You are on page 1of 6

Comm/ JB No 0993/C11

Rev 00 01/ 06.07.13


Isgec Heavy Engineering Ltd

SECTION 11 – BOILER CONTROL PHILOSOPHY

Instrumentation & Control 3 Transmitter


System
Secondary Element.
Instrumentation and control system is
It has the responsibility of passing the
designed for minimum local manning information acquired by the sensor to
and operator attention with the controller and sending the controller
facility for local start up and shut decision to the final control element.
down, if required. The basic need of
the instrumentation is for safe Measurement and control signals may
operation and efficient functioning of be transmitted or as electrical signals.
the plant. This can be achieved by Typical examples: Electrical
installing optimum number transmitters.
measurement, indicating,
transmitting and controlling
instruments for all required 4 Final control element
parameters of the plants (e.g.
pressure, level, temperature, flow etc.) Have the task of actually implementing
Operator supervision shall normally the control command issued by the
be from DCS. Alarm annunciation for controller on the process.
process and equipment malfunction Typical examples: Control valve, VFD
has been envisaged in DCS. motors, electric motors etc.

BASIC COMPONENTS OF A The importance of these components is


CONTROL SYSTEM/ CONTROL that they perform the three basic
SYSTEM HARDWARE operations that must be present in
every control system. These operations
are:
There are four basic components of all
control systems: 1. Measurement (M): Measuring the
variable to be controlled is usually
1. Sensor done by the combination of sensor
and transmitter.
Also often called as Primary Element.
Acquires information about the status 2. Decision (D): Based on the
of the process variables. measurements and the set point,
the controller must then decide,
Typical examples: what to do to maintain the variable
RTD/Thermocouples (for temperature at its desired value.
measurements), Capacitance type
cells (for liquid level /draft /pressure 3. Action (A): As the result of the
measurements), etc. controller's decision, the system
must then take an action. This is
2. Controller usually accomplished by the final
control element.
The Brain or Heart Of the control
system (the decision maker).
Operator Interface:
It is the hardware element with Built-
in capacity for performing the only For smooth operation of boiler, the
task requiring some forms of following minimum features are
Intelligence. required at DCS:
Typical examples: Electronic - Real/ Historical trends
controllers, digital computers used as - Data overview display
controller.

1 X 80 TPH CFBC Boiler Section 11, Page 1


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C11
Rev 00 01/ 06.07.13
Isgec Heavy Engineering Ltd

- Graphical mimic with dynamic FAN Inlet Guide Vanes (IGV) opening /
animation VFD speed as per the deviation from
- Data storage and retrieval set point.
- On demand/ shift/ daily /weekly
reports Control action of this controller is Direct
- Extensive alarm management i.e. if draft value increases the opening
- Event storage of IGV/speed command to VFD also
- Engineering software function increases and vice versa.
-Tuning of control parameters IGV and VFD is controlled by separate
-Changing of alarm controllers and at a time only one
controller will be in auto mode and the
Signal using for realising close loop other one, which will be in manual,
control and data acquisition: should be given 100% command. Ratio
factor is provided to balance the load on
-Transmitter signal: 4 to 20 mA parallel fans as per the site condition.
-Thermocouple signal: mV Initially the ratio is kept 1.
-RTD signal : Resistance
2. STEAM TEMPERATURE:
This loop maintains a constant
Major Control Loops of the boiler
temperature of steam at final super
heater outlet. The outlet steam
- Furnace Draft Control
temperature is sensed using
- Steam Temp Control temperature sensors.
- Drum Level Control A cascade control strategy is followed to
take care of final super heater response
- Combustion Control
to the spray water control provided
- Deaerator level control between stages of the superheaters.
The master controller takes the input of
- Deaerator Pressure Control main steam temperature and generates
- CBD Tank level control controller output used as set point to
slave controller. The slave controller
- Start Up Vent Control gets process value of steam temperature
- BFP Discharge Header Pressure after attemperator and regulates the
Control attemperator valve.
- Soot Blower Pressure Control For better control, in addition to this, a
part of feed forward signal of furnace
temperature difference with respect to
1. FURNACE DRAFT CONTROL: time is added with the slave controller
Typically the boiler flue gas system output.
comprises two Induced draft (ID) alias
flue gas fans with inlet vanes or inlet 3. DRUM LEVEL CONTROL:
damper, and the dampers after the A. Drum level is measured using drum
fan. Alternatively the control vanes level transmitters. The final output is
can be replaced with Variable compensated for drum pressure. As the
frequency Drives as speed controller characteristics of Drum pressure Vs
for Fans. Drum level is non-linear, the
Furnace pressure transmitters are compensated signal is to be generated
located at the same elevation in upper in DCS.
section of the furnace. The furnace B. Main Steam Flow
pressure (Draft) is one of the boiler
interlock signals. Main Steam flow is measured with the
help of steam flow transmitters. These
In this control loop, Furnace pressure transmitters output is compensated for
is controlled by ID fan Inlet Guide main steam pressure and main steam
Vanes/ VFD. Furnace pressure signal temperature.
is fed to furnace draft controller which
controls the furnace pressure by ID
1 X 80 TPH CFBC Boiler Section 11, Page 2
M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C11
Rev 00 01/ 06.07.13
Isgec Heavy Engineering Ltd

This compensated flow is computed in additional two parameters i.e. total feed
flow computing circuit where water flow and compensated main
averaging of compensated steam flow steam flow.
signal is generated as per following
In this control loop, 100% feed water
formula
control valve is controlled. In this
control we first take the difference of
QC=Q x √ (Pa+1.033) x (Td+273)
compensated main steam flow and total
(Pd+1.033) x (Ta+273)
feed water flow. Then this difference is
Where
QC=Compensated Steam Flow
re-ranged from +100 to -100 with
Q=Un-compensated Steam Flow from FT respect to +feed water flow range to –
Pa=Process Value of Main Steam Pressure feed water flow range. This value is then
Ta=Process Value of Main steam temp. multiplied with a factor called Steam
Pd=Design Pressure Load Factor (initially kept 0.3, which is
Td=Design Temperature. finally adjusted during the
Note: Pd and Td are the values on commissioning of Boiler). This value is
which DP calculations are done by passed through a selector switch which
nozzle supplier. All pressures are in passes 0 when single element is
Kg/Cm2 and Temperatures are in selected and passes the previously
DegC. calculated value when three element is
selected. Output of selector switch is
C. Feed Water Flow directly added to the output of PID
block which gives the output by
Feed Water Flow is measured with the
help of flow transmitter. The output of considering the drum level.
these transmitters is used in three Now if the selector switch is in single
element control. element position, selector switch passes
0 and then drum level control is
Note: If spray water tapping is taken
before feed water nozzle, Spray flow is considering the drum level only and if
to be added with Feed water flow to the selector switch is in three element
calculate total water consumption. position, selector switch passes the
calculated value generated by the
Control Loop difference of compensated main steam
flow and total feed water flow which is
Drum Level Control for 30%
added in the output of PID block
Control Valve:
considering drum level. In three element
The compensated drum level signal is control, a feed forward signal of the
compared with the set point in the difference in steam and feed water flow
primary level controller and the is utilized to compensate the water fed
output of the control controller is to the drum in fluctuating conditions of
used to regulate the 30% control load to make the control more effective.
valve.
4. COMBUSTION CONTROL:
30% feed water flow control valve is
working only in Single element drum A. Combustion Air Control
level control loop and take care of
This control loop controls the air supply
boiler feed water demand at start-up
to the boiler thru various fans and
duration and at lower load.
controls the fuel feeding depending on
the boiler load and maintains the boiler
Drum Level Control for 100%
pressure and excess air levels in the
Control Valve:
boiler.
100% feed water flow control valve is
Required combustion air quantity of
having option to control water flow in
solid fuel is determined based on air
boiler in Single element drum level
requirement at various loads. This is
control and Three element drum level
compensated based on excess oxygen
control.
level to increase or decrease the air flow
Three element drum level control loop to maintain the required conditions.
take care of sufficient water flow by
considering the drum level with
1 X 80 TPH CFBC Boiler Section 11, Page 3
M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C11
Rev 00 01/ 06.07.13
Isgec Heavy Engineering Ltd

The fuel supply to the boiler shall O2) is detected. Fuel feeding should be
depend on the boiler load and the immediately stopped if such condition
pressure of the boiler. arises.
Control Loop: Control Loop:
This loop maintains required air flow Oxygen trimming controller is giving the
in boiler as per the load v/s air flow O/P which is scaled between 0.9 to 1.1
curve. In this control loop, PA and SA and the same is multiplied and send to
air flow is controlled by fan Inlet the air flow controller as a remote set
Guide Vanes / VFD. point.
PA fan air flow signal with density Control action of this controller is
correction is fed to PA air flow Reverse i.e. if flow value increases the
controller which controls the PA fan output of controller decreases and vice
air flow as per the deviation from the versa.
remote set point generated out of the
C. Main Steam Pressure Control
curve depending on the load on the
boiler. The objective is to match the boiler’s
steam production to the steam demand
The total air required by the boiler is
of the process. To accomplish this
controlled using the control of air thru
objective the system must be designed
the upper and lower SA nozzles. These
to maintain a constant steam pressure
nozzles dampers are regulated based
and generate a demand for fuel to the
on a load Vs Total air curve for the
boiler.
boiler. Depending on the deviation of
actual measured total air flow and the The plant load change cause the steam
value generated out of the curve at flow to change which in turn causes a
the load of the boiler, the dampers of change in the main steam pressure.
upper and lower SA nozzles are Main steam pressure controller adjusts
controlled. the demand to the fuel which eliminates
deviation between the pressure set point
Control action of this controller is
and the steam pressure measurement.
Reverse i.e. if flow value increases the
output of controller decreases and The Boiler Masters output sets the
vice versa. demand to the boilers fuel which in turn
respond accordingly to both satisfy the
B. Oxygen Trim Control
steam flow demanded by the process
The oxygen trim controller is and eliminate any deviation between the
responsible for controlling the boiler’s main steam pressure and the pressure
excess air by trimming the air flow set point.
based on the oxygen content
Control loop:
measured in the flue gas. The
controller compares the oxygen The main steam pressure control of the
content of the flue gas to the operator boiler depends on the steam demand
adjustable set point and accordingly from the system. If the steam demand
generates an output that will cause from the system is high, then high
an adjustment to the set point of the amount of fuel shall be required to
air flow controller. The adjustment is maintain the pressure and vice versa. In
limited to ±10% of the required order to maintain a constant pressure,
airflow. the steam generation shall be increased
by increasing the fuel flow. Main Steam
It should be noted that oxygen
Pressure is considered as a major
content in flue gas is one of the most
parameters for combustion control.
important variables to be monitored
during the operation of the boiler. A The measured value is compared with
low content is indicative of fuel main steam pressure set point meant
overfeeding into the combustion for fuel flow and combustion air flow
chamber, and an alarm will be control logic system. The master
initiated to warn the operators when a pressure controller will generate the
low oxygen condition (typically<1% demand signal for fuel.

1 X 80 TPH CFBC Boiler Section 11, Page 4


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C11
Rev 00 01/ 06.07.13
Isgec Heavy Engineering Ltd

For better control, in addition to this, Pressure signal is fed to controller


a part of feed forward signal of which controls the Pressure by Pressure
furnace temperature and main steam control valve as per the deviation from
flow difference with respect to time is set point.
added with the controller output.
Control action of this controller is
The fuel demand signal of master Reverse i.e. if Pressure value increases
pressure controller is given as set the opening of control valve decreases
point to individual fuel feeder drives and vice versa.
with adjustable gain factor.
Individual analog output signal is
7. CBD TANK LEVEL CONTROL
provided with an Auto/Manual station
in DCS system to each feeder. The CBD tank level is controlled by the
control valve which is located between
Control action of this controller is
the blow down tanks.
Reverse i.e. if pressure value
increases the output of controller The loop maintains the CBD vessel level
decreases and vice versa. at a predetermined value. The level is
sensed by the level transmitter and
Secondary Air Header Pressure
used as a feed forward signal to the
Control
controller This final output of the
In this control loop, SA fan discharge controller will regulate the control valve.
pressure is controlled by regulating
Control action of this controller is Direct
the SA fan. SA fan discharge pressure
i.e. if level value increases the output of
signal is fed to SA fan discharge
controller increases and vice versa.
pressure controller which controls the
discharge pressure as per the
8. START UP VENT CONTROL
deviation from set point.
Start up vent control valve maintains
Control action of this controller is
the minimum main steam flow and the
Reverse i.e. if SA pressure increases
main steam pressure (in case pressure
the opening command decreases and
increases beyond a predetermined
vice versa.
value). Main steam Pressure and
5. DEAERATOR LEVEL CONTROL: Minimum steam flow is maintained by
two different controllers by higher
In this control loop, Deaerator level is
output selection.
controlled by Deaerator level control
valve. Deaerator level signal is fed to Control action of main steam pressure
controller which controls the controller is Direct i.e. if pressure value
Deaerator level by level control valve increases the output of controller
as per the deviation from set point. increases and vice versa.
Control action of this controller is Control action of minimum main steam
Reverse i.e. if level value increases the flow controller is Reverse i.e. if flow
opening of control valve decreases and value increases the opening of control
vice versa. valve decreases and vice versa.
DEAERATOR OVER FLOW
9. SOOT BLOWER PRESSURE
CONTROL
CONTROL
High-High level, operates the over flow
control valve in On/Off mode, thereby In this control loop, Soot blower
maintaining the water level in Pressure is controlled by soot blower
Deaerator up to desired limits. Pressure control valve. Soot blower
Pressure signal is fed to controller
6. DEAERATOR PRESSURE which controls the soot blower Pressure
CONTROL: by Pressure control valve as per the
deviation from set point.
In this control loop, Pressure of
Control action of this controller is
Deaerator is controlled by Deaerator
Reverse i.e. if Pressure value increases
Pressure control valve. The Deaerator

1 X 80 TPH CFBC Boiler Section 11, Page 5


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C11
Rev 00 01/ 06.07.13
Isgec Heavy Engineering Ltd

the output of controller decreases and


vice versa.

10. BFP DISCHARGE HEADER


PRESSURE CONTROL

In this control loop, BFP discharge


header pressure is controlled by
VFD/Fluid Coupling. BFP discharge
header pressure signal is fed to
controller which controls the BFP
discharge header pressure by
regulating the VFD speed /scoop
command as per the deviation from
set point. The normal set point for
this controller is 5 to 10 kg/cm2
above drum pressure.
Control action of this controller is
Reverse i.e. if Pressure value
increases the output of controller
decreases and vice versa.

1 X 80 TPH CFBC Boiler Section 11, Page 6


M/s. PT Tereos FKS, Indonesia

You might also like