Professional Documents
Culture Documents
A Case Study
Questions:
1. Degree of goal conflict. Goals and objectives occur naturally the moment a person
of such goals and objectives is a long process that requires effort and resources.
arises.
one's economic self-interest at the expense of the other. This occurs when one
party is in a difficult situation and needs assistance, while the other party tries to
profit from the situation. For instance, if a project is delayed but the client
party has access to more relevant and timely information while the others are not.
4. Level of trust. It requires a lot of time and connection between two parties before
they can achieve the desired level of trust. Sometimes, it just sort of happens
especially if you work with them for a long time but there are levels of trust. In
the case of Steven and Mark, they can build trust by being open and
will not do any good to the project. It will not only affect the relationship between
the client and contractor but the success of the project as well. In the case study,
Steven and Mark professionally handled the negative event during the project by
In the degree of goal conflict, Steven and Mark were both transparent and open to
their client. They made sure that the goals and objectives of the project were
clearly stated, communicated, and understood. It is one of the ways to reduce the
forward.
In the degree of opportunistic behavior, similar to the situation above, both parties
were transparent and open to the client. As the goals and objectives of the project
were stated, the process was explained next. This will allow both of them to
analyze how the bidders reacted, behaved, and to determine their strengths and
weaknesses.
bidders and vice versa. It may take time to develop the trust and connection, but it
In the level of concealment of negative outcomes, both parties provide all the
important and available information including the strengths and weaknesses, and
the level of difficulty from the project. This shows that both parties are honest and
3. Do you think the way Steven and Mark addressed the agency-related issues was
This is very subjective, but in my opinion, Steven’s and Mark’s way of addressing
the agency-related issues was appropriate and effective because of the successful
implementation of the project. This shows that there is a process that happened including
4. Can you relate mechanisms to resolve agency-related issues in this case to some of
the mechanisms identified in the CURED framework (see Bryde et al, in press)? What
1. Contract, to which both Steven and Mark made sure that the terms and conditions
2. Understanding, to which both Steven and Mark have. Both parties have developed
the process. Both parties are very transparent and open that helps them to reduce
resources are for the project. It is not enough to have the knowledge and skills
because the project will not be put into the process without the resources needed.
4. Education. Since Steven and Mark, including their respective teams, have no
formal education and training before the start of the project. The informal training
only started when the workshop took place, allowing participants to obtain an
5. The delegation, which both Steven and Mark have done by delegating the work to
appropriate team members including themselves. They also delegated some of the
5. Steven and Mark decided to develop their own collaborative way of procuring
concrete and steelworks. Do you think their model should be recommended for
Steven and Mark both did a great job in leading the success of the project. Their
contribution and point of view help the team to progress. However, whether the model
should be recommended for other projects or not is very subjective. There is a lot to
consider such as the resources, the team, terms, and conditions. This should be a matter
of discussion between the team or participants who will handle the project. This model
should only be used as a benchmark that could help and guide the team for the project’s
progress and success. Using this model alone is not advisable since it might need
In my opinion, Steven and Mark's decision to postpone the issue until after the
contract was completed was appropriate. Since one of their intentions is to establish a
collaborative and trustful relationship with the contractor, they showed their willingness
to discuss and resolve all issues and concerns collaboratively and fairly through their
precontract behavior. Again, as I stated in the previous question, this is a very subjective
7. Post-contract award the client offered bonus payments to Construct. Why did they
choose to spend extra money if they are not contractually obliged to do so? Do you
To properly distinguish this voluntary award from all contractual duties, Steven
and Mark provided the incentive to Construct post-contract. In my opinion, the bonus
payment was not for the construct, but its success. It’s like a payment for the debt of
gratitude.
8. Bryde et al (in press) point to another area, where agency problems arise, namely in
the allocation of benefits and risks in uncertain situations. Which instance in the case
study addresses this particular concern of Steven and Mark? Did they adopt a value
It is stated in the case study that the issue regarding the allocation of benefits and
risks in uncertain situations occurs in OGHQ. The remaining two bidders were invited to
risk mitigation meetings, where the causes and effects of the disruption were discussed,
and they were both asked for risk-reduction ideas and suggestions. Both parties were
9. Would you have done anything differently to Steven and Mark? Why?
Steven and Mark contributed a lot in leading the success of the project. Their
skills and knowledge, which can be seen through their point of view, helped the progress
of the project. I can’t say that what I would do will be different from Steven and Mark
because for sure, at some point, there will be similarities in our approach and of course,
differences. But as I stated earlier in the previous question, what Steven and Mark did
could be used as a benchmark that could help and guide the team for the project’s
progress and success. Using this model alone is not advisable since it might need
10. In your opinion, is it likely that Steven’s and Mark’s approach contributes to the
Steven and Mark’s approach contributes to the success of the project or if not, at
least to the progress of the project. Both parties have their own opinions and point of
view which once collaborated, can provide a more concrete, appropriate, and better set of
issues. It also helped to build client relationships by putting trust between the client and
the team. Having a great client relationship helps both parties as it minimizes
https://en.wikiversity.org/wiki/Motivation_and_emotion/Book/2014/Goal_conflict_and_emotion
https://www.masterclass.com/articles/information-asymmetry-explained#what-is-information-
asymmetry
https://leadingwithtrust.com/2017/12/03/3-levels-of-trust-you-experience-in-relationships/
https://eprints.whiterose.ac.uk/157462/3/Revised%20Relationship%20management%20to
%20outsourced%20projects%20Final.pdf