Professional Documents
Culture Documents
Introduction
II. Required Design Data
III. Design Criteria and Standards
IV. Design Procedures
V. Design Revisions
I. Introduction
II. Required Design Data
III. Design Criteria and Standards
IV. Design Procedures
V. Design Revisions
Introduction
1. Dike/Embankment/Levee
• constructed along the banks of a
stream, river, lake or other body of
water
• protects the landside from overflowing
floodwater
• confines the stream flow in the regular
channel
2. Spur Dikes
• river training structures constructed
along the banks of rivers and flood
dikes
• deflect or repel the flow for the
purpose of training the course of the
river channel
• protects the banks from scouring by
inducing siltation in the area
What are the FC &
Drainage Structures?
3. Revetments
• constructed along river banks subjected
to direct attack of the river flow and
along levee slopes
• protection against erosion, scouring,
riverbed degradation and wave wash
4. Ground Sill
• drop structures located within a channel
• used downstream of culverts to prevent
head cutting from discharge flows
• maintains a consistent streambed profile
in the vicinity of the culvert
What are the FC &
Drainage Structures?
5. Small Dams
• any dams that are less than 15 m in height
• constructed to meet a variety of needs such as:
o flood control and flood mitigation
o creation of fresh water storage for the provision of clean water
o generation of power through hydro-electric schemes
o creation of recreation areas
7. Overtopping Embankment
• Overtopping embankments include:
o Dikes that overtop during flooding
o Lower level road embankments or bridge approaches that overtop
-
<0 Iluberl ClIANSO'.N200
What are the FC &
Drainage Structures?
Composite Channels
o Utilizes a combination of rigid
lining and flexible lining.
o Losses at junctions
o Inlets and outlets
o Obstruction and penetrations
o Pipe branch losses, and
o Transition losses
What are the FC &
Drainage Structures?
3. Culverts
• a relatively short length of pipe or closed conduit
used to convey stormwater through an
embankment or road, connected at each end to
an open channel
What are the FC &
Drainage Structures?
4. Inlet Manholes
• Inlet pits should be located:
o Such that the capacity of the reach between inlet
pits is not exceeded.
6. Detention Basins
• used to reduce the peak outflow from a location
• Basins perform through intercepting stormwater
flows and releasing the stormwater volume in
acontrolled manner over a period of time
What are the FC &
Drainage Structures?
7. Overland Flowpaths
• designed to carry flow in excess of the
piped capacity
• where possible, overland flowpaths
should not be contained within private
properties
• if this is unavoidable, a drainage
easement should be obtained to contain
the overland flow path, in order to allow
maintenance teams to undertake any
required control works
What are the FC &
Drainage Structures?
8. Pumping Station
• Pumping stations allow for the removal of
stormwater from pipe systems that cannot
be drained through gravity.
B. Other Data
• Rainfall Data
• River Channel Gauge Data
• Runoff Data
• Tidal Data
• Soil Investigation
A. Field Survey Information: Topographic Survey
A. Field Survey Information: Hydrographic Survey
A. Field Survey Information: Hydrographic Survey
A. Field Survey Information: Soils Subsurface
and Surface Explorations
Rainfall Data
• Historical rainfall can be used to verify design rainfall information or as an
input to a hydrological model in order to calibrate it to a historical flood
event.
• Rainfall information is available from Philippine Atmospheric, Geophysical
and Astronomical Services Administration (PAGASA).
Runoff Data
• Can be obtained from:
o Rational Formula
– Catchment Area < 20 Km2 (Rural and Forested)
– Catchment Area ≤5 Km2 (Urban)
Q = cIA/3.6
Q = maximum flood discharge in cu. m./sec
c = runoff coefficient
I = rainfall intensity in mm/hr
A = catchment are in sq. km.
B. Other Data
Runoff Data
• Can be obtained from:
o Unit Hydrograph Method
B. Other Data
Runoff Data
• Can be obtained from:
o Storage Function Method
B. Other Data
Runoff Data
• Can be obtained from:
o Flood Frequency Analysis
B. Other Data
Runoff Data
• Can be obtained from:
o Specific Discharge Method
B. Other Data
Tidal Data
• Tidal data comes in two forms:
o Observed or measured data
o Predicted data
B. Other Data
Soil Investigation
• Subsoil conditions can be
explored by drilling and
sampling, seismic surveying,
excavation of test pits and by the
study of existing data
I. Introduction
II. Required Design Data
III. Design Criteria and Standards
IV. Design Procedures
V. Design Revisions
Old DGCS:
PROTECTION LEVELS
Design Discharge, Q
Freeboard(m)
(m3 /s)
Less than 200 0.60
200 and less than 500 0.80
500 and less than 2000 1.00
2000 and less than 5000 1.20
5000 and less than 10,000 1.50
10,000 and over 2.00
Design Criteria:
Dike/Embankment/Levee
RECOMMENDED CREST WIDTH
Design Discharge, Q
Crest Width (m)
(m3 /s)
Less than 500 3.00
500 and less than 2, 000 4.00
2, 000 and less than 5, 000 5.00
5, 000 and less than 10, 6.00
000
10,000 and over 7.00
Design Criteria:
Dike/Embankment/Levee
Slope
• The side slopes should be gentler on both landside and riverside of the
embankment that 1V:2H for low embankments (< 6.0 m) and 1V:3H
for high embankments (>6.0 m).
1 1 1 1
RIVERSIDE LANDSIDE RIVERSIDE LANDSIDE
2 EMBANKMENT 2 3 EMBANKMENT 3
Hf DFWL
1 1
RIVERSIDE EMBANKMENT LANDSIDE
4 4
• On the riverbank side, when the crest height from the river bed is more
than 6 m, berms shall be provided at every 3 to 5 m having a width
of 1 m or more.
Design Criteria:
Dike/Embankment/Levee
Berms
• On the landward side, when the crest height from the existing ground is
more than 4 m, berms shall be provided at every 2 to 3 m in height having
a width of 1 m or more
• When the levees is constructed along the road or the drain, toe
protection is required. It should have a height of 0.5-1.0 m and be made
of dry stone masonry to secure the drainage in the levee body
Design Criteria:
Dike/Embankment/Levee
Levees
Levees generally result in the obstruction of overland flow paths and the
drainage from the landward side to the river. Pipes or drainage culverts will
be required to cross through the levee to relieve local drainage.
Design Criteria:
Dike/Embankment/Levee
Types of Levee
1. Urban Levees - provide protection of the densely populated communities, including their
industrial, commercial, and residential facilities against flooding.
1. Mainline and Tributary Levees – lies along a mainstream and its tributaries
3. Setbacks Levees – built landward of existing levees that have suffered distress
or are in some way being endangered, as by river migration.
Design Criteria: Spur Dike
Design Criteria: Spur Dike
spur
- ScouringArea
Design Criteria: Spur Dike
Length
• Spur dikes should have lengths from 10 to 15% of the width of the
river or channel but not to exceed 100 metres.
DFL : Design Flood Level
Width
• Usually, the top width of spur dikes ranges from 1 to 3 metres.
Slope
• The longitudinal slope of the spur dike should be 1V:20H to 1V:100H
toward the center of the river.
DFL : Design Flood Level
Slope
• Slopes are typically between 1V:1H and 1V:2H on the upstream
side and 1V:1H and 1H:2H toward the center of the river.
DFL : Design Flood Level
TOE PROTECTION :
Gabion Mattress
/ Boulders
PLAN
Design Criteria: Revetment
Types of Revetment
R e v e t m e n t S c o u r i n g a n d
D e g r a d a t i o n P a r t
S a n d B a r
F o r m ation
SUMMARY OF QUANTlTIES
PAY ITEM DESCRIPTION UNIT QUANTITY UNIT COST COST/ Km.
NO.
505 (1) DRY BOULDER RIPRAP m' 3,123 Php 1,975.74 Php 6,170,236.02
622 (3) a COCONET w/ GRASS PLANTING m• 2,800 Php 109.07 Php 305,396.00
SAND & GRAVEL BACKING m' 1,040 Php 851.76 Php 885,830.40
l 000, EXISTING GROUND
TOTAL= Php 7,361,462.42 (MIN.)
0
8
L{)
ORDINARY FLOOD LEVEL
I
1000
LOOSEBOULDER APRON
300-400mm0
100mm THICKSAND AND
GRAVEL BACKING
NOTES:
1 IF THE HEIGHTS OF REVETMENTS GREATER
THAN FOUR (4) METERS BERM MUST BE
PROVIDED AND SHALL BE LOCATED MIDWAY
OF REVETMENT SLOPE W ITH 1.0M. WIDTH
COCONET w/ _/
GRASS PLANTING
0
SLIP PREVENTION PEG
0 ( 9 0 mm0 , L= 1500@ 2000 O.C. (STAGGERED)
0
LI)
/ ORDINARYFLOOD LEVEL
1000
GEOTEXTILEFABRIC
NOTES:
4000 (MIN.) ., MATTRESSFACING 1 IF THE HEIGHTS OF REVETMENTS GREATER
(6000 X 2000 X 300) THAN FOUR (4) METERS BERM MUST BE
PROVIDED AND SHALL BE LOCATED MIDWAY
OF REVETMENT SLOPE WITH 1 OM. WIDTH
MATTRESS REVETMENT W/OUT CUT-OFF
2. FOR BANK SLOPE 1;1
(9 WALL FOUNDATION (SPREAD TYPE II) 3. MAXIMUM ALLOWABLE FLOW VELOCITY = 5.0m/s
0
0
0
LI")
ORDINARY FLOOD LEVEL SUP PREVENTION PEG
I 1000
- - - (9 0 mm0 , L= 1500@ 1000 TO 2000 B.W.)
0...,.
0 MATTRESS FACING
LI")
- - (6000 X 2000 NOTES:
X 300) 1, IF THE HEIGHTS OF REVETMENTS GREATER
THAN FOUR (4) METERS BERM MUST BE
200 x l 000 x 1OOOMM GABION PROVIDED AND SHALL BE LOCATED MIDWAY
- - - - - - CUT-OFF WALL FOUNDATION
4000 (MIN.) .I 1000 I
OF REVETMENT SLOPE W ITH 1 OM WIDTH.
511 (1) GABION REVETiv1ENT m• 14,000 Php 3 ,564 .35 Php 49,900,900.00
622 (3) a COCONETw/ GRASS PLANTING m• 2,800 Php 109.07 Php 305,396.00
511 (3) Fil TER CLOTH m• 15,000 Php 410.87 Php 6,163.050.0D
TOTAL= Php 56,369,346.00
EXISTING GROUND
0
8
I.I")
sz
2000 X l 000 X l 000 GAB/ON
\_ --
WI 100-200mm 0 BOULDERS
GEOTEXTILE FABRIC
NOTES:
1. FOR BANK SLOPE 1:1
0
0
0
lJ") RUBBLE CONCRETE
1000 t = 300mm
MATTRE-SSFACING --
(6000 X 2000 X 300) - - GRADED GRAVEL WITH THE LARGER ONES
PLACED ADJACENT TO HOLES AS SHOWN
FILTER C L O T H - -
WEEPHOLES STAGGERED AT 2000mm
- -
INTERVAL ABOVE THE ORDINARY WATER LEVE
NOTES:
1. IF THE HEIGHTS OF REVETMENTS IS GREATER
THAN FOUR (4) METERS. BERM MUST BE
PROVIDED AND SHALL BE LOCATED MIDWAY
OF REVETMENT SLOPE W ITH 1.0M. WIDTH.
, 4_00_0-'(_M_IN ;.) [ 500 I 2. FOR BANK S L O P [ 1:1
622 (3) a COCONET w/ GRASS PLANTING m' 2.800 Php 109.07 Php 305.396.00
EXISTING
TOTAL= Php 20,270,494.00
I GROUND
COCONETw/
GRASS PLANTING
--
GRADED GRAVEL WITHTHE LARGER ONES
PLACED ADJACENT TO HOLES AS SHOWN
LOOSE BOULDER
RIVER BED
APRON -- WEEPHOLES STAGGERED AT 2000mm
INTERVAL ABOVE THEORDINARY WATER LEVE
/ , y _ , . .-;v, ( l>-< ,-,.,,...,...,._, :>--<'.......0-0-
0 150mm THK. CONCRETE SLAB W /
0
0 - - - - 12mm 0 REINFORCING BARS SPACED
@ 250mm O.C. B.W.
I. 4000 (MIN.)
NOTES:
1. IF THE HEIGHTS OF REVETMENTS IS GREATER
THAN FOUR (4) METERS, BERM MUST BE
622 (3) a COCONET w/ GRASS PLANTING m• 2,800 Php 109.07 Php 305,396.00
EXISTING GROUND
0
8
V)
r ORDINARY FLOOD LEVEL
GEOBAG TYPE I
(1.25m L X 0.50m H)
NOTES:
1250 1. FOR BANK SLOPE 1 1
Indicative
Type Maximum Velocity Slope (V:H)
(m/s)
11. Sheet Pile Vertical
12. Vegetation and Reinforced
Varies Milder than 1:4
Grass/TRM
Design Criteria: Revetment
Freeboard
• A freeboard of 0.60 meter should be adopted above the level of the
flood event
Slope
• same as those of the dike at 1V:2H or milder.
• In case of rapid flow stretches, the slope shall not be necessarily gentle
but shall be milder than 1V:0.5H.
Thickness
• Minimum thickness should be 300 mm for all types of revetment,
except for reinforced concrete type.
Design Criteria: Revetment
Slope
• In case of joint portion with a rock-strewn slope, the slope of revetment
shall be gradually changed to smoothly connect with the natural slope
• For the retaining wall type revetment (reinforced concrete, gravity wall,
rubble concrete etc.), a maximum slope of 1V:0.3H shall be observed
considering stability and the resulting residual hydraulic pressure.
Segment Length
• The length of one segment of revetment along the longitudinal direction
should not be more than 50 meters
Provision against scouring
of existing bank adjacent
the revetment. _ 20 cm
b>
(boulder/ gabion type)
_ 50 cm
a>
Original bank
River Flow A End protection
PLAN
50 cm
SECTION A- A
Design Criteria: Revetment
Berm
• If the height of revetment is more than 5.0 meters, berm must be
provided in order to separate the revetments into segments, as well as in
consideration of site and geological condition and structural stability of
the revetment. Berms shall be at least 1.0 meter in width for
maintenance
Berm
(banquette)
H
Design Criteria: Revetment
Weepholes
• Revetment should be provided with weepholes ranging from 50 – 75
mm in diameter PVC pipes spaced at 2.00 meters on center and
staggered.
• The lowest weepholes shall be installed 1.0 m above the ordinary water
level.
Design Criteria: Groundsill
Design Criteria: Groundsill
Height
• It is generally best to keep the height of the groundsill smaller.
• A drop of 2 meter or less is recommended.
Alignment
• Groundsills should be constructed as straight as possible.
Design Criteria: Small Dams
Design Criteria: Small Dams
Material Classification
• Earthen dams
• Rock dams
• Concrete dams
Design Criteria: Small Dams
Freeboard
Greatest Straight Line Distance over
Minimum Freeboard
Water on Reservoir (km)
<2 1.00
2 1.30
5 1.60
10 2.00
15 2.30
Design Criteria: Small Dams
Easement
• Easement shall conform to Articles 50 and 51 of the Water Code of the
Philippines.
Design Criteria: Sluiceway
Design Criteria: Sluiceway
Direction/Alignment
• The direction of a sluiceway should normally be at right angles to the dike
alignment.
Opening Level
• The opening level of a sluiceway for irrigation shall be according to its
particular intake and taking into account the bed variations in the future.
• For drainage, the opening level shall consider the height of the riverbed
or the foundation height of the channel to be connected.
Capacity
• For an irrigation sluiceway, the cross section area (or capacity) shall be
large enough to secure the design intake volume even during dry season
or based on the specific requirements of the project.
Gate
• The type of gate or control structure adopted for the sluiceway will
depend on the application.
• Each particular structure will result in specific head losses associated with
it, which will affect the capacity of the sluiceway. It is important to
consult with the manufacturer specifications to determine the
appropriate losses to account for.
Design Criteria:
Overtopping Embankment
Design Criteria:
Overtopping Embankment
Design analyses include hydraulic analyses, uplift pressures and slope
stability. A radius of 3.30 m is recommended for slope stability.
Design Flood
• For culverts crossing under expressways, a minimum internal width and clear
depth of 1 m is required.
Cover
• A minimum cover of 600 mm
should typically be adopted.
• For inlets located in depressions and low points, a blockage of 50% should be
adopted.
Entry
• In order to allow safe entry and exit from access points, all access chambers
should have a minimum inside diameter of 1.2 m, or 1.5 m for pipes larger
than 2.1m.
• The top of the access shaft may taper to 0.9 m, so long as the tapered zone
does not affect working at the base of the shaft.
Design Criteria:
Detention Basins
Design Criteria:
Detention Basins
Sizing
• The size of the basin will be governed by the volume of flow generated from
the upstream catchment and the amount of retardation required of the flow.
Freeboard
5. Establish an appropriate section for the dike based on the design criteria
2. From the location map of the river showing the extent of erosion and
scouring establish the positions and locations of the proposed spur dikes
2. Compute the velocity of flow based on the design flood discharge and
the river profile and the cross-section using the Manning’s formula
2. Establish a trial section of the dam and compute for all forces acting on
the dam based on the unit length of the dam
2. For the given material forming the channel body, estimate the roughness
coefficient n, side slopes and the maximum and or minimum permissible
velocity, for non-scouring or non-silting requirement as the case may be
3. Express the hydraulic radius R in terms of the bottom width, b and depth
of flow, y, by the Manning’s formula
4. Compute the water area required by the given design flood discharge
and the permissible velocity, or A = Q/V
7. Add a proper free board, and modify the section for practicability
8. Long channels are usually divided into several reaches. The discharge for
each is computed considering the total tributary area. The channel
section is then designed to carry this discharge following the above
procedures
Design Procedure:
Pumping Stations
1. Gather the necessary watershed data which include drainage area,
runoff coefficient and time of concentration.
2. Compute the runoff for duration equal to the time of concentration and
at hourly intervals using the data gathered and from the formula on
Rational Method expressed as:
V = 10CiTA (T - tc)
where:
V = total volume of flow
C = runoff coefficient
iT = average intensity in mm per hour for duration T
A = drainage area in hectares
T = storm duration in hours
tc = time of concentration in hours
Design Procedure:
Pumping Stations
5. With the above determined data and information, the pump capacity for
any desired condition can readily be obtained.
I. Introduction
II. Required Design Data
III. Design Criteria and Standards
IV. Design Procedures
V. Design Revisions
Bureau of Design (BOD)
prepared a checklist of requirements for the review and
evaluation of detailed engineering plans and variation
orders for reference and guidance
Requirements for Review of
Detailed Engineering Plans
1. General plans (location plan; schematic diagram for water supply;
vicinity map; legends and symbols; abbreviations; and general notes
including design criteria)
3. Design analysis and computations (in SI units) and quantity calculations for the
proposed changes