• In Once through (Drum less) boiler : Necessary

• Sub critical (with drum): Recommended

• Low Pressure boiler : Not required


REQUIREMENT OF CPU
• In once through only one way to reduce TDS

• During Condenser tube failure (leakage),


Prevents the boiler system

• In sub Critical units, TDS can be reduced by blow


REQUIREMENT
down but in super criticalOFno blow down facility
above 30% Load (Once through)
CPU….
• CPU Works on the same principle as Mixed
Bed of DM Plant.

• The Reactions are shown in the next


slide.

PRINCIPLE
The Differences which makes the performance of the
CPU ion exchange more difficultare

1. Higher Flow rate

2. Quality of treated water required

3. The higher temperature condition


DIFFERENCES BETWEEN
4. The higher pressureDM PLANT MB
condition
AND CPU
Sr. No. Equipment Description

2 Mixed Bed 2 Nos/Unit(1W+1S)

Shape Spherical

41 Kg/cm2
Max Pressure
656M3/Hr each
Flow
Max DP 3.5Kg/cm2

Internal Stainless steel

MIXED BED
Strainer

Vessel
MSRL
IMPORTANCE OF
RESIN TRAPS
• Resin Traps are very important at the time of any
strainer failure of MB.

• DP across Trap will indicate any leakage of


resin.

• Max allowable DP<2.1Kg/cm2.

• Prevents any ingress of Resin in the system


MAIN STEPS OF
REGENERATION
 Transferring exhausted Resin to Separation/ Anion
Regeneration Vessel

 Resin Separation

 Transferring Cation resin into Cation Regeneration vessel

 Regeneration of Individual resin in its respective vessel

 Mixing of both resin

 Transferring regenerated resin to Mixed Bed


CHEMICAL
HANDLING AREA….
Sr. No. Equipment Description
5. Acid Unloading Pump Quantity : 2 Nos
Capacity : 15 M3 /Hr
Head : 20 M

6. Alkali Unloading Pump Quantity : 2 Nos


Capacity : 15 M3 /Hr
Head : 20 M

Quantity : 2 No
7. Acid metering Pump Capacity : 2400 LPH
Head : 60 M

Quantity : 2 No
8. Alkali metering Pump Capacity : 1500 LPH
Head : 60 M
Sr. No. Equipment Description
1 Pre filters vessel 2 Nos/Unit
Flow (M3/Hr) 822 each

Max Pressure (Mpa) 4.5

Max DP (Mpa) 0.12

PRE Element
FILTERS Porosity
(DE
4
IRONING FILTERS)
(Micron)
 Each unit is provided with 2x50% capacity of pre filters.

 When Fe < 2000~3000 μg/L of condensate polishing system


in the initial start up period of unit, only pre filters are
started to rapidly reduce the content of iron suspended
matter to reduce start up time.

 The pre filters having 100% and 50% bypass system.

PRE FILTERS ….
 When DP>0.12MPa, 100% bypass is opened automatically and
the inlet and outlet valves of pre filter are closed.

 In case a certain pre filter has excessively high pressure drop


then 50% bypass is automatically opened and the failed filter
becomes out of service.

 When DP is high then we will have to go for PF back wash


followed by compressed air scouring.

PRE FILTERS ….
 When back wash is completed, the filter will be taken in
service again.
• Make sure that MB Bypass valve or CPU bypass is open.

• PFs Vessel is Flushed and backwashed properly.

• PFs are filled completely with DM water.

• Ensure all instruments are in line and working properly.


PRECAUTIONS BEFORE TAKING PFS INTO
OPERATION FIRST TIME.
PRE
FILTERS

PF Inlet
PF Outlet
NEW PRE FILTER
CARTRIDGE
AFTER
SERVICE(PREVENTION FROM
CRUD)