You are on page 1of 2

fluid technology international pvt. Ltd.

PROJECT SHIPMENT INSPECTION REPORT


ITEM NAME MODEL No.: ITEM PART No.:
SUPPLIER NAME MAKE
RECEIVING DATE RECEIVING TIME P.O NO.:
PACKING LIST
INSPECTION DATE INSPECTION TIME
NO.:
PURCHASED FOR FTI PROJECT QC NO.:
S.NO INSPECTION PARAMETERS SPECIFICATION RESULT
1 Transit Damage
2 Container Seal
3 Packing Health
4 Physical Health
5 Quantity
6 Type of Actuator
7 Type of Control Function
8 Torque
9 Pressure Rating
10 Temperature Range
11 Material of Construction (Body)
12 Material of Construction (Shaft)
13 Electrical Specifications
14 Documents Received
15
Remarks: STATUS:
INSPECTED BY VERIFIED BY FTI PROJECTS