S.No. Description Building Type Number of Storey No.s Area Unit Cost
A Civil Works
1 Landscape and Land Development 1 26172.41 Sq.m 112,646,031.12
2 Boundary Wall 1 1034.00 R.m 16,544,000.00
3 Academic Block RCC 3 5 528.00 Sq.m 298,267,200.00
4 Library and Student Centre RCC 3 1 576.00 Sq.m 68,795,136.00
5 Administration RCC 3 1 576.00 Sq.m 65,076,480.00
6 Staff Quarter 1 RCC 2 4 60.38 Sq.m 16,630,656.00
7 Staff Quarter 2 RCC 1 12 48.00 Sq.m 23,551,488.00
8 Hostel RCC 3 7 206.93 Sq.m 158,973,028.20
9 Workshop and Laboratories 1 Truss 2 120.00 Sq.m 8,780,160.00
10 Workshop and Laboratories 2 Truss 3 240.00 Sq.m 26,340,480.00
11 Auditorium Hall RCC 1 1 900.00 Sq.m 38,736,000.00
12 Canteen RCC 1 1 184.49 Sq.m 7,344,876.07
13 Sports Hall Truss 1 975.52 Sq.m 35,688,423.68
14 Shops and Stationery Centre RCC 1 3 32.00 Sq.m 3,512,064.00
15 Guest House RCC 1 1 48.00 Sq.m 1,859,328.00
16 Water Tank RCC 1 R 4.23 1,690,000.00
17 Road Asphalt 0.438 Km 19,710,000.00
18 Demolition 1518.000 Cu.m 3,900,592.08
S.No. Description Building Type Number of Storey No.s Area Unit Cost
A Civil Works
1 Landscape and Land Development 1 26172.41 Sq.m 112,646,031.12
2 Boundary Wall 1 1034.00 R.m 16,544,000.00
3 Academic Block _1 RCC 3 4 528.00 Sq.m 238,613,760.00
4 Academic Block _2 RCC 3 3 240.00 Sq.m 81,345,600.00
5 Library and Student Centre RCC 2 2 240.00 Sq.m 38,219,520.00
6 Administration RCC 3 1 576.00 Sq.m 65,076,480.00
7 Staff Quarter 1 RCC 2 4 60.38 Sq.m 16,630,656.00
8 Staff Quarter 2 RCC 1 8 48.00 Sq.m 15,700,992.00
9 Hostel RCC 3 7 206.93 Sq.m 158,973,028.20
10 Workshop and Laboratories 1 Truss 2 235.00 Sq.m 17,194,480.00
11 Workshop and Laboratories 2 Truss 2 235.00 Sq.m 17,194,480.00
12 Auditorium Hall RCC 1 1 900.00 Sq.m 38,736,000.00
13 Canteen RCC 1 1 185.00 Sq.m 7,365,220.00
14 Sports Hall Truss 1 975.52 Sq.m 35,688,423.68
15 Shops and Stationery Centre RCC 1 2 32.00 Sq.m 2,341,376.00
16 Guest House RCC 1 1 48.00 Sq.m 1,859,328.00
17 Water Tank RCC 1 R 4.23 1,690,000.00
18 Road Asphalt 0.438 Km 19,710,000.00
19 Demolition 1518.000 Cu.m 3,900,592.08