Professional Documents
Culture Documents
Faculty of engineering
Electrical engineering department
EPS
Level 4
Project
"Power System
Design Project "
Dr.Eng.Morshed Hadwan
2017\202 Abdulhadi mohammed
3
Procedures Of Design
4
Electrical grid Power System Components
5
Recommendations
6
References
Introduction
Yemen, with a population of 30 million, is one of the countries with the lowest rates of electricity supply in the
Middle East and North Africa, as it has suffered from economic instability. long-term, which constituted an obstacle
to social and economic development in it; In Yemen, access to the minimum level of basic services remains one of
the daily challenges facing the vast majority of Yemenis. The inability to Vital service utilities and households on
access to electricity are deteriorating in quality of delivery. (2)
Public services such as water supply, health care, education and the general welfare of Yemenis. Before the
outbreak of the war, less than half of the population in Yemen on public electricity; In 2014, the rural population
was about two-thirds of the total The population, but only 23% of them received electricity, compared to the
percentage of The urban population who used to have access to electricity by 85% . The maximum annual average
per capita electrical energy consumption in Yemen has never exceeded 255 KWh, which is much lower than the
annual average in the Middle East and North Africa region of 2900 KWh while at the world level it is 3100KWh (3).
to electricity and its reliability Below the required level, mainly due to lack of fuel supply and sabotage The recurring
frequency of the power transmission towers that connect the Ma'rib power station - the largest power station in
Yemen - in Sana'a and the National Network. Although the installed electrical capacity of the Public Electricity
Corporation was about 1.5GW, the available electrical capacity in 2012 and 2013 was only 1GW Almost, the number
of subscribers to whom this electrical capacity was provided hardly reached 2 million. joint only, and due to the
deficit in electricity generation, electric power is purchased from producers Electricity is from the private sector by
the Public Electricity Corporation. According to the statistics, the supply gap continued and the demand of about
376MW in 2012 is expanding due to population growth and the limited generating capacity, a capacity that has
been hampered and decreased more recently, more because of the destructive effects of war, both material and
immaterial, which led to the collapse that The National Electricity Network is witnessing it at the present time. (1)
Abstract
Starting from the current situation of electrical energy, as we are electrical engineers and application for (Power
System Engineering course) We conducted a semi-simple preliminary study to solve the problem of limited electric
power in Yemen by evaluating the needs of all service sectors, and given that most power plants In Yemen it was
old and incompetent. The actual electrical power was Stations with much less capacity Its nominal, and during the
period from 2013 to 2020 it was Actual capacity about 1GW (5). During this study, we made a vision for the electricity
network in Yemen in the future, with a capacity of up to 23.5GW, according to the needs of the population and
service sectors, with a load of up to 18.61GW, and the distribution of power plants in the Republic of Yemen
according to mineral resources in various cities of Yemen.
Procedures Of Design
Electricity is the backbone of life in any society, and it is the practical basis for the continuation of human presence
in a region/city/state and not others, and through it the size of the economy of this society is predicted.
The requirements for the use of electricity vary in many sectors, including the population sector -mainly - then the
industrial, commercial, governmental, industrial and agricultural sectors as well.
The population sector, which constitutes the most important sectors in any city/state. The amount of electricity
consumption depends on the number of people, their growth rate, their average annual consumption, as well as
their places of concentration, through research that is established for a basic purpose before starting any project
to establish power generation, transmission and distribution stations. electrical.
The agricultural sector constitutes the smallest part of electric energy consumption - especially in Yemen - and the
amount of electricity needed for this sector can be estimated based on the availability of fertile areas and the needs
of its operating equipment for the agricultural process, and taking into account the growth of this field according
to the plan studied for it.
The industrial field, which is the most consuming sector after the population sector, takes into account the areas
with many factories and containing various industrial / refining / extractive activities, and there are also minerals
and various wealth that require at the present time or with future expansions a large amount of electricity
compared to their counterpart cities Uncontained largely on this sector.
The commercial sector is the sector associated with the commercial sector. The amount of energy needed for this
sector can be estimated based on the presence of commercial components in it, such as large commercial markets
and various commercial activities.
The government sector depends on the importance of this area in terms of the large area and the crowding of the
population and the presence of large government facilities such as ministries, institutions, service bodies and
executive offices, as well as the presence of missions, embassies and consulates .
Taking all these factors into consideration, the expected quantities were calculated for each sector, which were as
follows:
12.03%
Residential sector
Commerence Sector
Taiz 4554430 2000 228.31 1.0398219 0.045 0.765 0.4284 0.11191104 2.390133
Ibb 3911070 2000 228.31 0.8929364 0.063 0 0.252 0.044764416 1.2527008
Hodaidah 3774914 2000 228.31 0.8618506 0.0495 0.675 0.4192 0.089522832 2.0950734
Sana'a 2279665 2000 228.31 0.5204703 0.0855 0.45 1.3284 1.09002 3.4743903
Hajja 1887213 2000 228.31 0.4308696 0.027 0 0.036 0.011191104 0.5050607
Thammar 1697067 2000 228.31 0.3874574 0.036 0 0.038 0.006714662 0.468172
Hadramout 1324083 2000 228.31 0.3023014 0.099 0.7 0.36 0.134293248 1.5955946
Mahwait 1174767 2000 228.31 0.2682111 0.036 0 0,0036 0.00223822 0.3064493
Ammran 1123651 2000 228.31 0.2565408 0.0225 0.135 0.0072 0.011191104 0.4324319
Aden 1087653 2000 228.31 0.2483221 0 0.81 0.54 0.559556 2.1578781
Saddah 987663 2000 228.31 0.2254933 0.162 0 0.036 0.00223822 0.4257316
Lahj 926291 2000 228.31 0.2114815 0.027 0.045 0.072 0.044764416 0.4002459
Al-Baida 835683 2000 228.31 0.1907948 0.0135 0 0.0036 0.006714662 0.2146094
Al-joff 732360 2000 228.31 0.1672051 0.036 0.0675 0.0072 0.006714662 0.2846198
Abyan 658824 2000 228.31 0.1504161 0.027 0.0675 0.108 0.011191104 0.3641072
Shaboua 651509 2000 228.31 0.148746 0.009 0.36 0.036 0.006714662 0.5604607
ADdali 602613 2000 228.31 0.1375826 0.018 0.045 0.072 0.044764416 0.317347
Ma'arib 504696 2000 228.31 0.1152271 0.1035 0.63 0.108 0.044764416 1.0014916
Raimah 502505 2000 228.31 0.1147269 0.0225 0 0.036 0.00223822 0.1754651
Al-Mahara 400000 2000 228.31 0.091324 0.018 0 0.072 0.006714662 0.1880387
With Studying and assigning the Sectors of the load according to its priority, as:
Loads which must be provided with electricity from at list two independent sources or two lines , and Loads that
should be provided with electricity from one direction but by at list two circuit line. As shown in table below
Degree City Degree City
I Hudidah I Sana'a
II Manakhah III Khamer
I Sadha III Amran
III Thamar II Ma'rib
III Ma'abar III sayuon
III yareem II Alhuzm
II Addalie III asshar
I Aden III Nuqup
I Taiz III Nesab
II Ibb II Bilhalf
II Almakha III Brum
Il Zabeed III hajjah
III zonjbar III moklaa
II Ataq III Sayhot
III tareem
After determine the needed of power for each city in all sectors as shown in tables above we study the map of
cities and determining the suitable bath , as shown below
Figure_1
Figure_2
Figure_3
We have simplified the network above by redrawing it in more suitable way, in order to ease our calculations as
shown below in figure
Figure_4
Then writing the distances between the branches (Cities ) , using google map as shown below in table (3).
Table No.(3)
Path From To Distance [km]
Loop (1)
Lab Hudaidah Manakah 137
Lbc Manakhah Sana'a 98
Lcd Sana'a Mabar 74
Lde Mabar Dhammar 33
Lef Dhammar Yareem 34
Lfg Yareem Addali 108
Lak Hodaidah Zabid 106
Lkj Zabid Makkah 130
Lji Makkah Taiz 107
Lih Taiz Ibb 68
Lhg Ibb Addali 98
Loop (2)
Lpo Marib Alhazm 134
Lon Alhazm Sadaa 302
Lnm Sadaa Khamer 147
Lml Khamer Ammran 47
Llc Ammran Sana'a 52
Lpc Sana'a Marib 172
Loop (3)
Lgv Adali Aden 173
Luv Aden zingbar 64
Ltu zingbar Belhaf 344
Lts Belhaf Ataq 564
Lsr Ataq Nesab 39
Lrq Nesab Nuqub 135
Lqp Nuqub Marib 136
After labeling each branch and determining directions, considering the network is lossless to calculate the power
in all branches ,then expressing each branch power in terms of loop powers, after that writing the mesh equation
for each loop using branch-current analysis method and doing the calculations, and the assigned branches power
references are :
𝑷𝟏𝟏 = 𝑷𝒂𝒃 , 𝑷𝟐𝟐 = 𝑷𝒐𝒏 , 𝑷𝟑𝟑 = 𝑷𝒓𝒒
Table No.(4)
P11=Pab P22=Pno P33=Prq
Loop (1)
Lab Hudaidah Manakah P11=Pab
Lbc Manakhah Sana'a P11-0.27
Lcd Sana'a Mabar P11+P33-0.13
Lde Mabar Dhammar P11+P33-0.56
Lef Dhammar Yareem P11+P33-0.78
Lfg Yareem Addali P11+P33-1.18
Lak Hodaidah Zabid 1.21-P11
Lkj Zabid Makkah 0.38-P11
Lji Makkah Taiz 3.58-P11
Lih Taiz Ibb 1.49-P11
Lhg Ibb Addali 0.24-P11
Loop (2)
Lpo Marib Alhazm P22-1.22
Lon Alhazm Sadaa P22
Lnm Sadaa Khamer P22-0.33
Lml Khamer Ammran P22-0.42
Llc Ammran Sana'a P22-1.26
Lpc Sana'a Marib P33- P22+2.6
Loop (3)
Lgv Adali Aden P33-1.26
Luv Aden zingbar 1.85-P33
Ltu zingbar Belhaf 2.23-P33
Lts Belhaf Ataq p33-0.95
Lsr Ataq Nesab P33+0.01
Lrq Nesab Nuqub P33
Lqp Nuqub Marib P33-0.42
then using 𝑳𝒊𝒋 × 𝑷𝒊𝒋 multiple each branch power by its distance using KVL for each loop to get one equation for
each loop , means 3 equations for the three loops this will result in free terms, and make these free terms in one
side ,then solve them in matrix 3×3 , as we got below :
𝟗𝟗𝟑𝑷𝟏𝟏 + 𝟎 + 𝟐𝟒𝟗𝑷𝟑𝟑 = 𝟖𝟗𝟒. 𝟎𝟖 1
𝑷𝟏𝟏 = 𝟎. 𝟕𝟎𝟗𝟏𝟓 GW
𝑷𝟐𝟐 = 𝟏. 𝟎𝟐𝟓𝟑𝟐 GW
𝑷𝟑𝟑 = 𝟎. 𝟕𝟔𝟐𝟔𝟐 GW
We use these values to substitute in branches equations that shown in tableNO. (4) above we got the values of each branch
power that shown below in table NO.(5)
Pij Expresed GW
Pab P11=Pab 0.70915
Pbc P11-0.27 0.43915
Pcd P11+P33-0.13 1.34177
Pde P11+P33-0.56 0.91177
Pef P11+P33-0.78 0.69177
Pfg P11+P33-1.18 0.29177
Pak 1.21-P11 0.50085
Pkj 0.38-P11 -0.32915
Pji 3.58-P11 2.087085
Pih 1.49-P11 0.78088
Phg 0.24-P11 -0.46915
Ppo P22-1.22 -0.19468
Pon P22 1.02532
Pnm P22-0.33 0.69532
Pml P22-0.42 0.60532
Plc P22-1.26 -0.23468
Pcp P33- P22+2.6 2.3373
Pgv P33-1.26 -0.49738
Pvu 1.85-P33 1.08738
Ptu 2.23-P33 1.46738
Pst p33-0.95 -0.18738
Psr P33+0.01 0.77262
Prq P33 0.76262
Pqp P33-0.42 0.34262
Table NO.(5)
The next is finding the voltage level in each branch using the following equations :
and the average power then selecting the suitable voltage as shown in table (NO.6)
Table NO.(6)
Electrical grid Power System Components:
8 power plants of total installed capacity 23.5GW
No Power plant Name Power Capacity Types of power plants
In [GW]
1 Hodeida power plant 3 steam turbines
2 Aljaof power plant 3 gas turbines
3 Sana’a power plant 2 gas turbines
4 Aden power plant 2 steam turbines
5 Safier power plant 4 gas turbines
6 Almakha power plant 4 steam turbines
7 Shaboua power plant 2.5 gas turbines
8 Balhaf power plant 3 gas turbines
Recommendations
Despite the deteriorating situation of the power sector, especially after the war, there remains an opportunity to
build a stronger power sector. This section includes maximum priorities to recover and reform the electricity sector.
Secure funding, both government financial resources or donors / international lenders, to rehabilitate the
infrastructure damaged during the war,
Maintenance of power plants requiring spare parts, and other corrective maintenance and Rehabilitation of the
basic transport lines needed to transfer energy from large power plants to the required locations.
Search for effective financial and technical adjustments among the concerned areas of conflict areas to restart the
national network.
Buying electricity from private sector as needed, through transparent and competitive process, preferably through
mechanisms leading to the General Electricity Corporation for infrastructure, such as construction, operation and
transportation.
Work to find a good and sustainable solutions.
Enhance the efficiency of the generation and subdivisement sectors, and reduce technical functions through
appropriate maintenance.
improve administrative practices and ensure an effective delegation of skilled managers and qualified leaders who
lead the departments.
Encouraging consumers and service facilities to install isolated solar systems on the high quality network and
designed well designed to form sustainable solutions.
Review of electricity tariffs on a consultative study dealing with their social dimensions and economic, including
consumers’ ability from all sectors to afford.
References
1. Central Statistics Organization (CSO) summar table of the most important results of population projections data and indicators
(2005-20025) according to various hypotheses and alternatives (Arabic)
2. http://www.cso-yemen.com/content.php?lng=arabic&id=553
3. https://data.worldbank.org/indicator/EG.USE
4. Power System Engineering
5. Recover priorities and repair sector Electricity in Yemen -Akram Almohamady (may 2020)