You are on page 1of 6

BOQ-EQUIPMENTS

SN Item 155 Nos Total Rate Cost Remarks


Capacity Unit Duty Stadndby
1 Coarse Screen,20 mm 16 m3/hr 0 0 0
2 Fine Bar Screen , 6 mm 16 m3/hr 1 0 1 Use this If before Balancing Tank
Fine Bar Screen, 6 mm 6.5 m3/hr 1 0 1 0 Use this if after Balancing Tank
3 Manual By Pass 16 m3/hr 1 0 1 Use this If before Balancing Tank
6 m3/hr 1 0 1 Use this if after Balancing Tank
4 Grit Removal 16 m3/hr 1 0 1 NOT APPLICABLE
6 m3/hr 1 0 1 Use this if after Balancing Tank
Note : The oil grease IS NOT STATED In Balancing Tank ,if reqd provde Skimmer mechanism OR AT LEAST COST FOR IT
5 Balancing Tank 0
Submersible SBR feed Pumps 6.46 m3/hr 1 1 2
Blower for Mixing 30 m3/hr 1 1 2
Diffusers, Coarse Bubble 10 m3/hr 3 3
0 0 0
6 SBR
SBR Aeration Blowers 109 m3/hr 2 1 3 0
Fine Bubble Diffusers 5 m3/hr 44 0 44 0
Decant Mechanism/Valve 19.375 m3/hr 2 0 2 0
WAS pumps 1 m3/hr 2 1 3 0
2 2 0
7 Chlorination System 2 2 0
Dosing Pumps 0.92 l/hr 1 1 2 0
Dosing Tank 28.18 litres 1 0 1 0
Mixers ? On tank 1 Hp 1 0 1 0
0
8 Pressure Sand Filter System dia 0
Pressure Sand Filter 0.90 m 1.00 0 1 0
Filter Feed Pumps, 20 mwc 7.18 m3/hr 1 1 2 0
Backwash Pumps, 20 mwc 19.08 m3/hr 1 1 2 0
Air blowers 32 m3/hr 1 1 2 0 Balancing Tank blower tobe used

9 Sludge Holding Tank


Air blower required 14 m3/hr 1 1 2 0 If combined with Balancing Tank
Coarse Bubble Diffusers 12 m3/hr 1 or SBR blowers, needs tapping
from main aeration line
TOTAL 0 0
Add 5 % for miscellaneous
Add 10 % for erection
GRAND TOTAL OF B/O 8 0.00

2SBR REACTOR -155 CMD 5 Equipments


PIPING
SN From - to Flow,m3/h V, m/s Size SIZE MOC L (mtrs) Mat. Rate Mat cost Lbr rate Lbr Cost Total cost Remarks
LIQUID- RAW SEWAGE, TSE 155
1 Gravity flow from C/S to Balance tank(BT) 16 0.75 87.2 100

2 SBR feed Pump A-Duty 6.46 1.80 36 50


SBR feed Pump B-Standby 6.46 1.80 36 50

3 Raw Sewage Inlet to SBR 1 6.46 2 36 50


Raw Sewage Inlet to SBR 2 6.46 2 36 50

4 Treated Sewage Outlet of SBR-1 19 0.65 103 150


Treated Sewage Outlet of SBR-2 19 0.65 103 150

5 Common Treated Sewage Outlet to CCT 19 0.65 103 150

6 Suction of Filter Feed Pumps 7 1.50 41 50


Dischrage of Filter Feed Pumps 7 2.00 36 50

7 Suction Backwash Pumps 19 1.80 61 80


Discharge of Backwash Pumps 19 2.00 58 80

8 WAS Pumps A- Suction 1 1.00 19 80 Not apllicbale if submersible


WAS Pumps B-scution 1 1.00 19 80
WAS Pumps A-Discharge 1 1.20 17 80
WAS Pumps B-Discharge 1 1.20 17 80

9 Sludge Pumps - Suction 2 1.00 29 80


Sludge Pumps -Discharge 2 1.20 26 80

AIR PIPING
8 Balancing Tank Blower Discharge 30 18.00 24 25
Drop pipes in Balancing tank 3 10 18.00 8 25

9 Air Inlet to SBR-1 109 18.00 46 50


Air Inlet to SBR-2 109 18.00 46 50

10 Drop pipes in SBR-1 , EACH 5 109 18.00 21 25


Drop pipes in SBR-2, EACH 5 109 18.00 21 25

11 Sludge Holding Tank air piping 14 18.00 17 25


Drop pipes in Sludge digestor 2 14 18.00 12 25

TOTAL
Add Fittings cost 20 % of the material cost
GRAND TOTAL OF PIPING

2SBR REACTOR -155 CMD 6 piping


2SBR REACTOR -155 CMD 7 piping
5

2SBR REACTOR -155 CMD 8 piping


0

2SBR REACTOR -155 CMD 9 piping


VALVES

SN Location 155 SIZE MOC Type Operation Nos Rate Cost Remarks
LIQUID- RAW SEWAGE, TSE , BFV:Butterfly valve
Gravity flow from C/S to Balance tank(BT) 100 0 GV -Gate Valve,BV-Ball Valve
KGV-Knife Edge Gate Valve
2 Common Suction of SBR pumps 50 SS-Disc KGV 1 Not applicable if submersible
Isolation valves in individual suctions 50 SS-Disc KGV 2 Not applicable if submersible
SBR feed Pump -suction 50 SS-Disc GV 2 Not applicable if submersible
SBR feed Pump - Delivery 50 SS-Disc GV 2
NRV for Above 50 SS -Disc FLAP 2

3 Raw Sewage Inlet to SBR 1 and 2 50 SS-Disc GV Motorized 2

4 Treated Sewage Outlet of SBR-1 and 2 150 SS-Disc BFV Motorized 2 for Decanters

6 Common Suction of Filter Feed Pumps 50 SS -Disc BFV 1 Not applicable if submersible
Isolation valves in individual suctions 50 SS -Disc BFV 2 Not applicable if submersible
Dischrage of Filter Feed Pumps 50 SS - Disc BFV 2
NRV for Above 50 SS - Disc FLAP 2

7 Backwash Pumps-Common Suction 80 CI BFV 1 Not applicable if submersible


Backwash Pump -Isolation valves 80 CI BFV 2 Not applicable if submersible
Backwash Pumps-Discharge of 80 CI BFV 2
NRV for Above 0 80 CI FLAP 2

8 WAS Pumps isolation valves 80 CI KGV 3


WAS Pumps - Suction 80 CI BFV 3 Not applicable if submersible
WAS Discharge 80 CI BFV 3
NRV for above 80 FLAP 3
PRV valves for above 50 3 if Progressive cavity pump used

9 Service Inlet - Pressure Sand Filter 50 SS -Disc BFV Motorized 1


Service Outlet- Pressure Sand Filter 50 SS -Disc BFV Motorized 1
Backwash Inlet - Pressure Sand Filter 80 SS -Disc BFV Motorized 1
Backwash outlet - Pressure Sand Filter 80 SS -Disc BFV Motorized 1

10 Common isloation VALVE 80 SS - Disc 8 1 if Digestor is used


Sludge Pumps - Suction 80 SS - Disc KGV 2 if Digestor is used
Sludge Pumps -Discharge 80 SS-Disc KGV 2 if Digestor is used
NRV for above 80 FLAP 2
PRV valves for above 50 2 if Progressive cavity pump used

AIR PIPING
SBR Blower Discharge , 1 2,3 50 BV 3
SBR Blower Discharge , 1 2,3 50 NRV 3

SBR AIR INLET 50 BFV 2


SBR DROP PIPES 25 BV 10
Sludge Blower Discharge ,1,2 25 BFV 2
Sludge Blower Discharge ,1,2 25 NRV 2
sludge holding tank Drop pipes 25 BV 2
Balancing Tank Blower Discharge 25 CI BFV 2 2 nos. I duty + standby blower

2SBR REACTOR -155 CMD 10 valves

You might also like