that is needed to create the conversions and
interfaces necessary to support the solution. It is intended to provide the
developer with the necessary information for writing accurate conversion,
transformation and load logic.
Approach
When performing this task, consider the following:
• Data should be populated in accordance with the predefined data load templates.
• Data obtained from client source systems should be cleansed prior to loading.
Activity/Task Group
Prototype Configuration – Iteration 2
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Reviewed Prototype The Reviewed Prototype provides results of prototyping conducted in the
Prototype Phase.
MoSCoW List The MoSCoW List contains a high-level, prioritized list of the additional
configurations identified during the prototyping sessions.
Approach
When performing this task, consider the following:
• Identify new or revised configuration settings that have not previously been
applied and prototyped.
• Have additional configurations (beyond those included as part of the fixed scope
offerings in scope) been identified?
• Update the Staging Environment with the new and/or revised configurations.
Prototype (B) Phase 5 - 24 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Roles and Responsibilities
The Oracle Implementation team has primary responsibility for this task.
Activity/Task Group
Prototype Configuration – Iteration 2
Work Product
Validated Configuration – The Validated Configuration verifies that the additional and
revised configuration values have been entered in accordance with the revised setup
documentation.
Prerequisites
You need the following for this task:
Prerequisite Usage
Approach
When performing this task, consider the following:
• Review the updated setup values in the Staging Environment and verify that they
have been made in accordance with the latest version of the setup
documentation.
Prototype (B) Phase 5 - 26 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
MC.050.2 – Document Functional Security (Core)
In this task, you gather role and function information and relate them to the functional
security needed to support the business processes.
Activity/Task Group
Prototype Configuration – Iteration 2
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Reviewed Prototype The Reviewed Prototype provides results of prototyping conducted in the
Prototype Phase.
MoSCoW List The MoSCoW List contains a high-level, prioritized list of the additional
configurations identified during the prototyping sessions.
Approach
When performing this task, consider the following:
Activity/Task Group
Prototype Configuration – Iteration 2
Work Product
Developed Reports – The Developed Reports are BI Publisher and other reports
requested by the client.
Prerequisites
You need the following for this task:
Prerequisite Usage
Reviewed Prototype The Reviewed Prototype provides results of prototyping conducted in the
Prototype Phase.
MoSCoW List The MoSCoW List contains a high-level, prioritized list of the additional
configurations identified during the prototyping sessions.
Approach
When performing this task, consider the following:
Activity/Task Group
Prototype Configuration – Iteration 2
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Validated Configuration The Validated Configuration verifies that the additional and revised configuration
values have been entered in accordance with the revised setup documentation.
Approach
When performing this task, consider the following:
Prototype (B) Phase 5 - 30 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
MC.060.3 – Implement Workflows (Optional)
In this task, you implement Workflows as required, based on the initial round of
configuration prototyping.
Activity/Task Group
Implement Extensible Elements
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Reviewed Prototype The Reviewed Prototype provides results of prototyping conducted in the
Prototype Phase
MoSCoW List The MoSCoW List contains a high-level, prioritized list of the additional
configurations identified during the prototyping sessions.
Approach
When performing this task, consider the following:
Activity/Task Group
Implement Extensible Elements
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Reviewed Prototype The Reviewed Prototype provides results of prototyping conducted in the
Prototype Phase
MoSCoW List The MoSCoW List contains a high-level, prioritized list of the additional
configurations identified during the prototyping sessions.
Approach
When performing this task, consider the following:
Prototype (B) Phase 5 - 32 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
MC.060.5 – Implement FastFormulas (Optional)
In this task, you implement FastFormulas as required, based on the initial round of
configuration prototyping.
Activity/Task Group
Implement Extensible Elements
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Reviewed Prototype The Reviewed Prototype provides results of prototyping conducted in the
Prototype Phase
MoSCoW List The MoSCoW List contains a high-level, prioritized list of the additional
configurations identified during the prototyping sessions.
Approach
This section is not yet available.
Activity/Task Group
Implement Extensible Elements
Work Product
Configured Flexfields – The Configured Flexfields are the Flexfields implemented in the
Staging environment.
Prerequisites
You need the following for this task:
Prerequisite Usage
Reviewed Prototype The Reviewed Prototype provides results of prototyping conducted in the
Prototype Phase
MoSCoW List The MoSCoW List contains a high-level, prioritized list of the additional
configurations identified during the prototyping sessions.
Approach
This section is not yet available.
Prototype (B) Phase 5 - 34 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
MC.060.7 – Implement Localizations (Optional)
In this task, you implement Localizations as required, based on the initial round of
configuration prototyping.
Activity/Task Group
Implement Extensible Elements
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Reviewed Prototype The Reviewed Prototype provides results of prototyping conducted in the
Prototype Phase
MoSCoW List The MoSCoW List contains a high-level, prioritized list of the additional
configurations identified during the prototyping sessions.
Approach
This section is not yet available.
Activity/Task Group
Implement Extensible Elements
Work Product
Composer Updates – The Implemented Composer Updates are the composer updates
implemented in the Staging environment.
Prerequisites
You need the following for this task:
Prerequisite Usage
Reviewed Prototype The Reviewed Prototype provides results of prototyping conducted in the
Prototype Phase
MoSCoW List The MoSCoW List contains a high-level, prioritized list of the additional
configurations identified during the prototyping sessions.
Approach
This section is not yet available.
Prototype (B) Phase 5 - 36 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
MC.065.2 – Validate Setup Changes (Optional)
In this task, you verify that the updated configuration reflects the revised setup
documentation per the changes made following the prototype sessions.
Activity/Task Group
Implement Extensible Elements
Work Product
Validated Configuration – The Validated Configuration verifies that all setup data,
including the additional and revised configuration values, have been entered in
accordance with the revised setup documentation.
Prerequisites
You need the following for this task:
Prerequisite Usage
Approach
When performing this task, consider the following:
• Review the updated setup values in the Staging Environment and verify that they
have been made in accordance with the latest version of the setup
documentation.
Activity/Task Group
Update Business Processes and Test Cases
Work Product
Future Process Model – The Future Process Model describes the future business
process that the business executes in response to triggering events as a set of one or
more activities.
Prerequisites
You need the following for this task:
Prerequisite Usage
Validated Configuration The Validated Configuration verifies that all setup data, including the additional
and revised configuration values, have been entered in accordance with the
updated setup documentation.
MoSCoW List The MoSCoW List is a prioritized list of the high-level requirements valid for the
application system that is being implemented, which has been updated to reflect
the additional configuration requirements identified during the prototyping
sessions.
Approach
When performing this task, consider the following:
Prototype (B) Phase 5 - 38 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
TE.027.1 – Update Validation Cases (Core)
In this task, you revise the Validation Scripts to align them with the final business
processes.
Activity/Task Group
Update Business Processes and Test Cases
Work Product
Updated Validation Cases – The Updated Validation Cases consist of the set of test
scenarios, that each includes a number of test steps, which should be executed during
the end-to-end solution review.
Prerequisites
You need the following for this task:
Prerequisite Usage
Validated Configuration The Validated Configuration verifies that the additional and revised configuration
values have been entered in accordance with the revised setup documentation.
Future Process Model The Future Process Model describes the future business process that the
business executes in response to triggering events as a set of one or more
activities.
Approach
When performing this task, consider the following:
• The scope of testing is described through a number of test types that are
performed during the end-to-end solution review, the test items that should be
tested, and the features that should be tested.
Activity/Task Group
Implement Integration Packages
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Detailed Technical Specifications The Detailed Technical Specification - Fusion pulls together all design elements
- Fusion for a component into a single document so that they can be easily assessed
against each other, against the design guidelines, and against the requirements.
Approach
When performing this task, consider the following:
• Code modules.
Prototype (B) Phase 5 - 40 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Roles and Responsibilities
The Oracle Implementation team has primary responsibility for this task.
Activity/Task Group
Implement Integration Packages
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Detailed Technical Specifications The Detailed Technical Specification – Client Systems pulls together all design
– Client Systems elements for a component into a single document so that they can be easily
assessed against each other, against the design guidelines, and against the
requirements.
Approach
When performing this task, consider the following:
• Code modules.
Prototype (B) Phase 5 - 42 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Roles and Responsibilities
The Oracle Implementation team has primary responsibility for this task.
Activity/Task Group
Implement Integration Packages
Work Product
Validated Data – Client Systems – The Validated Data – Client Systems is data that
has been loaded to the client system via a file or other integration means and validated to
correctly reflect the Fusion data in the format required by the client system.
Prerequisites
You need the following for this task:
Prerequisite Usage
Integration Strategy The Integration Strategy documents the high-level requirements for each
integration point and outlines the Fusion integration concepts which will be
utilized to satisfy the integration requirements
Detailed Technical Specification – The Detailed Technical Specification – Client Systems pulls together all design
Client Systems elements for a component into a single document so that they can be easily
assessed against each other, against the design guidelines, and against the
requirements.
Custom Components – Client The Custom Components – Client Systems consist of the actual program code
Systems for the integrations, data loads and extensions identified in the Detailed
Technical Specifications for client systems.
Approach
This section is not yet available.
Prototype (B) Phase 5 - 44 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Roles and Responsibilities
The client has primary responsibility for this task.
Activity/Task Group
Implement Integration Packages
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Custom Components – Fusion The Custom Components – Fusion consist of the actual program code for the
integrations, data loads and extensions identified in the Detailed Technical
Specifications for Fusion.
Custom Components – Client The Custom Components – Client Systems consist of the actual program code
Systems for the integrations, data loads and extensions identified in the Detailed
Technical Specifications for client systems.
Approach
This section is not yet available.
Prototype (B) Phase 5 - 46 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
CV.065.1 – Load, Reconcile and Validate Data (Core)
In this task, you load client data into the staging environment. This is performed as part of
the second cycle of prototyping performed in the Prototype Phase. Initially, you convert
sufficient data in each information category for test purposes, at the same time making
visible any inconsistencies or inadequacy in the legacy data.
Activity/Task Group
Validate Data Load - Prototype
Work Product
Validated Data – The Validated Data is the client data that has been loaded to the
staging/testing environment via the data load templates or other means and validated to
correctly reflect the legacy data in the format required by the new system.
Prerequisites
You need the following for this task:
Prerequisite Usage
Populated Data Load Templates The populated data load templates provide the extracted client data in the format
required by the new system.
Custom Components Custom components related to custom data loads provide the necessary support
for loading related client data.
Approach
When performing this task, consider the following:
• This task should be iterated until the data load process has been proven.
• Problems with production data are usually invisible until the data load processes
have been run.
• It is assumed that data has been cleansed, but you should look for potential data
issues as part of this process.
Activity/Task Group
Cloud Adoption - Prototype
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Process Change Candidate List The Process Change Candidate List contains the client’s current processes or
procedures which have been identified as candidates for change based on the
standard functionality supported by the off-the-shelf products in scope for the
project.
Stakeholder / End User Analysis The Stakeholder/End User Analysis Tools and Techniques provides the client
Tools and Techniques change lead with the necessary tools and methods necessary to conduct a
Stakeholder/End User Analysis and apply the results to the overall
implementation project.
Approach
When performing this task, consider the following:
Prototype (B) Phase 5 - 48 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Roles and Responsibilities
The Oracle Implementation team has primary responsibility for this task.
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Validated Configuration The Validated Configuration verifies that all setup data, including the additional
and revised configuration values, have been entered in accordance with the
updated setup documentation.
Validated Integration Packages The Validated Integration Packages represent the implemented integrations,
which have been validated to function as expected, in accordance with the
design.
Validated Data The Validated Data is the client data that has been loaded to the staging/testing
environment via the data load templates or other means and validated to
correctly reflect the legacy data in the format required by the new system.
Approach
When performing this task, consider the following:
• Have the key work products for the phase been completed and reviewed?
• Have the objectives set out for the phase been achieved?
Prototype (B) Phase 5 - 50 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
B.PEC.TSK – Manage Project Execution (Core)
In this task, the execution of the project is managed. This includes using the policies,
standards, and procedures delineated in the Project Start Up phase, performing the
necessary reviews and measurements to validate that the project is being executed
according to the project management plan.
The Manage Project Execution is made up of many ongoing tasks. An ongoing task is
defined as a task that occurs continuously throughout a project, rather than at a specific
pre-defined time. The ongoing tasks occur as needed and do not include dependencies
among the tasks or with the execution method tasks.
Activity/Task Group
Project Management
Work Product
Managed Project Assets – Reviewed project progress, analyzed variances and updated
management plans and policies.
Prerequisites
You need the following for this task:
Prerequisite Usage
High-Level Project Workplan The High-Level Project Workplan depicts the high-level tasks that need to be
executed during the course of the project. The high-level workplan identifies all
planned releases, but may not contain the details of the releases at this time.
Project Management Plan The Project Management Plan defines the governance approach to project
management by identifying how the critical, strategic areas of the project will be
planned, executed and controlled, and monitored and reported on
Detailed Release Plan The Detailed Release Plan contains a network of interdependent tasks
representing all work, with staff work assignments and schedules for the current
release.
• Review the key outputs for the phase with client and obtain agreement or
acceptance (for fixed price projects)
• Verify that phase objectives have been met and confirm next steps
Prototype (B) Phase 5 - 52 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
B.PGM.TSK – Program Management (Optional)
Some Cloud application service implementations may be managed as part of a larger
program. When this is the case, then the implementation will need to be managed at
both the project and the program level.
Activity/Task Group
Project Management
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
High-Level Project Workplan The High-Level Project Workplan depicts the high-level tasks that need to be
executed during the course of the project. The high-level workplan identifies all
planned releases, but may not contain the details of the releases at this time. If
the implementation is part of a program, then project workplan may include
additional program related task and activities.
Project Management Plan The Project Management Plan defines the governance approach to project
management by identifying how the critical, strategic areas of the project will be
planned, executed and controlled, and monitored and reported on. If the
implementation is part of a program, then the project management plan may
reference how the program is executing, controlling, monitoring and reporting on
the progress of this implementation in the context of the entire program.
Approach
When Program Management is included in the project, it is recommended that you
reference the “Program Management Method (PGM) Handbook” which can be found in
the OUM Method Pack on the OUM Manage Homepage.
Prototype (B) Phase 5 - 54 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
CHAPTER
T he goal of the Validate phase is to conduct an end-to-end review of the final solution
including any additional configurations, integrations, extensions and client legacy
data.
During the Validate phase, additional configurations required by the client that have not
previously been reviewed, are applied to the Staging Environment and validated An end-
to-end review of the final solution is conducted using established validation cases, which
have been revised to reflect the client’s solution.
During the Validate phase, preparations are made to train a cadre of instructors from the
client’s personnel ranks to teach the end users. One or more train-the-trainer session(s)
is/are conducted to equip those selected to train the end user community in the use of
the new system.
Like the Prototype phase, this phase culminates with an implementation checkpoint to
verify that phase objectives have been achieved and approval to proceed obtained.
Validate (C) Phase 6 - 2 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Work Product Description
OCM.165 Facilitate Change Enablement Change Enablement Plan Cloud Adoption Services
Plan have been requested as
an additional service.
DO.070 Publish User Guide (i.e. Job Aid) User Guide Project-specific
documentation has been
requested as an
additional service
TR.085 Translate Training Material Translated Train-the-Trainer Material Training materials must
be translated into other
languages
Responsibilities
The Oracle Implementation team has primary responsibility for the following tasks in this
phase:
The client has primary responsibility for the following tasks in this phase:
Validate (C) Phase 6 - 4 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
The Oracle Implementation team and the client have a shared responsibility for the
following task in this phase:
Activity/Task Group
Cloud Adoption - Validate
Work Product
Change Enablement Plan – The Change Enablement Plan outlines the plan of action
needed to implement the changes required to achieve organizational readiness with the
new system and addresses the communication of that plan to the entire organization.
Prerequisites
You need the following for this task:
Prerequisite Usage
Change Impact Assessment The Change Impact Assessment Approach equips the client change lead with
Approach the tools and guidance required to conduct an analysis of the process changes
identified in order to make an assessment of the associated impact and risk.
Approach
When performing this task, consider the following:
• Provide access to survey tool for deployment period and deploy survey.
• Assist the Client change lead in preparing a preliminary Communication plan and
matrix (Excel worksheet and our general communication planning framework).
• Provide the Client change lead with an end user Training Plan tool and
artifact (Excel worksheet and training assessment framework).
Validate (C) Phase 6 - 6 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
CV.065.2 – Load, Reconcile and Validate Data (Core)
In this task, you load the extracted client data into the staging/testing environment.
Initially, you convert sufficient data in each information category for test purposes, at the
same time making visible any inconsistencies or inadequacy in the legacy data.
Activity/Task Group
C.TG.DL Validate Data Load - Validate
Work Product
Validated Data – The Validated Data is the client data that has been loaded to the
staging/testing environment via the data load templates or other means and validated to
correctly reflect the legacy data in the format required by the new system.
Prerequisites
You need the following for this task:
Prerequisite Usage
Populated Data Load Templates The populated data load templates provide the extracted client data in the format
required by the new system.
Custom Components Custom components related to custom data loads provide the necessary support
for loading related client data.
Approach
When performing this task, consider the following:
• This task should be iterated until the data load process has been proven.
• Problems with production data are usually invisible until the data load processes
have been run.
• It is assumed that data has been cleansed, but you should look for potential data
issues as part of this process.
Activity/Task Group
C.TG.PR Prepare for End-to-End Review
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Updated MoSCoW List The Updated MoSCoW List contains a high-level, prioritized list of the additional
configurations identified during the prototyping sessions.
Approach
When performing this task, consider the following:
• Identify new or revised configuration settings that have not previously been
applied.
• Update the Staging Environment with the new and/or revised configurations.
Validate (C) Phase 6 - 8 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
MC.050.4 – Update Setup Documentation (Core)
In this task, you update the setup documentation in order to reflect any final changes
made the system configuration.
Activity/Task Group
C.TG.PR Prepare for End-to-End Review
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
MoSCoW List The MoSCoW List contains a high-level, prioritized list of the additional
configurations identified during the prototyping sessions.
Reviewed Business Processes The reviewed Business Processes reflect all of the business processes in scope
as they will be implemented in the Production Environment. The supporting
setup document describes the associated setup parameters.
Validated Configuration The Validated Configuration verifies that the additional and revised configuration
values have been entered in accordance with the revised setup documentation
Approach
When performing this task, consider the following:
• Update any existing setup document with the parameters, user-defined codes,
and other setups that were validated during the latest Prototype session
Activity/Task Group
C.TG.PR Prepare for End-to-End Review
Work Product
Future Process Model – The Future Process Model describes the future business
process that the business executes in response to triggering events as a set of one or
more activities. Following this update of the process models, they should reflect all of the
business processes in scope as they will be implemented in the Production Environment.
Prerequisites
You need the following for this task:
Prerequisite Usage
Updated MoSCoW List The Updated MoSCoW List is a prioritized list of the high-level requirements
valid for the application system that is being implemented, which has been
updated to reflect the additional configuration requirements identified during the
prototyping sessions.
Approach
When performing this task, consider the following:
• Use the process models that were updated in the Prototype phase as a starting
point.
• Update the process models to reflect the processes the client will employ with
the new system, including those related to any additional configurations applied
in the Validate phase.
Validate (C) Phase 6 - 10 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
TE.027.2 – Update Validation Cases (Core)
In this task, you revise validation/test cases to align them with the final business
processes.
Activity/Task Group
C.TG.PR Prepare for End-to-End Review
Work Product
Updated Validation Cases – The Updated Validation Cases consist of the set of test
scenarios, that each includes a number of test steps, which will be executed during the
end-to-end review.
Prerequisites
You need the following for this task:
Prerequisite Usage
Future Process Model The Future Process Model describes the future business process that the
business executes in response to triggering events as a set of one or more
activities. Following this update of the process models, they should reflect all of
the business processes in scope as they will be implemented in the Production
Environment.
Approach
When performing this task, consider the following:
• The scope of the validation is described through a number of test types that are
performed during the end-to-end review, the items that should be validated, and
the features that should be validated.
Activity/Task Group
C.TG.PR Prepare for End-to-End Review
Work Product
Prepared Users – The Prepared Users have been trained on the new system and are
able to conduct the End-to-End Review for their business process area.
Prerequisites
You need the following for this task:
Prerequisite Usage
Validated Configuration The Validated Configuration verifies that the additional and revised configuration
values have been entered in accordance with the revised setup documentation.
Future Process Model The Future Process Model describes the future business process that the
business executes in response to triggering events as a set of one or more
activities. Following this update of the process models, they should reflect all of
the business processes in scope as they will be implemented in the Production
Environment.
Approach
When performing this task, consider the following:
• The training necessary for users to perform their end-to-end review tasks.
• Instructions on how to read a validation scenarios and how to perform the end-to-
end review.
Validate (C) Phase 6 - 12 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
TE.070 – Conduct End-to-End Review (Core)
In this task, you conduct end-to-end review, by executing the validation cases
documented earlier in the project and using the converted client data. It is comparable to
a System Test.
Activity/Task Group
C.TG.ER End-to-End Review
Work Product
End-to-End Review Results – The End-to-End Review Results are the findings of the
end-to-end review of the application system. It should validate that the applications work
in a way that is consistent with what the users expect.
Prerequisites
You need the following for this task:
Prerequisite Usage
Validated Configuration Before the End-to-End Review can start, the configuration of the
Prototype/Testing Environment must be validated.
Validated Data After the data loads have been validated, the data is ready for use in the End-to-
End Review.
Updated Validation Cases The Updated Validation Cases are used when performing the End-to-End
Review.
User Guide Users should follow and validate the User Guide during the End-to-End Review.
Approach
When performing this task, consider the following:
• Has the necessary client data been loaded to the prototype/testing environment
and validated?
Validate (C) Phase 6 - 14 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
DO.070 – Publish User Guide (i.e., Job Aid) (Optional)
In this task, publish a User Guide, or Job Aid, that defines a set of detailed procedures for
using the applications.
Activity/Task Group
C.TG.DO Documentation
Work Product
User Guide – The User Guide describes a business procedure and provides detailed
instructions for using the applications in response to day-to-day business events.
Prerequisites
You need the following for this task:
Prerequisite Usage
Future Process Model The Validated Configuration verifies that the additional and revised configuration
values have been entered in accordance with the revised setup documentation.
Validated Configuration The Completed Setup Questionnaires contain the configuration information for
the functionality that is in-scope for the project.
Approach
When performing this task, consider the following:
• The User Guide introduces the user to the purpose of procedures and then
explains the detailed steps and options needed to perform the business task or
transactions.
• The tone of the documentation should be simple and straightforward, rather than
academic or technical.
• Anticipate questions that the user may ask regarding a procedure, and answer
them. As you document these procedures, compare the current and future
• Write the documentation to the level of the targeted audience. If you are
documenting a technical process, include technical details; if you are
documenting a business process, only include technical details if they are
necessary to convey a concept.
• Use diagrams and charts to explain broad or complex concepts. For example, a
paragraph containing many conditions may be more easily understood when the
information is presented in a table or chart.
Validate (C) Phase 6 - 16 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
DO.075 – Publish Admin Guide (Optional)
In this task, publish an Administrative Guide that describes administrative tasks and
processes specific for the customer’s implementation.
Activity/Task Group
C.TG.DO Documentation
Work Product
Admin Guide – The Admin Guide is focused at customer administrators, and describes
administrative tasks and processes specific to the customer’s implementation. It can
contain for example manual data imports that need to be performed on a regular basis
(e.g. for data migration) or specific checks that need to be performed in the application
when a functional issue occurs on configured functionality. It does not describe standard
application administration tasks.
Prerequisites
You need the following for this task:
Prerequisite Usage
Detailed Technical Specifications The Detailed Technical Specification - Fusion pulls together all design elements
- Fusion for a component into a single document so that they can be easily assessed
against each other, against the design guidelines, and against the requirements.
Detailed Technical Specifications The Detailed Technical Specification – Client Systems pulls together all design
– Client Systems elements for a component into a single document so that they can be easily
assessed against each other, against the design guidelines, and against the
requirements.
Validated Integration Packages The Validated Integration Packages represent the implemented integrations,
which have been validated to function as expected, in accordance with the
design.
Approach
This section is not yet available.
Validate (C) Phase 6 - 18 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
TR.080 – Prepare Training Material (Core)
In this task, you prepare the training materials needed to conduct a Train-the-Trainer
session for the client personnel identified to teach the end user community.
Activity/Task Group
C.TG.TR Training
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
User Guide The User Guide describes a business procedure and provides detailed
instructions for using the applications in response to day-to-day business events.
Future Process Model The Future Process Model describes the business processes that the business
executes in response to triggering events as a set of one or more activities.
Approach
When performing this task, consider the following:
• Tailor the existing training materials to reflect the new procedures derived from
the business process changes and the custom extensions, if appropriate.
Validate (C) Phase 6 - 20 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
TR.085 – Translate Training Material (Optional)
In this task, you translate the training materials needed to conduct a Train-the-Trainer
session for each language that is in scope for the current release.
Activity/Task Group
C.TG.TR Training
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
User Guide The User Guide describes a business procedure and provides detailed
instructions for using the applications in response to day-to-day business events.
Future Process Model The Future Process Model describes the business processes that the business
executes in response to triggering events as a set of one or more activities.
Approach
When performing this task, consider the following:
• Begin with the Train-the-Trainer materials that have already been developed for
the primary language of the project
• Translate the PowerPoint slides, UPK scripts, etc into each required language
based on the prioritization described in the MoSCoW list.
Activity/Task Group
C.TG.TR Training
Work Product
Trained Trainers – The Trained Trainers have learned what they need to succeed in
training the end users. This knowledge covers system literacy, procedural, and business
skills.
Prerequisites
You need the following for this task:
Prerequisite Usage
Train-the-Trainer Training The Train-the-Trainer training material is used to train the designated trainers on
Material the new system and equip them to provide training to the end users.
Approach
When performing this task, consider the following:
• Monitor the pulse and progress of the train-the-trainer events as they unfold, to
make sure that the momentum and quality are maintained.
Activity/Task Group
C.TG.EC Executive Checkpoint
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
End-to-End Review Results The End-to-End Review Results is the application system that has been
reviewed to verify that the applications work in a way that is consistent with what
the users expect.
Validated Configuration The Validated Configuration verifies that the configuration values have been
entered in accordance with the revised setup documentation.
Trained Trainers The Trained Trainers have learned what they need to succeed in training the end
users. This knowledge covers system literacy, procedural, and business skills.
Approach
When performing this task, consider the following:
• Have the key work products for the phase been completed and reviewed?
• Have the objectives set out for the phase been achieved?
Validate (C) Phase 6 - 24 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Roles and Responsibilities
The Oracle Implementation team has primary responsibility for this task.
The Manage Project Execution is made up of many ongoing tasks. An ongoing task is
defined as a task that occurs continuously throughout a project, rather than at a specific
pre-defined time. The ongoing tasks occur as needed and do not include dependencies
among the tasks or with the execution method tasks.
Activity/Task Group
Project Management
Work Product
Managed Project Assets – Reviewed project progress, analyzed variances and updated
management plans and policies.
Prerequisites
You need the following for this task:
Prerequisite Usage
High-Level Project Workplan The High-Level Project Workplan depicts the high-level tasks that need to be
executed during the course of the project. The high-level workplan identifies all
planned releases, but may not contain the details of the releases at this time.
Project Management Plan The Project Management Plan defines the governance approach to project
management by identifying how the critical, strategic areas of the project will be
planned, executed and controlled, and monitored and reported on
Project Infrastructure The Project Infrastructure details the system and tools needed to conduct the
project.
Detailed Release Plan The Detailed Release Plan contains a network of interdependent tasks
representing all work, with staff work assignments and schedules for the current
release.
Validate (C) Phase 6 - 26 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Approach
When performing this task, consider the following:
• Review the key outputs for the phase with client and obtain agreement or
acceptance (for fixed price projects)
• Verify that phase objectives have been met and confirm next steps
Activity/Task Group
Project Management
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
High-Level Project Workplan The High-Level Project Workplan depicts the high-level tasks that need to be
executed during the course of the project. The high-level workplan identifies all
planned releases, but may not contain the details of the releases at this time. If
the implementation is part of a program, then project workplan may include
additional program related task and activities.
Project Management Plan The Project Management Plan defines the governance approach to project
management by identifying how the critical, strategic areas of the project will be
planned, executed and controlled, and monitored and reported on. If the
implementation is part of a program, then the project management plan may
reference how the program is executing, controlling, monitoring and reporting on
the progress of this implementation in the context of the entire program.
Approach
When Program Management is included in the project, it is recommended that you
reference the “Program Management Method (PGM) Handbook” which can be found in
the OUM Method Pack on the OUM Manage Homepage.
Validate (C) Phase 6 - 28 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Roles and Responsibilities
The Oracle Implementation team has primary responsibility for this task.
T he goal of the Transition phase is to deploy the new system into the organization. All
the elements must come together to transition successfully to active system use.
During Transition, the configuration that was validated during the Validate phase is
moved to the Production Environment and client legacy data is loaded, reconciled and
validated.
A final validation review is conducted with users and stakeholders to verify that the
system is ready for use, an assessment is made of operational readiness, and the phase
culminates with the new system being placed into use.
Transition (D) Phase 7 - 2 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
ID Task Name Work Product Required When
Responsibilities
The Oracle Implementation team has primary responsibility for the following tasks in this
phase:
The client has primary responsibility for the following tasks in this phase:
Transition (D) Phase 7 - 4 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
TS.050 – Migrate Configuration to Production (Core)
In this task, you migrate the validated configuration to the Production Environment.
Activity/Task Group
D.TG.PT Prepare for Transition
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Setup Documentation The Setup Documentation defines the detailed setup parameters that have been
validated.
End-to-End Review Results The End-to-End Review Results is the application system that has been
reviewed to verify that the applications work in a way that is consistent with what
the users expect.
Approach
When performing this task, consider the following:
• Use the setup documentation and applicable tools, such as Fusion Functional
Setup Manager, as appropriate to configure the Production Environment with the
validated and reviewed configuration values.
• Review the setups in the Production Environment to ensure that they have been
migrated correctly.
Activity/Task Group
D.TG.PT Prepare for Transition
Work Product
Validated Data – The Validated Data is the client data that has been loaded to the
Production Environment via the data load templates or other means and validated to
correctly reflect the legacy data in the format required by the new system.
Prerequisites
You need the following for this task:
Prerequisite Usage
Populated Data Load Templates The populated data load templates provide the extracted client data in the format
required by the new system.
Custom Components Custom components related to custom data loads provide the necessary support
for loading related client data.
Validated Data The validated data from the Validate phase reflects the successful completion
and validation of uploaded client data from the previous trial data load iterations.
Approach
When performing this task, consider the following:
• During the Transition phase, the initial load of the production database is typically
carried out after the Production Environment is set up.
• A checklist and log of the data loads that were executed on the production
database should be provided and the correctness of the loads should be verified.
Transition (D) Phase 7 - 6 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
TE.120 – Conduct Final Validation Review with Users and Stakeholders (Core)
In this task, you review configured Production Environment with users and stakeholders.
Activity/Task Group
D.TG.FV Final Validation
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Configured Production The Configured Production Environment is complete once the application setups
Environment are applied to the Production Environment.
Validated Data The Validated Data is the client data that has been loaded to the Production
Environment via the data load templates or other means and validated to
correctly reflect the legacy data in the format required by the new system.
Approach
When performing this task, consider the following:
Activity/Task Group
D.TG.TR Training
Work Product
Skilled Users – Users have learned what they need to succeed in their new roles. This
knowledge covers system literacy, procedural, and business skills
Prerequisites
You need the following for this task:
Prerequisite Usage
Trained Trainers The client Trainers will be deliver the training to the end users
Approach
When performing this task, consider the following:
• What specific tasks each group of user will need to perform on the system?
• Pay special attention to how the users daily tasks will change, especially if the
related business process has been updated
• Be sensitive to the fact that some users will welcome the change, whilst other
may initially be resistant to change
• Be sensitive to the fact that some users might find being in a training
environment confronting
Activity/Task Group
D.TG.TS Transition to System Use
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Skilled Users Users will need to understand the processes for logging support calls, and the
expected response time period
Approach
When performing this task, consider the following:
• The establishment of a robust and capable internal and vendor external support
infrastructure is critical to the success of the project
Transition (D) Phase 7 - 10 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
TS.058 – Verify Production and Operational Readiness (Core)
In this task, you verify that all teams and required operational procedures are in place
and are ready to use the system
Activity/Task Group
D.TG.TS Transition to System Use
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Validated Production Environment The Validated Production Environment represents the final review of the
Production Environment by the client to ensure its’ readiness for use. It is
comparable to a User Acceptance, in that it effectively represents the client’s
willingness to proceed with system use.
Approach
When performing this task, consider the following:
• Have key users should gone through the Production Environment setup and data
to confirm that every screen can be accessed and all reports print successfully?
• Have users been trained and are the ready to use the new system in the
execution of their responsibilities?
Activity/Task Group
D.TG.TS Transition to System Use
Work Product
System in Use – The System in Use is a system for which you have verified that all
aspects of the system are operational and active use is achieved.
Prerequisites
You need the following for this task:
Prerequisite Usage
Production and Operational The Production and Operational Readiness Verification consists of checklists
Readiness Verification and optionally, a quality assurance review that allows you to verify production
readiness.
Approach
When performing this task, consider the following:
• The best way to begin using the new system is to control the initial transactions
and entries.
The Manage Project Execution is made up of many ongoing tasks. An ongoing task is
defined as a task that occurs continuously throughout a project, rather than at a specific
pre-defined time. The ongoing tasks occur as needed and do not include dependencies
among the tasks or with the execution method tasks.
Activity/Task Group
Project Management
Work Product
Managed Project Assets – Reviewed project progress, analyzed variances and updated
management plans and policies.
Prerequisites
You need the following for this task:
Prerequisite Usage
High-Level Project Workplan The High-Level Project Workplan depicts the high-level tasks that need to be
executed during the course of the project. The high-level workplan identifies all
planned releases, but may not contain the details of the releases at this time.
Project Management Plan The Project Management Plan defines the governance approach to project
management by identifying how the critical, strategic areas of the project will be
planned, executed and controlled, and monitored and reported on.
Project Infrastructure The Project Infrastructure details the system and tools needed to conduct the
project.
Detailed Release Plan The Detailed Release Plan contains a network of interdependent tasks
representing all work, with staff work assignments and schedules for the current
release.
Transition (D) Phase 7 - 14 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Approach
When performing this task, consider the following:
• Review the key outputs for the phase with client and obtain agreement or
acceptance (for fixed price projects)
• Verify that phase objectives have been met and confirm next steps
Activity/Task Group
Project Management
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
High-Level Project Workplan The High-Level Project Workplan depicts the high-level tasks that need to be
executed during the course of the project. The high-level workplan identifies all
planned releases, but may not contain the details of the releases at this time. If
the implementation is part of a program, then project workplan may include
additional program related task and activities.
Project Management Plan The Project Management Plan defines the governance approach to project
management by identifying how the critical, strategic areas of the project will be
planned, executed and controlled, and monitored and reported on. If the
implementation is part of a program, then the project management plan may
reference how the program is executing, controlling, monitoring and reporting on
the progress of this implementation in the context of the entire program.
Approach
When Program Management is included in the project, it is recommended that you
reference the “Program Management Method (PGM) Handbook” which can be found in
the OUM Method Pack on the OUM Manage Homepage.
Transition (D) Phase 7 - 16 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Roles and Responsibilities
The Oracle Implementation team has primary responsibility for this task.
The Sustain phase marks the last phase of the implementation and the beginning of the
system support cycle. During this phase a workshop is conducted to develop a roadmap
that addresses plans for the next release, ongoing maintenance and sustainability of the
system, and the establishment of organizational structures and processes to provide
adequate governance of the new system.
Updated MoSCoW List and Release Plan The Updated MoSCoW List and
Release Plan provide a high-level,
prioritized list of the requirements that
remain and the plan for the achieving
them.
PS.140 Plan for Next Release Updated MoSCoW List and Release Always
Plan
Sustain (E) Phase 8 - 2 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
ID Task Name Work Product Required When
OCM.265 Perform Change Completion Change Enablement Checklist Cloud Adoption Services
Check Point have been requested as
an additional service.
Responsibilities
The Oracle Implementation team has primary responsibility for the following tasks in this
phase:
The client has primary responsibility for the following tasks in this phase:
The Oracle Implementation team and the client have a shared responsibility for the
following tasks in this phase:
Activity/Task Group
E.TG.SP Stabilization and Planning
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
System in Use The System in Use is the system, which has been placed into active operation.
Approach
When performing this task, consider the following:
• Have users been adequately trained on the use of the new system to perform
their functions?
• Are follow-on releases planned, or are there enhancements that would contribute
to improved operations?
Sustain (E) Phase 8 - 4 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
PS.140 – Plan for Next Release (Core)
In this task, you conduct a workshop with client personnel to review the results of the
recently completed release and plan for next release.
Activity/Task Group
E.TG.SP Stabilization and Planning
Work Product
Updated MoSCoW List and Release Plan – The Updated MoSCoW List and Release
Plan provide a high-level, prioritized list of the requirements that remain and the plan for
the achieving them.
Prerequisites
You need the following for this task:
Prerequisite Usage
Updated MoSCoW List The Updated MoSCoW List provides a high-level, prioritized listing of the
requirements.
Final Release Plan The Final Release Plan contains the finalized listing of the planned releases and
describes the content of each release.
Approach
When performing this task, consider the following:
• Does the revised Release Plan reflect the client’s current priorities?
Activity/Task Group
E.TG.SP Stabilization and Planning
Work Product
Post Go-Live Support – Post Go-Live Support consists of monitoring and responding to
problems and issues throughout the post-production support period, as specified in the
contract.
Prerequisites
You need the following for this task:
Prerequisite Usage
System in Use The System in Use is the system, which has been placed into active operation
Approach
When performing this task, consider the following:
Sustain (E) Phase 8 - 6 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
OCM.265 – Perform Change Completion Check Point (Optional)
In this task, you verify the effectiveness of the change enablement plan, which was put
into action.
Activity/Task Group
Cloud Adoption - Sustain
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
Change Enablement Plan The Change Enablement Plan outlines the plan of action needed to implement
the changes required to achieve organizational readiness with the new system.
Approach
This section is not yet available.
The Manage Project Execution is made up of many ongoing tasks. An ongoing task is
defined as a task that occurs continuously throughout a project, rather than at a specific
pre-defined time. The ongoing tasks occur as needed and do not include dependencies
among the tasks or with the execution method tasks.
Activity/Task Group
E.TG.PM Project Management
Work Product
Managed Project Assets – Reviewed project progress, analyzed variances and updated
management plans and policies.
Prerequisites
You need the following for this task:
Prerequisite Usage
High-Level Project Workplan The High-Level Project Workplan depicts the high-level tasks that need to be
executed during the course of the project. The high-level workplan identifies all
planned releases, but may not contain the details of the releases at this time.
Project Management Plan The Project Management Plan defines the governance approach to project
management by identifying how the critical, strategic areas of the project will be
planned, executed and controlled, and monitored and reported on
Project Infrastructure The Project Infrastructure details the system and tools needed to conduct the
project.
Detailed Release Plan The Detailed Release Plan contains a network of interdependent tasks
representing all work, with staff work assignments and schedules for the current
release.
Sustain (E) Phase 8 - 8 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Approach
When performing this task, consider the following:
• Review the key outputs for the phase with client and obtain agreement or
acceptance (for fixed price projects)
• Verify that phase objectives have been met and confirm next steps
Activity/Task Group
E.TG.PM Project Management
Work Product
Prerequisites
You need the following for this task:
Prerequisite Usage
High-Level Project Workplan The High-Level Project Workplan depicts the high-level tasks that need to be
executed during the course of the project. The high-level workplan identifies all
planned releases, but may not contain the details of the releases at this time. If
the implementation is part of a program, then project workplan may include
additional program related task and activities.
Project Management Plan The Project Management Plan defines the governance approach to project
management by identifying how the critical, strategic areas of the project will be
planned, executed and controlled, and monitored and reported on. If the
implementation is part of a program, then the project management plan may
reference how the program is executing, controlling, monitoring and reporting on
the progress of this implementation in the context of the entire program.
Approach
When Program Management is included in the project, it is recommended that you
reference the “Program Management Method (PGM) Handbook” which can be found in
the OUM Method Pack on the OUM Manage Homepage.
Sustain (E) Phase 8 - 10 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
CHAPTER
T he goal of the Project Closure phase is to close the project from an administrative
and contractual standpoint.
• Project Closure
PS.ACT.CPC Close Processes and Contract Closed Processes and Contract Always
PS.ACT.DLLAP Document Lessons Learned and Lessons Learned and Archived Project Always
Archive Project
Project Closures (PC) Phase 9 - 2 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Responsibilities
The Oracle Implementation team has primary responsibility for the following tasks in this
phase:
• Gain Acceptance
Activity/Task Group
PC.ACT Project Closure
Work Product
Final Acceptance Certificate – The Final Acceptance Certificate verifying that the
contracted project scope was delivered.
Prerequisites
You need the following for this task:
Prerequisite Usage
Contract and associated Collective and ancillary documents such as vendor agreements, contract/labor
documentation agreements, system requirements documentation, Board-level directives and
communications, and requests for proposal. These documents assist in the
identification of the business drivers for the project and provide details on the
scope of the project; the modules purchased, the agreements, and so on. The
contract and associated documentation is validated against to determine if
contractual scope was delivered.
Project Management Plan The Project Management Plan defines the governance approach to project
management by identifying how the critical, strategic areas of the project will be
planned, executed and controlled, and monitored and reported on.
Approach
When performing this task, consider the following:
• If Fixed Price, gain acceptance from the client on the overall project. (Note:
make sure that client acceptance is documented on all outstanding project work
products
Project Closures (PC) Phase 9 - 4 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
PS.ACT.CPC – Close Processes and Contract (Core)
In this task, the contract and the project processes for each of the project management
processes are closed.
Activity/Task Group
PC.ACT Project Closure
Work Product
Closed Processes and Contract – The Closed Processes and Contract closes the
contract and the project processes for each of the project management processes.
Prerequisites
You need the following for this task:
Prerequisite Usage
Contract and associated Collective and ancillary documents such as vendor agreements, contract/labor
documentation agreements, system requirements documentation, Board-level directives and
communications, and requests for proposal. These documents assist in the
identification of the business drivers for the project and provide details on the
scope of the project, the modules purchased, the agreements, and so on. The
contract and associated documentation is validated against to determine if
contractual scope was delivered.
Project Management Plan The Project Management Plan defines the governance approach to project
management by identifying how the critical, strategic areas of the project will be
planned, executed and controlled, and monitored and reported on.
Final Acceptance Certificate The Final Acceptance Certificate verifying that the contracted project scope was
delivered.
Approach
When performing this task, consider the following:
• Release staff
• Close Project Processes (Project Financials, Issue, Risk, and Problem logs, and
other infrastructure process)
• Close Contract
Project Closures (PC) Phase 9 - 6 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
PS.ACT.DLLAP – Document Lessons Learned and Archive Project (Core)
In this task, the project manager compile the lessons learned documented during project
execution and control, and the project is archived.
Activity/Task Group
PC.ACT Project Closure
Work Product
Lessons Learned and Archived Project – The Lessons Learned and Archived Project
is a consolidation of the lessons learned throughout the project and contains the archived
project documentation for reuse and retention.
Prerequisites
You need the following for this task:
Prerequisite Usage
Final Acceptance Certificate The Final Acceptance Certificate verifying that the contracted project scope was
delivered.
Approach
When performing this task, consider the following:
A Plan Phase
Work Breakdown Structure A - 2 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Phase Activity/Task Task ID Task Name Work Product
Group
MC.060.1 Perform Initial Setup Configured Prototype/Staging
Environment
TE.020 Prepare Validation Scripts Validation Scripts
MC.070 Conduct Workshops & Prototype Reviewed Prototype
Configuration
MC.040.2 Capture & Prioritize Additional Updated MoSCoW List
Configurations
MC.050.1 Update Setup Documentation Setup Documentation
MC.063 Conduct Configuration Configuration Familiarization
Familiarization Session Session
(B.TG.ID) Prepare Integration Details
DS.140.1 Prepare Detailed Technical Detailed Technical Specification
Specifications - Fusion - Fusion
DS.140.2 Prepare Detailed Technical Detailed Technical Specification
Specifications - Client Legacy – Client Systems
Systems
(B.TG.DL) Prepare for Data Loads
CV.027.1 Perform Data Mapping Data Mapping
CV.053 Populate Data Load Templates Populated Data Load Templates
With Client Data
(B.TG.PC2) Prototype Configuration - Iteration 2
MC.060.2 Apply Setup Changes Configured Prototype/Staging
Environment
MC.065.1 Validate Setup Changes Validated Configuration
MC.050.2 Document Functional Security Functional Security
Documentation
MC.085 Prepare Reports Developed Reports
MC.050.3 Update Setup Documentation Setup Documentation
(B.TG.EE) Implement Extensible Elements
MC.060.3 Implement Workflows Configured Workflows
MC.060.4 Implement Notifications Configured Notifications
MC.060.5 Implement FastFormulas Configured FastFormulas
MC.060.6 Implement FlexFields Configured Flexfields
MC.060.7 Implement Localizations Implemented Localizations
MC.060.8 Implement Composer Updates Implemented Composer
Updates
MC.065.2 Validate Setup Changes Validated Configuration
(B.TG.BP) Update Business Process Models and Test Cases
RD.011.2 Update Business Processes Future Process Model
TE.027.1 Update Validation Cases Updated Validation Cases
(B.TG.IP) Implement Integration Packages
Validate [C]
(C.TG.CA) Cloud Adoption - Validate
OCM.165 Facilitate Change Enablement Change Enablement Plan
Plan
(C.TG.DL) Validate Data Load - Validate
CV.065.2 Load, Reconcile & Validate Data Validated Data
(C.TG.PR) Prepare for End-to-End Review
MC.060.9 Apply Setup Changes Configured Prototype/Staging
Environment
MC.050.4 Update Setup documentation Setup Documentation
RD.011.3 Update Business Processes Future Process Model
TE.027.2 Update Validation Cases Updated Test Cases
TE.105 Prepare Users for Validation Prepared Users
(C.TG.ER) End-to-End Review
TE.070 Conduct End-to-End Review End-to-End Review Results
(C.TG.DO) Documentation
DO.070 Publish User Guide (i.e., Job User Guide
Aids)
DO.075 Publish Admin Guide Admin Guide
(C.TG.TR) Training
TR.080 Prepare Training Material Train-the-Trainer Training
Material
Work Breakdown Structure A - 4 OUM Cloud Application Services Implementation Approach Solution Delivery Guide
Phase Activity/Task Task ID Task Name Work Product
Group
TR.085 Translate Training Material Translated Train-the-Trainer
Material
TR.095 Conduct Train-the-Trainer Trained Trainers
Workshops
(C.TG.EC) Executive Checkpoint
WM.050.3 Conduct Implementation Implementation Checkpoint
Checkpoint Meeting/Approval to Proceed
(C.TG.PM) Project Management
C.PEC.TSK Manage Project Execution Managed Project Assets
Transition [D]
(D.TG.PT) Prepare for Transition
TS.050 Migrate Configuration to Configured Production
Production Environment
CV.065.3 Load, Reconcile & Validate Data Validated Data
Loads in Production
(D.TG.FV) Final Validation
TE.120 Conduct Final Validation Review Validated Production
with Users & Stakeholders Environment
(D.TG.TR) Training
TR.100 Conduct End-User Training Skilled Users
(D.TG.TS) Transition to System Use
TS.052 Implement Support Support Infrastructure
Infrastructure
TS.058 Verify Production & Operational Production & Operational
Readiness Readiness Verification
TS.060 Begin System Use System in Use
(D.TG.PM) Project Management
D.PEC.TSK Manage Project Execution Managed Project Assets
Sustain [E]
(E.TG.SP) Stabilization and Planning
PS.005 Manage Transition to Steady- Steady-state Operations
state Operations
PS.140 Plan for next Release Updated MoSCoW List and
Release Plan
PS.065 Post Go-Live Support Post Go-Live Support
(E.TG.CA) Cloud Adoption - Sustain
OCM.265 Perform Change Completion Change Enablement Checklist
Check Point
(E.TG.PM) Project Management
E.PEC.TSK Manage Project Execution Managed Project Assets
Project Closure [PC]
Work Breakdown Structure A - 6 OUM Cloud Application Services Implementation Approach Solution Delivery Guide