Professional Documents
Culture Documents
(B+G+1+Terrace)
AT
Leqtaifiya
May 2017
Section 19 PLUMBING SYSTEM
TABLE OF CONTENTS
PART/CLAUSE TITLE PAGE
1. GENERAL ............................................................................................................................... 1
SECTION 19
PLUMBING WORKS
1. GENERAL
The scope of works covered by this specification shall include the whole of the labor &
materials necessary to form “ Complete Installation “ of plumbing, irrigation, waste and
drainage systems & such commissioning and testing as described in QCS Section 19,
(Plumbing Work) and QCS 20 ( Drainage Work for Buildings )
The Scope of Work shall include the following:
1. Cold water and hot water system for the buildings as shown in the drawings.
The installation, materials, and all components shall comply with all statutory instructions
and Regulations current at the time of the tender whether so detailed or not, and shall
conform in all respects with the following:
1. Qatar Construction Specifications
2. Safety Health & Welfare Regulations issued by the State of Qatar
Should any conflict arise between the codes and the standards mentioned above, then the
Regulations issued by the State of Qatar shall take precedence.
All above the ground cold & hot water pipe work within the buildings inside shafts, on roof
etc., shall be in copper tube to BS 2871 or EN 1057 Part 1 Table ‘ X ‘ All fittings shall be of
the capillary or compression type to BS 869: Part 2 Manufactured from even metal,
copper or dezincification resistance brass.
The copper tube shall be to BS 2871 or EN 1057 Part 1 Table ‘ Y ‘ externally coated over
entire length with a continuous seamless Polythene sheathing for cold water piping. The
colour of the Sheathing shall be green as per BS 4800 Ref: 12 D 45. For hot water piping
the sheathing shall be polythene with air channels on the internal surface. Joints shall be
carefully wrapped with PVC waterproof tape to maintain protective coating.
The copper tubes shall comply with the following specifications with regard to the sizes:
Outside
Nominal size (mm) Nominal Wall thickness of
Diameter (mm)
sheathing (mm)
Min Max Min
2.1.3 Cold & Hot Water supply – Inside toilet areas / pantries / below false ceiling.
Cold and hot water supply within each plumbing zones in a building to individual plumbing
fixtures shall be through PP-R pipes DIN 8077.All pipes which runs below floor slab or
concealed, in toilet, pantry and other wet areas of pipe sizes as shown on the drawings
shall be PP-R pipes DIN 8077. All accessories and fittings shall be made of Gunmetal.
The jointing of copper pipe work shall be by means of dezincification resistant integral
solder ring. Bronze welding will not be permitted.
All pipe work; fittings & accessories shall be installed strictly in accordance with the
manufacturers recommendations and due allowance shall be made for thermal
movement.
All pipe work; fittings & accessories shall be obtained from one manufacturer only, who
shall be nominated by the contractor in writing and approved by the Engineer prior to
ordering any Materials. All pipe work; fittings & accessories shall be stored in properly
ventilated & well-supported racked storage sheds.
All pipe work shall be installed to present a neat & orderly appearance arranged to or at
right angles to the structural member of the building, giving maximum headroom and not
obstructing window or doorways. Pipes shall bend round piers, projections and recesses
forming part of the structural works whether indicated in the drawing or not. Pipe work
shall be installed such that there is a minimum of 150mm clear below to the finished floor
level & at least 25mm clear to the finished wall face.
All pipe work, which is to be insulated, shall allow space for each pipe to be insulated
around its whole circumference. Adequate clearance shall be provided between insulated
pipe work running together adjacent to walls & floors. Clearance between insulation and
floor wall shall be as for bare pipe work.
No joints shall be formed in the thickness of floor slabs or roof slabs. No pipe work shall
be chased into floor or roof slabs. During the installation period open ends of pipe work
shall be capped off using purpose made plugs or blank counter flanges.
All pipe work shall be plumb in the vertical and leveled to the turn of a bubble in the
horizontal, except where wall or floor finishes deviate from the vertical or horizontal, all
pipe work shall be erected such that it may be vented and drained satisfactorily.
Swing joints, offsets, expansion joints etc., shall be provided wherever necessary to
accommodate expansion of piping.
Unions or flanges shall be provided at all by–passes, tanks, heaters, pumps and
elsewhere as may be required.
Expansion joints shall be placed in all pipes where they cross building expansion joints.
The contractor shall check all plumbing layouts with structural drawings.
All pipe work, valves and fittings & other components forming the installation shall be such
that they are accessible for maintenance and repairs. Unions and flanges shall be
provided as appropriate in order to allow for equipment removal.
All exposed pipe work in toilets, etc., shall be painted (minimum 2 coats) matching with
the tiles as per the instructions of the Engineer.
2.2.3 Pipe Supports, Brackets & Hangers
All pipe work shall be adequately supported in such a manner as to permit free movement
due to expansion, contractions, vibrations or other changes in the system. Supports shall
be arranged as near as possible to the joints and changes of direction. Spacing of support
shall comply with Table 13 of BS 5572:1978. Vertical rising pipes particularly in shafts
shall be adequately supported at the base to withstand the total weight of the riser. Under
no circumstances shall branches from vertical rising pipes be the means of support for the
vertical pipe work.
Pipe work up to and including 67mm diameter shall be supported clear of the structure
with cast brass brackets. Where exposed to view, bright finish brass hospital brackets
shall be used with crawl plugs and brass screws.
Where pipe work is concealed, bright finish brass single pipe ring with BSP female
screwed end and bright finish brass pack plate with male screwed end shall be used and
fixed to the wall using brass screws & crawl plugs.
All multi runs of pipe work within false ceilings or service shafts shall be supported on
purpose designed proprietary brackets suitable for carrying more than one pipe run, and
shall be secured using expanded plugs or other purpose designed fixing devices. Soft
wood plugs shall not be allowed. All-purpose designed proprietary brackets shall be
submitted to the Engineer for approval prior to ordering.
Where rollers and chairs are required, these shall be performed as manufactured by a
specialist approved by the Engineer, and where used singularly, they shall have
restraining U-bolts formed over the diameter of the pipe and bolted to the base support of
the chair. The “U” bolts shall be fitted to all movement of the pipe without binding.
All steel hangers & supporting brackets shall be painted with two coats of red oxide before
dispatch from the works. The spacing of supports where not specified must not exceed
the spacing given in the following schedules. Where one support carries more than one
pipe diameter, the spacing shall be that specified for the smallest diameter.
15 1.8 1.2
22 2.4 1.8
28 2.4 1.8
35 3.0 2.1
42 3.0 2.1
54 3.0 2.4
67 3.6 2.4
Pipe sleeves shall be supplied where pipe work passes through walls, floors. Footings and
waterproofing membranes. Sleeves shall be built in the correct locations at the time
required, by the main contractor. The inside diameter of all sleeves shall not be less than
1.5mm larger than the outside diameter of the pipe passing through. Where pipes pass
through buried walls or fittings, sleeves shall be 25mm larger than the outside diameter of
the pipe passing through. The space between the pipe sleeves shall be neatly packed
using asbestos string or rope to prevent the passage of noise, vermin or smoke. Sleeves
shall not protrude beyond the finished surface, where pipe work is exposed to view and
passes through wall or floor, chromium plated copper pipe flanges of the correct pipe
diameter shall be fitted.
The pipe sleeves shall be in new concrete construction before pouring. Sleeves in
foundation wall shall make water tight installation. Sleeve through walls, floor and partition
walls shall be in copper sleeve, through outside wall shall be UPVC sleeve properly
caulked to ensure water tight joints. Pipe sleeve shall not be arranged to support the pipe
work.
All pipe work on the roof shall be installed with 25mm thick preformed rigid glass fiber
sections of 48 kg / cum
The insulation shall further be covered with 6 oz. canvas and painted with two coats of
vapour seal material of minimum thickness of 1mm. The thermal insulation shall be non –
corrosive to the metal, water repellant & fire retardant.
All sanitary ware shall be provided as shown on the drawing and approved by the
Engineer. Bibb with mixers, taps, valves or mixer taps shall be bronze or gun metal
castings or hot pressing of brass or manganese bronze and shall be chromium plated.
Spindles. Glands, crutches, washer plates and nuts shall be of brass or bronze. The taps
shall have crutch or capstan head made of metal, being marked hot or cold with tail
having external parallel thread. They shall be marked with manufacturer’s name or trade
mark.
The water supply connection to sanitary fittings shall be in the following sizes:
FIXTURES SIZE
Washbasin 15mm
Bidet 15mm
W.C. 15mm
Where pipe pass through water proofed membranes, sleeves shall be provided with a
flashing flange to which a flashing shield can be clamped or brazed. The shield shall be
zinc or copper and shall not be less than 200mm from the sleeve in all directions. The
space between the sleeve and the pipe passing through shall be packed with waterproof
material and mastic compound.
All pipe anchors shall be heavy gauge steel collars with lugs and bolts for clamping and
attaching to anchor braces. No anchor brace shall be installed in a location where its
installation may result in damage to the building structure. All anchors and guides shall be
submitted to the Engineer for his final approval prior to the installation.
2.2.7 Pipe work Expansion
Provision for pipe work expansion and contraction shall be made by changes in the
direction of pipe work. The supports and brackets provided give adequate allowance for
this movement. In certain cases expansion loops or expansion bellows shall be provided
in the position indicated in the drawings. These items shall be manufactured by a
specialist approved by the Engineer. All bellow shall be installed in accordance with the
manufacturer’s instructions.
2.3.1 General
All valves and stopcocks shall comply with the regulations of the Ministry of Electricity and
Water, Water Department and shall be dezincification resistant. Valves shall be provided
as shown on the drawings and detailed below or similar and approved, all valves shall be
submitted for approval to the Engineer and this should be obtained in writing prior to
ordering.
All valves, strainers and non-return valves shall be numbered clearly using white/black
‘Traffolyte‘ label securely fixed to the valve or valve handle. These labels shall indicate the
service and function of the valve. The exact wording shall be approved by the Engineer
prior to manufacture of the labels.
Once a manufacturer has been approved and selected all valves shall be of the same
manufacturer.
Isolating Valves
All valves shall be fitted in readily accessible positions. They shall be of even thickness
throughout, clean, smooth and free from scale. All stuffing boxes shall be packed with
material specially selected and recommended by the manufacturer for the particular
service in which each valve is used.
Non –Return valves shall be screwed BSPT or flange BS 4504: Part 2 in accordance with
the valve schedule in this specification. All non – return valves shall be suitable for both
vertical and horizontal mounting and shall be fitted in readily accessible positions.
Non-return valves shall be in-line spring loaded, swing design with lever and weight or
lever and spring.
Strainers
All strainers shall be fitted in a readily accessible position and adequate access shall be
allowed for maintenance and cleaning of the strainer basket. All strainers shall be
manufactured by specialists and have a stainless steel 80mm mesh screen basket.
Drain cocks
All drain cocks shall be of the same manufacturer and be in accordance with BS 2879.
Generally drain cocks shall be provided at all low points in the system and other points
where necessary and as directed by the Engineer.
Stopcock
All stopcock used shall be as per BS 1010 with all parts in contact with water made from
material resistant to dezincification (example ) Yorkshire 501 GM. The size shall be 15mm
– 65mm.
Float Valves
Float valves shall be hydraulically operated, diaphragm actuated valve with the pilot
control and float mechanism mounted on the cover of the main valve. The float positions
the pilot control and close the valve when float contacts the upper stop and to open the
valve when the floats contacts the lower stop.
BS 1212 Pattern II or
Ball Valves 15 – 54
Portsmouth
All sections of pipe work shall be hydraulically tested during the installation of the works to
avoid the necessity for disturbing the building programme at the later stages. No pipes
shall be insulated, covered or made inaccessible before they have been tested. All tests
are to be recorded and signed by the Contractor’s Senior Site representative and
witnessed by the Engineer or his representative.
All pipe work except open ended vents and drain pipes shall be tested to 700KN/sq m or
twice the working pressure whichever is greater, for a period of not less than four (4)
hours.
Following successful completion of the test, the pipe work shall be thoroughly flushed out
and all open ends carefully plugged to prevent the entry of any contamination.
It is the Contractor’s responsibility to see that the tests are correctly carried out and that
any necessary remedial measures are effected and the section retested, so that on
completion of the Works each and every section has been tested satisfactorily and a
complete set of test certificates has been forwarded to the Engineer.
3.1 GENERAL
Underground cold water services shall comply with British Standard Code of Practice CP
310: 1965, CP 2010: Part I: 1966 and CP 2010: Part 3: 1972.
Each type of pipe work material and associated fittings shall comply be obtained from one
Manufacturer only, who shall be nominated by the contractor in writing and approved by
the Engineer prior to ordering any materials.
3.2 JOINTING
The jointing of copper pipe work shall be by means of dezincification resistant integral
solder ring. Bronze welding shall not be permitted.
All pipework, fittings and accessories shall be stored in properly ventilated, well-supported
racked storage sheds.
All pipework, fittings and accessories shall be inspected prior to use and damaged
material shall be disposed off.
Protection shall be provided to the complete works as it proceeds to prevent impact
damage from debris. All open ends of all pipes and fittings shall be plugged to prevent the
ingress of debris and rubbish using temporary purpose made manufactured plugs or
flanges. Plastic sheets or paper bags shall not be used for plugging pipework fittings.
3.4 TRENCH EXCAVATION
The contractor shall be responsible for the stability of all excavations and any claim arising
from accident or damage to the public, adjoining property or labor on site. The contractor
shall provide all necessary steel sheeting, timber supports, strutting and shoring to the
complete satisfaction of the Engineer. Any slip or fall shall be immediately reported &
made good by the contractor at his own expense and the contractor shall take sole
responsibility for any claim for damages arising out of inadequate support of excavations.
All excavations shall be maintained dry and free from water. To achieve this the contractor
shall without additional charge, provide all necessary pumping equipment, sumps, and
drains The contractor shall also be responsible for operating, running and maintaining all
equipment at all times to ensure excavations are free from water.
All obstructions shall be broken out and voids and soft spots filled with concrete grade
C15 or as otherwise as directed by the Engineer at the contractor’s expense.
3.5 GRANULAR BEDDING
Pipework shall be laid on a granular bed with a minimum cover above the crown of the
pipe as follows:
1. Pipe lines: 600mm cover when there is no traffic on the ground above the pipeline
2. Pipe lines: 1000mm cover when there is traffic on the ground above the pipeline.
The granular bedding shall comprise of gravel, stone chippings or crushed stone to pass
through 12mm sieve and be retained on a minimum of 5mm sieve mixed with free draining
coarse sand, in the ratio of two parts of crushed stone to every part of sand. Bedding
material shall not contain more than 0.3% sulphate nor shall it be obtained from locations
0.1% sulphate is present in the ground water.
Bedding shall be laid 150mm deep along the length of the trench and compacted prior to
work commencing on the pipe laying. After pipe laying, inspection and testing, a further
300mm of bedding material shall be compacted by hand above the uppermost crown of
the pipe lines along its entire length. The bedding material shall span the entire width of
the trench and shall be laid in not more than 150mm deep layers, each layer being
compacted by hand.
All underground pipelines shall be laid to true levels in straight lines to even gradients.
Pipelines laying shall not commence until the Engineer has inspected and approved the
granular bed and trench. All pipes passing through walls and foundations shall have
sleeves with puddle flanges. The flanges shall not be less than 200 mm from sleeve in all
directions. The space between the sleeves and pipes passing through shall be packed
with waterproof material and mastic compound.
When slings are used, only flat braided steel wire or band slings shall be used.
The cutting of pipes shall be by hacksaw and all burrs shall be trimmed off by filing.
All pipelines shall be anchored with thrust bocks at dead ends, tees, bends, tapers and
valves to resist the thrust arising from internal pressure.
below 1 in 2 to 1 in 4 11.00
below 1 in 4 to 1 in 16.50
below 1 in 5 to 1 in 22.00
After completion of granular bed and surround, the trench shall be backfilled using
selected excavated Material free from all rocks, large hard objects and builders’ debris of
greater than 40mm and shall be in layers of 150mm, each fully compacted over the width
of the trench. Power rammers and vibrators shall be used to compact backfilling when the
cover over the crown of the pipe exceeds 0.50 meters.
Written notice shall be given at least 24hours in advance for the purpose of inspection,
measurement and testing for each of the following cases:
1. Setting out complete
2. Excavation complete
3. Bedding laid
5. Pipeline bedding cover complete and compacted between joints and backfilling as
necessary, complete and compacted between joints, ready for testing.
6. Joints, bedding cover complete and compacted and backfilling complete and
compacted with ground level finish, ready for final testing.
All sections of pipe work shall be hydraulically tested during the installation of the works to
avoid the necessity for disturbing the building programme at the later stages. No pipes
shall be insulated, covered or made inaccessible before they have been tested. All tests
are to be recorded and signed by the Contractor’s Senior Site representative and
witnessed by the Engineer or his representative.
All pipe work except open ended vents and drain pipes shall be tested to 700KN/sq m or
twice the working pressure whichever is greater, for a period of not less than four (4)
hours.
Following successful completion of the test, the pipe work shall be thoroughly flushed out
and all open ends carefully plugged to prevent the entry of any contamination.
It is the Contractor’s responsibility to see that the tests are correctly carried out and that
any necessary remedial measures are effected and the section retested, so that on
completion of the Works each and every section has been tested satisfactorily and a
complete set of test certificates has been forwarded to the Engineer.
Cold & hot water storage tanks installed at roof deck of buildings as shown on the
drawing shall be manufactured to BS 6920 (British Standard for drinking water
storage) and comply strictly with the standards of the Water Department of the State of
Qatar, guaranteed by the manufacturer for a minimum of seven (10) years.
Roof deck water storage tanks shall be constructed of polyethylene material with
manhole inspection cover and all connections as shown in the drawings.
The tanks shall be provided to the capacities, dimensions and locations shown on the
drawings shall not encourage the growth of algae, have a smooth internal surface single
piece body with no seams of joints or seamless.
Tank is to be fixed on a concrete plinth which supports the whole of the tank. The details
of the tank base are to be approved by the Engineer before any installation work begins.
Tanks shall be fitted with the following:
1. Electrical type float switch.
2. Overflow pipe one size larger than float valve supply pipe, with SS insect screen at
terminal.
3. Drain valve provided at the lowest bottom side of the tank
4. Cold water outlets.
5. Close fitting openings on top of the tank for float switches wiring.
6. Sealed manhole cover adjacent to float valve.
The whole of the installation shall be guaranteed for a period of 10 years. Any defect/
damage or leakage occurred during the guarantee period shall be made good by the
CONTRACTOR at no cost to the client.
Supply and install pressure booster sets where shown on drawings and in accordance
with the schedule of equipment furnished. The booster sets shall be of horizontal closed
coupled end-suction type.
The packaged domestic water pressure booster set factory assembled system installed at
roof deck of the buildings as shown on the drawing shall consist of a structural base,
pumps, motors, suction & discharge headers, valves, flexible connectors, pressure
vessel, control panel, pressure outlets and necessary interconnecting piping.
Booster pump set shall be installed to pressurized water services. The unit shall be
complete with air vessel, control panel, interconnecting pipework, suction and discharge
headers, valves, flexible connectors electrical wiring etc. fixed to a single base plate.
All pumps shall be high efficiency closed coupled centrifugal type pump with cast iron
casing construction, stainless steel shaft, stainless steel impeller, stainless steel base
plate and with mechanical sealed bearing.
3.12.1.3 COMPONENTS
Water pressure booster pump set & circulating pumps for water heater and chiller package
shall comprise of 1-duty, 1-standby and diaphragm pressure vessel as shown on the
drawing. Duty & stand-by pump sets shall be of identical performance characteristics. All
the pumps shall be design having all wetted parts in stainless steel usable for potable
water applications. The packaged pumping system shall be constructed with Type L
copper suction and discharge headers, valves, Y-strainer and flexible connectors. Unit
shall be rated for 1.5 times the working pressure.
Headers shall be easily removable to allow for service access and moving the package
through doorways.
Cycling of duty pump between 2 pumps in the set to achieve equal running hours.
The pump control panel shall provide the following standard user-selectable features:
All motors shall be designed to suit the maximum temperature of air passing over the
motors and the additional temperature rise caused by exposure to the sun. The type of
winding insulation shall, however, be not less than Class ‘B’. The motors for exhaust fans
shall have the insulation suitable to operate on 50 deg. C ambient temperature. Pump
units shall be fitted with variable frequency drive and other necessary accessories for
safety operation.
All motors smaller than 0.50KW shall be designed to operate on single phase. All motors
0.75KW and above shall be designed to operate on three phase. All motors shall be
wound for 240 Volts, single phase, or 415 volts, 3 phases, 50 Hz, A.C system, TEFC
type.
Any motors brought to site not complying with above mentioned voltage and insulation
requirements shall not be accepted.
3.12.2.1 GENERAL
Supply and install lift pump set as shown on drawings and in accordance with the
schedule of equipment furnished.
The packaged domestic water lift pump set factory assembled system installed as shown
on the drawing shall consist of a structural base, pumps, motors, suction & discharge
headers, valves, flexible connectors, pressure vessel, control panel, pressure outlets and
necessary interconnecting piping.
System shall require a single point power connection and suction & discharge piping
connections. Each pump in the system shall be of equal size to minimize spare parts
requirements. Pumps shall have the duty points as scheduled in the drawings.
3.12.2.3 COMPONENTS
Water pressure Lift pump set package shall comprise of 1-duty, 1-standby and bladder
tank type pressure vessel as shown on the drawing. Duty & stand-by pump sets shall be of
identical performance characteristics. All the pumps shall be of vertical multistage design
having all wetted parts in stainless steel usable for potable water applications. The
packaged pumping system shall be constructed with Type L copper suction and discharge
headers, valves, Y-strainer and flexible connectors. Unit shall be rated for 1.5 times the
working pressure.
Headers shall be easily removable to allow for service access and moving the package
through doorways.
The pump control panel shall provide the following standard user-selectable features:
Packaged pump sets shall be self-contained fully automatic packaged units of closed
coupled centrifugal type, high efficiency pumps with cast iron casing, stainless steel
shaft, stainless steel impeller, stainless steel base plate and with mechanical sealed
bearing. The pumps shall be interconnected with piping using copper pipe work to
BS.2871 Table X. The units shall be equipped with IP65 automatic control panel all
mounted on a common heavy gauge galvanized steel base plate.
The speed of pumps shall not exceed 2900 rpm. The pressure sizing shall be made in
order to provide minimum run time on the lead pump.
Pump shall be controlled automatically by means of float ball valve and float switch or
level switch.
All motors shall be designed to suit the maximum temperature of air passing over the
motors and the additional temperature rise caused by exposure to the sun. The type of
winding insulation shall, however, be not less than Class ‘B’. The motors for exhaust fans
shall have the insulation suitable to operate on 50 deg. C ambient temperature. Pumps
units shall be fitted with constant pressure drive and other necessary accessories for
safety operation.
All motors smaller than 0.50KW shall be designed to operate on single phase. All
Motors 0.75KW and above shall be designed to operate on three phase. All motors shall
be wound for 240 Volts, single phase, or 415 volts, 3 phases, 50 Hz, A.C system.
Any motors brought to site not complying with above mentioned voltage and insulation
requirements shall not be accepted
Each of the pump shall be fitted with double duty at the discharge (in place of
standard isolating, throttle and check valve) and the suction diffuser plus an
isolating valve at the suction side of each pump.
Electrical panel will be base mounted with isolator, TPMCB, Starters, Run/trip
indication, duty selector switch. All inter-connecting pipe-work in copper with
insulation.
Re-circulating pumps shall comply with the relevant provisions of BS 1394: Parts 1
and
Re-circulating pumps shall be suitably suppressed to prevent radio and television
interference.
Pump capacity shall be as stated in the drawings.
Submersible Pump set
Submersible pumpset shall be installed as shown on the drawings. Pumps shall be
a multi-stage pump with stainless steel shaft, stainless steel impeller with housing
made of corrosion resistant alloy.
3.12.4 Filter
Sand filter shall be provided and installed downstream of the lift pump as shown on the
drawing. Filter housing shall be made of 100% non-corrosive material. Shell shall be
constructed of high performance composite and fibreglass materials with uniform inner
shell of thermoplastic material like polyethylene, polypropylene or any other high
performance materials. Standard operating pressure could stand for 10.5 bars at an
operating temperature of 65˚ C or at higher temperature. Filter cleaning shall be automatic
self – cleaning system (Automatic backwash). Filter control shall be modular cartridge
design (clean and service module is right up front), corrosion resistant with long service
life and versatile with easy to set electronic, mechanical or impulse controls. Dirt/rust filter
section should remove solid particles. Filter shall have discharge rating not less than the
discharge rating of the lift pumps. A package type filter shall include, but not limited to, the
following:
Aquatic valves
3-way solenoid valve
Power supply
Stager 2 circuit timer
Copper surface piping
Valve control operation
The water heaters shall have the following features and accessories:
-Magnesium anodes
-Drain valve.
3.12.6 Identification
All valves, plant and equipment installed shall be appropriate identified. The identification
system shall be agreed in details with the Engineer, but shall broadly meet the following
requirements:
A. Valves
Each item of plant and equipment (e.g. water heaters, etc), shall be provided with a
metal identification plate giving complete identification of the equipment in English and
Arabic.
1. General
The Contractor shall activate and operates the whole installation for a period of not
less than 48 hours, during which time all valves, heaters, fixtures, etc., shall be
operated as would occur in the normal operation of the installation for the full period
of this test. At the conclusion, the whole of the system shall operate to full
satisfaction of the Engineer. Testing generally shall be in accordance with BS CP
310:1965.
Eng.Adnan Saffarini Consultants
Westbay Villa
All pipework services shall be subjected to a test of 700 KN/m2 or one and a half
times working pressure whichever is the greater, for not less than 2 hours.
Where pipework is tested in sections, all valves shall be blanked off temporarily
using plugs or blank flanges. The valve wedge shall not be used to retain the water.
The Pipework services shall be charged with water allowing all air to escape and
avoiding shock or water hammer. The test pressure gauge shall be mounted within
the pipework system with a loop and cock and shall be calibrated such that the test
pressure falls above its mid-range.
The contractor shall carry out his own test first to ensure there are no leaks prior to
requesting the Engineer to witness the test. The witnessed test shall maintained for
a minimum of one hour without measurable loss and a without further pumping.
Pipework main laid in ground shall be tested for 24 hours and leakage shall be
measured by the quantity of water pumped into the main under test.
The Engineer shall witness all pipework tests. The contractor shall give the Engineer
a minimum of 24 hours notice of all tests. The contractor shall also provide test
sheets set out in an agreed manner for each pipework section to be tested.
3. Proving Tests
Prior to fixing on site, all water heaters shall be re-tested for water tightness
ensuring damaged equipment is not installed.
Each water service shall be cleaned down and thoroughly flushed out to remove all
dirt within the pipework system.
After the particular water service has been flushed out, refilled and pressure tested,
each tap and draw-off fitting shall be checked for satisfactory rate of flow. Particular
attention shall be given to groups of sanitary fittings to ensure satisfactory flow with
a number of taps open, also that is not drawn into any of the remaining taps or
fittings when opened.
4. Sterilization of Water Services
All pipe works, fittings and storage tanks shall be sterilized starting with the external
water supplies storage tanks and finally the water distribution system,
No sterilization shall be carried out until the system has been flushed out and
approval received in writing form the Engineer to begin sterilization.
The following procedure shall be adopted for sterilization of the water distribution
systems:
2. Recharge all water systems adding sufficient sterilization chemical at the roof
tank to a concentration shall be confirmed by using a measuring instrument
approved by the Water Department.
Sanitary ware shall be as specified in the contract documents. All sanitary ware shall be
installed in accordance with manufacturer's printed instructions for conditions indicated and
as required to obtain a rigid installation. The location of each fixture and the fixing method
of ceramic fixtures shall be as shown on the drawings or as directed by the Engineer.
After all fittings have been mounted and are ready for use and before completion, all fittings
furnished and mounted shall be thoroughly cleaned removing all plaster, stickers, rust, hair
and other foreign matter or discoloration of fixtures, leaving each and every part in perfect
condition and ready for use.
The Contractor shall take adequate precautions to ensure that the sanitary ware is not
damaged in any way before or after installations. Any piece of sanitary ware that is
damaged shall be replace at the Contractor's expenditure.
Testing Procedures
Just prior to handing over the building to the Client, each piece of sanitary ware shall be
tested. Each water closet shall be flushed twice and checked for leaks and any other
defects by the Engineer. Each basin and sink shall be filled to the overflow level and then
after running the water through the overflow for a minimum of 30 seconds, the plug shall be
removed or opened. Each of the above mentioned fixtures shall be inspected for leaks and
defects by the Engineer.
Any defects or leaks shall be repaired or in the case of the defect being chips or cracks or
other visible damage, the fixture shall be replaced at the Contractor's expense. Any sanitary
ware condemned by the Engineer for any other reason shall be replaced at the Contractor's
expense.
5. WARRANTY
The Contractor shall warranty for a period of 400 days after the Practical Completion of the
installation that all plant and equipment shall operate free of any defects due to defective
material or bad workmanship, and that any part found defective during this period shall be
replaced free of cost by the Contractor.
The contractor shall also guarantee the efficiency of performance of the plant and
equipment as per specification for a similar period of 400 days after the practical completion,
and if the services of Contractor’s personnel are requisitioned during this period such works
shall be made available free of cost to the client.
If the defects are not rectified within a reasonable period, the Client may proceed to rectify
these defects by another agency at the Contractor’s entire risk and expense without
prejudice to any rights of the Client.
: KEY TERRAIN
2. uPVC Pipes and Fittings HEPWORTH
HUNTER
MARLEY REDI
WAVIN
4. Water Heaters : A.O. SMITH,
RHEEM AMERICAN MAKE
5. Water Filters : CULLIGAN
BRUNER
CARESS
AQUAMATCH
Note: For approval of materials equivalent to the specified, Engineer’s decision shall be final and
binding.
END OF SECTION
TABLE OF CONTENTS
PART/CLAUSE TITLE PAGE
1. GENERAL ............................................................................................................................... 1
4. EXTERNAL DRAINAGE......................................................................................................... 4
5. MANHOLES ............................................................................................................................ 4
12. SOAKAWAYS......................................................................................................................... 6
4. Drive-in type UPVC clips complete with galvanized steel spike (171mm long) and
galvanized steel nuts and blots shall be used to fix pipes and fittings to the walls,
columns. Minimum stand off distance of 52mm shall be provided.
The clamps shall be gray, black or white colour as approved by the Engineer.
Alternatively, adjustable plastic coated steel holder bats shall be used to support
pipe or secure fittings.
5. UPVC pipes shall be connected to other materials, where applicable, with PVC
caulking bush, and special adaptors.
Rainwater pipes shall terminate with a shoe when discharging over a gully.
Roof / Balcony outlets shall be lacquered cast iron body, cast aluminium
dome/grating complete with fixing accessories.
3. PIPEWORK INSTALLATIONS
During installation of the internal drainage and waste system, the Contractor shall make
due allowance for the expansion of the Vulcathene I PVC pipework and fittings during
normal working conditions. Further allowance shall be made for solvent weld joining of the
above materials with regard to temperature and humidity.
The bores of all pipework shall be smooth and free from all burrs or obstructions; bends
wherever possible shall be of the long radius type. All connections between soil, waste,
vent or fixtures shall be made with approved connectors. The termination at high level of
all vent stacks shall be carried out with a vent guard.
All sanitary fittings which discharge directly to the foul drainage system shall be provided
with traps in accordance with BS 5572. Each trap shall be provided with a disconnecting
union for future removal and cleaning.
All fixtures and fittings draining into the internal drainage installation shall be fitted with
traps. In case of traps for sanitary fitments, e.g. wash hand basins, sinks etc., these shall
be of the deep seal type having a seal of 75 mm.
Sinks - 40 mm
Wash basins - 32 mm
Pipework shall be fixed accurately to approved falls, the gradient shall be consistent and
pipework shall follow a true line. Allowance shall be made for the rodding of the whole
installation, in addition to which, at all changes of direction, a rodding eye shall be
installed. The pipework shall be fixed to the walls using standard PVC coated mild steel or
PVC brackets of a screw-on type as recommended by the manufacturer.
The maximum spacing between supports shall be as follows:
Pipe Diameter (mm) Low Gradient Pipes (m) Vertical Pipes (m)
32 to 40 0.5 1.2
50 0.6 1.2
75 to 100 0.9 1.8
The Contractor shall provide access or rodding eyes wherever required to provide full
access to the system. The rodding eye shall be provided at the foot of all vertical stacks at
the point of connection to the underground drain pipe.
Access doors in suspended pipework within 0.5 m of the suffix shall not face upwards but
be located on the side or underneath the pipe. Where traps, access branches and access
doors are located above false ceiling, removable panels shall be provided.
No offsets shall be installed in pipework other than those indicated on the drawings,
without the consent of the Engineer. The offsets provided shall be sufficient to allow all
parts of the installation to be rodded in the event of a blockage.
Access doors provided shall be sufficient to allow all parts of the installation to be rodded
in the event of a blockage. The whole of the installation shall be tested in accordance with
the requirements of BS 5572, the tests being to the full satisfaction of the Engineer.
4. EXTERNAL DRAINAGE
The external drainage system consists of complete sewer system comprising of
manholes, soakaway pits and interconnected pipework. Pipework and fittings used in
external drainage installation are to be of extra strength vitrified clay to BS EN 295:1991
and BS 65: 1991. Pipework and fittings used in external surface water drainage shall be
UPVC to BS 4660 as indicated on the drawings. All pipework shall be laid with due regard
to the falls and invert levels set out on the drawings or as given on site by the Engineer.
All pipework is to be laid accurately with consistent gradients and following a true line.
All bends shall be of the long radius type. The bore of the pipework shall be clear of all
obstructions; further the Contractor shall ensure that, no cement or other substance which
sets hard when the contact with water is allowed, to remain in the installation. The
Contractor shall ensure that during backfilling of the excavations required to install the
external drainage no damage is caused to this installation.
Pipework passing through the walls or foundations shall be sleeved with UPVC of
sufficient size to allow clearance round the drain pipe. The gap between the drain pipe
and sleeves shall be caulked with mastic. Where drains pass through or below
foundations, flexible couplings shall be provided not closer than 150 mm or more than 300
mm from the face of the building.
The whole of the external drainage installation shall be tested in accordance with the
requirement of BS 8301, this shall be to the complete satisfaction of the Engineer.
5. MANHOLES
The Contractor shall provide manholes at the locations and to the sizes shown on the
drawings. Manholes shall be constructed in accordance with the detailed drawings and as
described in this specification.
Manhole chambers with depth upto one meter shall be constructed in sulphate resisting
concrete blocks of minimum strength 7.0 MN/m2 laid in bond and joined with a 3 : 1 sand
and sulphate resistant cement mortar and set on a 150 mm thick concrete base. The
block courses shall be laid even and uniform and broken blocks are not to be used except
for snap headers. Block cavities shall be filled with concrete and finished smooth with face
rendering. Manholes with depth more than one meter shall be cast insitu with reinforced
cement concrete as detailed in the drawings.
An in-situ concrete cover shall be constructed over the manhole to the size and thickness
shown on the drawings with a clear opening to suit the type of cover specified. The
opening being located to afford direct access onto the step irons.
Half channels with three quarter section bends shall be laid in the bottom of the manhole
with flexible joints on the drains immediately outside the manhole wall.
Concrete benching shall be formed to a fall of not less than 1 in 10 to the channel and
finished smooth with 12 mm thick 2: 1 sand and cement mortar trowel led with all angles
rounded.
External faces of structures shall be kept clear for inspection until they have been
approved by the Engineer.
Re-inforcing bars for cover slab shall be 12 mm diameter, high tensile or 16 mm mild steel
fixed at 100 mm centers with 25 mm cover from the underside of slab. The minimum
thickness of slabs shall be 150 mm.
9. RECORD OF TESTS
The Contractor shall keep a proper record of tests carried out on the drainage installation
throughout the contract, recording date of test, by whom tested, witnessed and result; one
copy of the record shall be sent to the Engineer on completion of each phase of the
contract. Records shall be countersigned by the witness.
A final test of the whole installation shall be carried out in the presence of the Engineer or
his representative at or about the completion of the contract. The satisfactory completion
of an earlier test during the progress of work shall in no way relieve the Contractor of any
of his obligations, and any defects found at the time of the final tests, or during the period
of maintenance shall be made good to the complete satisfaction of the Engineer.
12. SOAKAWAYS
Soakaways shall be constructed in accordance with tender drawings and shall have a
minimum internal depth of 2500 mm. Excavation and disposal of surplus earth shall be as
per general specifications for the purpose under Civil Works.
The precast rings shall be minimum 100 mm thick and shall have three evenly spaced
lifting points. The perforated rings shall be constructed with 75 mm diameter holes at 410
mm centers in rows spaced 300 mm apart vertically with each row symmetrically
staggered.
The soakaway shall be surrounded by granular material and shall infill the entire void
between the soakaway and the side of the excavation. The granular material shall be laid
and taped by hand in 300 mm layers and shall no where be less than 500 mm in width.
Borehole
The Contractor shall drill borehole at the bottom of soakaways for surface water drainage.
Size of borehole shall be 150 mm diameter. Borehole shall be taken to a depth of 20 m
below the bottom of soakaway or upto water table which ever is deeper, or as instructed
by the Engineer. Borehole shall be thoroughly flushed clean using compressed air and
clean water. The bore shall be lined to a depth of 2 meter below soakaway base and
extend minimum 500 mm above soakaway base. Bore hole lining material shall be
galvanized steel tube to BS 1775.
Vertical stack shall be adequately supported at the base to stand the total weight of
the riser. Under no circumstances shall branches from vertical rising pipes be the
means of support for the vertical pipework.
High temperature PVC waste pipework 32mm, 40mm and 50mm shall be supported
using stand off two piece clips screwed to the wall using round head zinc plated
wood screws. Pipe clips shall be plastic coated galvanized mild steel where
exposed to view and galvanized mild steel where concealed.
UPVC solid and ventilation pipework 82mm, 100mm and 150mm shall be supported
using two piece holder bats screwed to the wall using round head zinc plated wood
screws.
Brackets shall be galvanized steel and be rigid. Where soil and ventilation pipes are
suspended from the underside of slab, they shall be held rigid in position. Single
angle iron supports may be sued for pipework up to 500mm form underside of slab.
Double angle iron supports shall be used for pipework 500mm – 1000mm form the
underside of the slab. All supports shall be proprietary brand and manufactured from
galvanized steel. Double angle iron braces shall be installed on both single and
double angle iron supports at 6-meter centers for vertical and horizontal runs of
pipework and anchored as necessary.
2. Rodding Eyes
Rodding and cleaning eyes shall be provided as indicated on the contract drawings
and as required.
3. Vent Pipes
Vent shall be provided at horizontal trap-vent distance as follows, unless otherwise
shown on drawings:
Soil / Waste pipe dia.
Trap Vent distance (m)
(mm)
32 1.2
40 1.7
50 3.4
80 3.4
100 & larger 4.6
All vent-thru-roof pipes shall terminate 300mm above the pint of exit from the
service duct, or above parapet whichever is higher.
Vent for water closet shall be 50mm dia. minimum. Other vent sizes to be as shown
on drawing.
4. Jointing
Joints of UPVC and high temperature PVC shall be “O” ring and solvent welded.
Prior to jointing, all pipework, fittings and accessories shall be thoroughly cleaned.
Pipework shall be cut square, end chamfered and swarf and dust removed. Prior to
jointing, pipes and fitting should be checked for correct position and alignment and
marked to ensure accurate assembly.
Where “O” ring joints are to use pipes shall be marked for insertion depth, “O” ring
placed in ring seal prior to application of small quantity of lubricant or petroleum jelly
around the chamfered spigot end. The pipe shall then be inserted into the socket
joint and finally adjusted to the correct insertion depth.
Where solvent joints are to be sued, special care shall be taken to ensure both
spigot and socket are free from all dirt, grease and swarf. Solvent cement shall then
be applied liberally and evenly to both socket and spigot prior to inserting spigot into
socket. The joint shall immediately be cleaned of surplus solvent with a dry cloth
around newly formed joint.
Joining of W.C. outlet to UPVC pipework shall be by means of either a straight or
bent connector as required complete with rubber seal ring and suitable connection
for W.C. spigot outlet.
5. Laying Rigid Pipe
Each pipe immediately before being laid shall be carefully brushed out and
inspected for defects.
Pipes with flexible joints, except where concrete protection is provided as specified
hereafter, shall be laid on a well compacted bed of granular bedding material
extending for the full width of the trench and with sufficient material at the side to
permit the pipes to be worked into the granular material and firmly supported to true
line and level. Sufficient space should be left to enable the joints to be made, tested
and inspected but fully contractor shall ensure that at least three quarters of the pipe
length is fully supported. After the pipeline has been tested and approved by the
Engineer the trench shall be carefully filled to 300 mm above the crown of the pipe
with granular materials.
6. Laying Rigid Pipe
All operations involving the laying, bedding, joining, backfilling etc. of pipes plastic
materials shall be strictly in accordance with the manufactures recommendations
subject to the approval of the Engineer.
7. Marker Tape
Marker tape shall be laid 150mm above all sewerage and effluent pressure
pipelines. The marker tape shall be red, non-biodegradable plastic and inscribed
with the words
“DANGER – NON POTABLE WATER”, in both English and Arabic and shall be of a
type approved by the Engineer. Where specified in the Contract documents blue
marker tape as above shall be laid above potable water mains and inscribed with
the words “WATER MAIN” in both English and Arabic.
8. Setting out and Pipe Alignment
All pipes and pipeline shall be laid to the lines and depths shown on the drawings or
as otherwise directed by the Engineer.
All pipelines shall be laid accurately to line and gradient so that, except where
otherwise specified, the finished pipeline is in a straight line in both horizontal and
vertical planes. Where shown on the drawings or otherwise permitted by the
Engineer shall allow changes of direction achieved by deflection at joints within the
maximum permitted by the manufacturer. Where the angle of the bend required is
greater than that obtainable by joint deflection at joints then the manufactured bends
of the appropriate degree shall be used. Manufactured bends shall only used where
shown on the drawings or where otherwise permitted by the Engineer.
All pipelines forming part of a drainage system shall be laid to the specified line and
levels so that every pipeline lies in a straight line in both horizontal and vertical
planes between successive manholes on the line. No bends will be permitted other
than at manholes.
Every pipe shall be placed in position individually and shall be set out accurately to
the line and level required. All setting out to line and level of both pipeline and
individual pipes shall be achieved by methods approved by the Engineer.
Where pipelines of constant gradient are to be laid, the Contractor shall provide, fix
and maintain at such points as may be directed by the Engineer properly painted
sight rails and boning rods of pre-determined measurement for the boning in of
individual pipes to correct alignment. The sight rails shall be situated vertically over
the line of pipes or immediately adjacent to and there shall at no time be less than
three sight rails in position on each length of pipeline under construction to any one
gradient.
If the Contractor wishes to propose an alternative method of controlling pipeline
alignment, he shall submit his proposed method to the Engineer for approval.
9. Concrete Protection to Pipelines
All underground drainage pipework shall be surrounded with 150mm thick Grade
SRC 35 sulphate resisting concrete, along its entire length, in the following location.
a. All drainage below buildings or structural.
b. All drainage below roadways and parking areas with less than 600mm covers.
c. Drainage with cover of between 600mm and 1200mm, where there is
vehicular traffic over the ground above the drain line.
d. Elsewhere as indicated on the Contract Drawings.
The required depths of concrete bed and height of concrete backfill shall be as
indicated on the Contract Drawings.
Where a concrete bed and surround is specified, a minimum of 75mm blinding
of concrete Grade 20 shall first be laid over the full width of the trench.
The Pipes shall be laid, jointed and supported on precast concrete blocks,
which shall be separated from the barrel by 25mm thick timber packing.
After the pipeline has been tested and approved by the Engineer the top of the
concrete bed shall be thoroughly cleaned and additional concrete Grade SRC
35 carefully placed and compacted under and around the pipe to a height of at
least 150mm above the crown of the pipe.
Where pipes with flexible joints are to be surrounded, 13mm thick fiberboard
or polystyrene sheet shall be fixed at the pipe coupling joint extending for the
full cross section of the remaining concrete bed and surround, and accurately
cut to fit the profile of the pipe.
10. Pipelines Protection From Extraneous Material
The pipelines shall at all times be kept free of extraneous material and when work is
not in progress the open ends of the pipeline shall be securely plugged with an
approved watertight plug or stopper. Claw type plugs or any type liable to damage
the pipe will not be approved.
The Contractor shall clear the inside of each fitting and pipe length immediately prior
to jointing and shall swab all fittings and pipe lengths to remove all dirt, sand or
other matter that may contaminate the pipeline. The entire absence of foreign matter
from the completed line shall be a condition precedent to acceptance.
11. Trenches
All trench excavation shall comply fully with all the relevant clauses of QCS Section
20 and this specification.
Trench depths shall be sufficient to allow the installation of the required pipe
bedding, granular or concrete, as specified. Generally the depth of cover shall not
be less than 600 mm unless otherwise indicated on the Contract Drawings.
Trench width shall be in accordance with the following table:
The maximum and minimum widths shall apply from the bottom of the trench to 300
mm above the crown of the pipe.
Should the trench be excavated to a depth greater than is required in the opinion of
the Engineer, the Contractor shall fill in the bottom of the trench to the required
depth with concrete or other such materials as the engineer may direct.
In the case of trench excavations made in roads, footpaths, verges, central strips or
within 5 meters of buildings, the Contractor will be required to execute the works so
as to minimize damage and disturbance. Vertical trench sides will generally require
support by timbering or other suitable means. Under-cutting of trench sides will not
be permitted.
12. Granular Bedding Material for Rigid Pipes
Granular bedding material for rigid pipes shall consist of gravel or broken stone and
shall be a suitable “all in” ballast or stone.
For pipes up to 1200 millimeters nominal bore the material shall be graded 12
millimeters to 5 millimeters all passing 12 millimeters and not more than 20 percent
passing 5 millimeters B.S sieve.
The minimum thickness of granular material below the barrel of the pipe shall be as
follows:
14. MANHOLES/SOAKAWAYS
14.1 CEMENT AND CONCRETE
A. Cement
All cement used in all classes of concrete for drainage and sewerage works, whether
above or below ground level, shall be sulphate resistant cement, complying with BS 4027.
B. Granolithic Concrete
Granolithic Concrete shall be mixed using one part by weight of Portland cement to two
parts of clean granite chippings graded as table 1 of BS 882, to one part of sharp siliceous
and graded as Table 2 and clear water sufficient to form a stiff but workable mix and
provide a dense concrete.
C. Cement Mortar
Cement mortar shall consist of sulphate-resisting cement and sand gauged by volume in
suitable boxed in the proportions given.
Unless otherwise specified cement mortar shall be SRC Class No. 1
The ingredients of the mortar shall be mixed in an approved mechanical mixer or shall be
mixed together dry on a clean wooden stage until the mix is homogeneous in color. Water
shall then be added through a rose in sufficient quantity to give no more than stiff
workability. The whole shall then be turned until perfectly mixed.
Mortar shall be used within 30 minutes of mixing and shall not be remixed or worked up
again after it has stiffened. Any mortar that has commenced to set shall be removed from
the works.
D. Concrete Classification
Concrete Application Characteristic Strength
Grade (N/mm²)
SRC 30 30 Precast Concrete
Normal Reinforced concrete, binding
SRC 25 25 thrust blocks
SRC 25 25 Mass concrete hard standings
Mass concrete pipeline protection
SRC 20 20 and surrounds protection to taking
hollow blocks infill
No. 2 1 3 -
No. 3 1 5 1
All internal faces of manhole chambers except benching and vitrified clay channel fittings
shall be painted with one primer coat and two final coats of black bitumen coating
waterproofing solution to BS 3416, type 1 or equal and approved.
All exterior faces of manhole chambers shall be protected with 1000-gauge polythene
membrane with hardboard protection against damage during backfilling.
Where indicated on the Drawings, manhole cover frames shall be supported on solid
precast concrete bricks, manufactured from Grade SRC 35 concrete.
Reinforced cover slabs shall be provided where manhole access openings are less than
the internal dimensions of the manhole chamber.
The cover slabs shall be mounted by ductile or cast iron manhole covers and frames of
the quality specified. The covers in roads and paved areas shall be accurately set on
precast concrete brickwork to the level and slopes of the roads or pavements.
Manhole inverts shall be constructed of half section vitrified clay channels. Half section
vitrified clay channel branch bends shall be used for branch connections. Benching in
manholes shall be carefully formed according to the number, diameter and positions of
the incoming and outgoing pipes. The benching in the manholes shall have vertical sides
extending from the vitrified clay channels at least to the level of the crown of the highest
pipe. The benching shall be sloped towards the channels at a gradient of 1 in 10 or as
otherwise detailed on the drawings. The benching shall be rendered with a 12 mm
thickness of epoxy mortar rendering. The ends of all pipes entering and leaving the
manhole are to be carefully cut to shape to suit the internal dimensions of the manholes,
and shall project through on the inside, the benching being continued round the pipe to
form a fillet.
I. Precast Concrete Manholes
The base shall be cast in-situ and shall be Grade SRC 20 concrete to the dimensions
shown on the drawings.
The whole base including the outside surround to the pipes shall be cast monolithic.
Immediately before concreting, lengths of pipes to be built in shall be surrounded with a
layer of cement mortar No. 1
All chamber and shaft rings of the manholes shall comprise precast Grade SRC 35
concrete units as shown on the drawings.
The formwork for all precast concrete rings shall be purpose made in mild steel and shall
incorporate surface vibrators of adequate performance to ensure proper compaction of
the concrete. The forms must have provisions for allowing the casting in of the step irons.
All precast components for manholes shall be made in accordance with BS 5911 or
equivalent approved standard. Precast concrete components shall immediately after the
removal of forms, be sprayed with an approved curing membrane. Regular spraying with
water will not be an acceptable method of curing.
Where the Contractor does not own forms with surface vibrators for the production of
precast concrete manhole components he may, with the written approval of the Engineer
employ an approved method of hand compaction. If the Engineer gives such written
approval, this does not imply acceptance of the quality of the finished work.
The positions of lifting holes or eyes in precast components are to be approved by the
Engineer. Lifting holes are to be grouted up after construction of the manhole.
Step irons are to be positioned in the chamber shaft rings in such manner that the step
irons are vertically linear. The joints at each step iron shall be made watertight and strong,
free from any crack and if found otherwise the Engineer may reject the precast ring or
may instruct the Contractor to take any necessary measures to make the ring watertight.
The first step iron shall be fixed at a maximum of 600 mm below the cover level and the
last step iron shall be fixed at a maximum of 300 mm from the top level of the lowest
adjacent benching.
Step irons shall be staggered at 300 mm centers vertically and horizontally.
All joints between rings or slabs shall be made watertight to the satisfaction of the
Engineer with a bituminous mastic strip sealant as approved. The external face of the joint
is to be sealed with epoxy mortar.
A 150 mm thick in-situ Grade SRC 20 concrete surround shall be placed around the
manhole as shown on the drawings.
J. Chamber Rings
Chamber rings shall be manufactured from concrete Grade SRC 35.
Both internal and external surfaces of the chamber rings shall be coated with a solution of
bitumen refined from asphalted crude oil, the solution having total solids contents of
approximately 45% and a viscosity corresponding to a No. 4 Ford cup time of
approximately 30 seconds.
K. Soakaways
Soakaways shall be constructed using precast concrete manhole rings 1800 mm diameter
and shall have a minimum dept of 2.5 meters below invert of entry pipe and constructed to
BS 5911: Part 1- 3.
The precast concrete rings shall be made from sulphate resisting cement to British
Standard 4027:1980. The precast rings shall be a minimum of 100 mm thick with 75 mm
diameter perforations, space 30 mm vertically and 410 mm horizontally with each
symmetrically staggered. The bottom ring shall be set on a cost in situ concrete base of a
minimum 150 mm thick from concrete with a 300 mm diameter bore hole lining sleeve
cast in centrally as shown on the drawings. All rings shall be bedded in cement mortar
and the soakaway shall be surrounded by granular material. All soakaways shall also
comply with “Developer Drainage Guide” published by the Ministry of Public Works Civil
Engineering Department, Sewerage Division where applicable.
The granular infill shall extend 500 mm each side of the soakaways walls. The entire void
surrounding the soakaway walls shall be filled in layers of 300 mm each layer, tamped by
hand. The granular fill shall be clean crushed rock to the approval of the Engineer and
shall have grading complying with the following table.
The soakaway cover slab shall be reinforced precast concrete with cast iron cover and
frame as shown in the manhole schedule and complying with British Standard BS 497.
L. Manhole Covers and Frames
Manhole covers and frames shall be ductile iron and comply with BS 497 – 1976 and shall
be of the sizes and types as shown on the Contract Drawings.
In general, manhole covers and frames shall be one of three types, as follows, unless
otherwise specified:
Heavy Duty, to BS 497 Grade A
Medium Duty, to BS 497 Grade B1
Light Duty, to BS 497 Grade C
M. Heavy Duty
All manholes installed in roadways or trafficked and paved areas shall be heavy to BS 497
Grade A Reference MA 60. In paved areas, cover shall be recessed type or as per
Engineer’s requirements.
The cover and frame shall be made from ductile iron and the cover shall be of the loosely
bolted double triangular type with three point suspension to provide stability under load.
Such manholes shall incorporate double seal between cover and frame. Sealing groove
shall be filled with grease to provide airtight seal.
For diesel fuel fill chamber, cover shall be single, triangular, lockable, non rock to BS 497
Grade “A” 600 x 600 mm.
N. Medium Duty
All manholes installed external to buildings, but not in roadways or trafficked and paved
areas, shall be medium duty to BS 497 Grade B1.
The cover and frame shall be of grey or ductile iron and the cover shall be either
rectangular or circular as specified in the Manhole Schedule. Such manholes shall
incorporate a double seal between cover and frame. Following flushing out and testing of
the drainage system, the sealing groove shall be filled with grease to provide an airtight
seal.
O. Double Seal
Duplicate vertical “tongue in groove” relationship between a cover edge and frame. To
allow a double grease seal against the ingress of odour.
P. Light Duty
All manholes installed with buildings and not subject to motor vehicles or industrial trolleys
etc. shall be light duty to BS: 497 Grade C of the lockable type.
The cover and frame shall be made from ductile iron and shall incorporate a double seal
between cover and frame. Following flushing out and testing of the drainage system, the
sealing grooves shall be filled with grease to provide an airtight seal.
In those areas where it is required to accept a tiled floor finish; the manhole covers shall
be of the recessed type. In kitchens, or other areas subject to washing-down, manhole
covers and frames shall have stainless steel edging and trim. Double-cover units shall be
provided where specified in the Manhole schedule.
The Contractor shall provide two sets of lifting keys for each type of manhole.
Manhole covers and frames shall be as approved.
Q. Step Irons
Step irons shall be manufactured form galvanized malleable cast iron and shall comply
with BS 1247 and be of the general purpose or precast concrete manhole pattern as
applicable.
The tail length shall be 230 mm for both manhole types.
The loss of water over a period measuring vessel at intervals of ten minutes of noting the
quality of water required maintaining the original level in the standpipe. For drains up to
300 mm diameter, the water quantity added shall not exceed 0.06 liter per hour per 100
linear meters per millimeter of nominal bore of the drain under test.
All drains shall be tested for a second time as described above after correct bedding
cover and selected backfill have been consolidated and the finished surface complete.
15.4 AIR TEST
A gauge in the form of a “U” tube shall be connected to the plug fixed at one end of the
length to be tested and all junctions and connections to the sewer on drain shall be
plugged. Air shall then be pumped in form the other end of the drain ender test until a
pressure equal to 100 mm of water is indicated on the gauge. Without further pumping,
the pressure shall not fail more than 25mm during a period of five minutes.
Air tests shall be carried out after 3 pm and all pipework shall be shaded from the sun at
all times. Should an air test fail, a water test shall be carried out as described in this
Specification.
15.5 PROFILE TEST
A hardwood ball, of an approved profile, shall be drawn through all foul drains from
manholes to manhole and through branch foul drains before soil pipes; gullies and W.C’s
are filled. The diameter of the ball or profile shall differ form the nominal internal diameter
of the pipe by not more than 6mm or by not more than 4% of the nominal internal
diameter of the pipe, whichever is the greater difference.
During commissioning, all manhole cover shall be removed and water flow tests shall be
carried out to ensure that the drains are flowing at their designed capacity and that they
are free of debris.
15.6 MANHOLE TEST
All manholes shall be tested in accordance with the requirements of BS 8301 and the
requirements of section 20 of Q.C.S.
The Engineer shall witness all manhole tests. The Contractor shall give the Engineer a
minimum of 24 hours notice of all tests. The Contract shall also provide test sheets set out
in an agreed manner for each manhole to be tested.
All concrete manholes cast in-situ and precast concrete manholes shall be water tested
by plugging all necessary connections and filling the manhole with water to a minimum
height of 600 mm above the top of the benching. Water shall be added at ten-minute
intervals until absorption has ceased. No change of water level shall occur for an
uninterrupted period of three hours.
15.7 WARRANTY
The Contractor shall guarantee for a period of 400 days after the Practical Completion of
the installation that all plant and equipment shall operate free of any defects due to
defective material or bad workmanship, and that any part found defective during this
period shall be replaced free of cost by the Contractor.
All compressors up to 15 HP shall be guaranteed for a period of five years from the date
of Practical Completion. The Contractor shall also guarantee the performance of efficiency
of the plant and equipment as per Specification for a similar period of 400 days after the
Practical Completion and if the services of Contractor’s personnel are requisitioned during
this period such works shall be made available free of cost to the Client.
If the defects are not rectified within a reasonable period, the Client may proceed to rectify
these defects by another agency at the Contractor’s entire risk and expense without
prejudice to any rights of the Client.
END OF SECTION
AT
Leqtaifiya
IRRIGATION SPECIFICATIONS
November 2015
SECTION 28.2 – IRRIGATION SPECIFICATION
TABLE OF CONTENTS
1. GENERAL .............................................................................................................................. 2
2. PRODUCTS............................................................................................................................ 7
3. PROTECTION ....................................................................................................................... 14
4. INSTALLATION .................................................................................................................... 15
6. FLUSHING ............................................................................................................................ 19
1. GENERAL
1.1 Scope
13 The purpose of this project is to supply, install and commission an automated irrigation
system with all related components consisting of remote control units, remote control
valves, control wires, piping, backflow preventors, valves, fittings, inline emitters, pump
systems, filter, and necessary accessories in all respects and in accordance with the
Project Documentation.
14 The installed irrigation system shall be in compliance to BS 7562 and the regulations as
given in referenced standards provided for the American W ater Works Association
(AWWA). W here regulations are equal or indistinguishable, the British Standard shall
comply.
References shall be made to all related International Standards Irrigation, and relevant
to Qatar National Construction Standards.
1 References shall be made to relevant Qatar Construction Standards 2010 (QCS 2010).
2 In case of any discrepancy the most stringent requirement shall be applied and as
approved by Supervision Consultant.
1.3 Drawings
4 The Tendering Contractor shall be responsible for obtaining all necessary dimensions
and information required for the preparation of the construction, co-ordination, certified
manufacturers, and builders work drawings.
5 The Tendering Contractor drawings shall be based on the latest drawings produced by
the Architect, or other Consultants appointed by the client.
1 The Contractor shall schedule and perform all tests and inspections required. Costs of
all tests and inspections and costs of retesting of rejected work shall be borne by the
Contractor until such tests meet acceptance and approval by the Engineer.
2 Tests and inspections shall be to BS 7562and BS 7459.
1 The Contractor shall operate and maintain the irrigation system throughout the
Maintenance Period, and shall provide staff in full time attendance throughout the
period.
2 The maintenance of the irrigation system shall cover all work necessary to adequately
operate and keep all irrigation equipment, valves, pipelines and appurtenances in
proper operating condition, all to the satisfaction of the Engineer.
(a) supply of irrigation water of suitable quality and adequate quantities to meet the
irrigation requirements. The Contractor shall arrange to obtain water from an
approved source. A full analysis of the irrigation water shall be submitted to the
Engineer for approval and then at one month intervals thereafter during the
maintenance period.
(b) irrigation of areas forming part of the W orks at a frequency and depth as required
for very season in the maintenance period.
(c) maintenance and repair of all irrigation equipment, pipes, valves, and all
appurtenances; records shall be kept of all maintenance, repairs and operation
activities carried out during the maintenance period.
(d) the Contractor shall provide to the Engineer at the end of the maintenance period
a report which shall include details of the date, location and type of work
performed, all repairs and replacements, the amount of water applied and the
duration of each irrigation cycle, results of water analysis and all other relevant
information of work and activities carried out during the maintenance period.
(b) drawings are diagrammatic to the extent that swing joints, offsets and all fittings
are not shown and shall be the responsibility of the Contractor to incorporate as
needed and as compatible or acceptable with other included items
(d) remote controls valves shall be grouped wherever possible and aligned at a set
distance from road edges, footpaths, and buildings.
1.7 Submittals
1 Prior to start of any work at site the Contractor has to approach all Service Authorities
in Qatar to get their no objection for the work included in this contract and record
drawings for their existing services. Copy of these drawings and no objection certificate
should be submitted to the Engineer before starting the actual work at site.
2 Shop Drawings - The Contractor to prepare the project shop drawings in three (3) sets
of black hardcopies, one set colored hardcopy and a soft copy, which to be approved
by the Engineer representative prior to commencing installation work. The shop
drawings shall show but not limited to valves, control wires route and numbers,
controllers’ location and flow balancing. Please note that the contractor to make detail
survey of existing levels in the contract area. Trial pits should be taken at every 50
meter interval, mark all the existing services in reference to the road edge and building
line along with its depth from existing the ground level & the proposed Landscape finish
level. Contractor to check availability of all the existing ducts that are marked on the
tender drawings. Contractor to propose the route of Irrigation piping based this
information. All this information regarding trial pits, existing and proposed levels shall
be made available to the Engineer within mobilization period of the contract. All this
information shall be made available on hardcopy and in Digital format to the Engineer
as it is required for adjusting landscape and pipes/services alignment.
The successful contractor shall submit shop drawings, for approval by the Engineer, for
the following:
(a) In case of any conflict between contract drawings and any existing or future
services which may necessitate re-routing proposed irrigation mains or laterals,
the contractor has to prepare the shop drawings accordingly and submit it to the
Engineer for approval. This should be considered as integral part of the contract.
(b) The pump/filtration chamber, mechanical, electrical, and civil works shop
drawings. Necessary modifications to the existing feeding chambers (civil and
mechanical). Valve chambers including valves, pipe works, and civil works.
Electrical control equipment with circuit diagrams.
(c) Details of mainline, profile drawings for mainline, lateral pipes and other typical
connections.
(d) Wiring diagrams including conduits, pull boxes, sizing and calculations to verify
that cable sizing is in accordance with Kahramaa regulations and equipment
manufacturer’s recommendations.
(e) Electrical power and control wiring diagrams for irrigation controllers, field wiring
and grounding.
(g) Detail of distribution valve chambers and any modification to the existing feeding
chambers.
(h) The approval shall not relieve the Contractor of any of his responsibility under the
contract for successful completion of the work.
3 Product Samples: The Contractor shall submit samples of materials proposed for
installation for approval fourteen (14) days prior to starting any part of the Works
covered by this Project. The Contractor shall provide one of the following:
(a) plastic pipe and conduit, dripper/emitter distribution hose, 600mm length of each
size and type
(b) ductile iron pipe, 600 mm length of each size
(c) one of each valve chamber cover
(d) control wire, 600 mm length of each color, with schedule of color description
(e) sealing packet for waterproof control wire splices
(f) plastic fittings, one of each material type (one size only)
(g) drip lateral fittings, one of each type for each pipe size
(h) control valves complete with solenoid valve assembly, one of each type
(i) controller chart, one typical
(j) backflow preventer.
4 Operation and Maintenance Manuals – The Contractor shall submit four (4) sets of
black hard copies, one set colored hardcopy and a soft copy of detailed Operation and
Maintenance Manual and one (1) softcopy with equipment reordering codes and
literature.
5 As-Built Drawings – The Contractor shall submit three (3) sets of black hardcopies, one
set colored hardcopy and a soft copy of the complete project As-Built drawings
reflecting the actual site installation.
2. PRODUCTS
1 Remote Control Unit (RTU) shall be automatic irrigation, solid state electronic computer
controllers housed in a weather proof, lockable cabinet and mounted on a lockable
pedestal and shall comply with BS 7562. Controller cabinet and pedestal shall be
corrosion resistant epoxy painted steel with steel hinged doors and master-keyed locks.
2 Each RTU shall have the following features and characteristics:
(a) 4 stations outdoor controller with timing capability of 0-99 minutes (in 1- minute
increments) or 0-9.9 hours (in 0.1 hour increments) per stations. Stations shall
have multi-valve operation capability for up to four (4) 24 VAC solenoid valves
and shall have independent station programming
(b) sequential station operation with automatic starts of up to four (4) per day for each
station. The programming schedule shall be based upon a variable 8-day cycle
for every day, every other day, every third day, etc. Single station operation,
station advance key and manual override operation shall be provided
(c) water budgeting system whereby the timing for all stations may be varied from 25
% to 200 % (in 25 % increments) of the set program for all stations, with one
programming entry
(d) remote master control capability such that all RTU may be linked (in the future) to a
centralized master programming controller
1 Individual types of pipe, hose, and fittings supplied are to be of the same manufacturer
unless otherwise approved.
2 All pipework shall be free of blisters, internal striations, cracks, or any other defects or
imperfections. The pipe shall be continuously and permanently marked with the
manufacturer’s name, material type, size, schedule or class, and quality control
identifications. All main lines and lateral pipes shall be factory colored white for non-
potable waterline identification.
3 Pipes shall be High Density Polyethylene Pipe (HDPE). HDPE pipes shall be
manufactured in accordance with DIN 8074 and DIN 8075 for clean water.
4 HDPE pressure pipes shall have a maximum standard dimension ratio of SDR 11. SDR
shall be defined as outside diameter divided by wall thickness.
5 HDPE pipes shall have a minimum Class PE 100 and have a minimum pressure rating
0 0
of 16 bars (PN 16) at 20 C (de-rated to PN11 at 45 C) unless otherwise specified on
drawings or in Bill of Quantities.
6 HDPE pipe shall be supplied in standard lengths, unless otherwise specified, detailed
or required on the approved plans. Field cut lengths of pipe used as closures may not
be shorter than 0.75 metre in length, and must be approved by the Engineer.
7 Fittings and joints shall be as follows:
(a) HDPE pressure pipe fittings shall be injection moulded HDPE with the same
Class, material type, SDR and pressure rating as the pipe to which they are to be
connected. All joints between HDPE pipes and fittings shall be butt fusion welded
as specified above. The fittings when connected to the main pipe shall provide an
integrated system capable of withstanding the working and test pressure as
prescribed in Section 8.4.5.5 of QCS 2010.
(b) All joints between HDPE pipes to be made by “Thermal Butt- Fusion W elding” in
accordance with ASTM 2657. Jointing shall be carried out by a Certified Butt
Fusion W elding Tradesman under the Pipe Manufacturer’s Supervision.
1 Isolation valves for 50 mm diameter mains and smaller shall have a body complying
with ASTM B 61 bronze, or ASTM B 30 copper alloy 908 or alloy 954. They shall have
a non-rising stem, double wedge disc and a threaded inlet and outlet. Valves shall be
rated for 1.5 MPa working pressure and have the capability of being repacked while
under pressure. Operation of the valves shall be by a hand-wheel.
2 Isolation valves of 63 mm size and larger shall be the non-rising stem, outside screw
and yoke type with cast or ductile iron body and bronze trim. Ductile iron shall conform
to ASTM A 536, Grade 60-40-18 and cast iron to ASTM A 126, Class B. Valve spindles
shall be stainless steel complying with ASTM A 479, Type 316. Valves shall have a
solid wedge bronze or brass disc quipped with operating nut (unless otherwise
approved) and a flanged inlet and outlet. Valves shall be rated for 1.5 MPa water
working pressure and have the capability of being repacked while under pressure.
3 The rubber or wedge in sealing rings and the like shall be of a synthetic quality which
can withstand storage in the Qatar climate for at least five years and shall be suitable
for the water qualities specified.
1 The remote control valve shall normally be the closed 24 VAC, 50/60 cycle, solenoid
actuated globe pattern diaphragm type capable of having a flow rate ranging from 0.3
to 12.5 liters per second. The valves pressure rating shall not be less than 1.4 MPa.
2 The valve shall be of the slow-closing, solenoid type, with a manually operated flow
control stem. The valve body, bonnet and cover shall be constructed of brass. The
valve diaphragm and disc shall be constructed of reinforced nylon.
3 The valve shall be a pressure regulating type. The valve shall be capable of
maintaining a constant downstream pressure regardless of inlet pressure variations.
4 The valve shall have a self-flushing nylon screen to protect the internal orifices from
contamination.
1 Quick coupling valves shall be single piece construction brass and have solid brass
hinged covers.
2 They shall have a 25 mm female iron pipe size connection.
3 They shall be vinyl-covered. The vinyl shall be yellow in color.
1 Flush valve shall consist of a molded PVC ball valve with CPVC ball and stem seat, 19
mm diameter with threaded connections.
1 The valve shall be having constructed of Brass, Cast Iron, Ductile Iron and stainless
steel materials, 100% non-corrosive.
2 The valve shall allow flow in one direction by the action of a spring loaded flap which
closes against a rubber seal.
3 The spring and the flap shall be connected via a moment arm in order to ensure that
the spring pressure is maximum when the valve is closed.
4 The valve shall have a pressure rating of 16 bars and shall have an external position
indicator.
5 The valve shall be available in 50mm, 75mm, 90mm, 110mm, and 160mm size.
1 Gate valves shall be designed for a working pressure of not less than 10 bars and
water operating temperature of 45°C.
2 Valves shall be the same size as the incoming line size with a clear waterway equal to
the full nominal diameter of the valves and shall be opened by turning
counterclockwise.
3 The operating nut or wheel shall have an arrow cast in valve indicating the direction of
opening.
4 Valves smaller than 110mm shall be all bronze or brass conforming to BS or ASTM
with screwed end connections. Valves 110mm and larger shall be cast iron body, and
shall conform to BS or ASTM with flange end connections.
1 Ball valve for 50mm diameter size and smaller shall have a durable PVC body and
stem with impact-resistant Anti-lock Braking System (ABS) handle, rapid ¼-turn on/off
control, self-adjusting seals to compensate for water and a “pre-loaded” Ethylene
Propylene Diene Monometer (EPDM) stem seal for longer life.
2
2 They shall have an operating rating of 1 N/mm at 15.5 °C.
1 The ‘Y’ strainer shall be made of brass and shall have threaded connections.
2 It shall be fitted with a polyamide screen of 100 micron mesh.
2.12 Boxes
(b) they shall be constructed of fiber glass reinforced plastic or concrete with cast iron
trim, as approved by the Engineer
(c) box sizes shall be adequate for the proper function of item housed including
allowance for future component replacement
(d) all writing shall be molded into the lid material
(e) the writing shall be in black enamel and shall be in Arabic and English the
minimum height of letters and numerals shall be 38 mm.
2 Backflow preventer boxes shall be rectangular boxes with a lockable cover. They shall
have “IRRIGATION VALVE” written on the cover.
3 Emitter boxes shall be molded polypropylene construction with twist-lock cover. They
shall have “IRRIGATION WATER - DO NOT DRINK” written on the cover.
1 Dripline shall be 16mm outside diameter pressure compensating and extra flexible
tubing for fast & easy installation.
2 The tubing shall be dual-layered (brown over black or purple over black in color for non-
portable water) to provide unmatched resistance to chemicals, ultra-violet damage and
algae growth.
3 The drip line shall be installed at grade level, just below grade level, or under mulch.
4 The pressure-compensating inline emitter tubing should have 0.7 to 4.1 bar operating
and flow rates of 2.3 L/hr and 3.5 L/hr with a required filtration of 120 mesh.
1 Electrical materials for irrigation purposes shall comply with the relevant provisions of
Section 21, Electrical W orks.
2 Electrical wiring, unless shown otherwise, and all control conductors shall be solid
copper, 600 volt AC, to BS 7562 or National Electrical Manufacturing Association
(NEMA) Standards.
3 Low voltage cables shall be suitable for direct burial.
4 Non-degradable marker tape shall be laid at a depth of 300 mm below finished grade
over the entire route of the underground wiring system.
5 The Contractor is responsible for calculating the cable sizeconfigurations required and
cable drawing route &layout shall be provided by the Contractor.
6 The cable shall be approved for use by the manufacturer for the environment within its
operation.
7 All cablesshall be ducted into position, ducts shall be to EN1401 – BS3506, and shall
determined and supplied by the Contractor complete with necessary chambers and
draw chords.
8 All cables will be UV resistant and have a temperature operating range suitable for the
climate in State of Qatar.
9 Electrical cables will be jointed/established using approved national techniques and as
per manufacturer’s instructions.
2.15 Signage
1 Unless noted otherwise, all identification signs shall read in Arabic and English.
2 Construction of signage shall be porcelain-enameled steel. Colors, size and placement
or mounting system shall be as approved by the Engineer.
3 Signage identification shall be provided for RTU enclosures with the wording
“IRRIGATION CONTROL EQUIPMENT” and enclosure number.
4 Control valves shall be identified with a brass label engraved with valve tag number
and shall be attached to valve with copper wire.
1 The irrigation pump must be a pressure booster setand shall comply with the relevant
provisions of BS 5257 and with the QCS 2010, Section 19, Plumbing Works.
2 The irrigation pump shall be a booster set that should meet the peak irrigation water
demand and shall have minimum residual pressure of 3 bars at the farthest solenoid
valve.
3 The booster set shall comprise variable speed duty/standby pumps, control panel with
auxiliary contacts, pressure vessel, valves, digital pressure & temperature gauges, inter
connecting pipe, and others as shown in the drawing.
4 Materials of Construction:
(a) Pump
The pump system shall composed of three (3) vertical multistage centrifugal
pumps (booster pump set) fitted with standard motor.Each pump should consist of
a base and a pump head. The chamber stack and outer sleeve shall be secured
between the pump head and the base by means of staybolts.
The pumps shall be equipped with mechanical shaft seal.The base shall have a
suction and discharge ports on the same level (in-line) and of the same port size.
Pump head and base should be made of cast iron with stainless steel shaft,
impeller, chamber, and outer ring. All other hydraulic parts of the pump must be
made of stainless steel.
(b) Motor
Motors shall be totally enclosed, fan cooled (TEFC) rated 415 V, 3 phase, 50 Hz,
A.C. system, and should have a minimum Class ‘B’ insulation.
All motors should suit the maximum temperature of air passing over the motors
and the additional temperature rise caused by exposure to the sun.
All motors brought to site not complying with the above mentioned voltage and
insulation requirements shall not be accepted.
(c) Manifold
Suction and discharge manifolds shall be made of galvanized iron (GI) pipe,
Schedule 40. Such manifolds should be fitted on the suction and discharge side of
the pumps.
Gate valve shall be fixed between the suction manifold and the individual pumps.
While a gate valve and non-return valve shall be fitted between the discharge
manifold and the individual pumps as shown in the drawing.
The control panel shall be built-in with all necessary components (e.g. with a fan to
remove the surplus heat generated by the frequency converter).
The control panel should be mounted on its own steel angle base frame. This shall
be suitable for floor mounting.
The cable supplied shall allow the control panel to be placed up to 2 meters from
the pump system.
The control panel shall be provided with auxiliary contacts for integration to
Building Management System (BMS).
The pressure vessel shall be made of steel construction with replaceable bladder
for alimentary use, flexible enough to allow full expansion inside the tank.
The internal surface of the vessel should be coated with epoxy polyester resin
ideally suitable for potable and non-potable water application.
The vessel shall be pre-charged with nitrogen to the correct pressure at test stage.
1 Coupler swivels and quick coupling valves must be compatible and from the
samemanufacture.
2 Couplers shall be 38mm brass key fitted with a steel handle to fit the specified valve.
3 The hose swivel shall be 38mm x 18mm female by male thread, all brass construction
with “O” ring seal, and have a full 360° swivel action in any direction.
4 The valve lid key shall be steel construction, tee-shaped, with a square lug.
5 Control valve keys shall be constructed of solid steel, cadmium plated, and have a
shaft length of 750mm.
1 Manufacturers of listed equipment shall provide keys and all keys shall be permanently
and legibly identified to the related service.
2 All control system enclosures shall be keyed alike.
3 The Contractor shall provide keys for both RTU enclosures and quick couplers in the
numbers as specified in the Project Documentation or as agreed by the Engineer.
1 The Contractor shall provide plastic water sampling containers with a screw-on lid
capable of secure and watertight fit. The containers shall have a minimum capacity of
one liter and each shall be provided with a self-adhesive identification label.
2 Backflow prevention device test kit: The Contractor shall provide one (1) complete test
kit as recommended in writing by the backflow prevention device manufacturer.
3 Emitter line pressure testing assembly shall be provided by the Contractor to include
the following:
2
(a) hermetically sealed pressure gauge: the gauge shall be dual reading in kg/cm
and psi with 50mm diameter face, shatter-proof lens, neoprene cover and
molded-in diaphragm; bottom connections shall be standard 6 mm threaded
brass
(b) fittings
(c) cast bronze hex reducer: 18mm male iron pipe thread by 6 mm female iron pipe
thread
(e) red brass nipple: 18mm diameter, male threaded both ends and have a minimum
length of 150mm.
3. PROTECTION
1 All materials shall be handled and shipped or otherwise conveyed in such a manner as
to assure no damage.
2 All boxes shall be securely sealed and clearly marked with the name of the
manufacturer.
3 All pipes shall be protected from crimping, crushing, and splitting.
4 All non-metallic system components shall be protected from sunlight exposure as per
the manufacturer’s recommendations.
1 Work and materials shall be protected from damage during storage, and
installation/construction.
2 Particularly non-metallic pipes and fittings shall be protected from direct sunlight during
storage.
3 Facilities of the necessary dimensions should be provided and maintained for storage
and all non-metallic irrigation materials in their entirety.
1 The Contractor shall determine the location of underground utilities and perform work in
a manner which will avoid possible damage.
2 The Contractor shall hand excavate, as required, to minimize possibility of damage to
underground utilities.
3 The Contractor shall maintain grade stakes set by others until all parties concerned
mutually agree upon their removal.
4 Existing roads and footpaths shall not be cut during trenching and installation of pipe
unless otherwise approved by the Engineer.
5 The Contractor shall inspect all products for damage immediately before installation.
6 Any products that are found to be damaged or not in accordance with the specifications
shall immediately be repaired or removed from the site and replaced. Repairs shall not
be undertaken without the Engineer’s approval of Contractor’s proposed action.
4. INSTALLATION
1 The Contractor shall layout and provides verification of irrigation system installation as
follows:
(a) verify all horizontal and vertical site dimensions prior to staking
(b) stake-out the location of all pipework, valves and other irrigation works
2 The Contractor shall not relocate any existing construction without first obtaining the
Engineer’s approval. The Contractor shall remove and relocate such items, at his
expense, if so directed by the Engineer
3 Before starting work on irrigation system, the Contractor carefully check all grades to
determine that work may safely proceed.
1 The Contractor shall coordinate and provides water and electrical connection points as
follows:
2 The Contractor shall be responsible for making connections to existing piping, valves,
conduit, and appurtenances utilizing proper adaptation tools and procedures.
1 Isolation valves shall be installed in individual boxes and placed no closer than 300mm
to paving or structures.
2 Quick coupling valves shall be placed no closer than 300 mm to paving or planter walls.
3 Solenoid/remote control valve assemblies shall be grouped together where practical.
They shall be placed no closer than 300 mm to paving and housed in an individual box.
4 Boxes for valves and valve assemblies shall be placed in a neat and orderly fashion as
follows:
(a) set top of all boxes parallel with grade and as detailed
(b) place parallel to paving, curbs, walls or similar structures and in case of more
than one box, parallel to each other
(c) cover box base openings with fiberglass matting; the dimensions of the matting
shall be as required to block all soil intrusion
(d) review all box locations with Engineer prior to installation of valves
(e) valve boxes shall not rest or come in contact with valve, piping, hose or conduit.
1 All electrical work shall be in conformance with Qatar General Electricity & Water
Corporation (QGEWC) Regulations which inclusive of the following:
(e) secure specified wire markers on all wires at both ends, clearly indicating circuit
number or function
(f) provide corrosion resistant, sunshield, when required to protect Remote Control
Unit (RTU) from direct sun rays
(g) before connecting subject all wiring to testing. Replace wiring failing test and
retest to satisfaction of the Engineer.
(a) make connections to terminals after written notice to proceed from the Engineer
(b) install all wiring entering controller enclosure, valve and electrical boxes in short
run of concrete encased ducts
(c) direct burial of signal wire shall be made in same trench as irrigation piping,
securing wire to pipe at 3 meters internals
5 Control valve wiring shall be spliced utilizing specified epoxy packets in valve boxes.
Dead-end control wiring shall comply with the following:
(a) where indicated on the drawings, all dead-end wiring shall have an additional
length of 1.0 m and shall be insulated to the satisfaction of the Engineer
(b) provide protective boxes for all dead-end wiring as required and as directed by
QGEW C and/or the Engineer; where possible group dead-end wiring to be
protected in same box
(c) identify and properly mark all protective boxes to the satisfaction of the Engineer.
6 Cable shall be installed in such a manner that ensures that it is not stretched/
scraped/damaged/laid down under tension. The cable will be installed within a suitable
ducts with necessary draw points as required.
7 Cable shall be laid to a minimum depth of 600mm in mainlinetrenchlines.
8 Wiring under streets, driveways and other vehicular areas, and under walkways, plazas
and other hardscape areas shall be installed as specified in Section 6, Roadworks:
9 For concrete pads, chambers and ducts, the Contractor shall:
(b) in paved areas, make the top of box flush with top of finished paved surface, and
suitable for bearing the intended traffic
(c) in soil areas, the top of chamber shall be set at 25 mm above finish grade.
4.7 Clean-Up
1 Upon completion of the work, the Contractor shall restore the ground surface to
required elevations and remove excess materials, debris and equipment from the site
to satisfaction of Engineer.
5. SYSTEM TESTING
5.1 Purging
1 Immediately prior to hydrostatic testing, all irrigation lines shall be thoroughly purged of
all entrapped air.
2 Mainline piping system may be tested in sections. Lateral systems shall be
tested valve by valve.
3 Water shall be discharged from a single outlet by manipulation of isolation
control valves and installation of temporary caps.
4 Water shall be introduced into lines to be tested at full operating head and the water
flow at end discharge point, and observed until all air and residual debris has been
expelled from the line.
1 Individual parts of the main network between isolation valve points having a length not
greater than 500 meters shall be tested before backfilling operation.
2 Test shall be made only after completion of the above operations and not until at least
seven days after the last concrete thrust anchor block has been cast.
3 Contractor shall supply all testing material and equipment, including all caps, valves,
pumps, tanks, water and gauges as required.
4 Pressure gauges shall be dual reading in bar and psi units. Calibration shall be such
that accurate determination of potential pressure loss can be ascertained.
5 The section of the main pipeline to be tested shall be filled with potable water and all air
expelled. After the main pipeline has been completely filled, the pressure shall be
steadily and gradually increased until the specified test pressure has been reached.
Simultaneous pressure and leakage tests and separate pressure test shall be made at
150% of working pressure at the point of test, but not less than 125% of normal working
pressure at highest elevation. Separate elevation test shall be made at 150% of normal
working pressure of the segment tested. The minimum pressure test for mainlines is 9
bars and leakage test for lateral lines. Duration of pressure and leakage tests shall be 4
hours. All testing shall comply with AWWA M23-80, Polyvinyl Chloride Pipe Design and
Installation.
6 Separate tests shall be applied to the lateral distribution pipe work and the irrigation
pipe work from the remote control valves outwards. Test pressures for these shall be
as described above.
1 The tests as specified above shall be repeated for the entire network after pipelines
have been backfilled, cleaned and inspected.
2 Each test shall be restricted to pipes of one class and particular care shall be taken to
isolate air valves, etc. and not to apply higher pressures than specified at any point on
the pipeline and to ensure that the pipelines are adequately anchored before any test is
carried out.
1 Written records of every test clearly identifying the tested section of the pipe together
with time of test and name of testing engineer in tabulated format shall be submitted for
review and approval by the Engineer upon completion of the tests.
6. FLUSHING
6.1 General: On completion of the system test, the system is to be thoroughly flushed,
the velocity of water being at least 1m/s. Should the main water supply be
unavailable or inadequate for this purpose at the time of flushing, then a swab of
adequate size shall be used to remove all foreign matter from the pipeline. This
process shall continue until the pipeline is completely clean. Each control valve
shall be opened separately and the terminal systems also thoroughly flushed.
After completion of flushing, the emitters and other discharge devices shall be
fitted.
6.2 Operation Test: After the hydrostatic test, emitters shall be installed and the
system completed and tested to demonstrate functional efficiency. This shall be
prior to covering the lateralswith mulch (if necessary).
6.3 Testing and Commissioning: On completion of the entire irrigation system
installation, the system shall be commissioned to demonstrate the proper
functioning of the system. The process of commissioning shall be carried out in the
presence of the Engineer’s Representative.
6.4 Adjustment and re-testing of control valves and others shall be carried out until
satisfactory result is obtain and the whole system is functioning to the design
requirement.
(e) Maintenance program by date for each component and the description of the
maintenance procedure, cleaning, flushing, lubricating, changing parts & updating
(f) The general manual headings and descriptions should be both Arabic and English.
7.4 Others
(a) The contractor shall operate and maintain the irrigation system throughout the
maintenance period, and shall provide staff in full time attendance throughout the
period.
(b) The maintenance of the irrigation system shall cover all work necessary to
adequately operate and keep all irrigation equipment, valves, pipelines and
appurtenances in proper operating condition, all to the satisfactory of the
Engineer.
Supply of irrigation water with suitable quality and adequate quantities to meet the
irrigation requirements. The contractor shall arrange to obtain water from an approved
source. A full analysis of the irrigation water shall be submitted to the Engineer for
approval and then at one month intervals thereafter during the maintenance period.
Irrigation of areas forming part of the works at a frequency and depth as required for
every season in the maintenance period.
Maintenance and repair of all irrigation equipments, pipes, valves and all appurtenances;
records shall be kept of all maintenance, repairs and operation activities carried out
during the maintenance period.
The contractor shall provide to the Engineer at the end of the maintenance period a
report which shall include details of the date, location and type of work performed, all
repairs and replacements, the amount of water applied and the duration of each irrigation
cycle, results of water analysis and all other relevant information of work and activities
carried out during the maintenance period.
PRODUCTS MANUFACTURER
Dripline RainBird
Hunter
Al Wasail
Hepworth
Qatar Plast
Rain Bird
Toro
RainBird
Hunter
Rain Bird
Al Wasail
Toro
Pullen
Saer
Crane
Armstrong
Al Wasail
END OF SECTION
AT
Leqtaifiya
November 2015
Section 22
AIR CONDITIONING AND VENTILATION
TABLE OF CONTENTS
CLAUSE TITLE PAGE
2. EXCLUSION ........................................................................................................................... 1
3. STANDARD OF WORK.......................................................................................................... 1
4. PROGRAMME ........................................................................................................................ 2
7. DESIGN DATA........................................................................................................................ 2
8. INTRODUCTION ..................................................................................................................... 6
SECTION 22
AIR CONDITIONING AND VENTILATION
1. EXTENT OF CONTRACT
1. The work under this section of the specification shall include for the supply, delivery to site,
installation, testing and commissioning and setting to work the new Air conditioning and
Ventilation systems for the Westbay Villa, as given hereunder:
a). All air conditioning and ventilation system complete with all accessories and controls, as per
specifications, schedules and drawings.
b). Complete air distribution system, return air collecting system, fresh air and ventilation system
as shown on the drawings and as specified.
c). Various controls, instruments and their connections, electrical works related to air
conditioning and ventilation systems as detailed in the specifications.
d) The complete building shall be provided with BMS control system for maintaining all the
conditions as detailed in the design data, Kahra-maa / QCS requirements and as specified
herein and in the drawings.
2. The Contractor shall provide all the materials, labour, cartage, plant and appliances necessary
for the supply, installation, testing and commissioning of the work and all other minor and
incidental works necessary for the system.
3. The specifications and drawings are intended to indicate the nature and scope of the project.
The Contractor shall be responsible for the installation of plant of the correct capacity and shall
guarantee the efficient performance of the equipment.
2. EXCLUSION
1. Items necessary for the completion of the plant but not included in the tender are to be listed as
exclusions. It will be assumed that any items or services necessary to the air conditioning plant
and not specifically excluded will be provided by the Contractor even if not mentioned in the
tender.
3. STANDARD OF WORK
1. Unless otherwise specified, all equipment is to comply with the current Kahra-maa regulations,
relevant British and American codes of practice as listed below. However, the Kahra-maa / QCS
latest regulations shall take precedence over all other regulations.
a. ASHRAE : American Society of Heating, Refrigeration and Air
Conditioning Engineer
b. IHVE : The Institute of Heating and Ventilation Engineers (UK)
c. ASME : American Society of Mechanical Engineers
d. ARI : Air conditioning Refrigeration Institute (USA)
e. ASTM : American Society of Testing and Materials
f. AW S : American Welding Society
g. DW142 : Specification for Sheet metal ductwork
h. SMACNA : Sheet Metal and Air conditioning Contractor's National Association
i. AIA : American institute of Architects
j. QCS : Qatar Construction specification
k. NFPA : National Fire Protection Agency
l. ARI : American Refrigeration Institute
m. CDC & HICPAC : Healthcare infection control practices advisory committee U.S.A
n. USDHHS : United State Department of Health & Human Services
2. The workmen employed must be accustomed to the highest class of air conditioning installation.
3. A competent Engineer must be in regular attendance throughout the whole contract. The whole
of the installation shall be executed in conformity with the drawings, specifications, internationally
accepted codes of practice and local regulations.
4. PROGRAMME
1. Immediately on receipt of an order the Contractor shall prepare a programme detailing the
services and sequence of installation.
2. Approval of programme by the Engineer or Client shall not relieve the Contractor from his
obligations to execute and complete the works in conformity with the directions and requirements
of the Engineer.
6. PRACTICAL COMPLETION
1. The Contractor shall deliver the Operation and Maintenance Manuals along with the 'As-built'
drawings and loose items if any to the Client before practical completion. The completion
certificate will be issued by the Engineer after obtaining the Operation and Maintenance
manuals.
2. Recommendation for release or the release of Practical Completion Certificate would not absolve
the Contractor of his responsibility to provide the installation complete in all respects and in
satisfactory working order. If any item is discovered later during commissioning, maintenance
period or at F.C.C. stage to be short supplied or not in working order, the Contractor shall be
liable to make good the same to the satisfaction of the Engineer.
7. DESIGN DATA
O
BEDROOMS 22 +/- 1 C, DB 50%RH
O
KITCHEN 22 +/- 1 C, DB 50%RH
O
LOBBIES 22 +/- 1 C, DB 50%RH
O
Entrance/FAMILY HALL 22 +/- 1 C, DB 50%RH
2
BEDROOMS 2.0 W/ Ft 561 watts
2
Hallway 2.0 W/ Ft -
2
Lobby 2.0 W/ Ft -
2
Entrance Hall 2.0 W/ Ft -
2
Toilet 2.0 W/ Ft -
Note: The above rates have to be adjusted as per the actual values designed by the
electrical Engineer.
Living rooms 30 - 35
Dining rooms 30-35
Halls/Lobby 30-35
Bed rooms 25-30
Kitchen/Corridor/service areas 35 - 40
Electrical room 35-40
7.7 General
The ductwork sizing and room air distribution were considered in accordance with
the ASHRAE and SMACNA Standards. Friction loss and velocities were generally
considered as follows:
Duct pressure losses will be calculated in accordance with the ASHRAE Handbook
Fundamental during the Tender Document stage
Sensible : 10%
Latent : 5%
Total Cooling load : 20 %
1. The air conditioning scheme is based upon chilled water system having air cooled screw chillers
and air handling units.
2. It is proposed to provide 3 nos. air cooled screw chillers in which two(2) chiller shall be capable
of meeting the full load in peak environmental conditions and one Chiller as standby. The chillers
shall be located in the chiller yard at roof as shown on the design drawings.
3. These chillers shall be connected to 3 nos. pump sets, each to cater 50% load of all the chillers.
One of these pumps shall therefore provide 50% standby facility. The chilled water pumps shall
be installed in the Pump room at the roof. The distribution of chilled water pipe work to the
various air-handling units shall be carried out in accordance with the design drawings. Exposed
pipe work on the roof and Pump room etc., shall be aluminum cladded.
4. chemical dosing pot shall be included in the system for chilled water treatment.
5. The complete building shall be divided into various zones depending upon the utility, usage of
space, individual temperature requirement etc.
10. VENTILATION
10.1 Toilets
1. These areas shall be mechanically ventilated centrifugal exhaust fan and centralized ducting
system is utilized complete with all diffusers to areas being serve
10.2 Controls
1. The complete building shall be provided with BMS control system for maintaining all the
conditions as detailed in the design data, Kahra-maa / QCS requirements and as specified
herein and in the drawings.
1. All equipment and materials shall be brand new, of a quality accepted by the Engineer and
presenting no dent, damage or breakage during transportation or installation. All metal parts
shall be protected on site from rust, corrosion and dirt by properly storing, packing and
covering. All rusted parts of metal, subject to the Engineer's approval shall be cleaned of
corrosion products and given two coats of anti-rust paint before installation.
11.4.1 General
1. All drawings and material submissions, other information and samples must besupplied to the
Engineer as laid down in the specifications and as and when agreed during the site meetings,
in the progress chart or as instructed by the Engineer.
2. The work described on any shop drawing submitted shall be properly checked by the
Contractor for all clearance, field conditions, maintenance space and proper co- ordination.
Equipment layout is to be detailed on drawings showing the exact method of installing and
clearly illustrating components to be used in making all connections.
3. The Contractor shall submit to the Engineer, shop drawings of all sheet metal ductwork and
pipework for approval before work is fabricated and installed.
4. Ductwork drawings must show clearances between the ductwork and masonry. All dampers,
fresh air inlets, exhaust outlets, connections to equipment and methods of support and any
other details necessary for the satisfactory installation of the system must be indicated. Each
type of register, diffuser and louver is to be referenced in a schedule and the type and size
clearly indicated at each location.
5. Piping drawings must be fully detailed showing all piping in double line and indicating the
precise size of fittings, valves and equipment.
6. Position of hangers and supports with reference numbers must be indicated and large scale
detail must be given showing the type and method of installation of each type of hanger. A
schedule is to be included on each drawing, detailing the type of hanger fixing with a reference
number for each type.
7. All general layout drawings are to be drawn in 1 : 50 scale. Details of hangers, method of
fixing of pipes and ducts, detailed cross sections of pipes, ducts and risers, details of control
and piping connections to equipment are to be drawn in 1 : 10 scale.
8. In case the Contractor fails to produce the shop drawings and co-ordinated shop drawings in
accordance with the specified/agreed time schedule, the Engineer reserves the right to
engage an outside agency to undertake this work and debit the entire cost to the Contractor's
account.
9. At all places where multiple services cross over, the Contractor shall submit specific details on
the drawings of all services on a larger scale, which should be thoroughly checked by the A.C.
Contractor for their location, clearances, method of fixing etc., before submitting to the
Engineer for approval.
10. The Contractor shall prepare drawings and schedules showing precise details of holes in
concrete, masonry etc., and necessary wooden frames required for passage of ducts, pipes
and fittings of grilles, registers, diffusers, louvers, plant, plant supports etc. Drawings and
schedules approved by the Engineer must be available before any structural work requiring
holes or other modification is constructed. This schedule is to be submitted in a form to be
agreed with the Engineer.
11. All drawings prepared by the Contractor shall be submitted in the form of three sets of blue
prints to the Engineer for approval, who in turn, after making his comments will return one
set of the same to the Contractor for necessary revisions if any. Thereafter the Contractor
shall submit five sets of blue prints for the Engineer's final approval. Once the drawings
are finally approved, the Contractor shall submit in reproducible copy negative for Engineer's
signature and the same shall be kept on site for execution. It is the Contractor's responsibility
to co-ordinate all grilles, equipment, pipes, light fittings, false ceiling layout and other services
to allow a completely symmetrical installation.
12. The Contractor shall supply to the Engineer a set of 'As-installed' drawings showing the works
'As-installed' together with any other information necessary for operation and maintenance.
Six copies of each such drawing shall be supplied. In addition, two sets of copy negatives for
each drawing shall be handed over to the Client.
11.4.4 Manuals
1. The Contractor shall make provision for the supply of three copies of the Instruction Manual
before issue of Practical Completion Certificate.This manual shall include the following items
a. Complete list of all items of equipment, controls and accessories as actually supplied
including serial nos. and all name plate details.
b. A set of 'As-built' drawings showing equipment layout foundation details, ducting layout
and details, electrical wiring and drain piping. The drawings shall show plans and sections
necessary to show all required information correctly.
c. A set of manufacturer's catalogues, wiring diagram and installation drawings relevant only
to the particular item of air conditioning and ventilation equipment concerned. General
catalogues will not be acceptable.
d. Manufacturer's printed spare parts list for all items of equipment.
e. Operational description of the air conditioning plant including starting, stopping and
seasonal shut-down.
f. Preventive maintenance routine at weekly, monthly and yearly maintenance procedures
for all plant and equipment. intervals and
g. Manufacturer's full name and address together with telephone, fax numbers.
h. Name, address, telephone and fax numbers of local agents / suppliers.
12.1.1 General
1. The Contractor shall submit to the Engineer, one month prior to the date of commencement of
the tests, six (6) copies of the complete test procedures to be used. The procedure,
method of calculation etc., shall be approved by the Engineer before any test is carried out.
Six (6) copies of the test results shall be furnished to the Engineer for his approval.
2. The Contractor shall supply skilled staff and all necessary instruments and carry out tests of
any kind on a piece of equipment, apparatus, part of system or a complete system if the
Consultant requests such a test, for determining specified or guaranteed data as given in the
specifications or in the schedule of equipmentfilled in by the Contractor.
3. Any damage resulting from the tests shall be repaired and/or damaged material replaced, all
to the satisfaction of the Engineer. In the event of any repair or adjustment required to be
made, other than the normal running adjustment, the tests shall be void and shall be
recommended after the adjustments or repairs have been completed. The tests shall not be
void due to circumstances beyond the Contractor's control.
4. All testing, balancing and final adjustment shall be in accordance with the provision of the
applicable 'ASHRAE' standards.
5. Shall perform performance tests at factory simulating with project design conditions at factory
in presence of consultant engineer.
12.1.3 Ductwork
1. All branches and outlets shall be tested for air quantity and the total of the air quantities shall
be within five percent of fan capacity. Volume control dampers and splitter dampers shall be
tested for proper operation.
12.1.4 Equipment
1. All air handling and ventilating equipment, ductwork and air outlets shall be adjusted and
balanced to deliver the specified air quantities indicated at each inlet and outlet on the
drawings.
2. Where the equipment or systems depend upon controls for proper operation, functioning and
performance, the latter shall be operated simultaneously with the equipment or system during
tests. If air quantities cannot be delivered without exceeding the speed range of the sheaves
or the available horse-power, the Engineer shall be notified before proceeding with the
balancing of air distribution system.
Eng.Adnan Saffarini Consultants
Westbay Villa
3. Other tests as specified under the specific equipment headings are to be completed to the
satisfaction of the Engineer.
2. During the last month of the Maintenance period, the Contractor shall demonstrate to the
Engineer that all equipment and systems are operating according to the capacities and the
manner set down in the specifications. On completion of these tests, the Engineer shall issue
a formal letter of acceptance for the equipment and system or parts of the system satisfactorily
tested and approved.
3. The Maintenance Certificate will not be issued to the Contractor by the Engineer until all plant
has received the above mentioned letter of acceptance and/or unless a bank guarantee is
provided by the Contractor for the performance of that part of the plant and equipment not
formally tested and accepted.
13.1.1 General
1. The Contractor shall provide and install microprocessor controlled packaged air cooled chillers
having screw compressors working with HFC R-134a refrigerant, air cooled condensers,
flooded/DX evaporators, controls including starters within the panels. The capacity of the
chillers shall be as indicated in the schedule. The unit shall be designed, manufactured and
tested in a facility with quality assurance system certified to ISO 9001.
2. Each chiller shall have at least two independent refrigerant circuits. Each circuit shall have one
screw compressor.
3. Contractor may however offer chillers that have two compressors connected in parallel to
common refrigerant circuit. This shall be accepted at the discretion of the Engineer subject to:
a. Such equipment being manufactured by a reputed manufacturer represented and
approved for use in the State of Qatar.
b. The type of equipment offered having been in satisfactory use in Qatar for a period of at
least 5 to 10 years.
c. Extended 5 years guarantee being offered on the parallel running compressors including
recharge of gas and oil in case of burn-out.
d. Tandem arrangement is not acceptable.
4. The system shall operate on 415 / 240 volts, 3 phase, 50 Hz. at 115°F ambient temperature
and the plant shall be capable of providing not less than specified capacity at the specified
conditions as mentioned in the schedule.
5. The capacity rating shall be as per ARI or EUROVENT standards and manufacturer shall be
equipped with testing facilities at the required full load design conditions.
13.1.4 Evaporator
1. The units shall be supplied with shell and tubes counter-flow evaporator single refrigerant
pass, it will be direct expansion with refrigerant inside the tubes and water outside (shell side)
with carbon steel tube sheets, with straight copper tubes that are spirally wound internally of
higher efficiencies, expanded on the tube plates.
2. The flooded evaporator shall be mechanically cleanable, shell-and-tube type with removable
heads. Tubes shall be internally and externally grooved, seamless-copper, and shall be rolled
into tube sheets. Shell shall be insulated with 19 mm thick closed-cell foam. Evaporator
thermal insulation shall be factory fitted.
3. The evaporator will have 2 circuits, one for each compressor and shall be single refrigerant
pass.
4. The cooler shell insulation will be weather proofed with glass cloth & vapour barrier.
5. Evaporator is manufactured in accordance to ASME or equivalent and tested for refrigerant
side working pressure of 360 PSI and water side working pressure of 150 PSI. Coolers shall
be provided with water vent & drain connections.
13.1.5 Motors
1. Refer to Electrical Section.
2. The condenser/heat exchanger shall consist of multiple transversal V shaped coils to provide
self protection. Each V will have an angle superior to 50° to ensure optimum air distribution.
Coils with integrated sub cooling will be entirely made of aluminium to limit galvanic corrosion
and will offer a resistance to corrosion compatible with coastal or urban environments. Coils
will have a thickness of 1 inch to generate low air pressure drop and offer reduced sensitivity
to clogging. Coil shall be easily cleanable using a high pressure cleaner. This alternative shall
be acceptable subject to the whole condenser coil assembly being provided with factory
applied epoxy coating.
3. The coils will have an integral subcooler circuit which provides sufficient subcooling to
effectively eliminate the possibility of liquid flashing and increase the unit’s efficiency without
an increase in power absorbed.
4. The condenser coil shall be coated with suitable protective coating to safeguard against the
salt-laden corrosive atmosphere. The coating shall be guaranteed to last for minimum 5 years.
5. However the hole condenser coil shall be complete with factory applied epoxy coating.
6. Condenser coils shall be air pressure tested at 450 PSI under water.
2. The microprocessor shall withstand the surrounding air temperature of 50°C ambient. The
microprocessor shall be fully programmable type and suitable to be linked with the BMS at
later stage. The microprocessor control system shall be capable of performing the following
functions:
13.1.11 Controls
1. Compressor sequencing with lead-lag selection.
2. Compressors loading and capacity control
3. Pumpdown with safety function.
13.1.12 The microprocessor control shall provide an instantaneous visual display, the functional
status of the following:
1. Freeze protection (low leaving chilled water protection).
2. Low pressure switch each compressor
3. High pressure switch each compressor
4. Oil failure switch each compressor
5. Electronic motor protection each compressor
6. Pump down Manual/Auto each circuit
7. Control disconnect switch each circuit
8. Compressor(s) sequence lead
9. Compressor(s) sequence lag
10. All compressor(s) stages
11. Fan cycling switches for mild ambient operation
12. Fault reset
13. Entering and leaving water temperature
14. The function of the microprocessor control may vary slightly from one manufacturer to another.
13.1.13 Diagnostics
1. Diagnostic display module shall be capable of indicating the safety lock out conditions by
displaying a code for which an explanation may be scrolled at the display. Information included
for display shall be :
a. Low water flow
b. Low oil pressure
c. Cooler freeze protection
d. Thermistor and pressure transducer malfunction
e. Entering and leaving water temperature etc.
f. Evaporator and discharge pressure
13.1.14 Safeties
1. The control panel shall be equipped to provide the following protection:
a. Low water flow detection
b. Low chilled water temperature protection
c. Low control voltage protection
2. In addition to the above controls, the following shall be field supplied and installed as
components for the operation of the chillers:
a. Thermometer and gauges on inlet and outlet of chiller.
b. Double regulating valve on chiller outlet.
c. Isolating gate valve on chiller inlet and outlet.
d. Strainer on chiller inlet.
e. Flexible joints on chiller inlet and outlet.
f. Flow switches
Note: Chillers shall be capable to operate at an ambient temperature of 52°C. without failure.
3. The pressurization unit shall incorporate a break tank, two make-up pumps (one running, one
standby), twin expansion vessels, associated pipework and valves and controls.
4. The expansion vessels shall be of the pre-pressurized diaphragm type manufactured to BS 4814
and shall be subjected to a test pressure of 750 kPa.
5. The controls shall include the following:
a. Automatic pump change-over upon failure of duty pump indicated by pump failure light.
b. Manual pump selector switch.
c. Duty pump run light.
d. Hours run indicators for pumps.
e. Low pressure visible and audible alarm.
16.1.1 General
1. Air handling units shall be of size suitable for installation in the spaces provided and have
capacities as indicated in the air handling unit schedule.
2. The units shall comply with the following specifications:
a. The air handling units shall be completely factory built and assembled and shall have
sections and components as detailed in these specifications, drawings and schedules. Each
unit shall consist of a cooling coil, condensate pan, fan or fans, motor, filters, floor mounting
type channels with vibration isolators, controls and all other necessary components as
described below and shall be of compact size.
b. The unit casing shall be of insulated double skin construction from the best quality aluminum
alloy sheet properly reinforced and braced for maximum rigidity with bolted anodized
aluminum penta-post framework, suitable for the system operating pressures specified.The
casing shall be of sectionalized construction consisting of various sections as described
above. The Contractor shall provide sample of casing panel for Engineer’s approval.
c. Alternately, galvanized construction with 2mm internal & external polyster coating for the
panels can be accepted.
3
d. 50 mm thick rigid fiber glass insulation of density 48 kg/m and thermal conductivity 0.036
W/M°C., shall be sandwiched between the panels. Injected polyurethane or equivalent
material may be used, however the insulation thickness shall remain unchanged. AHU frame
and panel shall be of thermal bridge free construction to avoid condensation upto Engineer’s
approval. Factory built canopy shall be provided on the externally located air handling unit.
3. Probes for manometers etc., shall be factory installed.
5. Removable panels shall be incorporated in fan, coil and filter sections to provide good access
to internal parts. Latches shall be proprietary 'quick-release' and all hinges shall be of die-cast
construction.
16.1.6 Accessories
1. The air handling units shall be provided with the following accessories for the operation of the
unit:
a. Isolating valves at supply and return water lines.
b. Balancing valves at by-pass and main return water line of unit.
c. Three- way modulating valve.
d. Flexible connections at inlet and outlet.
e. Self sealing plugs.
f. Strainer on water inlet (flanged type).
g. Flanges and unions.
h. Automatic air vent.
i. Manometer across return air synthetic fiber pleated filters.
17.1.1 General
1. The plant required shall consist of air cooled split type air conditioning unit of wall mounted
type. The unit shall be composed of an indoor unit with refrigerant circuit and an air cooled
outdoor unit for application with R-410A / R-407C / R. 22 refrigerant.
allow. The unit shall be restarted by resetting the operation switch if any one of the protection
devices trips.
4. The pipe insulation shall be stuck to the pipe work with an approved adhesive. The insulation
shall be applied to the pipes with longitudinal joints staggered; laps and sealing strips shall be
sealed applying adhesive on circumferential joints.
5. Insulation shall be covered externally with 200 gm/sq.m quality glass cloth and painted with
two coats of approved weather proofing compound forming minimum thickness of 1 mm as per
Kahra-maa regulations.
2. The chillers shall be provided with suitable anti-vibration mountings. The anti-vibration
mountings shall be installed in accordance with the maker's recommendations and the
Mechanical Contractor shall ensure that the performance and type of isolator is suitable for the
machinery to be installed.
3. The air handling units and chilled water pumps shall have anti-vibration mountings in the
following form:
a. Multi-layer rubber pads with square grid convolutions on both sides, spaced with steel
shims and of a thickness to suit the points of uniform loading of the plant item, but of a
minimum thickness of 32 mm spaced not more than 750 to 1000 mm apart.
4. The condensing unit of split unit shall also have similar A.V. pads as described above.
However, the thickness shall be 10 mm.
21. DUCTWORK
21.1 General
1. The Contractor shall provide and erect all ductwork including controls, isolating/balancing
dampers, grilles, diffusers and vapor proof insulation to form a complete air distribution system
as indicated on the tender drawings. The Contractor shall balance, test and commission all
installations prior to the Engineer issuing a Completion Certificate. Shop drawings shall be
submitted to the Engineer prior to the commencement of works.
2. All sheet metal ductwork shown on the drawings, specified or required for various air
conditioning and ventilating systems, shall be fabricated and finished from best quality, cold
rolled annealed galvanized mild steel sheets of soft bending quality specially suitable for air
conditioning works. Materials used for ductwork, shall be free from blisters, pits and
imperfections in coating.
3. All bracing and reinforcement angles shall be preferably galvanized or made of black steel
properly cleaned from rust and painted with two prime coats of zinc-chromate paint prior to
installation, as approved by the Engineer. Angles shall be carried around all four sides of
ducts.
4. Reinforcing angles shall be fixed to the ducts by means of bolted joints made with cadmium
plated or galvanized steel hexagonal nuts and bolts with flat steel washers to the following
sizes :
* 25 mm angles : 6 mm diameter bolts at 10 cm center
* 38 mm angles : 8 mm diameter bolts at 10 cm center
5. Pockets, locks, deflectors and all branch ducts which need joints between two sheet metal
pieces, shall be made by aluminum rivets 5 mm diameter by 10 mm length minimum size
having head at one side. Rivets will be as specified in HVAC/DW /142.
6. Ductwork shall be so constructed that when erected, it shall be made air tight by tightly sealing
after fabrication and free from movement, sagging or drumming under all operating conditions.
It shall be true to size and accurately lined-up.
7. While the tender drawings shall be adhered to as closely as possible, runs and sizes of
ductwork may be varied only by the Engineer, at no extra cost to the Client, when deemed
necessary for co-ordination purpose with other works.
8. All duct elbows having an inside radius smaller than the width of the elbow shall be equipped
with approved vanes tightly riveted to the duct and in general as shown on the details of the
tender drawings.
9. Approved duct-turn shall be installed in all cases where 90 degree square elbows are used
and short take-offs are used on large ducts. Guide splitter vanes shall not be spaced more
than 15 cm apart.
10. Take-offs from main ducts shall be conical. All take-offs and connections shall be constructed
to minimize pressure loss. All raw edges of ductwork seams, rivets and areas where
galvanizing has been destroyed shall be cleaned, prepared and painted with zinc rich paint at
works and a further coat shall be applied after erection.
11. Allowances shall be made in ductwork construction for instruments and control connections
and adequate local stiffening shall be incorporated to provide rigid mountings.
12. The fabrication of ductwork shall be carried out in accordance with HVAC/DW/142, ASHRAE
or SMACNA standards.
13. Galvanized Sheet Hot dip galvanized steel shall be to ASTM-A527-87 standard, steel
shall be of lock forming quality, zinc coating designation Z-27 or
equivalent approved standard.
14. Flexible Ducting Pre-insulated flexible ducting for the linear diffusers shall be suitable
for low / medium pressure. The inner core shall shield the fibre glass
insulation from the air stream. The outer jacket shall be of very tough
spirally reinforced multi-layer aluminum laminated construction.
15. Duct Sealant Duct sealant shall be non hardening, non migrating mastic or liquid
sealant as compounded and recommended by the manufacturer
specially for sealing joint and seams in the duct.
16. Aluminum Aluminum alloy sheet shall be easy to form and to join and shall have
extra resistance to moist atmosphere (BS 1470).
17. PVC/Polyethylene/GRP Suitable material shall be proposed by the Contractor for Engineer’s
approval.
4. The material shall have a penetration time of at least fifteen minutes when tested in
accordance with BS 476 and shall remain flexible and without strain or distortion. Flexible
connections shall be 150 mm minimum and 250 mm maximum in length.
Circular Duct
2. All channels and angles shall be pre galvanized and shall be painted with a further two coats
of grey paint on exposed metal parts after erection. Ductwork supports shall preferably be
positioned close to dampers, diffusers and all similar equipment. Ductwork supports shall in
general conform to HVAC/DW /142 or SMACNA standards. Galvanized serrated band with
insulating band type supports shall also be acceptable up to duct size of 600 mm except in the
Plant room. Cotractor to sumit complete details for approval before fixing.
28.1 General
1. Air outlets and air inlets of an approved make, type and model shall be provided with sizes as
indicated on the drawings. They shall be fitted with sponge rubber gasket behind the frames
and nylon bushings at the blades connection to the frame. All air outlets and inlets shall be of
white powder coated extruded aluminum / custom proprietary finish and a sample of all air
devices must be approved by the Engineer prior to ordering.
28.3 Diffusers
1. The diffusers shall be fitted with opposed blade volume control dampers as furnished by the
manufacturer. Volume controls for these outlets shall be accessible through the outlet from
below the ceiling and shall maintain their setting, when adjusted. Each diffuser shall be
provided with sponge rubber or felt gasket and angle ring or frame for securing to ductwork.
Return air diffusers shall be identical to supply air diffusers.
2. Diffusers shall be of the type and shape indicated on the drawings, a sample of which must be
approved by the Engineer prior to ordering.
28.5 Alternative
1. Contractor can offer circular adjustable diffusers of aluminum construction, however, throw
and noise level should comply with the requirement and specifications. The circular diffusers
shall also be fitted with opposed blade dampers.
Note :
All diffusers, grilles, registers, linear diffusers etc., shall be powder coated including the pattern
adjustment and volume control elements in linear diffusers to match the interior finish or as
advised by the Engineer.
No internal insulation or lining shall be used inside the ducts, plenums etc.
2. The silencers shall be provided in the supply and return air ducts as shown on the tender
drawings. The silencers shall be constructed and tested according to BS 4773 Part 1971 and
ASHRAE Standard 36 B-63 for dynamic insertion loss, self generated noise and aerodynamic
performance. The outer casing of the silencers shall be constructed of 22 gauge galvanized
sheet steel. Baffles shall be made of 24 gauge perforated galvanized steel, filled with an
odourless, incombustible, vermin and moisture proof inorganic sound absorbing material. The
fill shall be compressed 10% and shall be of a density sufficient to meet catalogued
performance. The acoustical fill shall have the following minimum ratings - flame spread not
over 25, smoke developed not over 20. The silencers construction shall be such that
perforated sheet shall cover the black neoprene sheet over the insulation in order to avoid
ingress of fiber particles.
3. The silencers shall be complete with flanges to facilitate their removal for inspection.
Externally, the silencers shall be insulated in the same manner as the adjoining air ducting.
The Contractor shall carry out sound absorption calculations with respect to the characteristics
and the duct system to ensure the proper selection of silencers.
31.1 General
1. Each part of the system of piping shall be complete in all details and provided with all control
valves and accessories necessary for satisfactory operation. The tender drawings indicate
generally the sizes of all main piping but the right is reserved to modify the runs of piping to
accommodate conditions during construction.
2. All piping shall be grouped wherever practical and shall be erected to present a neat
appearance. Pipes shall be parallel to each other and paralleled or at right angles to structural
members of the building and shall give maximum possible headroom. Piping shall not pass in
front of door ways or windows and shall be generally arranged so that it is at least 2.5 cm from
the finished wall face. Sufficient space is to be allowed for accessibility, servicing and proper
insulation works.
3. Sleeves shall be provided for pipes passing through walls or slabs. Pipes shall be pitched for
proper circulation and drainage.
4. Run-outs shall be graded in such a manner as to prevent air traps being formed within them
when the mains expand or contract. Automatic or open vents are to be provided at high
points, piped to suitable drains or terminating over expansion tanks wherever possible.
5. All drain piping shall pitch down in the direction of flow. All low points of the system must be
fitted with drain valves to allow the complete draining of the system. Bottom of all risers must
have dirt pockets of the size of riser and at least 15 cms long with a drain valve fitted. All
water piping to equipment and valves shall be connected with either flanges or unions for
dismantling and removal. All piping shall be reamed after cutting to remove all burrs.
6. All reductions in sizes of piping in the direction of downward pitch shall be installed with
eccentric fittings to maintain a level top.
7. Approved pipe fittings shall be used and bending of pipes will not normally be allowed, except
that bending of black steel pipes 50 mm nominal diameter and smaller shall be permitted,
where space conditions allow for a bending radius of at least 10 times the diameter of the
pipe. A hydraulic pipe bender shall be used to bend all pipes. Bends showing kinks, wrinkles
or other malformations will not be acceptable. Cutting and shutting of bends will not be
permitted.
8. Alternatively, Contractor can provide mechanical grooved system fittings with companion
couplings. The complete grooved system shall be submitted for Engineer’s approval and shall
meet ISO 9001 certification.
9. Piping shall not be installed passing through ductwork or directly under electric light outlets or
extend beyond footing lines, as determined by the drawings.
10. In placing pipes through sleeves, near walls, partitions or in chases, care must be taken to
provide sufficient space for pipe covering. Where pipes are held in vices, as and when
screwing, care shall be taken to ensure that the pipe surface is not damaged. Any pipe work
so damaged shall not be fitted.
11. All pipes stored on site shall be kept clear of the ground and where possible stored under
cover. Pipes corroded beyond normal 'stock-rust' condition shall not be used. Special care
should be taken to prevent dirt and foreign materials entering open ends of pipes during
erection. A valve fitted to the open end of a disconnected pipe will not be considered
satisfactory to prevent entry of foreign matter.
12. Screwed iron caps or plugs or plastic covers shall be used to seal pipe ends. Wood, rag
paper or other make-shift plugs will not be permitted.
13. Before connecting up to return mains, the system of piping must be blown and flushed out.
After flushing, all strainers shall be opened and baskets cleaned.
14. Liberal allowances shall be made for expansion and contraction of pipes by means of changes
in the direction or by the inclusion of expansion joints in the piping system.
31.4 Weding
1. Where shown on the drawings or specified or directed, welded joints, outlets and flanges shall
be used.
2. Care shall be taken to ensure that welding metal or flux does not project into the bore of the
pipe. All welds shall be of good clean metal, free from slag and porosity, of even thickness
and contour, well fused with the parent metal, hammered on completion and finished smooth.
3. The Engineer reserves the right to have cut for examination 2% of all welds made. The
Contractor shall remake the joints at no extra charge.
4. All welded joints (except pipe welded end to end) shall be made by use of forged one piece,
welding flanges, caps, elbows, branch outlets and tees of approved make. All such fittings
etc., shall be of a type which maintains full wall thickness at all points, ample radius, fillets and
proper levels or shoulders at ends.
5. All joint welding may be by the electric arc or acetylene process.
6. Wherever welded piping connections to equipment, valves or other units needing
maintenance, servicing or requiring possible removal, the connecting joints shall be by means
of unions or flanges.
7. Pressure rating of the flanges shall match the pressure rating of the flanges on the equipment
to which the pipe connects.
8. Alternatively, Contractor can provide grooved mechanical system fittings with companion
couplings as per the details below:
31.5.1 Pipe/Grooved
1. Carbon Steel, A-53B/A-106B Grade B - Roll or cut grooved-ends as appropriate to pipe
material, wall thickness, pressures, size and method of joining. Pipe ends to be grooved in
accordance with manufacturer current listed standards conforming to ANSI/AWWA C-606.
Flange Adapters
1. ANSI Flange Adapters -For sizes from 2"-24" (DN50-DN600), use flange adapters suitable
for connection to ANSI class 125/150 – class 250/300 flanged components. Cast of ductile
iron conforming to ASTM A-395, Grade 65-45-15.
2. PN Flange Adapters - For sizes 2"-24" (DN50-DN600), use flange adapters suitable for
connection to PN10 OR PN16 flanged components. Cast of ductile iron conforming to ASTM
A-395, Grade 65-45-15.
Gaskets
1. All the gaskets shall be manufactured by the same source of couplings and fittings to secure
compatibility. These shall be Grade ‘E’ EPDM compound (green color coded) conforming to
ASTM D-2000 designation 2CA615A25B24F17Z. Grade ‘E’ gaskets are UL / ULC classified
to ANSI / NSF 61 for cold + 86°F (+30°C.) and hot + 180°F (+82°C.) potable water service.
Temperature operating range -30°F to +230°F (-34°C to +110°C).
Note: Use Dielectric Waterway when connecting dissimilar metals in liquid systems.
1. Coatings - Standard grooved end fittings and couplings can be provided with an alkyd
enamel finish. Fittings and couplings can also be hot dip galvanized to ASTM A-153. Zinc
electroplated fittings and couplings conform to ASTM B633. Fittings and mechanical tees
should be coated to comply with that of the pipes.
Valves upto 50 mm
1. Bronze Gate Valves
Bronze gate valves shall be solid wedge disk, non rising stem screwed in bonnet and shall
be minimum PN16. Valves shall be manufactured in accordance with BS 5154 PN16
Series B and shall preferably have Kitemark. Hand wheel shall be of aluminum.
2. Bronze Globe Valves
Bronze globe valves shall incorporate spherical shape disk spum on upto 1½" size and one
size 2" detailed by threaded ring and shall be minimum PN16. Body seat shall be integral
and narrow contact angle type. Valves shall be manufactured in accordance with BS 5154
PN16 Series B and shall preferably have Kitemark. Hand wheel shall be of aluminum.
3. Bronze Double Regulating Valves
Bronze double regulating valves shall be Y pattern having characterized throttling disk
tending towards equal percentage performance. Valve shall have integral square edged
entrance orifice plate and insertion test points. Fitting valve shall be minimum PN16. DRV-
valve opening shall have setting with an allen key and operation by means of the microset.
4. Bronze Swing Check Valves
Bronze swing check valves shall have disk and connected to hinges by a spud and nut and
free to rotate. The hinge shall be mounted on a hinge pin and free to rotate in internal lugs.
Valve shall be manufactured to BS 5154 PN16 for Series B rating and shall be Kite
marked.
31.10 Unions
1. Unions are required on pipe sizes 50 mm and under. Unions shall be ground taper joint type,
good for 150 psi working pressure.
31.11 Strainers
1. Approved strainers shall be provided in the suction line of each pump and at the inlet
connections to each feeder and connections to each automatic control valve. The intention is
to protect by strainers, all apparatus of an automatic nature, whose proper functioning would
be impaired by dirt on the seat or by scoring of the seat. All strainers shall be suitable for
pressure as stipulated for the system concerned and shall be inspected and pressure tested at
works.
2. All strainers shall be 'Y' type cast iron or bronze bodied of ample strength for the pressure to
which they shall be subjected and suitable flanges to connect with the piping they serve.
Strainer basket screens shall be of stainless steel/brass and shall be of ample strength to
prevent collapsing of the basket under shock loading.
3. 'Y' type strainer, size 65 mm and above shall be fitted with drain cock and threaded nipple.
One roll (30 meter length) of flexible plastic hose shall be supplied loose, suitable for
connection to the drain cocks.
number of arches (corrugations) dependant on projected movement. All joints must be finish-
coated with eypalon paint to prevent ozone attack.
4. Split back or retaining rings shall be furnished. Joints size 2" and below shall have threaded
malleable iron unions on both sides. All joints shall be suitable for minimum test pressure of
one and a half times the working pressure or 225 ft. of water, whichever is higher.
5. Flexible connections shall be provided to AHUs, FCUs, pumps, chillers etc., in order to
prevent transmission of vibration to pipework.
the floor. Vertical piping shall have heavy wrought iron or steel clamps securely bolted on the
piping with the end extension bearings on the building construction.
7. Piping shall be anchored where required to localize expansion or to prevent undue strain on
piping and branches. Anchors shall be entirely separate from hangers and shall be heavy
forged or welded construction of approved design.
8. Hangers and supports for cold piping shall have tongue and groove design rubber support
inserts of approved make or high density insulation capable of withstanding the compression
and allowing the hanger to support the pipe without any metal to metal contact.
9. All internal pipe supports, hangers and anchors etc., are to be painted with two coats of an
approved rust preventive paint, preferably zinc rich primer and two coats of enamel paint of
grey color or as approved by the Engineer.
10. All external pipe supports including for chiller yard pumproom and plantroom roof etc., shall be
finally painted with two coats of enamel paint of grey color or as approved by the Engineer.
32. INSULATION
32.1 General
1. All insulating materials required for piping, mechanical equipment, ductwork etc., shall be
furnished and installed under this section of the specifications. The thermal insulation shall be
non-corrosive to the metal, water repellent and fire-retardant.
2. All metal surfaces shall be thoroughly cleaned and treated with approved corrosion inhibitor
before applying insulation. Inhibitor coating will not be required for galvanized surfaces. All
surfaces to be insulated shall be dry and free of loose scale, dirt, oil or water, when insulation
is applied. Application and completion shall be of highest quality and shall comply with BS
5244 and CP 3005.
3. Insulation shall be carried out neatly and to a high standard by skilled workers, experienced in
the trade. Insulation shall be applied in such a manner that there will be no air circulation
within the insulation or between the insulation and the applied surface.
4. Surface imperfections in the insulation such as chipped edges, small joints or cracks and small
voids not over 25 mm square shall be filled with light insulating material or with insulating
cement. Samples of all materials proposed for use shall be submitted.
5. All duct flanges, stiffeners and inspection doors etc., shall be insulated in accordance with the
recommended practices and to the Engineer's approval. W here a vapour barrier is fixed at
site, it shall be fixed in such a manner as to obviate the possibility of moisture penetration.
6. No piping, ducts or equipment shall be insulated until tested and approved for air/water
tightness.
7. Insulation for all services shall be continued through sleeves. The insulation on exposed
risers extend through the floor slab. All materials including fixing and furnishing materials shall
be rated Grade 'P' when tested for ignitability as defined in BS 476 - Part 4.
32.2 Thermal Insulation to Ductwork (Internal) and Exhaust Ducts (Internal / External)
1. Ductwork internal to the building shall be insulated with 25 mm thick rigid fiber glass insulation
3
of 48 kg/m density covered with re-inforced aluminum foil. The insulation for the round
3
ductwork shall be flexible fiber glass blanket of not less than 24 kg/m density with reinforced
aluminum foil and thickness of 50 mm compressed to 25 mm during application. The
Contractor shall ensure that the surface to be insulated is completely cleaned and free from
dust before applying the insulation.
2. The method of application shall be as follows:
a. An approved adhesive material shall be applied on the entire surface of duct-wall and
entire surface of insulation. In addition, adhesive shall also be applied on insulation butt
and lap joints. The adhesive applied to the insulation shall cover evenly the faces to be
fixed, the surfaces forming the longitudinal joint and the surfaces forming the
circumferencial joint. Upon the application of the approved adhesive, the insulation shall
be fixed in position immediately and permanently.
b. Adhesive tape, not less than 75 mm wide, shall be used to seal both the circumferencial
and longitudinal joints. Suitable GI angle edges shall be applied on the four corners of
square and rectangular ducts as an additional protection.
c. Cover and secure 200 g/sq. meter high quality glass cloth while it is wet (soaked in
approved vapor sealant) and then wrap carefully to become a vapor seal with a smooth
surface free from wrinkling and gaps. Ensure that the overlap shall be 50 mm minimum.
After it is dry, apply further brush coats of vapor seal to the Engineer's satisfaction. The
vapor seal material shall be fire-resistant, non-toxic, weather resistant and of anti-fungus
quality.
32.5 Chilled Water Piping Insulation (Inside & Outside the Building)
1. Pipe insulation shall be 50 mm thick for pipes upto 6" dia and 75 mm thick for 8" dia and
above. The insulation shall be sectional rigid fiber glass having thermal conductivity of
3
maximum 0.036 W/M°C. at mean temperature of 24°C. with density of 96 kg/m , bonded to
conform to pipe, with a factory applied flame retardant vapor barrier jacket of aluminum foil,
laminated to Kraft paper with a flame retardant type adhesive.
2. Each joint shall be sealed by using 75 mm wide aluminum foil adhesive tape and the whole
shall be covered with 200 g/sq.m. high quality glass cloth securely wrapped and all joints
lapped and sealed with vapor seal, followed by two coats of weather proofing compound of
approved make to the satisfaction of the Engineer.
1. The vapour seal material shall be fire resistant non toxic, weather resistant and have anti
rodent and anti fungal properties.
2. Bitumen product shall not be used.
3. The vapour seal material shall be approved by the client in writing prior to use.
33.1 General
1. Exhaust fans shall be supplied and installed by the Contractor as shown on the drawings.
Capacity, type and rating of the fans shall be as indicated in the schedule. The fan motors and
switches shall be in accordance with this specification regarding electrical works. Fixing
details shall be in accordance with manufacturer's recommendations. All roof fans shall be
suitable to operate for 50°C. ambient temperature.
2. As an alternative, heat resistant plastic fans, if offered shall have the above components
except for the fan casing and impeller construction. The Contractor shall also produce a
certificate of approval from Qatar Fire Department and further it shall be subject to the
approval of the Engineer.
Mounting frame to support drive and to permit mounting of fan on any side.
B. Fan Blades
Axial flow, Aerofoil inline type.
Fans must be sited away from the fire zone to ensure a supply ambient air to motor
compartment (65 °C Max)
33.7 Basement Carpark exhaust and fresh air fan centrifugal floor mounted
1. Centrifugal Floor Mounted Exhaust Fan ( 2-Speed Motor )
A. Exhaust fan shall be of the centrifugal type with backward inclined wheels. The housing
shall be of continuously welded heavy gauge steel with the bearing support shall be
constructed of welded structural steel members to prevent vibration and rifidly support the
shaft and bearings.
B. The fan wheel shall be of the non overloading backward inclined centrifugal type. The
wheels shall be statically and dynamically balanced. The wheel cone and fan inlet cone
shall be carefully matched and shall have precise running tolerance for maximum
performance and operating efficiency
C. Precision ground and polished steel shaft shall be sized so the first critical speed is at
least 25% over the maximum operating speed for each pressure class, close tolerance
shall be maintained where the shaft passes through the bearing.
D. Bearings shall be heavy duty grease lubricated, self aligning ball bearing or roller pillow
block type. Bearing shall be selected for a minimum (L50) life of 200,000 hours at
maximum operating speed for each pressure class. Fan performance shall be based on
test and procedures performed in accordance with AMCA publication 211 and comply with
the requirements of AMCA certified ratings program. Fans shall be licensed to bear the
AMCA seal
E. After assembly each fan shall be given an electronic vibration analysis while running at the
specified operating RPM. Vibration amplitude and frequency shall be recorded in the
horizontal, vertical and axial planesof each bearing to assure smooth vibration free
operation. The analyzer print out shall filed and made available upon customer request
F. Centrifugal fans shall be BIDW ( backward inclined doubled width )
34.3 Manometers
1. Inclined type differential pressure manometers shall be installed to measure the pressure drop
across the filters. The manometers shall be provided across mixed return air filters at each air
handling unit. The manometers shall be of metallic construction and shall be suitable for
outdoor installation.
35.1 General
1. All electrical works and materials shall be as described under the Electrical specifications and
shall conform to the regulations of Ministry of Electricity and Water.
2. All electrically operated equipment shall be so designed that it will continue to function without
damage to itself or otherwise, if the voltage and/or frequency vary within the following
tolerances:
Voltage -± 6%
Frequency -± 0.3%
3. All electrically operated equipment shall be suitable for continuous and prolonged operation
within the ambient temperature or exposed condition to the atmosphere where they are
installed to operate. Allowance for the local high ambient temperature shall be made by
reducing the permitted rise of temperature above ambient or by derating the capacity and
ratings.
remote installed A.C. control panels, the power cabling from the control panel upto the
isolator near the A.C. equipment shall be carried out by the Electrical Contractor. (For
continuity, refer electrical drawings and specifications).
b. Specifications for conduits, cables, cable trays to conform to electrical specifications.
c. Power cabling from the controller of twin extract fans to the actual fan units.
35.4 Starters
1. All three phase motors for A.C. units shall be provided with D.O.L. / Star Delta starters having
the following facilities :
a. To disconnect the supply in the event of power failure or voltage drop.
b. To protect the motor from over load in each phase.
c. Start/stop push button.
d. ON/OFF/TRIP indicating lamp.
e. Single phase preventer.
2. All three phase starters shall have thermal overload protection in each phase as well as under
voltage reset plus two auxiliary normal open contacts.
35.5 Isolators
1. All electrical drives shall have local isolators, weather proof to IP 55. Isolators shall be of
reputed manufacturers, up to Engineer's approval.
35.6 Earthing
1. All motors starting equipment panels shall have their frames, carcasses and all metal parts
effectively and continuously connected to the general mass of the earth.
35.7 Testing
1. All wiring within control panels shall be works checked, prior to despatch, for loose
connections, correct terminations and compliance with wiring diagrams. In addition, functional
checks shall be carried out in the works to ensure that all interlocking and sequencing is in
accordance with the performance requirements of the specification. The Engineer shall be
given 7 days written notice of such tests so that he may attend if he so desires.
2. With all control circuits disconnected but with all isolators closed and power fuses fitted, the
panels shall be subjected to a voltage test of 2.5 kV for one minutes, across the following
points:
a. Phase to phase
b. Phase to neutral
c. Phase to earth
d. Neutral to earth
3. Certified schedules detailing all tests and their results shall be submitted to the Engineer within
fourteen days of the test.
36.1 General
1. The air conditioning installation shall be capable of automatic operation. Necessary
operational and safety controls shall be provided for chillers, pumps, and air handling units.
Low voltage control system shall be preferred. The location of controls should permit easy
access for calibration, adjustment and maintenance.
2. Selector switches shall be provided for manual selector switch for pumps and automatic
operation of A.C. plants. The A.C. control panel to be located as indicated on the drawings
shall be suitable for operation at 50°C. ambient condition.
3. The Contractor shall submit the control schematic diagrams indicating the single line from all
the control functions in sequential order, control wiring diagram and power wiring from control
panel as a whole to the Engineer for his approval.
2. Chiller flow switch would sense the required flow rate and energies chiller control circuit.
3. Condenser fan motors would start automatically.
4. A chilled water temperature sensor mounted in the return water header would sense the
demand for cooling and transmit signals through a DDC controller for the refrigeration system
to start operation. First the lead chiller shall start.
5. Compressor would start unloaded or partially loaded provided the safety controls, high
pressure cut-out, low pressure cut-out, oil pressure failure switch and compressor motor
winding thermostats are satisfied. In multi-compressor chillers, the subsequent compressors
would start after the preset time interval.
6. Operation of any safety control and non-operation of any interlocking function would initiate
pump down cycle and stop the compressor. Once the plant trips on any safety control,
restarting should be possible only after manual resetting.
7. Interlocks and safety controls will function in an identical manner even when the selector
switch is at manual position with the exception that all the motors would require manual
starting from remote start/stop buttons installed on the motor control panel.
8. Some of the condenser fans would cycle in response to head pressure during low ambient
temperature conditions.
9. A dedicated microprocessor based DDC controller shall be provided on the main control
panel for synchronized operation of chillers. The DDC controller would respond to a
temperature sensor mounted in the common chilled water return header. The DDC controller
shall match with the refrigerant capacity of chillers and with the cooling load requirements
through the operation of compressor capacity control mechanism in alternating sequence for
both step-up or step-down. Care should be taken in the case of chillers having in-built step
controllers for capacity control to ensure that the second or subsequent chillers do not come
on line until the lead chiller has reached 100% capacity.
10. A switch on the control panel shall enable the sequence of lead/lag chiller operation to be
changed and to allow all combinations of the chillers available.
11. The DDC shall monitor the following for the chillers:
Individual chiller supply temperature
Common header supply temperature
Common header return temperature
Chiller run status
Chiller trip alarm
Chiller on full load status
12. The chiller shall be sequenced (lead - lag) by DDC on monthly basis, for e.g.. 1-2-3, 2-3-1, 3-
1-2.
13. Temperature log of all the monitored temperature shall be available at the DDC. Graphic
viewing of valves shall be possible using portable operation terminal.
14. The direct digital controller should support the following minimum configuration:
CPU - 32 bit processor
Cyde time -1 sec. max.
Supply voltage - 240 volts
Operating condition -0 to 45°C., 0 to 90% RH non condensing.
3. Starting and stopping of air handling units shall be carried out from the starter installed in the
AHU control panel or override switch shall be provided to bypass the time zone programmed
with DDC controller as indicated on the tender drawings. Means of local isolation shall be
provided to conform to I.E.E. regulations, latest edition.
36.15 Transformers
5. Flow and return (F & R) and direction of flow arrows shall be in black with letters 25 mm high
on 50 mm wide white self adhesive tape applied in a continuous band around the pipe
insulation.
6. Pipe contents shall be in black lettering 25 mm high on 50 mm wide clear self adhesive tape
with one set of identification letters per color code.
7. Pipe sizes shall be metric in black printed lettering 25 mm high on 50 mm wide clear self
adhesive labels.
8. All ductwork whether insulated or exposed shall be identified in accordance with DW /142
Appendix 'A' together with descriptive lettering approved by the Engineer.
9. The materials employed shall be as for pipework identification, i.e. self-adhesive plastic.
10. All the lettering and wording shall be in Arabic and English.
Balancing shall be performed in accordance with the current issue of the associated air
balance council standards for total system balance and SMACNA standards where applicable.
B) Fans
Name of manufacturer
Model or serial number
Rated air flow
Measured air flow
Rated RPM
Rated pressure
Measured pressure - suction, discharge
Pulley size, type and manufacturer
Belt size and quantity
C) Air system
Grille, register or diffuser reference number and manufacturer
Grille, registers or diffuser identification
Design velocity
Measured velocity
Design air flow
Measured air flow
Effective area factor and size
Grilles and diffusers must be adjusted to provide draft less air distribution. Noise level
must not exceed those specified. Primary balancing at the duct dampers with final
adjustment only at the grilles and diffusers shall be carried out.
On completion of the adjustment and balancing of all system, three copies of full
report in approved format shall be submitted to the QP REPRESENTATIVE. The
report shall include the following items.
The air conditioning system shall be fully balanced after installation. Performance
testing of the system shall then be carried out during a period of peak summer design
conditions. CONTRACTOR shall liaise with the QP REPRESENTATIVES, regarding
the timing of the tests, which shall include
(a) Demonstration that the systems are capable of achieving the specified
internal conditions and handling the correct air flow rates.
(b) Measurements of air or water pressure drops through all filters and cooling
coils
(c) Measurements of air temperature and water temperature change through all
cooling coil at air volume flow rate.
(d) Measurements of outside air condition at every two hours and at the
beginning and end of each testing period.
(e) Measurements of dry and wet bulb temperature, together with a record of time
that the measurements were made, of the supply air and room temperatures.
(h) Noise level shall be measured for each octave band with the air condition and
ventilation system in operation under normal running conditions, in each room
served. The background noise level in each room shall be measured at the
same time.
After finishing the above tests and adjustments, CONTRACTOR shall be responsible
to run a Reliability Trial Test for the whole Plant installed. The trial of the plant shall
take place during the appropriate seasons when design conditions are met. The trial
shall last for a period of fourteen (14) consecutive days during which the whole of the
plant shall operate continuously without readjustment or repair.
During the Reliability Trial Test, performance tests shall be conducted on the
refrigerating and air conditioning equipment. The test data shall not deviate by more
than three Percent (3%) from the specified capacity data. Should any part of the
apparatus or system fails to meet with the Specification requirements, it shall be
adjusted, repaired or replaced to the satisfaction of the QP REPRESENTATIVE.
Contractor shall submit the final official approval from the concerned statutory
authority.
46. WARRANTY
1. The Contractor shall guarantee for a period of 400 days after the practical completion of the
installation that all plant and equipment shall operate free of any defects due to defective
material and bad workmanship and that any part found defective during this period shall be
replaced free of cost by the Contractor.
2. Maintenance period for all air conditioning equipment, controls, components and systems etc.,
shall start only after regular electricity power supply is available at site.
3. All the compressors up to and including 15 HP shall be guaranteed for a period of 5 years
from the date of regular power supply at site. The Contractor shall also guarantee the
performance and efficiency of the plant and equipment as per the specifications for a similar
period of 400 days after the practical completion and if the services of Contractor's personnel
are requisitioned during this period, such works shall be made available free of cost to the
Client.
4. If the defects are not rectified within a reasonable period, the Client may proceed to do so by
another agency at the Contractor's entire risk and expense without prejudice to any rights of
the Client.
5. If the equipment selected by the tenderer should require any special alteration or addition to
the architectural or structural work, he must list the requirements separately.
1. The technical schedules listed hereunder must be filled in and signed by the Tenderer and
they must be attached with the offer with complete engineering catalogues for every piece of
equipment to enable the Engineer to evaluate each offer. Offers submitted without such
information will not be acceptable.
Air-cooled Chillers
Reference :.................................................................................
Quantity :.................................................................................
Refrigerant :.................................................................................
Type :.................................................................................
F.L.A. of each
Compressor motor :.................................................................................
Inrush Amperes
Serving :.................................................................................
Type :.................................................................................
Quantity :.................................................................................
Manufacturer :.................................................................................
B.H.P. :.................................................................................
Overall dimension of
foundations :.................................................................................
Components
Controls
a. Motorized valve
Make / Model :.................................................................................
b. Temperature Controls
Make/Model :.................................................................................
Type :.................................................................................
Reference :.................................................................................
Location :.................................................................................
Make/Model :.................................................................................
Type :.................................................................................
Cooling Coil
Total Cooling Capacity :.................................................................................
Fans
Type :.................................................................................
B.H.P. :.................................................................................
Miscellaneous Information
Type of filters and thickness :.................................................................................
Filters
Type/Model :.................................................................................
Frame :.................................................................................
Cell Dimensions
Efficiency :.................................................................................
Filter :.................................................................................
Is the filter :-
d. High Efficiency
Filters :.................................................................................
Area of media ft.sq. :.................................................................................
General
Make :..................................................................................
Type :..................................................................................
Model :..................................................................................
Indoor Unit
Model :.................................................................................
W :.................................................................................
D :.................................................................................
Refrigerant :.................................................................................
High :.................................................................................
Low :.................................................................................
Motor :.................................................................................
Evaporator :.................................................................................
Outdoor Unit
Model :.................................................................................
Refrigerant :.................................................................................
Motor :.................................................................................
Quantity :.................................................................................
Condenser :.................................................................................
Motor :.................................................................................
Quantity :.................................................................................
Insulation
Manufacturer : ……………………………………………………………………
Type : ……………………………………………………………………
Finish : ……………………………………………………………………
Ventilation/Exhaust Fans
Reference : …………………………………………………………………..
Location : …………………………………………………………………..
Service : …………………………………………………………………..
Type : …………………………………………………………………..
Make : …………………………………………………………………..
Model : …………………………………………………………………..
Size : …………………………………………………………………..
CFM : …………………………………………………………………..
NIBCO
HONEYW ELL
CRANE
SPIRAX SARCO
IDEAL
CLIM, FOSTER
Note: 1. The above recommended manufacturers should meet the detailed specification given in
the relevant sections.
END OF SECTION
AT
Leqtaifiya
November 2015
Section 23 FIRE FIGHTING AND FIRE
FIGHTING SYSTEMS
TABLE OF CONTENTS
PART/CLAUSE TITLE PAGE
1. GENERAL ............................................................................................................................... 1
4. SPRINKLER SYSTEM:.......................................................................................................... 16
SECTION 23
FIRE FIGHTING AND FIRE FIGHTING SYSTEMS
1. GENERAL
NFPA-25, Standard for Inspection, Testing, and Maintenance of Water Based Fire
Protection Systems
NFPA-70, National Electric Code
NFPA 72, National Fire Alarm Code
NFPA 92A, Standard for Smoke Control Systems
NFPA-101, Life Safety Code
NFPA-110, Standard for Emergency and Stand by Power systems
NFPA-170, Standard for Fire Safety Symbols
NFPA 204, Standard for Smoke and Heat Venting
NFPA-220, Standard for types of Building Construction
NFPA-221, Standard for Fire Walls and Fire Barrier Walls
NFPA 780, Standard for the Installation Lightning Protection Systems
NFPA-2001, Standard on Clean Agent Fire Extinguishing systems
NFPA 5000, Building Construction & Safety Code
OSHA, Code of federal regulations, Title 29, Part 1926
BS EN3 for portable fire extinguishers
BS EN 1866 for mobile extinguishers
BS EN 671-1 for fixed fire fighting system
BS 5041-3 for dry riser inlet
BS EN 54 Standard for installation of Fire Alarm System.
b. The fire water mains (sprinkler, standpipe & hydrant), including the piping, the fittings, the
hanging, the block-valves & the hydrants.
c. The wet sprinkler systems, including the control valves, the piping, the hanging, the heads,
the instrumentation.
f. Clean agent fire suppression system for the rooms mentioned in the drawings.
The Contractor shall be responsible for all the following aspects of the provided systems:
h. The checking of the tender drawings and any calculations supplied with the drawings. The
Contractor shall check each drawing and satisfy himself that the design is correct for the
equipment offered and will meet all applicable rules and regulations
j. The provision of drawings and equipment data related to the systems as required by the
Engineer
k. The supply of all required equipment and other fixtures associated with the systems
m. The provision and fittings of suitable wall boxes, transits and plates where pipe work or
cable passes through walls, etc...as well as fire rating reinstatement materials
o. The provision of scaffolding, ramps and any other equipment required to enable the systems
to be installed, tested and commissioned correctly
p. A demonstration to key personnel in the use and testing of the systems and equipment
supplied
1.6 Materials
1. The Contractor shall supply all materials necessary to make up effective and operable fire
protection, detection and alarm systems, voice alarm system and emergency & exit lighting
systems for the facilities indicated in the drawings and in the present specification, and
particularly :
a. All the necessary pipe work, valves, equipment and instrumentation required for the
facilities
b. All electrical cable between panels, junction boxes, sensors, call points, pressure
switches, alarm bells, flashing lights, and generally all the cable (and their supports)
required for the facilities.
d. All detectors, fire signalling and alarm cabling shall be installed by the Contractor using
materials in accordance with international standards.
e. All emergency lights, exit lights with directional arrow marks & pictograms as
required,central battery panels, addressable monitoring panel, interface modules, phase
monitoring relays and interconnecting cabling shall be installed by the contractor using
the materials in accordance with International standards.
1.9 Submittals
1. The installing contractor shall submit the following design infromation and drawing for
approval prior to starting work on this project.
1. Field installation layout drawings having a scale of not less than (1:100m) detailing the
location of all equipments, pipe runs including pipe sizes and lengths, controls and other
accessories.
2. Auxiliary details and information such as maintenance panels, door holders, special sealing
requirements and equipment shutdown.
3. Separate layouts, or drawings, shall be provided for each floor plans (i.e.; sectional drawings,
raised floor drawings, and above false ceiling drawings) for mechanical and electrical work.
4. A separate layout or drawing, shall show isometric details of clean agent storage containers,
mounting details and proposed pipe runs and sizes.
5. Electrical layout drawings shall show the location of all devices and include point-to-point
conduit runs and a description of the method(s) used for detector mounting.
6. A complete sequence of operation shall be submitted detailing all alarm devices, shutdown
functions, remote signaling, and agent discharge for each system.
7. Submit drawings, calculations and system component data sheets for approval to the local
Fire Prevention Agency, and all other Authorities Having Jurisdiction before starting
installation. Submit approved plans to the Architect/Engineer for record.
1.11 Drawings
1. Refer to fire fighting tender drawings layout.
2.3 General
1. Fire Extinguishers shall be manufactured to comply with BS EN 3 (portable), BS EN 1866
(Mobile) standards.
2. Fire Extinguishers shall comply with NFPA-10 or BS 5306 for the installation.
3. The classification of fire extinguishers shall consist of a letter that indicates the class of fire
on which a fire extinguisher has been found to be effective, preceded by a rating number
(Class A, Class B and Class F only) that indicates the relative extinguishing effectiveness.
4. The distribution of fire extinguishers shall comply with the prescribed requirements of
NFPA-10, as shown on the drawings and the specific requirements of the local Civil Defence
Authorities.
5. Cabinets housing fire extinguishers shall not be locked.
6. Portable fire extinguishers shall be maintained in a fully charged and operable condition, and
kept in their designated places at all times when they are not being used.
2.4 Definitions
1. The type of extinguisher needed depends on the right type of fire that may occurs in the room
or building.
2. According to NFPA 10, several classes of fire have been defined:
a. Class A Fires: Fires in ordinary combustible materials, such as wood, cloth, paper,
rubber, and many plastics.
b. Class B Fires: Fires in flammable liquids, combustible liquids, petroleum greases, tars,
oils, oil-based paints, solvents, lacquers, alcohols, and flammable gases.
c. Class C Fires: fires that involve energized electrical equipment where the electrical non-
conductivity of the extinguishing media is of importance. (W here electrical equipment is
de-energized, fire extinguishers for class A or B fires can be used safely.)
e. Class K or Class F Fires: Fires in cooking appliances that involve combustible cooking
media (vegetable or animal oils and fats.)
According to these definitions, all parts of the buildings shall be equipped with
class ABC type extinguishers. In the meantime, rooms such as Storages,
Workshops and other rooms housing electrical equipments, shall be equipped with
adding class C extinguishers.
7. The CO2 extinguishers are recommended with the capacities and minimum fire rating as
follows:
1 5 Kg CO2 55B
3. The Foam extinguishers are recommended with the capacities and fire rating as follows:
4. The Foam type fire extinguishers: The product should have at least been certified by two
independent Certification Organizations from International Testing Laboratories &
Accredited Certification Bodies as LPCB approval/KITE mark approval and or UL
listed/FM Approved.
3. The Wet chemical type fire extinguishers: The product should have at least been certified
by two independent Certification Organizations from International Testing
Laboratories & Accredited Certification Bodies as LPCB approval/KITE mark approval
and or UL listed/\fm Approved.
2.9 Installation:
1. Fire extinguishers shall be conspicuously located where they will be readily accessible and
immediately available in the event of fire. Preferably they shall be located along normal paths
of travel, including exits from areas.
2. Fire extinguishers shall not be obstructed or obscured from view.
3. Portable fire extinguishers other than wheeled types shall be securely installed on the hanger
or in the bracket supplied or placed in cabinets or wall recesses. The hanger or bracket shall
be securely and properly anchored to the mounting surface in accordance with the
manufacturer’s instructions. Wheeled-type fire extinguishers shall be located in a designated
location.
4. Fire extinguishers having a gross weight not exceeding 40 lb (18.14 kg) shall be installed so
that the top of the fire extinguisher is not more than 5
5. ft (1.53 m) above the floor. Fire extinguishers having a gross weight greater than 40 lb (18.14
kg) (except wheeled types) shall be so installed
6. that the top of the fire extinguisher is not more than 31/2 ft (1.07 m) above the floor. In no
case shall the clearance between the bottom of the fire extinguisher and the floor be less
than 4 in. (10.2 cm).
7. Fire extinguishers shall be installed in a 1.2 mm thick, stainless steel, polished finish cabinets
where required in finished rooms / office areas and as shown on the drawings and shall be
confirmed with the Architect.
694. The semi rigid hose shall be 25mm or 40 mm diameter x 30m long, coiled on a revolving
drum. The outer end of a hose shall be fitted with a “jet / spray / shut-off” control nozzle. The
inner end of the hose shall be connected through the reel to the water supply. All water
passage must be brass chrome plated and plastic parts are not permitted. Complete
unit to be listed. The product should have at least been certified by two independent
Certification Organizations from International Testing Laboratories & Accredited
Certification Bodies as LPCB approval/KITE mark approval. Incase of automatic hose
reels, the reels shall incorporate a valve that automatically turns on the water supply when
approximately 3 mtr of hose is unreeled, and shut off again when the hose is re-wound onto
the reel. A manual shut-off valve of the wheel type shall also be installed on the service pipe
to each hose reel.
2. The hose nozzle shall be, (JET/SPRAY/SHUT OFF) type nozzle.
3. Each hose reel shall be installed and tested to BS 5306 and shall deliver not less than 0.4 l/s
when the two top-most reels are in use simultaneously providing a jet of approximately 6 mtr.
in length. Pressure reducing devices shall be provided whenever necessary to limit the
pressure as per local authority remotest point requirenment.
4. Brief operating instructions should be clearly displayed on or by each hose reel in both
English & Arabic languages
5. The hose reels shall be suitable for working pressures up to 12 bar (175psi) and shall be
installed in accordance with the manufacturer’s instructions.
minimum 1.2mm thickness electro-galvanized steel sheet or stainless steel as per design
requirement. The door can be different type like wood to steel finish, marble finish, MDF
wooden door, clear glass or wired glass. The stainless steel cabinets shall be polished finish
type, the finish shall be decided upon the approval of the architect.
3. The Double fire hose reel cabinet in different locations of the building shall have following
specified fire equipments:
a. Automatic or manual Fire Hose Reel
b. Landing Valves, Fire Hose and Nozzle or fire hose rack assembly
c. 2 kg CO2 Fire Extinguisher
d. 6 kg DCP Fire Extinguisher
7. A drain valve and piping, located at the lowest point of the standpipe piping downstream of
the isolation valve, shall be arranged to discharge water at an approved location.
3.1 GENERAL:
1. Each system shall be design to insure the maximum pumping capacity even if 1 pump fails.
2. The total supplying of all the necessary equipment for the firewater production (including
pumps, engines driven, controllers, instrumentation, piping, valves, relief valves, …) is
included in the Contractor’s scope of work.
3. The supplying and installation of the day fuel tank of the engines is included in the
Contractor’s scope.
4. The fuel tank (and all the fuel installation) shall be in accordance with NFPA standards.
5. The air supply system of the diesel engines drive (automatic opening, venting panels, ..) is
included in the Contractor’s scope.
6. The fire pumps, motor, engine and electric pump controllers and diesel pump controllers shall
be UL listed or FM approved, built in the country where the agreement is made. Unit
responsibility must be submitted from the manufacturer.
7. The fire pumps and engine driven shall be in accordance with NPFA 20 (curves, starting,
protection, …).
8. The problem of surge (hammer effect) shall be taken into account in the design. A surge
analysis shall be conducted and specific surge pressure control system shall be installed.
9. Over-pressure system shall also be installed.
10. The contractor shall provide fully certified hydraulic calculations for exact sizing of the pumps.
11. The pumps shall be furnished with a full set of bench test certificates proving acceptability for
the design points of this installation.
3.2 PRODUCTS:
3. The pumps shall also deliver not less than 150% of rated capacity at a pressure of not less
than 65% of rated pressure. The shutoff pressure shall not exceed 140% of the rated
pressure at rated capacity.
2. The engine shall be of the self contained open type, mounted on a suitable base with the
following minimum plus any others that may be necessary by NFPA-20 and local CD
requirements.
a. Dual battery set sized to NFPA -20 requirements with electrolyte shipped in separate
containers, rack and cables.
b. Dual battery charger of proper type for batteries used ( included in UL Listed / FM
Approved controller ). Power to battery charger shall be supplied from electric pump
control panel. W iring from control panel to battery chargers shall be by the contractor.
c. Electric starter with suitable generator and voltage regulator.
d. Engine water pump.
e. Heat exchanger cooling system.
f. Water cooled or ceramic blanketed exhaust manifold.
g. Lubricating oil pump and filter.
h. Fuel injection system.
i. Air cleaner.
j. Proper instrument panel, complete with engine run warning light, water temperature
gauge, oil pressure gauge, voltmeter, totalizing type tachometer and hour meter.
k. Residential Grade Muffler.
l. Cooling water line for the engine heat exchanger assembly.
m. Flexible exhaust connectors.
n. All engine wiring for automatic operation shall terminate in a proper junction box to
permit connection to control panel.
3. The silencer shall be designed by HEAVY DUTY APPLICATIONS, with noise attenuation
across the entire audible range of the frequency spectrum 63 through 8000 Hz. The silencer
shall consist of a series of chambers connected by non-resonant tubes. The entire silencer
shall be manufactured from plate steel and be of a completely welded design. The heavy
plate ensure longer silencer life and better resistance to damage. The heavy plate shall
prevent shell radiated noise. There shall be no spot welds or press fits used.
4. Silencer inlet and discharge shall be flanged, manufactured from minimum 10mm thick plate
and drilled to ANSI 70 kg. Silencers shall be either and in/end out and side in/end out
configurations to suit installation.
5. Provide 12mm drain connections. Prior to shipping, the silencers shall be thoroughly cleaned
and coated in a high temperature 650ºC aluminium paint.
be provided and a 240 volt single phase power failure relay or a pressure switch, which will (
when the system pressure drops ) activate all electric circuits to automatically start the
engine.
2. Should the engine fail to start after the required cranking cycles, the controller shall
disconnect the starting circuit and activate an alarm system using lights and buzzer or bell.
“Low oil pressure” and “high jacket-water temperature” shall also be indicated by a suitable
alarm system. The engine shall not shut down if either of these conditions occurs during an
operating cycle.
3. The engine shall be started automatically by the Controller at least once a week, adjustable,
and operate a minimum of 30 minutes ( adjustable ). An appropriate timing arrangement
shall determine the day and hour of this test.
4. Pressure recorder ( 7 day drive ) shall be provided within the control panel.
5. Fire Pump Controller shall be a diesel engine type, Controller approved and listed by the
Underwriters Laboratories for fire pump service, carry the labels of both UL/FM and meet the
requirements of the NFPA20.
The controller shall incorporate the following :
6. Each charger shall be completely independent of the other charger and equipped with its
own individual power transformer, rated for a maximum continuous charge current of 10A.
The charger shall be of solid state electronic design, with semi-conductor type rectifier, and
include the following supervisory and safety features :
a. Current limiting in every charging mode
b. Over current shut-off
c. Automatic selection of bulk or charge by sensing battery voltage
d. Trickle charge limited to less than 500MA
e. Reverse voltage shut-off
f. Dead cell detection
g. Over and under voltage alarm
7. In case of battery failure, the charger shall initiate an alarm and provide a signal to prevent
the use of the defective battery during the start attempt cycle.
8. Relays : All relays shall be equipped with manual test buttons, status “ON” – “OFF”
indicators, be of the plug in type and shall meet all voltage and current requirements.
9. Remote Alarm Circuit : A total of five ( 5 ) standard alarm contacts, rated at 10 A, 125 V shall
be provided and wired to the field terminal block, to indicate the following engine conditions :
a. SPDT contact : Engine Running
b. 1 N/O contact : Contact shall close when main switch in Auto-position
c. 1 N/O contact : Contract shall close when main switch is in OFF or Manual position.
d. SPDT contact : Engine trouble. This shall be a common alarm contact indicating the
following conditions. Engine over speed, engine fail to start, low oil pressure, high
coolant temperature.
10. Description of Operation : A four positions main switch shall provide selection of three
starting method and one OFF position.
a. OFF position shall shut down engine and alarms under any condition.
b. AUTO position : a water pressure switch mounted inside the controller shall provide the
engine start on water pressure drop. The automatic starting circuit shall alternate the
two storage batteries after each start attempt. The attempt to start cycle shall consist of
six cranks and five rest periods of 15 seconds duration. In the event of one battery
failure, the starting cycle shall lock itself to the remaining battery. In case of engine
failure, the controller shall stop any further cranking and energize the ENGINE FAIL TO
START alarm. A manual stop push button shall enable engine shut down, but only after
all starting causes have returned to normal. The automatic Weekly Exercise cycle shall
also be operational in the auto-position. This cycle shall be programmed on the 7 day
time clock. A short opening of the water solenoid valve shall create a momentary
pressure drop and cause automatic engine start. At the end of the programmed
Exercise cycle, engine shall shut down automatically. A manual test switch located on
the time clock shall allow for manual test operation of the weekly exercise cycle. The 7
day time clock shall hold its time on A/C power failure and not require resetting.
c. TEST Position : Engine shall start in the same manner as the above exercise cycle
start. Turning main switch to Auto or Off position shall shut down engine.
d. MANUAL Position : Start pushbutton “Battery 1” or “Battery 2”, shall override all
automatic starting circuits, and allow for direct manual engine start.
e. Safety Shut Down : Engine overspeed condition shall shut down engine without time
delay and lock out until manually reset.
11. The controller shall provide the following additional safety features Engine shut down in case
of low oil pressure or high coolant temperature during exercise, test or optional AC failure
operation only.
4. SPRINKLER SYSTEM:
4.3 General
1. All sprinklers shall be of UL listed / FM Approved .
2. The sprinkler heads shall be of the spray pattern installed in an upright position or pendant
position as may be required. Sprinkler in false ceilings shall be concealed to ceiling and to
architects’ approval.
3. The design Criteria for all sprinklers such as K-factor, type and operating temperature shall
be submitted for approval.
4. A set of spare sprinkler heads shall be provided and located in a cabinet in the fire pump
room together with sprinkler spanners for use in removing and installation of the heads as
recommended in NFPA-13 and local authority requirements.
5. The sprinklers and lines shall not be spaced too close together in order to prevent an
operating sprinkler from wetting and hereby delaying operation of adjacent sprinklers.
6. In locations where sprinkler heads are liable to be operated or damaged by accidental blows,
stout metal guards should protect them; care being taken
7. to ensure that the normal operation of the sprinkler head in the event of fire is not thereby
impeded.
8. The contractor shall supply set of spare sprinkler heads in each type / temperature range and
located in a cabinet in the fire pump room together with sprinkler spanners for use in
removing and installation of the heads as recommended in NFPA-13 and local authority
requirements.
9. Finish of sprinklers shall be to the approval of the architect.
manufactured from a non-ferrous material to prevent the hole from becoming blocked by
corrosion or foreign matter.
4. A 15 mm test valve shall be installed on the installation side of each alarm valve.
d. Installed in such a way that the test shall be conducted from a central control room,
through single push button and the individual WFMS status can be read from main fire
alarm panel or separate flow monitoring panel.
e. Have the future (contacts and relays) facilitating the connection to BMS, for automatic
actuation, once in 3 months which records the status as required.
4.7 EXECUTION/INSTALLATION.
1. The “Protection Area of Coverage” per sprinkler shall be determined as the multiplication of
the distance between sprinklers upstream and downstream, and the perpendicular distance
between a sprinkler and another on the adjacent branch line.
2. Installation for hydraulically calculated system with concealed pendent and upright sprinklers
shall be, according to NFPA 13 latest edition and local authority requirements.
3. Complete Sprinkler system shall be installed in accordance with NFPA-13 and authority
having jurisdiction requirements and as shown on the drawing.
4. The Fire protection contractor shall be responsible to co-ordinate his work with all other
trades and shall be completely familiar with and shall make allowance for conditions which
affect the fire protection installation.
5. The Zone control valve assembly locations and access panels shall be mounted securely
and provided with proper sign boards.
6. Provide a pressure guage with a isolation cock with inspectors test plug on top of the each
sprinkler pipe risers.
5. All testing shall be performed under the work of this section. All services required for testing
shall be a responsibility of the work of this section. The MEP Contractor shall notify the
Engineer of all tests, 48 hours prior to testing.
6. The fire protection piping System shall be tested hydrostatically for not less than 2 hours and
at one time of the system pressure without any leaks or as directed by the local fire
department.
7. If the systems are tested in sections, the connection to the previously tested section shall be
included.
8. All tests that may be required by the local fire authorities shall be performed under the work
of this section, in the presence of their representative, if so required.
9. All leaks shall be corrected and the system re-tested until no leaks are found, at no cost to
the client.
10. Functional tests of all water flow alarms are a responsibility of the works of this Section.
11. When the various systems are completed, operation tests shall be run on all equipment to
demonstrate proper operating conditions. These tests shall be run under the observation of
the inspector and the client’s operating engineer. The client’s operators shall be instructed
during this period. Operation tests shall be performed under the work of this section.
12. Should any piece of equipment or apparatus of any material or work fail in any of these tests,
it shall be immediately removed and replaced by a perfect material, and the portion of the
work replaces shall again be tested under the work of this Section.
13. Cost to repair any damages to the building construction occasioned by pipe leaks or
defective materials shall be become under the works of this section, at no cost to the client.
All corrective work shall commence immediately after damage occurs.
5.1.1 SCOPE:
1. This specification outlines the requirements for a “Total Flooding” Clean Agent Fire
Suppression System with automatic detection and control. The work described in this
specification includes all engineering, labor, materials, equipment and services necessary,
and required, to complete and test the suppression system.
5.1.3 REQUIREMENTS:
1. The FM 200 Fire Suppression System installation shall be made in accordance with the
drawings, specifications and applicable standards.
5.3.1 MANUFACTURER:
1. The manufacturer of the Suppression System hardware and detection components shall
have a minimum of 10 years experience in the design and manufacture of similar types of
suppression systems and who can refer to similar installations providing satisfactory service.
2. The name of the manufacturer, part numbers and serial numbers shall appear on all major
components.
3. All devices, components and equipment shall be new, standard products of the
manufacturer’s latest design and suitable to perform the functions intended.
4. All equipment shall be U.L listed and/or FM approved.
5.4 INSTALLER:
1. The installing contractor shall be trained by the supplier to design, install, test and maintain
Suppression Systems.
2. The installing contractor shall be an experienced firm regularly engaged in the installation of
automatic Clean Agent, or similar, fire suppression systems in strict accordance with all
applicable standards.
3. The installing contractor must have a minimum of eight (8) years experience in the design,
installation and testing of Clean Agent, or similar, fire suppression systems.
A list of systems of a similar nature and scope shall be provided on request.
4. The installing contractor shall maintain, or have access to, a Clean Agent recharging station.
The installing contractor shall provide proof of his ability to recharge the largest Clean Agent
system within 24 hours after a discharge. Include the amount of bulk agent storage
available.
5. The installing contractor shall be an authorized stocking distributor of the Clean Agent
system equipment so that immediate replacement parts are available from inventory.
6. The installing contractor shall show proof of emergency service available on a twenty-four
hour, seven-days-a-week basis.
5.5 SUBMITTALS:
1. The installing contractor shall submit the following information for approval to the local Fire
Prevention Agency, owners Insurance Underwriter, Architect/Engineer, and all other
Authorities Having Jurisdiction before starting installation:
2. Field installation layout drawings scale shall be 1:100m detailing the location of all agent
storage tanks, pipe runs, including pipe sizes and lengths, control panel(s), detectors,
manual pull stations, abort stations, audible and visual alarms, etc.
a. Auxiliary details and information such as maintenance panels, door holders, special
sealing requirements and equipment shutdowns.
b. Separate layouts, or drawings, shall be provided for each level, ( i.e.; room, underfloor,
and above ceiling) and for mechanical and electrical work.
c. d) A separate layout or drawing shall show isometric details of agent storage
containers, mounting details and proposed pipe runs and sizes.\
3. Electrical layout drawings shall show the location of all devices and include point-to-point
conduit runs and a description of the method(s) used for detector mounting.
4. Internal control panel wiring diagram shall include power supply requirements and field wiring
termination points.
5. Graphic Annunciator wiring schematics and dimensioned display panel illustration shall be
provided. (Optional device)
6. Complete flow calculations shall be provided from a U.L. listed computer program, for all
engineered Clean Agent systems. Calculation sheet(s) must include the manufacturers
name and U.L. listing number for verification. The individual sections of pipe and each fitting
to be used, as shown on the isometrics, must be identified and included in the calculation.
Total agent discharge time must be shown and detailed by zone.
7. Provide calculations for the battery stand-by power supply taking into consideration the
power requirements of all alarms, initiating devices and auxiliary components under full load
conditions.
8. A complete sequence of operation detailing all alarm devices, shutdown functions, remote
signaling, damper operation, time delay and agent discharge for each zone or system.
System design shall not exceed the NOAEL value of 9.0%, adjusted for maximum space
temperature anticipated, unless provisions for room evacuation, before agent release, are
provided.
3. The system shall be complete in all ways. It shall include all mechanical and electrical
installation, all detection and control equipment, agent storage containers, FM 200 agent,
discharge nozzles, pipe and fittings, manual release and abort stations, audible and visual
alarm devices, auxiliary devices and controls, shutdowns, alarm interface, caution/ advisory
signs,
4. functional checkout and testing, training and all other operations necessary for a functional,
U.L. Listed and/or F.M. approved FM 200 Clean Agent Suppression System.
5. Provide two (2) inspections during the first year of service. Inspections shall be made at 6
month intervals commencing when the system is first placed into normal service.
6. The general contractor shall be responsible for sealing and securing the protected spaces
against agent loss and/or leakage during the 10 minute "hold" period.
7. The system(s) shall be actuated by cross zoned photoelectric detectors installed at a
maximum spacing of 250 sq. ft. (23.2 sq. m) per detector, in both the room, underfloor and
above ceiling protected spaces. If the air flow is one air change per minute, photoelectric
detectors shall be installed at a spacing not to exceed 125 sq. ft. (11.6 sq. m) per detector.
(Ref. NFPA No. 72 - current edition)
8. Detectors shall be wired in Sequential Detection method of operation, standard Cross-Zoned
detection, or Single Detector Release, using either a Class "A" or Class "B" wiring
arrangement. No other detection / wiring arrangements will be acceptable.
9. Automatic operation of each protected area shall be as follows:
a. Actuation of one (1) detector, within the system, shall:
Illuminate the "ALARM" lamp on the control panel face.
Transfer sets of 5 Amp rated auxiliary contacts which can perform auxiliary
system functions such as:
14. After completion of the time-delay sequence, the HFC-227ea Clean Agent system shall
discharge and the following shall occur:
a. Illuminate a "SYSTEM FIRED" lamp on the control panel face.
b. Shutdown of all power to high-voltage equipment
c. Energize a visual indicator(s) outside the hazard in which the discharge occurred.
d. Energize a "System Fired" audible device. (Optional)
15. The system shall be capable of being actuated by manual discharge devices located at each
hazard exit. Operation of a manual device shall duplicate the sequence description above
except that the time delay and abort functions SHALL be bypassed. The manual discharge
station shall be of the electrical actuation type and shall be supervised at the main control
panel.
11. Distribution piping, and fittings, shall be installed in accordance with the manufacturer's
requirements, NFPA 2001 and approved piping standards and guidelines. All distribution
piping shall be installed by qualified individuals using good, accepted practices and quality
procedures. All piping shall be adequately supported and anchored at all directional changes
and nozzle locations.
a. All piping shall be reamed, blown clear and swabbed with suitable solvents to remove
burrs, mill varnish and cutting oils before assembly.
b. All pipe threads shall be sealed with Teflon tape pipe sealant applied to the male thread
ONLY.
2. The optical smoke detector shall continuously measures the smoke level in the air, and gives
a proportional output. It shall comply with the requirements of EN54 part 7.
3. The detector shall be an optical light scattering type sensitive to visible smoke and be stable
under all environmental conditions. The internal test and calibration circuits shall use the
same optical elements as the smoke sensing circuits, to ensure reliability.
4. A light emitting diode (LED) on the base must illuminate when a detector is in alarm
3. All system components shall be securely supported independent of the wiring. Runs of
conduit and wiring shall be straight, neatly arranged, properly supported, installed parallel
and perpendicular to walls and partitions.
4. The sizes of the conductors shall be those specified by the manufacturer. Color coded wire
shall be used. All wires shall be tagged at all junction points and shall be free from shorts,
earth connections (unless so noted on the system drawings), and crosses between
conductors. Final termination’s between the SHP control panel and the system field wiring
shall be made under the direct supervision of a factory trained representative.
5. All wiring shall be installed by qualified individuals, in a neat and workmanlike manner, to
conform to the National Electrical Code, Article 725, and Article 760, except as otherwise
permitted for limited energy circuits, as described in NFPA 72 - current edition. W iring
installation shall meet all local, state, province and/or country codes.
6. The complete system electrical installation, and all auxiliary components, shall be connected
to earth ground in accordance with the National Electrical Code.
5.21 WARRANTY:
1. All system components furnished, and installed under this contract, shall be guaranteed
against defects in design, materials and workmanship for the full warranty period which is
standard with the manufacturer, but in no case less than one (1) year from the date of system
acceptance.
6.1 GENERAL
1. Sprinkler system shall be an overhead deluge AFFF foam sprinkler system. System shall be
designed to provide adequately proportioned foam water solution at listed water flows past
proportioning device. System shall be installed in accordance with NFPA 16, Standard for the
Installation of Foam-Water Sprinkler and Foam-Wate Spray Systems, NFPA 11, Standard for
Low Expansion Foam, NFPA 13, Standard for Installation of Sprinkler.Systems and
occupancy standards pertaining to the system installation.
7.1 General
1. The piping for the fire sprinkler system & hose system shall be based on QCS section 23
Part 4 Fire Fighting System unless otherwise specified herein. The pipework shall be
pressure tested to two times the working pressure of the system. Each type of pipe work
material and associated fittings shall be obtained from one manufacturer only, who shall be
nominated by the contractor in writing and approved by the engineer prior to ordering any
materials.
4. Pipes and fittings used in the sprinkler system shall be designed to withstand a working
pressure of not less than 175 psi (12.1 bars).
2. Details of hangers and supports to be used by the Contractor shall be submitted to the
Engineer for approval before installation. All hangers shall be provided with lock-nuts and
have provision for vertical adjustment.
3. The pipework shall be supported, anchored and guided in order to preclude failure or
deformation. The contractor shall construct and install hangers, supports, anchors, guides
and accessories as necessary to the approval of the Engineer. Supports shall be designed to
support the weight of the pipe and the weight of the fluid.
4. Piping shall be securely fastened to the structure without over-stressing any portion of the
structure itself. Pipe supports, anchors and guides shall be secured to concrete by means of
inserts or if greater load carrying capacity is required by means of steel fishplates embedded
in the concrete.
5. Hanger shall be arrange so as to prevent transmission of vibration from piping to building and
supports.
6. Pipe hangers and supports shall be furnished complete with rods, bolts, lock, nuts, swivels
couplings, brackets and all other components and accessories to allow installation to freely
expand and contract.
7. Hangers spacing shall be such that the piping is installed without undue strains and stresses
and provision shall be made for expansion, contraction, structural settlement and water
hammer.
8. Supports, clamps and hangers shall be made of galvanized steel, fixed with drilled plugs.
proposed from listed makes also must fully comply with the detailed specifications, country of
origin, where listed, must be complied.
2. All Materials should have at least been certified by two independent Certification
Organizations from International Testing Laboratories & Accredited Certification
3. Bodies as LPCB/ BSI Kitemark /Vds and or UL/FM.
Item Make
Galvanised Steel Pipes - UL Listed a) Sumitomo
b) Shield
c) Nippon
d) TUF
or Equal and Approved
Sprinkler heads and accessories (UL listed and or FM Approved) a) Central / Spraysafe
b)Automatic Sprinkler
c) Shield
or Equal and Approved
Item Make
Special Valves (Alarm valve, pre-action valve) a) Automatic Sprinkler Corporation
b) Central / Spraysafe
c) Shield
or Equal and Approved
Fire Hose Reel, Fire Hose, Nozzle, Landing Valve, Cabinets and a) Chubb
accessories (LPCB, BSI/Kitemark/ UL listed and or FM Approved).
b) Shield
d) Kidde
e) Norsen
or Equal and Approved
Item Make
Diesel Engine (UL Listed and or FM Approved) a) Caterpillar
b) Clarks
c) Cummins
d) Firedriver
or Equal and Approved
END OF SECTION