HARBOUR SPORTS HUB BUILDING EARTHWORKS QUOTATION PHIL ROBINSON EARTHMOVING

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


1 Establishment LS 1 $2,500.00 $2,500.00
2 Erosion and sediment control LS 1 $2,500.00 $2,500.00
3 Surveying LS 1 $2,500.00 $2,500.00
4 Level 1 geotechnical supervision LS 1 $6,000.00 $6,000.00

Remove unsuitable foundation to on site stockpile (to 
5 be measured insitu for payment purposes) m3 399 $20.00 $7,980.00
Import fill to Level 1 standards  (to be measured in situ 
6 for payment purposes) m3 399 $40.00 $15,960.00

7 50mm sand blinding layer under slabs m2 788 $10.00 $7,880.00


Detail excavations (to be measured in situ for payment 
8 purposes) m3 66 $100.00 $6,600.00

9 50mm DGB20 layer under sand layer and external slabs m2 1197 $10.00 $11,970.00

10 Trim to final levels m2 1240 $2.50 $3,100.00


$66,990.00
Exclusions GST $6,699.00
Support of unstable ground TOTAL $73,689.00
Location or relocation of existing services

Page 1 of 1