Planned Schedule

STG1.0 Installation Commissioning Plan Rev.0

10 Nov
Project Name : Pengadaan Retrofit Sistim Eksitasi STG # 1.0 Responsibility STG1.0 SITE DAILY Day, Date : Wed, 10 Nov, 2021
Project No : 095.PJ/061/IP/2020 Time Start : 7:30 AM
Location : PLTGU Blok 1 Tambak Lorok Unit Pembangkitan Semarang REPORT Time Finish : 7:00 PM
PT. Control Systems PT Indonesia Power Semarang PGU
Gunawan Dicky S Dini Indriastuti Johan Kurniawan
Andika Anugrah Triputranto Wiwin SN Agung Pikandra
Arifin Purwanto Ibadus solihin Agus Ardie Wibowo
Arif Cahyo Permana Abdurahman Ari Purnama
Rivie Ariana Ghozy Permana
Reksa Solichul Hadi
Iqbal Kadafi Sofyan
Muhadi Wibisono Wahyudi
Tools : Termination Tools, Set box Tools, Crowbar, LAN tester

Activities
No Description PIC Remarks
1 Open crate and moving for EWS, OWS, and console desk to CCR
2 Survey panel room STG1.0
3 Survey and plan route for moving new panel to STG1.0 panel room
4 Survey for FO cable laying route
5 Set up OWS in CCR
6 Laying ethernet cable for OWS and EWS
Planning for Next Day Thu, 11 Nov, 2021
1 Open crate for new panel
2 Moving new panel to STG1.0 panel room
3 Set up EWS & console desk (position to be confirmed by IP)
4 Verify cable entry for power and network FO

Obstacle Remark Solution


1 No space to install EWS and console desk Need confirmation from IP
2 High Water level in cable tray tunnel for FO cable Need support from IP to drain out water

PT. CONTROL SYSTEMS ARENA PARA NUSA


Page 1 of 2
Planned Schedule
STG1.0 Installation Commissioning Plan Rev.0

10 Nov

PT. CONTROL SYSTEMS ARENA PARA NUSA


Page 2 of 2