Professional Documents
Culture Documents
STN-00-Z22-V-SP-0003
Rev. A01– June 2018
Internal Page 2 of 51
Approvals Terms
The Originator of this document shall be responsible for writing of STN. The Originator acts as the technical custodian
O and focal point for questions relating to the content and meaning of an STN and is responsible for any changes to STN.
Verifier. It is the responsibility of TA’s to verify the technical content of this STN. TA’s is involved during STN creation,
V revision and the provision of on-going feedback.
A Approver. Line manager/ Functional Manger responsible to ensure this STN, within their areas of authority.
Consulted List
The following is a list of those individuals who have been consulted prior to approval of this document.
Date Name of Consultee / Job Title Role
June 2018 Alexandr Chugunov/Askhat Alpamyssov – EW Onshore Maintenance Supervisor-Civil IFR
June 2018 Andrew Perry/Adam Scott – EW Onshore Maintenance Superintendent IFR
June 2018 Almat Zakiyev – Civil /structural engineer IFR
June 2018 Arumugam Ramesh - QC Engineer- Inspector IFR
June 2018 Askhat Arenov – Industrial Compliance Team Lead IFR
June 2018 Ayaguz Kartzhanova – Civil/Structural Engineer IFR
June 2018 Badrick John Mark - Inspection Engineer IFR
June 2018 Crispin Grose/GianRomano Andena – Maintenance Execution Manager IFR
June 2018 Dominguez Dan Lavarias - Lead Mechanical Engineer (Static Equipment) IFR
June 2018 Eelco Gehring/Vassiliy Skripko– SU&OD Offshore Maintenance Superintendent IFR
June 2018 Geers Henricus Abraham - Process Engineering Team Lead IFR
June 2018 Kim Alexander - Permitting Coordinator IFR
June 2018 Maximo Vinci –Lead civil Engineer IFR
June 2018 Miras Uap – Civil/Structural Engineer IFR
June 2018 Nurbolat Kuanysh – Quality Control Lead IFR
June 2018 Pavel Girkin – NDD Permitting Coordinator IFR
June 2018 Pennicott Philip - Head of Technical Support IFR
June 2018 Pun Roger Kwok Ching - Lead Corrosion Engineer IFR
June 2018 Puttal Chaleo - Civil & Structural Maintenance Engineer IFR
June 2018 Robert Jenson - Lead Civil/Structural Engineer IFR
June 2018 Samuel Zhong – Corrosion Engineer IFR
June 2018 Saltanat Jumayeva - Engineer of various disciplines IFR
June 2018 Saken Urazgaliyev – Civil/Structural Inspection Engineer IFR
June 2018 Wenman Timothy Frederick - Lead Pipeline Engineer IFR
June 2018 Ahrabian Javid - Engineering Manager IFI
June 2018 Ayagoz Rakhmetulina – Head of Codes & Standards IFI
June 2018 Dehler Glenn Bernd – Engineering Manager - POD IFI
June 2018 Fossen Coen - General Manager (Technical) IFI
June 2018 Gangopadhyaya Shamik - Maintenance Planning Manager IFI
June 2018 Igor Lukashov – Core Systems Manager IFI
June 2018 Irina Ward – Technical Control & Inspection Manager IFI
June 2018 Maccarrone Sebastiano – Head of Quality Control IFI
June 2018 Pavel Pak - Civil Engineering Team Lead IFI
June 2018 Pak Tatyana - Head of Plant Modification IFI
June 2018 Prestini Paolo - Lead Piping Engineer IFI
June 2018 Ronald Nance – Engineering manager (Projects) IFI
June 2018 Timur Nurpeissov – Codes & Standards Coordinator IFI
June 2018 Wong, Kai Chain Samuel - Head of Mechanical Engineering IFI
TABLE OF CONTENTS
PREFACE 6
1. INTRODUCTION 7
1.1 SCOPE 7
1.2 PURPOSE 7
1.3 SPECIFIC TERMS, DEFINITIONS, ACRONYMS AND ABBREVIATIONS 7
1.3.1 General NCOC N.V. Terms & Definitions 7
1.3.2 Specific STN Terms, Acronyms, Abbreviations, and Definitions 7
1.4 REFERENCED DOCUMENTS 8
1.5 ORDER OF PRECEDENCE 9
2. GENERAL REQUIREMENTS 10
2.1 ROK REQUIREMENTS 10
2.2 QUALIFICATION OF PERSONNEL 10
3. TECHNCIAL REQUIREMENTS 10
3.1 TECHNICAL DOCUMENTATION 10
3.2 GENRAL 11
3.3 OPERATING ENVIRONMENTS (ATMOSPHERIC-CORROSIVITY CATEGORY) 12
3.4 CRITERIA FOR PAINT SYSTEM SELECTION 12
3.5 SURFACES NOT REQUIRING COATING 13
3.6 SUPPLIER’S REPRESENTATIVE 13
3.7 AUDITS 13
3.8 COATING MATERIALS REQUIREMENT 13
3.8.1 General 13
3.8.2 Zinc silicate 14
3.8.3 Zinc rich primer 14
3.8.4 Epoxy-acrylic or urethane-acrylic topcoats 14
3.8.5 Pure or modified epoxy 15
3.8.6 Epoxy Mastic 15
3.8.7 Thermally sprayed Aluminium 15
3.8.8 Hot Dip Galvanizing 15
4. SURFACE PREPARATION 15
4.1 PRIMARY SURFACE PREPARATION 15
4.2 SECONDARY SURFACE PREPARATION 15
4.2.1 General 15
4.2.2 Steel and weld imperfection 16
4.2.3 Pre-cleaning of surfaces 16
PREFACE
NCOC N.V. Company Technical Standards (STNs) are developed for mandatory internal use in regards to
technical work describing specifications, common terminology and specific criteria reflecting essential
project requirements to comply with RoK regulations (legislative) requirements.
The objective of the STNs is to establish fit-for-purpose design and engineering requirements, based on
experience and good engineering practices acquired by NCOC N.V. personnel during their involvement with
the design, construction, operation and maintenance of NCOC N.V. assets as well as the experience of co-
venture companies. Where appropriate STNs are based on, or reference is made to, International,
Regional, National and Industry Standards.
This content of this STN shall be reviewed, updated / revised (as required), and re-issued no later than 5
years from the last Revision Date.
Contractors during their operations shall determine by careful scrutiny and define a possibility of referenced
standards application, including HSE, economic, and legal aspects. In all cases, the Contractor shall inform
the Company of any deviation from the requirements of referenced standard which is considered to be
necessary in order to comply with new or revised RoK regulations and all other cases.
Subject to any particular terms and conditions as may be set forth in specific agreements with users, NCOC
N.V. disclaims any liability of whatsoever nature for any damage (including injury or death) suffered by any
company or person whomsoever as a result of or in connection with the use, application or implementation
of any STN, combination of STN or any part thereof, even if it is wholly or partly caused by negligence on
the part of NCOC N.V. The benefit of this disclaimer shall inure in all respects to NCOC N.V. and/or any
company affiliated to the companies that may issue STN or require the use of STN.
Without prejudice to any specific terms in respect of confidentiality under relevant contractual
arrangements, STN shall not, without the prior written consent of NCOC N.V., be disclosed by users to any
company or person whomsoever and the STN shall be used exclusively for the purpose for which they have
been provided to the user. They shall be returned after use, including any copies, which shall only be made
by users with the express prior written consent of NCOC N.V.
The copyright of STN vests in NCOC N.V. Users shall arrange for STN to be held in safe custody and
NCOC N.V. may at any time require information satisfactory to them in order to ascertain how users
implement this requirement.
This STN is developed in accordance with NCOC N.V. Technical Standards Management process.
Comments to this STN should be sent to C&S Group at Codes&StandardsNV@ncoc.kz mail box.
1. INTRODUCTION
1.1 SCOPE
This specification covers the minimum technical requirements for materials, surface preparation, application
and inspection to be used for all external coating of equipment, steel structures, piping, tanks, etc. on the
NCOC N.V. new assets (Onshore/Offshore).
1.2 PURPOSE
The purpose of this document is to cover the minimum technical requirements for surface preparation,
application, inspection and materials to be used for all external coating of equipment, steel structures, tanks
and piping at offshore and onshore .
Exclusions from the scope of this specification and covered by alternative specifications are as given below:
Fireproofing, however surface preparation and application of coating(primer) required beneath the
PFP included in this specification;
Thermal and Acoustic Insulation;
Internal lining of pressure vessels and storage tanks;
Internal coating of barge ballast tanks and other internal spaces within the hull;
Coating of Buried Pipe-work;
Coating of Buried Pipelines.
Contractor package equipment which will be delivered to the jobsite coated with a shop applied system
shall be coated in accordance with this Specification. Use of other painting systems shall require prior
approval from Company.
The Contractor is the party who has entered into a written agreement with Company
to carry out all or part of the design, engineering, procurement, construction,
Contractor
commissioning and/or management of a project, operation or maintenance of a
facility.
RoK Republic of Kazakhstan
Shall The word shall is used to indicate that a provision is mandatory
Surface Treatment
GOST CIS State Standards
ISO International Organisation for Standardisation
MDFT Minimum Dry Film Thickness
MIO Micaceous Iron Oxide
MSDS Material Safety Data Sheets published by Paint Manufacturer
NACE NACE International (former National Association of Corrosion Engineers)
NAMAS National Accreditation of Measuring and Sampling
NDFT Nominal Dry Film Thickness is the dry film thickness specified for each coat or for the
complete paint system
NORSOK Norwegian Industry Standards (Petroleum)
PDS Product Data Sheet
PFP Passive Fire Protection
QCP Quality Control Plan
RAL Colour definition according to RAL standard of Institute fϋr Gϋtesicherung und
Kennzeichnung e.V.
SSPC The Society for Protective Coatings
ST RK RoK State Standard
TDFT Total Dry Film Thickness
TSA Thermally Sprayed Aluminium
VOC Volatile Organic Compound
WFT Wet Film Thickness
Field measurement of surface profile of abrasive blast cleaning steel surfaces using a
42 NACE SP0287 replica tape.
NACE No. 12/AWS Specification for the application of thermal spray coatings (metalizing) of aluminium,
43
C2.23M/SSPC-CS 23.00 zinc, and their alloys and composites for the corrosion protection of steel
44 NORSOK M-501 Surface preparation & protective coating
45 RAL 840 HR Deutschen Normen Auschuss.
46 SSPC-SP 1 Solvent cleaning.
Any interpretation of precedence, unresolved conflicts or discrepancies between the requirements defined
in this NCOC Technical Standard and other applicable Codes, Standards, Laws, Regulations or Project
Specific Documents shall be advised to Company and addressed in writing by use of the established NCOC
N.V. Clarification Procedure.
In the event that a requirement defined by this STN is considered fit-for-purpose by Company but is
identified as non-compliant with RoK National and/or Local Regulations by a recognized Kazakhstan
authority (e.g. GOSP Entity, RoK Design Institute, etc.), the RoK requirement shall be challenged. If the
challenge is unsuccessful, the STN requirement shall be modified (as required) to ensure that all safety,
technical, and RoK certification requirements are satisfied.
2. GENERAL REQUIREMENTS
3. TECHNCIAL REQUIREMENTS
3.2 GENRAL
It is Contractor’s responsibility to purchase, supply, apply and inspect coatings in accordance with the
requirements given in this specification. Based on the requirements of this specification Contractor shall
prepare a “Work Procedure” in which methods concerning each work and activity must be described in
detail.
The approved procedures shall be followed for all work of which Contractor is responsible.
The detailed procedures shall include, but not necessarily be limited to the following:
Method and equipment for surface preparation;
Method and equipment for coating application;
Coating materials data (Supplier’s product data sheets and application notes);
Ranges of temperature and relative humidity control methods for surface preparation and coating work;
Time restrictions between surface preparation, first coat and subsequent coats;
Number of coats and minimum total dry film thickness;
Procedure for repair of damaged coating;
Methods of inspection and testing;
Acceptance criteria for each inspection and testing;
Frequency of monitoring, inspection and testing;
Surface preparation and coating record sheets, ref. ANNEX D;
Finish colours.
Unless specifically excluded in the contract, Contractor scope of supply shall include the provision of all
facilities, equipment consumables, labour and documentation necessary to complete the work in
accordance with the requirements detailed herein. Skid-mounted assemblies and packaged equipment,
and all major items such as vessels and pumps etc. will normally be delivered in the fully coated condition.
Contractor shall carry out any necessary repairs to these coatings in addition to providing coating systems
on items within Contractor’s own scope.
During preparation and coating, Contractor shall be responsible for the protection of all structure and
equipment surfaces from mechanical damage or coating over-spray and droppings.
The coating systems listed in ANNEX A of this specification shall be applied. The specific coating products
and the Paint Supplier shall require approval of Company. Only Suppliers with a proven track record of
supply of equivalent products to the offshore/onshore petrochemical industry over at least 10 years, with
quality systems certified to ISO 9002 [Ref.33], and with experienced locally available technical
representatives will be acceptable. The Paint Supplier shall be able to provide supporting data from
exposure tests and/or cyclic weathering testing to confirm the suitability of the materials proposed for the
operating and prevailing environmental conditions.
The final colour schedule for equipment, piping and structures, and the identification marking of piping, shall
be in accordance with ANNEX B and C of this Specification.
3.7 AUDITS
Company reserves the right to conduct quality, safety or environmental audits at the coating work place
prior to or during the work.
Coating materials shall be stored and used in a manner that assures that products are used within their
storage limits (shelf-life), and those stored first are the first used.
The material shall be delivered to the site, or Contractor’s premises, addressed for the job, in the original
containers with labels intact and seals unbroken.
Notice shall be taken at all times of the Supplier’s instruction in respect of storage, shelf life, mixing and
thinning, as well as method of application and recommended time limits between coats.
All coating materials shall be supplied to the work site in their original unopened and clearly identified
containers, bearing readable labels of the coating Supplier and clearly reporting the following information:
a) Commercial name of the coating material,
b) Name of the Supplier,
c) Colour with RAL code,
d) Batch number of each components (Part A – Part B),
e) Date of manufacture,
f) Date of expiry,
Paint shall not be thinned except as recommended specifically by the Supplier and only the thinners or
reducers so recommended shall be used. Coating materials which have gelled or otherwise deteriorated
during storage shall not be used.
Partial mixing of multi component (part) paints shall not be done.
Mixed paints shall be used with in their “Pot Life” with respect to the ambient temperature as mentioned in
the material TDS, Contractor’s Coating Inspector/Supervisor shall ensure the same
Any coating system that will be used in combination with cathodic protection shall possess excellent
cathodic disbondment properties. All such coating systems shall be tested in accordance with ASTM G8
[Ref.9]. The extent of disbondment at any point from the periphery of the intended holiday shall not exceed
10mm (8 mm for Coating system 9 & 10) after 28 days at ambient temperature. If the coating system will
be subject to elevated temperatures the coating system shall be tested in accordance with
ASTM G42 [Ref. 10] at the maximum operating temperature. The acceptable criteria shall be as per the
ambient temperature test.
Zinc silicate primers and zinc rich epoxy primers shall not be used in combination with cathodic protection.
Zinc coatings shall not be used for insulation services particularly for the operation temperature range
50-90°C; this is applicable also for the surfaces to be covered with removable PFP materials.
3.8.2 Zinc silicate
Zinc silicate primers shall always be mixed in a mechanically agitated pot which shall be kept not lower than
the spray gun at all times. All coating materials shall be premixed by mechanical agitators for a sufficient
time to thoroughly mix pigment and vehicle and bring material to a uniform consistency. Where pigment
separation readily occurs, provision shall be made for continuous mixing during application.
Zinc silicate primer shall be based on two pack inorganic or ethyl silicate media and shall contain not less
than 85% metallic zinc by weight in the dry film.
3.8.3 Zinc rich primer
Zinc rich primers shall be based on two pack epoxy media, containing minimum 90% metallic zinc by weight
in the dry film.
3.8.4 Epoxy-acrylic or urethane-acrylic topcoats
Epoxy-acrylic or urethane-acrylic topcoats shall be two-pack products formulated to provide either high
gloss or sheen finish. They shall be suitable for recoating after extended periods of exposure to marine
conditions without requiring surface roughening. The specified thickness shall be capable of fully
obliterating the selected intermediate build coat colour.
4. SURFACE PREPARATION
the paint system the grade of secondary surface preparation are specified for the appropriate coating
system in ANNEX A.
If the surface has been exposed to salt laden atmosphere these shall be removed by high pressure washing
with clean, fresh water prior to blasting or mechanical cleaning. Contractor shall be required to demonstrate
by surface testing that the salt level is not detrimental to the applied coating, see Table 1, item 4.11.
Contractor shall be responsible, for adequately protecting all surfaces, structures and equipment’s that
should not be abrasive blasted, as required in section 4.4 of this Specification.
4.2.2 Steel and weld imperfection
Welding shots, drops and spatters, pores in welding seams, lamination defects, edges, flame cuts,
fragments and dents or any other foreign material have to be considered imperfections and therefore shall
be removed before any surface preparation.
The steel imperfections detected before, during or after surface preparation shall be removed with suitable
power tools according to the requirements of standard ISO 8501-3 [Ref.22] as follows:
Grade P3: for all surfaces intended to be permanent or intermittent immersed. Spot and discontinuous
welds shall be not permitted on these surfaces. Edges from flame or mechanical knife cutting shall be
rounded to a radius of 2 mm.
Grade P2: for all surfaces exposed to environment, voids and cofferdams, sealed compartments. Spot
and discontinuous welds shall be not permitted on these surfaces. Edges from flame or mechanical
knife cutting shall be chamfered and smoothed.
Grade P1: for all other surfaces.
The removal of welding defects and/or steel imperfection shall not have negative impact on the integrity of
the weld seams and of the steel material. In particular the minimum design thickness of the steel materials
shall not be compromised. In case of the removal of weld imperfections and a re-welding operation are
needed, the applicable fabrication specification shall be followed.
4.2.3 Pre-cleaning of surfaces
Prior to any surface preparation (abrasive blasting, power tooling, water-jetting, etc.), any oil, grease,
welding fumes, and other fatty materials, shall be removed by appropriate solvents in accordance with
standard SSPC-SP-1 Solvent Cleaning [Ref.46].
Petroleum, kerosene, diesel oil or other fatty solvents shall not be used.
All bolt-holes shall be solvent cleaned prior to abrasive blasting.
No acid washes or other cleaning solutions or solvents shall be used on steel surfaces after they are
abrasive blasted. This includes inhibitive washes intended to prevent rusting.
All welding areas and appurtenances shall be given special attention for removal of welding flux in crevices.
When electrodes are used with basic coating or shielding, the welded area has to be free from alkaline
residues by rinsing with warm water prior to blasting.
After abrasive blasting or power tool cleaning and prior to coat, all surfaces shall be examined for traces or
smudges of oil or grease. If any exist, they shall be removed by solvent washing and the area re-cleaned as
originally provided.
All metal surfaces to be coated which do not require abrasive blasting or power tool cleaning shall be
thoroughly cleaned and/or degreased with a high-pressure water or steam cleaning unit to remove all mud,
oil, grease, or other foreign matter.
The final appearance shall be checked and conform to the visual references reported in the standard ISO
8501-1 [Ref.21].
After abrasive blasting, all metal shall be free of rust, grease, dirt, water soluble salts, corrosion products,
oxides, paint and any other foreign matter according to the specified standard requirements.
Abrasive type and size shall be selected in order to assure the profile and roughness of substrate reported
in the coating system sheets of ANNEX A and the surface profiles shall be continuously checked against
surface comparators in accordance with standard ISO 8503-1 [Ref.27] The surface/profile roughness shall
be measured, at the frequency given in Table 1, item 4.9, according to standard NACE SP0287 [Ref.42].
Blast cleaning shall not be done in areas close to coating operations and/or wet coated surfaces in order to
prevent dust or grit contamination.
No acid or inhibitor solutions shall be used on steel surfaces after they have been blast cleaned.
4.3.2 Equipment for Abrasive Blast Cleaning
The compressed air supply used for blast cleaning shall be free from water and oil.
Adequate separators and traps shall be provided and these shall be kept emptied of water and oil.
Accumulations of water and oil shall be removed from the air receiver by regular purging. Control of the
compressed air cleanliness shall be done according to standard ASTM D-4285 [Ref.6].
In no circumstances compressed air temperature shall be more than 100°C and pressure lower than 650
kPa measured at nozzle.
4.3.3 Abrasives
All abrasive materials used for blast cleaning shall be free from oil, grease, or moisture and shall be tested
for water-soluble slats content. Soluble salt content of abrasives shall not exceed 300 µS/cm when tested
according ASTM D4940 [Ref.7] and chloride content of 25 ppm. Non-metallic abrasives shall meet the
requirements of std. ISO 11126 Parts 1, 3-8 [Ref.36]. Tests and controls shall be done according to
standard ISO 11127 Parts 1-7 [Ref.37].
Metallic abrasives shall meet the requirements of standard ISO 11124 Parts 1 - 4 [Ref.34]. Tests and
controls shall be done according to standard ISO 11125 Parts 1 - 7 [Ref.35].
Abrasives based on metallic slag shall not contain any free metals.
Contractor shall have available for review by Company full details of the proposed abrasive. Only non-
metallic abrasives shall be used for stainless steel and other noble metallic surfaces.
Recycling of abrasives shall require Company approval.
For safety and health reason in no circumstances sand or silica producing abrasives shall be used.
5. PAINT APPLICATION
5.1 GENERAL
Coating application shall be performed in accordance with the coating systems sheets of ANNEX A and the
recommendation reported in the relevant PDS published by the Paint Supplier. All application procedures
and equipment shall be available for review by the Company.
The specified primer coating/first coat shall be applied to the specified grade of prepared metal surface as
soon as practicable after completion of blast cleaning (or other approved preparation) of that area. In no
case shall the coating be applied to cleaned surfaces showing evidence of flash rusting or contamination
(including condensation). Blast cleaned surfaces shall be coated within a maximum of 4 hours after blast
cleaning of carbon steel and within 1 hour after sweep blasting of stainless steel.
Sequential coats shall be in contrasting colours so that each stage of the work can be readily identified and
their film thickness determined, unless otherwise approved by Company.
All paints in any one particular paint system, whether shop or site applied, shall originate from a single
Supplier. Use of different Supplier materials in one paint system shall not be allowed. Repair material shall
be the same material as used for original application unless otherwise recommended by the coating
Supplier.
All coating materials shall be thoroughly mixed and stirred with a power mixer for a time sufficient to
thoroughly remix the pigments and vehicles. Sufficient continuous agitation to maintain good mixing shall be
applied until the product is used.
Only thinners as specified by Paint Supplier shall be used. Mixing and thinning directions as recommended
by paint Supplier shall be followed.
If a coating requires a catalyst the pot life shall not be exceeded. When the pot life limit is reached, the
spray pot or container must be emptied, the material discarded, equipment cleaned and new material
catalysed.
Coatings containing heavy or metallic pigments that have a tendency to settle must be kept in suspension in
the pressure pot by a mechanical agitator.
All parts or spaces not specifically mentioned or covered by this specification shall be cleaned and painted
to conform to the surroundings or to comparable spaces.
Each coat in the system shall dry for a time period within the limits prescribed by paint Supplier before next
coat is applied. During drying as well as during application, there must be strict adherence to paint
Supplier's recommendations regarding temperature, humidity adequate and efficient ventilation (if the work
area is enclosed) to ensure that all coatings are properly dried and cured. In the event of specified
maximum recoating intervals being exceeded, or for the application of additional coats to existing
weathered coatings, Company shall be informed and the Supplier’s recommendations for surface
preparation shall be fully described. This may involve sweep blasting and/ or water or solvent washing
before top coating or such other measure as approved by the Company.
Zinc silicate and zinc rich epoxy primers shall be tie-coated or over coated within a maximum of seven (7)
days unless specific approval has been given by the Company to extend this period.
Spray method including overlap, gun adjustment and direction of spray shall be in accordance with the paint
Supplier’s recommendations. As general rule the spray gun shall always be held at right angle to the
surface and shall be held no closer than 450 mm nor more than 600 mm from surfaces.
Coatings shall be applied in a uniform manner to the specified film thickness without runs, sags or other
blemishes that, if any, shall be brushed out immediately or the coating removed and the surfaces re-
sprayed.
Before or after spraying each coat of a paint system, all areas as corners, edges, bolts, nuts and welds,
small brackets etc. shall be stripe coated by brush to ensure that these areas have at least the minimum
specified film thickness. Brushes used shall be of a type and quality to permit efficient application and of
good quality.
The roller application shall be discouraged and shall be subject to the specific approval of the Company.
In no circumstances the use of roller shall be accepted to apply primer/first coat. The roller may be used,
subject to Company approval, only for top-coat application when the required thickness is less than 40/50
µm.
5.5 SHOP-PRIMERS
A Shop-primer (or pre-fabrication primers) may be applied to prepared metal surfaces to facilitate shop or
site handling procedures. Such primers shall in no way replace the function or film thickness of any part of
the specified coating system. Overcoating of any type of shop-primer shall not be permitted by the
Company. These primers shall be removed by blast cleaning prior to application of specified primer/first
coat. Sweep blasting of inorganic zinc shop primers may be allowed where Contractor can demonstrate to
Company satisfaction, by submission of supporting test data based on long term cyclic testing, that there is
no reduction in system adhesion or performance. Contractor shall also demonstrate that sufficient controls
are in place to ensure adequate cleanliness and condition of the aged primer before overcoating.
In all cases, all areas of localised breakdown, and all weld areas or damaged areas shall be cleaned to the
full specified standard.
In areas where cathodic protection will be applied, the full coating system including the shop-primer shall be
tested for cathodic disbondment in accordance with ASTM G8/ASTM G42 [Ref.9/10] depending on
temperature, ref. section 3.8.1
The measurement of DFT, including calibration and acceptance criteria, shall be performed according to
standard ISO 19840 [Ref.40].
The acceptance/rejection criteria shall be as follows:
The DFT of any coat shall not be greater than 40% above nor 10% below the nominal value specified. The
exception from these criteria is for Thermally Sprayed Aluminium (TSA) where the minimum overall
thickness shall be 200μm. The DFT shall be measured in accordance with ISO 19840 [Ref.40].
The minimum dry film thickness (MDFT) is the acceptance thickness for the total applied coating system,
based on a 95% probability of this value being exceeded by any individual measurement. In practice, this
requires statistical records to be maintained of thickness measurements.
6. REPAIRS
6.1 GENERAL
Contractor shall repair all coating defects and damages that will occur during paintworks execution.
Repair of defective areas shall be accomplished in the same manner as the original coating in regard to
surface preparation prior to recoating, unless alternative and equivalent methods are defined within this
specification, or agreed by the Company.
Any repair shall be performed according to the instruction reported in the Product Technical Data Sheet
published by the paint Supplier; if no instructions are reported on the matter the criteria listed below shall be
adopted.
Repair materials shall be as per paint Supplier recommendations.
All damages occurred to previous coats shall be repaired before application of the next one and before the
final acceptance of the Company.
Coating which have aged to the point where further application may give rise to intercoat adhesion
problems, shall be sweep blasted after cleaning prior to further coating. Approval for this work shall be
obtained from the Company.
Coating repair of the vendor supplied items at site shall be done as per vendor’s repair procedures and by
the use of vendor recommended coating materials (i.e. material same as original application). Use of
alternative materials shall require Company, coating Supplier and vendor approval
6.8 CLEAN UP
After coating and inspection have been completed, all scaffolding, equipment, surplus materials, spent
abrasive, empty paint containers and trash resulting from coating works, shall be collected and disposed.
Contactor shall provide the disposal of such materials, in accordance with local rules.
8.1 GENERAL
Contractor shall be responsible for all inspection and quality control functions necessary to achieve
standard coating in accordance with this specification.
Before the beginning of the works a pre-job meeting shall be held with the attendance of representatives of
all involved parties (Company, Contractor, Coating Supplier, Sub-Contractors). The purpose of the meeting
is to clarify and agree the production procedures, check and inspections program, report forms and any
other necessary requirements to achieve the correct job execution.
All testing and inspection equipment shall be kept accurately calibrated at all times and shall be covered by
current calibration certificates issued by the equipment Supplier or a test laboratory accredited by NAMAS
or equivalent for conducting such work.
In addition to the above, DFT gauge and holiday test instrument shall be calibrated at site at least one per
shift by the use of calibrated shims and reference volt meter respectively.
It is Contractor’s responsibility to ensure that monitoring and testing work is carried out to show that the
coatings comply with this specification. Company reserves the right to carry out any additional tests at
random to ensure compliance and the Contractor shall have suitable calibrated test equipment available for
Company use.
The Company inspector shall have the right to inspect at all times any tools, instruments, materials, staging
or equipment used or to be used in the performance of the coating application. Contractor shall make all
parts of the work accessible for these inspections.
All personnel and paint products applied under Passive Fire Protection (fireproofing) shall be approved by
the fireproofing material Supplier and the Company
8.2 INSPECTIONS
All steps of the coating work including (repairs and touch-ups) shall be tested and inspected. Tests and
inspection shall be performed jointly by Company, Contractor & paint Supplier representatives.
During the coating works execution and progress the inspections and tests listed in Table 1 shall be
performed. The frequency, method, and acceptance criteria listed in Table 1 shall be considered minimum
requirements and be subject to a formal agreement during the pre-job meeting.
In any case all inspections and tests, listed in Table1 shall be integrated in Contractor’s QCP.
Review of
certificates and
Calibration status of as per According to the Specification
3 Before the start of work
Inspection/Testing instruments instruments requirements ( Ref. section 8.1)
Supplier
instructions
4.5 Compressed air ASTM D4285 Every shift Free of oil and moisture
4.10 Dust test ISO 8502-3 Spot Checks (1) ≤ Grade 2 Class 2
Metallic “Comb
Methodically during According to PDS for the
5.2 WFT Gauge” as per
any application specified DFT
ISO 2808
5.3 Cleaning of each coat ISO 8502-3 Spot Checks (1) ≤ Grade 2 and Class 2
No sagging, contaminations,
Visual and as per
orange peel, cracking,
5.5 Visual examination of coating ISO 4628 1-6 100% of surface
blistering, rust damages and
[Ref.20]
any other defect
NACE
5.7 Holiday test when required Free from holidays
SP0188[Ref.41]
(1) Number and location shall be defined by COMPANY before the start of work
Percentage of Glass flake in Dry Film (glass flake containing coatings only);
Percentage of epoxy resin in the dry film.
Additional test shall be carried out in accordance with procedures to be approved by the Company. Test
procedures shall be in accordance with applicable international norm and codes. Testing of coating
materials shall be carried out under conditions that reflect the prevailing environmental and application
conditions.
Any batch of materials found inferior in any way to the standards and specifications of the Supplier’s
approved data sheets shall not be used and the Company will require further testing of materials by
Contractor until confidence in the materials is restored to the Company.
Certain coatings shall be tested for adequacy of cure. The test method and frequency shall be submitted by
Contractor for Company approval and may involve solvent wiping, pencil hardness testing or other chemical
or mechanical methods.
9. DOCUMENTATION
9.1 GENERAL
Contractor shall maintain records of all coating and inspections work, ref. ANNEX D, carried out in
accordance with this specification.
Prior to the commencement of work Contractor shall obtain full details(as listed in section 4.1) of all
coatings materials to be used from the selected Supplier (s) including product data sheets and safety
sheets. The following properties of the cured coating systems shall be reported using standardised and
approved laboratory test methods:
Adhesion;
Resistance to sea water and marine atmosphere as appropriate;
Service temperature, maximum limits;
Resistance to ageing (UV/salt spray);
Resistance to mechanical damage, e.g. impact resistance, elongation, tensile strength, abrasion;
Resistance to biological attack, for coating exposed to sea water;
Resistance to cathodic disbondment when coating is used in combination with cathodic protection;
Compatibility of different coatings when such are combined;
Reparability during construction, installation and service.
Pre-qualification tests for the coating material shall be performed in accordance with NORSOK M-501 Rev.
5 [Ref.45]. Paint Supplier shall provide proof of qualification according to the standard and Company
requirements at the bid stage.
The Supplier’s technical and application data sheets shall be obtained by Contractor for all components of
each coating system. Certificate of Conformity for each product and batch to be used shall be issued with
the material.
Contractor shall, at no additional cost to the Company, provide material samples and test panels of the
prepared coated surfaces if required by Company.
As general rules the tests shall be performed on carbon steel panels with the dimension of 300 mm x 300
mm, thickness 5 mm.
Panels shall be subjected to all works steps performed on the component (similar surface preparation and
paint system application).
The test shall be performed at the shop or field location where production coating will take place and
Contractor is responsible for the provision of all materials and equipment. Company may witness each step
of the preparation, coating application and inspection by Contractor and may conduct independent testing
as seen fit.
In addition Contractor shall keep up to date calibration certificates for all test or measurement equipment.
Contractor shall monitor all work and shall perform to the requirements of this specification against a project
specific Inspection Report, given in ANNEX D.
9.2 REPORTING
A full reporting/recording system, as given in ANNEX D, shall be maintained by Contractor who shall log
daily the following data:
Date and Time
Items Painted
Air and substrate temperatures;
Relative humidity and ambient conditions;
Coating progress;
Type and grade of blast cleaning abrasive;
Abrasive material and blasting air cleanliness;
Surface cleanliness;
Surface profiles;
Applied painting system & material details including batch number and shelf life.
Measured coating film thickness-WFT & DFT;
Visual inspection;
Details of other tests and results (holiday test, adhesion test, etc.)
Details of coating repair if any
Any other information pertinent to the work.
SYSTEM ONSHORE /
MATERIAL EXPOSURE APPLICATION
NUMBER OFFSHORE
Non Insulated, -Structural Steel and Claddings
Carbon & General - Piping, External Surfaces of
ONSHORE
SYSTEM 1 Low Alloy Atmospheric/Buried Vessels, Tanks, Process Plant
Steel (excluding buried and Equipment
piping) exposure - Miscellaneous steelwork
- Piping, External Surfaces of
Vessels and Process Systems
Non Insulated, Offshore, low maintenance
Carbon & Low General Atmospheric areas
SYSTEM 2 OFFSHORE - Barges, including external hull
Alloy Steel Exposure, Low
and topsides,
Maintenance
- Flare Structures
- Foundation piles and
- Pipe-Racks
ONSHORE Carbon & Low
SYSTEM 3 Insulated All items
OFFSHORE Alloy Steel
ONSHORE Carbon & Low
SYSTEM 4 Fireproofed All items
OFFSHORE Alloy Steel
ONSHORE Stainless Non Insulated/
SYSTEM 5 All items
OFFSHORE Steel Insulated
General Atmospheric
Exposure where
ONSHORE Galvanised Stair treads, Gratings, Handrails,
SYSTEM 6 colour requirement is
OFFSHORE Carbon Steel Ladders, Cable trays, etc.
specified
- Walkways
Marine Atmospheric
SYSTEM 7 OFFSHORE Carbon Steel - Escape routes
Exposure with traffic
- Lay down areas
- Piles
- Sheet Piles
SYSTEM 8 OFFSHORE Carbon Steel Sea Water Exposure - Caissons
- Equipment (sea water
exposure)
SYSTEM 9 ONSHORE Pipelines Atmospheric, All pipelines
Carbon Steel Intermittent wet/dry
SYSTEM Pipelines Atmospheric,
OFFSHORE All pipelines
10 Carbon steel Intermittent wet/dry
Miscellaneous steel work;
- Grating
ONSHORE
SYSTEM General Atmospheric - Stairs
Carbon Steel
11 OFFSHORE Exposure
- Ladders
- Handrails
-Cable trays, etc.
SYSTEM ONSHORE Atmospheric
Concrete Road Marking
12 OFFSHORE Intermittent wet/dry
ONSHORE NON-INSULATED
- Structural Steel and claddings
- Piping (except buried piping), External Surfaces of Vessels, Tanks, Process Plant and
SYSTEM 1 CARBON & GENERAL/ Equipment
LOW ALLOY ATMOSPHERIC/BURIED - Miscellaneous steelwork
STEEL
Surface shall be free from all grease, oil, dust, dirt, salts and other contaminants. Cleaning shall BLAST CLEAN: SA 2½
be as per SSPC SP1. SURFACE PROFILE: 30 - 85μm
Mechanical preparation ST 3 (local area only) subject to Company/paint
Surface shall be free from imperfections(Grade P2 as per ISO 8501-3) Supplier approval
GENERIC SYSTEM
SYSTEM 1A Atmospheric, General use - operating temperature <120˚C SYSTEM 1B Atmospheric, General use - operating temperature 120˚C -
160˚C
1 x 75μm Zinc rich Epoxy Primer, see note 2, 8 1 x 125μm Epoxy Phenolic
1 x 200μm Epoxy Mastic 1 x 125μm Epoxy Phenolic Topcoat
1 x 75μm Polyurethane Acrylic TOTAL MDFT 250μm
TOTAL MDFT 350μm See notes 5
SYSTEM 1C Atmospheric, General use - operating temperature 160˚C - 400˚C
Template: TSM-C30-FR-0001-000_A03
TYPE A
1 x 75μm Zinc Silicate Primer, see notes 3 and 4
1 x 125μm Inorganic Silicate Topcoat, see note 10 SYSTEM 1D Buried (except buried piping), operating temperature < 120˚C
OR 1 x 60μm Epoxy Primer, see notes 6 &7
TYPE B 1 x 400μm Glass Flake Epoxy
1 x 100μm Inorganic Copolymer Coating
1 x 100μm Inorganic Copolymer Coating, see note 9
TOTAL MDFT 400μm
This document is the property of North Caspian Operating Company N.V. (NCOC N.V.).
It must not be reproduced or transmitted to others without Company’s authorization.
NORTH CASPIAN OPERATING COMPANY N.V. STN-00-Z22-V-SP-0003
Rev. A01– June 2018
Internal Page 31 of 51
NOTES:
General Notes:
1. Solid content of all epoxy coatings shall be > 75%.
Specific Notes:
2. Zinc rich Epoxy shall be 2 pack formulations containing minimum 90% zinc dust by mass in the dry film. Zinc dust shall conform to ISO 3549 [Ref.19]. It shall
be overcoated before formation of zinc salts; otherwise these shall be removed completely prior to overcoating.
3. Zinc silicate shall have a minimum 85% zinc dust in the dry film. Zinc dust shall conform to ISO 3549[Ref.19].
4. Primed surface of system 1C shall be free of zinc dust prior to top coating
5. System 1B may be applied for bulk valves in service up to 160˚C.
6. The epoxy primer in System 1D is only necessary to maintain the integrity of the blasted steel surface. In situations where the primer is required the MDFT
shall increase to 460μm.
7. System 1D (including any primer) shall be certified as having high resistance to cathodic disbondment. All systems shall be tested in accordance with ASTM
G8/ASTM G42 [Ref.9/10] depending on temperature. The extent of disbondment at any point from periphery of the intended holiday shall not exceed 10mm
after 28 days at ambient temperature.
8. For onshore structural steel and other Company approved applications surface tolerant epoxy mastic may be used in place of the zinc primer.
9. System 1C TYPE B can be used for the operating temperature range 160-400°C and above.
10. Silicone acrylic or Silicone aluminium coating shall not be considered as an alternative.
NON-INSULATED
OFFSHORE - Piping, External Surfaces of Vessels and Process Systems, Barges including
external hull and topsides
SYSTEM 2 CARBON & - Flare Support Structure
LOW ALLOY GENERAL,ATMOSPHERICAND/OR - Foundation Piles
STEEL HIGH TEMPERATURE - Pipe-rack
Surface shall be free from all grease, oil, dust, dirt, salts and other contaminants. Cleaning BLAST CLEAN: Sa 2½, 2B:Sa 3
shall be as per SSPC SP1. SURFACE PROFILE: 30 - 85μm, 2B: 50 - 85μm
Surface shall be free from imperfections(Grade P2 as per ISO 8501-3 & Grade P3 for all Mechanical preparation ST 3 (local area only) subject to Company
surfaces intended to be permanent or intermittent immersed) /paint Supplier approval
GENERIC SYSTEM
SYSTEM 2A; Barge Hull, Sheet Pile Tie-rods, Flare Support Structure, Foundation
SYSTEM 2B Foundation Piles (splash zone and immersed zones),
Piles (buried in backfill and atmospheric areas) and Pipe Racks (atmospheric area
Barge Hull (Optional) operating temperature <120˚C and Flare
only) operating temperature <120˚C
Support Structure operating temperature 120˚C - 500˚C
1 x 50μm Epoxy Primer, see note 2
1 x 200μm Thermally Sprayed Aluminium
1 x 400μm Glass Flake Epoxy note3
2 x 25μm Silicone Aluminium Sealer
1 x 75μm Polyurethane Acrylic note 4
Ant-fouling paint note 4
TOTAL MDFT 200μm (TSA)
See notes 5 ,6 & 15
TOTAL MDFT 475μm
SYSTEM 2D Atmospheric, General use - operating temperature
SYSTEM 2C Atmospheric, General use - operating temperature <120˚C
120˚C - 160˚C
1 x 75μm Zinc rich Epoxy Primer, see note 7,8
1 x 125μm Epoxy Phenolic
1 x 200μm Epoxy Mastic
1 x 125μm Epoxy Phenolic Topcoat
1 x 75μm Polyurethane Acrylic
TOTAL MDFT 250μm
TOTAL MDFT 350μm
See notes 9 and 10
OR
TYPE B
1 x 100μm Inorganic Copolymer Coating
1 x 100μm Inorganic Copolymer Coating, see note14
Specific Note:
2. The epoxy primer in system 2A is only necessary to maintain the integrity of the blasted steel surface. In situations where the primer is required the MDFT shall
increase to 525μm.
3. The glass flake epoxy (including any primer if used) for the external surfaces of the barges shall be in accordance with Norsok M-501[Ref.44] systems 1 & 7.
4. Anti-fouling paint shall be used for the immersed areas of the hull and polyurethane acrylic shall not be used in these submerged areas of the hull (bottom and
vertical sides). The anti-fouling paint shall be tin and copper free, shall provide anti-fouling properties for a minimum 2 year life when exposed to seawater and
canal waters and shall be capable of being removed by high pressure water washing after the barge is removed from the water.
5. TSA shall be in accordance with Norsok M-501 [Ref.44] system 2. Aluminium wire shall be grade 99.5% to BS EN 1301[Ref.11]
6. Sealer in system 2B shall be suitable for temperatures up to 500˚C.
7. Zinc rich Epoxy shall be 2 pack formulations containing minimum 90% zinc dust by mass in the dry film. Zinc dust shall conform to ISO 3549[Ref.19]. It shall
be overcoated before formation of zinc salts; otherwise these shall be removed completely prior to overcoating.
8. For Company approved applications a Company approved surface tolerant epoxy mastic may be used in place of the zinc primer.
9. The epoxy phenolic shall be an immersion grade with greater than 6 months test data in sea water as per ISO 2812-2[Ref.17].
10. System 2D may be applied for bulk valves in service up to 160˚C.
11. Zinc silicate shall have a minimum 85% zinc dust in the dry film. Zinc dust shall conform to ISO 3549[Ref. 19].
12. Primed surface of system 2E shall be free of zinc dust prior to top coating.
13. Silicone acrylic or Silicone aluminium coating shall not be considered as an alternative.
14. System 2C TYPE B can be used for the operating temperature range 160-400°C and above
15. TSA application shall be as per NACE No. 12/AWS 2.23M/SSPC-CS 23.00 [Ref.43]
ONSHORE INSULATED
OFFSHORE - Structural Steel and claddings
SYSTEM 3 CARBON & - Piping ,Vessels and process plant
LOW ALLOY ATMOSPHERIC - Miscellaneous steelwork
STEEL
Surface shall be free from all grease, oil, dust, dirt, salts and other contaminants. BLAST CLEAN: Sa 2½ 3D: Sa 3
Cleaning shall be as per SSPC SP1. SURFACE PROFILE: 30 - 85μm, 3D: 50 - 85μm
Surface shall be free from imperfections(Grade P2 as per ISO 8501-3 & Grade P3 for Mechanical preparation ST 3 (local area only) subject to Company/paint
all surfaces intended to be permanent or intermittent immersed) Supplier approval
GENERIC SYSTEM
SYSTEM 3A Insulated - operating temperature up to 120˚C SYSTEM 3B Insulated - operating temperature 120˚C - 160˚C
1 x 50μm Epoxy Primer, see note 2 1 x 125μm Epoxy Phenolic
2 x 150μm Epoxy Mastic 1 x 125μm Epoxy Phenolic
NOTES:
General Notes:
1. Solid content of all epoxy coatings shall be > 75%.
Specific Notes:
2. The epoxy primer in system 3A shall not contain any zinc.
3. The epoxy phenolic shall be an immersion grade with greater than 6 months test data in sea water as per ISO 2812-2[Ref.17].
4. System 3B may be applied for bulk valves in service up to 160˚C.
5. Zinc silicate shall have a minimum 85% zinc dust in the dry film. Zinc dust shall conform to ISO 3549[Ref.19].
6. Primed surface of system 3C shall be free of zinc dust prior to top coating.
7. TSA shall be in accordance with Norsok M-501[Ref.44] system 2. Aluminium wire shall be grade 99.5% to BS EN 1301[Ref.11].
8. The sealer in system 3D shall be suitable for temperatures up to 500˚C.
9. For standardisation purposes, System 3A can be replaced by System 3B, where Contractor prefers.
10. Silicone acrylic or Silicone aluminium coating shall not be considered as an alternative.
11. System 3C TYPE B can be used for the operating temperature range 160-400°C and above for onshore/offshore services
12. TSA application shall be as per NACE No. 12/AWS 2.23M/SSPC-CS 23.00[Ref.43].
SURFACE PREPARATION:
PRE TREATMENT:
BLAST CLEAN: Sa 2½
Surface shall be free from all grease, oil, dust, dirt, salts and other contaminants.
SURFACE PROFILE: 30 - 85μm
Cleaning shall be as per SSPC SP1.
Mechanical preparation ST 3 (local area only) subject to Company /paint
Surface shall be free from imperfections(Grade P2 as per ISO 8501-3)
Supplier approval
GENERIC SYSTEM
SYSTEM 4B Cementitious PFP
SYSTEM 4A Epoxy Intumescent PFP system see note 7
1 x 60μm Zinc rich Epoxy Primer, see note 1 and 8
1 x 50 - 70μm Zinc rich Epoxy Primer, see notes 1,2 and 8
1 x 200μm Epoxy MIO, see notes 3 and 4
MDFT 50μm
MDFT 260μm
PFP, see note 9
PFP, see note 9
1 x 75μm Polyurethane Acrylic
1 x 75μm Polyurethane Acrylic, see note 5
see note 6
see note 6
NOTES:
1. Zinc rich Epoxy shall be 2 pack formulations containing minimum 80% zinc dust by mass in the dry film. Zinc dust shall conform to ISO 3549[Ref.19]. It shall be
over coated before formation of zinc salts, otherwise these shall be removed completely prior to over coating.
2. Under intumescent epoxy fireproofing: The primer shall be approved by PFP Supplier based on results of shear strength.
3. Solid content of epoxy shall be > 75%.
4. Under cementitious fireproofing: Alternative coating system may be offered, subject to PFP Supplier’s recommendations.
5. The specific sealing/topcoat requirements for cementitious fireproofing shall be agreed with Company and the PFP supplier.
6. Repair system shall be approved compatible systems.
7. Intumescent epoxy fireproofing Supplier, grade, qualification data, application and inspection procedures shall be approved by Company.
8. For Stainless Steel and Nickel Alloy, primer to be confirmed by intumescent Supplier.
9. PFP DFT as per PFP Specification/PFP Supplier recommendation
ONSHORE / OFFSHORE
NON-INSULATED
SYSTEM 5 STAINLESS STEEL & NICKEL All applicable surfaces
INSULATED
ALLOYS
CLASSIFICATION OF ENVIRONMENT AS PER ISO 12944-2: C5I & C5M
PRE TREATMENT: SURFACE PREPARATION:
Surface shall be free from all grease, oil, dust, dirt, salts and other contaminants. SWEEP BLAST ONLY, see note 3
Cleaning shall be as per SSPC SP1. SURFACE PROFILE: 25 - 45μm
Surface shall be free from imperfections(Grade P2 as per ISO 8501-3 & Grade P3 for Mechanical preparation ST 3 (local area only) subject to Company/paint
all surfaces intended to be permanent or intermittent immersed) Supplier approval
GENERIC SYSTEM
SYSTEM 5A Non-Insulated and Atmospheric Exposure SYSTEM 5B Insulated and Atmospheric / Seawater Exposure
Austenitic Steel: Operating temperature 50 - 160˚C All insulated Austenitic, Duplex Stainless Steel and Alloy 825, Operating
Duplex Steel and Alloy 825: Operating temperature 90 - 160˚C temperature below 160˚C
1 x 125μm Epoxy Phenolic 1 x 125μm Epoxy Phenolic
1 x 125μm Epoxy Phenolic Topcoat 1 x 125μm Epoxy Phenolic
TOTAL MDFT 250μm TOTAL MDFT 250μm
See note 4 See note 4
SYSTEM 5C All Insulated and Operating temperature 160˚C - 500˚C SYSTEM 5D Insulated/Non-Insulated and Atmospheric
Operating temperature 160˚C - 500˚C, Austenitic, Duplex Stainless Steel
1 x 200μm Thermally Sprayed Aluminium and Alloy 825
2 x 25μm Silicone Aluminium Sealer
1 x 100μm Inorganic Copolymer Coating
TOTAL MDFT 200μm (TSA) 1 x 100μm Inorganic Copolymer Coating
See notes 5, 6 and 8 TOTAL MDFT 200μm
NOTES:
General Notes:
1. Non-insulated stainless steels, operating up to 50˚C do not require coating.
2. Non-insulated Duplex stainless steels and Alloy 825, operating up to 90˚C do not require coating.
Specific Notes:
3. Aluminium oxide or Garnet or other approved non-metallic abrasive shall be used for surface preparation.
4. The epoxy phenolic shall be an immersion grade with greater than 6 months test data in sea water as per ISO 2812-2[Ref.17].
5. TSA shall be in accordance with Norsok M-501[Ref.44] system 2. Aluminium wire shall be grade 99.5% to BS EN 1301[Ref.11].
6. Sealer in system 5C shall be suitable for temperatures up to 500˚C.
7. SS and Nickel alloy piping flanges using carbon steel bolting, shall be painted on the back surface of the flange with System 5A.
8. TSA application shall be as per NACE No. 12/AWS 2.23M/SSPC-CS 23.00[Ref.43].
Specification for External Coating - Onshore/Offshore
NORTH CASPIAN OPERATING COMPANY N.V. STN-00-Z22-V-SP-0003
Rev. A01– June 2018
Internal Page 38 of 51
Surface shall be free from all grease, oil, dust, dirt, salts and other contaminants. SWEEP BLAST ONLY (see note 2 and 3)
Cleaning shall be as per SSPC SP1. SURFACE PROFILE: 30μm
Finally, galvanising to be scrubbed with bristle brushes and suitable detergent to Mechanical preparation ST 3 (local area only) subject to Company/paint
remove all traces of flux. Supplier approval
Surface shall be free from imperfections(Grade P2 as per ISO 8501-3 & Grade P3 for
all surfaces intended to be permanent or intermittent immersed)
GENERIC SYSTEM
SYSTEM 6
1 x 125μm Epoxy Mastic
1 x 75μm Polyurethane Acrylic, see note 4
NOTES:
General Notes:
1. Touch-up of damaged galvanising:
1 x 2 pack zinc rich epoxy primer, DFT 70μm
Specific Notes:
2. Contractor shall demonstrate that sweep blasting will not cause cracking, flaking or lifting of galvanising.
3. Etch priming may be used as an alternative to sweep blasting subject to Company approval.
4. Final coat shall be light grey or white unless otherwise noted in ANNEX B or C.
- Walkways
OFFSHORE MARINE ATMOSPHERIC - Escape routes
SYSTEM 7 WITH TRAFFIC - Lay down areas
CARBON (DECKING ) - Helideck
STEEL - Photo luminescent escape way markings (note 6)
GENERIC SYSTEM
SYSTEM 7A Light Duty general Walkways and Decks
SYSTEM 7B Escape Routes, Heavy Duty Walkways, Lay Down Areas and
1 x 60μm Zinc Rich Epoxy Primer, see note 3
Helideck
1 x 400μm Glass Flake Epoxy (or High build epoxy) incorporating silica aggregates
1 x 60μm Zinc Rich Epoxy Primer, see note 3
see note 4)
1 x 3000μm Epoxy Compound with silica aggregate, see note 4
1 x 75μm Polyurethane Acrylic, see notes 5 and 6
1 x 50μm Polyurethane Acrylic, see notes 5 and 6
TOTAL MDFT 3mm
TOTAL MDFT 475μm
NOTES:
General Notes:
1. Repair systems to be based on approved compatible systems.
2. Primer selection, application and overcoating to be subject to Supplier’s written recommendation.
Specific Notes:
3. The epoxy primer in System 7A and 7B is only necessary to maintain the integrity of the blasted steel surface. In situations where the primer is required the MDFT shall
increase to 535μm for system 7A.
4. Aggregates to be approved non-slip and non-sparking type. For Helideck the system shall comply with CAP 437[Ref.12].
5. Topcoat colour shall be as per safety or marking / colour requirements
6. An approved photo luminescent paint system shall be used to provide strips 100mm wide on escape routes as indicated in the project specification and drawings. If
the substrate is steel then either of the above two coating systems shall be used substituting the final layer of Polyurethane acrylic by the photo luminescent paint
system. For concrete walkways the photo luminescent paint system shall be applied directly on the concrete surface. The photo luminescent paint system shall
comprise a white base coat, a photo luminescent coat and a coat of high transparency protective lacquer/varnish. All components of the photo luminescent paint
system shall be supplied by the same Supplier and shall be applied strictly in accordance with their written instructions.
- Foundation Piles
OFFSHORE
SEA WATER - Sheet Piles
SYSTEM 8
EXPOSURE - Caissons
CARBON STEEL - Equipment (sea water exposure)
CLASSIFICATION OF ENVIRONMENT AS PER ISO 12944-2: C5M
- Atmospheric
SYSTEM 9 ONSHORE PIPELINES - Intermittent (wet and dry)
GENERIC SYSTEM
SYSTEM 9A Atmospheric - operating temperature <120˚C SYSTEM 9B Intermittent (Wet and Dry) – Non-Hydrocarbon Service up to
1 x 75μm Zinc rich Epoxy Primer, see note 2 60°C
1 x 200μm Epoxy Mastic (or HB Epoxy) incorporating silica aggregates, see note 4 1 x 1500μm 100% solids polyurethane, See note 3
1 x 75μm Polyurethane Acrylic
TOTAL MDFT 350μm TOTAL MDFT 1500μm See note 4
SYSTEM 9C Intermittent (Wet and Dry) or Burial – Hydrocarbon Service up to
160°C
1 x 1500μm Epoxy Phenolic
1 x 50μm Polyurethane Acrylic, See note 5
TOTAL MDFT 1550μm See notes 4 , 6 & 7
NOTES:
General Notes:
1. Coating systems 9B, and 9C shall be certified as having high resistance to cathodic disbondment. All systems shall be tested in accordance with ASTM G8,
ASTM G42 [Ref.9, 10] depending on temperature. The extent of disbondment at any point from periphery of the intended holiday shall not exceed 8 mm after
28 days at ambient temperature.
Specific Notes:
2. Zinc rich Epoxy shall be 2 pack formulations containing minimum 90% zinc dust by mass in the dry film. Zinc dust shall conform to ISO 3549[Ref.19]. It shall
be overcoated before formation of zinc salts occur otherwise these shall be removed completely prior to overcoating.
3. The polyurethane shall be pre-qualified to EN 10290[Ref.14] or approved equivalent.
4. Field touch up materials may be brush applied for systems 9B and 9C in accordance with coating Supplier recommendation.
5. Polyurethane acrylic is only required for items subject to direct UV exposure.
6. System 9C may be applied for bulk items (e.g. valves, tees, bends, etc.) installed above/below ground.
7. Phenolic Epoxy shall be pre-qualified to EN 10289[Ref.13] or approved equivalent.
- Atmospheric
SYSTEM 10 OFFSHORE PIPELINES
- Intermittent (wet and dry)
CLASSIFICATION OF ENVIRONMENT AS PER ISO 12944-2: C5M
Surface shall be free from all grease, oil, dust, dirt, salts and other contaminants. BLAST CLEAN: 10A: Sa 2½ 10B: Sa 3
Cleaning shall be as per SSPC SP1. SURFACE PROFILE: 50 - 85μm
Surface shall be free from imperfections(Grade P2 as per ISO 8501-3 & Grade P3 for Mechanical preparation ST 3 (local area only) subject to Company/paint
all surfaces intended to be permanent or intermittent immersed) Supplier approval
GENERIC SYSTEM
SYSTEM 10A Atmospheric up to 160°C SYSTEM 10B Intermittent (wet and dry) up to 500˚C
1 x 1500μm Epoxy Phenolic, See note 5 1 x 200μm Thermally Sprayed Aluminium
1 x 50μm Polyurethane Acrylic, See note 2 2 x 25μm Silicone Aluminium Sealer
TOTAL MDFT 1550μm TOTAL MDFT 200μ (TSA), See notes 3 ,4 and 6
NOTES:
General Notes:
1. Coating systems 10A and 10B shall be certified as having high resistance to cathodic disbondment. All systems shall be tested in accordance with ASTM G8,
ASTM G42 [Ref.9, 10] depending on temperature. The extent of disbondment at any point from periphery of the intended holiday shall not exceed 8mm after
28 days at ambient temperature.
Specific Notes:
2. Polyurethane acrylic is only required for items subject to direct UV exposure.
3. TSA shall be in accordance with Norsok M-501[Ref.44] system 2. Aluminium wire shall be grade 99.5% to BS EN 1301[Ref.11].
4. The sealer in system 10B shall be suitable for sea water exposure.
5. Phenolic Epoxy shall be pre-qualified to EN 10289[Ref.13] or approved equivalent.
6. TSA application shall be as per NACE No. 12/AWS 2.23M/SSPC-CS 23.00[Ref.43].
Surface shall be free from all grease, oil, dust, dirt, salts and other contaminants. BLAST CLEAN: Sa 2½
Cleaning shall be as per SSPC SP1. SURFACE PROFILE: 50-85μm
Surface shall be free from imperfections(Grade P2 as per ISO 8501-3 & Grade P3 for
all surfaces intended to be permanent or intermittent immersed)
GENERIC SYSTEM
SYSTEM 11
Hot Dip Galvanised Coating
See Note 1, 2 & 3
NOTES:
1. Hot Dip Galvanising shall be as per section 3.8.8.
2. Touch-up on damaged galvanised surface shall be as per section 6.9
3. Where ever required ,galvanised surface shall be coated as per coating system 6
New concrete should be cured for at least 14 days. Surface should be free
Remove all oil, salts and other contaminants with a water miscible detergent from laitance. All Surfaces shall be brushed ensuring all dust and loose
and high pressure fresh water washing material is removed before the markings are applied.
GENERIC SYSTEM
NOTES:
General Notes:
1. Markings shall be applied at the locations and colours indicated in project specifications and drawings
2. All road marking paint shall be, quick drying, re-coatable, slip resistant. Paint shall have high reflectivity by the application of Ballotini glass beads at a rate
of 400g per square metre.
3. Product Supplier shall confirm suitability for the proposed environmental conditions; alternative products may be submitted for approval.
4. Application shall be strictly in accordance with the product Supplier instructions.
This document is the property of North Caspian Operating Company N.V. (NCOC N.V.).
It must not be reproduced or transmitted to others without Company’s authorization.
NORTH CASPIAN OPERATING COMPANY N.V. STN-00-Z22-V-SP-0003
Rev. A01– June 2018
Internal Page 46 of 51
BACKGROUND COLOUR
120 mm 50 mm 120 mm
COATING ACTIVITY:
REMARKS:
This document is the property of North Caspian Operating Company N.V. (NCOC N.V.).
It must not be reproduced or transmitted to others without Company’s authorization.