CAWANGAN KONTRAK DAN UKUR BAHAN 02.01.2022

Work Item Unit Overall Average (RM)


SEWERAGE m Location Range (RM) Average (RM) RM 5.28
DRAINAGE
A 3.00 - 3.20 3.10
EXCAVATION
Excavating trenches starting from formation level; C 3.00 - 3.00 3.00
earthwork support, part return, fill in and ram and D 8.00 - 8.00 8.00
remainder deposit, spread and level within site
To receive drain pipes not exceeding 200mm nominal F 7.00 - 7.00 7.00
size, not exceeding 2.00m average 1.00m deep
SEWERAGE m Location Range (RM) Average (RM) RM 3.50
DRAINAGE
F 3.50 - 3.50 3.50
EXCAVATION
Excavating trenches starting from formation level;
earthwork support, part return, fill in and ram and
remainder deposit, spread and level within site
To receive drain pipes 250mm nominal size, not
exceeding 2.00m; average 1.00m deep
SEWERAGE m Location Range (RM) Average (RM) RM 21.80
DRAINAGE
C 21.80 - 21.80 21.80
EXCAVATION
Excavating trenches starting from formation level;
earthwork support, part return, fill in and ram and
remainder deposit, spread and level within site
To receive drain pipes 250mm nominal size, 2.00m -
4.00m; average 3.00m deep
SEWERAGE m Location Range (RM) Average (RM) RM 8.15
DRAINAGE
C 8.00 - 8.30 8.15
EXCAVATION
Excavating trenches starting from formation level; D 7.50 - 9.20 8.14
earthwork support, part return, fill in and ram and
remainder deposit, spread and level within site
To receive drain pipes 250mm nominal size, not
exceeding 2.00m; average 1.75m deep
SEWERAGE m Location Range (RM) Average (RM) RM 9.75
DRAINAGE
EXCAVATION
Excavating trenches starting from formation level;

1/5
Portal RATOL & Rates PreMo
CAWANGAN KONTRAK DAN UKUR BAHAN 02.01.2022

Work Item Unit Overall Average (RM)


earthwork support, part return, fill in and ram and C 9.50 - 10.00 9.75
remainder deposit, spread and level within site
To receive drain pipes 250mm nominal size, not
exceeding 2.00m; average 2.00m deep
SEWERAGE m Location Range (RM) Average (RM) RM 12.00
DRAINAGE
C 12.00 - 12.00 12.00
EXCAVATION
Excavating trenches starting from formation level;
earthwork support, part return, fill in and ram and
remainder deposit, spread and level within site
To receive drain pipes 250mm nominal size,
exceeding 2.00mm not exceeding 4.00m; average
2.50m deep
SEWERAGE m Location Range (RM) Average (RM) RM 16.00
DRAINAGE
D 16.00 - 16.00 16.00
EXCAVATION
Excavating trenches starting from formation level;
earthwork support, part return, fill in and ram and
remainder deposit, spread and level within site
Exceeding 1.50m but not exceeding 3.00m deep
SEWERAGE m3 Location Range (RM) Average (RM) RM 12.00
DRAINAGE
C 12.00 - 12.00 12.00
EXCAVATION
Excavating trenches starting from formation level;
earthwork support, part return, fill in and ram and
remainder deposit, spread and level within site
depth not exceeding 2.00m
SEWERAGE m2 Location Range (RM) Average (RM) RM 10.00
DRAINAGE
C 10.00 - 10.00 10.00
BEDDING
Aggregate bedding, spread, levelled and well
compacted to receive pipe laid to falls
150mm grade 20
SEWERAGE m Location Range (RM) Average (RM) RM 114.43
DRAIN
Pipework

2/5
Portal RATOL & Rates PreMo
CAWANGAN KONTRAK DAN UKUR BAHAN 02.01.2022

Work Item Unit Overall Average (RM)


Vitrified clay pipe and fittings as specified; laid and D 75.00 - 111.60 88.87
jointed in trench on and including bedding as specified
225mm Nominal size; not exceeding 4.00m, average E 140.00 - 140.00 140.00
1.35m deep
SEWERAGE m Location Range (RM) Average (RM) RM 30.57
DRAINAGE
D 16.70 - 40.00 30.57
BEDDING
Aggregate bedding, spread, levelled and well
compacted to receive pipe laid to falls
600mm wide x 213mm thick
SEWERAGE m Location Range (RM) Average (RM) RM 13.31
DRAINAGE
A 8.50 - 8.50 8.50
EXCAVATION
Excavating trenches starting from formation level; B 25.50 - 25.50 25.50
earthwork support, part return, fill in and ram and C 4.70 - 15.00 11.23
remainder deposit, spread and level within site
To receive drain pipes 225mm nominal size, 2.00m - D 8.00 - 8.00 8.00
4.00m; average 3.00m deep
SEWERAGE m Location Range (RM) Average (RM) RM 58.00
DRAIN
F 58.00 - 58.00 58.00
Pipework
Vitrified clay pipe and fittings as specified; laid and
jointed in trench on and including bedding as specified
230mm Nominal size; not exceeding 2.00m, average
1.75m deep
SEWERAGE m Location Range (RM) Average (RM) RM 78.17
DRAIN
A 95.00 - 134.00 114.50
Pipework
Vitrified clay pipe and fittings as specified; laid and B 55.00 - 92.00 73.50
jointed in trench on and including bedding as specified D 12.00 - 19.00 14.40
225mm Nominal size; not exceeding 2.00m average
1.50m deep E 60.00 - 140.00 110.29

SEWERAGE m Location Range (RM) Average (RM) RM 15.00


DRAINAGE
EXCAVATION
Excavating trenches starting from formation level;

3/5
Portal RATOL & Rates PreMo
CAWANGAN KONTRAK DAN UKUR BAHAN 02.01.2022

Work Item Unit Overall Average (RM)


earthwork support, part return, fill in and ram and D 15.00 - 15.00 15.00
remainder deposit, spread and level within site
To receive drain pipes 225mm nominal size, not
exceeding 2.00m; average 1.00m deep
SEWERAGE m Location Range (RM) Average (RM) RM 15.00
DRAINAGE
F 15.00 - 15.00 15.00
EXCAVATION
Excavating trenches starting from formation level;
earthwork support, part return, fill in and ram and
remainder deposit, spread and level within site
To receive drain pipes not exceeding 200mm nominal
size, not exceeding 2.00m average 1.25m deep
SEWERAGE m Location Range (RM) Average (RM) RM 20.00
DRAINAGE
F 20.00 - 20.00 20.00
EXCAVATION
Excavating trenches starting from formation level;
earthwork support, part return, fill in and ram and
remainder deposit, spread and level within site
To receive drain pipes not exceeding 200mm nominal
size, not exceeding 2.00m average 1.50m deep
SEWERAGE m Location Range (RM) Average (RM) RM 30.00
DRAINAGE
F 30.00 - 30.00 30.00
EXCAVATION
Excavating trenches starting from formation level;
earthwork support, part return, fill in and ram and
remainder deposit, spread and level within site
To receive drain pipes 225mm nominal size, not
exceeding 2.00m average 1.75m deep
SEWERAGE m Location Range (RM) Average (RM) RM 30.00
DRAINAGE
F 30.00 - 30.00 30.00
EXCAVATION
Excavating trenches starting from formation level;
earthwork support, part return, fill in and ram and
remainder deposit, spread and level within site
To receive drain pipes 225mm nominal size, not
exceeding 2.00m average 2.00m deep

4/5
Portal RATOL & Rates PreMo
CAWANGAN KONTRAK DAN UKUR BAHAN 02.01.2022

Work Item Unit Overall Average (RM)

Nota Catatan
Sekiranya anda mempunyai sebarang pertanyaan, sila hubungi:
Ketua Penolong Pengarah Kanan
Bahagian Perolehan dan Khidmat Kos
Cawangan Kontrak dan Ukur Bahan
Ibu Pejabat JKR Malaysia
Tingkat 19, Menara Tun Ismail Mohamed Ali
No 25, Jalan Raja Laut
50582 Kuala Lumpur

u.p: En Husnan Husin


Tel: 03-26161111
Email: husnan@jkr.gov.my