System Earthing and Lightening Arrestor For 4U3S RCC Building

Estimated For Material Charges

Builder's Quantity

Sr No Particular Unit Rate(K) Qty Amount(K) Remark

A Lightening Arrester
1 Earth Plate C.I 12" x 12" x 1/4" thk Sht 25000 4 100000
2 Earth Spike 3/4" dia and 6' MS Rod No 9000 8 72000
3 Hard drawn bare copper wire No.2 Lb 6000 60 360000
4 Lightening Arrester 3ft copper with base frame Set 45000 6 270000
5 Earth Test Terminal Box No 15000 4 60000
6 PVC Conduit (10'-length)
(a) 20 mm (White Color) No 1000 55 55000
7 PVC Saddle (20mm) No 80 50 4000
Cost of Material (A) 921000

B Earthing System
1 Earth Plate C.I 12" x 12" x 1/4" thk Sht 25000 2 50000
2 Earth Spike 3/4" dia and 6' MS Rod No 9000 4 36000
3 Hard drawn bare copper wire No.6 Lb 6000 10 60000
4 Earth Test Terminal Box No 12000 2 24000
Cost of Material (B) 170000

C Miscellaneous Charges
1 Black Screw (1") Kg 4500 1 4500
2 PVC Wall Plug (No-7) Pax 3000 1 3000
Cost of Material (C) 7500

Total Material Cost 1098500

1
System Earthing and Lightening Arrestor For 4U3S RCC Building
Estimated For Labour Charges

Builder's Quantity
Sr No Particular Unit Rate(K) Qty Amount(K) Remark

A Lightening Arrester
1 Earth Plate C.I 12" x 12" x 1/4" thk Sht 5000 4 20000
2 Earth Spike 3/4" dia and 6' MS Rod No 7000 8 56000
3 Hard drawn bare copper wire No.2 Rft 300 540 162000
4 Lightening Arrester 3ft copper with base frame Set 7000 6 42000
5 Earth Test Terminal Box No 5000 4 20000
6 PVC Conduit (10'-length)
(a) 20 mm (White Color) Rft 100 550 55000
7 ‌ြေမကျင်းတူ းခ ကျင်း 15000 4 60000
Cost of Labour (A) 415000

B Earthing System
1 Earth Plate C.I 12" x 12" x 1/4" thk Sht 5000 2 10000
2 Earth Spike 3/4" dia and 6' MS Rod No 7000 4 28000
3 Hard drawn bare copper wire No.6 Rft 300 90 27000
4 Earth Test Terminal Box No 5000 2 10000
5 ‌ြေမကျင်းတူ းခ ကျင်း 15000 2 30000
Cost of Labour (B) 105000

Total Labour Cost 520000

2
System Earthing and Lightening Arrestor For 4U3S RCC Building
Internal Electrical Installation Work

Abstract Cost

Item Description Unit Material Labour Total Remark

1 Lightening Arrester Item 921,000 415,000 1,336,000

2 Earthing System Item 170,000 105,000 275,000

3 Miscellaneous Charges Item 7,500 - 7,500

Total ( Material + Labour ) Cost 1,098,500 520,000 1,618,500

Transportating Charges (3% of Material) 32,955

Supervision Charges (10% of Mat+Lab+Transport) 165,146

Grand Total 1,816,601 (KYATS)

Commercial Tax (5%) 90,830.03

Total 1,907,430.53 (KYATS)

SAY 1,907,400 (KYATS)