Professional Documents
Culture Documents
2
Broad Creek II WTP-Overview
3
Expansion Project Layout
Ɣ 4-8 mgd
Ɣ New treatment train
Ɣ Lime feed and polymer feed improvements
Ɣ New residuals handling
4
Existing system (<10% lime)
1-1/2” UW
3/4” UW
3/4” UW
LIME LIME 60,000 lbs
60,000 lbs SILO SILO
VOLUMETRIC
FEEDER 2
M 100 cft/hr
M M M
VOLUMETRIC
FEEDER 1
100 cft/hr OVERFLOW OVERFLOW
DISSOLVING DISSOLVING
TANK-1 TANK-2
50 gallons 50 gallons
DRAIN
DRAIN
2” LIME
2” LIME
5
Bin activator and volumetric feeder
6
Feed lines and acid cleaning system
7
Issues with the existing system
Ɣ Scaling
± Acid-cleaning system installed, parallel lines provided
± Increase Chemical (acid) cleaning
± Backup lime slurry line
Ɣ Need redundant train/system for peak demands
Ɣ Better control on lime dosage
8
Alternatives – new feed point (8 mgd)
Ɣ Alternative 1: Retrofit Existing
± Two (2) larger dissolving tanks
± Upsize the piping
± Two (2) new jet pumps
± Continue using acid cleaning system
± No modifications to silo
Bin Activator
Day Tank with metering
Transfer Pump pumps
11
Advantages
12
High/Low Density Lime Comparison
Mixer for batch tank: Mixer for batch tank:
Mixer for batch tank only runs when batching and then Mixer for batch tank must run continuous if
every say 6 hrs for 30 minutes. slurry is in tank.
The HDLS system will have 2 ½ times more lime in
suspension and does not require continuous operation Mixer for the holding/aging tanks:
as stated above. Must run continuous 24/7
13
Evaluation summary
14
Specifics - High density lime (35%)
Ɣ 35% slurry acts as a pseudo plastic and will not settle or
scale pipelines
Ɣ 35% slurry has a viscosity of 200 cps . Tomato juice is
180 cps
Ɣ Size metering pumps with a 30:1 turn-down.
Ɣ Size slurryy p
piping
p g with a min velocity
y of 2 fps
p and max of 4
fps.
Ɣ Low grade hydrated lime contains higher silica causing
pump and meter wear.
Ɣ Less water required (compared to 18%) to produce a high
density slurry.
Ɣ No heat of reaction in the hydration process (safety)
15
No settling at concentrations >20%
16
Courtesy – Merrick Industries, Inc.
17
High Density System Advantages
18
High Density Lime System Installations
19
Proposed HD Lime System
20
Proposed System Design Criteria
21
Proposed layout
22
Conveyor and Batch Tank
23
Hose Pumps – Verderflex Dura
•Slurry Transfer Pumps
•Metering Pumps
24
Batch Tank
25
Day Tank and Metering System
26
Maintenance of plant operations during
construction
Ɣ No shutdowns
Ɣ One lime feed system may be out of service at a time
Ɣ Lime silo must be emptied before existing bin activators can be removed
Ɣ After new treatment train is operational-remove existing lime feed point from service-connect new
lime slurry pipe to existing feed point
27
Acknowledgements
28
Questions???
29