PAMT PROJECT

BARITO TIMUR

Hazred Umar Fathan B.Eng, MAusIMM

Umar Rivaldy Pulukadang B.Eng, MAusIMM

1
PAMT PROJECT
BARITO TIMUR

Mtd Review Desember 2021


01 Desember – 18 Desember 2021
Arranged by,
Engineering Dept.

2
Raw Data Equipment Event
Equipment Date Status Duration Remarks Equipment Date Status Duration Remarks Equipment Date Status Duration Remarks
Kobelco SK-200 01/12/2021 Stby 1 Depart from mess to pit Kobelco SK-200 09/12/2021 Ready 4,5 Komatsu d-85 08/12/2021 Stby 5 Menunggu air sungai surut
Kobelco SK-200 01/12/2021 Idle 2 General (pembuatan pad tendon) Kobelco SK-200 09/12/2021 Stby 1 Rest time Komatsu d-85 08/12/2021 Stby 1 Rest time
Kobelco SK-200 01/12/2021 Ready 2 Kobelco SK-200 09/12/2021 Ready 3,5 Komatsu d-85 08/12/2021 Ready 3
Kobelco SK-200 09/12/2021 Stby 0,5 Rain Komatsu d-85 08/12/2021 Stby 1 Refueling
Kobelco SK-200 01/12/2021 Stby 1 Rest time
Kobelco SK-200 10/12/2021 Stby 5 Sosial issue Komatsu d-85 09/12/2021 Stby 0,5 Depart from mess to pit
Kobelco SK-200 01/12/2021 Ready 1
Komatsu d-85 09/12/2021 Ready 4,5
Kobelco SK-200 01/12/2021 Stby 3 Rest Fuel Kobelco SK-200 10/12/2021 Stby 1 Rest time
Komatsu d-85 09/12/2021 Stby 1 Rest time
Kobelco SK-200 02/12/2021 Stby 1 Depart from mess to pit Kobelco SK-200 10/12/2021 Stby 4 Rain
Komatsu d-85 09/12/2021 Ready 2
Kobelco SK-200 02/12/2021 Idle 1 Refueling Kobelco SK-200 11/12/2021 Stby 0,5 Depart from mess to pit
Komatsu d-85 09/12/2021 Stby 2 Rain
Kobelco SK-200 02/12/2021 Ready 3 Kobelco SK-200 11/12/2021 Ready 4,5 Komatsu d-85 10/12/2021 Stby 5 Sosial issue
Kobelco SK-200 02/12/2021 Stby 1 Rest time Kobelco SK-200 11/12/2021 Stby 1 Rest time Komatsu d-85 10/12/2021 Stby 1 Rest time
Kobelco SK-200 02/12/2021 Ready 4 Kobelco SK-200 11/12/2021 Ready 2 Komatsu d-85 11/12/2021 Stby 0,5 Depart from mess to pit
Kobelco SK-200 03/12/2021 Stby 1 Depart from mess to pit Kobelco SK-200 11/12/2021 Stby 2 Rain Komatsu d-85 11/12/2021 Ready 4,5
Kobelco SK-200 03/12/2021 Ready 4 Kobelco SK-200 12/12/2021 Stby 0,5 Depart from mess to pit Komatsu d-85 11/12/2021 Stby 1 Rest time
Kobelco SK-200 03/12/2021 Stby 1 Rest time Kobelco SK-200 12/12/2021 Idle 1 Refueling Komatsu d-85 11/12/2021 Ready 0,5
Kobelco SK-200 12/12/2021 Ready 3,5 Komatsu d-85 11/12/2021 Down 1,5 Pin blade patah
Kobelco SK-200 03/12/2021 Ready 4
Kobelco SK-200 12/12/2021 Stby 1 Rest time Komatsu d-85 11/12/2021 Stby 2 Rain
Kobelco SK-200 04/12/2021 Stby 0,5 Depart from mess to pit
Kobelco SK-200 12/12/2021 Stby 4 Rain Komatsu d-85 12/12/2021 Stby 0,5 Depart from mess to pit
Kobelco SK-200 04/12/2021 Idle 1 Refueling Komatsu d-85 12/12/2021 Ready 4,5
Kobelco SK-200 13/12/2021 Stby 0,5 Depart from mess to pit
Kobelco SK-200 04/12/2021 Ready 3,5 Komatsu d-85 12/12/2021 Stby 1 Rest time
Kobelco SK-200 13/12/2021 Ready 3,5
Kobelco SK-200 04/12/2021 Stby 1 Rest time Komatsu d-85 12/12/2021 Stby 4 Rain
Kobelco SK-200 13/12/2021 Stby 1 Rain
Kobelco SK-200 04/12/2021 Ready 4 Komatsu d-85 13/12/2021 Stby 0,5 Depart from mess to pit
Kobelco SK-200 13/12/2021 Stby 1 Rest time
Kobelco SK-200 05/12/2021 Stby 1 Depart from mess to pit Komatsu d-85 13/12/2021 Ready 3,5
Kobelco SK-200 13/12/2021 Stby 0,5 Rain
Kobelco SK-200 05/12/2021 Ready 4 Kobelco SK-200 13/12/2021 Ready 2,5
Komatsu d-85 13/12/2021 Stby 1 Rain
Kobelco SK-200 05/12/2021 Stby 1 Rest time Komatsu d-85 13/12/2021 Stby 1 Rest time
Kobelco SK-200 13/12/2021 Stby 1 Rain
Kobelco SK-200 05/12/2021 Ready 4 Komatsu d-85 13/12/2021 Stby 0,5 Rain
Kobelco SK-200 14/12/2021 Stby 5 Sosial issue Komatsu d-85 13/12/2021 Ready 2,5
Kobelco SK-200 06/12/2021 Stby 0,5 Depart from mess to pit Kobelco SK-200 14/12/2021 Stby 5 Rain Komatsu d-85 13/12/2021 Stby 1 Rain
Kobelco SK-200 06/12/2021 Idle 4,5 General (Pembuatan pad fuel) Kobelco SK-200 15/12/2021 Stby 10 Sosial issue Komatsu d-85 14/12/2021 Stby 5 Sosial issue
Kobelco SK-200 06/12/2021 Stby 1 Rest time Kobelco SK-200 16/12/2021 Stby 10 Sosial issue Komatsu d-85 10/12/2021 Stby 4 Rain
Kobelco SK-200 06/12/2021 Ready 4 Kobelco SK-200 17/12/2021 Stby 10 Sosial issue Komatsu d-85 14/12/2021 Stby 5 Rain
Kobelco SK-200 07/12/2021 Stby 0,5 Depart from mess to pit Kobelco SK-200 18/12/2021 Stby 10 Sosial issue Komatsu d-85 15/12/2021 Stby 10 Sosial issue
Kobelco SK-200 07/12/2021 Idle 1 Refueling Komatsu d-85 06/12/2021 Stby 1 Rest time Komatsu d-85 16/12/2021 Stby 10 Sosial issue
Kobelco SK-200 07/12/2021 Stby 1 Rest time Komatsu d-85 06/12/2021 Ready 4 Komatsu d-85 17/12/2021 Stby 10 Sosial issue
Kobelco SK-200 07/12/2021 Stby 7,5 Operator sakit Komatsu d-85 07/12/2021 Stby 0,5 Depart from mess to pit Komatsu d-85 18/12/2021 Stby 10 Sosial issue
Kobelco SK-200 08/12/2021 Stby 5 Menunggu air sungai surut Komatsu d-85 07/12/2021 Ready 4
Kobelco SK-200 08/12/2021 Stby 1 Rest time Komatsu d-85 07/12/2021 Stby 0,5 Rest Fuel
Kobelco SK-200 08/12/2021 Ready 3 Komatsu d-85 07/12/2021 Stby 1 Rest time
Kobelco SK-200 08/12/2021 Idle 1 Refueling Komatsu d-85 07/12/2021 Stby 3 Rest Fuel
Kobelco SK-200 09/12/2021 Stby 0,5 Depart from mess to pit Komatsu d-85 07/12/2021 Stby 1 Refueling

3
Equipment Availibility

Equipment Ready Stby Idle Down Total


Kobelco SK-200 64,5 104 11,5 - 180,0
Komatsu d-85s 33 90,5 1,5 125,0

Kobelco SK-200 Komatsu d-85s


MA UA Ewh MA UA Ewh
Actual 100% 36% 36% Actual 96% 27% 26%
Plan 87% 65% 56% Plan 87% 65% 56%

4
Mtd Review (1-18 Des)
Equipment Working Hour

Total Working Hour 180 Total Working Hour 125

Stand by : Stand by :
• Social Issue (50 h) • Social Issue (50 h)
• Rain (18 h) • Rain (19,5 h)
• Rest time (13 h) • Rest time (8 h)
• Operator Sakit (7,5 h) • Menunggu air sungai surut (5 h)
• Depart from mess to pit (7,5 h) • Rest fuel (3,5 h)
• Menunggu air sungai surut (5 h) • Depart from mess to pit (2,5 h)
• Rest fuel (3 h) • Refueling (2 h)

Down :
Idle : • Pin blade patah (1,5 h)
• General activities (6,5 h)
• Refueling (5 h)

5
Mtd Review (1-18 Des)
Equipment Performance

Kobelco SK-200 Komatsu d-85s

Actual Plan

6
Please don't be hesitate to contact us with our professional team. We give the best win to win solution.

Head Office:
Branch Office:
Ruko Irigasi Residence Kav. No. 8
The Mansion Bougenville Gloria 28M1
Jl. Irigasi, Srijaya, Alang- Alang Lebar, Palembang,
Jl. Trembesi Blok D, Pademangan Tim., Kec. Pademangan,
South Sumatra, 30153
Kota Jkt Utara, Daerah Khusus Ibukota Jakarta 14410
T: 0711-5716033 E: admin@geosriwijaya.com

You might also like