Project Spreadsheets to EC2 The Concrete Centre

Client Advisory Group Made by Date Page


Location Level 2 - Beam on Grid 7 rmw 15-Nov-2021 259
POST-TENSIONED ANALYSIS & DESIGN to BS EN 1992-1:2004 Checked Revision Job No
Originated from TCC42.xls v4.0 on CD © 2005-21 TCC chg - FB625

POST-TENSIONED ANALYSIS & DESIGN to BS EN 1992-1:2004 - GENERA


LOAD COMBINATIONS
TRANSFER SLS 1 Transfer prestress + dead load at transfer
SLS 2 Final prestress + dead + full imposed load on all spans NOTES
RARE SLS 3 Final prestress + dead + full imposed load on odd spans INPUT IS UNDERLINED.
SLS 4 Final prestress + dead + full imposed load on even spans FRAMES ARE ASSUMED
SLS 5 Final prestress + dead + frequent imposed load on all s TO BE BRACED
FREQUENT SLS 6 Final prestress + dead + frequent imposed load on odd spans
SLS 7 Final prestress + dead + frequent imposed load on even spans USAGE
QUASI- SLS 8 Final prestress + dead + QP imposed load on all spans Shopping
PERMANEN SLS 9 Final prestress + dead + QP imposed load on odd spans
T SLS 10 Final prestress + dead + QP imposed load on even spans
ULS 1 Final prestress + factored dead and imposed load on all spans VIBRATION
ULTIMATE ULS 2 Final prestress + factored dead + factored imposed load Limiting
on odd reponse factor
ULS 3 Final prestress + factored dead + factored imposed load on even R=8

ULS LOADING PATTERN min max DEFLECTION


Dead 1.25 1.25 Limit QP deflection to L/ 250
Imposed 0 1.50 Limit after construction Δ to L/ 500
BS EN 1990: (6.10b)

OPTIONS Exposure class is X0, XC1 stress system is bonded d stressed from left end
Slab Wmax, mm = 0.2
Jacking force /fpk = 0.8 bonded rebar in spans? Yes (Helps to reduce deflections - recommended)
Slab type R (S)olid, (R)ibbed or (W)affle, supported by beam
Damping, z (1% to 4½%) 1.5%

MATERIALSCONCRETE fck = 40 Ecm = 35.2205 σc,max = 18.00 σt,max = 5.79 Design


hypothetical
At transfer, 4 days, fck(i) = 26.54
Ecm(i) = 31.91 σc,max(i) = 11.94 σt,max(i) = 4.17 tensile stresses to
γc = 1.50 limit cracking
Cement type R Curing time (days) = 3
Ave ambient during curing = 18ºC Longterm R/H % 55 .

STRAND fpk = 1860 Aps, mm² = 100 µ = 0.200 K = 0.0085


Eps = 195 Rel % = 2.5 Δ, draw in =6 Depth to strand centre = 41

REBAR fyk = 500 Grade A COVERS Top Bottom Sides


γm = 1.15 to links 25 25 25

LOADING SEQUENCE Loading sequence for φ assessm ψ2 = 0.6 Rare combination


Load @ Age fctm fctm,fl φ Ecm(t) Load φ Ecm(t)
kN/m days MPa MPa Creep GPa kN/m² Creep GPa
Dead at transfer 10.19 4 2.52 2.52 1.93 12.01 10.19 1.93 12.01
Applied dead 2.07 30 3.51 3.51 1.51 14.05 2.07 1.51 14.05
uasi-permanent imposed 5.40 -=- 9.00
COMBINED 17.66 - 1.75 12.79 21.26 1.71 12.99

NOTES on MATERIALS
BRITISH LOW RELAXATION STRAND
Type Dia Area fpk Weight RELAXATION at 0.7fpk
Standard 15.2 139 1670 1.090 Ambient ºC 20 40 60 80 100
12.5 93 1770 0.730 Relaxation 1.8 3.5 5.1 7.5 10.7
Super 15.7 150 1770 1.180
12.9 100 1860 0.785
Compact 15.2 165 1820 1.295
12.7 112 1860 0.890
Project Spreadsheets to EC2 The Concrete Centre
Client Advisory Group Made by Date Page
Location Level 2 - Beam on Grid 7 rmw 15-Nov-2021 260
POST-TENSIONED ANALYSIS & DESIGN to BS EN 1992-1:2004 Checked Revision Job No
Originated from TCC42.xls v4.0 on CD © 2005-21 T chg - FB625
Dimensions and Loads
NORMAL DIRECTION
SPANS Lm H mm bw mm hf mm Section beff mm No Bays Bay width m
Span 1 16.000 800 350 150 T 1200 10 7.200
Span 2 14.400 800 350 150 T 1200 10 7.200
Span 3 13.800 800 350 150 T 1200 10 7.200

SUPPORTS Above m H mm b mm End cond Below m H mm b mm End cond


Support 1 K
Support 2 K
Support 3 K
Support 4 K

CONFIGURATION SLAB supporting Ribbed Slab, Exposure class X0, XC1, Wk = 0.2 mm, fck = 40,
Stressed from Both Ends

LOADING UDLs~kN/m (char), PLs~kN (char), Position~m


Dead at Applied Imposed Position Loaded Dead at Applied Imposed Position Loaded
SPAN 1 transfer Dead Load from left Length SPAN 3 transfer Dead Load from left Length
UDL 10.19 2.07 9.00 ~~~~~ ~~~~~ UDL 10.19 2.07 9.00 ~~~~~ ~~~~~
PL 1 ~~~~~ PL 1 ~~~~~
PL 2 ~~~~~ PL 2 ~~~~~
Part UDL Part UDL
SPAN 2
UDL 10.19 2.07 9.00 ~~~~~ ~~~~~
PL 1 ~~~~~
PL 2 ~~~~~ GLOBAL STATUS
Part UDL VALID DESIGN

TENDON PROFILE (heights to strand centre: see heights specified under TENDONS below)

826

501 501

41 80

EQUIVALENT LOADS in service

80
60 5 2 kN/m
52 kN/m 52 kN/m
38 kN/m
40 31 kN/m
23 kN/m
20
0 -11 kN/m -13 kN/m -7 kN/m
-20
-40
Project Spreadsheets to EC2 The Concrete Centre
Client Advisory Group Made by Date Page
Location Level 2 - Beam on Grid 7 rmw 15-Nov-2021 261
POST-TENSIONED ANALYSIS & DESIGN to BS EN 1992-1:2004 Checked Revision Job No
Originated from TCC42.xls v4.0 on CD © 2005-21 T chg - FB625
Tendons & bonded reinforcement
(a) TENDONS Pj = 149 kN Pi/A = 1.52 MPa max
Supt 1 Span 1 Supt 2 Span 2 Supt 3 Span 3 Supt 4
Pi/Pj 71.7% 53.7% 43.0%
P30/Pj 70.6% 52.6% 42.1%
Pf/Pj 63.3% 46.0% 35.6%
No of strands
Recommended ≥5 ≥5 ≥5 ≥3 ≥3 ≥3 ≥3 ≥3 ≥3
Use 5 5 5 5 5 5 4 4 4
Recommend'd height 501 41 759 41 759 41 501
Height mm 501 41 826 826 41 826 826 41 501
Length Straight mm 0 0 0 0 0 0
x to max Sag mm 7056 7200 7714
Pi kN 618 618 534 515 454 400 320 282 256
Balance Load kN 80.6 108.5 99.1 99.1 57.4 42.7
Pf kN 550 553 471 453 396 342 274 238 212
Balance Load kN 61.4 82.7 74.6 74.6 43.1 32.0

CHECKS 'EFFICIENCY' a 45%


Tendons (a) OK
b(C) 24%
Stresses at transfer (b) OK
b(T) 12%
Stresses in service (c) OK √ for (c) see line RESULTS! li
ULS MOR (d) OK c(C) 31%
Shear (e) OK c(T) 79%
Vibration (f)
OK - see note
d 70%
Deflection (g) OK
Neutral axis depth OK e 23%
Rebar stress OK f7% √ for n. a. depth see DETAIL
g 82% √ for rebar stress see DETAIL
GLOBAL STATUS VALID DESIGN
0% 131%

REINFORCEMENT Input bonded rebar arrangement (Support bars cutailed at 0.3L)


Span 1 Span 2 Span 3
Supt 1 btm top Supt 2 btm top Supt 3 btm top Supt 4
Required at SLS 1662 956 1196 1662 485 1196 1662 1278 1196 1662
Main bar Ø 16 25 16 16 16 16 16 20 16 16
No 9 4 7 9 4 7 9 4 7 9
As provided 1810 1963 1407 1810 804 1407 1810 1257 1407 1810
% 0.646% 0.701% 0.503% 0.646% 0.287% 0.503% 0.646% 0.449% 0.503% 0.646%
Link Ø = 8
No of legs 3 3 3 3 3 3 3 3 3 3

(d) ULS MOMENTS With bonded reinforcement


Supt 1 Span 1 Supt 2 Span 2 Supt 3 Span 3 Supt 4
Mu 0.0 441.9 421.0 421.0 133.3 357.9 357.9 413.1 0.0
MOR 756.6 1017.3 885.1 874.1 559.7 806.9 758.6 592.0 646.0

1500 ULS MOMENT ENVELOPE/MOR

1000

500

-500

-1000

-1500
Project Spreadsheets to EC2 The Concrete Centre
Client Advisory Group Made by Date Page
Location Level 2 - Beam on Grid 7 rmw 15-Nov-2021 263
POST-TENSIONED ANALYSIS & DESIGN to BS EN 1992-1:2004 Checked Revision Job No
Originated from TCC42.xls v4.0 on CD © 2005-21 T chg - FB625
Results (2)
(e) SHEAR Link Ø = 8
Span 1 Span 2 Span 3
Left Right Left Right Left Right
VEd - Vtd 170.3 217.7 160.1 168.9 194.2 159.1
cracked ? N Y Y Y Y N
(VEd - Vtd)/VRdc 0.856 1.138 0.845 0.945 1.129 0.959
No of legs 3 3 3 3 3 3
Link spacing 425 425 425 425 425 425

ULS SHEAR ENVELOPE (VEd)


400
300
200 204.1 206.9 224.7
100
0
-100
-200 -208.0 -172.8
-256.8
-300
-400

(f) VIBRATION Span 1 Span 2 Span 3


Response factor 0.46 0.40 0.52
OK OK OK

(g) DEFLECTION

MAX DEFLECTIONS (mm)


5
0
-5
-10
-15
-20
-25
-30
At transfer Span 1 = -0.4mm Span 2 = -1.8mm Span 3 = 0.2mm
Quasi-permanent
Span 1 = 13.4mm < 64 OK Span 2 = 3.1mm < 57.6 OK = 25.5mm < 55.2 OK
After construction
Span 1 = 11.3mm < 32 OK Span 2 = 5.1mm < 28.8 OK = 22.5mm < 27.6 OK

SUPPORT REACTIONS Supt 1 Supt 2 Supt 3 Supt 4


ULS 1 194.6 478.1 432.7 167.8 kN
ULS 2 194.7 384.3 328.2 171.7 kN
ULS 3 91.6 360.2 343.8 75.4 kN
Dead 83.3 199.6 186.8 72.0 kN
Imposed 58.1 154.5 135.2 50.0 kN

COLUMN MOMENTS Supt 1 Supt 2 Supt 3 Supt 4


Above 0.00 0.00 0.00 0.00 kNm
ULS 1
Below 0.00 0.00 0.00 0.00 kNm
Above 0.00 0.00 0.00 0.00 kNm
ULS 2
Below 0.00 0.00 0.00 0.00 kNm
Above 0.00 0.00 0.00 0.00 kNm
ULS 3
Below 0.00 0.00 0.00 0.00 kNm
Project Spreadsheets to EC2 The Concrete Centre
Client Advisory Group Made by Date Page
Location Level 2 - Beam on Grid 7 rmw 15-Nov-21 264
POST-TENSIONED ANALYSIS & DESIGN to BS EN 1992-1:2004 Checked Revision Job No
Originated from TCC42.xls v4.0 on CD © 2005- chg - FB625

TYPICAL CALCULATION
for Span 1 at 4.80 m from C/L of LH support EC2 Ref
Class X0, XC1 Tee section, h = 800 mm, bw = 350 mm hf = 150 mm, bf =1 Table 4.1
Ac = 407500mm², Z top = 81.9E6 mm³, and Z bottom = 48.7E6 mm³
Tendons are bonded, Ap = 100mm², fpk = 1,860 N/mm2 and 101.8 mm from soffite
There are 5 tendons, jacked to 1,488 N/mm² or 80% fpk
Prestress losses at this section are 126.1 kN at transfer and 192.2 kN longterm 5.10.5 & 6

(b) STRESSES at TRANSFER


M = 21.7 kNm hogging, and prestressing force = 617.9 kN
Max compression (bottom) = M/Z + P/A = -21.7E3 / 81.9 + 617.9 / 407.5 = 1.96 N/mm²
< 11.94 N/mm² allowed
5.10.2.2(5)
Max tension (top) = M/Z - P/A = 21.7E3 / 81.9 - 617.9 / 407.5 = 0.00 N/mm²
< 4.17 N/mm² allowed TR43
(c) STRESSES in SERVICE
Frequent M = 217.7 kNm sagging, and prestressing force = 551.8 kN
Max compression (top) = 217.7E6 / 81.9E6 + 551.8E3 / 407.5E3 = 3.77 N/mm²
< 18.00 N/mm² allowed
5.10.2.2(5)
Quasi-permanent M = 197.5 kNm sagging
Max tension (bottom) = 197.5 / 48.7 - 551.8 / 407.5 = 3.12 N/mm²
< 5.79 N/mm² allowed TR43
(d) MOR at ultimate limit state
M = 414.7 kNm sagging, and prestressing force = 551.8 kN
σpe = 1000 x 551.8 / 5 / 100 = 1,103.5 N/mm²
Reinforcement d = 754.5 mm
Tendon force = 0.9 (551.8 + 100 /1000 x 5 x 100) = 541.6 kN 5.10.8(2)
As = π/4 x 25² x 4 = 1,963 mm²
Rebar force = 500 / 1.15 x 1,963 / 1000 = 853.7 kN
Total tensile force = 541.6 + 853.7 = 1,395.3 kN
η∙fcd = 1 x 0.85 x 40/1.5 = 22.67 N/mm² 3.1.7(3)
Compression block depth, λx = 1000 x 1,395.3 / 22.67 / 1200 = 51.30 mm Fig 3.5
MOR = (541.6 ( 800 - 101.8 - 51.30 / 2) + 853.7 x (754.5 - 51.30 / 2)) / 1000
= 986.5 kNm > 414.7 ok
Project Spreadsheets to EC2 The Concrete Centre
Client Advisory Group Made by Date Page
Location Level 2 - Beam on Grid 7 rmw 15-Nov-2021 272
POST-TENSIONED ANALYSIS & DESIGN to BS EN 1992-1:2004 Checked Revision Job No

Originated from TCC42.xls v4.0 on CD © 2005-21 TCC chg - FB625


Detailed calculations (8)
Loadings 0 0
Span 3 Left < > PL1 < > PL2 < > Right UDL PL1 PL2 pUDL 13.8
V SLS 1 72.0 0 72.0 0 72.0 100 68.5 10.2 0.0 0.0 0.0
SLS 2 166.3 0 166.3 0 166.3 100 127.0 21.3 0.0 0.0 0.0
SLS 3 157.7 0 157.7 0 157.7 100 135.6 21.3 0.0 0.0 0.0
SLS 4 98.0 0 98.0 0 98.0 100 71.2 12.3 0.0 0.0 0.0
SLS 5 144.1 0 144.1 0 144.1 100 112.0 18.6 0.0 0.0 0.0
SLS 6 137.5 0 137.5 0 137.5 100 118.5 18.6 0.0 0.0 0.0
SLS 7 95.9 0 95.9 0 95.9 100 73.3 12.3 0.0 0.0 0.0
SLS 8 136.6 0 136.6 0 136.6 100 107.0 17.7 0.0 0.0 0.0
SLS 9 130.8 0 130.8 0 130.8 100 112.8 17.7 0.0 0.0 0.0
SLS 10 95.1 0 95.1 0 95.1 100 74.0 12.3 0.0 0.0 0.0
ULS 1 224.7 0 224.7 0 224.7 100 172.8 28.8 0.0 0.0 0.0
ULS 2 220.9 0 220.9 0 220.9 100 176.6 28.8 0.0 0.0 0.0
ULS 3 130.9 0 130.9 0 130.9 100 80.3 15.3 0.0 0.0 0.0

Untensioned bars at SLS


Supt 1 Span 1 Supt 2 Span 2 Supt 3 Span 3 Supt 4
Right btm top Left Right btm top Left Right btm top Left
fctm 3.51 3.51 2.52 3.51 3.51 3.51 2.52 3.51 3.51 3.51 2.52 3.51
d 759.0 754.5 759.0 759.0 759.0 759.0 759.0 759.0 759.0 757.0 759.0 759.0
As,min 1662 482 1196 1662 1662 485 1196 1662 1662 483 1196 1662 (9.1N)
σct 0.000 3.402 0.000 1.761 1.806 0.628 0.000 1.860 2.027 4.548 0.000 0.000
Ft 0 299 0 93 95 55 0 98 98 399 0 0
As 0 956 0 298 305 177 0 314 314 1278 0 0

ULS MOMENT CHEC Supt 1 Supt 2 Supt 3 Supt 4


Span 1 Span 2 Span 3
(d) Right Left Right Left Right Left
Design moment 0.0 441.9 421.0 421.0 133.3 357.9 357.9 413.1 0.0
Tendon height 501.0 46.1 826.0 826.0 41.0 826.0 826.0 41.2 501.0
dp 501.0 753.9 826.0 826.0 759.0 826.0 826.0 758.8 501.0
dr 759.0 754.5 759.0 759.0 759.0 759.0 759.0 757.0 759.0
Tendon force 540 543 469 452 401 353 283 250 227
As 1810 1963 1810 804 1810 1257 1810
Rebar force 786.8 853.7 786.8 786.8 349.7 786.8 786.8 546.4 786.8
TOTAL TENSION 1326 1396 1256 1239 751 1140 1069 797 1013
λx 167.2 51.3 158.3 156.2 27.6 143.7 134.8 29.3 127.7
Rebar stress 435 435 435 435 435 435 435 435 435
Zp 417.4 728.2 746.9 747.9 745.2 754.2 758.6 744.1 437.1
Zr 675.4 728.8 679.9 680.9 745.2 687.2 691.6 742.4 695.1
MOR 756.6 1017.3 885.1 874.1 559.7 806.9 758.6 592.0 646.0

SHEAR (e) Span 1 Span 2 Span 3 fctd = 1.637


Left Right Left Right Left Right fcd = 26.67
VEd 204.3 256.8 211.8 208.0 224.7 176.6 σc,lim = 13.05
MEd 0.0 421.0 421.0 357.9 357.9 0.0
NEd 549.5 471.0 452.7 342.2 274.1 211.8
σct 0.000 4.101 4.004 3.488 3.766 0.000 12.6.3 (3)
Cracked ? N Y Y Y Y N
PLAIN Acc 407500 407500 407500 407500 407500 407500
σcp 1.349 1.156 1.111 0.840 0.673 0.520 Equation (12.3)
τcp 0.752 0.945 0.780 0.765 0.827 0.650 Equation (12.4)
fcvd 2.211 2.139 2.121 2.014 1.945 1.879 Equations (12.5) & (12.6)
plain concrete ? Y Y Y 12.6.3
REINFORCED Vtd 33.9 39.1 51.7 39.1 30.5 17.6
VEd - Vtd 170.3 217.7 160.1 168.9 194.2 159.1 Equation (6.1)
Asl 1810 1810 1810 1810 1810 1810
d 759.0 759.0 759.0 759.0 759.0 759.0
ρl 0.0068 0.0068 0.0068 0.0068 0.0068 0.0068
αcw 1.051 1.043 1.042 1.031 1.025 1.019
cotθ + tanθ 19.8171 15.4012 20.9079 19.6258 16.9632 20.5912
cotθ 2.5 2.5 2.5 2.5 2.5 2.5
VRd,max 1096 1103 1104 1115 1122 1128

vRdc 0.749 0.720 0.713 0.672 0.647 0.624


VRdc 198.9 191.2 189.4 178.6 172.0 165.9 Links required
Asw/S 0.354 0.354 0.354 0.354 0.354 0.354
S 425 425 425 425 425 425
Project Spreadsheets to EC2 REINFORCED CONCRETE COUNCIL
Client Advisory Group Made by Date Page
Location Level 2 - Beam on Grid 7 rmw 15-Nov-2021 275
POST-TENSIONED ANALYSIS & DESIGN to BS EN 1992-1:2004 Deflection calculations (2) Checked Revision Job No

Originated from TCC42.xls v4.0 on CD © 2005-21 TCC chg - FB625


SPAN 2 As(b) = 804 d = 759 h = 800 bw = 350 bf = 1200 hf = 150 bd3/12 = 1.5E+10
Distance 0 720 1440 2160 2880 3600 4320 5040 5760 6480 7200 7920 8640 9360 10080 10800 11520 12240 12960 13680 14400
Element b 360 720 720 720 720 720 720 720 720 720 720 720 720 720 720 720 720 720 720 720 360
d2 41 41 41 41 41 41 41 41 41 41 41 41 41 41 41 41 41 41 41 41 41
As(t) 1810 1810 1810 1810 1810 1810 1810 1407.43 1407.43 1407.43 1407.43 1407.43 1407.43 1407.43 1810 1810 1810 1810 1810 1810 1810
Transformed section properties at TRANSFER E = 31.91 m = 6.27 m - 1 = 5.27
A 421269 421269 421269 421269 421269 421269 421269 419151 419151 419151 419151 419151 419151 419151 421269 421269 421269 421269 421269 421269 421269
∑ A.Yt 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08
Yt 297.123 297.123 297.123 297.123 297.123 297.123 297.123 298.418 298.418 298.418 298.418 298.418 298.418 298.418 297.123 297.123 297.123 297.123 297.123 297.123 297.123
Yb 502.877 502.877 502.877 502.877 502.877 502.877 502.877 501.582 501.582 501.582 501.582 501.582 501.582 501.582 502.877 502.877 502.877 502.877 502.877 502.877 502.877
Ixx 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10
Transformed properties at 30 days E = 23.54 αe = 8.50 αe - 1 = 7.50
A 427094 427094 427094 427094 427094 427094 427094 424080 424080 424080 424080 424080 424080 424080 427094 427094 427094 427094 427094 427094 427094
∑ A.Yt 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08
Yt 296.643 296.643 296.643 296.643 296.643 296.643 296.643 298.461 298.461 298.461 298.461 298.461 298.461 298.461 296.643 296.643 296.643 296.643 296.643 296.643 296.643
Yb 503.357 503.357 503.357 503.357 503.357 503.357 503.357 501.539 501.539 501.539 501.539 501.539 501.539 501.539 503.357 503.357 503.357 503.357 503.357 503.357 503.357
Ixx 2.7E+10 2.7E+10 2.7E+10 2.7E+10 2.7E+10 2.7E+10 2.7E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.6E+10 2.7E+10 2.7E+10 2.7E+10 2.7E+10 2.7E+10 2.7E+10 2.7E+10
Transformed section properties - LONGTERM E = 12.79 m = 15.64 m - 1 = 14.64
A 445754 445754 445754 445754 445754 445754 445754 439869 439869 439869 439869 439869 439869 439869 445754 445754 445754 445754 445754 445754 445754
∑ A.Yt 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08 1.3E+08
Yt 295.19 295.19 295.19 295.19 295.19 295.19 295.19 298.591 298.591 298.591 298.591 298.591 298.591 298.591 295.19 295.19 295.19 295.19 295.19 295.19 295.19
Yb 504.81 504.81 504.81 504.81 504.81 504.81 504.81 501.409 501.409 501.409 501.409 501.409 501.409 501.409 504.81 504.81 504.81 504.81 504.81 504.81 504.81
Ixx 2.9E+10 2.9E+10 2.9E+10 2.9E+10 2.9E+10 2.9E+10 2.9E+10 2.8E+10 2.8E+10 2.8E+10 2.8E+10 2.8E+10 2.8E+10 2.8E+10 2.9E+10 2.9E+10 2.9E+10 2.9E+10 2.9E+10 2.9E+10 2.9E+10
Cracked section properties - LONGTERM bt = 912 bt = 846
bc - bw 0 0 850 850 850 850 850 850 850 850 850 850 850 850 850 850 850 0 0 0 0
bt - bw 850 850 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 846 846 846 846
Flange centre 725 725 75 75 75 75 75 75 75 75 75 75 75 75 75 75 75 725 725 725 725
As 1810 1810 804 804 804 804 804 804 804 804 804 804 804 804 804 804 804 1810 1810 1810 1810
As2 804 804 1810 1810 1810 1810 1407 1407 1407 1407 1407 1407 1407 1407 1407 1810 1810 804 804 804 804
d 759 759 759 759 759 759 759 759 759 759 759 759 759 759 759 759 759 759 759 759 759
d2 41 41 41 41 41 41 41 41 41 41 41 41 41 41 41 41 41 41 41 41 41
Uncracked X 504.8 504.8 295.2 295.2 295.2 295.2 298.6 298.6 298.6 298.6 298.6 298.6 298.6 298.6 298.6 295.2 295.2 504.5 504.5 504.5 504.5
Uncracked I 2.9E+10 2.9E+10 2.9E+10 2.9E+10 2.9E+10 2.9E+10 2.8E+10 2.8E+10 2.8E+10 2.8E+10 2.8E+10 2.8E+10 2.8E+10 2.8E+10 2.8E+10 2.9E+10 2.9E+10 2.9E+10 2.9E+10 2.9E+10 2.9E+10
Cracked X (w) 257.8 257.8 108.8 108.8 108.8 108.8 110.8 110.8 110.8 110.8 110.8 110.8 110.8 110.8 110.8 108.8 108.8 257.8 257.8 257.8 257.8
Cracked X (f) 257.8 257.8 84.6 84.6 84.6 84.6 85.8 85.8 85.8 85.8 85.8 85.8 85.8 85.8 85.8 84.6 84.6 257.8 257.8 257.8 257.8
Cracked X 257.8 257.8 84.6 84.6 84.6 84.6 85.8 85.8 85.8 85.8 85.8 85.8 85.8 85.8 85.8 84.6 84.6 257.8 257.8 257.8 257.8
Cracked I 9.7E+09 9.7E+09 6E+09 6E+09 6E+09 6E+09 6E+09 6E+09 6E+09 6E+09 6E+09 6E+09 6E+09 6E+09 6E+09 6E+09 6E+09 9.7E+09 9.7E+09 9.7E+09 9.7E+09
σp 1.016 1.003 0.990 0.990 0.978 0.965 0.952 0.952 0.939 0.926 0.913 0.900 0.888 0.876 0.852 0.840 0.828 0.816 0.804 0.792 0.792
Mcr 439.5 438.2 255.5 255.5 254.8 254.1 251.7 251.7 250.9 250.2 249.5 248.8 248.1 247.4 246.0 247.0 246.3 419.2 418.1 416.9 416.9
Deflections at TRANSFER
M (SLS 1) 37.8 67.1 55.4 25.0 -1.8 -24.9 -44.4 -60.2 -72.4 -80.9 -85.9 -87.1 -84.8 -78.8 -69.2 -55.9 -39.0 -18.4 5.7 11.3 -24.2
1/R 4.6E-08 8.1E-08 6.7E-08 3E-08 -2E-09 -3E-08 -5E-08 -7E-08 -9E-08 -1E-07 -1E-07 -1E-07 -1E-07 -1E-07 -8E-08 -7E-08 -5E-08 -2E-08 6.9E-09 1.4E-08 -3E-08
Load 1.6E-05 5.8E-05 4.8E-05 2.2E-05 -2E-06 -2E-05 -4E-05 -5E-05 -6E-05 -7E-05 -8E-05 -8E-05 -7E-05 -7E-05 -6E-05 -5E-05 -3E-05 -2E-05 5E-06 9.8E-06 -1E-05
Load x dist 0.00296 0.04198 0.06929 0.04688 -0.0044 -0.0779 -0.1666 -0.2651 -0.3644 -0.4584 -0.5403 -0.6032 -0.6403 -0.6446 -0.606 -0.5247 -0.3904 -0.1962 0.06473 0.134 -0.1456
End slope -0.0002 -0.0004
Span Δ 0 -0.14 -0.33 -0.55 -0.79 -1.03 -1.25 -1.44 -1.60 -1.71 -1.77 -1.78 -1.73 -1.62 -1.47 -1.28 -1.05 -0.79 -0.52 -0.26 0
Cant Δ 0 -5.15 -5.07 -5.03 -5.01 -4.98 -4.94 -4.87 -4.76 -4.61 -4.40 -4.15 -3.83 -3.47 -3.05 -2.59 -2.10 -1.58 -1.05 -0.52 0
Δ 0 -0.14 -0.33 -0.55 -0.79 -1.03 -1.25 -1.44 -1.60 -1.71 -1.77 -1.78 -1.73 -1.62 -1.47 -1.28 -1.05 -0.79 -0.52 -0.26 0
Deflections at 30 days
M -56.0 -12.4 -5.8 -17.1 -27.1 -35.8 -43.1 -49.1 -53.8 -57.1 -59.1 -59.8 -59.2 -57.2 -53.9 -49.2 -43.2 -35.9 -27.3 -39.0 -92.7
1/R -9E-08 -2E-08 -9E-09 -3E-08 -4E-08 -6E-08 -7E-08 -8E-08 -9E-08 -9E-08 -1E-07 -1E-07 -1E-07 -9E-08 -9E-08 -8E-08 -7E-08 -6E-08 -4E-08 -6E-08 -1E-07
Load -3E-05 -1E-05 -7E-06 -2E-05 -3E-05 -4E-05 -5E-05 -6E-05 -6E-05 -7E-05 -7E-05 -7E-05 -7E-05 -7E-05 -6E-05 -6E-05 -5E-05 -4E-05 -3E-05 -4E-05 -5E-05
Load x dist -0.0058 -0.0102 -0.0096 -0.0425 -0.0898 -0.1481 -0.2142 -0.2868 -0.3589 -0.4288 -0.4932 -0.5488 -0.5921 -0.6199 -0.6242 -0.6111 -0.5726 -0.5055 -0.4065 -0.6132 -0.7388
End slope -0.0004 -0.0006
Span Δ 0 -0.30 -0.59 -0.86 -1.13 -1.37 -1.59 -1.76 -1.90 -1.99 -2.04 -2.03 -1.98 -1.87 -1.72 -1.52 -1.29 -1.01 -0.71 -0.39 0
Cant Δ 0 -7.83 -7.71 -7.60 -7.47 -7.31 -7.13 -6.91 -6.65 -6.35 -6.00 -5.60 -5.15 -4.65 -4.10 -3.51 -2.87 -2.20 -1.50 -0.78 0
Δ 0 -0.30 -0.59 -0.86 -1.13 -1.37 -1.59 -1.76 -1.90 -1.99 -2.04 -2.03 -1.98 -1.87 -1.72 -1.52 -1.29 -1.01 -0.71 -0.39 0
Deflections - LONGTERM
M (SLS 4) -139.6 -50.6 0.5 30.5 56.3 77.7 94.8 107.6 116.2 120.4 120.3 115.9 107.2 94.2 76.8 55.2 29.3 -0.9 -35.5 -91.1 -184.6
M (SLS 10) -104.6 -33.1 2.3 18.5 32.3 43.7 52.6 59.0 63.1 64.7 63.8 60.5 54.8 46.7 36.1 23.0 7.5 -10.4 -30.7 -70.3 -145.9
ζ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Final I 2.9E+10 2.9E+10 2.9E+10 2.9E+10 2.9E+10 2.9E+10 2.8E+10 2.8E+10 2.8E+10 2.8E+10 2.8E+10 2.8E+10 2.8E+10 2.8E+10 2.8E+10 2.9E+10 2.9E+10 2.9E+10 2.9E+10 2.9E+10 2.9E+10
1/R -3E-07 -9E-08 6.3E-09 5.1E-08 8.8E-08 1.2E-07 1.5E-07 1.6E-07 1.7E-07 1.8E-07 1.8E-07 1.7E-07 1.5E-07 1.3E-07 1E-07 6.3E-08 2.1E-08 -3E-08 -8E-08 -2E-07 -4E-07
Load -0.0001 -7E-05 4.5E-06 3.6E-05 6.3E-05 8.6E-05 0.0001 0.00012 0.00013 0.00013 0.00013 0.00012 0.00011 9.3E-05 7.2E-05 4.5E-05 1.5E-05 -2E-05 -6E-05 -0.0001 -0.0001
Load x dist -0.0185 -0.0468 0.00654 0.0786 0.18274 0.30861 0.45196 0.59217 0.72297 0.83388 0.91441 0.9541 0.94245 0.86898 0.72322 0.48804 0.17057 -0.2495 -0.7826 -1.8901 -1.987
End slope 0.00049 0.00023
Span Δ 0 0.41 0.88 1.35 1.80 2.20 2.53 2.80 2.97 3.06 3.06 2.96 2.77 2.51 2.18 1.80 1.39 0.96 0.55 0.19 0
Cant Δ 0 3.51 3.82 4.13 4.41 4.65 4.82 4.92 4.93 4.86 4.69 4.43 4.08 3.65 3.16 2.62 2.04 1.45 0.88 0.35 0
Δ 0 0.41 0.88 1.35 1.80 2.20 2.53 2.80 2.97 3.06 3.06 2.96 2.77 2.51 2.18 1.80 1.39 0.96 0.55 0.19 0
Deflections - after construction
Δ 0 0.71 1.47 2.22 2.93 3.57 4.12 4.56 4.88 5.05 5.09 4.99 4.75 4.39 3.90 3.33 2.68 1.98 1.27 0.58 0
Project Spreadsheets to EC2 The Concrete Centre
Client Advisory Group Made by Date
Location Level 2 - Beam on Grid 7 rmw 15-Nov-2021
Graphics
POST-TENSIONED ANALYSIS & DESIGN to BS EN 1992-1:2004 Checked Revision Job No

Originated from TCC42.xls v4.0 on CD © 2005-21 TCC chg - FB625


GEOMETRY -306.44
BEAM X 0 0 0 16000 16000 16000 16000 30400 30400 30400 30400 44200 44200 44200
BEAM Y -306.4 0 0 0 -306.44 0 0 0 -306.44 0 0 0 -306.44 0
C SECa X 0 0 0 0 0 16000 16000 16000 16000 16000 30400 30400 30400 30400 30400 44200 44200 44200 44200 44200
C SECa Y 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500
C SECb X 0 0 0 0 0 16000 16000 16000 16000 16000 30400 30400 30400 30400 30400 44200 44200 44200 44200 44200
C SECb Y -806.4 -806.44 -806.44 -806.44 -806.44 -806.44 -806.44 -806.44 -806.44 -806.438 -806.44 -806.44 -806.44 -806.44 -806.44 -806.44 -806.44 -806.44 -806.44 -806.44
B SEC X 7400 8600 8600 8175 8175 7825 7825 7400 7400 22600 23800 23800 23375 23375 23025 23025 22600 22600 36700 37900 37900 37475 37475 37125 37125 36700 36700
B SEC Y -1500 -1500 -1650 -1650 -2300 -2300 -1650 -1650 -1500 -1500 -1500 -1650 -1650 -2300 -2300 -1650 -1650 -1500 -1500 -1500 -1650 -1650 -2300 -2300 -1650 -1650 -1500

LOADING scaling factor 35.28


UDL X 0 0 16000 16000 16000 16000 30400 30400 30400 30400 44200 44200
DEAD 0 432.47 432.47 0 0 432.465 432.465 0 0 432.465 432.465 0
IMPOSED 432.47 750 750 432.465 432.465 750 750 432.465 432.465 750 750 432.465
PUD X 0 0 0 0 16000 16000 16000 16000 30400 30400 30400 30400
PUD D 750 750 750 750 750 750 750 750 750 750 750 750
PUD L 750 750 750 750 750 750 750 750 750 750 750 750
PL X 0 0 0 0 16000 16000 16000 16000 30400 30400 30400 30400
PLs D 750 750 750 750 750 750 750 750 750 750 750 750
PLs L 750 750 750 750 750 750 750 750 750 750 750 750
DRAPE AXES
STRESS DIAGRAMS X 0.00 16.00 16.00 30.40 30.40 44.20 44.20 0 0 16 16 30.4 30.4 44.2 44.2
Balance scaling = 1 x profile Top 800 800 800 800 800 800 800 880.00 -80 880 -80 880 -80 880 -80
n/a 501.69 501.69 501.69 501.69 501.69 501.69 501.69 16 0 16 0 16 0 16 0
Vl Vr W1 we Vl Vr W1 we Vl Vr W1 we 56.9957 -18.13 56.9957 -18.135 56.9957 -18.135 56.9957 -18.135
83.89 112.23 68.51 -12.56 86.39 90.12 85.39 -14.83 96.48 72.68 50.96 -8.05
71.31 91.69 80.56 -14.77 69.04 77.66 99.10 -17.20 78.69 61.89 57.45 -9.07
141.39 198.73 61.42 -11.26 155.44 150.67 74.61 -12.95 171.32 122.04 43.11 -6.81
148.13 191.99 61.42 -11.26 91.42 85.08 74.61 -12.95 162.69 130.66 43.11 -6.81
79.76 116.36 61.42 -11.26 149.93 156.18 74.61 -12.95 102.94 66.21 43.11 -6.81
SPAN 1

SPAN 2

SPAN 3

123.97 172.95 61.42 -11.26 134.85 132.38 74.61 -12.95 149.05 107.04 43.11 -6.81
129.06 167.86 61.42 -11.26 90.08 86.43 74.61 -12.95 142.53 113.56 43.11 -6.81
81.41 114.71 61.42 -11.26 130.68 136.55 74.61 -12.95 100.84 68.31 43.11 -6.81
118.16 164.36 61.42 -11.26 127.98 126.28 74.61 -12.95 141.63 102.04 43.11 -6.81
122.70 159.82 61.42 -11.26 89.63 86.88 74.61 -12.95 135.81 107.86 43.11 -6.81
81.95 114.17 61.42 -11.26 124.27 130.00 74.61 -12.95 100.14 69.02 43.11 -6.81
194.57 266.33 61.42 -11.26 211.79 203.03 74.61 -12.95 229.69 167.84 43.11 -6.81
194.70 266.20 61.42 -11.26 118.10 102.32 74.61 -12.95 225.87 171.66 43.11 -6.81
91.58 153.32 61.42 -11.26 206.86 207.96 74.61 -12.95 135.88 75.35 43.11 -6.81
TypiCalc!
SPAN 1 0.8 Btm 0 0 0 0 0 0 0 20 0 20 0 20 0 20 0
X 0 0 0 0 0.8 1.6 1.6 2.4 3.2 4 4.80 5.6 6.4 7.2 8 8.8 9.6 10.4 11.2 12 12.8 13.6 14.4 14.4 15.2 16 16 0 16 7.200 7.200 6.400 6.400 6.400
profile X 0 0.8 1.6 1.6 2.4 3.2 4 4.8 5.6 6.4 7.2 8 8.8 9.6 10.4 11.2 12 12.8 13.6 14.4 14.4 15.2 16 16 7.200 7.200 6.400 6.400 6.400
PROFILE 501.0 501.0 501.0 501.0 474.9 396.7 396.7 300.0 218.7 152.6 101.8 66.3 46.1 41.2 51.7 77.4 118.4 174.7 246.2 333.1 435.3 552.8 685.6 685.6 790.9 826.0 826.0 41.2 41.2 46.1 46.1 46.1
BALANCE 0.00 0.00 0.00 38.39 38.39 38.39 -11.26 -11.26 -11.26 -11.26 -11.26 -11.26 -11.26 -11.26 -11.26 -11.26 -11.26 -11.26 -11.26 -11.26 -11.26 -11.26 -11.26 51.68 51.68 51.68 0.00
Beam 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
30 days 0 0 0 0 -49.486 -63.724 -63.724 -60.434 -57.335 -54.428 -51.7137 -49.191 -46.86 -44.72 -42.773 -41.017 -39.454 -38.082 -36.902 -35.913 -35.117 -34.512 -34.1 -34.1 -8.1698 68.9862 0.00 56.00
M-SLS 1 0 0 0 0 -37.679 -36.613 -36.613 -17.639 -1.5958 11.5163 21.6976 28.948 33.2675 34.6562 33.114 28.641 21.2371 10.9023 -2.3633 -18.56 -37.687 -59.745 -84.734 -84.734 -86.238 -37.841 34.6562 7.2 0.00 -37.84 34.6562
M-SLS 2 0 0 0 0 -94.029 -149.89 -149.89 -183.46 -210.63 -231.4 -245.769 -253.74 -255.31 -250.49 -239.26 -221.63 -197.6 -167.18 -130.35 -87.124 -37.498 18.5277 80.953 80.953 169.917 305.558 0.00 305.56 -250.49
M-SLS 3 0 0 0 0 -99.416 -160.66 -160.66 -199.62 -232.17 -258.33 -278.087 -291.44 -298.4 -298.96 -293.12 -280.88 -262.24 -237.2 -205.76 -167.92 -123.68 -73.038 -15.999 -15.999 67.5783 197.834 -298.96 7.2 0.00 197.83 -298.96
M-SLS 4 0 0 0 0 -47.606 -62.798 -62.798 -61.465 -59.492 -56.879 -53.6268 -49.735 -45.203 -40.031 -34.22 -27.769 -20.678 -12.947 -4.5771 4.43285 14.0825 24.3719 35.301 35.301 67.0087 139.634 0.00 139.63 -40.031
M-SLS 5 0 0 0 0 -80.951 -125.46 -125.46 -149.4 -168.68 -183.28 -193.217 -198.48 -199.07 -194.98 -186.23 -172.8 -154.71 -131.94 -104.49 -72.382 -35.597 5.85948 51.9876 51.9876 122.926 238.815 0.00 238.81 -199.07
M-SLS 6 0 0 0 0 -85.023 -133.6 -133.6 -161.62 -184.97 -203.65 -217.652 -226.98 -231.65 -231.64 -226.95 -217.6 -203.58 -184.88 -161.51 -133.47 -100.76 -63.373 -21.318 -21.318 45.5484 157.364 -231.65 6.4 0.00 157.36 -231.65
M-SLS 7 0 0 0 0 -48.919 -65.426 -65.426 -65.406 -64.747 -63.448 -61.5091 -58.931 -55.712 -51.854 -47.357 -42.219 -36.442 -30.026 -22.969 -15.273 -6.937 2.03866 11.654 11.654 42.0481 113.36 0.00 113.36 -55.712
M-SLS 8 0 0 0 0 -76.591 -117.31 -117.31 -138.05 -154.7 -167.25 -175.699 -180.06 -180.32 -176.48 -168.55 -156.53 -140.41 -120.19 -95.876 -67.468 -34.963 1.63675 42.3325 42.3325 107.263 216.567 0.00 216.57 -180.32
M-SLS 9 0 0 0 0 -80.226 -124.58 -124.58 -148.96 -169.24 -185.42 -197.507 -205.5 -209.39 -209.19 -204.9 -196.51 -184.02 -167.44 -146.76 -121.99 -93.117 -60.152 -23.091 -23.091 38.2051 143.874 -209.39 6.4 0.00 143.87 -209.39
M-SLS 10 0 0 0 0 -49.357 -66.302 -66.302 -66.72 -66.499 -65.637 -64.1365 -61.996 -59.216 -55.796 -51.736 -47.036 -41.697 -35.718 -29.1 -21.842 -13.943 -5.4057 3.77173 3.77173 33.7278 104.602 0.00 104.60 -59.216
M-ULS 1 0 0 0 0 -134.16 -225.31 -225.31 -289.35 -342.15 -383.72 -414.067 -433.18 -441.06 -437.71 -423.13 -397.31 -360.27 -311.99 -252.49 -181.75 -99.781 -6.5809 97.85 97.85 233.651 420.961 0.00 420.96 -441.06
M-ULS 2 0 0 0 0 -134.26 -225.52 -225.52 -289.66 -342.57 -384.25 -414.694 -433.91 -441.89 -438.65 -424.17 -398.46 -361.52 -313.35 -253.95 -183.32 -101.45 -8.3573 95.969 95.969 231.665 418.871 -441.89 6.4 0.00 418.87 -441.89
M-ULS 3 0 0 0 0 -56.086 -77.807 -77.807 -81.051 -81.704 -79.765 -75.236 -68.116 -58.404 -46.101 -31.207 -13.722 6.35382 29.021 54.2793 82.1288 112.569 145.601 181.224 181.224 239.576 340.798 0.00 340.80 -58.404
Pi 617.9 617.9 617.9 617.9 617.9 617.9 617.9 617.9 617.9 617.9 616.5 609.0 601.5 594.0 586.4 578.9 571.4 563.9 556.4 548.8 548.8 541.3 533.8 616.5 616.5 617.9 617.9 617.9
Pf 549.5 549.9 550.3 550.3 550.6 551.0 551.4 551.8 552.1 552.5 551.5 544.2 536.9 529.5 522.2 514.9 507.6 500.3 492.9 485.6 485.6 478.3 471.0 551.5 551.5 552.5 552.5 552.5
C top @ trans 0 1.516 1.516 1.516 1.976 1.963 1.963 1.732 1.536 1.376 1.251 1.163 1.110 1.090 1.090 1.126 1.198 1.306 1.450 1.629 1.844 2.095 2.382 2.382 2.382 1.772 1.090
C btm @ trans 0 1.516 1.516 1.516 0.742 0.764 0.764 1.154 1.483 1.753 1.962 2.111 2.200 2.225 2.175 2.064 1.894 1.663 1.372 1.021 0.610 0.138 0.000 0.000 0.000 0.533 2.225
T top @ trans 0 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
T btm @ trans 0 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 1.574 1.574 1.771 0.000 0.000
C top, final 0 1.349 1.349 1.349 2.329 2.872 2.872 3.170 3.419 3.618 3.766 3.865 3.913 3.908 3.838 3.717 3.547 3.326 3.056 2.735 2.365 1.944 1.474 1.474 0.762 0.000 1.353 1.356 3.913 1.356
C btm, final 0 1.349 1.349 1.349 0.336 0.000 0.000 0.000 0.000 0.005 0.037 0.082 0.140 0.207 0.273 0.351 0.443 0.548 0.666 0.797 0.941 1.243 2.061 2.061 3.377 5.604 1.353 1.356 0.140 1.356
T top, final 0 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 1.310 7.044 0.000 0.000 0.000 0.000
T btm, final 0 0.000 0.000 0.000 1.587 5.575 5.575 7.873 9.788 11.318 12.465 13.228 13.608 13.617 13.304 12.608 11.527 10.063 8.215 5.983 3.367 0.368 0.000 0.000 0.000 0.000 0.000 13.608 0.000 0.000
C top, ULS 0 1.483 1.483 1.483 3.124 4.240 4.240 5.024 5.671 6.181 6.554 6.790 6.888 6.846 6.649 6.316 5.845 5.237 4.491 3.609 2.589 1.433 0.139 0.139 0.000 0.000 6.753
C btm, ULS 0 1.483 1.483 1.483 0.332 0.000 0.000 0.000 0.000 0.000 0.000 0.091 0.292 0.542 0.828 1.167 1.560 2.006 2.505 3.057 3.662 4.321 5.033 5.033 6.212 9.917 0.156
T top, ULS 0 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 1.080 2.758 4.563 4.563 7.478 16.404 0.000
T btm, ULS 0 0.000 0.000 0.000 6.173 13.667 13.667 18.933 23.276 26.697 29.195 30.771 31.423 31.166 30.041 27.993 25.023 21.130 16.315 10.577 3.916 0.000 0.000 0.000 0.000 0.000 7.720
National Annex values - BS EN 1992-1
EC2 Ref Function Value National Annex values - BS EN 1990
2.4.2.2 (1) γp,fav 0.9 TABLE A1.1 ψ0 ψ1 ψ2
2.4.2.2 (2) γp,unfav 1.1 A 0.7 0.5 0.3
Table 2.1 γc 1.5 concrete B 0.7 0.5 0.3
Table 2.1 γs 1.15 steel C 0.7 0.7 0.6
3.1.6 (1)P αcc 0.85 strength factor (flexure) D 0.7 0.7 0.6
3.1.6 (1)P αcc 1.00 strength factor (shear) E 1 0.9 0.8 1
3.1.6 (2)P αct 1.00 -=- F 0.7 0.7 0.6
3.3.4 (5) K 1.1 fpk /fp0.1k G 0.7 0.5 0.3
5.1.2 (1)PPattern loading b alternate & all spans H 0.5 0.2 0
5.5(4) k1 0.4 redistribution factor J 0 0 0 1
-=- k2 a 1 a(b+c/εcu2)
-=- k2 b 0.6 -=- γG,sup 1.35 dead load factor
-=- k2 c 0.0014 -=- γG,inf 1 dead load factor
-=- k3 0.4 redistribution factor γQ 1.5 imposed load factor
-=- k4 a 1 a(b+c/εcu2) Allow 6.10a & b? Yes loading equations
-=- k4 b 0.6 -=- ξ 0.925Gk modification factor
-=- k4 c 0.0014 -=-
-=- k5 0.7 redistribution factor
-=- k6 0.8 redistribution factor
5.10.2.1 K1 0.8 σp,max
-=- K2 0.9 σp,max
5.10.8 (2) Δσp,ULS 100 prestress reduction at ULS
6.2.2 (1) CRd,c 0.18 basic shear stress 0.12
-=- vmin 0.035 x k3/2fck1/2
-=- k1 0.15 prestress factor
6.2.3(2) cotØmin/max 1 ←max/min strut angle→2.5
6.2.3(3) αcw 1 for VRdmax
7.2(5) k3 1 max steel stress
9.2.2(6) St,max 0.75 xd
12.6.3 (2) k 1.5 torsional factor

TABLE 7.1N Values of Wmax


Exposure class Unbonded Bonded
X0, XC1 0.3 0.2 0.2
XC2, XC3, XC4 0.3 0.2 0.2
XD1, XD2, XS1, XS2, XS3 0.3 0 0
Loading equation select ψ0 = 0.7

Span 1 2 3
Gk 196.1 176.5 169.2
Qk 144.0 129.6 124.2
6.10a 416.0 374.4 358.8 1149.095 Dead 1.24875 b
6.10b 460.9 414.8 397.5 1273.25 Imposed 1.5 a
Checks 0 0 0 0
BS EN 1990: (6.10b)
.
Disclaimer
All advice or information from MPA-The Concrete Centre is intended for those who will evaluate the
significance and limitations of its contents and take responsibility for its use and application. No liability
(including that for negligence) for any loss resulting from such advice or information is accepted by
MPA-The Concrete Centre or its subcontractors, suppliers or advisors. Users should note that all MPA-
The Concrete Centre software and publications are subject to revision from time to time and they
should therefore ensure that they are in possession of the latest version.

This spreadsheet should be used in compliance with the accompanying publication 'User Guide RC
Spreadsheets: v4' available from The Concrete Centre www.concretecentre.com/rcdesign Tel +44
(0)1276 606800

Status of spreadsheet This spreadsheet is shareware but may not be used for commercial purposes until
the user has registered with The Concrete Centre using the licence validation form
Public release version available on The Concrete Centre website www.concretecentre.com/rcdesign

Revision history TCC42 Post tensioned Analysis & Design


Date Version Action Size (kB)
25-Mar-10 TCC42 v4.0 Updated to revised UK National Annex 2332
7-Dec-09 TCC42 v3.2 Correction to minimum ULS support moments. 2323
3-Sep-07 TCC42 v3.1 Correction to ψ2 for vehicular useage. 2301
6-Feb-07 TCC42 vβ8 Improvement to loss calculations. 2305
4-Jan-07 TCC42 vβ7 Enablement of negative partial UDLs. 2357
Improvement to vibration checks when slabs selected. Included
28-Jun-06 TCC42 vβ6 in v3 release. Page nos, User Guide and registration details 2230
amended.
Various minor improvents and de-bugs during ECFE data
29-Apr-06 TCC42 vβ5 2316
generation.
22-Mar-06 TCC42 vβ4 65% of centreline moment limit added to ULS design. 2315
7-Mar-06 TCC42 vβ3 Separate αcc value added for shear. 2321
Tool tips added for beff, heff and column end conditions. Level of
6-Mar-06 TCC42 vβ2 prestress (Pi/A) added. Correction to switch for stressing at left, 2318
right or both ends.
19-Oct-05 TCC42 vβ1 First β version for comment. 2411