Bill of Qty for SPS Augmentation at Venkatpuram

Iron Works and fabrication


S.No Name of Work/ Item Unit Qty Rate Amount
DI Pipe K9 with 200 NB : 11m each
1 length from bottom ducfkoot bend till RM 35 2900 101500
the Plinth Level Top of Floor
MS Pipes 200 NB for creating pump
delivery pipe jointing till the common
2 kg 410 89 36490
header 4 mm thk: 3 pipes of 20 ft in
length
MS Pipes 400 NB for creating common
3 header for all three pumps and joining kg 830 89 73870
in the existing 700 NB rising main
4 NRV check valves 200NB No. 3 38000 114000
5 Sluice Valves 200NB No. 3 28000 84000
6 Dismantling Joints 200NB No. 3 8900 26700
7 DIsmantling Joints 400NB No.s 1 14200 14200
MS pipe for creating elbow /bend for
8 kg 160 89 14240
all 3 pumps 200NB
I Beam section 300x 150 mm total 3
9 kg 545 78 42510
pieces
MS flange 200NB , 12 mm thk 20 no.s 8
10 kh 160 120 19200
kg each
H beam 150 x 150 mm total length 36
11 kg 216 80 17280
ft
12 MS reducer 700 x 400 No. 1 12000 12000
13 Elbow 90 deg 400 mm No. 1 8000 8000
14 Plate circle 400NB 10 mm thkness MS kg 400 89 35600
15 Nut Bolts for fittinng in MS kg 90 120 10800
Welding electrodes cutter, 12''x 12''
16 kg 70 135 9450
MS, 10 mm thk
On Site Fabrictaion includes rental /
17 purchase cost for procurement welder 315000
units, gas cyclinders etc.
Freight till site 45000

979840