RENCANA ANGGARAN BIAYA

(RAB)
UNIT KERJA : -
KEGIATAN :
LOKASI :
TAHUN ANGGARAN : 2021

Tanggal : 18 June 2021


TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN
HARGA

A PEKERJAAN SISTEM PENDINGIN

1 PABRIK ES AMONIA, KAP. 20 TON x 1 set

a Brine Tank, kapasitas 400 ice can


a.1 Plat Baja tebal 8mm 1.00 ls Rp574,000,000.00 Rp574,000,000.00
Besi Siku
a.2 Insulation Polyurethane Foam Density : 45 ± 3% kg/m3, tebal 100mm 1.00 ls Rp97,000,000.00 Rp97,000,000.00
a.3 Brine Agitator, vertical cyl, 5HP, 380V/50Hz/3PH 2.00 unt Rp23,000,000.00 Rp46,000,000.00
a.4 Pengguling dengan pelapisan HOTDIP 1.00 ls Rp62,000,000.00 Rp62,000,000.00
a.5 Filling Water Tank 1.00 ls Rp57,000,000.00 Rp57,000,000.00
- Pompa Air lengkap jalur pemipaan air ke sistem pengisian air cetakan es
a.6 Cetakan Es, Kap. 50Kg 400.00 bh Rp895,000.00 Rp358,000,000.00
- Bahan : Besi tebal 1.8 – 2.0mm dengan pelapisan HOTDIP
- Ukuran : Atas 260mm x 260mm, Bawah 240mm x 240mm, Tinggi 115mm
a.7 Frame Cetakan Es dengan pelapisan HOTDIP, kapasitas 16 cetakan/baris 25.00 bh Rp11,000,000.00 Rp275,000,000.00
a.8 Crane System 1.00 ls Rp319,000,000.00 Rp319,000,000.00
- Konstruksi Baja Crane
- Crane naik turun (motor 7.5HP) + Trolley Maju Mundur (motor 5HP)
a.9 Frame pinggiran Bak Celup, siku besi 1.00 ls Rp16,000,000.00 Rp16,000,000.00
a.10 Papan Penutup Brine Tank 1.00 ls Rp13,000,000.00 Rp13,000,000.00
a.11 Garam 14.00 ton Rp5,800,000.00 Rp81,200,000.00

b Mesin Pendingin dan Accessories


b.1 Condensing Unit 60HP 1.00 Set Rp1,377,000,000.00 Rp1,377,000,000.00
Open Type Compressor MYCOM 8WA, 380V/50Hz/3PH
Electro Motor TECO 60HP, 380V/50Hz/3PH
Expansion Valve
Oil Separator
Filter Drier
Liquid Solenoid Valve
Check Valve
Stop Valve
High & Low Pressure Switch
Accumulator
Liquid Receiver Tank
Sight Glass
Manometer Pressure Gauge
NH3 Refrigerant Pipe system complete with insulation pipe and insulation tape
Lubricant Oil
Sheel N Tube Condensor
Condenser water pump EBARA 10HP
Cooling Tower LBC 075
Refrigerant : Ammonia (NH3)
Chasis

b.2 #VALUE! 1.00 unit Rp192,000,000.00 Rp192,000,000.00


Bahan : Seamless 1”, SCH40
Spiral System

b.3 Control Panel & Instalasi 1.00 Ls Rp319,000,000.00 Rp319,000,000.00


MCCB
Magnetic Contactor
Thermal Overload
Indicator lamp
Time Delay Relay
Cable from control panel to compressor : NYY
Cable From control Panel to evaporator and condensor : NYY

SUB TOTAL PABRIK ES Rp3,786,200,000.00

2 ICE STORAGE, KAP. 50 TON x 1 set, Uk. P. 10.5m x L. 5.0m x T. 3.2m (Dimensi Luar), Suhu Ruangan -15oC

a Panel Insulasi Ruangan 1.00 set Rp198,000,000.00 Rp198,000,000.00


a.1 Atap
Spesifikasi :
- Polyurethane Foam, Density 45kg/m3 ± 3%
- Thickness : 75mm
- Skin : Bahan PPGI, tebal 0.5mm (2 sisi)
- Connection : Cam-lock Joint
a.2 Dinding
Spesifikasi :
- Polyurethane Foam, Density 45kg/m3 ± 3%
- Thickness : 75mm
- Skin : Bahan PPGI, tebal 0.5mm (2 sisi)
- Connection : Cam-lock Joint
a.3 Lantai
Spesifikasi :
- Polyurethane Foam, Density 45kg/m3 ± 3%
- Thickness : 75mm
- Skin : Bahan Alumunium Foil, (1 sisi atas) & Plastic sheet (1 sisi bawah)
- Connection : Manual Injection foam at site
b Accessories Pemasangan Ruangan Panel Insulasi 1.00 ls Rp14,000,000.00 Rp14,000,000.00
b.1 Atap
- Sealant, Tutup Cam-lock, Lampu weatherproof lengkap instalasi kabel,Rivet, Siku PVC, dll.
b.2 Dinding
- Sealant, Tutup Cam-lock, Saklar lampu & heater,Thermometer Jarum dll.
b.3 Lantai
- Cairan ISO & POLY
c Pintu Pendingin Ruangan 1.00 set Rp18,000,000.00 Rp18,000,000.00
Spesifikasi :
- Uk. L. 1.0m x T. 2.0m
- Type : Swing
- Polyurethane Foam, Density 45kg/m3 ± 3%
- Thickness : 75mm
- Skin : Bahan PPGI, tebal 0.5mm (2 sisi)
- Accessories : Handle, Engsel, Kusen, Heater, Strip Curtain, Hanger & Bracket
d Jendela Pendingin Ruangan 1.00 set Rp11,000,000.00 Rp11,000,000.00
Spesifikasi :
- Uk. L. 0.7m x T. 0.7m
- Type : Swing
- Polyurethane Foam, Density 45kg/m3 ± 3%
- Thickness : 75mm
- Skin : Bahan PPGI, tebal 0.5mm (2 sisi)
- Accessories : Handle, Engsel, Kusen, Heater, Strip Curtain, Hanger & Bracket
e Mesin Pendingin & Accessoriesnya
e.1 Condensing Unit 1.00 Unit Rp113,000,000.00 Rp113,000,000.00
- Compressor Kapasitas Min. 9HP, Type Semi-Hermetic
Displacement : Min. 41 m3/h
No of Cylinder : Min, 3 Cylinder
Voltage range : 380V/3PH/50Hz
Cooling cap. : Min. 11 kW @TE -25oC & TC 40oC
- Condenser
Type : Air Cooled
Fan Qty : Min 2 x 500mm
- Acc Condensing Unit
e.2 Evaporator 1.00 Unit Rp60,000,000.00 Rp60,000,000.00
- Cooling Cap. : Min, 11kW @ TE -25oC & Room Temperature -19oC
- Fin Spacing : min.6mm
- Fan Qty : Min. 2 x 500mm
- Air Throw : min.31m
- Air Flow : Min. 14000 m3/h
- Defrost type : Electric in Coil & Drain Pan
e.3 Control Panel 1.00 ls Rp33,000,000.00 Rp33,000,000.00
- MCCB / MCB
- Magnetic Contactor
- Thermal Overload
- Indicator Lamp
- Time Delay Relay
- Temperature & Defrost Digital Controller
e.4 Komponen Instalasi & Instalasi 1.00 ls Rp41,000,000.00 Rp41,000,000.00
- Kabel Kabel Pengendali Mesin Mesin Utama (Compressor, Condenser & Evaporator)
- Pipa Tembaga ASTM B 280 (Hard Temper) atau Setara
- Pipe Insulation
- Refrigerant : R 404a

HARGA ICE STORAGE 20 TON Rp488,000,000.00

SUB TOTAL SISTEM PENDINGIN Rp4,274,200,000.00

B LAIN – LAIN
a Panel Distribusi 105kva 1.00 Ls Rp158,000,000.00 Rp158,000,000.00
a.1 lengkap kabel power & skun untuk ke Control Panel Pabrik Es
a.2 lengkap kabel power & skun untuk ke Control Panel Ice Storage

SUB TOTAL LAIN – LAIN Rp158,000,000.00

TOTAL KESELURUHAN Rp4,432,200,000.00


PPN 10% Rp443,220,000.00
TOTAL AKHIR KESELURUHAN Rp4,875,420,000.00

Kondisi Harga :
* Termasuk jasa pemasangan di lokasi Pulau Nusa Tenggara Timur & Nusa Tenggara Barat
* Termasuk PPN 10%
* Termasuk Garansi Servis selama 12 bulan setelah serah terima pekerjaan (tidak meliputi transportasi, akomodasi & konsumsi)
* Termasuk Garansi Spare Part selama 12 bulan setelah serah terima pekerjaan (tidak meliputi transportasi pengiriman barang)
Catatan : 1. Garansi dapat berlaku dengan ketentuan bukan karena kesalahan operasional, tegangan yang tidak stabil, huru – hara, bencana alam dan aus karena pemakaian
2. Garansi ini tidak termasuk oli, lampu, heater pintu, penambahan freon, handle, rel dan filter drier
* Termasuk pengiriman barang ke lokasi Pulau Nusa Tenggara Timur & Nusa Tenggara Barat
* Termasuk transportasi, konsumsi dan akomodasi teknisi saat perjalanan dan pemasangan di lokasi Pulau Nusa Tenggara Timur & Nusa Tenggara Barat
* Termasuk bahan pendukung kerja seperti Oksigen, LPG dan Nitrogen
* Tidak Termasuk listrik / genset untuk running test
* Tidak Termasuk power listrik PLN untuk sarana kerja
* Tidak Termasuk kebutuhan air untuk brine tank & bahan baku es balok
* Tidak Termasuk kabel power dari Gardu utama (PLN) ke Panel Distribusi / Compressor