Government of Province

Provincial Policy and Planning Commission


Gandaki Province, Pokhara, Nepal
Gandaki Technical Institute (GIT) Infrastructure Development Project
Gandaki Province

S.No. Description Building Type Number of Storey No.s Area Unit Cost
A Civil Works
1 Landscape and Land Development 1 26172.41 Sq.m 112,646,031.12
2 Boundary Wall 1 1034.00 R.m 16,544,000.00
3 Academic Block RCC 3 5 528.00 Sq.m 298,267,200.00
4 Library and Student Centre RCC 3 1 576.00 Sq.m 68,795,136.00
5 Administration RCC 3 1 576.00 Sq.m 65,076,480.00
6 Staff Quarter 1 RCC 2 4 60.38 Sq.m 16,630,656.00
7 Staff Quarter 2 RCC 1 12 48.00 Sq.m 23,551,488.00
8 Hostel RCC 3 7 206.93 Sq.m 158,973,028.20
9 Workshop and Laboratories 1 Truss 2 120.00 Sq.m 8,780,160.00
10 Workshop and Laboratories 2 Truss 3 240.00 Sq.m 26,340,480.00
11 Auditorium Hall RCC 1 1 900.00 Sq.m 38,736,000.00
12 Canteen RCC 1 1 184.49 Sq.m 7,344,876.07
13 Sports Hall Truss 1 975.52 Sq.m 35,688,423.68
14 Shops and Stationery Centre RCC 1 3 32.00 Sq.m 3,512,064.00
15 Guest House RCC 1 1 48.00 Sq.m 1,859,328.00
16 Water Tank RCC 1 R 4.23 1,690,000.00
17 Road Asphalt 0.438 Km 19,710,000.00
18 Demolition 1518.000 Cu.m 3,900,592.08

B Total Civil Works 908,045,943.15

C Electrical (7% ) 63,563,216.02


D Sanitary (8% ) 72,643,675.45
E Total (B+C+D) 1,044,252,834.62
F Contingencies (4% of E) 41,770,113.38
G Vat (13% of E) 135,752,868.50
H Price Escalation (10%) 122,177,581.65
I Grand Total 1,343,953,398.16
Government of Province
Provincial Policy and Planning Commission
Gandaki Province, Pokhara, Nepal
Gandaki Technical Institute (GIT) Infrastructure Development Project
Gandaki Province

S.No. Description Building Type Number of Storey No.s Area Unit Cost
A Civil Works
1 Landscape and Land Development 1 26172.41 Sq.m 112,646,031.12
2 Boundary Wall 1 1034.00 R.m 16,544,000.00
3 Academic Block _1 RCC 3 4 528.00 Sq.m 238,613,760.00
4 Academic Block _2 RCC 3 3 240.00 Sq.m 81,345,600.00
5 Library and Student Centre RCC 2 2 240.00 Sq.m 38,219,520.00
6 Administration RCC 3 1 576.00 Sq.m 65,076,480.00
7 Staff Quarter 1 RCC 2 4 60.38 Sq.m 16,630,656.00
8 Staff Quarter 2 RCC 1 8 48.00 Sq.m 15,700,992.00
9 Hostel RCC 3 7 206.93 Sq.m 158,973,028.20
10 Workshop and Laboratories 1 Truss 2 235.00 Sq.m 17,194,480.00
11 Workshop and Laboratories 2 Truss 2 235.00 Sq.m 17,194,480.00
12 Auditorium Hall RCC 1 1 900.00 Sq.m 38,736,000.00
13 Canteen RCC 1 1 185.00 Sq.m 7,365,220.00
14 Sports Hall Truss 1 975.52 Sq.m 35,688,423.68
15 Shops and Stationery Centre RCC 1 2 32.00 Sq.m 2,341,376.00
16 Guest House RCC 1 1 48.00 Sq.m 1,859,328.00
17 Water Tank RCC 1 R 4.23 1,690,000.00
18 Road Asphalt 0.438 Km 19,710,000.00
19 Demolition 1518.000 Cu.m 3,900,592.08

B Total Civil Works 889,429,967.08

C Electrical (7% ) 62,260,097.70


D Sanitary (8% ) 71,154,397.37
E Total (B+C+D) 1,022,844,462.14
F Contingencies (4% of E) 40,913,778.49
G Vat (13% of E) 132,969,780.08
H Price Escalation (10%) 119,672,802.07
I Grand Total 1,316,400,822.78