Professional Documents
Culture Documents
b. Engineering Manager/Assistant Engineering Manager shall oversee that all defects are
promptly and properly rectified and instruct Building Supervisor/Building Officer to announce
appropriate message (see Annex 2A) via PA System.
2. Procedure
When the Fire Command Centre (FCC) detects a power failure or is informed of a power
failure, Building Supervisor/Building Officer in FCC shall contact the Engineering
Manager/Assistant Engineering Manager/Engineering Supervisor to immediately attend to
the problem.
• Proceed to the affected area to check the cause of the tripping and isolate/rectify the
fault
• Reset the electrical leakage current breaker(s) or miniature circuit breaker(s) and
report to Engineering Manager/Assistant Engineering Manager.
Page 1 of 5
Revised on 5th February 2018
Instruct Technician to check if all affected systems such as air-conditioning system,
lift, etc. is supported by the emergency genset
Proceed to the affected switchroom and note the fault registered at the switchboard
Inform the Engineering Manager of the findings
Check the cause of the tripping and isolate/rectify the fault
Reset switchboard to put power supply to normal
Report via walkie-talkie to Engineering Manager/Building Operation Manager when
the system is back to normal
Check with PLN the cause of power failure and when it can be restored.
Instruct Technician to check if all affected systems such as air-conditioning system,
lift, etc. is supported by the emergency genset
Inform General Manager (FM)/Building Operation Manager of the findings.
Instruct Assistant Engineering Manager/Engineering Supervisor/Technician to
standby at LT switchroom to reset switchboards and re-activate M&E equipment
after power has been restored.
Assistant Engineering Manager/ Engineering Supervisor to check M&E equipment
such as chillers, cooling tower, lift, plasma/LCD TV are in normal operating
condition. If not, to rectify immediately.
Report to Head (FM)/Building Manager when the system is back to normal.
Request PLN for a letter on the time power failure.
If the power failure results in major or total power failure in the building, Building
Supervisor/Building Officer shall co-ordinate the emergency operation.
iii Carpark
Deploy 2 Security Officer at carpark exit barrier to manually open the exit barrier
All vehicles are allowed 'free' exit during power failure
iv Lift Mantrap
Building Supervisor/Building Officer to check if any passengers are trapped inside the lift. If
so, Building Supervisor/Building Officer shall activate and direct lift contractor for lift rescue
operations.
v Signages
Check to ensure all systems are back to normal on resumption of normal supply, Report to
General Manager (FM) and inform the Tenants via PA System (see message text 2 at
Annex 2A) Send letters of apology to Tenants affected by the emergency after situation is
back to normal. Submit a report to the General Manager (FM within 24 hours
Page 3 of 5
Revised on 5th February 2018
f. Contingency plan
If the generator could not be started manually, the generator term contractor should
be called to rectify the fault.
Engineering Manager shall determine how long can the normal power supply is
restored. If the normal power supply cannot be restored within the next working day,
Engineering Manager shall activate the diesel fuel supplier to top up the diesel tank.
Alternatively, he shall seek permission from General (FM) to install an emergency
portable power generator.
Page 4 of 5
Revised on 5th February 2018
ANNEX 2A
The power failure has affected the building air-condition, lift and card access operation. We are
attending to the problem and will inform you of further developments. All Tenants are advised to
safeguard access control to the office premises. We apologise for the inconvenience caused.
Thank you."
(Announce twice)
Power supply to the building has been restored. All affected services are now back to normal. We
apologise for the inconvenience caused.
Thank you."
(Announce twice)
Page 5 of 5
Revised on 5th February 2018