You are on page 1of 2

structural T here are many issues that arise when one

places mass concrete, specifically as it relates


to reinforced concrete elements in buildings.
Goals of Mass Concreting
The ACI definition of mass concrete names heat

PRACTICES
These elements, which most typically include generated within the member due to the heat
reinforced mat foundations, pile caps, footings, of hydration as a core concern. It is this heat, if
piers, and transfer elements, differ from other not controlled, that can have detrimental effects
reinforced structures such as dams and retaining on the concrete element. These could include
practical knowledge beyond walls due to high stresses, quantities of steel rein- cracking, delayed ettringite formation (DEF),
the textbook forcement, and the use of high strength concrete. and other issues. Another core concern with mass
Mass concrete element placement in buildings, concreting is the potential formation of cold joints
therefore, presents unique challenges. in the element. This is a problem more common
to building structures as the use of higher strength
concretes will rapidly accelerate the setting time
Mass Concrete: When It Applies of the concrete.
The definition of mass concrete per the American
Concrete Institute (ACI) is “any volume of con- ®
Temperatures

E
crete with dimensions large enough to require that
measures be taken to cope with generation of heat ACI 301 provides two recommended tempera-

R
from hydration of the cement and attendant ture limits:
volume change to minimize cracking” (ACI a) The maximum concrete temperature shall

Mass Concreting
U
116R and ACI 301). hAlthough
t no specific not exceed 160 degrees Fahrenheit during
yrig

T
thickness is given,Coapmember thickness of three curing, and
feet is often used as the threshold dimension for b) The maximum temperature differential

C
when mass concreting procedures are to be set between the center and surface of placement
By J. Benjamin Alper, P.E., S.E.,
e
U
in motion. Note that there may be circumstances shall not exceed 35 degrees Fahrenheit.
and Cawsie Jijina, P.E., SECB where members with a thickness less than three
i n These limits are in place to avoid delayed ettrin-

R
feet will call for mass concreting procedures. The gite formation (DEF) which can cause cracking
z
T
final determination as to whether mass concreting and reduce concrete strength. Although these

g a
procedures should be followed is at the discretion of temperature limits may not seem significant, they

S
the Structural Engineer of Record (SER). can often be difficult to achieve, especially the
a restriction on the temperature differential.
J. Benjamin Alper is an Associate at
Severud Associates and serves as the
mACI 207 Beginning concrete placement with a lower ini-
tial concrete temperature is recommended to keep
The ACI Committee 207 provides several reports the concrete from reaching upper-temperature
Quality Control Officer for Severud
Associates’ inspection services. He can
for guidance in the use of mass concrete. ACI limits. Typical methods to keep concrete tempera-
be reached at jalper@severud.com.
207.1, Guide to Mass Concrete, is the primary tures low include the introduction of crushed ice
resource for guidance in the use of mass con- to the mix in lieu of some of the mixing water
crete for structural building elements. Most and the use of precooled aggregate. For times
Cawsie Jijina is a Principal at Severud of the data and concerns related to the use of when the ambient temperatures are high, it may
Associates and serves as the Deputy mass concrete were formulated
Technical Director for Severud from lessons learned during the
Associates’ inspection services. He can United States golden era of dam
be reached at cjijina@severud.com. construction. It was during the
construction of these massive
structures more than one hun-
Review the following publications for dred years ago that issues related
additional information, considerations, to the placement of mass con-
and approaches for mass concreting. crete began to emerge. During
ACI 207.1 – Guide to Mass Concreting dam construction, the strengths
ACI 207.2 – Report on Thermal and Volume of concrete required were low
Change Effect on Cracking of Mass Concrete (typically under 5,000 psi)
ACI 207.4 – Cooling and Insulating Systems compared to the requirements
for Mass Concrete for strength of current build-
ing elements, where concrete
strengths can exceed 10,000
psi. Although many of the rec-
ommendations from ACI 207
may be useful for these types of
structures, other recommenda-
tions from ACI 207 may not be
practical for building elements. Nighttime foundation mat placement with multiple points of placement.

STRUCTURE magazine 12 April 2018


set prior to additional concrete being placed
next to it. Maximizing the number of points
of placement keeps concrete flowing as much
as possible. The pre-placement meeting may
reveal that, due to site restrictions, the forma-
tion of a cold joint in an element is highly
probable. The SER may need to consider
the addition of strategically placed construc-
tion joints within the structural element to
minimize the risk of a cold joint forming,
and provide for the reliable transfer of forces.
The use of a retarding admixture or a set
Completion of mat placement; insulation and tarps Thermocouple and wiring installed delaying admixture is important to prolong
being placed. with mat slab. the workability period of concrete and can help
control temperatures. A typical procedure is to
be necessary to post-cool the concrete via Monitoring Concrete start the early concrete
® trucks with the maxi-

E
embedded cooling coils. Other than when Temperatures mum recommended quantity of admixture
insulation is used, the use of curing water on and then slowly taper off the admixture during

R
the slab is essential to prevent water loss and The monitoring of concrete temperatures concrete placement. Tapering the admixture
assist in the curing operation. in mass concreting is commonly achieved during placement helps keep the concrete

U
In a normal concrete element, a tempera- through the use ofrigthermocouples.
ht These sen- workable and also supports constructabil-

T
y
ture gradient is created between the interior, Copwithin the structural element
sors are buried ity for the contractor. The added fluidity of
where the heat of hydration is trapped, and prior to the concrete placement operation. the concrete late in the placement increases

C
the exterior surface of the concrete that is Often, the SER generates a three dimensional the pressure head on the formwork system.

e
U
transferring heat to the atmosphere. In colder grid that allows the temperature gradient to Additionally, for most elements, laborers must
weather, insulation is added to the top of the
n
be plotted throughout the cross-sectional area
i
remain on site until finishing and curing proce-

R
slab to maintain the thermal temperature of the element. The sensors report the tem- dures are completed. If the retarding admixture
z
T
gradient and prevent the top from cooling perature within the element and enable the is used in its full dosage until the end of the
more rapidly than the core. Trying to main- a
engineer to verify that the temperatures have
g
placement, the staff needs to wait on site for

S
tain this same 35-degree differential when the remained within the desired range from the many additional hours beyond the pour until
interior of the concrete is “insulated” with a
initial concrete placement until final concrete they can walk on the concrete and begin fin-
several feet of concrete above and below it,
zones that are also generating heat, is difficult m
curing operations are complete. When tem-
peratures approach the limits of the desired
ishing/curing. Tapering the quantity of the
admixture allows for more efficient staffing.
when the exterior of the concrete is exposed to range, changes can be made to the curing A licensed structural engineer or an ACI
colder atmospheric temperatures, even with procedures, such as the addition or removal of certified technician observing the placement
the use of insulating blankets. Note that the insulating layers to balance the temperatures. is recommended to help prevent the forma-
35-degree limit is a general recommendation tion of cold joints. The engineer, in concert
to prevent deterioration of the concrete due to with the contractor, can use observations to
the separation of concrete layers, but it is often
Cold Joints make strategic real-time changes to the pour
at the discretion of the Engineer of Record A cold joint forms when concrete already sequencing. The contractor can come back
whether higher temperature differentials may placed within the element begins to set even with a small amount of concrete to refresh
be tolerated. as subsequent layers of concrete are still being an area that is starting to set and potentially
placed on top of it. The formation of a cold form a cold joint. The pour can then continue.
joint negates the monolithic properties that Unfortunately, even with the best planning,
Mix Designs are always desired and, unlike a planned and things can go wrong – a pump breaks, the
Many recommended changes to the concrete formed construction joint, it is typically hap- concrete delivery is delayed, and so forth. It
mix for mass concreting reduce or slow the heat hazard in its locations and is horizontal or is critical that someone on site, typically the
of hydration to limit temperature change and on a slope. The failure plane created within inspector or engineer, record and document
thereby lower the amount of crack formation. the structural element is often hard to docu- the location of any cold joints that form.
It is critical to reduce the quantity of cement in ment, as it usually happens in the middle of This allows the Engineer of Record to more
the mix. The replacement of cement with slag the concrete placement when operations are accurately evaluate the impact to the structure
and fly ash (and now ground glass pozzolans) the most hectic. and provide the most efficient remediation,
can help maintain required strengths. The use Avoiding cold joints takes prior planning. if one is required.
of larger aggregates can also help; however, this During a pre-placement meeting before
can often be difficult as the congestion of steel the start of mass concreting operations, it
reinforcement and the method of concrete is important to plan and discuss the order
Conclusion
placement may restrict the aggregate sizes. of concrete placement and the number of This article describes general approaches to
Admixtures used for air entrainment, water placement points. The order in which the address some of the mass concreting concerns
reduction, set time, and shrinkage reduction, concrete is intended to be placed should be that are particularly relevant to building struc-
strength, and durability can be adjusted to slow strategic to avoid leaving specific areas for tural systems. Several ACI publications are
or reduce the heat of hydration. extended periods where concrete can start to available for more information.▪

STRUCTURE magazine 13 April 2018

You might also like