Note: 2 For hilly areas 80% above the rates in the plain areas shall be allowed for total mileage (Km) covered.
Note: 3 In case of articles longer than 15 ft. (4.6 m) carried in trucks, the following rates shall be allowed:-
i) Above 15 ft. to 25 ft. (4.6 to 7.6 m) :- Total rates to be paid for 15 ft. to 25 ft. (4.6 to 7.6 m) length will be 1.5 times of the
rate given in the Composite Schedule of Rates.
ii) Above 25 ft. (7.6 m) :- The total rate to be paid for above 25 ft. (7.6 m) length will be 2 times of the rate given in the
Composite Schedule of Rates.
The length measured shall not be the actual length, but the length of the form of consignment as actually
received.
Note: 4 The term 'mile' (Km) whenever used is to mean statute mile (Km).
Note: 5 The rates include loading and unloading of material from the conveyance and stacking as directed.
Note: 6 The rates for carriage by boat or steamer shall be the same as by any other mechanical means on land.
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
1 Carriage of 100 Cft. (2.83 cu.m) of all materials like stone 16.1 Add 20% extra for the item
aggregate, spawl, kankar lime (unslaked), surkhi, etc. or "Recouping of Reserve Stock of stone
150 Cft. (4.25 cu.m) of timber, by truck or by any other for Flood Protection Work in
means owned by the contractor. Irrigation Department".
1st chain (1st 30 m) Chain 225.35 30M 225.35
2nd chain (2nd 30 m) " 41.30 30M 41.30
3rd to 10th chain (60 to 300 m) " 25.80 30M 25.80
1000 to 3000 ft. (300 to 900 m) 1000 ft. 252.95 300 M 252.95
1st Km Km 247.30
2nd Km Km 113.75
3rd Km Km 84.25
4th Km Km 56.45
5th Km Km 51.75
6th Km Km 50.70
7th Km Km 46.50
8th Km Km 45.85
9th Km Km 42.45
10th Km Km 38.95
11th Kms to 200Kms Km 30.75
201 Kms to 250 Kms Km 3.25
251 Kms & susequent Kms Km 2.00
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
2 Carriage of 5 tons of all material like coal, stone lime 16.1 Cement carried in containers other
(unslaked), etc. B.G. Rail fastenings, points and crossing, than bags will be paid according to
Bridge Girders, pipes, sheets, Rail, M.S. bars, etc. etc. this item. The word "pipes" covers
by truck or any other means owned by the contractor. G.I,C.I,R.C.C. and P.C.C.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
10th Km Km 38.95
7th mile and subsequent miles " 37.50
11th & subsequent Kms Km 30.75
4 Carriage of 1000 Nos. bricks 10"x5"x3" (250x125x75 mm) ditto Reduce the rate by 33% in case of
or 1000 Nos. tiles 12"x6"x2" (300x150x50 mm) by truck or carriage of 1000 Nos. tiles size
any other means owned by the contractor :- 12"x6"x1¼" (300 x 150 x 30 mm).
1st chain (1st 30 m) Chain 225.35 30 M 225.35
2nd chain (2nd 30 m) " 41.30 30 M 41.30
3rd to 10th chain (60 to 300 m) " 25.80 30 M 25.80
1000 to 3000 ft. (300 to 900 m) 1000 Ft 252.95 300 M 252.95
1st Km Km 247.30
2nd Km Km 113.75
3rd Km Km 84.25
4th Km Km 56.45
1st mile Mile 398.00
5th Km Km 51.75
2nd mile " 90.60
6th Km Km 50.70
3rd mile " 81.20
7th Km Km 46.50
4th mile " 73.10
8th Km Km 45.85
5th mile " 66.75
9th Km Km 42.45
6th mile " 61.50
10th Km Km 38.95
7th mile and subsequent miles " 37.50
11th & subsequent Kms Km 30.75
5 Carriage of 100 cft. (2.83 cu.m) of all material like stone, 16.1 Material trolly to be supplied by the
aggregate, spawl, kankar lime(unslaked), surkhi, etc. or Government and maintained and run
150 cft. (4.25 cu.m) of timber, by means of material trolly. by the contractor.
1st chain (1st 30 m) Chain 225.35 30 M 225.35
2nd chain to 10th chain (2nd 30 m to 300 m) " 41.30 30 M 41.30
1000 to 3000 ft. (300 to 900 m) 1000 Ft. 252.95 300 M 252.95
1st Km Km 202.85
2nd Km Km 150.80
3rd Km Km 76.40
4th Km
1st mile Mile 326.40 Km 58.00
5th
2ndKm
mile 108.70 Km 50.45
6th Km
3rd mile 91.70 Km 48.35
7th Km Km 40.30
8th Km Km 39.75
9th
6th Km
mile 61.50 Km 36.75
10thmile
7th Km and subsequent miles 37.50 Km 33.75
11th Kms to 200Kms Km 28.30
201 Kms to 250 Kms Km 3.25
251 Kms & susequent Kms Km 2.00
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
6 Carriage of 5 tons of all material like coal, stone lime 16.1 Material trolly to be supplied by the
(unslaked), etc. B.G. Rail fastening, points and crossing, Government and maintained and run
Bridge girders, pipes, sheets, Rail, M.S. bars, etc. etc. by by the contractor.
means of material trolly.
1st chain (1st 30 m) Chain 225.35 30 M 225.35
2nd chain (2nd 30 m) " 41.30 30 M 41.30
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 252.95 300 M 252.95
1st Km Km 202.85
2nd Km Km 150.80
3rd Km Km 76.40
4th Km Km 58.00
5th Km Km 50.45
6th
3rd Km
mile and subsequent miles 91.7 Km 48.35
7th
4th Km
mile 73.10 Km 40.30
8th Km Km 39.75
9th Km Km 36.75
10th Km q Km 33.75
11th Kms to 200Kms Km 28.30
201 Kms to 250 Kms Km 3.25
251 Kms & susequent Kms Km 2.00
7 Carriage of 100 maunds of fuel wood, by means of ditto Material trolly to be supplied
material trolly. by the Government and
1st chain (1st 30 m) Chain 225.35 30 M 225.35 maintained and run by the
2nd chain (2nd 30 m) " 41.3 30 M 41.30 contractor.
1000 to 3000 ft. (300 to 900 m) 1000 Ft 252.95 300 M 252.95
1st Km Km 202.85
2nd Km Km 150.80
3rd Km Km 76.40
4th Km Km 58.00
1st mile Mile 326.40
5th Km Km 50.45
2nd mile " 108.70
6th Km Km 48.35
3rd mile subsequent miles " 91.70
7th Km Km 40.30
4th mile 73.10
8th Km Km 39.75
5th mile 66.75
9th Km Km 36.75
6th mile 61.50
10th Km Km 33.75
7th mile and subsequent miles 37.50
11th & subsequent Kms Km 28.30
8 Carriage of 1000 Nos. tiles 12"x6"x2" (300x150x50 mm), ditto Material trolly to be supplied by the
by means of material trolly. Government and maintained and run
1st chain (1st 30 m) Chain 225.35 30 M 225.35 by the contractor.
2nd chain (2nd 30 m) " 41.30 30 M 41.30
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 252.95 300 M 252.95
1st Km Km 202.85
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
2nd Km Km 150.80 16.1
3rd Km Km 76.40
4th Km Km 58.00
1st mile Mile 326.40
5th Km Km 50.45
2nd mile " 108.70
6th Km Km 48.35
3rd mile subsequent miles " 91.70
7th Km Km 40.30
4th mile 73.10
8th. Km 39.75
5th mile 66.75
9th Km Km 36.75
6th mile 61.50
10th Km Km 33.75
7th mile and subsequent miles 37.50
11th & subsequent Kms Km 28.30
9 Carriage of 1000 No. bricks, 9"x4½"x3" ditto
(225x113x75 mm) or 8"x4"x4" (200x100x100
mm) (nominal)
1st chain (1st 30 m) Chain 184.64 30 M 184.64
2nd chain (2nd 30 m) " 39.85 30 M 39.85
3rd to 10th chain (60 to 300 m) " 21.18 30 M 21.18
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 207.10 300 M 207.10
1st Km Km 202.75
2nd Km Km 93.00
3rd Km Km 69.00
4th Km Km 46.55
1st mile Mile 326.25
5th Km Km 43.70
2nd mile " 74.25
6th Km Km 42.55
3rd mile " 68.70
7th Km Km 38.05
4th mile " 59.90
8th Km Km 37.55
5th mile " 54.70
9th Km Km 34.75
6th mile " 50.35
10th Km Km 31.90
7th mile and subsequent miles " 30.75
11th & subsequent Kms Km 25.05
10 Carriage of 1000 No. tiles 9"x4½"x1½" 16.1
(225x113x38 mm).
1st chain (1st 30 m) Chain 111.43 30 M 111.43
2nd chain (2nd 30 m) " 20.40 30 M 20.40 16.1
3rd to 10th chain (60 to 300 m) " 12.66 30 M 12.66
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 125.11 300 M 125.11
1st Km Km 122.40
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
2nd Km Km 56.30
3rd Km Km 41.70
4th Km Km 27.90
1st mile Mile 196.95
5th Km Km 25.45
2nd mile " 44.85
6th Km Km 24.95
3rd mile " 39.90
7th Km Km 23.00
4th mile " 36.20
8th Km Km 22.70
5th mile " 33.00
9th Km Km 21.00
6th mile " 30.45
10th Km Km 19.30
7th mile and subsequent miles " 18.50
11th & subsequent Kms Km 15.20
11 Carriage of 1 Cwt. (50 Kg) cement in bags. ditto
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 2.49 300 M 2.49
1st Km Km 3.05
1st mile Mile 4.90
2nd Km Km 2.10
2nd mile " 1.40
3rd Km Km 0.85
3rd mile subsequent miles " 0.75
4th Km and subsequent kilometers. Km 0.50
12 Carriage of 100 Nos. empty cement bags including 16.1
bundling.
1st Km Km 7.45
1st mile Mile 12.00
2nd Km Km 6.95
2nd mile to 6th mile Mile 1.95
3rd Km Km 2.90
7th mile and subsequent miles " 4.55
4th Km & subsequent Kms Km 2.40
13 Carriage of 100 (2.83 cu.m) cft. of Sarkanda or pilchi, frash ditto Previous lead of collection not
or brushwood, by boat or road :- to be deducted from the next
lead of carriage.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
2nd chain (2nd 30 m) " 41.30 30 M 41.30
3rd to 10th chain (60 to 300 m) " 12.66 30 M 12.66
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 103.92 300 M 103.92
1st Km Km 116.40
1st mile Mile 175.10
2nd Km Km 56.30
2nd mile " 126.65
3rd Km Km 41.70
3rd mile " 105.50
4th Km Km 27.90
4th mile " 76.80
5th Km Km 25.45
5th mile " 63.35
6th Km Km 24.95
6th mile 50.35
7th Km Km 23.00
7th mile and subsequent miles 30.75
8th Km Km 22.70
9th Km Km 21.00
10th Km Km 19.30
11th Km & subsequent Km 15.20
1st Km Km 243.30
1st mile Mile 391.55
2nd Km Km 111.40
2nd mile " 71.60
3rd Km Km 73.50
3rd mile " 67.45
4th Km Km 45.65
4th mile " 53.80
5th Km Km 42.90
5th mile " 54.30
6th Km Km 41.10
6th mile " 41.80
7th Km Km 35.00
7th mile and subsequent miles " 29.35
8th Km Km 34.60
9th Km Km 33.60
10th Km Km 26.30
11th Km & susequent Km 22.50
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
15 Carriage of small consignments weighing upto 5 maunds 16.1 For consignment weighing 5 to 10
(job rates) : maunds, rate be increased by 25%;
and for consignments weighing 10
Consig- to 20 maunds, rate be increased by
Upto 1000 ft. (300 metre) ment/ 61.06 Consign- 61.06 100%.
1000 ft. ment/
Exceeding 1000 to 3000 ft. (300 to 900 1000 ft. 41.87 300 M 41.87
metre)
Each Each
iii) Cart load for a distance :- Consign- Consig-
ment nment
a) upto 4 Miles/ 6.4 Km " 89.85 " 89.85
b) Exceeding 4 Miles(6.4 Km) to10 Miles(16 Km) " 163.55 " 163.55
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
loading and unloading shall be paid
by the borrower.
1000 to 9000 ft. (300 to 900 m) 0/00 Ft. 13.10 300 M 13.10
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
1st Km Km 12.80
1st mile Mile 20.60
2nd Km Km 5.85
2nd mile " 4.70
3rd Km Km 4.35
3rd mile " 4.20
4th Km Km 2.90
4th mile " 3.80
5th Km Km 2.65
5th mile " 3.45
6th Km Km 2.55
6th mile " 3.20
7th Km Km 2.40
7th mile and subsequent miles " 1.95
8th Km Km 2.30
9th Km Km 2.15
10th Km Km 2.00
11th Km & subsequent Km Km 1.90
iii) 6" (150 mm) i/d pipes:-
1st chain (1st 30 m) Chain 17.50 30 M 17.50
2nd chain (2nd 30 m) " 3.20 30 M 3.20
3rd to 10th chain (60 to 300 m) " 2.00 30 M 2.00
1000 to 9000 ft. (300 to 900 m) 0/00 Ft. 19.65 300 M 19.65
1st Km Km 19.20
2nd Km Km 8.80
3rd Km Km 6.55
1st mile Mile 30.90
4th Km Km 4.35
2nd mile " 7.05
5th Km Km 4.00
3rd mile " 6.30
6th Km Km 3.90
4th mile " 5.65
7th Km Km 3.55
5th mile " 5.20
8th Km Km 3.45
6th mile " 4.75
9th Km Km 3.30
7th mile and subsequent miles " 2.90
10th Km Km 2.95
11th Km & subsequent Km Km 2.60
iv) 8" (200 mm) i/d pipes:
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
2nd Km Km 15.45
3rd Km Km 11.25
1st mile Mile 52.25
4th Km Km 7.50
2nd mile " 11.90
5th Km Km 6.85
3rd mile " 10.65
6th Km Km 6.75
4th mile " 9.60
7th Km Km 6.15
5th mile " 8.75
8th Km Km 5.95
6th mile " 8.05
9th Km Km 5.25
7th mile and subsequent miles " 4.90
10th Km Km 2.50
11th Km & subsequent Km Km 1.85
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
4th Km Km 12.80
1st mile Mile 91.30
5th Km Km 11.75
2nd mile " 20.80
6th Km Km 11.50
3rd mile " 18.65
7th Km Km 10.50
4th mile " 16.75
8th Km Km 10.35
5th mile " 15.30
9th Km Km 9.55
6th mile " 14.10
10th Km Km 8.80
7th mile and subsequent miles " 8.60
11th Km & subsequent Kms Km 7.00
vii) 16" (400 mm) i/d pipes:-
1st chain (1st 30 m) Chain 84.70 30 M 84.70
2nd chain (2nd 30 m) " 15.55 30 M 15.55
3rd to 10th chain (60 to 300 m) " 9.70 30 M 9.70
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 95.10 300 M 95.10
1st Km Km 92.95
2nd Km Km 43.00
3rd Km Km 31.65
1st mile Mile 149.60
4th Km Km 21.20
2nd mile " 34.05
5th Km Km 19.45
3rd mile " 30.55
6th Km Km 19.05
4th mile " 27.50
7th Km Km 17.45
5th mile " 25.10
8th Km Km 17.20
6th mile " 23.15
9th Km Km 15.90
7th mile and subsequent miles " 14.10
10th Km Km 14.65
11th Km & subsequent Kms Km 11.55
viii) 18" (450 mm) i/d pipes:-
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
4th Km Km 27.25
2nd mile " 43.75
5th Km Km 25.05
3rd mile " 39.25
6th Km Km 24.50
4th mile " 35.30
7th Km Km 22.45
5th mile " 32.25
8th Km Km 22.15
6th mile " 29.70
9th Km Km 20.50
7th mile and subsequent miles " 18.10
10th Km Km 18.80
11th Km & subsequent Kms Km 14.75
ix) 20" (500 mm) i/d pipes:-
1st chain (1st 30 m) Chain 115.55 30 M 115.55
2nd chain (2nd 30 m) " 21.20 30 M 21.20
3rd to 10th chain (60 to 300 m) " 13.20 30 M 13.20
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 129.70 300 M 129.70
1st Km Km 126.85
2nd Km Km 58.30
3rd Km Km 43.20
1st mile Mile 204.10
4th Km Km 28.95
2nd mile " 46.45
5th Km Km 26.55
3rd mile " 41.65
6th Km Km 26.00
4th mile " 37.50
7th Km Km 23.85
5th mile " 34.25
8th Km Km 23.50
6th mile " 31.55
9th Km Km 21.75
7th mile and subsequent miles " 19.25
10th Km Km 20.00
11th Km & subsequent Kms Km 15.85
x) 24" (600 mm) i/d pipes:-
1st chain (1st 30 m) Chain 128.05 30 M 128.05
2nd chain (2nd 30 m) " 23.45 30 M 23.45
3rd to 10th chain (60 to 300 m) " 14.65 30 M 14.65
1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 143.75 300 M 143.75
1st Km Km 140.55
2nd Km Km 64.55
3rd Km Km 47.80
1st mile Mile 226.15
4th Km Km 32.55
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
2nd mile " 51.45
5th Km Km 29.35
3rd mile " 46.15
6th Km Km 28.75
4th mile Mile 41.55
7th Km Km 26.35
5th mile " 37.95
8th Km Km 26.00
6th mile " 34.95
9th Km Km 24.05
7th mile and subsequent miles " 21.30
10th Km Km 22.10
11th Km & subsequent Kms Km 17.35
20 Carriage of PVC pipes B.S.S. Class 'B' including loading,
unloading and stacking (Rate per 1000 ft.) (300 metre) :-
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
3rd Km Km 10.05
1st mile Mile 47.45
4th Km Km 6.65
2nd mile " 10.80
5th Km Km 6.10
3rd mile " 9.70
6th Km Km 5.95
4th mile " 8.70
7th Km Km 5.45
5th mile " 7.95
8th Km Km 5.40
6th mile " 7.35
9th Km Km 4.95
7th mile and subsequent miles " 4.45
10th Km Km 4.60
11th Km & subsequent Kms Km 4.05
iii) 5" (125 mm) i/d pipes:-
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
3rd Km Km. 18.90
1st mile Mile 89.25
4th Km Km. 12.65
2nd mile " 20.30
5th Km Km. 11.60
3rd mile " 18.20
6th Km Km. 11.35
4th mile " 16.40
7th Km Km. 10.45
5th mile " 14.95
8th Km Km. 10.30
6th mile " 13.80
9th Km Km. 9.50
7th mile and subsequent miles " 8.40
10th Km Km. 8.75
11th Km & subsequent Kms Km. 6.90
v) 8" (200 mm) i/d pipes:-
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
3rd Km Km 51.35
1st mile Mile 242.70
4th Km Km 34.40
2nd mile " 55.25
5th Km Km 31.55
3rd mile " 49.50
6th Km Km 30.90
4th mile " 44.60
7th Km Km 28.35
5th mile " 40.70
8th Km Km 27.95
6th mile " 37.50
9th Km Km 25.85
7th mile and subsequent miles " 22.85
10th Km Km 23.75
11th Km & subsequent Kms Km 18.80
vii) 12" (300 mm) i/d pipes:-
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
3rd Km Km 94.10
1st mile Mile 444.70
4th Km Km 63.05
2nd mile " 101.20
5th Km Km 57.85
3rd mile " 90.75
6th Km Km 56.65
4th mile Mile 81.70
7th Km Km 51.95
5th mile " 74.60
8th Km Km 51.25
6th mile " 68.75
9th Km Km 47.40
7th mile and subsequent miles " 41.90
10th Km Km 43.55
11th Km & subsequent Kms Km 34.45
21 Carriage of PVC pipes B.S.S. Class 'D' including loading,
unloading and stacking (Rates per 1000 ft.):-
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
1st Km Km 21.80
2nd Km Km 10.05
3rd Km Km 7.45
1st mile Mile 35.05
4th Km Km 5.00
2nd mile " 7.95
5th Km Km 4.60
3rd mile " 7.15
6th Km Km 4.50
4th mile " 6.45
7th Km Km 4.15
5th mile " 5.90
8th Km Km 3.90
6th mile " 5.40
9th Km Km 3.70
7th mile and subsequent miles " 3.30
10Km Km 3.35
11th Km & subsequent Kms Km 2.75
iii) 3" (75 mm) i/d pipes:-
1st chain (1st 30 m) Chain 27.50 30 M 27.50
2nd chain (2nd 30 m) " 5.05 30 M 5.05
3rd to 10th chain (60 to 300 m) " 3.15 30 M 3.15
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 30.85 300 M 30.85
1st Km Km 30.15
2nd Km Km 13.90
3rd Km Km 10.30
1st mile Mile 48.55
4th Km Km 6.90
2nd mile " 11.05
5th Km Km 6.35
3rd mile " 9.90
6th Km Km 6.20
4th mile " 8.90
7th Km Km 5.70
5th mile Mile 8.15
8th Km Km 5.60
6th mile " 7.50
9th Km Km 5.10
7th mile and subsequent miles " 4.55
10th Km Km 4.65
11th Km & subsequent Kms Km 3.80
iv) 4" (100 mm) i/d pipes:-
1st chain (1st 30 m) Chain 45.50 30 M 45.50
2nd chain (2nd 30 m) " 8.35 30 M 8.35
3rd to 10th chain (60 to 300 m) " 5.20 30 M 5.20
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 51.05 300 M 51.05
1st Km Km 49.95
2nd Km Km 22.95
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
3rd Km Km 17.00
1st mile Mile 80.35
4th Km Km 11.40
2nd mile " 18.30
5th Km Km 10.45
3rd mile " 16.40
6th Km Km 10.25
4th mile " 14.75
7th Km Km 9.45
5th mile " 13.50
8th Km Km 9.20
6th mile " 12.40
9th Km Km 8.55
7th mile and subsequent miles " 7.55
10th Km Km 7.75
11th Km & subsequent Kms Km 6.30
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
3rd Km
1st mile Mile 173.05 Km 36.60
4th
2ndKm
mile 39.40 Km 24.55
5th
3rd Km
mile 35.30 Km 22.50
6th Km
4th mile 31.80 Km 22.05
7th
5th Km
mile 29.05 Km 20.20
8th
6th Km
mile 26.75 Km 19.95
9th
7th Km
mile and subsequent miles 16.30 Km 18.45
10th Km Km 16.90
11th Km & subsequent Kms Km 13.45
22 Hand shunting loaded Railway wagons or
trucks:-
a) upto ¼ mile / ¼ Km Each 363.60 Each 227.25
b) upto ½ mile / ½ Km No 658.20 No 411.40
c) upto ¾ mile / ¾ Km " 888.65 " 555.40
d) upto 1 (1.6 Km) mile " 1057.45 " 660.90
e) 2nd mile and subsequent miles/ Each Each
2nd and subsequent kilometres No/Mile 605.20 No/Km 378.25
23 Hand shunting empty Railway wagons or trucks.
Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
1 Loading or unloading into or from Railway wagons, lead 100 Cft. 792.00 cu.m 279.75
within one chain, (30m) shingle, sand, ballast, surkhi, ashes,
kankar, brick bats, coal, lime or 1,000 Nos. tiles size
12"x6"x2" (300x150x50 mm) or 9"x4½"x1½"
(225x113x37mm) properly laid & stacked.
a) Bricks 10" (250 mm) size. 1000 Nos. 990.00 1000 Nos. 990.00
b) Bricks 9" (225 mm) or smaller size. ditto 792.00 ditto 792.00
3 Loading or unloading into or from Railway wagons cement 100 Bags 990.00 100 Bags 990.00
in bags (from inside or outside the godown) and stacking
within one chain (30 m)
4 Loading or unloading into or from Railway wagons empty 100 Nos. 95.05 100 Nos. 95.05
cement bags (from inside or outside the godown) and
stacking.
5 Loading or unloading into or from Railway wagons (from 100 Mds. 594.00 100 Kg 15.90
inside or outside the godown) and stacking, white lime in
bags.
6 Loading or unloading into or from Railway wagons Per 475.20 Per 467.70
Structural Steel, R.S. joists, broad, narrow or meter gauge Tonne Tonne
rail and rail fastenings, etc.
7 Loading or unloading 45 gallon (204.57 Litres) drums full Each 59.40 Each 59.40
into or from Railway wagons, lead upto one chain.
8 Loading or unloading packages of all sorts, upto one Cwt Each 29.70 Each 29.70 Except cement in jute or
(50 Kg). paper bags.
9 Loading or unloading sleepers other than wooden,
including stacking lead within one chain:-
b) Metre gauge and narrow gauge sleepers. ditto 990.00 ditto 990.00
Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
10 Loading or unloading timber logs or timber for shuttering, Per 247.5 Per 243.6
into or from Railway wagons of any gauge, including Ton Tonne
stacking lead within one chain (30 m)
11 Loading or unloading bhoosa in Railway wagons lead upto 100 Mds. 2376 100 Kg 63.65
150 ft. (45 m)
12 Loading or unloading timber scrap or wooden plugs, into or Per 396.00 Per 389.75
from Railway wagons, and stacking within one chain lead. Ton Tonne
13 Loading or unloading pitching stone or spawl from Railway 100 Cft. 293.05 cu.m 103.50
wagons of any gauge (including clearing 5 ft. (1500 mm)
away from the rail).
14 Loading or unloading building stone (including clearing 5 ft. 100 Cft. 380.15 cu.m 134.25
(1.5 m) away from rails).
a) Crude oil (to be pumped from tank wagon into tank). 1000 990.00 100 21.80
Gallon litres
c) Crude oil materials from railway wagons. 100 Cft. 126.70 cu.m 44.75
d) Fuel oil from tank into empty drums, including Per 352.00 Per 346.45
stacking within one chain (30 m). Ton Tonne
e) Petrol (2 gallon tin) 100 Nos. 498.95 100 Nos. 498.95 The rate includes checking
and weighing the tins.
f) Kerosene oil (4 gallon tin) 100 Nos. 990.00 100 Nos. 990.00
16 Removing and stacking within one chain
(30 m) lead:
a) Stone, spawl, brick bats, shingle, sand, lime, 100 Cft. 396.00 cu.m 139.85
surkhi, ashes, kankar and coat, etc.
c) Broad gauge wooden sleepers. 100 Nos. 633.6 100 Nos. 633.6
d) Metre gauge or narrow gauge wooden sleepers. 100 Nos. 377.15 100 Nos. 377.15
Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
f) Bridge and crossing timbers, etc. 100 No. 2112.00 100 No. 2112.00
17 Loading into wagons girders, rails, permanent way Per 396.00 Per 389.75
material (except wooden sleepers) iron work, M.S. bars, Ton Tonne
pipes, etc. including lead one chain (30 M) and stacking
inside wagons.
18 Unloading from wagons girders, rails, permanent way Per 226.30 Per 222.70
material (except wooden sleepers) iron work, M.S. bars, Ton Tonne
pipes, etc. lead upto one chain (30 m) but excluding
stacking.
19 Loading into wagons wooden broad gauge sleepers, 100 Nos. 1584.00 100 Nos. 1584.00
including one chain (30 m) lead and stacking,.
20 Unloading wooden broad gauge sleepers from wagons, 100 Nos. 754.30 100 Nos. 754.30
including one chain (30 m) lead and stacking.
21 Loading metre gauge or narrow gauge wooden sleepers, 100 Nos. 792.00 100 Nos. 792.00
including one chain (30 m) lead and stacking inside
wagons.
22 Unloading metre gauge or narrow gauge wooden sleepers, 100 Nos. 416.85 100 Nos. 416.85
including one chain (30 m) lead but excluding stacking.
23 Loading bridge and crossing timbers, including one chain 100 Nos. 3168.00 100 Nos. 3168.00
(30 m) lead and stacking.
24 Unloading bridge and crossing timbers, including one 100 Nos. 1584.00 100 Nos. 1584.00
chain (30 m) lead but excluding stacking.
25 Loading or unloading bitumen, asphalt or tar in drums, into Per 237.60 Per 233.85
or from railway wagons, lead upto one chain (30 m). Ton Tonne
Before the work is let out to be done by tractors, scrapers, etc. deduction ranging between 3% to 6% should be agreed to with the contractors.
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
a) In ashes, sand, soft soil or silt clearance. 1000 Cft. 2,970.00 -- cu.m 104.90 --
b) In ordinary soil. 1000 Cft. 3,564.00 -- cu.m 125.90 --
2 Earthwork excavation in ashes, sand and soft soil or silt 1000 Cft. 4,356.00 -- cu.m 153.85 -- ditto
clearance, undressed lead upto 50 ft (15 metre).
3 Bed clearance and dressing slopes of drains to required ditto The rate is applicable where the earth
sections including the removal of weeds, roots, etc. of the bed to be removed is of the
disposal of excavated materials within 50 ft. (15 metre) lead. type of ordinary soil. When it is silt or
a) Excavated material undressed. 1000 Cft. 5,544.00 -- cu.m 195.80 -- 1 or 2 above, whichever is applicable.
b) Excavated material dressed in the specified manner. 1000 Cft. 6,008.65 -- cu.m 212.25 -- the drains of each category.
5 Earthowrk in ordinary soil for embankments lead upto 100 * 411-1 to The rate includes hire charges of
ft. (30 m), including ploughing and mixing with blade grade 411-13 and machinery, cost of fuel, lubricants, pay
or disc harrow or other suitable equipment, and 301-1 & of driver and cleaner. The rate also
compaction by mechanical means at optimum moisture 202-3 includes clearing and grubbing
content and dressing to designed section, complete in all where necessary.
respects:-
i) 95% to 100% maximum modified AASHO dry density. 1000 Cft. 6,061.45 6,871.95 cu.m 214.10 242.70
ii) 90% maximum modified AASHO dry density. 1000 Cft. 6,061.45 6,744.75 cu.m 214.10 238.25
iii) 85% maximum modified AASHO dry density. 1000 Cft. 6,061.45 6,617.55 cu.m 214.10 233.75
6 Regular excavation dressed. 1000 Cft. 4,113.10 -- cu.m 145.30 -- * 411-2
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
13 Rehandling of earthwork:
a) Lead upto a single throw of Kassi, phaorah or shovel 1000 Cft. 1,980.00 -- cu.m 69.95 -- ditto
b) Upto a lead of 50 ft. (15 m). 1000 Cft. 2,772.00 -- cu.m 97.90 --
14 Rehandling of gravel work or excavated rock, 1000 Cft. 7,920.00 -- cu.m 279.75 -- 17.1 to 17.5
lead upto 50 ft.( 15 m)
i)with surplus earth from foundation, etc. 1000 Cft. 4,039.20 -- cu.m 142.65 --
with new earth excavated from outside,
ii) 1000 Cft. 8,722.55 -- cu.m 308.10 --
lead upto one chain (30 m).
16 Extra for every 50 ft. (15 m) additional lead or part thereof :- This rate shall be applicable upto
1000 ft. total distance, including the
i) for earhtwork soft, ordinary, hard and very hard. 1000 Cft. 85.70 -- cu.m 3.05 -- lead covered in the item of earthwork
ii) for gravel, shingle or rock. 1000 Cft. 101.85 -- cu.m 3.60 --
17 Transportation of earth all types when the total distance, This rate will be paid inaddition to the
including the lead covered in the item of work, is more than rate of earthwork, without deducting
1000 ft. (300 m) the lead covered in the item of
a) upto ¼ mile (400 m). 1000 Cft. 3,488.80 -- cu.m 123.20 -- earthwork
b) for every 330 ft. (100 m) additional lead or part thereof,
beyond ¼ mile (400 m) upto one mile. (1.6 Km.) 1000 Cft. 40.95 -- cu.m 1.45 --
c) for every ¼ mile (400 m) additional lead or part thereof,
beyond one mile (1.6 Km.) upto 5 mile (8 Km). 1000 Cft. 226.50 -- cu.m 8.00 --
d) for every ½ mile (800 m) additional lead
or part thereof, beyond 5 miles (8 Km). 1000 Cft. 208.45 -- cu.m 7.35 --
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
19 Dowel dressing. Per 242.00 -- Metre 7.95 -- ditto This rate is in addition to payment for
Chain dressed earhtwork.
20 a) Dressing slopes of banks or ground surface. 100Sft. 108.25 -- sq.m 11.65 -- ditto To be paid only when exclusively
dressing is done and no earthwork is
carried out in embankment or cutting.
b) Dressing of earthwork (done by machinery or otherwise 100Sft. 189.75 -- sq.m 20.40 -- i) The surface area dressed is to be
and left undressed) to designed section. taken for measurement.
23 Extra for excavation requiring shoring. 1000 Cft. 1,056.00 1,314.70 cu.m 37.30 46.45 17.1 to 17.5 Composite rate includes materials,
i.e. plank, etc.
24 Compaction of earthwork (soft, ordinary or hard soil) :- ditto
a) Mixing, moistening earth to optimum moisture content 1000 Cft. 982.10 -- cu.m 34.70 --
in layers for compaction, etc. complete.
c) Ramming earthwork (all types of soil). 1000 Cft. 1,188.00 -- cu.m 41.95 --
d) Ramming earhtwork behind retaining walls. 1000 Cft. 1,584.00 -- cu.m 55.95 --
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
content in layers, etc. complete: 202-3 machinery, cost of fuel, lubricant, pay
of driver and cleaner, etc.
i) 95% to 100% maximum modified AASHO dry density. 1000 Cft. -- 810.50 cu.m - 28.65
ii) 90% maximum modified AASHO dry density. 1000 Cft. -- 683.30 cu.m - 24.15
iiii) 85% maximum modified AASHO dry density. 1000 Cft. -- 556.10 cu.m - 19.65
26 Extra for wet earthwork. 1000 Cft. 2,772.00 -- cu.m 97.90 - 17.1 to 17.5 That will support a man's weight.
27 Extra for slush or Daldal including dewatering. 1000 Cft. 6,336.00 -- cu.m 223.80 - 17.1 to 17.5 That will not support a man's weight.
29 Earthwork on small rain water drains, along canal banks, 100 Rft. 752.40 -- Metre 24.70 - ditto
roads and plantation drains, dressed, etc. complete.
30 Filling and compacting soil, earth and boulders behind 1000 Cft. 7,128.00 -- cu.m 251.75 -- 17.1 to 17.5
retaining walls (including excavation of soil and lead upto 50
ft.( 15 m).
31 Dag bailing 3" (75 mm) deep. Per mile 3,122.40 -- Per 1940.55 -- ditto Dag bailing for layout of borrow pit, to
Km be done by contractors at their own
cost.
32 Turfing slopes of banks or lawns with grass sods including 100Sft. 1,320.00 -- sq.m 142.05 -- ditto
ploughing, laying, setting and watering (Turf got from within a
distance of 5 miles (8 Km.) and maintenance for 15 days).
a) lead upto a single throw of Kassi, phaora or shovel 1000 Cft. 3,564.00 -- cu.m 125.90 --
(without dressing).
b) upto 50 ft(15 m)lead (including dressing). 1000 Cft. 6,388.80 -- cu.m 225.65 --
a) upto 3½ ft. (1.06 m) depth. Per Mile 9,328.00 -- Per Km. 5830.00 --
b) exceeding 3½ ft. to 5 ft. (1.06 to 1.5 m) depth. Per Mile 13,046.00 -- Per Km. 8153.75 --
c) exceeding 5 ft. to 8 ft. (1.5 to 2.4 m) depth Per Mile 20,350.00 -- Per Km. 12718.75 --
i) upto 3 ft. (0.9 m) depth. Per Acre 1,980.00 -- Per Hect. 4892.70 --
ii) above 3 ft. (0.9 m) depth. Per Acre 3,960.00 -- Per Hect. 9785.35 --
i) in unploughed land:
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
a) from 10.0 ft. to 20.0 ft. (3 to 6 m) wide. Per Chain 1,012.00 -- Metre 33.20 --
b) from 20.1 ft. to 40.0 ft. (6.10 to 12 m) wide. Per Chain 1,364.00 -- Metre 44.75 --
a) from 10.0 ft. to 20.0 ft. (3 to 6 m) wide. Per Chain 1,035.30 -- Metre 33.95 --
b) from 20.1 ft. to 40.0 ft. (6.10 to 12 m) wide. Per Chain 1,387.30 -- Metre 45.50 --
37 Earthwork by boats, including hire of boats:- 17.1 to 17.5 For ordinary soil.
i) Digging and loading into boats, upto 50 ft. (15 m) lead. 1000 Cft. 5,940.00 -- cu.m 209.80 --
ii) Carriage by boats upto 10 chains (300 m). 1000 Cft. 1,484.65 -- cu.m 52.45 --
iii) Extra for every additional one chain (30 m) or part 1000 Cft. 158.40 -- cu.m 5.60 --
thereof beyond 10 chains (300 m).
iv) Unloading earth from boats. 1000 Cft. 2,772.00 -- cu.m 97.90 --
38 Unloading earth from B.G. trucks and clearing 5 ft. (1.5 m) 1000 Cft. 2,376.00 -- cu.m 83.90 -- 17.1 to 17.5
from rail.
39 Earthwork by tramway, digging and loading in trucks, upto 50 1000 Cft. 5,544.00 -- cu.m 195.80 -- 17.1 to 17.5
ft. (15 m) lead.
40 Unloading earth from B.G. trucks and spreading upto 1000 Cft. 4,455.00 -- cu.m 157.35 -- ditto
15 ft. (4.5 m) from rail.
41 Supplying clean and screened river or pit sand within 5 100Cft. 765.60 788.60 cu.m 270.40 278.55 ditto The rate incudes:-
chains (150 m). i) removal of top crust of earth
over burden
ii) royalty to the government or cost
to the private owner.
42 Earthwork excavation in open cutting for sewers and 17.1 to 17.5 The rate does not include back filling
manholes as shown in drawings including shuttering and * * 13.1 & 13.4 after laying of sewer, which is payable
timbering, dressing to correct section and dimensions separately.
according to templates and levels, and removing surface
water, in all types of soil except shingle, gravel and rock:-
If the timbering and shuttering is not
i) 0 ft. to 7.0 ft. (0 to 2.10 m) depth 1000 Cft. 6,492.50 6,925.65 cu.m 229.30 244.60 actually done at site, the composite
ii) 7-01 ft. to 15.0 ft. (2.15 to 4.5 m) depth 1000 Cft. 10,995.60 11,638.55 cu.m 388.35 411.05 rate may be reduced by Rs. 368.20,
iii) above 15.0 ft. (4.5 m) depth 1000 Cft. 14,163.60 14,806.55 cu.m 500.25 522.95 579.60 and 579.60 respectively.
43 Earthwork excavation of trenches in open cutting for sewers 17.1 to 17.5 The rate does not include back filling
and manhole chambers, etc. below sub-soil water level to * * 13.3 & after laying of sewer, which is payable
correct section and dimensions according to templates and 13.5 separately.
levels, including shoring, timbering and shuttering of M.S.
sheets on both sides of the trenches:
i) 0 ft. to 4.0 ft. (0 to 1.20 m) depth below SSWL. 1000 Cft. 9,526.00 12,537.55 cu.m 336.45 442.85
ii) 4.01 ft. to 8.0 ft. (1.22 to 2.4 m) depth below SSWL. 1000 Cft. 11,908.60 15,827.35 cu.m 420.60 559.00
iii) Exceeding 8 ft. (2.4 m) depth below SSWL. 1000 Cft. 17,862.90 22,103.35 cu.m 630.90 780.70
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
44 Excavation of trenches in all kinds of soil, except cutting 1000 Cft. 5,966.40 -- cu.m 210.75 -- 17.1 to 17.5 The rate does not include back filling
rock, for watersupply pipelines upto 5 ft. (1.5 m) depth * * 8.1 after laying of pipe line, which is
from ground level, including trimming, dressing sides, payable separately.
leveling the beds of trenches to correct grade and cutting
pits for joints, etc. complete in all respects.
46 Uprooting stump and removing within 100 ft. (30 m) from 2 ft. Each 1,485.00 -- Each 1485.00
to 6 ft. (600 to 1800 mm) girth.
48 Uprooting Sarkanda growth and disposal within 100 ft. (30 m) 100Sft. 95.05 -- sq.m 10.25 --
* Specification number correspond to Book of "Specification for Road & Bridge Construction, 1971".
** Specification number correspond to Book of "Building & Roads Department Specification Vol. II, 1966 (Public Health Works).
2 The rates for dismantling roofs or upper storey floor, include the dismantling of all materials, except roof
supports such as beams and trusses.
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
Stone Work
2 Dismantling stone masonry in mud mortar. 100Cft. 990.00 cu.m 349.65 ditto
3 Dismantling stone masonry in lime or cement mortar. 100Cft. 2,376.00 cu.m 839.20 ditto Add extra 13%, 32% and 51% on
labour rates only for 2nd, 3rd, 4th
and subsequent floors respectively.
4 a) Dismantling dry stone or spawl pitching. 100Cft. 1,188.00 cu.m 419.60 ditto
b) Dismantling stone or spawl pitching (mud grouted). 100Cft. 1,504.80 cu.m 531.50 ditto
5 Dismantling stone or spawl pitching and apron in silted 100Cft. 1,980.00 cu.m 699.35 ditto
condition.
6 Dismantling stone pitching, cement or lime grouted. 100Cft. 3,168.00 cu.m 1118.95 ditto
8 Dismantling stone ware drain including base concrete. 100Cft. 1,108.80 cu.m 391.65 ditto
Brick Work
10 Dismantling sun dried brick masonry. 100Cft. 990 cu.m 349.65 ditto
12 Dismantling brick work in mud mortar. 100Cft. 1386 cu.m 489.55 18.1 Add extra 13%, 32% and 51% on
labour rates only for 2nd, 3rd, 4th
13 Dismantling brick work in lime or cement mortar. 100Cft. 3366.00 cu.m 1188.85 ditto and subsequent floors respectively
against item No. 12, 13, 14 & 15.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
Concrete
17 Dismantling lime concrete. 100Cft. 2,178.00 cu.m 769.25 Add extra 13%, 32% and 51% on
labour rates only for 2nd, 3rd, 4th
18 Dismantling lime or cement concrete, under water. 100Cft. 8,316.00 cu.m 2937.20 and subsequent floors respectively
against item No. 17, 19 & 20.
Roofing
22 a) Dismantling 1st class tile roofing. 100Sft. 1,188.00 sq.m 127.85 Add extra 13%, 32 and 51% on
labour rate only for 2nd, 3rd, 4th
b) Dismantling 2nd class tile roofing. 100Sft. 990.00 sq.m 106.50 ditto and subsequent floors respectively
against items No. 22, 25, 26 and 28.
23 Dismantling from any height, asbestos sheets and ridge 100Sft. 660.00 sq.m 71.00 18.1
coping.
24 a) Dismantling roof of wooden planks and battens, from 100Sft. 528 sq.m 56.8 ditto
any height.
b) Dismantling wooden ceiling above 20' (6.0 m) height 100Sft. 2,059.20 sq.m 221.55 ditto
in difficult position, including lifting with care and
special scaffolding along live electric wires and with
machines underneath.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
25 Dismantling jack arch roofing, including removal of joists. 100Sft. 1,584.00 sq.m 170.45 ditto
26 Dismantling R.B. roof complete with mud and plaster, 100Sft. 1,980.00 sq.m 213.05 ditto
including separating reinforcement, cleaning and
straightening the same.
27 a) Stripping and stacking slate or tiles from the truss 100Sft. 990.00 sq.m 106.50
roofing.
b) Stripping and stacking C.I. sheet roof. ditto 918.70 ditto 98.85
c) Extra for dismantling C.I. sheet roof above 20 ft. (6m) ditto 1,254.00 ditto 134.95
in difficult position, including lifting with special
scaffolding along live electric wire with machine
underneath.
28 Dismantling slates or tiles including battens, purlins and 100Sft. 1,584.00 sq.m 170.45 18.1
planking.
Flooring
29 Dismantling brick or flagged flooring without 100Sft. 673.20 sq.m 72.45 18.1 Add extra 13%, 32% and 51% on
concrete foundation. labour rates only for 2nd, 3rd, 4th
and subsequent floors respectively
30 Dismantling plank or wooden block flooring, 100Sft. 990.00 sq.m 106.50 ditto against items No. 29 and 30.
etc.
31 Disjoining R.C.C. pipes inside the trench and dismantling i) The rate does not include the
and removing the pipes from the trench and stacking them cost of excavation and refilling of
outside:- trench, or the demolition of any
masonry or brick work.
a) 6" to 12" (150 to 300 mm) diameter Per Lft 26.40 Metre 86.60
b) 13" to 24" (325 to 600 mm) diameter Per Lft 42.25 Metre 138.60 ii) Bends, elbows, sluice valves,
c) 25" to 36" (625 to 900 mm) diameter ditto 49.50 ditto 162.35 etc. should not be paid for extra if
d) Above 36" (Above 900 mm) diameter ditto 70.40 ditto 230.90 fixed in the length of pipe line that
is being dismantled.
WOOD WORK
32 a) Removing door with chowkat. Per 346.50 Per 346.50 18.1 Add extra 13%, 32% and 51% on
No. No. labour rates only for 2nd, 3rd, 4th
b) Removing windows and sky lights with chowkat. ditto 270.60 ditto 270.60 and subsequent floors respectively
against items No. 32, 33, 34, 35 &
36.
33 Removing ventilators and wooden sunshade, etc. Per No. 141.90 Per No. 141.90 ditto
34 a) Dismantling wooden beams upto 12' (3.65m) Per No. 247.50 Per No. 247.50 ditto
length.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
b) Dismantling wooden beams from 12.1' to 23' ditto 396.00 ditto 396.00
(3.65 to 7.0 m) length.
35 a) Dismantling wooden partition Jaffry work etc. 100Sft. 471.45 sq.m 50.75 ditto
36 Dismantling wooden palisade fencing. Per Lft. 38.50 Metre 126.30 ditto
I ron work
37 Dismantling iron work of trusses, sheds, water tanks, etc. 100Kg 1,407.40 %Kg 1407.40 18.1 Add extra 13%, 32% and 51% on
excluding cutting of rivets. labour rates only for 2nd, 3rd, 4th
and subsequent floors respectively
against items No. 37 and 38.
38 Dismantling rolled steel beams or iron rails, etc. 100Kg 649.95 %Kg 649.95 ditto
39 Dismantling iron latrine. Per Unit/ 1,518.00 Per Unit/ 1518.00 ditto
2 Seats 2 Seats
40 Dismantling tees, bends or sluice valves upto 12" Each per 32.10 Each per 12.85 ditto
(300 mm) bore. inch bore cm bore
b) Dismantling M.G. or N.G. water column. Each 6,600.00 Each 6600.00 ditto
42 Dismantling all type of wire fencing, including rolling wire 100Lft. 673.20 Metre 22.10 18.1
into bundles and collecting material.
M iscellaneous
43 Dismantling wire netting of tennis courts and frame work. 100Sft. 316.80 sq.m 34.10 18.1
44 Dismantling cloth ceiling and supporting timber. 100Sft. 594.00 sq.m 63.90 ditto
45 Dismantling and removing road metalling. 100Cft. 1,584.00 cu.m 559.45 ditto
46 Dismantling and removing road pavement, etc., including 100Cft. 2,114.65 cu.m 746.90 ditto
screening and stacking of byproducts upto one chain lead
(30 metre).
47 Removing mud plaster from walls. 100Sft. 165.00 sq.m 17.75 ditto Add extra 13%, 32% and 51% on
labour rates only for 2nd, 3rd, 4th
48 Removing cement or lime plaster. 100Sft. 330.00 sq.m 35.50 ditto and subsequent floors against item
No. 47, 48, 49, & 50 respectively
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
49 Scraping:- 18.1
50 Dismantling glazed or encaustic tiles, etc. 100Sft. 1,848.00 sq.m 198.85 18.1
52 Cleaning lime or cement mortar of old stones 100Cft. 1,386.00 cu.m 489.55 18.1
to be used in masonry.
Electric Wiring
53 Dismantling light, fan and call bell point Per 60.50 61.05 Per 60.50 61.05
including casing and capping/strip open type, point point
and making good damaged surface (building
portion).
54 Dismantling plug point and making good Per 51.85 52.30 Per 51.85 52.30
damaged surface (building portion). point point
3 Lime : Sand
1 : 2 43 86 0.43 0.86
1 : 3 31 93 0.31 0.93
5 Lime : Surkhi
2 : 3 49.00 - 73.5 - 0.49 - 0.74 -
1 : 2 40.75 - 81.5 - 0.41 - 0.82 -
1 : 3 30.30 - 91.0 - 0.30 - 0.91 -
7 Lime : Cinder
1 : 1 57.0 - 57.0 - 0.57 - - 0.57
Wet material required for 100 Cft. Wet material required for 1M³ (35.32 Cft)
masonry (including wastage): masonry ( including wastage) :
1 Brick M asonry :
a) Mud Mortar 35.00 Cft 0.35 M3
b) Cement, Sand 25.00 Cft 0.25 M3
c) Cement, Lime (Putty) Sand 25.00 Cft 0.25 M3
d) Lime (Putty) Sand 25.00 Cft 0.25 M3
2 Stone M asonry :
a) Random rubble, uncoursed
i) Foundation and Plinth 45.00 Cft 0.45 M3
ii) Superstructure 40.00 Cft 0.40 M3
iii) Coursed 35.00 Cft 0.35 M3
b) Ashlar Block in course or Scabled masonry 30.00 Cft 0.30 M3
c) Ashlar fine masonry 20.00 Cft 0.20 M3
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
1 Mud concrete in foundation including watering and ramming, 100Cft 4395.60 7014.60 cu.m 1552.55 2477.55 The stone ballast, crushed bajri,
using brick or stone ballast 1½" (40 mm) gauge. round shingle from nallah, or brick
ballast may be used according to
2 Dry rammed brick or stone ballast, 1½" to 2"( 40 mm to 50 100Cft 2970.00 5478.00 cu.m 1049.00 1934.85 their comparative cheaper rates in
mm) gauge. various areas of the Province.
3 Cement concrete brick or stone ballast 1½ " to 2" (40 mm to 20.1 -do-
50 mm) gauge, in foundation and plinth:-
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
6 Providing and laying reinforced cement concrete (including 20.4 1) The rate includes rendering floor
prestressed concrete), using coarse sand and screened surface smooth, and the plastering
graded and washed aggregate, in required shape and design, done for making up all surfaces
including forms, moulds, shuttering, lifting, compacting, after removing centring.
curing, rendering and finishing exposed surface, complete
(but excluding the cost of steel reinforcement, its fabrication 2) Plastering done under soffit of
and placing in position, etc.):- R.C.C. roof slab meant for human
habitation buildings shall be paid
(a) (i) Reinforced cement concrete in roof slab, beams, extra.
columns lintels, girders and other structural members laid in
situ or precast laid in position, or prestressed members cast 3) This item shall not be applicable
in situ, complete in all respects:- to factory made units.
(1) Type A (nominal mix 1:1:2) Per Cft 186.10 504.20 cu.m 6573.05 17808.35 4) Composite rate shall be reduced by Rs:
(2) Type B (nominal mix 1: 1½: 3) ditto 186.10 442.90 " 6573.05 15643.25 5/50- P.Cft & Rs:12/- P.Cft if chenab sand
and local sand respectively is used.
(3) (c) Type C (nominal mix 1: 2: 4) ditto 186.10 409.95 " 6573.05 14479.45
(a)(ii) Reinforced cement concrete in slab of rafts / strip
foundation, base slab of column and retaining walls; etc and
other structural members other than those mentioned in
5(a) (i) above not requiring form work (i.e. horizental
shuttering) complete in all respects:-
(1) Type A (nominal mix 1: 1: 2) Per Cft 109.55 395.35 cu.m 3869.30 13963.75
(2) Type B (nominal mix 1: 1½: 3) ditto 109.55 329.00 " 3869.30 11620.30
(3) Type C (nominal mix 1: 2: 4) ditto 109.55 295.95 " 3869.30 10452.95
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
(d) Add extra labour for R.C. concrete in Per Cft 29.70 -- cu.m 1049.00 -
2nd and subsequent storeys.
7 Providing and casting in situ bored reinforced concrete piles * 851-1 Composite rate shall be reduced by
with type C concrete (nominal mix 1: 2: 4 ) , using 10% extra to Rs: 5/50 P.Cft & Rs:12/- P.Cft if chenab
cement in dry mix, and course sand, including all labour and 851-10 sand and local sand respectively is used.
material (except the cost of steel reinforcement and its
labour for bending and laying in position, etc. which will be
paid separately, including, screening & washing of shingle
and curing:-
i) 18 " (450 mm) dia pile Per Rft 902.55 1252.25 Metre 2960.35 4107.40
ii) 20" (500 mm) dia pile Per Rft 1091.95 1523.45 Metre 3581.60 4996.90
iii) 22" (550 mm) dia pile Per Rft 1349.85 1856.55 Metre 4427.50 6089.50
iv) 24" (600 mm) dia pile Per Rft 1735.45 2357.05 Metre 5692.30 7731.15
7(a) Providing and casting in situ bored reinforced concrete piles with specified
type of concrete using course sand, including all labour and materials,
boring, rig machine, crane, excavator, welding plant, batching plant, transit If percussion boring is used based on the bore
mixer, I-Land etc (except the cost of steel reinforcement, its labor for log/strata, derive rate accordingly with the
bending and laying in position and boat plateform etc) which will be paid permission of Superintending Engineer.
separately, including, screening & washing of shingle and curing as
approved by Engineer Incharge:- In Ordinary Soil
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
(v) 1.07 m / 42 inch Per Rft. 1921.85 3670.05 Meter 6303.60 12037.70
(vi) 1.22 m / 48 inch Per Rft. 2036.35 4319.70 Meter 6679.20 14168.65
(vii) 1.37 m / 54 inch Per Rft. 2156.60 5046.45 Meter 7073.60 16552.45
(viii) 1.52 m / 60 inch Per Rft. 3139.05 6706.85 Meter 10296.15 21998.45
(ix) 1.68 m / 66 inch Per Rft. 3506.50 7823.50 Meter 11501.30 25661.05
(x) 1.83 m / 72 inch Per Rft. 3770.85 8908.45 Meter 12368.35 29219.65
(xi) 1.98 m / 78 inch Per Rft. 4046.20 10075.20 Meter 13271.55 33046.60
(xii) 2.13 m / 84 inch Per Rft. 4534.65 11527.45 Meter 14873.60 37810.10
(b) Type-B Concrete (1:1-1/2:3)
(i) 0.46 m / 18 inch Per Rft. 595.85 973.60 Meter 1954.35 3193.45
(ii) 0.51 m / 20 inch Per Rft. 632.45 1098.70 Meter 2074.45 3603.65
(iii) 0.56 m / 22 inch Per Rft. 697.55 1263.80 Meter 2287.90 4145.25
(iv) 0.61 m / 24 inch Per Rft. 762.45 1433.80 Meter 2500.85 4702.85
(iii) 0.76 m / 30 inch Per Rft. 1054.10 2103.50 Meter 3457.40 6899.40
(iv) 0.91 m / 36 inch Per Rft. 1556.05 3067.15 Meter 5103.80 10060.30
(v) 1.07 m / 42 inch Per Rft. 1872.60 3929.40 Meter 6142.05 12888.45
(vi) 1.22 m / 48 inch Per Rft. 2036.35 4722.80 Meter 6679.20 15490.80
(vii) 1.37 m / 54 inch Per Rft. 2156.60 5556.65 Meter 7073.60 18225.75
(viii) 1.52 m / 60 inch Per Rft. 3139.05 7336.70 Meter 10296.15 24064.30
(ix) 1.68 m / 66 inch Per Rft. 3506.50 8585.60 Meter 11501.30 28160.75
(x) 1.83 m / 72 inch Per Rft. 3770.85 9815.40 Meter 12368.35 32194.45
(xi) 1.98 m / 78 inch Per Rft. 4046.20 10075.20 Meter 13271.55 33046.60
(xii) 2.13 m / 84 inch Per Rft. 4534.65 12761.95 Meter 14873.60 41859.10
8 Fabrication of mild steel reinforcement bar cage for R.C.C. * 851-5 The rate includes wastage, overlaps,
bored piles, including cutting, bending, laying in position, etc. but does not apply to the laps and
welding and fastening, including cost of binding wire and spiral reinforcement which are specifically
labour charges for binding of steel reinforcement (also shown in the structural / working drawings
includes removal of rust from the bars):- of piles as per lapping requirements
of design.
(a) plain bars Per Cwt. 2145.00 9911.60 100 kg 4222.45 19511.00
(b) deformed bars ditto 2145.00 11133.10 " 4222.45 21915.55
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
10 Precast cement concrete solid or face blocks (1:2:4), Per Cft 73.25 236.35 cu.m 2587.20 8347.90 20.2
including cost of templates.
11 Precast cement concrete hollow blocks (1: 2: 4) , including Per Cft 161.05 267.90 cu.m 5688.30 9462.25 20.2
cost of templates and constructing walls thereof.
12 Providing and fixing ornamental cement jali 2" (50 mm) thick Per Sft 46.20 73.80 sq.m 497.10 794.10 20.1 to
(1: 2: 4), without steel. 20.4
(a) above 20' (6 m) upto 40'(12 m) height 100Cft 3168.00 - cu.m 1118.95 -
(b) for every additional 10'(3 m) height. 100Cft 1980.00 - cu.m 699.35 -
14 Extra labour for work of weirs, rail or road bridges, syphons, and 100Cft 792.00 - cu.m 279.75 -
concreting in superstructure
15 Making reinforced cement concrete spout, including fixing in Each 577.50 797.20 Each 577.50 797.20 20.4
position (2½' x 6" x5") (760 mmx150 mm x 125 mm)
16 Making holes upto 3"(75 mm) dia 18"(450 mm) depth in cement Per hole 1386.00 - Each 1386.00 - 20.1
concrete or stone masonry walls and repairing.
17 Extra labour for skipping concrete in wells. 100Cft 4840.00 - cu.m 1709.50 - 20.1
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
20 Fabrication of high tensile steel prestressing cables for 100 Kg. 7127.85 51283.15 100 Kg. 7127.85 51283.15 * 811-1 The rate includes wastage in
prestressed (post tensioned) concrete, including assembling by to cutting and breakage in stressing,
drawing the H.T. wire through metal spacer plate, inserting in helix 811-11 etc.
core and taping or tying, sheathing in longitudinally welded metal
corrugated sheath, positioning , anchorage with male and female
set of anchorage cone, forming ducts for transverse cable,
stressing cables with jack at both ends as per stressing schedule,
maintaining stressing record and supply the same in the approved
proforma to the Engineer-in-charge, making loop at blind end,
including all materials required for it, grouting the cable ducts with
cement, cutting projected ends and making good recesses, etc.,
complete in all respects.
21 Fabrication of High Tensile steel reinforcement for prestressed 100kg 4224.00 48864.80 %kg 4224.00 48864.80 1) The rate includes wastage in
(pretension) concrete work, including inserting wire in moulds, cutting and breakage in stressing,etc.
providing M.S. shear bars, spacers and lift hooks, male and
female anchorage, tie down, struts, stressing cables, maintaining 2) Quantity of H. T. wire will form
stress record and supply the same in approved proforma to the basis of payment.
Engineer-in-charge, cutting wires and projecting ends and making 3) This item shall not be applicable
good recesses, etc., complete in all respects. to factory made units.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
23 Providing and laying foam concrete 3 inch (75 mm) thick, Per Sft. 44.55 86.90 sq.m. 479.35 935.05
using cement sand in the ratio of 1:2 and aluminium powder
at the rate of 0.2% of the cement, sand mix,
i) aluminium sheet 1/16 in(1.5 mm) thick Per Rft. 24.10 101.70 Metre 79.05 333.60
ii) G.I. sheet, 18 SWG Per Rft. 24.65 110.30 Metre 80.85 361.80
25 Providing and fixing 1/8" (3 mm) thick 3" (75 mm) wide aluminium
strip on horizontal and vertical expansion joints in walls, columns,
ceilings and floors etc., including cost of clips/screws etc.,
complete in all respects:-
a) On interior surface (without mastic strip) Per Rft. 22.00 99.65 Metre 72.15 326.85
b) On exterior surface (with mastic strip) ditto 22.00 103.25 " 72.15 338.65
26 Providing and fixing 1/16" (1.5 mm) thick copper flashing on Per Sft. 23.10 113.70 Sq.m 248.55 1223.40
expansion joints complete in all respects.
27 Providing and fixing 6 in (150 mm). wideG.I. sheet 18SWG. Per Rft. 8.15 88.15 Metre 26.75 289.15
stopper to expansion joint.
28 Providing embeding 10" (250 mm) wide ¼" (6 mm) thick Per Rft. 33.00 213.00 Metre 108.25 698.60
rubber water stopper in expansion joints of R.C.C. roof
slab complete in all respects.
29 Filling expansion joints with bitumen. sand & saw dust in Per Rft P.Metre/
ratio 1:2:2. per inch 4.95 23.90 Per 25 mm 16.25 78.40
width Width
30 Filling expansion joints with bitumen. Per Rft. 85.80 - Metre 281.40 -
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
31 Laying asphaltic mixture in expansion joints. Per Rft. 69.30 - Metre 227.30 - Material to be paid on actuals.
a) 1" (25 mm) thick thermopore sheet Per Sft. 9.25 14.75 Sq.m 99.55 158.70
b) 1½" (40 mm) thick thermopore sheet ditto 9.25 18.60 " 99.55 200.15
(a) with one coat bitumen and one coat polythene sheet
500gauge
i) 1½" thick (40 mm) 100Sft 2068.00 5731.70 sq.m 222.50 616.75
ii) 2" thick (50 mm) 100Sft 2068.00 6349.05 sq.m 222.50 683.15
iii) 3" thick (75 mm) 100Sft 2156.00 7790.05 sq.m 232.00 838.20
i) 1½" thick (40 mm) 100Sft 2068.00 6127.70 sq.m 222.50 659.35
ii) 2" thick (50 mm) 100Sft 2068.00 6744.30 sq.m 222.50 725.70
iii) 3" thick (75 mm) 100Sft 2156.00 8185.30 sq.m 232.00 880.75
(a) with one coat of bitumen and one coat of polythene sheet
500 gauge :-
i) Ratio 1: 4
a) ½" thick (13 mm) 100Sft 1936.00 3998.20 sq.m 208.30 430.20
b) ¾" thick (20 mm) 100Sft 1936.00 4324.85 sq.m 208.30 465.35
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
i) Ratio 1: 4
a) ½" thick (13 mm) 100Sft 1936.00 4205.85 sq.m 208.30 452.55
b) ¾" thick (20 mm) 100Sft 1936.00 4532.85 sq.m 208.30 487.75
(a) with one coat of bitumen and one coat of polythene sheet
500 gauge:
i) Ratio 1: 4
a) ½" thick (13 mm) 100Sft 1936.00 3871.40 sq.m 208.30 416.55
b) ¾" thick (20 mm) 100Sft 1936.00 4198.70 sq.m 208.30 451.80
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
i) Ratio 1: 4
a) ½" thick (13 mm) 100Sft 1936.00 4205.70 sq.m 208.30 452.55
b) ¾" thick (20 mm) 100Sft 1936.00 4532.85 sq.m 208.30 487.75
36 Grouting concrete between, the grooves of gates, including 100Cft 9306.00 - cu.m. 3286.90 -
shuttering.
37 Chiesel dressing concrete surface on sides of grooves. 100Sft 290.40 - sq.m 31.25 -
38 Laying and ramming dry ballast or kankar. 100Cft 3217.50 - cu.m 1136.40 -
39 Hoisting and placing in position R.C.C. shelves. per No. 103.15 - per No. 103.15 -
41 Supplying and fixing broken glasses on court yard walls, Per Rft 77.50 126.20 metre 254.20 413.95
including 1:3: 6 cement concrete coping.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
42 Crushing stone ballast by machine. 100Cft 2475.00 - cu.m. 874.15 - This does not include the charges
for working of crushers, but includes
manual labour for carriageof stone to
crusher within three chains (90 m)
and also stacking the product after
crushing within three chains (90 m).
43 Breaking stone ballast screened and stacked:-
44 Screening and stacking stone ballast shingle or bajri, etc. 100Cft. 792.00 - cu.m. 279.75 -
47 Extra for Kentledge and loading arangements for test pile to ensure Per Cwt. 0.80 22.00 Per M.Ton 17.35 484.75
structural and Geotechnical soundness of pile upto a maximum test load
applying in stages i/c the hiring of machinary required for complete job
and furnishing a report in this regard by a qualified/authorized Geo
Technical Engineer by studying the data of at least seven days as approved
and directed by the Engineer Incharge.
48 Making Temporary floating plateform comprising of required Nos. of Each 6930.00 61746.00 Each 6930.00 61746.00
unifloats in running water / pond to place machinery, manpower and
proper access complete in all respect as approved and directed by the
Engineer Incharge.
49 Providing and fixing precast Edge Kerb Stone (4"to 6" thick), of 3500 PSI * 1203-1
Compressive Strength, embeded in PCC 1:2:4 over lean concrete 1:4:8 etc to
complete in all respect. 1203-3
a) Without Painting
(i) 14" high Per Rft 84.80 286.20 Meter 278.10 938.80
(ii) 18" high Per Rft 87.35 294.35 Meter 286.55 965.45
b) With Painting
(i) 14" high Per Rft 107.75 323.60 Meter 353.35 1061.35
(ii) 18" high Per Rft 110.30 331.70 Meter 361.85 1088.05
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
50 Providing & fixing precast Edge Kerb Stone (4" to 6" thick) and 14" high
of Compressive Strength of 3500 PSI laid in cement sand mortar (1:3) over
pre-laid brick masonary for drain cum footpath etc complete in all respect.
(i) Without painting Per Rft 71.10 219.70 Meter 233.25 720.70
(ii) With painting Per Rft 94.05 257.10 Meter 308.50 843.25
51 Providing and laying Kerb Block / RCC Barrier of Concrete having
compressive strength of 4000 PSI ratio (1:1.25:2.25) of required size, over
Lean Concrete of (1:4:8), with Slip form Paver / power kerber machine, If batching plant is not used, reduce rate for
batching plant, excluding the cost of additive / super plasticizer, steel Rs.35/- P.Cft or Rs.1236/- P.Cu.m.
reinforcement and its labour for bending and laying in position as specified
etc complete in all respect.
a) Kerb Block Per Cft 64.25 311.35 Cu.m 2268.60 10996.90
b) R.C.C Barrier
(i) Single Face Per Cft 51.45 298.55 Cu.m 1816.85 10545.15
(ii) Double Face Per Cft 52.75 299.85 Cu.m 1862.80 10591.05
52 Providing and mixing super plasticizer (water reducing admixture) as
defined in ASTM C-94 in order to achieve the required consistancy /
The use of Super Plasticizer will be subject to
workablility measured by the slump, used in the ratio of (0.05% to 1.00%) Per Gallon 10.50 528.75 Per Ltr. 2.30 116.30
the permission of Superintending Engineer.
by weight of cement as proposed by the designer etc complete in all
respect.
Specification numbers correspond to book of standard specification of Road and Bridge Construction, "1971"
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
1 Pacca brick work in mud mortar in buildings: 21.1 Masonry of boundary wall to be
to considered as masonry other than
i) in foundation and plinth 100Cft. 4087.25 22144.55 cu.m 1443.60 7821.45 21.4 building.
ii) in ground floor ditto 5407.25 23464.55 ditto 1909.85 8287.70
The composite rate is to be
reduced by 7% and 14%, if 2nd or
3rd class bricks are used.
2 Add extra labour on item No. 1 for brick work in:-
3 Pacca brick work in mud mortar other than building:- 21.1 to Same remarks as against
21.4 item No. 1 above
i) upto 20 ft. (6.1 m) height 100Cft. 5558.80 23616.10 cu.m 1963.35 8341.20
ii) extra labour for every 5 ft. (1.5 m) ditto 1056.00 -- ditto 373.00 -
additional height, or part thereof.
4 Pacca brick work in foundation and plinth in:- ditto Same remarks as against
item No. 1 above.
i) Cement, sand mortar:-
ii) lime, cement sand mortar:- 21.1 The rate of lime mortar also
includes grinding of mortar.
Ratio 1:1:6 100Cft. 5382.95 26340.15 cu.m 1901.20 9303.35
Ratio 1:1:7 ditto 5382.95 26052.85 ditto 1901.20 9201.85
Ratio 1:1:8 ditto 5382.95 25820.25 ditto 1901.20 9119.70
Ratio 1:1:9 ditto 5382.95 25625.30 ditto 1901.20 9050.85
Ratio 1:1:10 ditto 5382.95 25479.20 ditto 1901.20 8999.25
iii) lime, sand mortar 1:2 100Cft. 5382.95 24849.85 cu.m 1901.2 8776.95 ditto ditto
chapter-7(Brickwork).xls Page 53
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
ii) lime, cement, sand mortar:- The rate of lime mortar also
includes grinding of mortar.
Ratio 1:1:6 100Cft. 7098.95 28056.15 cu.m 2507.35 9909.45
Ratio 1:1:7 ditto 7098.95 27771.55 ditto 2507.35 9808.90
Ratio 1:1:8 ditto 7098.95 27536.25 ditto 2507.35 9725.80
Ratio 1:1:9 ditto 7098.95 27341.30 ditto 2507.35 9656.95
Ratio 1:1:10 ditto 7098.95 27195.65 ditto 2507.35 9605.50
iii) lime, sand mortar 1:2 100Cft. 7098.95 26565.85 cu.m 2507.35 9383.05 The rate of lime mortar also
includes grinding of mortar.
7 Pacca brick work other than building upto 10ft. (3 m) 21.1 i) The composite rate is to be
height. to reduced by 7% and 14%, if 2nd or
21.5 3rd class bricks are used.
i) cement, sand mortar:-
ii) Workshops, godowns,, bins,
Ratio 1:2 100Cft. 6230.40 30146.40 cu.m 2200.60 10647.70 house type godowns, reservoirs,
Ratio 1:3 ditto 6230.40 28748.40 ditto 2200.60 10153.95 filter beds, storage tanks, wells,
Ratio 1:4 ditto 6230.40 27909.60 ditto 2200.60 9857.65 screening chambers, collecting
Ratio 1:5 ditto 6230.40 27350.40 ditto 2200.60 9660.15 tanks, manholes etc. are to be
Ratio 1:6 ditto 6230.40 26930.15 ditto 2200.60 9511.75 treated as masonry other than
Ratio 1:7 ditto 6230.40 26655.60 ditto 2200.60 9414.75 buildings.
Ratio 1:8 ditto 6230.40 26413.65 ditto 2200.60 9329.30
ii) lime, cement, sand mortar:- The rate of lime mortar also
includes grinding of mortar.
Ratio 1:1:6 100Cft. 6230.40 27187.60 cu.m 2200.60 9602.65
Ratio 1:1:7 ditto 6230.40 26900.30 ditto 2200.60 9501.20
chapter-7(Brickwork).xls Page 54
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
iii) lime, sand mortar 1:2 100Cft. 6230.40 25697.30 cu.m 2200.60 9076.30 ditto
8 Add extra labour on item No. 7, for every 10ft.(3 m) 100Cft. 1056.00 -- cu.m 373.00 -
additional height, or part thereof.
9 Extra labour for arch work in brick masonry, including 100Cft. 1980.00 -- cu.m 699.35 - 21.5
labour for centring and decentring.
10 Extra for pacca brick work in steining of wells or any other 100Cft. 1320.00 2402.40 cu.m 466.20 848.55 21.1 The composite rate is to be
circular masonry. to reduced by 7% and 14%, if 2nd or
21.4 3rd class bricks are used.
11 Extra labour for profile and flared walls. 100Cft. 454.10 -- cu.m 160.40 -
13 Extra for face work (half brick thick) using special bricks 100Cft. 986.60 cu.m 348.45 This item is to be executed only
instead of first class bricks. under the written permission of
Superintending Engineer.
14 Reinforced brick work in lintel of openings, laid in 1:3 Per Cft. 177.30 397.80 cu.m 6262.30 14050.30
cement mortar, including all labour, material, forms,
moulds, lifting & shuttering, etc, (but excluding cost and
labour of steel reinforcement which shall be paid for
separately).
16 Perforated pacca brick walling half brick thick, in ground 21.1 The composite rate is to be
floors:- to reduced by 7% and 14%, if 2nd or
21.4 3rd class bricks are used.
i) mud mortar 100 Sft. 2699.65 7220.60 Sqm. 290.50 776.95
chapter-7(Brickwork).xls Page 55
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
iii) lime, cement sand mortar The rate of lime mortar also
includes grinding of mortar.
Ratio 1:1:6 100Sft. 3557.65 8803.55 sq.m 382.80 947.25
Ratio 1:1:7 100Sft. 3557.65 8730.20 sq.m 382.80 939.35
Ratio 1:1:8 100Sft. 3557.65 8676.30 sq.m 382.80 933.55
Ratio 1:1:9 100Sft. 3557.65 8623.95 sq.m 382.80 927.95
Ratio 1:1:10 100Sft. 3557.65 8593.20 sq.m 382.80 924.65
iv) lime, sand mortar 1:2 100Sft. 3557.65 8427.45 sq.m 382.80 906.80 ditto
17 Add extra labour on item No. 16 for pacca brick work in:-
18 Perforated pacca brick walling one brick thick, in ground 21.1 The composite rate is to be
floor: to reduced by 7% and 14%, if 2nd or
21.4 3rd class bricks are used.
i) mud mortar 100Sft. 3793.70 12822.35 sq.m 408.20 1379.70
iii) lime, cement, sand mortar:- The rate of lime mortar also
Ratio 1:1:6 100Sft. 5346.00 15824.60 sq.m 575.25 1702.75 includes grinding of mortar
Ratio 1:1:7 ditto 5346.00 15677.35 ditto 575.25 1686.90
Ratio 1:1:8 ditto 5346.00 15564.70 ditto 575.25 1674.75
Ratio 1:1:9 ditto 5346.00 15467.15 ditto 575.25 1664.25
Ratio 1:1:10 ditto 5346.00 15395.50 ditto 575.25 1656.55
iv) lime, sand mortar 1:2 100Sft. 5346.00 15078.25 sq.m 575.25 1622.40 ditto
chapter-7(Brickwork).xls Page 56
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
ii) Extra for every 5 ft. (1.5 m) additional height, or part 100Cft. 1056.00 -- ditto 373.00 - A&C No.I dated 2.9.1998
thereof.
i) 4½" (113 mm) thick walling with hoop iron, bonding 6" 100Sft. 3019.50 12734.90 sq.m 324.90 1370.30
(150 mm) apart.
ii) 4½" (113 mm) thick walling with hoop iron, bonding 100Sft. 2706.00 11968.10 sq.m 291.15 1287.75
12" (300 mm) apart.
iii) 3" (75 mm) thick walling with hoop iron, bonding 6" ditto 2389.20 9320.60 ditto 257.10 1002.90
(150 mm) apart.
iv) 3" (75 mm) thick walling with hoop iron, bonding 12" ditto 1911.35 8339.25 ditto 205.65 897.30
(300 mm) apart.
22 Ghilafi work (1½ brick thick wall) 100Cft. 5441.05 15256.60 cu.m 1921.80 5388.65 21.18
23 Dry brick pitching 100Cft. 3300.00 21120.00 cu.m 1165.55 7459.60 21.1
24 Sun dried bricks in mud mortar 100Cft. 4567.20 6141.00 cu.m 1613.15 2169.00 21.16
26 Eave brick moulded, weathered and throated with back 21.1 to 21.2
brick or drip course cornice, in 1:3 cement mortar:-
i) 3" (75 mm) thick drip course cornice Rft. 34.45 67.95 Metre 113.00 222.90 correction vide A&C No.I
ii) 4½" (113 mm) thick drip course cornice. ditto 39.05 140.90 ditto 128.10 462.15 dated 2.9.98
iii) 4½" (113 mm) thick eave brick with back brick. ditto 26.40 164.20 ditto 86.60 538.60
28 Cleaning bricks dismantled from kacha pacca masonry 1,000 1386.00 -- 1,000 1386.00 -
Nos Nos
29 Scraping bricks dismantled from pacca masonry 1,000 2613.60 -- 1,000 2613.60 -
chapter-7(Brickwork).xls Page 57
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
Nos Nos
30 Supplying and filling sand under floor; or plugging in wells. 100Cft. 330.00 2010.00 cu.m 116.55 709.95
31 Providing and laying 2" (50 mm) thick and 15" (375 mm) Rft. 144.40 209.55 Metre 473.65 687.30
projected tile band, laid in 1:2 cement sand mortar, with
hoop iron 1" (25 mm) wide 18 gauge flat iron sheet 9"
apart.
32 First class brick tiles clad by laying tiles in stretcher This item is to be executed only
course in cement sand mortar reinforced with 18 SWG under the written permission of the
hoop iron strips bonding placed at 2.0' (600 mm) apart Superintending Engineer.
horizontally, and at 1.0' (300 mm) interval vertically.
33 Chamfering sides of head regulators and masonry walls to Per Sft. 77.00 -- sq.m 828.50 -
increase width.
34 Replacing kallar eaten bricks Each No. 60.50 71.55 Each 60.50 71.55
35 Repairing corners of bridges and other hydraulic masonry Each No. 385.00 475.80 Each 385.00 475.80
works
36 Extra labour for drains of bath rooms, etc. Per Lft. 33.00 -- Metre 108.25
37 Maroo corners Each 211.20 -- Each 211.20 Payable in addition to brick work
Corner Corner
chapter-7(Brickwork).xls Page 58
8. STONE MASONRY
1 The composite rates do not include the carriage of stone or spawl which will be paid separately by road and/or rail whichever means of
transport is adopted. The supply and carriage to site of work of all other materials is included in the composite rates.
2 The payment of carriage of stone or spawl will be made on the basis of the actual stack measurement (without any reduction factor) of the
stone or spawl carried.
3 Where the stone or spawl is issued from stock and the contractor is paid for its carriage and/or labour only; or where the stone or spawl is
supplied, carried or handled by the contractor in which no laying is required, the actual stack measurement (without any reduction factor)
shall form the basis of the payment of supply or carriage of stone or spawl. The quantity of finished and completed item of work shall form
the basis of laying.
4 Rates for all finished work include the removal of surplus debris, unused material and byproducts.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
c) in lime, sand mortar 1:2 100 Cft. 11682.00 14602.80 cu.m 4126.10 5157.70
d) in cement, sand mortar:
i) ratio 1:3 100 Cft. 11682.00 19533.00 cu.m 4126.10 6899.05
ii) ratio 1:4 100 Cft. 11682.00 18274.80 cu.m 4126.10 6454.65
iii) ratio 1:6 100 Cft. 11682.00 16834.80 cu.m 4126.10 5946.05
iv) ratio 1:8 100 Cft. 11682.00 16038.00 cu.m 4126.10 5664.60
a) in lime, sand mortar 1:2 100 Cft. 35706.00 38394.80 cu.m 12611.35 13561.05
b) in cement, sand mortar:
i) ratio 1:3 100 Cft. 35706.00 41681.85 cu.m 12611.35 14722.05
ii) ratio 1:4 100 Cft. 35706.00 40843.05 cu.m 12611.35 14425.75
iii) ratio 1:6 100 Cft. 35706.00 39892.40 cu.m 12611.35 14090.00
8 Extra labour on items 3,4,5 & 6 above for every 5 ft.(1.5 m) 100 Cft. 1320.00 - cu.m 466.20 -
additional height, other than building, or part thereof.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
9 Extra labour for arch work in stone masonry, including 100 Cft. 3718.15 - cu.m 1313.25 - 22.12
centering and decentring, etc.
12 Dhajji walling 5"x5" (125 mmx125 mm) thick deodar 100 Sft. 14314.10 22046.10 sq.m 1540.20 2372.15 22.13
framing with stone laid in 1:6 cement sand mortar, and 1:4
cement sand plaster on both sides.
13 Providing and fixing stone blocks from 2 Cft. Per Cft. 617.10 648.55 cu.m 21795.95 22906.80
(0.6 cu.m) to 6 Cft (0.17 cu.m). each
including lift upto 20 ft. (6 m)
14 Providing and fixing stone blocks, under 2 Per Cft. 353.10 387.55 cu.m 12471.50 13688.25
Cft. (06 cu.m) each including lift upto 20 ft.
(6 m)
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
1 First class tile roofing, consisting of 4" (100 mm) earth 100Sft. 9662.40 16330.45 sq.m 1039.65 1757.15 23.1 Add extra 13%, 32% & 51% on
and 1" (25 mm) mud plaster with Gobri leeping over ½" (13 labour rates only or 6%, 15% & 23%
mm) thick cement plaster 1:6 with 34 lbs. per %Sft or on composite rates for 2nd, 3rd, 4th
1.72 Kg/sq.m hot bitumen coating sand blinded, provided & sub- sequent floors, respectively.
over 2 layers of tiles 12"x6"x1¼" (300x150x30 mm) laid in
1:6 cement mortar with ½" (13 mm) thick sand wiched
layer of 1:6 cement mortar, including 1:2 cement pointing
underside of tiles, complete, including curing, etc.
2 Second class tile roofing consisting of 4" (100 mm) earth 100Sft. 7444.80 12277.40 sq.m 801.05 1321.05 23.2 ditto
and 1" (25 mm) mud plaster with Gobri leeping over ½" (13
mm) thick cement plaster 1:6 with 34 lbs. per %Sft or
1.72 Kg/sq.m of hot bitumen coating sand blinded,
provided over one layer of 12"x6"x2" (300x150x50 mm)
tiles laid in 1:6 cement mortar, including 1:2 cement
pointing underneath of tiles complete including curing, etc.
3 Covering mud roof with coal tar, and fine sand. 100Sft. 405.90 1351.10 sq.m 43.70 145.40 23.1 to 23.2 ditto
a) Wooden battens over beams, filled with 100Sft. 770.00 3313.55 sq.m 82.85 356.55 Add extra 13%, 32% & 51% on
deodar wood pieces (spacers). roof area labour rates only or 6%, 15% &
b) RCC battens, filled with CC block 1:3:6. -ditto- 1425.60 1851.25 153.40 199.20 23% on composite rates for 2nd,
c) Spaces filled with bricks. -ditto- 398.65 1149.25 42.90 123.65 3rd, 4th & sub- sequent floors,
respectively.
5 Single layer of tiles 9"x4½"x1½" (225x113x40 mm) laid 100Sft. 2376.00 8486.75 sq.m 255.65 913.15 23.1 ditto
over 4"(100 mm) earth and 1" (25 mm) mud plaster without
Bhoosa, grouted with cement sand 1:3 on top of RCC roof
slab, provided with 34 lbs. per %Sft. or 1.72 Kg/Sq.m
bitumen coating sand blinded.
6 Jack arch roofing 4½" (113 mm) thick laid in 1:5 cement 23.3 to For steel part and its erection etc.
mortar, including an average depth of 4" (100 mm) cement 23.5 items 10 & 14 under Chapter IRON
concrete in haunches and over crown, with 3" (75 mm) WORK be referred.
earth and 1" (25 mm) plaster, soffits of arches cement
plaster 1:6 and ½" (13 mm) thick. The rate also includes Add extra 13%, 32% & 51% on
bitumen coating, centring, laying skew bricks in cement labour rates only or 6%, 15% & 23%
mortar (1:3), and encasing exposed flanges of the joints on composite rates for 2nd, 3rd, 4th
with fine cement concrete 1:2:4 using stone aggregate:- & sub- sequent floors, respectively.
chapter-9(Roofing).xls Page 62
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
a) cement concrete in haunches 1:6:12. 100Sft. 10612.80 23154.40 sq.m 1141.95 2491.40
b) cement concrete in haunches 1:3:6. ditto 10612.80 24613.75 ditto 1141.95 2648.45
7 Jack arch roofing 4½" (113 mm) thick laid in 1:5 cement 23.3 For steel part and its erection etc.
mortar, including an average depth of 4" (100 mm) cement to items 10 & 14 under Chapter IRON
concrete in haunches and over crown, with ½" (13 mm) 23.5 WORK be referred.
cement plaster 1:6 on top (except earth filling mud plaster
and gobri) soffit of arches cement plastered. The rate also Add extra 13%, 32% & 51% on
includes bitumen coating, centring, laying skew bricks in labour rates only or 6%, 15% & 23%
cement sand mortar (1:3), and encasing exposed flanges on composite rates for 2nd, 3rd, 4th
of the joints with fine cement concrete 1:2:4 using stone & sub- sequent floors, respectively.
aggregate:-
a) cement concrete in haunches 1:6:12. 100Sft. 8632.80 22309.90 sq.m 928.90 2400.55
b) cement concrete in haunches 1:3:6. ditto 8632.80 22364.90 ditto 928.90 2406.45
8 Extra for vaulted jack arch roofing. 100Sft. 2112.00 sq.m 227.25 - ditto
9 Jack arch roofing of shingle and cement concrete 1:3:6, 100Sft. 11946.00 20869.20 sq.m 1285.40 2245.55 23.3 ditto
4½" (113 mm) thick at crown, with ½" (13 mm) cement to
plaster including cost of supplying, erecting and 23.5
dismantling centring.
10 Earth filling over roof including watering, ramming with 1" 23.1 Add extra 13%, 32% & 51% on
(25 mm) mud plaster finished, with gobri leeping: to labour rates only or 6%, 15% & 23%
23.3 on composite rates for 2nd, 3rd, 4th
a) 3" (75 mm) thick earth filling and 1" (25 mm) mud 100Sft. 1020.10 1353.50 sq.m 109.75 145.65 & sub- sequent floors, respectively.
plaster
b) 4" (100 mm) thick earth filling and 1" (25mm) 100Sft. 1338.50 1739.70 sq.m 144.00 187.20
mud plaster
11 1/8" (3 mm) thick gobri leeping on roofs or floors. 100Sft. 147.85 162.65 sq.m 15.90 17.50 ditto ditto
12 Two coats of bitumen laid hot using 34 lbs. per %Sft, or 100Sft. 792.00 2650.45 sq.m 85.20 285.20 23.1
1.72 Kg per square metre over roof and blinded with sand
at one Cft. per %Sft. (0.003 cu.m per sq.m)
13 Providing & Fixing corrugated galvanized iron sheets with G.I. bolts, 23.7 Add extra 13%, 32% & 51% on
nuts, limpet and bitumen washers, wind ties, complete in labour rates only or 6%, 15% & 23%
all respects without valleys and ridges:- on composite rates for 2nd, 3rd, 4th
& sub- sequent floors, respectively,
a) 20 BWG 100Sft. 1540 19103.15 sq.m 165.7 2055.5 on items 13 to 18.
b) 22 BWG 100Sft. 1540 16720.4 sq.m 165.7 1799.1
c) 24 BWG 100Sft. 1540 13625.75 sq.m 165.7 1466.15
14 Khassi parnalas in cement, sand mortar 1:2, 12" (300 Rft. 109.50 134.75 Metre 359.15 442.00 23.10
chapter-9(Roofing).xls Page 63
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
15 Khuras on roof 2'x2'x6" (600 x 600 x 150 mm) Each 411.85 614.60 Each 411.85 614.60 23.10
16 Bottom Khuras of brick masonry in cement mortar 1:6, Each 411.85 1069.90 Each 411.85 1069.90 23.10
4'x2'x4½" (1200x600x113 mm) over 3" (75 mm) cement
concrete 1:4:8.
a) 4" (100 mm) diameter down pipe Per Rft. 87.10 220.75 Metre 285.70 724.05
b) 5" (125 mm) diameter down pipe Per Rft. 87.10 250.55 Metre 285.70 821.80
18 Plain galvanized iron sheet flashing, 22 gauge. Per Sft. 87.10 187.50 sq.m 937.20 2017.50 23.11
19 Providing and fixing 1/16" (1.5 mm) thick lead flashing over Per Sft. 26.40 96.00 Sq.m 284.05 1032.95
roof expansion joint complete in all respects.
20 Cast iron rain water downpipe fixed in position, excluding Add extra 13%, 32% & 51% on
heads and shoes, but including painting and clamps, etc:- labour rates only or 6%, 15% & 23%
on composite rates for 2nd, 3rd, 4th
a) 4" dia (100 mm) cast iron down pipe. Per Rft. 77.00 240.85 Metre 252.55 790.00 & sub- sequent floors, respectively,
b) 3" (75 mm) cast iron down pipe. Per Rft. 77.00 216.55 Metre 252.55 710.30 on items 19 to 24
21 Rain water down pipe cast iron head fixed in place, Each 326.70 638.70 Each 326.70 638.70
including cost of clamp holdfast and painting.
22 Shoes, bends or offsets for cast iron rain water down pipe, Each 115.50 357.80 Each 115.50 357.80
including fixing and painting.
23 Plain GI sheet iron spouts fixed in position, including Each 363.00 516.70 Each 363.00 516.70 23.10
painting.
24 Laying ½" (13 mm) thick deodar ceiling complete, 100Sft. 8250.00 27844.30 sq.m 887.70 2996.05 26.1
including sawing, planing and fixing.
a) 22 BWG sheets roofing 100Sft. 4884.00 21219.05 sq.m 525.50 2283.15 23.60
b) 24 BWG sheets roofing 100Sft. 4884.00 19247.40 sq.m 525.50 2071.00
26 Asbestos cement corrugated sheet roofing including 100Sft. 3300.00 7362.00 sq.m 355.10 792.15 23.8
necessary overlaps, and GI hook bolts, nuts, screws,
washers and bitumen washers, etc. (excluding valleys and
chapter-9(Roofing).xls Page 64
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
ridges, etc).
27 Extra labour for erection of GI sheets, flat sheet or 100Sft. 382.80 -- sq.m 41.20 - 23.6
asbestos sheet roofing, above 20' (6.10 m) height in
difficult position, including lifting with care and special
scaffolding along live electric wires.
28 Fixing asbestos cement sheet ridges and valleys ¼" Per Rft. 39.60 92.70 Metre 129.90 304.05 23.8
(6 mm) thick.
a) 6" (150 mm) lap and 18" (450 mm) Per Rft. 108.90 555.20 Per Metre 357.20 1821.05
overall, of 22 gauge G.I sheet ridging.
b) 9" (225 mm) lap and 24" (600 mm) Per Rft. 138.60 553.15 Per Metre 454.60 1814.35
overall, of 24 gauge G.I sheet ridging.
c) 12" (300 mm) lap and 30" (750 mm) Per Rft. 138.60 639.25 Per Metre 454.60 2096.75
overall, of 22 gauge G.I sheet ridging.
30 Plain 22 gauge G.I sheet gutter semi circular Per Rft. 69.30 213.25 Per Metre 227.30 699.45 23.11
8" (200 mm) dia meter.
31 Making masonry ventilators in cement, sand Each 1540.00 2337.20 Each 1540.00 2337.20
mortar 1:4
33 Making drip course 2"x½" (50x13 mm) under RCC slab edges Per Rft. 19.55 21.10 Metre 64.10 69.20
in outer opening, in cement, sand mortar 1:2.
34 Supplying and laying of twin G.I sheet 20 SWG duly Per Sft. 56.10 425.85 sq.m 603.65 4582.15
painted with bitumen, with polythene film in between 300
gauge, to provide a sliding joint under the bearing of the
beams, including 3" (75 mm) long, 3/8" (10 mm) dia bar to
act as holdfast on wall and beam.
i) Thermopore sheet ½ " (13 mm) thick 100Sft. 3663.00 10133.65 sq.m 394.15 1090.40
ii) Thermopore sheet ¾ " (20 mm) thick 100Sft. 3663.00 10511.65 sq.m 394.15 1131.05
iii) Thermopore sheet 1" (25 mm) thick 100Sft. 3669.60 10770.25 sq.m 394.85 1158.90
36 Providing and fixing AC rain water down pipe 4" (100 mm) Rft. 23.10 337.70 Metre 75.75 1107.65
chapter-9(Roofing).xls Page 65
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
37 Making jharries in existing brick masonry for providing Rate will be increased by 1.5 time
recesses for bearing of RCC roof slab, including repairing for stone masonry or plain; concrete;
the damaged face:- and 2 times for reinforced cement
concrete.
i) for slabs upto 6" (150 mm) thick Rft. 26.40 28.65 Metre 86.60 93.95
ii) for slabs exceeding 6" to 12" (150 to 300 mm) thick. Rft. 44.55 48.65 Metre 146.10 159.55
38 Making recess in existing brick masonry for bearing of Rates will be increased by 1.5 times
beam, girder, R.S. Joist, etc. including repairing damaged for stone masonry and plain
face:- cement concrete and two times
for reinforced cement concrete.
i) upto 1.0' (300 mm) height of girder or beam. Each 110.00 117.45 Each 110.00 117.45
ii) for every 6" (150 mm) additional height or part thereof. Each 52.80 56.40 Each 52.80 56.40
39 Hoisting RS. Beams and wooden beams and placing in Each 429.00 - Each 429.00 -
position.
40 Hoisting and placing in position sahl ballies, over roof. Each 66.00 - Each 66.00 -
42 Hoisting and placing in position R.C. trough: Applicable only to roof trough
(inverted tees & trough) for height of
a) upto 10' (3 m) in length Each 171.60 - Each 171.60 - 1st storey only.
b) 10' to 11' (3 to 3.36 m) in length ditto 214.50 - ditto 214.50 -
c) 11' to 12' (3.36 to 3.66 m) in length ditto 286.00 - ditto 286.00 -
d) 12' to 13' (3.66 to 3.96 m) in length ditto 330.00 - ditto 330.00 -
e) 13' to 14' (3.96 to 4.26 m) in length ditto 357.50 - ditto 357.50 -
f) 14' to 15' (4.26 to 4.57 m) in length ditto 390.00 - ditto 390.00 -
g) 15' to 16' (4.57 to 4.88 m) in length ditto 429.00 - ditto 429.00 -
h) 16' to 17' (4.88 to 5.19 m) in length ditto 476.65 - ditto 476.65 -
i) 17' to 18' (5.19 to 5.49 m) in length ditto 612.85 - ditto 612.85 -
j) 18' to 19' (5.49 to 5.80 m) in length ditto 660.00 - ditto 660.00 -
k) 19' to 20' (5.80 to 6.10 m) in length ditto 715.00 - ditto 715.00 -
chapter-9(Roofing).xls Page 66
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
iv) from 13' to 14' (3.96 to 4.26 m) span ditto 440.00 - ditto 440.00 -
v) from 14' to 15' (4.26 to 4.57 m) span ditto 480.00 - ditto 480.00 -
vi) from 15' to 16' (4.57 to 4.88 m) span ditto 528.00 - ditto 528.00 -
vii) from 16' to 18' (4.88 to 5.49 m) span ditto 660.00 - ditto 660.00 -
viii) from 18' to 20' (5.49 to 6.10 m) span ditto 1056.00 - ditto 1056.00 -
44 Reinforced cement concrete spout, including fixing in Each 616.00 917.35 Each 616.00 917.35
position, with top and bottom Khurras.
chapter-9(Roofing).xls Page 67
10. FLOORING
Rates for all finished works include the removal of surplus debris, unused material and byproducts
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
1 Laying Murum flooring, consisting of 1"(25 mm) layer of 100 Sft. 4158.00 5427.35 sq.m 447.40 584.00
fine powdery or flakey variety of Murum, laid over 6"(150
mm) good hard layer of Murum spreaded over 9"(225 mm)
thick sub-base comprising of hand packed rubble or
broken bricks properly watered and rammed, provided over
well rammed earth.
2 Earth flooring, consisting of 6"(150 mm) thick consolidated 100 Sft. 1419.00 1758.00 sq.m 152.70 189.15 24.1
layer of moistened earth, including ramming.
3 Providing, laying, watering and ramming brick ballast 1½" 100 Cft. 3174.60 5874.60 cum. 1121.25 2074.90
to 2"(40 mm to 50 mm) gauge mixed with 25% sand, for
floor foundation, complete in all respects.
4 Mud flooring, consisting of 6"(150 mm) thick consolidated 100 Sft. 2574.00 3082.05 sq.m 276.95 331.65 24.2
layer of moistened earth and finished off with 1"(25 mm)
mud plaster and gobri leeping.
5 Dry brick paving laid flat, sand grouted, including 100 Sft. 1362.25 6106.90 sq.m 146.60 657.10 24.12
preparation of bed by watering, ramming and bringing the
same to proper camber, by ½"(13 mm) thick mud plaster.
6 Dry brick on edge paving, sand grouted, including 100 Sft. 2453.90 9525.35 sq.m 264.05 1024.95 24.12
preparation of bed by watering, ramming & bringing the
same to proper camber, by ½ "(13 mm) thick mud plaster.
7 Grouting 4½"(113 mm) dry brick work with cement mortar 100 Sft. 1346.40 1926.00 sq.m 144.85 207.25
ratio 1: 5
8 Flat brick flooring laid in 1:6 cement mortar, over a bed of 100 Sft. 2402.40 8126.40 sq.m 258.50 874.40 24.4
3/4" (20 mm) thick cement mortar, 1:6.
9 Brick on edge flooring, laid in 1:6 cement mortar, over a 100 Sft. 3,062.40 11,456.40 sq.m 329.50 1232.70 24.4
bed of ¾" (20 mm) thick cement mortar 1:6.
10 Brick tiles (12"x6"x2") (300x150x50mm) laid in 1:6 100 Sft. 3,003.00 5,542.20 sq.m 323.10 596.35 ditto
cement mortar, over a bed of ¾" (20 mm) thick cement
mortar 1:6.
11 Brick ties (9"x4½"x1½")(225 mm x 113 mm x 40 mm) laid 100 Sft. 3,333.00 7,902.60 sq.m 358.65 850.30 24.4
flat in 1:3 cement mortar, over a bed of 3/4"(20 mm) thick
cement mortar 1:6.
12 Cement tiles (8"x8"x¾")(200 x 200 x 20 mm) laid flat in 100 Sft. 1,994.50 7,163.90 sq.m 214.60 770.85 24.7
1:2 cement mortar, over 3/4" (20 mm) thick bed of cement
chapter-10(Flooring).xls Page 68
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
mortar 1:2.
(a) 12"x12"x1" (300 x 300 x 25 mm) 100 Sft. 1,994.50 5,295.00 sq.m 214.60 569.75
(b) 9"x9"x¾" (225 x 225 x 20 mm) ditto 1,994.50 6,537.00 ditto 214.60 703.40
(c) 6"x6"x¾"(150 x 150 x 20 mm) ditto 1,994.50 8,986.15 ditto 214.60 966.90
14 Coloured cement tiles (8"x8"x¾")(200 x 200 x 20 mm) of 100 Sft. 1,994.50 7,193.40 sq.m 214.60 774.00 24.7
approved dark shade laid flat in 1:2 cement mortar, over
¾" (20 mm) bedding mortar of 1:2.
15 Providing and laying topping of cement concrete 1:2:4, 24.9 If glass or marble strips are used
including surface finishing and dividing in panels:- for panelling, it will be paid extra as
per item No. 41 or 42.
(a) 1"(25 mm) thick 100 Sft. 2,250.60 3,637.95 sq.m 242.15 391.45
(b) 1¼"(30 mm) thick ditto 2,250.60 3,947.20 ditto 242.15 424.70
(c) 1½"(40 mm) thick ditto 2,798.40 4,804.25 ditto 301.10 516.95
(d) 1¾"(45 mm) thick ditto 2,798.40 5,127.10 ditto 301.10 551.70
(e) 2"(50 mm) thick ditto 3,346.20 6,058.50 ditto 360.05 651.90
(f) 2¼"(56 mm) thick ditto 3,445.20 6,444.40 ditto 370.70 693.40
(g) 2½"(62 mm) thick ditto 3,894.00 7,096.35 ditto 419.00 763.55
(h)2¾"(70 mm) thick ditto 3,894.00 7,522.70 ditto 419.00 809.45
(i) 3"(75 mm) thick ditto 3,894.00 7,881.70 ditto 419.00 848.05
16 Providing and laying conglomerate flooring (two coat work) 24.10 If glass or marble strips are used
with top layer of ½"(13mm) thick wearing surface, for panelling, it will be paid extra as
consisting of one part of cement and 2 parts of stone per item No. 41 or 42.
chips passing 3/16"(6 mm) sieve, over bottom layer of
cement concrete 1:3:6, including surface finishing and
dividing in panels:-
(a) 1½"(40 mm) thick 100 Sft. 3,329.70 5,301.55 sq.m 358.30 570.45
(b) 1¾"(45 mm) thick ditto 3,329.70 5,510.30 ditto 358.30 592.90
(c) 2"(50 mm) thick ditto 4,207.50 6,697.20 ditto 452.75 720.60
17 Add extra in cement concrete floor topping, if finished with 100 Sft. 770.00 1,320.85 sq.m 82.85 142.10
pigment and polishing.
18 Extra labour for each storey above ground, for mosaic, 100 Sft 594.00 - sq.m 63.90 - On items 19-25 & 29-34
conglomerate, tiles, stone and wooden floor.
19 Flag stone flooring in lime mortar 1:2, over ¾"(20 mm) 24.5
bedding mortar, in platforms and floors, etc.
(a) 2"(50 mm) thick 100 Sft. 6,627.70 8,373.15 sq.m 713.15 900.95
(b) 3"(75 mm) thick ditto 6,627.70 8,611.30 ditto 713.15 926.60
chapter-10(Flooring).xls Page 69
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
(a) 1"(25 mm) thick topping 100 Sft. 2,640.00 19,052.50 sq.m 284.05 2050.05
(b) ½"(13 mm) thick topping ditto 2,079.00 10,453.20 ditto 223.70 1124.75
(c) ¼"(6 mm) thick topping ditto 1,544.40 5,838.30 ditto 166.20 628.20
3
21 1 /8"(35 mm) thick mosaic flooring, consisting of 3/8"(10 If glass or marble strips are used
mm) mosaic topping of one part of cement and marble for panelling, it will be paid extra as
powder in the ratio of 3:1 and two parts of marble chips, per item No. 41 or 42.
laid over 1"(25 mm) thick flooring of 1:2:4 cement concrete
including rubbing and polishing complete :-
(a) using grey cement 100 Sft. 10,288.10 13,731.35 sq.m 1107.00 1477.50
(b) using white cement ditto 10,288.10 14,295.40 ditto 1107.00 1538.20
22 1½"(40 mm) thick mosaic flooring, consisting of ½ "(13 If glass or marble strips are used
mm) mosaic topping of one part of cement and marble for panelling, it will be paid extra as
powder in the ratio of 3:1 and two parts of marble chips, per item No. 41 or 42.
laid over 1"(25 mm) thick floor of 1:2:4 cement concrete,
including rubbing and polishing complete with finishing :-
(a) using grey cement 100 Sft. 10,288.10 13,953.45 sq.m 1107.00 1501.40
(b) using white cement ditto 10,288.10 15,186.55 ditto 1107.00 1634.05
23 Providing and laying floor of mosaic marble chips tiles 100 Sft. 5,559.85 9,891.70 sq.m 598.25 1064.35 24.8
1"(25 mm) thick of approved quality and shade, laid in
white cement and pigment, over ¾"(20 mm) thick bedding
of cement sand mortar 1:2, including finishing and
polishing, complete.
24 Laying floor of approved white glazed tile ¼" (6 mm) thick 100 Sft. 7,128.00 16,462.55 sq.m 766.95 1771.35 24.7
in white cement 1:2 over ¾" (20mm) thick cement mortar
1:2, complete.
25 Laying floor of approved coloured glazed tiles ¼ "(6 mm) 100 Sft. 7,128.00 18,018.85 sq.m 766.95 1938.85 ditto
thick, laid in white cement and pigment on a bed of ¾"
(20 mm) thick cement mortar 1:2.
26 Rubbing and polishing old grit/ mosaic floor, including 100 Sft. 2,059.20 2,199.80 sq.m 221.55 236.70 The composite rate will be reduced
repairing voids, uneven surface, complete in all respects. by Rs. 150.00 per % Sft or Rs.13.95 per
Sq. metre respectively, if no
polishing is done.
27 Rubbing and polishing grit floor, including repairing voids, 100 Sft. 2,185.90 2,329.25 sq.m 235.20 250.65 The composite rate will be reduced
uneven surface, complete in all respects by Rs. 150.00 per % Sft or Rs.13.95 per
Sq. metre respectively, if no
polishing is done.
chapter-10(Flooring).xls Page 70
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
28 Cleaning and washing mosaic or marble floor with caustic 100 Sft. 304.50 350.00 sq.m 32.75 37.65 24.6
soda mixture.
29 Shisham wood boarding or strip flooring 3/4" (20mm) thick 100 Sft. 6,600.00 54,119.55 sq.m 710.15 5823.25 24.13
(sawn to required size) tongued and grooved or splayed
rebated fixed with brass screws on deodar wood battens
1½ "x2"(40 x 50 mm),size placed at 12"(300 mm) centre
to centre, including two coats of bitumen laid hot on the
base.
30 Deodar wood boarding or strip flooring 3/4" (20 mm) thick 100 Sft. 6,930.00 60,575.75 sq.m 745.65 6517.95 ditto
(sawn to required size) tongued and grooved or splayed
rebated fixed with brass screws on deodar wood battens
1½"x2"(40 x 50 mm) size , placed at 12"(300 mm) centre,
to centre including two coats of bitumen laid hot on the
base.
31 Teak wood boarding or strip flooring ½" (13 mm) "thick 100 Sft. 6,050.00 110,242.15 sq.m 651.00 11862.05 ditto
(sawn to required size) to tongued and grooved screwed
on deodar wood battens 1½ " x2"(40 x 50 mm) size,
placed at 12"(300 mm) centre to centre, including 2 coats
of bitumen laid hot on base.
32 Shisham wood block flooring 1"(25 mm) thick cut to 100 Sft. 6,435.00 61,297.15 sq.m 692.40 6595.55 24.13
required size, fixed on a layer of asphalt bitumen laid on
base.
33 Teak wood block 1"(25 mm) thick cut to required size, 100 Sft. 6,050.00 206,736.25 sq.m 651.00 22244.80 ditto
fixed on a layer of asphalt bitumen laid on base.
(a) cement tiles 100 Sft. 3,262.15 8,915.25 sq.m 351.00 959.30
(b) mosaic tiles ditto 5,379.00 13,002.50 ditto 578.80 1399.05
(a) 1:2 cement, sand mortar 100 Sft. 4,115.25 4,848.45 sq.m 442.80 521.70
chapter-10(Flooring).xls Page 71
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
(b) 1:3 cement, sand mortar ditto 4,115.25 4,633.25 ditto 442.80 498.55
(c) Extra if skirting or dado is finished ditto 247.50 515.15 ditto 26.65 55.45
with pigment of any colour.
37 White glazed tile (6"x6"x¼") (6 mm) thick dado jointed in white 100 Sft. 8,778.00 18,112.55 sq.m 944.50 1948.90 24.7
cement and laid over 1:2 cement sand mortar 3/4" (20mm)
thick, including finishing.
38 Coloured glazed tile dado (6"x6"¼") (6mm) thick in pigment over 100 Sft. 8,778.00 19,650.70 sq.m 944.50 2114.40 ditto
1:2 cement, sand mortar 3/4"(20mm) thick, including finishing.
'i) 3/8"(10 mm) thick 100 Sft. 12,276.00 15,603.20 sq.m 1320.90 1678.90
ii) ½"(13 mm) thick ditto 12,276.00 16,053.55 ditto 1320.90 1727.35
40 Rubber flooring, consisting of 12"x12"x1/8" Per Sft. 28.05 90.95 sq.m 301.80 978.60 24.14 The cost of base for rubber flooring
(300x300x3mm) rubber tiles, laid on firm foundation. is not included in the rate and is
payable separately.
41 Providing and fixing glass strip 5mm thick and 1½" Per Rft. - 4.60 Metre - 15.10 Labour for fixing already included in
(40 mm) wide, for dividing the mosaic flooring into panels. items No. 15, 16, 21and 22 of this
Chapter.
3
a) sSize 1½" x /8" (40 x 10 mm) Per Rft. - 9.25 Metre - 30.35
b) sSize 1½" x ¼" (40 x 6 mm) ditto - 7.90 ditto - 25.90
43 Providing and laying Tuff pavers, having 7000 PSI, crushing strength
of approved manufacturer, over 2" to 3" sand cushion i/c grouting with
sand in joints i/c finishing to require slope . complete in all respect.
(50% Grey / 50% Coloured)
a) 50-mm thick P.Sft 19.25 94.25 Sq.m 207.25 1,014.15
b) 60-mm thick P.Sft 19.25 105.35 Sq.m 207.25 1,133.30
c) 80-mm thick P.Sft 19.25 126.20 Sq.m 207.25 1,358.10
chapter-10(Flooring).xls Page 72
11. SURFACE RENDERING
1 PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING AND DISTEMPERING, ETC.
2 Rates for all finished works include the removal of surplus debris, unused material and byproducts.
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
a) ½" (13 mm) thick 100 Sft. 617.75 703.45 sq.m 66.45 75.70
b) 1" (25 mm) thick ditto 864.35 1035.70 ditto 93.00 111.45
2 Mud plaster on floor or roof (excluding Gobri leeping):- ditto Add extra 13%, 32% and 51% above
the labour rates only or 6%, 15% &
a) ½" (13 mm) thick 100 Sft. 557.05 642.70 sq.m 59.95 69.15 23% on the composite rates for 2nd,
3rd, 4th and subsequenct floors,
b) 1" (25 mm) thick ditto 557.05 728.40 ditto 59.95 78.40 respectively.
3 Cement lime plaster 1:7:12 (cement, lime and sand) upto 25.1 to 25.6
20' (6.00 m) height.
a) ¼" (6 mm) thick 100 Sft. 1795.20 1982.15 sq.m 193.15 213.30
b) ½" (13 mm) thick ditto 1795.20 2169.00 ditto 193.15 233.40
4 Cement Neru plaster 1:2 (cement and sand) upto 20' ditto
(6.00 m) height:-
a) ¼" (6 mm) thick 100 Sft. 1795.20 2308.90 sq.m 193.15 248.45
b) ½" (13 mm) thick ditto 1795.20 2617.05 ditto 193.15 281.60
5 2" (50 mm) stucco cement plaster 1:2:4 (cement, sand 100 Sft. 4477.45 7616.75 sq.m 481.75 819.55 ditto
and shingle) upto 20' (6.00 m) height.
6 Providing and laying machine sprayed plaster ½" (13 mm) ditto
thick, using cement and chips zero gauge, over the
existing plastered and roughened surface, upto 20' (6.00
m) height:-
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
a) 3/8" (10 mm) thick 100 Sft. 1795.20 2313.25 sq.m 193.15 248.90
b) ½" (13 mm) thick ditto 1795.20 2485.90 ditto 193.15 267.50
c) ¾" (20 mm) thick ditto 2257.20 3293.30 ditto 242.90 354.35
a) 3/8" (10 mm) thick 100 Sft. 1795.20 2256.00 sq.m 193.15 242.75
b) ½" (13 mm) thick ditto 1795.20 2381.30 ditto 193.15 256.25
c) ¾" (20 mm) thick ditto 2257.20 3170.40 ditto 242.90 341.15
10 Cement plaster 3/8" (10 mm) thick under soffit of R.C.C. ditto i) This item shall be applicable to
roof slabs only, upto 20' height. buildings meant for human
habitation only, such as buildings
like residences, offices,
a) 1:2 100 Sft. 2059.20 2937.25 sq.m 221.55 316.05 educational institutions and
b) 1:3 ditto 2059.20 2721.25 ditto 221.55 292.80 hospitals, etc. It shall not be
c) 1:4 ditto 2059.20 2664.00 ditto 221.55 286.65 admissible on godowns; bins;
agriculture, poultry and animal
sheds; cycle stands; garrages; etc.
ii) The thickness of the plaster will
not be more than 3/8" (10 mm)
thick.
11 Cement plaster 1:5 upto 20' (6.00 mm) height:- 25.1 to 25.6
a) 3/8" (10 mm) thick 100 Sft. 1795.20 2205.60 sq.m 193.15 237.30
b) ½" (13 mm) thick ditto 1795.20 2294.40 ditto 193.15 246.90
c) ¾" (20 mm) thick ditto 2257.20 3078.00 ditto 242.90 331.20
13 Applying floating coat of cement 1/32" (0.8 mm) thick. 100 Sft. 1074.50 1362.50 sq.m 115.60 146.60 25.4 to 25.6
14 Lime pointing flush upto 20' (6.00 m) height including 100 Sft. 1333.20 1460.20 sq.m 143.45 157.10 25.8
raking joints, in lime, sand mortar 1:2.
15 Lime pointing struck joints on walls, upto 20' (6.00 m) 100 Sft. 2059.20 2186.20 sq.m 221.55 235.25 ditto
height, including raking joints in lime sand mortar 1:2.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
17 Cement pointing 1:2 flush on floor. 100 Sft. 1333.20 1881.85 sq.m 143.45 202.50 ditto
a) in lime mortar 1:2 (lime, sand) 100 Sft. 1663.20 1831.15 sq.m 178.95 197.05
b) in cement mortar 1:3 ditto 1663.20 2085.60 ditto 178.95 224.40
c) on stone work raised:-
i) in lime mortar 1:2 100 Sft. 3115.20 3283.15 sq.m 335.20 353.25
ii) in cement mortar 1:3 ditto 3115.20 3537.60 ditto 335.20 380.65
20 Raking and washing joints of stone masonry 100 Sft. 1056.00 - sq.m 113.65 - ditto
(old work).
21 Raking and washing joints of brick masonry (old work). 100 Sft. 528.00 - sq.m 56.80 - ditto
22 Priming coat of chalk under distemper. 100 Sft. 184.80 206.65 sq.m 19.90 22.25 25.11
23 Distempering:- ditto
a) new surface:-
i) one coat 100 Sft. 172.50 455.10 sq.m 18.55 48.95
ii) two coats ditto 255.20 627.80 ditto 27.45 67.55
iii) three coats ditto 337.90 800.55 ditto 36.35 86.15
b) old surface:-
i) one coat 100 Sft. 158.40 351.00 sq.m 17.05 37.75
ii) two coats ditto 255.20 447.80 ditto 27.45 48.20
a) new surface:-
i) one coat 100 Sft. 174.25 256.55 sq.m 18.75 27.60
ii) two coats ditto 261.35 380.90 ditto 28.10 41.00
b) old surface:-
i) one coat 100 Sft. 174.25 229.95 sq.m 18.75 24.75
ii) two coats ditto 261.35 352.50 ditto 28.10 37.95
a) new surface:-
i) one coat 100 Sft. 174.25 238.05 sq.m 18.75 25.60
ii) two coats ditto 261.35 356.90 ditto 28.10 38.40
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
b) old surface:-
i) one coat 100 Sft. 174.25 222.05 sq.m 18.75 23.90
ii) two coats ditto 261.35 340.90 ditto 28.10 36.70
27 Striking joints of burnt bricks in lime or cement mortar. 100 Sft. 264.00 - sq.m 28.40 - 25.8 Payable with fresh masonry, when
the face of the work is not to be
plastered/pointed.
28 Extra for lime, mud or cement plaster and pointing from 100 Sft. 324.70 - sq.m 34.95 -
20' (6.00 m) and above for each additional 10' (3.00 m)
height or part thereof.
29 Caulking joints of sleeper wall, with sand and coaltar. 100 Sft. 924.00 1487.05 sq.m 99.40 160.00
30 Caulking joints of sleepers, withmud and chopped straw. 100 Sft. 924.00 956.50 sq.m 99.40 102.90
31 Extra cost of labour and material for red oxide pigment in 100 Sft. 330.00 510.00 sq.m 35.50 54.90
cement pointing to match with the colour of bricks.
i) 3/8" (10 mm) thick 100 Sft. 2059.20 2577.25 sq.m 221.55 277.30
ii) ½" (13 mm) thick ditto 2059.20 2749.90 ditto 221.55 295.90
33 Providing and fitting expanded metal edge bead for Rft. 15.70 45.35 Metre 51.50 148.75
corners, with nails on both sides of edges.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
i) 2" (50 mm) thick Per Sft. 192.50 3809.10 sq.m 2071.30 40985.90
ii) 1¾" ( 45 mm) thick ditto 192.50 3547.80 ditto 2071.30 38174.35
iii) 1½" (40 mm) thick ditto 192.50 3292.65 ditto 2071.30 35428.90
4 First class teak wood wrought joinery in wire gauze doors 26.8 i) This also includes the cost of
and windows with frames 22 SWG galvanized iron wire to wood required for extra thickness of
2
gauze 12x12 meshes to square inch, (5x5 meshes in cm ) 26.10 chowkat.
including brass fittings, sash bars, etc. complete:- ii) If 24 SWG wire gauge is used,
the composite rate shall be
a) teak wood framing 1¾" (45 mm) thick with wire gauze reduced by Rs.4.70 per sft. and
fixed in position:- Rs.50.60 per sq.m.
i) without springs or spring hinges. Per Sft. 36.65 1570.70 sq.m 394.35 16900.75
ii) with springs or spring hinges. ditto 36.65 1577.00 ditto 394.35 16968.50
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
c) G.I. wire gauze 22 SWG, 12x12 meshes per square Per Sft. 66 433 sq.m 710.15 4659.1
2
inch, (5x5 meshes per cm ) fixed to chowkat with ¾"
(20 mm) teak wood strips and screws.
d) G.I. wire gauze 22 SWG, 12x12 meshes per square Per Sft. 61.90 1497.05 sq.m 666.05 16108.25
2
inch (5x5 meshes per cm ) fixed with ½" (13 mm) strip
on separate frame of teak wood 2"x2" (50x50 mm),
for windows, etc.
5 P/F expanded metal ½" to ¾" (13 to 20 mm) mesh, 16 Per Sft. 82.50 701.05 sq.m 887.70 7543.30
Guage, fixed to chowkat with 1" (25 mm) teak wood cover
strips and screw etc., complete.
6 Providing and fixing expanded metal ½" (13 mm) to ¾" Per Sft. 82.50 1076.85 sq.m 887.70 11586.90
20 mm), 16 gauge, fixed to chowkat with 1" (25 mm)cover
moulding and screws, including teak wood frame 2"x2"
(50 mm x 50 mm)
a) 2" thick (50 mm) Per Sft. 195.55 1466.85 sq.m 2104.10 15783.30
b) 1¾" thick (45 mm) ditto 195.55 1377.00 ditto 2104.10 14816.60
c) 1½" thick (40 mm) ditto 195.55 1312.90 ditto 2104.10 14126.80
8 Deodar wood framed, braced and battened doors and 26.1, 26.2
windows, complete with iron fittings and fixed in position, & 26.4
including chowkats:-
a) 2¼" (56 mm) thick, with 1¼" (30 mm) Per Sft. 220.00 1048.05 sq.m 2367.20 11277.00
battens and 1" (25 mm) planks.
b) 1¾" (40 mm) thick with 1" (25 mm) ditto 203.10 900.45 ditto 2185.35 9688.85
battens and ¾" (20 mm) planks.
9 1" (25 mm) thick battneded doors and windows fitted in Per Sft. 250.80 620.65 sq.m 2698.60 6678.20
position, complete with iron fittings, without chowkats.
10 Deodar battened ledged and braced doors and windows 26.1, 26.2
2¼" (56 mm) thick (1¼" (30 mm) thick ledge braces and 26.4 to
1" (25 mm) thick battens complete with iron fittings, Per Sft. 236.90 1017.65 sq.m 2549.05 10949.90 26.6
chowkats and fixed in position.
11 a) Deodar wood framed with braces and 22 SWG G.I. 26.1, 26.2 If 24 gauge G.I. sheet is used, the
sheet facing, including holdfast, wooden beadings, & 26.4 composite rate will be reduced by
hinges, and locking arrangements as directed by the Re.4.70 per Sft. (Rs. Per 50.60
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
i) G.I. sheet facing on one side. Per Sft. 103.15 316.70 sq.m 1109.90 3407.70
ii) G.I. sheet facing on both sides. ditto 113.45 367.25 ditto 1220.70 3951.60
12 First class deodar wood wrought joinery work in wire 26.8 to i) This also includes the cost of
gauze doors and windows, with 22 SWG G.I. wire gauze, 26.10 wood required for extra thickness
2
12x12 meshes per square inches (5x5 per cm ) including of chowkat.
iron fittings etc. complete:-
ii) If 24 SWG wire gauze is used
a) deodar wood framing 1¾" (45 mm) thick with wire the composite rate shall be
gauze fixed in position:- reduced by Rs.4.70 per sft or
Rs.50.60 per sq.m.
i) without springs or spring hinges. Per Sft. 110.00 652.05 sq.m 1183.60 7016.05
ii) with springs or spring hinges. ditto 110.00 659.15 ditto 1183.60 7092.45
13 Making and fixing trellis doors and windows of deodar Per Sft. 183.35 693.40 sq.m 1972.85 7461.00 26.1
wood, complete. 26.2
a) M.S. angle iron 1½"x 1½"x ¼" (40x40x6 mm) welded Per Sft. 43.95 262.55 sq.m 472.90 2825.05
with M.S. flat 2"x ¼" (50 mm x 6 mm)
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
b) M.S. tee iron 1½"x 1½"x ¼" (40x40x6 mm) welded Per Sft. 43.95 200.45 sq.m 472.90 2156.85
with M.S. flat 2"x ¼" (50 mm x 6 mm)
16 Extra for providing and fixing iron double spring hinges, Per Sft. 6.30 27.10 sq.m 67.80 291.60 26.2
with brass fittings (it shall include brass finger plate, 6" door area door area
(150 mm) tower bolt).
17 Providing and fixing brass spring hinges to wire gauzed Each 132.00 284.40 Each 132.00 284.40
doors.
i) iron sliding bolt, 10" (250 mm) long Each 123.75 327.75 Each 123.75 327.75
ii) iron sliding bolt, 12" (300 mm) long ditto 123.75 399.75 ditto 123.75 399.75
iii) brass sliding bolt, 10" (250 mm) long ditto 123.75 603.75 ditto 123.75 603.75
iv) brass sliding bolt, 12" (300 mm) long ditto 123.75 384.15 ditto 123.75 384.15
i) deodar wood panelled or panelled and Per Sft. 3.75 28.80 sq.m 40.35 309.90
glazed or fully glazed.
ii) deodar wood wire gauzed shutters. ditto 3.75 18.95 ditto 40.35 203.90
20 Extra for providing and fixing approved quality rim lock Each 396.00 686.40 Each 396.00 686.40
adjustable over the style surface.
21 Providing and fixing, approved quality mortice lock. Each 550.00 661.60 Each 550.00 661.60
a) fixed to chowkat with 1" (25 mm) thick deodar wood Per Sft. 82.50 325.70 sq.m 887.70 3504.55
strip and screws, etc.
b) fixed with 1" (25 mm) cover moulding and screws, ditto 82.50 450.40 ditto 887.70 4846.30
including deodar wood frame 2"x2" (50 x 50 mm)
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
23 a) Providing and fixing deodar wood almirah 9" to 12" For hollow frame shutter with
(225 mm to 300 mm) depth, including boxing with Per Sft. 264.00 2097.90 sq.m 2840.65 22573.65 commercial ply on one side, the
back, shelves, shutter and brass fittings, etc. composite rate shall be reduced by
complete. Rs.54.00 per Sft;or Rs.580.00
per Sqm and for hollow frame
shutter with commercial ply on
both sides, the composite rate
shall be reduced by Rs.22.80 per
Sft. or Rs.245.00 per Sq. metre.
b) Providing and fixing deodar wood almirah 9" to 12"
(225 mm to 300 mm)depth with shelves, shutters, Per Sft. 198.00 804.15 sq.m 2130.50 8652.75
brass fittings, etc., without boxing and back,
complete.
24 Providing and fixng class room almirah consiting of 1" (25 Per Sft. 146.65 477.70 Sq.m 1578.15 5140.15
mm) thick solid flush shutter with deodar wood lipping ¼" (6 mm)
thick all around (Approved Factory Manufactured) fixed in deodar
wood frame 3"x1" (75mm x 25mm) including full hinges
C.P. fittings with RCC (1:1½:3) shelves 1½" (40 mm) thick
including 3 coats of painting.
25 Providing and fixing wooden box type wardrobe 22" (550 If hollow flush door leaves 1" thick
mm) deep including ¾" (20 mm) thick boxing and shelves, (25 mm) with commercial ply
hanger rods, hard board back drawers, brass fittings, 3 ply) on both sides of deodar
locking arrangements, handles, internal bolts, shoe rods, wood frame and partal wood
etc. including three coats of enamel paint:- bracing and deodar wood lipping is
used, the composite rate will be
i) Partal wood boxing and deodar wood reduced by Rs.13.00 per Sft. or
shelves and leaves, etc. Per Sft. 304.60 1068.10 sq.m 3277.65 11492.85 Rs.140.00 per Sq. metre.
ii) Deodar wood boxing, and deodar wood ditto 297.00 1402.95 ditto 3195.70 15095.95
shelves and leaves, etc.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
a) 1" (25 mm) thick Sft. 66.00 431.10 sq.m 710.15 4638.75
b) ¾" (20 mm) thick ditto 66.00 339.70 ditto 710.15 3655.40
c) ½" (13 mm) thick ditto 66.00 248.70 ditto 710.15 2676.15
i) 1" (25 mm) thick Sft. 66.00 431.10 sq.m 710.15 4638.75
ii) 1½" (40 mm) thick ditto 66.00 613.50 ditto 710.15 6601.40
iii) 2" (50 mm) thick ditto 66.00 795.90 ditto 710.15 8564.00
30 a) Making and fixing cleats for doors and windows, Each 79.20 190.70 Each 79.20 190.70 26.1 and
including hinges and screws. 26.2
b) Making and fixing cleats with brass hooks for roof Each 105.60 184.40 Each 105.60 184.40
ventilators.
c) Providing and fixing door stops of 1½" (40 mm) dia Each 11.00 64.10 Each 11.00 64.10
rubber block.
d) Providing and fixing G.I. hook with clamps for doors. Each 3.50 12.45 Each 3.50 12.45
32 Deodar wood dado or picture rail 3"x1½" (75x40 mm) as Per Rft. 109.55 344.15 Metre 359.35 1128.85 26.1
per approved design including moulding and fixed in place, 26.2
cost of screws, nails, plugs, and painting complete.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
35 Making and fixing sun-shade of deodar wood including Per Sft. 92.40 527.85 sq.m 994.20 5679.75 26.1
fixing brackets.
36 Making and fixing 1" (25 mm) thick kail or chir wooden ditto
notice board with frame. Per Sft. 110.00 243.10 sq.m 1183.60 2615.75
37 Making deodar punkha pole 10'x6"x6" Each 396.00 10308.00 Each 396.00 10308.00 ditto
(3.0 m x 150 mm x 150 mm)
38 Dismantling and refixing eave boards. Per Rft. 28.30 -- Metre 92.80 --
39 Making wooden stair-cases complete 2' to 3' (600 to 900 Per Rft. 431.20 3269.75 Metre 1414.35 10724.75 26.1
mm) wide frame 1½" (40 mm) thick planks of deodar
wood, including hand rails.
i) ¾" (20 mm) thick 100Sft. 4468.75 15045.75 sq.m 480.85 1618.90
ii) 1" (25 mm) thick ditto 4468.75 15242.10 ditto 480.85 1640.05
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
i) ¾" (20 mm) thick 100Sft. 4468.75 10073.25 sq.m 480.85 1083.90
ii) 1" (25 mm) thick ditto 4468.75 10325.25 ditto 480.85 1111.00
b) Glazing with panes (16 oz. to 18 oz.) Per Sft. 59.40 126.75 sq.m 639.15 1364.05
using deodar wooden fillets and putty.
45 Glazing with panes (24 oz. to 26 oz.), using Per Sft. 86.90 150.10 sq.m 935.05 1615.10 26.12
putty and deodar wooden fillets.
46 a) Cutting to required size and fixing glass Per Sft. 33.00 34.10 sq.m 355.10 367.05
panes with putty
b) Cutting to required size and fixing glass panes with Per Sft. 49.50 74.50 sq.m 532.60 801.35
wooden fillets and putty.
47 Glazing with plate glass 1/4" (6 mm) thick including the cost
of deodar wood fillets and putty:-
a) Glazing upto 8 sft (0.75 sq.m) Per Sft. 75.90 207.45 sq.m 816.70 2232.15
b) Glazing exceeding 8 Sft (0.75 sq.m) but not exceeding 24 sft Per Sft. 75.90 207.65 sq.m 816.70 2234.25
(2.25 sq.m).
i) M.S. angle iron 1½"x1½"x¼", welded Per Sft. 282.10 1117.30 sq.m 3035.30 12022.00
i) (40 mmx 40 mmx 6mm) with M.S. flat
2"x¼" (50 mm x 6 mm)
ii) M.S. tee iron 1½"x1½"x¼", welded Per Sft. 282.10 1029.75 sq.m 3035.30 11080.20
(40 mmx40 mmx 6mm) with M.S. flat
½"x¼" (13 mm x 6 mm)
49 Providing and fixing 1½" (40 mm) thick hollow flush doors Teak ply would be used under the
and windows with commercial ply (3 ply) on both faces of written permission of the
deodar wood shutter frame 1¼" (30 mm) thick and partal superintending Engineer, and the
wood braces at about 3" (75 mm) apart and deodar wood composite rate of using teak ply
lipping 1½"x3/8" (40 mmx10 mm) fixed with M.S. chowkat will be increased by Rs.20.00 per
(frame) including chromium plated fittings, etc. complete Sft. ( 216.00 per Sq.m)
in all respects (without sliding bolt or lock):-
i) M.S. angle iron 1½"x1½"x¼", welded Per Sft. 195.55 866.55 sq.m 2104.20 9324.20
(40 mmx40 mmx 6mm) with M.S. flat
2"x¼" (50 mm x 6 mm)
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
ii) M.S. tee iron 1½"x1½"x¼", welded Per Sft. 195.55 804.45 sq.m 2104.20 8656.00
(40 mmx40 mmx 6mm) with M.S. flat
½"x¼" (13 mm x 6 mm)
50 Providing and fixing 1½" (40mm) thick solid flush door shutter It C.P. Finger plate and kick plate
(Approved Factory Manufactured) with commercial ply (5 mm thick) are not provided/fixed the
on both sides double pressed and deodar wood lipping Per Sft. 107.75 409.20 sq.m 1159.45 4403.00 composite rate will be reduced by
1½"x3/8" (40mm x 10mm) around shutter including Rs.15.20 per Sft.
chromium plated fitting, iron hinges with aluminium kick Reduce composite rate by Rs.20.00
plate 22 SWG on both sides & finger plate complete in all per. Sq/ft or Rs.215 per sq.meter if
respect. 3-mm commmercial ply is used
51 Providing and fixing panelled door of M.S. sheet, with Per Sft. 179.75 540.65 sq.m 1933.90 5817.40
forged door leaves of M.S. sheet 22 SWG fitted in hollow
frame chowkat 3"x4½" (75 mmx113 mm) made of M.S.
sheet 18 SWG filled with plain cement concrete 1:3:6 etc.
complete with all fittings and hammer painting, including
carriage to site and fixing in position.
52 Providing and laying 24 SWG aluminum kick plate 4" (100 Per Rft. 39.60 55.80 Metre 129.90 183.00
mm) high, fixed with screws 4" (100 mm) centre to centre,
on bottom rail of flush doors only of commercial ply.
53 Providing and fitting curtain railing to doors and windows, Per Rft. 16.50 165.55 Metre 54.10 543.05
comprising of TOSO-elite Japan made superior type of
railing or equivalent, fixed over 4"x¾" (100mmx20mm)
deodar wood strip, including painting.
54 Providing and fixing M.S. flat ½"x1/8" (13mm x 3mm) grill Per Sft. 95.05 321.70 sq.m 1022.65 3461.60
including ¾" x 1/8" (20 mmx3 mm) M.S. flat frame, in
windows of approved design, including painting three
coats, complete in all respects.
55 Providing and fixing G.I. wire gauze 22 SWG, 12x12 Per Sft. 33.60 108.80 sq.m 361.55 1170.50 It 24 SWG wire gauze is used, the
2
meshes per square inch, (5x5 meshes in cm ) fixed to composite rate shall be reduced by
steel window, complete with flat iron patti ½"x 1/8" (13 Rs.4.70 per Sft. or Rs.50.60 P.SQM
mmx3 mm) and machine made screws.
a) Teak wood moulding Per Sft. 41.25 275.05 sq.m 443.85 2959.40
b) Deodar wood moulding ditto 41.25 97.40 ditto 443.85 1048.15
57 Providing and fixing deodar wood dolly frame having Rate shall be paid as per surface
1½"x1½" (40 x 40 mm) vertical and horizontal double post area of dolly frame
with 1½"x1½" (40 x 40 mm) full width of james braces at e-g 0.75' x (3.5' + (2 x 7))
12" (300 mm) including filling of the spaces in between
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
a) Teak wood ply Per Sft. 101.55 435.90 sq.m 1092.55 4690.20
b) With commercial ply ditto 101.55 429.75 ditto 1092.55 4624.00
a) Teak wood architrave Per Sft. 17.80 176.15 sq.m 191.30 1895.20
b) Deodar wood architrave ditto 17.80 55.10 ditto 191.30 592.90
2 The rates for all finished works include the removal of surplus debris, unused material and by products
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
1 a) Cleaning painted wood work with oil and water. 100 Sft. 198.00 255.60 sq.m 21.30 27.50
b) Oiling woodwork with boiled linseed oil. 100 Sft. 132.00 183.35 sq.m 14.20 19.75 27.7
2 Brushing and scraping blisters of old paints from 100 Sft. 396.00 -- sq.m 42.60 - 27.3
woodwork.
3 Scraping, brushing and removing old paint from metal 100 Sft. 1584.00 -- sq.m 170.45 - 27.9
surface.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
i) first coat 100 Nos. 783.75 964.95 100 Nos. 783.75 964.95
ii) each subsequent coat ditto 707.15 808.55 ditto 707.15 808.55
i) first coat 100 Nos 1791.45 2327.85 100 Nos 1791.45 2327.85
ii) each subsequent coat ditto 1037.15 1305.35 ditto 1037.15 1305.35
i) priming coat. 100 Nos. 1155 1713.15 100 Nos. 1155 1713.15
ii) each subsequent coat of paint. ditto 569.80 1012.00 ditto 569.80 1012.00
chapter-13(Painting & Var).xls Page 88
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
i) priming coat. 100 Nos. 3300.00 4207.20 100 Nos. 3300.00 4207.20
ii) each subsequent coat of paint. ditto 990.00 1780.20 ditto 990.00 1780.20
h) Extra for knotting and stopping to 100 Sft. 52.80 68.45 sq.m 5.70 7.35
priming coat on new surface of wood.
i) 20 lbs. per 100 Sft. (9.07 Kg per Sq.m) 100 Sft. 330.00 1442.05 sq.m 35.50 155.15
ii) 14 lbs. per 100 Sft. (6.35 Kg per Sq.m) ditto 316.80 886.15 ditto 34.10 95.35
iii) 10 lbs. per 100 Sft. (4.54 Kg per Sq.m) ditto 261.35 830.75 ditto 28.10 89.40
10 Writing letters or figures, per letter, per inch (25 mm) Per No. 15.40 16.15 Per No. 15.40 16.15 27.1
height.
11 Writing letters or figures at any surface with reflective paint Per Letter 15.40 15.90 Per Letter 15.40 15.90 27.1
of approved quality and colour per letter per inch height. per inch per 25 mm
height height
12 Writing letters of figures on any surface with reflective tape ditto 18.15 19.05 ditto 18.15 19.05 ditto
of approved quality and colour per letter per inch (25 mm)
height.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
a) one coat, applied hot 100 Sft. 290.40 337.20 sq.m 31.25 36.30
b) two coats, applied hot ditto 440.00 514.30 ditto 47.35 55.35
a) one coat, applied hot 100 Sft. 348.50 473.30 sq.m 37.50 50.95
b) two coats, applied hot ditto 528.00 734.90 ditto 56.80 79.05
16 Burning off or rubbing down with pumice stone, old paint 100 Sft. 1254.00 1269.60 sq.m 134.95 136.60 27.3
from wood work.
17 Removing with caustic soda, old paint from wood work. 100 Sft. 396.00 403.75 sq.m 42.60 43.45 ditto
18 Painting distance marks for white ground and black Each 77.00 85.65 Each 77.00 85.65 27.1
lettering on both sides.
19 Painting two feet wide gauges, reading to 10th of a foot Per Rft. 154.00 171.05 per Metre 505.10 561.00 ditto
(metre).
20 Painting sounding rods and other gauges, reading to 10th Per Lft. 77.00 82.40 per Metre 252.55 270.25 27.1
of a foot (metre)
21 Painting leveling staves. Per Lft. 242.00 250.50 per Metre 793.75 821.70
23 Removing paint or varnish from wall. 100 Sft. 792.00 - sq.m 85.20 - 27.12
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
25 Painting letters with shade. per letter 24.65 24.65 per letter 24.65 24.65 27.1
per inch per 25 mm
height height
26 Scraping rust from old rail or girders. 100 Sft. 1188.00 1242.00 sq.m 127.85 133.65 27.9
27.10
27 Chiselling old paint from brick work. 100 Sft. 1584.00 1616.40 sq.m 170.45 173.95 27.12
28 Cleaning glasses with chalk and spirit, etc. 100 Sft. 1320.00 1348.00 sq.m 142.05 145.05
29 Cleaning and oiling rafter or rolled steel 100 Sft. 396.00 438.85 sq.m 42.60 47.20 27.9
beams.
30 Cleaning and painting punkha poles, including fixing Each 330.00 338.85 Each 330.00 338.85 27.3
hooks.
a) new surface:
b) old surface:
a) new surface:
33 Painting traffic lane 5" (125 mm) wide, with road marking Per Rft. 2.30 3.70 Metre 7.60 12.15
enamel.
chapter-13(Painting & Var).xls Page 91
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
34 Painting traffic lane 5" (125 mm) wide with reflective Per Rft. 2.95 11.20 Metre 9.75 36.80 AASHTO Rates shall be reduced by Rs.0.50
clorinated rubber (CR) paint including glass beads comlpete M248-91 P.Rft or Rs.1.65 P.Mtr.
in all respect. (2000) If glass beads are not used.
35 Repainting of ceiling fan (all sizes and types), including Per Job 94.30 134.80 Job 94.30 134.80
painting of blades, canopy, suspension rod and regulator,
with suitable enamel paint.
36 Repainting of iron poles with cross arms, with bitumen or Per Job 220.00 347.50 Job 220.00 347.50
other approved paint.
i) upto 40 mm (1½") dia Per Rft. 2.00 6.60 Metre 6.60 11.40
ii) above 40 mm (1½") to 50 mm (2") dia ditto 4.00 6.30 ditto 13.20 20.75
iii) above 50 mm (2") to 100 mm (4") dia ditto 6.70 10.15 ditto 22.00 33.30
38 Repainting main switches and branch distribution boards Per Job 43.55 101.05 Job 43.55 101.05
of all sizes and types, with approved paint (complete set).
39 Extra labour for painting, varnishing, etc. from 20' (6.10 m) 100 Sft. 126.70 - sq.m 13.65 - The height will be taken from the
height and above, for every additional 10' (3.05 m) height, per coat floor, roof or ground underneath, as
or part thereof, requiring scaffolding. the case may be on the side
towards which the work is to be
done.
40 Painting Traffic Lanes 5" wide (125mm), (1.5 mm thick), with * 1205-1 Payment will be made as per actual
thermoplastic (TP) Paint including Glass Beads, complete in al respect. to measurement.
1205-8
i) 5" wide Per Rft. 4.25 32.40 Metre 14.00 106.30
ii) 6" wide Per Rft 4.25 37.50 Meter 14.00 122.90
41 Lettering and printing of signage / direction boards / road delineators of
any colour by machine i/c cost of Digital Lettering, Lamination & pasting
etc complete in all respect.
a) High Intensity Prismatic (HIP) Tape P.Sft 96.25 936.25 Sq.m 1035.65 10074.05
b) Diamond Grade Tape P.Sft 96.25 1116.25 Sq.m 1035.65 12010.85
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
2 Stabilized layer of cement, sand ratio 1:30, 2" (50 mm) 100Sft. 2138.40 2800.80 sq.m 230.10 301.35 ditto
thick on slope.
6 Tile lining 12"x6"x2" (300x 150x50 mm) in 1:6 cement, 28.2 to 28.3 The rates are only for laying tiles
sand mortar:- over 1/8" (3 mm) thick layer of 1:6
mortar. Items 1 to 5 above are
a) in bed 100Cft. 9042.00 21166.55 cu.m 3193.65 7476.05 payable separately.
b) on slope ditto 10362.00 22486.55 ditto 3659.85 7942.25
7 Tile lining 12"x6"x2" (300x150x50 mm) in 28.2 to 28.3 The rates are only for laying tiles
1:3 cement, sand mortar:- over 1/8" (3 mm) thick layer of 1:3
mortar. Items 1 to 5 above are
a) in bed 100Cft. 9042.00 22956.00 cu.m 3193.65 8108.05 payable separately.
8 Brick lining 9"x4½"x3" (225x113x75 mm) in 1:6 cement, 28.2 The rates are only for laying bricks
sand mortar:- over 1/8" (3 mm) thick layer of 1:6
mortar. Items 1 to 5 above are
a) in bed 100Cft. 9042.00 29770.55 cu.m 3193.65 10514.95 payable separately.
b) on slope ditto 10362.00 31090.55 ditto 3659.85 10981.20
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
9 Brick lining 9"x4½"x3" (225x113x75 mm), in 1:3 cement, ditto The rates are only for laying
sand mortar:- bricks over 1/8" (3 mm) thick
layer of 1:3 mortar. Items 1 to
a) in bed 100Cft. 9042.00 31560.00 cu.m 3193.65 11147.00 5 above are payable
b) on slope ditto 10362.00 32880.00 ditto 3659.85 11613.20 separately.
a) in bed:-
b) on slope:-
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
1 Cutting Ransome and Larson piles. Per 264.00 - Per 264.00 - 29.1-
cut cut 29.3
2 Cutting universal piles. Per cut 390.70 - Per cut 390.70 - ditto
3 Driving steel piles, 25' to 30'. (7.5 to 9.0 m) 100Sft. 6072.00 - sq.m 653.35 - ditto 1) The rate includes laying and
removing of track and also carriage
of piles to machine, average
distance of 3 chains (90 metre).
4 Driving steel piles,more than 15' (4.6 m) and less than 25' 100Sft. 5808.00 - sq.m 624.95 - ditto ditto
(7.5 m).
5 Driving steel piles, 15' (4.5 m) and under. 100Sft. 4224.00 - sq.m 454.50 - ditto ditto
6 Dolleying piles. Each 369.60 - Each 369.60 - ditto Upto 5' (1.5 m) dolleying.
8 Raising and lowering machine. Per Ft. 5720.00 - Metre 18761.60 - ditto
o.
9 Turning Machine, 90 Per 8184.00 - Per 8184.00 - 29.1 to
Job Job 29.3
o
10 Turning Machine, 135 . Per 10296.00 - Per 10296.00 - ditto
Job Job
o
11 Turning Machine, 180 . Per 13992.00 - Per 13992.00 - 29.1 to
Job Job 29.3
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
13 Loading and unloading piles. Ton 293.05 - Tonne 288.40 - ditto To be done by hand carts or
ramps, including cost of ropes.
16 Carriage of piling machine under different conditions. per 6666.00 - 30 M 6666.00 - ditto
chain
i) the cost of the carriage within one mile (one Km) shall not be deducted from the carriage charges to follow thereafter
from the point of supply.
ii) if the site of work happens to be within one mile (one Km.) of the source of supply, the materials will be collected
and measured at site of work and no extra carriage would be admissible in such cases.
iii) where the site of the work is situated at more than one mile (one Km.) distance from the source of supply, the point
of supply will be fixed carefully by the Engineer-in-charge in such a way that the carriage charges would
be arrived at, most economically. Extra carriage will be admissible from the place of supply of the
material which will be considered its starting point. The demarcation of the place of supply will be
pre-determined before calling the tenders.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
1 Cutting pilchi frash or sarkanda inlcuidng carriage within 100Cft. 1504.80 cu.m 531.40
one mile.
3 a) Supplying and filling jute bags 1.25 (o.o35 cum) Cft., Per 44.55 59.40 Per Baq 44.55 59.4 The rate does not include supply of
capacity, with sand or earth, sewing and stacking, in Bag sand or earth for filling bags, which
dry. will be paid extra.
b) Supply and filling jute bags 1.25 (0.35 ccum) Cft. ditto 69.30 84.15 Per Baq 69.30 84.15 -ditto-
capacity, with sand or earth, sewing and laying in
position, under water.
4 a) Supplying and filling jute bags 4 to 5 cft Per 106.60 160.05 Per 106.60 160.05 The rate does not include supply of
(0.11 to 0.14 cum) capacity, with sand or earth, Bag Bag sand or earth for filling bags, which
sewing and stacking, in dry. will be paid extra.
b) Supply and filling new jute bags 4 to 5 cft (0.11 to ditto 152.30 205.75 ditto 152.30 205.75 -ditto-
0.14 cu.m) capacity, with sand or earth, sewing and
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
b) 2nd to 4th chain (30 m to 120 m) Per chain 142.55 Per 30 m 142.55
per 100 Per 100 Nos/
Nos
b) 2nd to 4th chain (60 m to 120 m) per chain 554.40 Per 30 m 554.40
per 100Nos per %Nos
c) 5th and subsequent chains (150 m and ditto 213.85 ditto 213.85
subsequent every 30 m)
8 Sewing empty cement bags in sheets. 100 Nos 1386.00 1421.85 % Nos 1386.00 1421.85
9 Making compact round pilchi, frash or sarkanda round 100Cft. 1930.50 2033.70 cu.m 681.85 718.3 Measured in the shape of compact
bundles of specified size for the work. round bundles and of size specified
for the work, before filling at site.
10 Launching the above and placing in position. 100Cft. 950.40 cu.m 335.65
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
a) Boulders 9" (225 mm) and above 100Cft. 2867.05 cu.m 1012.50
b) Over size shingle 3" to 9"(75 to 225 mm) ditto 1916.65 ditto 676.85
12 Supplying Munj or Patha Trungers 6" (150 mm) mesh to hold Each 123.75 168.65 Each 123.75 168.65
3 Cft. (0.085 cu.m)
13 Providing and weaving G.I. wire netting for wire crates, with
G.I. wire of approved size (including siding and partition to
make crate):-
14 Providing and laying shingle on top of bund, including 100Cft. 990.00 1452.00 cu.m 349.60 512.80
handling of materials within three chains.
a) stone or boulder 100Cft. 1732.50 3052.50 cu.m 611.85 1078 The rate includes supply of brick
b) shingle or spawl ditto 1732.50 2194.50 ditto 611.85 775 bats to site of work.
c) brick bats ditto 1336.50 4240.50 ditto 472.05 1497.75
16 Supply and dumping by boat, including loading into boat The rate includes supply of brick
within three chains (90 m) lead, and hire charges of boat and bats to site of work.
boatman.
17 Providing and filling brick bats in crates 100Cft. 2607.00 5511.00 cu.m 920.80 1946.5 The rate includes supply of brick
(excluding cost of crates). bats to site of work.
18 Supplying and filling bricks in crates and hand packing 100Cft. 3102.00 22902.00 cu.m 1095.65 8089 The rate includes supply of bricks
(excluding cost of crates). to site of work.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
20 Extra for anchoring boat, for dumping by boats or tipping 100Cft. 348.50 - cu.m 123.10 -
crates.
21 Extra for tipping crates (in addition to anchoring boats). 100Cft. 1742.40 - cu.m 615.40 -
22 Pilchi reventment, including carriage upto one mile 100Sft. 990.00 1500.00 sq.m 106.50 161.4 30.1
(1.6 km.)
23 Surface protection with pilchi matresses, carriage upto 100Sft. 2475.00 2526.00 sq.m 266.30 271.80 ditto
one mile (1.6 Km).
24 Pilchi, sarkanda or frash pitching on slopes, including The cost of placing earth between
supply of pilchi, sarkanda or frash within one mile, (1.6 km) 100Sft. 6681.65 7795.05 sq.m 718.95 838.75 rolls shall be paid separately, as
also supply and driving of pegs 1½' (460 mm) long earthwork.
sharpened at one end and, tying with wire or Munj Ban
(excluding cost of placing earth between rolls).
25 Constructing Groynes upto 5' (1.5 m) height, with single 100Sft. 2112.00 2215.20 sq.m 227.25 238.35 Measurement to be made of the
row of wooden vertical stakes 7" to 12" (175 to 300 mm) area of elevation on one face only.
dia, 1' (300 mm) apart, average lead one mile (1.6 km.)
26 Construction Groynes upto 10' (3.0 m) height, with double 100Sft. 3564.00 3686.40 sq.m 383.50 396.65
row of wooden vertical stakes 7" to 12" (175 to 300 mm)
dia, 2' (600 mm) apart, average lead one mile (1.6 Km).
27 Providing and laying stone pitching/filling, dry hand 100Cft. 2310.00 3201.00 cu.m 815.90 1130.6
packed, as filling behind retaining walls or in pitching and
aprons.
28 Providing and laying stone pitching with hammer dressed 100Cft. 5940.00 6732.00 cu.m 2098.00 2377.75
stones on surface, laid in courses.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
33 Sand grouting in stone apron, with high 100Sft. 759.00 1599.00 sq.m 81.65 172.05
pressure hose.
34 Grouting stone filling or pitching, with bajri. 100Cft. 1237.50 2425.50 cu.m 437.10 856.7
35 Removing stone and repitching hand packed, on slopes or 100Cft. 4633.20 - cu.m 1636.45 -
level after making good damaged slope/portion.
36 Collecting and stacking boulders from nullah beds or loose 100Cft. 1584.00 - cu.m 559.45 -
shale, or from any other site, within 3 chains (90 m) lead.
37 Levelling and dressing stone filling under blocks and 100Cft. 1320.00 2508.00 cu.m 466.20 885.85
grouting with shingle.
38 Grouting jharies between blocks with bajri. 100Cft. 1320.00 2112.00 cu.m 466.20 745.95
39 Breaking stone into spawls and stacking 100Cft. 1188.00 - cu.m 419.60 -
a) upto 2.0' (600 mm) F.S. depth Each 41.35 - Each 41.35 -
b) above 2.0' to 3.0' (600 to 900 mm) F.S. depth ditto 46.55 - ditto 46.55 -
c) above 3.0' to 4.0' F.S. (900 mm to 1200mm) depth Each 62.05 - ditto 62.05 -
d) above 4.0' (1200 mm) F.S. depth ditto 155.10 - ditto 155.10 -
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
a) i) Cutting and supply unsharpened pegs 3.5' (1.07 100 Nos 1980.00 2012.55 % Nos 1980.00 2012.55
m) long, 3" to 6" (75 to 150 mm) dia, within one mile
(1.6 Km) lead.
ii) Sharpening one end of 3.5' (1.07 m) long pegs, 3" 100 Nos 924.00 - 100 Nos 924.00 -
to 6" (75 to 150 mm) dia.
iii) Driving pegs 3.5' (1.07 m) long, 3" to 6" (75 to 150 100 Nos 1478.40 - 100 Nos 1478.40 -
mm) dia (driven 1.0' (300 mm) below the available bed
or ground (average).
iv) Tying pegs with Munj, Patha ban (one line, Per Chain 99.00 130.20 Per 30 99.00 130.20
incuding tying around the pegs). of One Metre
Row of one
row
v) Cutting and supplying brush wood from canal ditto 1511.10 1685.90 ditto 1511.10 1685.90
plantation or private owners, lead within one mile
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).
b) i) Cutting and supplying unsharpened pegs 4.0' 100 Nos 87.65 124.65 100 Nos 87.65 124.65
(1.20 m) long, 3" to 6" (75 to 150 mm) dia, from canal
plantation, lead within one mile (1.6 Km).
ii) Sharpening one end of 4' (1.20 M) long pegs, 3" 100 Nos 924.00 - 100 Nos 924.00 -
to 6" (75 to 150 mm) dia.
iii) Driving pegs 4' (1.20 m) long, 3" to 6" (75 to 150 100 Nos 1634.15 - 100 Nos 1634.15 -
mm) dia (driven 1.0' (300 mm) below the available bed
or ground (average).
iv) Tying pegs with Munj, Patha ban (one line, Per 99.00 Per 99.00
incuding tying around the pegs). Chain of 30 M of
one row one row
v) Cutting and supplying brush wood from canal ditto 3795.00 ditto 3795.00
plantation or private source, lead within one mile
(1.6 Km). and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).
c) i) Cutting and supplying unsharpened pegs 5.0' (1.5 100 Nos 109.60 155.95 100 Nos 109.60 155.95
m) long, 3" to 6" (75 to 150 mm) dia, from canal
plantation, lead within one mile (1.6 Km).
ii) Sharpening one end of 5' (1.5 m) long pegs, 3" to 100 Nos 976.80 - 100 Nos 976.80 -
6" (75 to 150 mm) dia.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
iii) Driving pegs 5' (1.5 m) long, 3" to 6" (75 to 150 100 Nos 1848.00 - 100 Nos 1848.00 -
mm) dia (driven 1.5' (450 mm) below the available bed
or ground (average).
iv) Tying pegs with Munj, Patha ban (one line, Per 99.00 130.20 Per 99.00 130.20
incuding tying around the pegs). Chain of 30 M
one row of one
row
v) Cutting and supplying brush wood from canal Per chain 1980.00 2224.60 Per 30 M 1980.00 2224.60
plantation or private source, lead within one mile of one row of one row
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).
d) i) Cutting and supplying unsharpened 100 Nos 3960.00 4015.60 100 Nos 3960.00 4015.6
pegs 6.0' (1.8 m) long, 3" to 6" (75 to
150 mm) dia, from canal plantation, lead
within one mile (1.6 Km).
ii) Sharpening one end of 6' (1.8 m) long pegs, 3" to 100 Nos 1161.60 - 100 Nos 1161.60 -
6" (75 to 150 mm) dia.
iii) Driving pegs 6' (1.8 m) long, 3" to 6" (75 to 150 100 Nos 2217.60 - 100 Nos 2217.60 -
mm) dia (driven 1.75' (530 mm) below the available
bed or ground (average).
iv) Tying pegs with Munj, Patha ban (one line, Per Per Chain
incuding tying around the pegs). Chain of 99.00 130.20 of one row 99.00 130.20
one row
v) Cutting and supplying brush wood from canal ditto 4290.00 4587.05 ditto 4290.00 4587.05
plantation or private source, lead within one mile
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).
e) i) Cutting and supplying unsharpened pegs 6'-1" to 100 Nos 2970.00 3085.30 100 Nos 2970.00 3085.30
8.0' long (1.85 to 2.45 m), 4" to 8" (100 to 200 mm)
dia, from canal plantation, lead within one mile
(1.6 Km).
ii) Sharpening one end of 6'-1" to 8.0' (1.85 to 2.45m) 100 Nos 1478.40 - 100 Nos 1478.40 -
long pegs, 4" to 8" (100 to 200 mm) dia.
iii) Driving pegs 6'-1" to 8.0' (1.85 to 2.45 m) long, 3" 100 Nos 2442.00 - 100 Nos 2442.00 -
to 6" (75 to 150 mm) dia driven 2' (600 mm) below
the available bed or ground (average).
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
iv) Tying pegs with Munj, Patha ban (one line, Per chain 99.00 116.30 Per 30 M 99.00 116.3
incuding tying around the pegs). of one row of one row
v) Cutting and supplying brush wood from canal Per 4950.00 5299.45 Per 30 M 4950.00 5299.45
plantation or private source, lead within one mile Chain of of one row
(1.6 Km) and wattling between stakes and intertwining one row
(thickness of wattled brushwood 1.0' (300 mm)
average).
a) i) Supplying Bamboos 8'-1" to 10.0' (2.46 to 3.05 m) 100 Nos 7200.00 - 100 Nos 7200.00 -
long, 2½" to 5" (63 m to 125 mm) dia.
ii) Sharpening one end of 8'-1" to 10.0' (2.46 to 30.5 100 Nos 1293.60 - 100 Nos 1293.60 -
m) long Bomboos, 2½" to 5" (63 to 125 mm) dia.
iii) Driving Bamboos 8'-1" to 10.0' (2.46 to 3.05 m) 100 Nos 2679.60 - 100 Nos 2679.60 -
long 2½" to 5" (63 to 125 mm) dia, driven 2.5' (750
mm) below the available bed or ground (average).
iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per Per 30 M
Munj, Patha Ban, two lines, including tying around Chain of 148.50 197.45 of one 148.50 197.45
the Bamboos. one row Row
v) Cutting and supplying brushwood from canal ditto 6105.00 6558.85 ditto 6105.00 6558.85
plantation or private source, lead within one mile
(1.6 Km), and wattling between stakes and
intertwining (thickness of wattled brushwood 1.0'
(300 mm) average).
b) i) Supplying Bamboos 10'-1" to 12.0' (3.07 to 3.66 100 Nos - 10800.00 100 Nos - 10800
m) long, 2½" to 5" (63 to 125 mm) dia.
ii) Sharpening one end of 10'-1" to 12.0' 100 Nos 1478.40 - 100 Nos 1478.40 -
(3.07 to 3.66 m) long Bamboos, 2½" to
5" (63 to 125 mm) dia.
iii) Driving Bamboos 10'-1" to 12.0' (3.07 to 3.66 m) 100 Nos 2904.00 - 100 Nos 2904.00 -
long 2½" to 5" (63 to 125 mm) dia, driven 2.75'
(840 mm) below the available bed or ground (average).
iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per chain Per 30 M
S.W.G. No. 10 wire, two lines, including tying around of one 495.00 1541.90 of one Row 495.00 1541.90
the Bamboos and third tie around the top end only. row
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
v) Cutting and supplying brushwood from canal ditto 7425.00 8001.60 ditto 7425.00 8001.60
plantation or private source, lead within one mile
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' ( 300 mm)
average).
c) i) Supplying Bamboos 12'-1" to 14.0' (3.68 to 4.27 100 Nos - 11400.00 100 Nos - 11400.00
m) long, 2½" to 5" (63 to 125 mm) dia.
ii) Sharpening one end of 12'-1" to 14.0' (3.68 to 4.27 100 Nos 1663.20 - 100 Nos 1663.20 -
m) long Bamboos, 2½" to 5" (63 to 125 mm) dia.
iii) Driving Bamboos 12'-1" to 14.0' (3.68 to 4.27 m) 100 Nos 3326.40 - 100 Nos 3326.40 -
long 2½" to 5" dia, driven 3.5' (1.07 mm) below the
available bed or ground (average).
iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per chain Per 30 M
S.W.G. No. 10 wire, two lines, including tying around of one row 495.00 1541.90 of one row 495.00 1541.90
the Bamboos and third tie around the top end only.
v) Cutting and supplying brushwood from canal ditto 8745.00 9409.00 ditto 8745.00 9409.00
plantation or private source, lead within one mile
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).
d) i) Supplying Bamboos 14'-1" to 16.0' (4.30 to 4.90 m) 100 Nos - 12600.00 100 Nos - 12600.00
long, 2½" to 5" (63 to 125 mm) dia.
ii) Sharpening one end of 14'-1" to 16.0' (4.30 to 100 Nos 1848.00 - 100 Nos 1848.00 -
4.90 m) long Bamboos, 2½" to 5" (63 to 125 mm) dia.
iii) Driving Bamboos 14'-1" to 16.0' long (4.30 to 4.90m) 100 Nos 3696.00 - 100 Nos 3696.00 -
2½" to 5" (63 to 125 mm) dia, driven 4' (1.20 m)
below the available bed or ground (average).
iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per Chain Per 30 M
S.W.G. No. 10 wire, two lines, including tying around of one 495.00 1541.90 of one 495.00 1541.90
the Bamboos and third tie around the top end only. Row Row
v) Cutting and supplying brushwood from canal ditto 10098.00 10866.80 ditto 10098.00 10866.80
plantation or private source, lead within one mile
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).
e) i) Supplying Bamboos 16'-1" to 20' (4.9 to 6.10 m) 100 Nos - 13200.00 100 Nos - 13200.00
long, 2½" to 5" (63 to 125 mm) dia.
ii) Sharpening one end of 16'-1" to 20' (4.9 to 100 Nos 2217.60 - 100 Nos 2217.60 -
6.10 m) long Bamboos, 2½" to 5" (63 to 125 mm) dia.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
iii) Driving Bamboos 16'-1" to 20' long (4.9 to 6.10 m) 100 Nos 4435.20 - 100 Nos 4435.20 -
2½" to 5" (63 to 125 mm) dia, driven 4' (1.20 m)
below the available bed or ground (average).
iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per Chain Per 30 M
S.W.G. No. 10 wire, two lines, including tying around of one 495.00 1541.90 of one 495.00 1541.90
the Bamboos and third tie around the top end only. row row
v) Cutting and supplying brushwood from canal ditto 12705.00 13683.35 ditto 12705.00 13683.35
plantation or private source, lead within one mile
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).
43 Cutting and supplying brushwood from canal plantation or 100Cft. 495.00 564.75 cu.m 174.85 199.45 Royalty to be paid to the Forest
from any other source, within one mile (1.6 Km). Department or cost to the private
owner, if and when required.
44 Filling brush wood only, thoroughly packed. 100Cft. 396.00 - cu.m 139.85 - Measured in compacted and
packed shape before filling.
45 Covering road 10' to 12' (3.00 to 3.65 m) wide, with 3" Per 950.40 - Per 950.40 -
(75 mm) sarkanda or jungle upto one chain lead (30 m). Chain 30 M
46 a) Gachi pitching 1' (300 mm) thick. 100Sft. 5148.00 - Sq.m 553.95 -
b) Gachi pitching done with silt clearance 100Sft. 4356.00 - Sq.m 468.70 -
and berm dressing.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
1 Earthwork for outlets, excavation refilling, ramming and 17.1 Includes consolidation of earth after
puddling:- to refilling.
17.5
a) channels, discharge upto 50 cusecs. Job 1650.00 - Job 1650.00 -
c) channels, discharge from 101 to 200 cusecs. Job 3300.00 - Job 3300.00 -
d) channels, discharge from 201 to 350 cusecs. Job 4455.00 - Job 4455.00 -
3 Making temporary A.P.M. bricks block and fixing at site. Each 762.30 1223.10 Each 762.30 1223.10 21.1 & 21.2
4 Dismantling walls, taking out temporary Job 1584.00 - Job 1584.00 - 18.1, 21.1
A.P.M. brick block, fixing iron block and & 21.2
rebuilding dismantled walls.
5 Dismantling walls and fitting iron block of O.F. outlet. Each 1584.00 - Each 1584.00 - 18.1, 21.1
& 21.2
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
7 Adjusting "B" of tail cluster by dismantling and rebuilding Each 847.00 1492.60 Each 847.00 1492.60 18.1, 21.1
throat walls. & 21.2
8 Adjusting "Y" of an A.P.M. outlet, including dismantling Each 1650.00 2703.60 Each 1650.00 2703.60 ditto
and rebuilding.
9 Extra labour in fixing A.P.M. and O.F. outlet blocks, 21.1 & 21.2 Rates to be Rs. 4.00 less in case
including dressing of bricks:- of O.F. outlets, where there is no
O.F. iron block.
a) for channel depth of 5.0'. (1.5 m) Each 1848.00 2008.80 Each 1848.00 2008.80
b) for channel depth of 4.0'. (1.2 m) ditto 1386.00 1546.80 ditto 1386.00 1546.80
c) for channel depth of 3.0'. (900 mm) ditto 1108.80 1269.60 ditto 1108.80 1269.60
d) for channel depth of 2.0'. (600 mm) ditto 924.00 1048.80 ditto 924.00 1048.80
e) for channel depth of less than 2.0'. (600 mm) ditto 739.20 828.00 ditto 739.20 828.00
10 Repairing damaged reducing collar of Hume pipe outlets. Each 762.30 998.70 Each 762.30 998.70
11 Laying iron pipes for outlets. Per Lft. 36.95 - Metre 121.25 - 21.1, 21.2
& 17.1 to
17.5
12 Water allowance for constructing outlets or culverts, when Each 805.20 Each 805.20 At the discretion of the
canal water is not flowing. to to Engineer-in-charge depending upon
1650.00 1650.00 the distance and source of supply.
13 Hoisting and placing R.C. slab or stone in position on Each 605.00 - Each 605.00 -
outlets or W.C. culverts.
14 Fixing pipe outlet, including back filling of earth and 17.1 to 17.5
puddling:- & 21.1 to
21.2
a) portion under bank. Rft. 154.00 164.70 Metre 505.25 540.4
b) portion under road, beyond bank. ditto 67.10 77.80 ditto 220.15 255.3
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
1 Providing and laying sub-base course of brick on edge 100Cft. 4917.60 23767.20 cu.m 1736.90 8394.60 521-1 The nominal thickness of bricks
4½" (113 mm) thick, including compaction to required to shall be taken for the purpose of
camber and grade. 521-6 measurement and payment.
2 Providing and laying sub-base course of brick aggregate, 100Cft. 3859.50 6312.30 cu.m 1363.20 2229.50 501-1 To be used only when brick
including compaction of sub-base course material to to aggregate is cheaper than stone
required depth, camber, grade & density. 501-6 aggregate.
i) Pit run or bed run gravel. 100Cft. 3859.50 5227.50 cu.m 1363.20 1846.35
ii) Crushed stone aggregate. 100Cft. 3859.50 5875.50 cu.m 1363.20 2075.25
(b) Subsequent carriage of gravel and crushed stone 100Cft. of 1) The carriage of the whole distance
aggregate consoli- to the site of work shall be
dated calculated on the basis of the rates
sub-base of the actual means of transport
used in carriage, i.e. road and/or rail,
as the case may be.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
4 a) Providing and laying base course of crushed stone 100Cft. 4519.50 7679.25 cu.m 1596.30 2712.30 501-1
aggregate of approved quality and grade, and supply and to
spreading of stone screening, including placing, mixing, 501-6
spreading and compaction of base course material to
required depth, camber and grade to achieve 100%
maximum modified AASHO dry density, including
carriage of all materials to site of work except gravel and.
aggregate.
b) Subsequent carriage of crushed stone aggregate. 100Cft. of 1) The carriage for the whole
console- distance to the site of work shall be
dated calculated on the basis of the rates
base of the actual means of transport
used in carriage, i.e. road and/or
rail, as the case may be.
5 Providing and laying road edging of 3" (75 mm) wide and Per Rft. 13.20 51.20 Metre 43.30 168.05 552-1 to
9" (225 mm) deep brick on end, complete in all respects. 552-5
1) 1st coat:-
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
i) 40 lbs. bitumen, and 5.5 Cft. bajri of nominal size 1" (25 100Sft. 167.40 2794.55 Sq.m 18.00 300.70
mm) per 100 sq. feet or 1.96 Kg bitumen and 0.017
cu.metre bajri per square metre..
ii) 35 lbs. bitumen, and 4.0 Cft. bajri of nominal size ¾" 100Sft. 167.40 2439.55 Sq.m 18.00 262.50
(20 mm) per %Sft. or 1.72 Kg bitumen and 0.013 cu.metre
bajri per sq.metre.
2) 2nd coat:-
i) 25 lbs. bitumen, and 2.75 Cft. bajri of nominal size ½" 100Sft. 128.80 1748.00 Sq.m 13.85 188.10
(13 mm) per %sft or 1.23 Kg bitumen and 0.008 cu. metre bajri per
sq.metre.
ii) 18 lbs. bitumen, and 2.0 Cft. bajri of nominal size 3/8" 100Sft. 128.80 1295.40 Sq.m 13.85 139.40
(10 mm) per %Sft. or 0.89 Kg bitumen and 0.006 cu.metre
bajri per sq. metre.
3) 3rd coat:-
14 lbs. bitumen, and 1.5 Cft. bajri of nominal size ¼" (6 100Sft. 88.10 993.15 sq.m 9.50 106.85
mm) per %sft or 0.69 Kg bitumen and 0.005 cubic metre
bajjri per sq.metre.
b) Subsequent carriage of crushed stone aggregate/bajri, 100Cft. cu.m 1) The carriage for the whole
distance to the site of work shall be
calculated on the basis of the rates
of the actual means of transport
used in carriage, i.e. road and/or rail,
as the case may be.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
i) 22 lbs. bitumen, and 2.5 Cft. bajri of nominal size ½" 100Sft. 111.60 1539.05 sq.m 12.00 165.60
(13 mm) per %Sft. or 1.07 Kg bitumen and bajjri 0.007 cu.m
per sq.m.
ii) 20 lbs. bitumen, and 2.0 Cft. bajri of nominal size 3/8" 100Sft. 111.60 1398.60 sq.m 12.00 150.50
(10 mm) per % Sft. or 0.79 Kg bitumen and 0.006
cu.metre bajri per sq.metre.
b) Subsequent carriage of crushed stone aggregate/bajri. 100Cft. cu.m Same remarks as against
item 8(b) above.
10 a) Providing and laying plant premixed bituminous carpet, per inch per 25mm 641-1 to
including compaction and finishing to required camber, grade thickness thickness 642-6
and density. per 100Sft. per Sq.m
(i) 3% Bitumen -do- 1112.20 3529.85 -do- 119.70 379.95
(ii) 3.5% Bitumen -do- 1112.20 3847.90 -do- 119.70 414.20
(iii) 4% Bitumen -do- 1112.20 4166.00 -do- 119.70 448.45
(iv) 4.5% Bitumen -do- 1112.20 4484.10 -do- 119.70 482.65
(v) 5% Bitumen -do- 1112.20 4802.00 -do- 119.70 516.90
(vi) 5.5% Bitumen -do- 1112.20 5120.30 -do- 119.70 551.15
(vii) 6% Bitumen -do- 1112.20 5438.40 -do- 119.70 585.40
b) Subsequent carriage of crushed stone aggregate/bajri. 100Cft. cu.m Same remarks as against item 8(b)
above.
11 Scarifying old road surface including removal of debris within 100Sft. 330.00 - Sq.m 35.50 -
1 chain (30 m).
I ncidental Construction
12 Providing R.C.C. railing on bridges, as per standard drawing. Per Rft. 187.15 1382.65 Metre 614.00 4536.30 901-1 The rate includes cost of steel, its
to fabrication, laying in position and
901-4 fastening, including cost of binding
wire and removal of rust from the
bars, etc.
13 Providing and fixing G.I. pipe railing, as per Per Rft. of 149.05 1333.15 Metre 488.95 4373.95 ditto
standard drawing. 3 rows of
Pipes
14 Providing and fixing steel bearings of standard quality and Each Set - 2400.00 Each set - 2400.00 911-1 to
type at site of work. of one of one 911-6
end end
15 Providing and fixing rubber bearing pad at site Per - 18.00 cu.cm - 1.10 ditto
of work. Cu. Inch
16 Providing and laying expansion joint of neoprine strip 4"x¼" Per Rft. 132.00 279.40 Metre 433.05 916.70 921-1 to
(100 mmx 6 mm) and plastic bitumen. 921-4
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
17 Providing and fixing rain water outlet of A.C. pipe. Each 66.00 396.70 Each 66.00 396.70 931-1 to
933-4
18 Providing and erection at site of work:- 941-1 to The rate is for complete item of
941-5 work according to Standard design
i) R.C.C. mile/Km. stone Each 3566.10 6847.50 Each 3566.10 6847.50 including cement concrete
ii) R.C.C. furlong/½ Km. stone Each 171.35 507.10 Each 171.35 507.10 foundation block and painting
iii) R.C.C. boundary pillar. Each 328.25 746.30 Each 328.25 746.30 letters etc.
iv) Sign post of M.S. plate 1/8" thick (3 mm)
19 Providing and laying dry brick pavement/soling in streets or 100Cft. 4511.10 23360.70 cu.m 1593.30 8251.00 The nominal thickness of bricks
roads, etc. sand grounted, laid in proper camber, including ( 9" x 4-3/8"x 2-11/16") shall be taken
preparation, watering, compaction of bed to proper camber, for the purpose of measurement
and sand cushion. and payment.
I- Grade 50A
(a) Plain
(i) Without Anchrage Cu. Inch - 40.80 Cu.cm - 2.50
(ii) With Anchrage Cu. Inch - 44.40 Cu.cm - 2.70
(b) Laminated
(i) Without Anchrage Cu. Inch - 42.00 Cu.cm - 2.55
(ii) With Anchrage Cu. Inch - 45.60 Cu.cm - 2.80
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
ROAD SAFETY
23 Providing, fabrication and fixing pole mounted Direction Board / road
* 1204-1 If 3 mm thick Aluminium sheet is
delineator of any shape and size, with specified Sheet and thickness,
to used,increase composite rate by Rs
supported with G.I Channel, (excluding the cost of vertical post and
1204-4.2 627/- Psft or Rs 6747/- Per Sq.Mtr
painting) etc complete in all respect.
(a) G.I Sheet 14 SWG
CI RCULAR/TRI ANGULAR
3 ft size P.Sft 69.00 433.65 Sq.m 742.50 4667.95
RECTANGULAR SHAPE
(I) 12 -48 sft P.Sft 86.65 393.45 Sq.m 932.45 4235.10
(II) 54 -120 sft P.Sft 52.05 348.20 Sq.m 560.25 3748.00
24 Providing and fixing pole mounted reflecting mirror (Convex type) of 36
inch diameter of specified material, excluding the cost of vertical post,
which will be paid extra etc complete in all respect.
(a) Acrylic made Each 49.50 18049.50 Each 49.50 18049.50
(b) Stainless Steel Each 49.50 14449.50 Each 49.50 14449.50
25 Providing, fabrication and fixing Vertical Post comprising of medium
quality G.I Pipe of specified diameter, including the cost of clamping
arrangements, top cover, hold fasts embeded in PCC 1:2:4 etc complete in
all respect.
(a) 2 inch diameter P.Rft 51.50 601.55 Meter 168.95 1973.10
(b) 3 inch diameter P.Rft 51.50 858.35 Meter 168.95 2815.40
(c) 4 inch diameter P.Rft 51.50 1154.65 Meter 168.95 3787.30
(d) 5 inch diameter P.Rft 51.50 1512.00 Meter 168.95 4959.30
(e ) 6 inch diameter P.Rft 51.50 1743.50 Meter 168.95 5718.65
26 Providing & fixing Cat Eyes of size 4" x 4" x 3/4" duly casted with
specified material having plastic strip containing mini retro-reflective
* 1206-1
glass beads of color white/red/yellow having specifid reflections , quality if L-Key steel bolt is used, increase
to
& shape i/c the cost of self built in 12 mm diax120 mm long steel zinc Composite rate by Rs 25/- each
1206-4.2
plated nail,fixing to road with epoxy/ hammering with separate nail
complete.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
a) Acrylic material
(A) Dual-Directional
(i) 19x2=38 Glass beads a side Each 19.80 331.80 Each 19.80 331.80
(ii) 31x2=62 Glass beads a side Each 19.80 385.80 Each 19.80 385.80
(iii) Micro Cube Corner Spark glow reflectors Each 19.80 409.80 Each 19.80 409.80
(B) Uni-Directional 0 0.00 0.00
(i) 31 Glass beads a side Each 19.80 295.80 Each 19.80 295.80
(ii) 43 Glass beads a side Each 19.80 355.80 Each 19.80 355.80
b) Aluminium Alloy
(A) Dual-Directional
(i) 31x2=42 Glass beads a side Each 19.80 475.80 Each 19.80 475.80
(ii) 43x2=86 Glass beads a side Each 19.80 595.80 Each 19.80 595.80
(iii) Micro Cube Corner Spark glow reflectors Each 19.80 625.80 Each 19.80 625.80
(B) Uni-Directional
(i) 31 Glass beads a side Each 19.80 445.80 Each 19.80 445.80
(ii) 43 Glass beads a side Each 19.80 475.80 Each 19.80 475.80
27 Providing & fixing Road Studs of aluminium alloy (raised profile) of
specified size with Diamond grade reflectors on both sides etc complete.
a) Uni-Directional
(i) 8" x 4" x 2" Each 19.80 763.80 Each 19.80 763.80
(ii) 6" x 4" x 1.75" Each 19.80 643.80 Each 19.80 643.80
b) Dual-Directional
(i) 8" x 4" x 2" Each 19.80 883.80 Each 19.80 883.80
(ii) 6" x 4" x 1.75" Each 19.80 781.80 Each 19.80 781.80
28 Providing and Fixing L-type Barrier delineator of specified material of
Size 150 x 100mm i/c the cost of hardware, reflective tape etc complete in
all respect.
(a) Acrylic made Each 49.50 445.50 Each 49.50 445.50
(b) Alluminium (3mm thick) Each 49.50 565.50 Each 49.50 565.50
29 Providing and fixing 3" dia G.I Pipe Delineator 3' long with HIP reflective Each 86.00 3689.30 Each 86.00 3689.30
tape (Red & White), duly embedded in P.C.C (1:2:4) etc complete in all
respect.
30 Providing of Portable Cautionary Plastic Barriers 6.50' Long & 2.50' high Each - 12000.00 Each - 12000.00
of approved shape & design etc complete in all respect.
31 Providing of Cautionary Portable Traffic safety Cones made of Plastic
polymer of approved shape, colour, size & design having wide
squar/hexagonal base provided with reflective sleeve having arrangement
for plastic chain etc complete in all respect.
a) 18" high, Bottom dia 13" & Top dia 2-1/2" Each - 540.00 Each - 540.00
b) 28" high, Bottom dia 13-3/4" & Top dia 2-1/2" Each - 720.00 Each - 720.00
c) 36" high, Bottom dia 15" & Top dia 2-1/2" Each - 840.00 Each - 840.00
32 Providing and fixing PLASTIC BODY Reflective cautionary flexible
spring post of specified height with reflective strips at the top for fixing to
road with bolts etc complete in all respect.
(i) 300 mm high Each 49.50 559.50 Each 49.50 559.50
(ii) 600 mm high Each 49.50 589.50 Each 49.50 589.50
(iii) 700 mm high Each 49.50 739.50 Each 49.50 739.50
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
35 Providing and fixing Uni/Dual directional reflective extreme end road Each 49.50 469.50 Each 49.50 469.50
berm indicator made of plastic body of size 80x50x16 mm having ultra -
violet resistant colors (white/yellow/red) with high intensity reflectors
duly fixed on road egde Kerb with a hardened steel nail as approved and
dirrected by the Engineer Incharge.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
4 Providing and fitting white glazed earthen ware water closet, Each 453.75 2,205.75 Each 453.75 2,205.75
squartter type, with separate foot rest.
5 Providing and fitting water closet, squatter type of terrazzo Each 453.75 793.80 Each 453.75 793.80
concrete.
7 Providing and fixing stainless steel sink with drain board, size Each 515.65 4,690.45 Each 515.65 4,690.45
120x60 cm (48"x24") including bracket set, waste pipe and
waste coupling.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
8 Providing and fitting terrazzo concrete sink 60x45 cm (24"x18") Each 515.65 1,392.95 Each 515.65 1,392.95
with drain board of mosaic, including bracket set, waste pipe
and waste coupling.
10 Providing and fixing glazed earthen ware flat back urinal. Each 330.00 1,032.85 Each 330.00 1,032.85
i) white Each 515.65 1,598.30 Each 515.65 1,598.30 If rubber connection is used, the
ii) coloured Each 515.65 1,598.30 Each 515.65 1,598.30 composite rate will be reduced by
Rs. 12.50
13 Providing and fixing white enameled cast iron low down flushing Each 515.65 1,581.70 Each 515.65 1,581.70
cistern 13.63 litres (3 gallons) capacity, including bracket
set, copper connection, etc.
i) 13.63 litres (3 gallons) capacity Each 548.65 2,712.70 Each 548.65 2,712.70
ii) 4.55 litres (1 gallon) capacity Each 548.65 1,872.70 Each 548.65 1,872.70
15 Providing and fixing, chromium plated soap dish. Each 33.00 206.05 Each 33.00 206.05
17 Providing and fixing, chromium plated toilet paper holder. Each 44.00 432.25 Each 44.00 432.25
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
i) 60 cm (24") long, and 2 cm (¾") dia. Each 44.00 376.05 Each 44.00 376.05
ii) 50 cm (20") long, and 1.5 cm (½") dia. Each 44.00 316.05 Each 44.00 316.05
19 Providing and fixing looking glass 55x40 cm (22"x16") size, Each 82.5 416.60 Each 82.5 416.60
and 5 mm thick, first quality.
i) with chromium plated brackets and railing. Each 103.15 587.40 Each 103.15 587.40
ii) glass shelf only, without chromium plated brackets Each 66.00 270.00 Each 66.00 270.00
and railing.
25 Providing and fixing underground stop cock 13 mm (½"), Each 63.25 521.20 Each 63.25 521.20
with chromium plated cover.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
27 Providing and fixing chromium plated tee stop cock Each 44.00 470.00 Each 44.00 470.00
15mm (½").
29 Providing and fixing, chromium plated mixing valve, for wash Each 55.00 1,579.00 Each 55.00 1,579.00
hand basin, sink or shower.
30 Providing and fixing gun metal peet/gate valve (screwed):- For brass peet/gate valve (screwed),
the composite rates of items (i) to (v)
i) 30 mm (1¼") dia Each 66.00 468.00 Each 66.00 468.00 will be reduced by Rs. 66, 77, 95, 107
ii) 40 mm(1½") dia Each 66.00 618.00 Each 66.00 618.00 and 120 respectively.
iii) 50 mm(2") dia Each 66.00 846.00 Each 66.00 846.00
iv) 65 mm(2½") dia Each 66.00 1,314.00 Each 66.00 1,314.00
v) 80 mm(3") dia Each 66.00 1,926.00 Each 66.00 1,926.00
35 Providing and fitting 10 cm (4") gully trap, including cement Each 165.00 848.65 Each 165.00 848.65
concrete, cost of PVC grating 15x15 cm (6"x6") and
masonry chamber 30x30 cm (12"x12").
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
38 Providing and fitting cast iron specials, such as tee bend, In case of plug type, the composite
collar, cross, etc. plain type:- rate shall be increased by Rs.2 per kg.
42 Providing and fitting nipple or bush, 6 mm to Each 33.00 63.90 Each 33.00 63.90
10 mm (¼" to 3/8") i/d.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
45 Hoisting and placing in position, precast R.C. latrine seats. Each 660.00 - Each 660.00 -
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
Replacement
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
i) wash hand basin and cistern Each 66.00 195.60 Each 66.00 195.60
ii) sinks Each 66.00 212.40 Each 66.00 212.40
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
xiv) 1680 mm (66") i/d Rft. 2715.75 9146.95 Metre 8907.65 30002
xv) 1830 mm (72") i/d Rft. 3379.40 10386.20 Metre 11084.45 34066.75
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
6 Lowering of sub-soil water table, by installation of tubewells 1) This rate shall be payable, in
along sewer line and pumping out water, for excavation in addition to the item of excavation
open cutting below sub-soil water level, concreting, curing, below SSWL for sewers and
laying and jointing pipes, filling haunches, etc. till the manholes under Chapter,
completion of sewer line, including disposal of pumped out EARTHWORK
water:- 2) The grant of these rates shall be
Rft of Metre of subject to Superintending Engineer's
1) 0-1 ft. (0 to 310 mm) below SSWL laid sewer - 392.1 laid sewer - 1286.15 approval.
2) 0-2 ft. (0 to 610 mm) below SSWL ditto - 721.25 ditto - 2365.75
3) 0-3 ft. (0 to 910 mm) below SSWL ditto - 1258.05 ditto - 4126.45 3) The rate includes cost of
4) 0-4 ft. (0 to 1220 mm) below SSWL ditto - 1834.8 ditto - 6018.15 providing pumps, POL and all
5) 0-5 ft. (0 to 1520 mm) below SSWL ditto - 2591.80 ditto - 8501.15 operation charges at the site
6) 0-6 ft. (0 to 1830 mm) below SSWL ditto - 3203.70 ditto - 10508.2 of work, etc.
7) 0-7 ft. (0 to 2170 mm) below SSWL ditto - 3833.60 ditto - 12574.25
8) 0-8 ft. (0 to 2480 mm) below SSWL ditto - 4401.10 ditto - 14435.65
9) 0-9 ft. (0 to 2790 mm) below SSWL ditto - 4732.85 ditto - 15523.80
10) 0-10 ft. (0 to 3100 mm) below SSWL ditto - 5470.10 ditto - 17941.95
11) 0-11 ft. (0 to 3410 mm) below SSWL ditto - 6098.70 ditto - 20003.80
12) 0-12 ft. (0 to 3720 mm) below SSWL ditto - 6773.15 ditto - 22215.85
7 Constructing gully grating chamber, 12"x12", ( 300x300 16.2 Pipe connection to be paid
mm) complete in all respects: separately.
a) with C.I. gully trap, weighing 81 lbs. (36.75 Kg.) frame Each 1191.75 8209.80 Each 1191.75 8209.80
hinged safety type.
8 Constructing standard gully grating chamber, 3'x2½' Each 3630.05 12495.50 Each 3630.05 12495.50 ditto Pipe connection to be paid
(900x750 mm), with chinaware trap as per PHED Drawing separately.
STD/PD No. 3 of 1977, complete in all respects.
9 Extra for making and finishing benching floor work in 100Sft. 1523.30 2120.90 Sq.m 163.90 228.20 14.4
manhole chamber, with 1/8" (3 mm) thick cement finish.
10 Restoration of brick pavement on edge, over laid service 100Sft. 2180.00 4770.55 Sq.m 234.55 513.30 13.1
line, with 2" (50 mm) sand cushion under soling.
11 Restoration of flat brick pavement sand grouted, over 2" 100Sft. 1323.30 3148.25 Sq.m 142.40 338.75 13.1
(50 mm) thick dry sand cushion, under soling on laid
service line.
a) Carpetted road, with 2" (50 mm) carpet and 10" (250 100Sft. 3285.75 10405.75 Sq.m 353.55 1119.65
mm) depth of stone metal for sub-base and base.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
b) Carpeted road, with 1½" (38 mm) carpet and 6" (150 100Sft. 2312.85 7599.15 Sq.m 248.85 817.65
mm) depth of stone metal, for sub-base and base.
c) Black Topped Road with two coats of surfacing & 10" 100Sft. 1368.40 5442.60 Sq.m 147.25 585.60
(250 mm) depth of stone metal, for sub base & base.
14 Fixing manhole frame and cover in R.C.C. slab including Per 321.20 - Per 321.20 - ditto
carriage to site. set set
15 Providing and fixing 3" (75 mm) thick R.C.C. manhole Per 204.70 9148.55 Per 204.70 9148.55 ditto
cover, 22" (550 mm) dia, with tee shaped C.I. frame of 20" set set
(500 mm) clear i/d (frame weighing 37.324 Kg. or one
maund) as per Standard Drawing STD/PD No. 5, of 1977,
complete in all respects.
15-A Providing and fixing 6" thick R.C.C. manhole Per 468.55 11458.80 Per 468.55 11458.80
cover with tee shaped C.I. frame of 22" I/d (frame set set
weighing 37.324 Kg. or one maund as per Standard
Drawing STD/PD No. 6, of 1977, complete in all respect.
16 Providing and fixing, 6" (150 mm) thick R.C.C. manhole Per 415.60 4428.60 Per 415.60 4428.60 ditto
cover for 22" as per standard drawing STD/PD No. 6 of set set
1977, complete in all respects.
17 Providing and fixing, 6" (150 mm) thick R.C.C. manhole Per 342.55 7045.80 Per 342.55 7045.80 ditto
cover with 3"x3"x¼" (75x75x6mm) angle iron frame, 22" set set
(550 mm) i/d as per standard drawing STD/PD No. 7 of
1977, complete in all respects.
18 Desilting of disposal work collecting tank, including 100Cft. 1131.45 1185.70 cum 399.60 418.80 16.2
removal of sludge within 3 chains (90 metre).
i) 18 ft. (5.5 metre) long Per Cwt 330.00 9741.80 %kg 649.60 19176.75
ii) 24 ft. (7.30 metre) long ditto 366.65 9788.15 ditto 721.80 19268.05
iii) 30 ft. (9.15 metre) long ditto 396.00 9811.20 ditto 779.55 19313.45
iv) 36 ft. (11 metre) long ditto 414.35 9832.20 ditto 815.65 19354.70
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
i) 18 ft. (5.5 metre) long Per Cwt 290.40 9699.05 %kg 571.65 19092.55
ii) 24 ft. (7.30 metre) long ditto 312.95 9720.90 ditto 616.00 19135.60
iii) 30 ft. (9.15 metre) long ditto 335.10 9742.85 ditto 659.60 19178.80
iv) 36 ft. (11 metre) long ditto 403.35 9810.95 ditto 793.95 19312.85
i) 18 ft. (5.5 metre) long Per Cwt 256.65 9666.00 %kg 505.25 19027.55
ii) 24 ft. (7.30 metre) long ditto 330.00 9735.40 ditto 649.60 19164.15
iii) 30 ft. (9.15 metre) long ditto 385.00 9790.05 ditto 757.85 19271.75
a) upto 10' (3.00 m) depth of slush Per well 9405.00 - Per well 9405.00 -
b) beyond 10' (3.00 m) depth of slush Per well 18480.00 - Per well 18480.00 -
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
b) in hard soil
i) from 0' to 5'(0 to 1.5 metre) depth 1000 Cft. 7167.60 - cu.m 253.15 -
ii) from 5.1' to 10'(1.5 to 3.0 metre) depth ditto 7492.30 - ditto 264.65 -
iii) from 10.1' to 15'(3.0 to 4.5 metre) depth ditto 8189.30 - ditto 289.25 -
iv) from 15.1' to 20'(4.5 to 6.0 metre) depth ditto 9210.95 - ditto 325.35 -
i) from 0' to 5'(0 to 1.5 metre) depth 1000 Cft. 15459.85 - cu.m 546.05 -
ii) from 5.1' to 10'(1.5 to 3.0 metre) depth ditto 16014.25 - ditto 565.60 -
iii) from 10.1' to 15'(3.0 to 4.5 metre) depth ditto 16695.35 - ditto 589.70 -
iv) from 15.1' to 20'(4.5 to 6.0 metre ) depth ditto 17922.95 - ditto 633.05 -
a) in ordinary soil :-
i) from 10' to 15'(3.0 to 4.5 m) depth 1000 Cft. 31680.00 - cu.m 1118.95
ii) from 15.1' to 20'(4.5 to 6.0 m) depth ditto 39600.00 - ditto 1398.65
iii) from 20.1' to 25'(6.0 to 7.5 m) depth ditto 47520.00 - ditto 1678.40
iv) from 25.1' to 30'(7.5 to 9.0 m) depth ditto 55440.00 - ditto 1958.15
v) from 30.1' to 35'(9.0 to 10.5 m) depth ditto 63360.00 - ditto 2237.90
vi) from 35.1' to 40'(10.5 to 12.0 m) depth ditto 71280.00 - ditto 2517.60
vii) from 40.1'to 45'(12.0 to 13.5 m) depth ditto 79200.00 - ditto 2797.35
viii) from 45'(13.5 Sm) to any depth ditto 87120.00 - ditto 3077.10
b) in hard soil :-
i) from 10' to 15'(3.0 to 4.5 m) depth 1000 Cft. 43560.00 - cu.m 1538.55 -
ii) from 15.1' to 20'(4.5 to 6.0 m) depth ditto 51480.00 - ditto 1818.25 -
iii) from 20.1' to 25'(6.0 to 7.5 m) depth ditto 59400.00 - ditto 2098.00 -
iv) from 25.1' to 30'(7.5 to 9.0 m) depth ditto 67320.00 - ditto 2377.75 -
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
i) from 10' to 15'(3.0 to 4.5 m) depth 1000 Cft. 59400.00 - cu.m 2098.00 -
ii) from 15.1' to 20'(4.5 to 6.0 m) depth ditto 67320.00 - ditto 2377.75 -
iii) from 20.1' to 25'(6.0 to 7.5 m) depth ditto 75240.00 - ditto 2657.50 -
iv) from 25.1' to 30'(7.5 to 9.0 m) depth ditto 76230.00 - ditto 2692.45 -
v) from 30.1' to 35'(9.0 to 10.5 m) depth ditto 91080.00 - ditto 3216.95 -
vi) from 35.1' to 40'(10.5 to 12.0 m) depth ditto 99000.00 - ditto 3496.70 -
vii)from 40.1' to 45'(12.0 to 13.5 m) depth ditto 106920.00 - ditto 3776.40 -
viii) from 45'-1" (13.5 m) to any depth ditto 114840.00 - ditto 4056.15 -
3 Wet sinking of well in ordinary soil (value of C upto 5), for * 841-1 The outer dimensions of the curb
depths below spring level, including charges of machinery, to shall form basis of payment.
shoring, kentledge and removal of excavated spoil within 841-9
one chain (30 m):-
i) from o' to 10'(0 to 3.0 m) depth 1000 Cft. 50470.60 - cu.m 1782.60 -
ii) above 10' to 20'(3.0 to 6.0 m) depth ditto 107250.00 - ditto 3788.05 -
iii) above 20' to 30'(6.0 to 9.0 m) depth ditto 132000.00 - ditto 4662.25 -
iv) above 30' to 40'(9.0 to 12.0 m) depth ditto 171600.00 - ditto 6060.90 -
v) above 40' to 50'(12.0 to 15.0 m) depth ditto 190666.65 - ditto 6734.35 -
vi) above 50' to 60'(15.0 to 18.0 m) depth ditto 214500.00 - ditto 7576.15 -
vii) above 60' to 70'(18.0 to 21.0 m) depth ditto 220000.00 - ditto 7770.40 -
viii) above 70' to 80'(21.0 to 24.0 m) depth ditto 225789.45 - ditto 7974.90 -
ix) above 80'(24.0 m) to any depth ditto 245142.85 - ditto 8658.45 -
4 Wet sinking of well in cohesive soil (value of Cmore than * 841-1 The outer dimensions of the curb
5), for depths below spring level, including charges of to shall form basis of payment.
machinery shoring, kentledge and removal of excavated 841-9
spoil within one chain (30 m):-
i) from o' to 10'(0 to 3.0 m) depth 1000 Cft. - 68216.35 cu.m - 2409.40
ii) above 10' to 20'(3.0 to 6.0 m) depth ditto - 85270.45 ditto - 3011.75
iii) above 20' to 30'(6.0 to 9.0 m) depth ditto - 102324.55 ditto - 3614.10
iv) above 30' to 40'(9.0 to 12.0 m) depth ditto - 136432.70 ditto - 4818.80
v) above 40' to 50'(12.0 to 15.0 m) depth ditto - 157422.35 ditto - 5560.15
vi) above 50' to 60'(15.0 to 18.0 m) depth ditto - 170540.90 ditto - 6023.50
vii) above 60' to 70'(18.0 to 21.0 m) depth ditto - 186044.60 ditto - 6571.10
viii) above 70' to 80'(21.0 to 24.0 m) depth ditto - 193065.15 ditto - 6819.05
ix) above 80'(24.0 m) to any depth ditto - 204649.05 ditto - 7228.20
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
5 Wet sinking of well in shingle, or gravel, etc, for depths * 841-1 The outer dimensions of the curb
below spring level, including charges of machinery, to shall form basis of payment.
shoring, kentledge and removal of excavated spoil within 841-9
one chain (30 m) :-
i) from o' to 10'(0 to 3.0 m) depth 1000 Cft. - 93022.30 cu.m - 3285.55
ii) above 10' to 20'(3.0 to 6.0 m) depth ditto - 113693.95 ditto - 4015.65
iii) above 20' to 30'(6.0 to 9.0 m) depth ditto - 136432.70 ditto - 4818.80
iv) above 30' to 40'(9.0 to 12.0 m) depth ditto - 186044.60 ditto - 6571.10
v) above 40' to 50'(12.0 to 15.0 m) depth ditto - 204649.05 ditto - 7228.20
vi) above 50' to 60'(15.0 to 18.0 m) depth ditto - 227387.85 ditto - 8031.35
vii) above 60' to 70'(18.0 to 21.0 m) depth ditto - 237964.05 ditto - 8404.90
viii) above 70' to 80'(21.0 to 24.0 m) depth ditto - 243629.85 ditto - 8605.00
ix) above 80'(24.0 m) to any depth ditto - 269275.10 ditto - 9510.80
6 Making and fixing in position, kiker wood well curb. Per Cft. 1482.20 3632.45 cu.m 52351.40 128298.00
8 Providing, making and laying R.C.C. well curb in position, * 841-1 1) If concrete mixer is supplied by
using coarse sand, including all kinds of form, moulds, to Government, all charges including
curing, shuttering, rendering and finishing the exposed 841-9 depreciation will be recovered from
surface, (including screening and washing of aggregate :- the contractor.
2) The rate does not include cost of
a) Ratio 1:1½:3 Per Cft. 318.80 564.55 cu.m 11259.30 19940.60 steel reinforcement and its labour for
b) ratio 1:2:4 ditto 318.80 531.80 ditto 11259.30 18782.65 bending, which is payable, separately.
9 Providing and fixing structural steel for cutting 100Kg 1155.00 19366.90 100Kg 1155.00 19366.90 841-1 to
edge. 841-9
10 Making and removing false masonry on well. 100Cft. 9911.00 29046.50 cu.m 3500.55 10259.25 21.1 to The rate includes dismantling of false
21.5 & 18.1 masonry, scraping bricks obtained
from dismantling and credit of
byproducts.
* Specification No. correspond to Book of "Standard Specification for Road and Bridge Construction, 1971".
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
1 Boring for tubewell in all types of soil except shingle and Chap. 2
rock, from ground level to 100 ft. (30 m) depth, including
sinking and withdrawing of casing pipe, complete:-
a) 3" (75 mm) i/d Per Rft. 185.45 Per Metre 608.25
b) 4" (100 mm) i/d of bore 250.85 of bore 822.80
c) 5" (125 mm) i/d ditto 459.45 ditto 1507.00
d) 6" (150 mm) i/d ditto 694.95 ditto 2279.35
e) 8" (200 mm) i/d ditto 920.10 ditto 3017.90
f) 10" (250 mm) i/d ditto 1155.15 ditto 3788.95
g) 12" (300 mm) i/d ditto 1249.60 ditto 4098.70
h) 15" (375 mm) i/d ditto 1900.90 ditto 6234.90
i) 18" (450 mm) i/d ditto 2015.15 ditto 6609.65
a) 5" (125 mm) i/d Per Rft. 770.35 Per Metre 2526.80
b) 6" (150 mm) i/d of bore 1082.15 of bore 3549.45
c) 8" (200 mm) i/d ditto 1250.05 ditto 4100.10
d) 10" (250 mm) i/d ditto 1417.85 ditto 4650.60
e) 12" (300 mm) i/d ditto 1527.65 ditto 5010.75
f) 15" (375 mm) i/d ditto 2232.90 ditto 7323.85
g) 18" (450 mm) i/d ditto 2347.15 ditto 7698.60
a) 8" (200 mm) i/d Rft of bore 1908.65 Per Metre 6260.45
b) 10" (250 mm) i/d ditto 2116.10 of bore 6940.85
c) 12" (300 mm) i/d ditto 2216.75 ditto 7270.90
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
6 Boring for tubewell in shingle, gravel and rock, including ditto Location and depth of shingle,
sinking and withdrawing of casing pipe:- gravel or rock is to be determined
from the bore log.
a) from ground level to 200 ft. (60 m) below ground level:-
7 Providing strong substantially built box of deodar wood Job for 2575.30 17491.30 Job for 2575.30 17491.30 ditto
4'x2½'x9" (1200x750x225 mm), with compartments, lock compl- compl-
and locking arrangement, for preserving samples of strata ete bore ete bore
from bore hole.
8 Furnishing sample of water from bore hole. Per Set 118.80 170.70 Per Set 118.80 170.70 Chap. 2
of 2 of 2
bottles bottles
9 Providing and installing, brass strainer in tubewell bore ditto Cost/labour of jointing both ends is
hole, including sockets, special sockets, studs, etc. included in the rate.
complete:-
a) 2" i/d, 5/32" (50 mm i/d 4 mm) thick Per Rft. 41.65 1076.05 Per Metre 136.60 3529.45
b) 3" i/d, 5/32" (75 mm i/d 4 mm) thick Per Rft. 41.65 2045.65 Per Metre 136.65 6709.75
c) 4" i/d, 3/16" (100 mm i/d 5 mm) thick Per Rft. 55.55 2497.55 Per Metre 182.20 8191.95
d) 5" i/d, 3/16" (125 mm i/d 5 mm) thick Per Rft. 63.35 3178.55 Per Metre 207.70 10425.55
e) 6" i/d, 3/16" (150 mm i/d 5 mm) thick Per Rft. 69.45 3579.45 Per Metre 227.75 11740.55
f) 7" i/d, 3/16" (175 mm i/d 5 mm) thick Per Rft. 82.10 4301.30 Per Metre 269.20 14108.20
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
g) 8" i/d, 3/16" (200 mm i/d 5 mm) thick Per Rft. 101.05 5100.25 Per Metre 331.45 16728.85
h) 9" i/d, 3/16" (225 mm i/d 5 mm) thick Per Rft. 101.05 5303.05 Per Metre 331.45 17394.00
i) 10" i/d, 3/16" (250 mm i/d 5 mm) thick Per Rft. 114.60 5847.00 Per Metre 375.90 19178.20
j) 10" i/d, ¼" (250 mm i/d 6 mm) thick Per Rft. 114.60 7469.40 Per Metre 375.90 24499.65
k) 12" i/d, ¼" (300 mm i/d 6 mm) thick Per Rft. 115.85 8496.65 Per Metre 379.95 27869.00
l) 15" i/d, ¼" (375 mm i/d 6 mm) thick Per Rft. 133.90 10452.70 Per Metre 439.25 34284.90
m) 18" i/d, ¼" (450 mm i/d 6 mm) thick Per Rft. 133.90 11903.50 Per Metre 439.25 39043.55
n) 20" i/d, ¼" (500 mm i/d 6 mm) thick Per Rft. 159.20 13128.80 Per Metre 522.25 43062.50
o) 22" i/d, ¼" (550 mm i/d 6 mm) thick Per Rft. 160.45 15081.25 Per Metre 526.30 49466.50
10 Providing and installing M.S. Bail plug in tubewell bore In the case of increase or decrease
hole: in the length of Bail plug, the rates
will be increased or decreased as
a) 2" i/d, 1.5 ft. (50 mm i/d 450 mm) long. Each 199.35 804.70 Each 199.35 804.70 per rates given in serial No. 14 of
b) 3" i/d, 1.5 ft. (75 mm i/d 450 mm) long. Each 199.35 1040.25 Each 199.35 1040.25 this chapter for the respective
c) 4" i/d, 2 ft. (100 mm i/d 600 mm) long. Each 332.75 1863.20 Each 332.75 1863.20 diameter.
d) 5" i/d, 2 ft. (125 mm i/d 600 mm) long. Each 332.75 2306.30 Each 332.75 2306.30
e) 6" i/d, 2 ft. (150 mm i/d 600 mm) long. Each 450.40 2909.25 Each 450.40 2909.25
f) 7" i/d, 2 ft. (175 mm i/d 600 mm) long. Each 450.40 3343.05 Each 450.40 3343.05
g) 8" i/d, 2 ft. (200 mm i/d 600 mm) long Each 553.65 3738.20 Each 553.65 3738.20
h) 9" i/d, 2 ft. (225 mm i/d 600 mm) long Each 553.65 4128.10 Each 553.65 4128.10
i) 10" i/d, 2 ft. (250 mm i/d 600 mm) long Each 553.65 5133.35 Each 553.65 5133.35
j) 12" i/d, 2 ft. (300 mm i/d 600 mm) long Each 664.50 6160.85 Each 664.50 6160.85
k) 15" i/d, 2 ft. (375 mm i/d 600 mm) long Each 664.50 7529.95 Each 664.50 7529.95
l) 18" i/d, 2 ft. (450 mm i/d 600 mm) long Each 800.65 8649.65 Each 800.65 8649.65
m) 20" i/d, 2 ft. (500 mm i/d 600 mm) long Each 870.00 9586.15 Each 870.00 9586.15
n) 22" i/d, 2 ft. (550 mm i/d 600 mm) long Each 870.00 10506.65 Each 870.00 10506.65
a) 3" i/d (75 mm) Per Rft. 30.80 131.60 Per Metre 100.95 431.60
b) 4" i/d (100 mm) Per Rft. 35.15 189.95 Per Metre 115.30 623.05
c) 5" i/d (125 mm) Per Rft. 37.15 253.15 Per Metre 121.90 830.40
d) 6" i/d (150 mm) Per Rft. 43.60 331.60 Per Metre 142.95 1087.60
e) 8" i/d (200 mm) Per Rft. 59.10 779.10 Per Metre 193.90 2555.50
f) 10" i/d (250 mm) Per Rft. 60.45 1152.45 Per Metre 198.30 3780.05
g) 12" i/d (300 mm) Per Rft. 60.45 1536.45 Per Metre 198.30 5039.55
a) 1¼" i/d (30 mm) Per Rft. 21.10 60.70 Per Metre 69.20 199.1
b) 1½" i/d (40 mm) Per Rft. 21.60 67.20 Per Metre 70.80 220.35
c) 2" i/d (50 mm) Per Rft. 21.75 98.55 Per Metre 71.40 323.3
d) 3" i/d (75 mm) Per Rft. 30.80 196.40 Per Metre 101.05 644.2
e) 4" i/d (100 mm) Per Rft. 35.05 303.85 Per Metre 115.00 996.65
f) 5" i/d (125 mm) Per Rft. 37.15 439.15 Per Metre 121.90 1440.45
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
g) 6" i/d (150 mm) Per Rft. 65.85 635.85 Per Metre 215.95 2085.55
a) 2" i/d, 1/8" (50 mm i/d 3 mm) thick Per Rft. 120.20 421.40 Per Metre 394.25 1382.20
b) 3" i/d, 1/8" (75 mm i/d 3 mm) thick Per Rft. 120.20 559.40 Per Metre 394.25 1834.85
c) 4" i/d, 1/8" (100 mm i/d 3 mm) thick Per Rft. 150.35 721.55 Per Metre 493.15 2366.70
d) 5" i/d, 3/16" (125 mm i/d 5 mm) thick Per Rft. 150.35 1333.55 Per Metre 493.15 4374.05
e) 6" i/d, 3/16" (150 mm i/d 5 mm) thick Per Rft. 214.55 1648.55 Per Metre 703.70 5407.25
f) 7" i/d, 3/16" (175 mm i/d 5 mm) thick Per Rft. 214.55 1846.55 Per Metre 703.70 6056.70
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
g) 8" i/d, 3/16" (200 mm i/d 5 mm) thick Per Rft. 250.35 2044.35 Per Metre 821.15 6705.45
h) 9" i/d, 3/16" (225 mm i/d 5 mm) thick Per Rft. 250.35 2218.35 Per Metre 821.15 7276.20
i) 10" i/d, ¼" (250 mm i/d 6 mm) thick Per Rft. 250.35 2832.75 Per Metre 821.15 9291.40
j) 12" i/d, ¼" (300 mm i/d 6 mm) thick Per Rft. 300.50 3338.90 Per Metre 985.65 10951.60
k) 15" i/d, ¼" (375 mm i/d 6 mm) thick Per Rft. 300.50 4104.50 Per Metre 985.65 13462.75
l) 18" i/d, ¼" (450 mm i/d 6 mm) thick Per Rft. 368.55 5096.55 Per Metre 1208.85 16716.70
m) 20" i/d, ¼" (500 mm i/d 6 mm) thick Per Rft. 396.90 5649.30 Per Metre 1301.85 18529.70
n) 22" i/d, ¼" (550 mm i/d 6 mm) thick Per Rft. 396.90 6173.70 Per Metre 1301.85 20249.75
a) 3" i/d (75 mm) Per Rft. 41.95 241.15 Per Metre 137.60 790.95
b) 4" i/d (100 mm) Per Rft. 47.50 352.30 Per Metre 155.80 1155.55
c) 5" i/d (125 mm) Per Rft. 49.55 481.55 Per Metre 162.50 1579.45
d) 6" i/d (150 mm) Per Rft. 59.10 663.90 Per Metre 192.30 2176.05
e) 8" i/d (200 mm) Per Rft. 78.45 996.45 Per Metre 257.35 3268.40
f) 10" i/d (250 mm) Per Rft. 81.65 1638.05 Per Metre 267.75 5372.75
g) 12" i/d (300 mm) Per Rft. 97.95 2280.75 Per Metre 321.30 7480.90
h) 14" i/d (350 mm) Per Rft. 94.85 2739.65 Per Metre 311.15 8986.10
17 Testing and developing of tubewell of size 6" (150 mm) Compressor, accessories along with
i/d and above continuously. working staff, to be supplied by
Government.
i) upto 1.5 cs. discharge Per 1194.45 Per 1194.45
Hour Hour
ii) above 1.5 cs. discharge ditto 1443.30 ditto 1443.30
18 Shrouding with graded pea gravel 3/8" to 1/8" (10 to 3 Per Cft. 53.50 105.15 cu.m 1889.60 3713.85 The rate includes wastage, etc.
mm), around tubewell in bore hole.
19 Laying cutting, jointing, testing and disinfecting cast iron Chap. 1) Pipes to be supplied by
pipe line in trenches, with spigot and socket caulked lead 2 Government.
joints, including cost of materials, such as lead, yarn, etc. 2) Providing and installing specials
complete in all respects:- and valves is not included in the
rate, which is payable separately.
a) 3" (75 mm) i/d Per Rft. 75.75 Per Metre 248.45
b) 4" (100 mm) i/d Per Rft. 93.60 Per Metre 306.95
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
c) 5" (125 mm) i/d Per Rft. 118.10 Per Metre 387.30
d) 6" (150 mm) i/d Per Rft. 138.45 Per Metre 454.10
e) 8" (200 mm) i/d Per Rft. 163.50 Per Metre 536.25
f) 10" (250 mm) i/d Per Rft. 250.45 Per Metre 821.45
g) 12" (300 mm) i/d Per Rft. 294.30 Per Metre 965.30
h) 15" (375 mm) i/d Per Rft. 377.65 Per Metre 1238.60
i) 18" (450 mm) i/d Per Rft. 494.45 Per Metre 1621.80
20 Laying, cutting, jointing, testing and disinfecting cast iron ditto 1) Pipes to be supplied by
pipe line in trenches, with flanged and flanged joints, Government.
complete in all respects:- 2) Providing and installing specials
and valves is not included in the
a) 3" (75 mm) i/d Per Rft. 35.40 Per Metre 116.05 rate, which is payable separately.
b) 4" (100 mm) i/d Per Rft. 38.95 Per Metre 127.80
c) 5" (125 mm) i/d Per Rft. 52.75 Per Metre 173.00
d) 6" (150 mm) i/d Per Rft. 58.30 Per Metre 191.15
e) 8" (200 mm) i/d Per Rft. 68.15 Per Metre 223.60
f) 10" (250 mm) i/d Per Rft. 93.25 Per Metre 305.85
g) 12" (300 mm) i/d Per Rft. 109.75 Per Metre 360.00
h) 15" (375 mm) i/d Per Rft. 152.85 Per Metre 501.15
i) 18" (450 mm) i/d Per Rft. 198.70 Per Metre 651.80
21 Laying, cutting, jointing, testing and disinfecting cast iron Chap. 2 1) Pipes to be supplied by
pipe line in trenches with Tyton joints, complete in all Government.
respects:- 2) Providing and installing specials
and valves is not included in the
a) 3" (75 mm) i/d Per Rft. 16.25 Per Metre 53.30 rate, which is payable separately.
b) 4" (100 mm) i/d Per Rft. 18.15 Per Metre 59.60
c) 5" (125 mm) i/d Per Rft. 23.65 Per Metre 77.50
d) 6" (150 mm) i/d Per Rft. 26.35 Per Metre 86.45
e) 8" (200 mm) i/d Per Rft. 35.85 Per Metre 117.65
f) 10" (250 mm) i/d Per Rft. 45.60 Per Metre 149.55
g) 12" (300 mm) i/d Per Rft. 54.05 Per Metre 177.25
h) 15" (375 mm) i/d Per Rft. 73.75 Per Metre 241.85
i) 18" (450 mm) i/d Per Rft. 88.10 Per Metre 289.05
22 Providing, laying, cutting, jointing, testing and disinfecting Chap. Cost of sockets, tees, elbows,
G.I. pipeline in trenches, with socket joints, using G.I. 2 bends, valves, crosses, unions and
pipes of B.S.S. 1387-1967 complete in all respects, with plugs, etc. is included in the rates.
specials and valves.
i) Light Quality
a) ½" i/d (15 mm) 2mm thick Per Rft. 12.75 99.55 Per Metre 41.80 326.45
b) ¾" i/d (20 mm) 2.35mm thick Per Rft. 14.05 138.80 Per Metre 46.00 455.20
c) 1" i/d (25 mm) 2.65mm thick Per Rft. 15.95 193.60 Per Metre 52.30 634.95
d) 1¼" i/d (32 mm) 2.65mm thick Per Rft. 16.05 245.20 Per Metre 52.60 804.25
e) 1½" i/d (40 mm) 2.9mm thick Per Rft. 16.15 310.40 Per Metre 52.95 1018.10
f) 2" i/d (50 mm) 2.9mm thick Per Rft. 17.90 388.10 Per Metre 58.70 1272.90
g) 2"½ i/d (65 mm) 3.25mm thick Per Rft. 18.50 532.40 Per Metre 60.65 1746.30
h) 3" i/d (75 mm) 3.25mm thick Per Rft. 21.15 624.55 Per Metre 69.35 2048.60
i) 4" i/d (100 mm) 3.65mm thick Per Rft. 22.90 883.95 Per Metre 75.10 2899.40
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
a) ½" i/d (15 mm) 3.25mm thick Per Rft. 12.75 148.35 Per Metre 41.85 486.60
b) ¾" i/d (20 mm) 3.25mm thick Per Rft. 14.05 190.30 Per Metre 46.00 624.20
c) 1" i/d (25 mm) 4.05mm thick Per Rft. 15.95 293.90 Per Metre 52.30 964.05
d) 1¼" i/d (32 mm) 4.05mm thick Per Rft. 16.05 382.15 Per Metre 52.60 1253.50
e) 1½" i/d (40 mm) 4.05mm thick Per Rft. 16.35 436.70 Per Metre 53.65 1432.40
f) 2" i/d (50 mm) 4.5mm thick Per Rft. 17.90 610.45 Per Metre 58.70 2002.35
g) 2"½ i/d (65 mm) 4.5mm thick Per Rft. 18.50 741.25 Per Metre 60.65 2431.25
h) 3" i/d (75 mm) 4.85mm thick Per Rft. 21.15 982.55 Per Metre 69.35 3222.80
i) 4" i/d (100 mm) 5.4mm thick Per Rft. 22.90 1396.55 Per Metre 75.10 4580.60
j) 5" i/d (125 mm) 5.4mm thick Per Rft. 26.45 1721.45 Per Metre 86.75 5646.35
k) 6" i/d (150 mm) 5.4mm thick Per Rft. 26.75 2060.75 Per Metre 87.75 6759.30
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
d) 8" i/d (200 mm) Per Rft. 41.35 996.50 Per Metre 135.65 3268.50
e) 10" i/d (250 mm) Per Rft. 53.60 1389.55 Per Metre 175.85 4557.75
f) 12" i/d (300 mm) Per Rft. 68.15 1933.05 Per Metre 223.55 6340.40
g) 14" i/d (350 mm) Per Rft. 78.35 3322.95 Per Metre 257.05 10899.20
h) 16" i/d (400 mm) Per Rft. 88.25 4243.70 Per Metre 289.45 13919.35
i) 18" i/d (450 mm) Per Rft. 103.95 5204.70 Per Metre 341.00 17071.35
j) 20" i/d (500 mm) Per Rft. 122.15 6194.85 Per Metre 400.70 20319.05
k) 24" i/d (600 mm) Per Rft. 146.55 8716.35 Per Metre 480.70 28589.70
25 D Class Working Pressure PS 428 &
a) 3" i/d (75 mm) Per Rft. 20.60 257.00 Per Metre 67.65 842.90 ISO 160
b) 4" i/d (100 mm) Per Rft. 21.85 365.95 Per Metre 71.70 1200.40
c) 6" i/d (150 mm) Per Rft. 30.00 631.25 Per Metre 98.40 2070.45
d) 8" i/d (200 mm) Per Rft. 41.35 996.50 Per Metre 135.65 3268.50
e) 10" i/d (250 mm) Per Rft. 53.60 1389.55 Per Metre 175.85 4557.75
f) 12" i/d (300 mm) Per Rft. 68.15 1933.05 Per Metre 223.55 6340.40
g) 14" i/d (350 mm) Per Rft. 78.35 3322.95 Per Metre 257.05 10899.20
h) 16" i/d (400 mm) Per Rft. 88.25 4243.70 Per Metre 289.45 13919.35
i) 18" i/d (450 mm) Per Rft. 103.95 5204.70 Per Metre 341.00 17071.35
j) 20" i/d (500 mm) Per Rft. 122.15 6194.85 Per Metre 400.70 20319.05
26 Providing, laying, cutting, jointing, testing and disinfecting PS 3051 Providing and installing specials
PVC/ uPVC pipe line with `B' Class working pressure BS 3505 and valves is not included in the
pipe, in trenches, complete in all respects:- rate, which is payable separately.
a) 3" i/d (75 mm) Per Rft. 6.00 209.15 Per Metre 19.65 686.10
b) 4" i/d (100 mm) Per Rft. 7.75 318.65 Per Metre 25.45 1045.15
c) 5" i/d (125 mm) Per Rft. 9.40 450.05 Per Metre 30.90 1476.15
d) 6" i/d (150 mm) Per Rft. 9.75 626.65 Per Metre 31.95 2055.35
e) 8" i/d (200 mm) Per Rft. 13.85 950.20 Per Metre 45.40 3116.65
f) 10" i/d (250 mm) Per Rft. 18.65 1606.20 Per Metre 61.25 5268.35
h) 12" i/d (300 mm) Per Rft. 23.20 2249.65 Per Metre 76.10 7378.85
g) 14" i/d (350 mm) Per Rft. 30.30 2727.95 Per Metre 99.30 8947.75
27 Providing, laying, cutting, jointing, testing and disinfecting Chap Providing and installing specials
pipe line in trenches with PVC/ uPVC pipes of B.S.S. with `D' 2 and valves is not included in the
Class working pressure complete in all respects:- rate, which is payable separately.
a) 2" i/d (50 mm) Per Rft. 4.85 148.05 Per Metre 15.85 485.60
b) 3" i/d (75 mm) Per Rft. 5.95 325.40 Per Metre 19.45 1067.30
c) 4" i/d (100 mm) Per Rft. 7.70 546.25 Per Metre 25.25 1791.70
d) 5" i/d (125 mm) Per Rft. 9.35 812.30 Per Metre 30.60 2664.30
e) 6" i/d (150 mm) Per Rft. 9.65 1188.35 Per Metre 31.65 3897.80
28 Providing and fixing cast iron special of B.S.S. Class `B' 9.1 i) Labour rates include the cost of
(such as bend, tee cross collar, reducer, tail piece, jointing material & labour.
flanged spigot, cap, flanged socket, taper, angle branch,
plug etc.) for cast iron pipe line , complete:- ii) The internal dia of the pipe, from
which the branch is taken out will
a) C.I.S.S. Specials, with spigot. and be considered the internal dia for
socket joint:- the purpose of payments of
i) 3" to 6" (75 to 150 mm) i/d Per Kg. 32.65 131.15 Per Kg 32.65 131.15 specials.
ii) 8" to 12" (200 to 300 mm) i/d Per Kg. 18.00 116.55 Per Kg 18.00 116.55
iii) 15" to 18" (375 to 450 mm) i/d Per Kg. 14.20 112.75 Per Kg 14.20 112.75
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
i) 3" to 6" (75 to 150 mm) i/d Per Kg 12.35 110.90 Per Kg 12.35 110.90
ii) 8" to 12" (200 to 300 mm) i/d Per Kg 2.35 100.90 Per Kg 2.35 100.90
iii) 15" to 18" (375 to 450 mm) i/d Per Kg 5.50 100.90 Per Kg 5.50 100.90
i) 3" to 6" (75 to 150 mm) i/d Per Kg 20.70 119.25 Per Kg 20.70 119.25
ii) 8" to 12" (200 to 300 mm) i/d Per Kg 20.70 119.25 Per Kg 20.70 119.25
iii) 15" to 18" (375 to 450 mm) i/d Per Kg 20.70 119.25 Per Kg 20.70 119.25
29 Providing and fixing cast iron specials of B.S.S. Class 'B' 9.1 1) Labour rates include the cost of
(such as bend, tee, cross collar, reducer, tail piece, jointing material and labour.
flanged socket, flanged spigot, cap, taper, angle branch,
plug, etc) for Asbestos cement pipe line, with comet joint 2) The internal dia of the pipe, from
and rubber ring, complete. which the branch is taken out, will
i) 3" to 6" (75 to 150 mm) i/d Per Kg 13.75 112.30 Per Kg 13.75 112.30 be considered the internal dia for
ii) 8" to 18" (200 to 450 mm) i/d Per Kg 6.85 105.40 Per Kg 6.85 105.40 the purpose of payment.
iii) 20" to 24" (500 to 600 mm) i/d Per Kg 5.40 103.95 Per Kg 5.40 103.95
30 Providing and fixing sluice valve of B.S.S. quality and 9.1 Labour rates include cost of jointing
weight, Class `B', for cast iron pipe line, and Asbestos material and labour.
cement pipe line (including cost of jointing material):-
a) 3" i/d (75 mm) Each 1346.40 8366.40 Each 1346.40 8366.40
b) 4" i/d (100 mm) Each 1465.20 9565.20 Each 1465.20 9565.20
c) 5" i/d (125 mm) Each 2637.35 14517.35 Each 2637.35 14517.35
d) 6" i/d (150 mm) Each 2811.60 18891.60 Each 2811.60 18891.60
e) 8" i/d (200 mm) Each 3282.85 28122.85 Each 3282.85 28122.85
f) 10" i/d (250 mm) Each 5280.65 39840.65 Each 5280.65 39840.65
g) 12" i/d (300 mm) Each 5934.05 57534.05 Each 5934.05 57534.05
h) 16" i/d (400 mm) Each 7870.50 88870.50 Each 7870.50 88870.50
i) 18" i/d (450 mm) Each 9058.50 138658.50 Each 9058.50 138658.50
31 Providing and fixing, sluice valve of B.S.S. quality and Labour rates include cost of jointing
weight, for Asbestos cement pipe line, with comet joint 9.1 material and labour.
and rubber ring, complete (including cost of jointing
materials):-
a) 3" i/d (75 mm) Each 564.00 7584.00 Each 564.00 7584.00
b) 4" i/d (100 mm) Each 666.65 8766.65 Each 666.65 8766.65
c) 6" i/d (150 mm) Each 810.05 14610.05 Each 810.05 14610.05
d) 8" i/d (200 mm) Each 1276.75 26116.75 Each 1276.75 26116.75
e) 10" i/d (250 mm) Each 1591.45 33751.45 Each 1591.45 33751.45
f) 12" i/d (300 mm) Each 1928.35 42248.35 Each 1928.35 42248.35
g) 16" i/d (400 mm) Each 2261.25 80861.25 Each 2261.25 80861.25
h) 18" i/d (450 mm) Each 2624.20 132224.20 Each 2624.20 132224.20
32 Providing and fixing, fire hydrants B.S.S. quality and Each 71.45 4985.45 Each 71.45 4985.45 9.1 1) Labour rates include cost of
weight of 2½" (65 mm) dia (including cost of jointing jointing material and labour.
material).
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
a) 3" to 6" (75 to 150 mm) i/d Per Kg 55.30 132.30 Per Kg 55.30 132.30
b) 8" to 12" (200 to 300 mm) i/d Per Kg 35.05 112.10 Per Kg 35.05 112.10
c) 15" to 18" (375 to 450 mm) i/d Per Kg 29.50 106.50 Per Kg 29.50 106.50
36 Providing, laying, cutting, jointing, testing and disinfecting Cost of sockets, tees, elbows,
G.I. pipe line in trenches, with flanged joints, using G.I. bends, valves, crosses, unions and
pipe of B.S.S. 1387-1967 complete in all respects, plugs, etc. is included in the rates.
including specials and valves:-
a) 1½" i/d (40 mm) Per Rft. 27.95 375.75 Per Metre 91.75 1232.40
b) 2" i/d (50 mm) Per Rft. 26.10 517.50 Per Metre 85.60 1697.40
c) 2½" i/d (65 mm) Per Rft. 29.05 664.05 Per Metre 95.25 2178.15
d) 3" i/d (75 mm) Per Rft. 29.05 844.05 Per Metre 95.30 2768.40
e) 4" i/d (100 mm) Per Rft. 34.10 1216.50 Per Metre 111.85 3990.05
f) 6" i/d (150 mm) Per Rft. 39.05 1644.80 Per Metre 128.10 5394.95
g) 8" i/d (200 mm) Per Rft. 39.30 1930.80 Per Metre 128.90 6333.05
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
a) 3" i/d (80 mm) Each 188.80 668.80 Each 188.80 668.80
b) 4" i/d (100 mm) Each 209.90 1145.90 Each 209.90 1145.90
c) 5" i/d (125 mm) Each 257.20 2129.20 Each 257.20 2129.20
d) 6" i/d (150 mm) Each 266.20 2222.20 Each 266.20 2222.20
a) 3" i/d (75 mm) Each 81.25 165.25 Each 81.25 165.25
b) 4" i/d (100 mm) Each 94.05 244.05 Each 94.05 244.05
c) 5" i/d (125 mm) Each 117.55 327.55 Each 117.55 327.55
d) 6" i/d (150 mm) Each 121.70 409.70 Each 121.70 409.70
e) 8" i/d (200 mm) Each 173.25 821.25 Each 173.25 821.25
f) 10" i/d (250 mm) Each 197.95 1937.95 Each 197.95 1937.95
g) 12" i/d (300 mm) Each 230.50 4310.50 Each 230.50 4310.50
h) 14" i/d (350 mm) Each 254.05 3494.05 Each 254.05 3494.05
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
c) 2" i/d (50 mm) Each 61.90 112.30 Each 61.90 112.30
d) 3" i/d (75 mm) Each 81.25 236.05 Each 81.25 236.05
e) 4" i/d (100 mm) Each 94.05 379.65 Each 94.05 379.65
f) 5" i/d (125 mm) Each 117.55 645.55 Each 117.55 645.55
g) 6" i/d (150 mm) Each 121.70 1045.70 Each 121.70 1045.70
a) 3" i/d (75 mm) Each 125.85 167.85 Each 125.85 167.85
b) 4" i/d (100 mm) Each 138.65 192.65 Each 138.65 192.65
c) 5" i/d (125 mm) Each 173.35 241.75 Each 173.35 241.75
d) 6" i/d (150 mm) Each 177.45 259.05 Each 177.45 259.05
e) 8" i/d (200 mm) Each 247.60 383.20 Each 247.60 383.20
f) 10" i/d (250 mm) Each 272.30 446.30 Each 272.30 446.30
g) 12" i/d (300 mm) Each 319.70 533.30 Each 319.70 533.30
h) 14" i/d (350 mm) Each 343.25 610.85 Each 343.25 610.85
41 Making connection for new watersupply lines with the The rate includes the component of
running main, including excavation of trench and refilling, bailing out water from the trench
complete, but excluding cost of pipe and specials, etc. and cutting of existing pipe line.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
b) PN-8 (SDR-21)
i) 90 mm P.Rft 4.20 122.50 PM 11.50 401.95
ii) 110 mm P.Rft 11.25 188.65 PM 30.75 618.90
iii) 125 mm P.Rft 12.40 239.90 PM 33.85 787.10
iv) 160 mm P.Rft 13.55 387.80 PM 37.05 1,272.30
v) 180 mm P.Rft 17.05 487.10 PM 46.60 1,598.15
vi) 200 mm P.Rft 18.95 601.80 PM 51.85 1,974.55
vii) 225 mm P.Rft 21.55 759.55 PM 58.95 2,492.00
viii) 250 mm P.Rft 30.60 933.90 PM 83.65 3,064.10
ix) 315 mm P.Rft 54.85 1,483.00 PM 150.00 4,865.75
x) 355 mm P.Rft 60.90 1,874.85 PM 166.45 6,151.35
xi) 400 mm P.Rft 68.75 2,384.95 PM 187.95 7,824.95
xii) 450 mm P.Rft 69.75 3,008.90 PM 190.65 9,872.10
xiii) 500 mm P.Rft 81.65 3,719.45 PM 223.30 12,203.45
xiv) 560 mm P.Rft 89.70 4,671.45 PM 245.30 15,327.05
xv) 630 mm P.Rft 100.85 5,867.25 PM 275.75 19,250.45
xvi) 710 mm P.Rft 112.90 7,492.55 PM 308.75 24,583.05
xvii) 800 mm P.Rft 128.50 9,444.50 PM 351.40 30,987.30
xviii) 900 mm P.Rft 158.70 12,056.40 PM 433.90 39,557.05
xix) 1000 mm P.Rft 185.80 14,859.00 PM 508.05 48,752.45
c) PN-10 (SDR-17)
i) 90 mm P.Rft 4.20 149.50 PM 11.50 490.55
ii) 110 mm P.Rft 11.25 228.20 PM 30.75 748.65
iii) 125 mm P.Rft 12.40 291.05 PM 33.85 954.85
iv) 160 mm P.Rft 13.55 468.80 PM 37.05 1,538.20
v) 180 mm P.Rft 17.05 593.20 PM 46.60 1,946.30
vi) 200 mm P.Rft 18.95 730.10 PM 51.85 2,395.50
vii) 225 mm P.Rft 21.55 925.45 PM 58.95 3,036.40
viii) 250 mm P.Rft 30.60 1,137.45 PM 83.65 3,731.90
ix) 315 mm P.Rft 54.85 1,811.95 PM 150.00 5,945.00
x) 355 mm P.Rft 60.90 2,302.20 PM 166.45 7,553.45
xi) 400 mm P.Rft 68.75 2,898.10 PM 187.95 9,508.75
xii) 450 mm P.Rft 69.75 3,664.85 PM 190.65 12,024.30
xiii) 500 mm P.Rft 81.65 4,536.15 PM 223.30 14,883.10
xiv) 560 mm P.Rft 89.70 5,697.85 PM 245.30 18,694.60
xv) 630 mm P.Rft 100.85 7,182.05 PM 275.75 23,564.35
xvi) 710 mm P.Rft 112.90 9,136.30 PM 308.75 29,976.20
xvii) 800 mm P.Rft 128.50 11,532.95 PM 351.40 37,839.55
xviii) 900 mm P.Rft 158.70 14,693.75 PM 433.90 48,210.20
xix) 1000 mm P.Rft 185.80 18,124.35 PM 508.05 59,465.95
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
d) PN-12.5 (SDR-13.6)
i) 90 mm P.Rft 4.20 181.35 PM 11.50 595.00
ii) 110 mm P.Rft 11.25 274.50 PM 30.75 900.55
iii) 125 mm P.Rft 12.40 350.85 PM 33.85 1,151.10
iv) 160 mm P.Rft 13.55 568.15 PM 37.05 1,864.15
v) 180 mm P.Rft 17.05 721.50 PM 46.60 2,367.25
vi) 200 mm P.Rft 18.95 883.50 PM 51.85 2,898.75
vii) 225 mm P.Rft 21.55 1,120.30 PM 58.95 3,675.75
viii) 250 mm P.Rft 30.60 1,384.40 PM 83.65 4,542.15
ix) 315 mm P.Rft 54.85 2,199.75 PM 150.00 7,217.35
x) 355 mm P.Rft 60.90 2,781.60 PM 166.45 9,126.45
xi) 400 mm P.Rft 68.75 3,521.30 PM 187.95 11,553.35
xii) 450 mm P.Rft 69.75 4,452.95 PM 190.65 14,610.15
xiii) 500 mm P.Rft 81.65 5,501.15 PM 223.30 18,049.25
xiv) 560 mm P.Rft 89.70 6,918.10 PM 245.30 22,698.35
xv) 630 mm P.Rft 100.85 8,710.05 PM 275.75 28,577.70
xvi) 710 mm P.Rft 112.90 11,088.75 PM 308.75 36,382.20
xvii) 800 mm P.Rft 128.50 14,013.05 PM 351.40 45,976.80
xviii) 900 mm P.Rft 158.70 17,858.75 PM 433.90 58,594.55
xix) 1000 mm P.Rft 185.80 21,722.45 PM 508.05 71,271.45
e) PN-16 (SDR-11)
i) 90 mm P.Rft 4.20 218.00 PM 11.50 715.30
ii) 110 mm P.Rft 11.25 330.45 PM 30.75 1,084.15
iii) 125 mm P.Rft 12.40 424.15 PM 33.85 1,391.65
iv) 160 mm P.Rft 13.55 688.75 PM 37.05 2,259.80
v) 180 mm P.Rft 17.05 867.15 PM 46.60 2,845.20
vi) 200 mm P.Rft 18.95 1,070.65 PM 51.85 3,512.75
vii) 225 mm P.Rft 21.55 1,352.80 PM 58.95 4,438.50
viii) 250 mm P.Rft 30.60 1,668.00 PM 83.65 5,472.65
ix) 315 mm P.Rft 54.85 2,643.50 PM 150.00 8,673.25
x) 355 mm P.Rft 60.90 3,352.70 PM 166.45 11,000.15
xi) 400 mm P.Rft 68.75 4,249.60 PM 187.95 13,942.90
xii) 450 mm P.Rft 69.75 5,373.20 PM 190.65 17,629.55
xiii) 500 mm P.Rft 81.65 6,636.55 PM 223.30 21,774.45
xiv) 560 mm P.Rft 89.70 8,328.45 PM 245.30 27,325.55
xv) 630 mm P.Rft 100.85 10,517.80 PM 275.75 34,508.95
xvi) 710 mm P.Rft 112.90 13,373.05 PM 308.75 43,876.90
f) PN-20 (SDR-9)
i) 90 mm P.Rft 4.20 238.65 PM 11.55 783.05
ii) 110 mm P.Rft 11.25 360.65 PM 30.75 1,183.30
iii) 125 mm P.Rft 12.40 464.25 PM 33.85 1,523.25
iv) 160 mm P.Rft 13.55 754.35 PM 37.05 2,475.00
v) 180 mm P.Rft 17.05 953.10 PM 46.60 3,127.10
vi) 200 mm P.Rft 18.95 1,178.25 PM 51.85 3,865.80
vii) 225 mm P.Rft 21.55 1,490.00 PM 58.95 4,888.60
viii) 250 mm P.Rft 30.60 1,837.30 PM 83.65 6,028.15
ix) 315 mm P.Rft 54.85 2,922.00 PM 150.00 9,587.10
x) 355 mm P.Rft 60.90 3,706.10 PM 166.45 12,159.70
xi) 400 mm P.Rft 68.75 4,696.15 PM 187.95 15,408.10
xii) 450 mm P.Rft 69.75 5,937.80 PM 190.65 19,481.85
xiii) 500 mm P.Rft 81.65 7,318.30 PM 223.30 24,011.30
chapter-23(Tubewell).xls Page 148
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
44
P/F Ejector Pump of specified Suction and Delivery heads,coupled with
Single Phase Seimen Electric Motor of required rating for water supply i/c
the cost of connection charges, necessary wire, PVC pipes etc complete in
all respect as approved and directed by the Engineer Incharge.
i) G-II (1-1/4"x3/4") with 1 HP Electric Motor, 21-Mtr Suction and 21 Each 836.90 11903.30 Each 836.90 11903.30
M delivery head
ii) G-IV (2-1/2"x2") with 2.5 HP Electric Motor, 38-Mtr Suction and 38 Each 836.90 17282.90 Each 836.90 17282.90
M delivery head
45 Providing and fixing CP heavy duty brass Ball valve with CP handle of
specified diameter made of Faisal/Sonex / Master best quality or
equivalent complete in all respect as approved and directed by the
Engineer Incharge.
i) 1/2" dia Each 178.20 838.20 Each 178.20 838.20
ii) 3/4" dia Each 178.20 1282.20 Each 178.20 1282.20
iii) 1" dia Each 178.20 1522.20 Each 178.20 1522.20
iv) 1-1/4" dia Each 178.20 1678.20 Each 178.20 1678.20
v) 1-1/2" dia Each 178.20 1978.20 Each 178.20 1978.20
vi) 2" dia Each 178.20 2398.20 Each 178.20 2398.20
vii) 2-1/2" dia Each 178.20 2518.20 Each 178.20 2518.20
46 Providing, laying, testing and commissioning of POLYPROPYLENE
RANDOM COPOLYMER (PPRC) water supply pipe made of (Dadex
/Popular/ Beta / BBJ) with specified pressure rating PN (PRESSURE
NOMINAL)and conforming to DIN 8077-8078 code i/c cost of solvent,
specials,making jharries complete in all respect as approved and directed
by Engineer Incharge.(Internal/External Diameters mentioned).
a) PN-16 pipe
(i)(1/2") 20 mm Per Rft 5.25 32.20 Meter 17.25 105.65
(ii)(3/4") 25 mm Per Rft 5.25 43.35 Meter 17.25 142.15
(iii)(1") 32 mm Per Rft 6.10 69.85 Meter 20.00 229.10
(iv) (1-1/4") 40 mm Per Rft 6.15 96.15 Meter 20.15 315.35
(v)(1-1/2") 50 mm Per Rft 6.20 160.00 Meter 20.30 524.75
(vi)(2") 63 mm Per Rft 6.75 243.15 Meter 22.15 797.45
(vii)(2-1/4") 75 mm Per Rft 6.95 406.90 Meter 22.75 1334.60
(viii)(2-1/2") 90 mm Per Rft 7.80 582.30 Meter 25.60 1909.90
(ix) (3") 110 mm Per Rft 8.70 865.00 Meter 28.60 2837.15
b) PN-20 pipe
(i)(1/2") 20 mm Per Rft 5.25 36.05 Meter 17.25 118.30
(ii)(3/4") 25 mm Per Rft 5.25 49.75 Meter 17.25 163.20
(iii)(1") 32 mm Per Rft 6.10 79.70 Meter 20.00 261.40
(iv) (1-1/4") 40 mm Per Rft 6.15 119.95 Meter 20.15 393.50
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
47
Providing, laying, testing and commissioning µ-PVC (Un plasticized
Polyvinyl Chloride) Schedule pipe of nominal diameter, made
(Dadex/Popular / Beta / BBJ ) for water supply i/c the cost of solvent and
specials complete as approved and directed by the Engineer Incharge.
a) Schedule 40
(i) 1/2" Per Rft 3.90 68.60 Meter 12.80 225.00
(ii) 3/4" Per Rft 3.90 80.40 Meter 12.80 263.70
(iii) 1" Per Rft 3.90 119.25 Meter 12.80 391.10
(iv) 1-1/4" Per Rft 3.90 145.15 Meter 12.80 476.15
(v) 1-1/2" Per Rft 3.90 163.70 Meter 12.80 536.85
(vi) 2" Per Rft 3.90 224.75 Meter 12.80 737.15
(vii) 3" Per Rft 3.90 515.30 Meter 12.80 1690.15
(viii) 4" Per Rft 3.90 678.55 Meter 12.80 2225.65
(ix) 6" Per Rft 3.90 1355.85 Meter 12.80 4447.25
(x) 8" Per Rft 3.90 2025.80 Meter 12.80 6644.60
(xi) 10" Per Rft 3.90 2946.05 Meter 12.80 9663.10
(xii) 12" Per Rft 3.90 3675.70 Meter 12.80 12056.25
b) Schedule 80
(i) 1/2" Per Rft 3.90 12.80 Meter 79.50 260.80
(ii) 3/4" Per Rft 3.90 12.80 Meter 101.65 333.40
(iii) 1" Per Rft 3.90 12.80 Meter 140.50 460.80
(iv)1-1/4" Per Rft 3.90 12.80 Meter 179.35 588.25
(v) 1-1/2" Per Rft 3.90 12.80 Meter 198.75 651.95
(vi) 2" Per Rft 3.90 12.80 Meter 295.90 970.50
(vii) 3" Per Rft 3.90 12.80 Meter 684.75 2246.05
(viii) 4" Per Rft 3.90 12.80 Meter 859.60 2819.45
(ix) 6" Per Rft 3.90 12.80 Meter 1597.70 5240.45
(x) 8" Per Rft 3.90 12.80 Meter 2471.80 8107.45
(xi) 10" Per Rft 3.90 12.80 Meter 4239.00 13903.85
(xii) 12" Per Rft 3.90 12.80 Meter 5132.50 16834.55
48 Providing, laying, testing and commissioning of Grade-B,MS Seemless
Schedule pipe of nominal diameter, conforming to ASTM-106 made
(Jamal Pipes/ Hufaz Pipes/ Crescent Pipes ) duly welded i/c the cost of
specials complete as approved and directed by the Engineer Incharge.
(i) Schedule 40
(i) 1/2" Per Rft 7.80 70.45 Meter 25.60 231.15
(ii) 3/4" Per Rft 7.80 72.25 Meter 25.60 237.05
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
56 Supply and Installation of Gas & Liquid Copper Piping of specified size
and thickness including the cost of Fittings, Welding Complete
clamps/hangers/supports,testing charges and all other related material for
installation purpose complete in all respect as approved and directed by
the Engineer Incharge
(i) Ø 1/4" Per Rft 10.95 206.50 Meter 35.90 677.30
(ii) Ø 3/8" Per Rft 10.95 294.40 Meter 35.90 965.65
(iii) Ø 1/2" Per Rft 10.95 390.30 Meter 35.90 1280.25
(iv) Ø 5/8" Per Rft 10.95 512.95 Meter 35.90 1682.40
(v) Ø 3/4" Per Rft 16.40 605.95 Meter 53.80 1987.45
(vi) Ø 7/8" Per Rft 16.40 705.70 Meter 53.80 2314.75
(vii) Ø 1" Per Rft 16.40 740.90 Meter 53.80 2430.20
(viii) Ø 1-1/8" Per Rft 16.40 967.70 Meter 53.80 3174.05
(ix) Ø 1-1/4" Per Rft 21.90 1021.75 Meter 71.75 3351.25
(x) Ø 1-3/8" Per Rft 21.90 1124.80 Meter 71.75 3689.30
(xi)Ø 1-1/2" Per Rft 21.90 1668.40 Meter 71.75 5472.45
(xii)Ø 1-3/4" Per Rft 27.35 1792.00 Meter 89.70 5877.80
(xiii)Ø 2" Per Rft 27.35 1877.00 Meter 89.70 6156.55
(xiv)Ø 2-1/2" Per Rft 27.35 2036.90 Meter 89.70 6680.95
(xv)Ø 3" Per Rft 32.80 3799.25 Meter 107.65 12461.55
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
2 Supply and erection of M.S. conduit pipes for wiring, including 38.4 & 38.6
pull boxes, inspection boxes, bends, tees, etc. complete with
all specials.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
3 Supply and erection of PVC pipe for wiring recessed in walls, 38.3 &
including inspection boxes, pull boxes, hooks, cutting jharries, 38.5
and repairing surface, etc., complete with all specials.
5 Supply and erection of G.I. flexible pipe for wiring, including 38.4
welding of sockets, nipples and check nuts, etc. complete:-
6 Supply and erection PVC pipe for recessed wiring (main and 38.2 &
sub-main) purpose, including bends, specials, etc. in floor, 38.3
wall or trenches:-
7 Supply and erection of PVC pipe for surface wiring (main and
sub-main) including clamps, inspection boxes, pull boxes
bends etc., complete with all specials:-
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
ii) 80 mm i/d Per Rft. 20.10 150.00 Per Metre 66.00 492.05
iii) 100 mm i/d Per Rft. 23.00 191.95 Per Metre 75.45 629.65
8 Supply and erection of wooden strip batten for wiring Per Rft. 4.00 6.45 Per Metre 13.20 21.20 38.8 Additional width required to
purposes, including clips, insulation cleats, etc. accommodate wires will be provided
by erection of additional strips.
9 Supply and erection of Sahl wood casing and capping for Per Rft. 4.00 15.60 Per Metre 13.20 51.15 38.8
wiring purposes, including insulation cleats, screws, etc.
complete.
i) 3/0.74 mm (3/0.029") Per Rft. 8.05 14.45 Per Metre 26.40 47.45
ii) 3/0.91 mm (3/0.036") Per Rft. 8.05 14.90 Per Metre 26.40 48.85
iii) 7/0.74 mm (7/0.029") Per Rft. 8.05 18.75 Per Metre 26.40 61.50
iv) 7/0.91 mm (7/0.036") Per Rft. 8.95 26.05 Per Metre 29.35 85.50
v) 7/1.12 mm (7/0.044") Per Rft. 10.05 35.75 Per Metre 33.00 117.20
vi) 7/1.63 mm (7/0.064") Per Rft. 12.40 80.00 Per Metre 40.60 262.40
vii) 19/1.32 mm (19/0.052") Per Rft. 28.75 134.25 Per Metre 94.30 440.40
viii) 19/1.63 mm (19/0.064") Per Rft. 33.55 180.60 Per Metre 110.00 592.30
i) 3/0.74 mm (3/0.029") Per Rft. 8.95 15.35 Per Metre 29.35 50.40
ii) 3/0.91 mm (3/0.036") Per Rft. 8.95 15.80 Per Metre 29.35 51.80
iii) 7/0.74 mm (7/0.029") Per Rft. 8.95 19.65 Per Metre 29.35 64.40
iv) 7/0.91 mm (7/0.036") Per Rft. 9.45 26.60 Per Metre 31.05 87.20
v) 7/1.12 mm (7/0.044") Per Rft. 10.60 36.25 Per Metre 34.75 118.95
vi) 7/1.63 mm (7/0.064") Per Rft. 12.20 79.80 Per Metre 40.00 261.75
i) 3/0.74 mm (3/0.029") Per Rft. 8.05 14.05 Per Metre 26.40 46.05
ii) 3/0.91 mm (3/0.036") Per Rft. 8.05 17.05 Per Metre 26.40 55.90
iii) 7/0.74 mm (7/0.029") Per Rft. 8.05 21.30 Per Metre 26.40 69.90
iv) 7/0.91 mm (7/0.036") Per Rft. 8.95 29.05 Per Metre 29.35 95.30
v) 7/1.12 mm (7/0.044") Per Rft. 10.05 39.60 Per Metre 33.00 129.85
vi) 7/1.63 mm (7/0.064") Per Rft. 12.40 73.60 Per Metre 40.60 241.35
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
i) 3/0.74 mm (3/0.029") Per Rft. 9.45 30.85 Per Metre 31.05 101.25
ii) 3/0.91 mm (3/0.036") Per Rft. 9.45 41.55 Per Metre 31.05 136.35
iii) 7/0.74 mm (7/0.029") Per Rft. 9.45 54.40 Per Metre 31.05 178.45
iv) 7/0.91 mm (7/0.036") Per Rft. 10.60 77.55 Per Metre 34.75 254.35
v) 7/1.12 mm (7/0.044") Per Rft. 11.20 108.20 Per Metre 36.65 354.95
vi) 7/1.63 mm (7/0.064") Per Rft. 12.80 213.20 Per Metre 41.90 699.35
i) 3/0.74 mm (3/0.029") Per Rft. 10.05 38.30 Per Metre 33.00 125.65
ii) 3/0.91 mm (3/0.036") Per Rft. 10.05 51.15 Per Metre 33.00 167.75
iii) 7/0.74 mm (7/0.029") Per Rft. 10.60 68.20 Per Metre 34.75 223.75
iv) 7/0.91 mm (7/0.036") Per Rft. 10.60 97.90 Per Metre 34.75 321.05
v) 7/1.12 mm (7/0.044") Per Rft. 11.20 138.30 Per Metre 36.65 453.65
vi) 7/1.63 mm (7/0.064") Per Rft. 12.80 275.50 Per Metre 41.90 903.65
vii) 19/1.32 mm (19/0.052") Per Rft. 17.90 510.70 Per Metre 58.65 1,675.15
d) PVC insulated, PVC sheathed 4 core 660/1100 volt grade cable, Cost of trenches where necessary
armoured with G.I. wire 16 SWG. is included in the rates.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
i) 19/1.32 mm (19/0.052") Per Rft. 17.90 568.35 Per Metre 58.65 1,864.20
ii) 19/1.63 mm (19/0.064") Per Rft. 19.15 756.95 Per Metre 62.85 2,482.75
iii) 19/1.83 mm (19/0.072") Per Rft. 20.10 1,021.90 Per Metre 66.00 3,351.85
iv) 19/2.11 mm (19/0.083") Per Rft. 21.75 1,426.55 Per Metre 71.35 4,679.00
v) 37//1.83 mm (37/0.072") Per Rft. 22.35 1,939.05 Per Metre 73.35 6,360.05
vi) 37/2.11 mm (37/0.083") Per Rft. 26.85 2,450.35 Per Metre 88.00 8,037.10
vii) 37/2.36 mm (37/0.093") Per Rft. 32.20 2,986.25 Per Metre 105.60 9,794.90
viii) 37/2.62 mm (37/0.103") Per Rft. 40.25 3,716.80 Per Metre 132.00 12,191.15
15 Supply and erection of round block of Sahl wood, 10x4 cm Each 37.70 51.05 Each 37.70 51.05 38.1
(4"x1½") thick.
16 Supply and erection of teak wood board, 4.5 cm (1¾") thick. 38.1
18 Supply and erection of iron/aluminum clad, 500 volts main 38.1 When the base frame is already
switches with kitkat fuses, on angle iron board with 3 mm installed, the labour and composite
(1/8") thick M.S. sheet covering, including bonding to earth rates will be reduced as follows:- For
with necessary flexible pipe and thimbles, etc. 15 to 35 Amps. by Rs. 21.20 and Rs.
145.50. For 60 to 65 Amps. by Rs.
a) double pole: 38.80 and Rs. 252.60. For 100 Amps.
by Rs. 38.80 and Rs. 350.80.
i) 15/20 Amp. Each 880.00 1,959.70 Each 880.00 1,959.70
ii) 30/35 Amp. Each 880.00 2,250.20 Each 880.00 2,250.20
iii) 60/65 Amp. Each 1,320.00 3,005.20 Each 1,320.00 3,005.20
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
b) triple pole:
i) 15/20 Amp. Each 1,320.00 2,727.25 Each 1,320.00 2,727.25
ii) 30/35 Amp. Each 880.00 2,719.85 Each 880.00 2,719.85
19 Supply and erection of iron/aluminum clad, 500 volts main When the base frame is already
switches with triple pole and neutral link and HRC fuses, on 38.1 installed, the labour & composite
angle iron board with 3 mm (1/8") thick M.S. sheet covering, rates will be reduced as follows:-
including bonding to earth with necessary flexible pipe and
thimbles. i) For 60/65 Amp. by Rs. 21.20 and
Rs. 145.50.
60/65 Amp Each 1,320.00 3,794.25 Each 1,320.00 3,794.25 ii) For 100 to 300 Amp. by Rs. 21.20
100 Amp Each 1,729.20 5,241.70 Each 1,729.20 5,241.70 and Rs. 350.80
150 Amp Each 1,729.20 6,806.45 Each 1,729.20 6,806.45 iii) For 400 to 500 Amp. by Rs. 42.20
200 Amp Each 3,960.00 11,593.15 Each 3,960.00 11,593.15 and Rs. 526.20
300 Amp Each 3,960.00 13,002.20 Each 3,960.00 13,002.20
400 Amp Each 5,610.00 17,647.45 Each 5,610.00 17,647.45
500 Amp Each 5,940.00 21,805.75 Each 5,940.00 21,805.75
20 Supply and erection of iron/aluminum clad, branch ditto When the base frame is already
distribution board, 250 volt, on angle iron frame of suitable installed the labour and composite
size with 3 mm (1/8") M.S. sheet covering: rates will be reduced by Rs. 19.50 &
Rs. 152.20 respectively.
i) 2 way, 15 Amp per way Each 440.00 847.60 Each 440.00 847.60
ii) 3 way, 15 Amp per way Each 440.00 847.60 Each 440.00 847.60
iii) 4 way, 15 Amp per way Each 440.00 921.75 Each 440.00 921.75
iv) 5 way, 15 Amp per way Each 440.00 983.55 Each 440.00 983.55
v) 6 way, 15 Amp per way Each 440.00 1,026.80 Each 440.00 1,026.80
vi) 7 way, 15 Amp per way Each 440.00 1,082.45 Each 440.00 1,082.45
vii) 8 way, 15 Amp per way Each 440.00 1,131.85 Each 440.00 1,131.85
viii) 9 way, 15 Amp per way Each 440.00 1,187.50 Each 440.00 1,187.50
ix) 10 way, 15 Amp per way Each 440.00 1,267.85 Each 440.00 1,267.85
x) 11 way, 15 Amp per way Each 440.00 1,329.65 Each 440.00 1,329.65
xi) 12 way, 15 Amp per way Each 440.00 1,385.25 Each 440.00 1,385.25
xii) 2 way, 30 Amp per way Each 660.00 1,067.60 Each 660.00 1,067.60
xiii) 3 way, 30 Amp per way Each 660.00 1,073.75 Each 660.00 1,073.75
xiv) 4 way, 30 Amp per way Each 660.00 1,135.55 Each 660.00 1,135.55
xv) 5 way, 30 Amp per way Each 660.00 1,203.55 Each 660.00 1,203.55
xvi) 6 way, 30 Amp per way Each 660.00 1,246.80 Each 660.00 1,246.80
xvii) 7 way, 30 Amp per way Each 660.00 1,314.80 Each 660.00 1,314.80
xviii)8 way, 30 Amp per way Each 660.00 1,370.40 Each 660.00 1,370.40
xix) 9 way, 30 Amp per way Each 660.00 1,419.85 Each 660.00 1,419.85
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
xx) 10 way, 30 Amp per way Each 660.00 1,506.35 Each 660.00 1,506.35
21 Supply and erection of bus bars, for 500 volts 3 phase A.C. When the base frame is already
supply with four copper bars, including glazed porcelain 38.1 installed the labour and composite
bridges, on angle iron board, fixed with rag bolts and M.S. rates will be reduced by Rs. 21.20 and
sheet box 1.5 mm thick, etc. complete:- Rs. 145.50 respectively.
i) 60 Amp. with 4 copper bars Each 1,485.00 3,597.50 Each 1,485.00 3,597.50
size 1½"x1/8" (40 x 3 mm)
ii) 100 Amp. with 4 copper bars Each 1,485.00 3,597.50 Each 1,485.00 3,597.50
size 1½"x1/8" (40 x 3 mm)
iii) 200 Amp with 4 copper bars Each 2,310.00 4,521.40 Each 2,310.00 4,521.40
size 2"x1/8" (50x 3 mm)
iv) 300 Amp with 4 copper bars Each 2,970.00 5,181.40 Each 2,970.00 5,181.40
size 2"x3/16" (50x 5 mm)
v) 500 Amp with 4 copper Each 1,815.00 4,635.80 Each 1,815.00 4,635.80
size 2"x1/4" (50x 6 mm)
22 i) Supply and erection of plain pendent lamp holder, Each 27.50 119.65 Each 27.50 119.65 38.1
complete with bakelite lamp holder and flexible twin wire
23/0.0076" upto 2 metre length (without bulb and shade).
ii) Extra for additional length of flexible wire, beyond Per Rft. -- 1.65 Per Metre -- 5.45
2 metres.
23 Supply and erection of counter weight pedent with porcelain Each 55.00 264.25 Each 55.00 264.25 38.1
counter weight, and fitting on bakelite lamp holder, with
flexible twin wire 23/0.0076" complete (without bulb and
shade).
24 Supply and erection of stiff pedent with brass/metal pipe 6.3 Each 77.00 689.40 Each 77.00 689.40 ditto
cm (2.5") long, and 15 mm (½") dia brass oxidised or painted,
along with brass lamp holder with VIR/PVC cable 3/0.74 mm
(3/0.029").
25 Supply and erection of 22.5 cm (9") long swan neck plain Each 79.65 179.65 Each 79.65 179.65 ditto
brass/steel brass oxidised bracket lamp holder, complete.
26 Supply and erection of wall type/pole type bracket, with double Each 110.00 662.25 Each 110.00 662.25 ditto
cover water tight reflector, flexible wire and brass bolder.
27 Supply and erection of bakelite button holder shade, large Each 18.15 68.55 Each 18.15 68.55 ditto
size.
28 Supply and erection of call bell 220/250 volts, fixed on teak Each 77.00 306.20 Each 77.00 306.20 38.1
wood board 17.5x10 cm (7"x4").
29 Supply and erection of bell push or bed switch, with 5 metres Each 16.50 219.00 Each 16.50 219.00 38.1
twin flexible wire 23/0.0076".
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
30 Supply and erection of ceiling rose, bakelite. Each 27.50 48.30 Each 27.50 48.30 ditto
33 Supply and erection of wall socket with 3 pin 5 Amp, shoe. Each 26.40 91.20 Each 26.40 91.20 ditto
34 Supply and erection of 3 pin. 5 Amp wall socket. Each 26.40 66.50 Each 26.40 66.50 ditto
37 Supply and erection of 3 pin 10/15 Amp. wall socket with shoe, Each 26.40 159.20 Each 26.40 159.20 ditto
open type.
40 Supply and erection of brass bracket with holder. Each 22.00 91.00 Each 22.00 91.00 ditto
41 Supply and erection of bell push open/recessed type Each 14.65 36.20 Each 14.65 36.20 ditto
(without flexible wire).
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
43 Supply and erection of tube light, including rod, choke, starter 38.1
with frame, flexible wire, including connection from ceiling
rose, etc., complete.
i) double rod (80 watts) with two chokes and 2 starters. Per set 453.75 1,411.95 Per set 453.75 1,411.95
ii) single rod (40 watts) with one choke and one starter. ditto 363.00 802.05 ditto 363.00 802.05
iii) round tube, 32 watt, with one choke and one starter, Each 363.00 860.15 Each 363.00 860.15
without cover.
iv) round tube, 32 watt with one chock and one starter, with ditto 302.50 923.25 ditto 302.50 923.25
cover.
44 Providing and fixing M.S. iron box for housing main switches, ditto
made of 1.5 mm (1/16") thick M.S. sheet, with locking
arrangement, including painting:-
i) 60x35x15 cm (24"x14"x6") Each 948.75 3,345.45 Each 948.75 3,345.45
ii) 95x40x20 cm (38"x16"x8") Each 1,375.00 4,303.35 Each 1,375.00 4,303.35
iii) 105x52.5x22.5 cm (42"x21"x9") Each 2,092.20 5,998.10 Each 2,092.20 5,998.10
iv) 135x70x27.5 cm (54"x28"x11") Each 2,310.00 8,451.30 Each 2,310.00 8,451.30
45 Supply and erection of girder clamp hook, 16 mm (5/8") with Each 60.50 175.45 Each 60.50 175.45 38.1
M.S. plate 25x6 mm (1"x¼"), with bolts and nuts for hanging &
ceiling fans. 38.10
46 Supply and erection of girder strut, of M.S. tee section Each 77.00 1,506.25 Each 77.00 1,506.25 ditto
40x40x6 mm (1½"1½"x ¼"), complete with clamp, bolts and
nuts, etc., including fixing with cement concrete 1:3:6.
47 Supply and erection of roof suspension hook, 16 mm (5/8") Each 82.50 1,266.75 Each 82.50 1,266.75 38.1
dia rod with 75x40x3 mm (3"x1½"x1/8") M.S. steel channel,
with clamp, bolts and nuts, etc., including fixing with cement
concrete 1:3:6.
48 Supply and erection of roof suspension hook of M.S plate Each 110.00 561.40 Each 110.00 561.40
75x40x12.7mm (3"x1½"x½") with 16 mm (5/8") hook complete
with bolts, nuts and fixing with cement concrete 1:3:6
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
49 Supply and erection of 3/8" (10 mm) dia M.S. bar fan hook, Each 33.85 51.15 Each 33.85 51.15 ditto
placed at the time of casting of slab.
50 Erection of circular L.T. pole in cement concrete 1:3:6 one Each 935.40 3,103.90 Each 935.40 3,103.90 38.12
metre below ground level (excluding the cost of pole),
including cement concrete collar (1:2:4) excavation of
foundation, and finishing surface.
52 Supply and erection of anchor rod Henley type for pole, Per Rft. 14.35 28.40 Per Metre 47.15 93.10 38.14
including necessary clamps and 7/12" stay wire, straining
screws, etc., erected in cement concrete 1:3:6 and collar of
cement concrete.
53 Supply and erection of stay for house service pipe, erected Per Rft. 23.00 45.95 Per Metre 75.45 150.75 ditto
with straining screws and 7/14" stay wire, complete.
54 Supply and erection of house service pipe Henley (G.I. pipe Per Rft. 100.60 483.40 Per Metre 330.00 1,585.60
water quality) or pole type, 50 mm (2") dia, erected to instal
insulated overhead line,include shackle insulator for holding
insulated wire and straining devices for bearer wire and other
accessories etc., complete.
55 Supply and erection of house service pipe 50 mm (2") dia G.I. Per Rft. 83.85 464.40 Per Metre 275.00 1,523.25
pipe Henley or pole type for bare copper wire overhead line,
including shackle insulator, straining devices and other
accessories etc.
56 Supply and erection of lightning arrestor horn type, complete. Each 462.00 2,686.80 Each 462.00 2,686.80
57 Supply and erection of shackle insulator, medium size. Each 62.25 229.10 Each 62.25 229.10 38.12
58 Supply and erection of pin insulator, green medium size. Each 62.25 111.65 Each 62.25 111.65 ditto
59 Supply and erection of bare copper conductor wire No. 2 to Per Kg 32.35 1,116.35 Per Kg 32.35 1,116.35 38.1
No. 10 SWG, including binding wire No. 16 SWG.
60 Supply and erection of G.I. wire of all sizes, including binding Per Kg 32.35 180.35 Per Kg 32.35 180.35 ditto
wire No. 16 SWG for support of rubber wire or earthing wire,
pole to pole etc.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
i) 3/0.74 mm (3/0.029") Per Rft. 7.85 16.20 Per Metre 25.65 53.20
ii) 7/0.74 mm (7/0.029") ditto 7.85 24.60 ditto 25.65 80.60
iii) 7/0.91 mm (7/0.036") ditto 7.85 31.20 ditto 25.65 102.40
iv) 7/1.12 mm (7/0.044") ditto 7.85 40.35 ditto 25.65 132.40
62 Supply and erection of all aluminum stranded hard drawn bare Per Rft. 15.50 28.75 Per Metre 50.75 94.40 38.1
conductor, of size 7/3.099 mm (7/0.122").
63 Supply and erection of street light pole bracket 30 mm (1¼") Each 385.00 1,912.20 Each 385.00 1,912.20
G.I. pipe 2 metre long, complete with 2 No. pole clamp.
64 Supply and erection of pole mounted street light, holders,
shade and glass, etc., for fitting 125/250 watts mercury vapour
lamp (excluding cost of lamps):
i) G.E.C. design Each 770.00 3,192.55 Each 770.00 3,192.55
ii) Philips design ditto 770.00 3,575.70 ditto 770.00 3,575.70
66 Manufacture and erection of angle iron lattice steel structure Each 13,218.05 40,523.65 Each 13,218.05 40,523.65 38.13 The composite rate will be reduced
pole (36.0') 10,923 mm long 9348 mm (30.5') above ground or increased by Rs. 36.50 for each
level) 355 mm (14") square at base and 204 mm (8") square at (100 mm) of reduction or addition in
top for electric distribution line, using 1¼"x1¼"x3/16" (30x30x5 the height of the pole above ground
mm) angle iron legs and ¾"x¾"1/8" (20x20x3 mm) angle iron level.
bracing 420 mm (17") long fixed between legs on all the four
sides in diagonal position, and 1¾"x1¾"x3/16"(45x45x5 mm)
angle iron on top and 4 bands of M.S. flat iron 2"x¼" (50x6 mm)
305 mm (12") centre to centre, as per standard drawing
including silver painting of pole 3 coats, excavation and refilling
of foundation cement concrete 1:2:4. 6'-0"x1'-8"x1'-8"
(1807x500x500 mm) for foundation, etc, complete in all
respects.
67 Manufacture and erection of galvanized angle iron lattice steel Each 12,479.40 60,939.10 Each 12,479.40 60,939.10 38.13 The composite rate will be reduced
structure pole 37 ft. (11.25 m) long 30 ft. (9 m) above ground or increased by Rs. 237.00 for each
level), 34" square (850 mm) at base, 13.75" (35 mm) square at foot (300 mm) of reduction or
top, for electric distribution line, using 2"x2"x5/32" addition in the height of the pole
(50x50x4mm) high tensile steel angle iron legs, and 1-3/8"x above ground level.
1-3/8"x1/8" (35x35x3 mm) M.S. angle iron bracings fixed
between legs on all the four sides in diagonal position as per
standard drawing including silver painting of pole, excavation
and refilling of foundation, one ft. (300 mm) thick cement
concrete 1:3:6 foundation of outer size 8'x3½'x3½'
(2400x1050x1050 mm), etc. complete in all respects.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
68 Earthing of iron clad/aluminum switches, etc. with G.I. wire No. Job 1,650.00 7,226.75 Job 1,650.00 7,226.75
8 SWG in G.I. pipe 15 mm (½") dia, recessed or on surface of
wall and floor, complete with 1.5 metre long G.I. pipe, 50 mm
(2") dia with reducing socket 4 to 5 metre below ground level,
and 2 metre away from building plinth.
69 Earthing of Metallic cases, etc. with G.I. wire No. 8 SWG, in 38.11
15 mm (½") dia G.I. pipe, best quality:-
i) on surface, including clamps, etc. Per Rft. 17.60 104.85 Per Metre 57.75 343.85
ii) recessed in wall, including hooks, ditto 40.25 128.80 ditto 132.00 422.50
jharries and making good surface.
b) Copper wire:
71 Erection only, of lightning conductor of copper tape, including Per Rft. 28.15 34.05 Per Metre 92.40 111.70 38.11 Rate includes all materials required
supply of copper staple and copper nails and cement, sand in erection (excluding copper tape
mortar. lightning conductor).
72 Supply and erection of 600x600x3 mm (2'x2'x1/8") copper Each 1,100.00 4,963.20 Each 1,100.00 4,963.20 ditto
plate, including revitting to copper tape and placing in mixture
of salt and charcoal, etc.
i) tape 40x3 mm (1½"x1/8") Per Rft. 40.25 282.75 Per Metre 132.00 927.40
ii) tape 50x3 mm (2"x1/8") ditto 40.25 332.05 ditto 132.00 1,089.20
74 Supply and erection of 25 mm (1") dia and one metre long Job 770.00 3,106.05 Job 770.00 3,106.05
lightning conductor copper rod with 5 spikes on ball and base,
etc. complete.
a) single phase:
i) 1x10 Amp, 250 volts Each 330.00 2,466.00 Each 330.00 2,466.00
ii) 1x30 Amp, 250 volts ditto 330.00 2,466.00 ditto 330.00 2,466.00
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
i) 3x15 Amp, 400 volts Each 660.00 6,415.20 Each 660.00 6,415.20
ii) 3x50 Amp, 400 volts ditto 907.50 6,662.70 ditto 907.50 6,662.70
iii) 3x80 Amp, 400 volts ditto 907.50 6,662.70 ditto 907.50 6,662.70
76 Rewinding of A.C. ceiling fan, capacitor type, including cost of The credit of out turn of dismantled
wire, leatheride paper cotton tape, soldering, etc. material has been accounted for in
the rate.
i) 1200 mm (48") sweep, 275-300 RPM. Each 618.75 1,189.85 Each 618.75 1,189.85
ii) 1400 mm (56") sweep, 250-275 RPM. ditto 680.65 1,352.40 ditto 680.65 1,352.40
77 Rewinding of A.C. exhaust fan, including cost of wire, The credit of out turn of dismantled
leatheride paper, cotton tape, soldering, etc. material has been accounted for in
the rate.
i) 375 mm (15") sweep, and 1300-1500 RPM Each 440.00 837.50 Each 440.00 837.50
ii) 450 mm (18") sweep, and 1300-1500 RPM ditto 440.00 913.45 ditto 440.00 913.45
78 Rewinding of pedestal fan 600 mm (24") sweep, and 900-950 Each 528.00 1,068.25 Each 528.00 1,068.25 The credit of out turn of dismantled
RPM, including wire, leatheride paper, cotton, tape, etc. material has been accounted for in
the rate.
79 Supply and fitting of regulator knob with shaft Each 82.50 144.30 Each 82.50 144.30 38.1
and plate of electric fan regulator.
80 Supply and fitting of capacitor 2.2 uF, for ceiling fans. Each 66.00 114.00 Each 66.00 114.00 ditto
81 Supply and fitting of ball bearing of size Each 82.50 206.10 Each 82.50 206.10 ditto
6201, 6202 or 6203 for ceiling fans.
82 Rewinding regulator of ceiling fan 48"/56" (1200/1400 mm) Each 165.00 270.10 Each 165.00 270.10 The credit out turn of dismantled
sweep, to control 3/4 speeds. material has been accounted for in
the rate.
83 Erection of ceiling fan alongwith regulator (all sizes), including Each 285.65 323.80 Each 285.65 323.80
carriage from local Railway Station/Store to site of work,
electric wire/cable for suspension rod and board connection,
and cutting, threading on the rod, where necessary.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
1 Laying, linking and packing tramway line. 100Lft. 2658.85 Metre 87.20
3 Laying, linking of B.G. track, including packing, 100Lft. 6930.00 Metre 227.30
straightening and leveling.
4 Linking points and crossings, complete with fastenings. Each 6633.00 Each 6633.00
5 Bending or strainghtening B.G. rail with Jim Each 759.00 Each 759.00
Crow. Point Point
7 Binding ends of sleepers and timber of all sizes and kinds, 100 Nos 8200.50 100 Nos 8200.50
including spreading and restacking.
8 Opening stacks of sleepers and timber of all kinds and 100 Nos 994.40 100 Nos 994.40
sizes, including spreading for inspection and restacking
within one chain lead.
I RON WORK
9 Small iron work, such as gusset plates, knees, bends, Per Cwt 4455.00 14035.95 100 Kg 8769.70 27629.80
stirrups, straps, rings, etc. including cutting, drilling,
riveting, handling, assembling and fixing; but excluding
erection in position.
10 Fabrication of heavy steel work, with angle, tees, flat iron Per Cwt 1610.40 10735.80 100 Kg 3170.10 21133.45
round iron and sheet iron for making trusses, girders,
tanks, etc., including cutting, drilling, revitting, handling,
assembling and fixing, but excluding erection in position.
11 Erection and fitting in position iron trusses, staging of Per Cwt 513.35 100 Kg 1010.50
water tanks, etc.
12 Fixing corrugated iron sheet, including revitting, etc. 100 Sft. 1848.00 sq.m 198.85
13 Erecting corrugated iron sheet tanks, upto 20' Per Cwt 845.25 100 Kg 1663.90
(6 m) height.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
14 Erecting rolled steel beams or old rails, in roofs, etc., Per Cwt 500.50 100 Kg 985.25
erection and fixing in position.
15 Erecting rolled steel beams or rails, erection for posts etc. Per Cwt 244.75 100 Kg 481.80
(other than in roofs).
16 Making bolts and nuts of iron rods. Per Cwt 3514.50 14049.15 100 Kg 6918.30 27655.80
a) upto 6" size (150 mm) Per Cut 346.50 Per Cut 346.50
b) above 6" size (150 mm) Per Cut 514.80 Per Cut 514.80
18 Cutting rails or rolled steel beams of size below 6" Per 165.00 Per Cwt 165.00
(150 mm), with jim. Cut Cut
19 Bending rolled steel beams or rails. Per 178.20 430.10 Per 178.20 430.10
Bend Bend
20 Drilling holes, in plates upto ½" (13 mm) thick, per inch Per 66.00 Per 66.00
dia, (25mm) or part thereof. Hole Hole
21 Extra for drilling holes in plates over ½" (13 mm) thick, per Per 35.75 Per 35.75
inch dia, (25 mm) or part thereof. Hole Hole
22 Rivetting 1/8" dia (3 mm). 100 Nos 852.50 100 Nos 852.50
23 Cutting out Rivets, all sizes. 100 Nos 2970.00 100 Nos 2970.00
24 Fitting and erection of gutters of sheet iron. Per Lft. 109.05 Metre 357.65
25 Cutting and fixing iron bars, for barred windows. Per bar 66.00 Per bar 66.00
29 Fixing zinc iron or G.I. sheet on table tops. Per Sft. 27.20 sq.m 292.40
30 Making and fixing steel grated doors, complete with Per Sft. 278.15 1264.60 sq.m 2992.80 13607.10
locking arrangement, angle iron frame 2"x2"x3/8"
(50x50x10 mm) and ¾" (20 mm) square bars 4" (100 mm)
centre to centre.
31 Making and fixing steel grated door with 1/16" thick Per Sft. 289.95 1440.75 sq.m 3119.65 15502.50
(1.5mm) sheeting, including angle iron frame 2"x2"x3/8"
(50x50x10 mm) and ¾" (20 mm) square bars 4" (100 mm)
centre to centre, with locking arrangement.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
32 Making and fixing grating in opening, including fixing at Per Sft. 111.40 624.70 sq.m 1198.40 6721.85
site with flat iron 2"x3/8" (50x10 mm) and ¾" (19 mm)
square bars, at 4" (100 mm) centre to centre.
33 Providing and fixing stair railing (all types and designs) of Per Rft. 579.40 1378.70 Metre 1900.95 4523.30 The composite rate shall be
hard wood, including bends and corners, screwed to reduced or increased by Rs. 31.90
5/8"x5/8" (16x16 mm) M.S. square bars 2.75 ft. (838 mm) for each foot of reduction or
high, at 5.5 inch (137 mm) inch centre to centre, fixed in addition in the height of the square
steps of stairs, M.S. flat 1"x1/8" (25x3 mm) welded to bars.
bars, painting/polishing 3 coats, etc. complete.
34 Providing/fixing stair railing consisting of M.S. Box section Per Rft. 307.20 922.45 Metre 1007.85 3026.45
size 1-1/2"x3" of 16 SWG welded with M.S. flat 1"x1/8"
continuously and welded over M.S. square bars 5/8"x5/8"
punched in M.S. flat 2 ¾' high @ 5½" c/c fixed in steps of
stair I/C painting 3 coats complete.
35 Providing and fixing terrace railing of 2" (50 mm) i/d Per Rft. 222.05 992.75 Metre 728.51 3257.05 -do-
conduit pipe 16 SWG, welded with 5/8"x5/8" (16x16 mm)
square bar 2.75 ft. (838 mm) high fixed at 5" (125 mm)
centre to centre, in reinforced cement concrete slab with
suitable arrangement, complete in all respects, as per
design and drawing.
36 Providing and fixing collapsible gate made of 2"x2"x"¼" Per Sft. 430.40 1101.95 sq.m 4631.20 11856.75
(50x50x6 mm) tee iron at top and bottom, channel iron
verticals ¾"x¼"x¼"x1/8" (20x6x6x3 mm) at 3" (75 mm) to
5" (125 mm) centre to centre (approximate) and flat iron
crosses 3"x3/16" (75x5 mm), and best quality rollers at
bottom of 3" (75 mm) diameter including holdfasts,
handles 12" (300 mm) long of ¾"x¼"x¼"x1/8" (20x6x6x3
mm) channel iron, locking arrangement inside and
outside, painting 3 coats of black Japan enameled,
complete in working order.
37 Providing and fixing 24 SWG G.I. sheet rolling shutter, Per Sft. 96.25 342.40 sq.m 1035.65 3684.45
consisting of steel frame of M.S. channel 2"x1¼"x1/8"
(50x30x3 mm), angle iron 1½"x1½"x1/8" (40x40x3 mm),
M.S. plate 1'x1'x1/8" (300x300x3 mm), G.I. pipe 1½" (37
mm) dia, springs 2' (600 mm) centre to centre, rollers, 24
SWG G.I. covering 1 ft. x 1 ft. (300x300 mm), handles,
holdfast, and painting three coats, complete in all
respects.
38 Providing and fixing M.S. angle iron 1½"x1½"x¼" Per Rft. 46.60 246.50 Metre 152.85 808.80
(40x40x6 mm) edge protector nozing of steps of stairs,
having holdfast or 3/8" (10 mm) dia M.S. bars 8" (200 mm)
long welded at 2' (600 mm) centre to centre and
embedded in cement concrete on steps, complete in all
respects.
39 Providing and fixing stair railing of 2½" (63 mm) i/d G.I. Per Rft. 249.75 1200.15 Metre 819.35 3937.55 The composite rate shall be
pipe, welded with 5/8"x5/8" (16x16 mm) square M.S. bars reduced or increased by Rs. 31.90
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
2'-9" (838 mm) high, fixed in each step, complete in all for each foot of reduction or
respects, including painting, polishing three coats. addition in the height of the square
bars.
40 Providing and fixing G.I. wire gauze 24 SWG, 12x12 Per Sft. 44.00 91.55 sq.m 473.45 985.30
meshes per square inch, fixed to steel windows or doors,
etc., complete in all respects.
i) glass pane 2 mm thick Per Sft. 110.55 514.85 sq.m 1189.60 5539.80
ii) glass pane 2.5 mm thick ditto 110.55 517.30 ditto 1189.60 5566.40
iii) glass pane 3 mm thick ditto 110.55 521.05 ditto 1189.60 5606.30
iv) glass pane 4 mm thick ditto 110.55 527.20 ditto 1189.60 5672.75
v) glass pane 5 mm thick ditto 110.55 539.55 ditto 1189.60 5805.75
b) fixed with wire gauze, 22 SWG
i) glass pane 2 mm thick Per Sft. 156.85 619.15 sq.m 1687.60 6662.25
ii) glass pane 2.5 mm thick ditto 156.85 621.65 ditto 1687.60 6688.85
iii) glass pane 3 mm thick ditto 156.85 625.35 ditto 1687.60 6728.75
iv) glass pane 4 mm thick ditto 156.85 631.55 ditto 1687.60 6795.25
v) glass pane 5 mm thick ditto 156.85 643.90 ditto 1687.60 6928.25
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
44 Providing and fixing windows consisting of M.S. box Per Sft. 145.70 604.75 Per Sft. 1567.60 6507.10
section frame 2"x1½", (50x40mm) leaves frame 1½"x1"
(40x25mm) box section frame for glazing 3/8"x3/8"
(10x10mm) using 16 SWG sheet 'U' shaped rubber
supported with 1"x1/8" (25x3mm) M.S. flat for fixing 3/16"
(5 mm) thick glass panes M.S. box section ½"x½"
(13x13mm) of 16 SWG for fixing 24 SWG wire gauze on
outer side by means of ¾"x1/8" (20x3mm) M.S. flat and
screws including grill of M.S. flat ½"x1/8" (13x3mm) or
¼"x¼" (6x6mm) square bar with independent frame of
½"x½" (13x13mm) box section of 16 SWG i/c all C.P.
fitting and painting 3 coats complete in all respect.
45 Flapping G.I. pipes for bath room drains. Each 990.00 1029.55 Each 990.00 1029.55
46 Supply and fixing iron grating for fire place. Per Sft. 181.50 286.55 sq.m 1952.95 3083.40
47 Fixing copper flashing, including cutting of sheets, Per Lft. 77.00 Metre 252.55
grooving and rivetting.
48 Providing and fixing angle iron railing, using 2½"x2½"x3/8" Per Rft. 122.40 1407.40 Metre 401.50 4617.50
(63x63x10 mm) angle iron post 4½" (113 mm) long, 5' to
6' (1500 to 1800 mm) apart, with 2½"x2½"x3/8" (63x63x10
mm) angle iron top rail, and two rows of M.S. flat 2½"x¼"
(63x6 mm) including fixing to side of Bridge/structure with
U.bolt 1½' (450 mm) long ¾" (20 mm) dia, painting posts,
etc. complete in all respects.
49 Providing and fixing barbed wire fencing on compound 100Rft. 2678.25 15955.75 Metre 87.85 523.50
wall, consisting of 1½"x1½"x3/16" (40x40x5 mm), angle
iron post 3¼ ft. (990 mm) long, 5 to 6 ft. (1500 to 1800
mm) centre to centre, embedded in cement concrete
1:4:8, base of size 9"x9"x12" (225x225x300 mm), and
three rows of barbed wire, painting posts, etc. complete in
all respects.
50 Providing and fixing barbed wire fencing on compound 100Rft. 4502.55 20670.75 Metre 147.70 678.20
wall, consisting of 1½"x1½"x3/16" (40x40x5mm) angle
iron post 3' (900 mm) long, 4' (1200 mm) apart embedded
in cement concrete 1:4:8 base of size 6"x6"x9"
(150x150x225 mm) and 4 rows of barbed wire, including
binding wire, painting posts, etc. complete in all respects.
chapter-25(Iron work).xls Page 172
AMMENDED MRS, 2nd BI-ANNUAL-2021 (01.07.2021 to 31.12.2021) DISTRICT RAWALPINDI
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
51 Providing and fixing all types of partly fixed and partly (1) Increase rate by Rs. 40.00 per
openable glazed anodised bronze colour aluminium Sft or Rs.430.50 per Sq-metre if
doors, using delux section of M/s Al-Cop or Pakistan sections thickness is 2 mm.
Cables, having chowkat frame of size 40 x 100 mm (1½" x (2) Reduce rate by Rs.20.00 per Sft
4") and leaf frame of 60x40mm (2½"x1½") wide sections or Rs.215.20 per Sq-metre if
including the cost of ¼" (5 mm) thick imported tinted sections are of dull aluminimum
glass with aluminium triangular gola and rubber gasket to Per Sft 145.55 592.20 sq. m 1566.10 6372.05 shade.
support the glass and leaf edging, using approved (3) Reduce rate by Rs.20.00 per
standard fittings, locks, 3" (75 mm) wide long handles Sft or Rs.215.20 per Sq-metre if
etc., and hardware any required as approved by the local glass is used.
engineer in-charge.
52 Providing and fitting all types of glazed aluminium Per Sft 211.75 507.05 sq. m 2278.45 5455.85 (1) Reduce rate by Rs.20.00 per Sft
windows of anodised bronze colour partly fixed and partly or Rs.215.20 per Sq-metre if
sliding using delux sections of approved manufacturer section thickness is 1.2 mm.
having frame size of 100 x 20 mm (4"x¾") and
leaf frame sections of 50 x 20 mm (2"x¾"), all of 1.6mm (2) Reduce rate by Rs.20.00 per Sft
thickness including 5 mm thick imported tinted glass with or Rs.215.20 per Sq-metre if
rubber gasket using approved standard latches, hardware sections are of dull aluminium
etc., as approved by the Engineer in-charge. shade.
(3) Reduce rate by Rs.20.00 per Sft
or Rs.215.20 per sq-metre if local
glass is used.
53 Providing and fixing Aluminum Fly screen comprising of Fiber / Per Sft 48.15 332.15 P.Sqm 517.85 3573.65 Reduce composite rate by Rs.29.40
Aluminum wire guaze (Malasian) fixed in aluminum frame of P.Sft, if 1.2mm thick aluminum is
approved manufacturer brownze Colour / powder coated of size 1- used.
1/2"x1/2" and 1.6mm thick with rubber gasket i/c cost of Hardwares
as approved and directed by the engineer incharge. complete in all
respect.
54 P/F MS box section of 16 SWG, having frames of 2” x 1-1/2” , leave Per Sft 98.90 654.70 P.Sqm 1064.20 7044.65 i. If Brass stays will be provided, rate
frame of T-type box section of 2” x1” x1” , with ½” x1/2” box section of Rs.20/- P.Sft will be paid.
using, U shaped rubber for fixing 5 mm thick glass panes i/c the cost ii. For fixed pannels without guaze,
of fixing of 24 SWG wire guaze on inner side by means of ½” x1/8” reduce rate of Rs.150/- P.Sft.
MS flat patti, MS grill fitted within the window frame and screws Iii. If box sections of 18SWG used,
including hinges, brass handles and painting 3 coats. Complete in all reduce rate of Rs. 25/- P.Sft.
respect
55 Providing / Laying M.S Liner of specified thickness for concrete Cwt 0.80 4.35 P.Kg 41.80 221.45
bored piles, placed at the upper part of bore, as mentioned on
drawings etc complete in all respect.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
1 Notice board made of cement, sand mortar 1:3. Per Sft. 99.00 110.80 Per 1,065.25 1,192.30 The board is to be of cement
sq.m plaster ½" (13 mm) thick, with 2"
(50 mm) wide and 1" (25 mm) thick
beading.
2 Fixing handles to iron hammers. Each 137.50 - Each 137.50 -
3 Providing and fixing barbed wire fencing, with 4 horizontal 100Lft. 10,189.95 36,514.80 L.m. 334.30 1,198.00 Vertical bars in straining and
and 2 number cross wires fixed with posts of R.C.C., 1:2:4 stiffening posts to be 4 No. each by
(straining posts 7'x9"x9" (2.13 mx225x225 mm) at 100' ½" (13 mm) dia and for
(30 m) centre to centre, stiffening posts 7'x6"x6" (2.13 intermediate posts to be 4 No. of
mx150x150 mm) at 50 ft. (15 m) interval and intermediate 3/8" (10 mm) dia Stirrups for all
post 7'x5"x5" (2.13 mx125x125 mm) at 8 ft.(2.4 m) centre posts to be ¼" (6 mm) dia. at 12"
to centre), including cost of steel, its fabrication and (300 mm) centre to centre.
placing of steel reinforcement, eye bolts, washers, etc.
complete.
Surveying
4 Supplying Bamboo Jhandies 10' to 12' (3.00 to 3.65 m) with Each 62.05 191.80 Each 62.05 191.80
iron shoes, and flags 15" (375mm) square.
5 Supplying wooden pegs for levelling, 1½" (40 mm) dia, 6" 100Nos. 220.00 237.70 100Nos. 220.00 237.70
(150mm) long.
6 Supplying wooden pegs for alignment, 2" to 3" dia (50 to 100Nos. 528.00 731.95 100Nos. 528.00 731.95
75 mm), 9" (225 mm) long.
7 Fixing enamalled iron gauges flush with masonry, including Per Lft. 115.50 124.40 Per 378.95 408.15
cost of hooks. L.M.
8 Placing boundary pillars in position, including digging pits. Each 77.00 - Each 77.00 -
9 Fixing main line type distance mark in position, including Each 330.00 524.40 Each 330.00 524.40 Composite rate does not include
making 1:3:6 cement concrete base block, size cost of iron distance marks.
14"x10"x15" (350x250x375 mm).
10 Cutting pipes, upto 2" (50 mm) dia. Per cut 77.00 - Per cut 77.00 -
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
11 Cutting pipe, above 2" (50 mm) dia. Per cut 141.9 0 Per cut 141.9 0
12 Threading pipe ends, 1½" (40 mm) to 4" (100 mm) dia. Each 99.00 - Each 99.00 -
End End
13 Assembling 1½" (40 mm) dia pressure pipe. 100Lft. 350.65 - Per Metre 11.50 -
15 Repairs to hand pump, pulling out and refitting. Per Lft. 52.80 - Per Metre 173.25 -
17 Washing Niwar of bed. Per bed 742.50 777.80 Per bed 742.50 777.80
19 Recaning chairs:
i) office chairs, single caning seat only. Each 462.00 497.70 Each 462.00 497.70
ii) office chairs, double canning seat only. Each 594.00 644.45 Each 594.00 644.45
iii) office chairs, single caning back only. Each 330.00 332.25 Each 330.00 332.25
iv) office chairs, double caning back only. Each 528.00 547.35 Each 528.00 547.35
v) easy chairs, single caning seat only. Each 330.00 377.90 Each 330.00 377.90
vi) easy chairs, double caning seat only. Each 924.00 995.45 Each 924.00 995.45
vii) easy chairs, single caning only, back and seat in one Each 1,320.00 1,614.15 Each 1,320.00 1,614.15
piece.
viii) easy chairs, double caning back & seat in one piece Each 1,980.00 2,694.40 Each 1,980.00 2,694.40
or couches with caned area about 16 Sft (1.5 Sqm).
20 Making and fixing Hat pegs ordinary. Each 237.60 768.00 Each 237.60 768.00
21 Weaving charpoy. Each 858.00 - Each 858.00 -
23 Picture railing, including making, fixing and painting. Per Lft. 68.00 166.05 Per LM 223.05 544.85
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
26 Burning charcoal, including loading, unloading and 100Kg of 795.80 - 100Kg of 795.80 -
repairing kilns. Char- Char-
coal coal
27 Filling cement bags with coal and sewing (including cost 100Cft. 2,029.50 2,032.60 cu.m 716.80 717.90
of strings).
28 Supplying manure. Cart 247.50 383.45 Cart 247.50 383.45 Capacity of cart, 20 Cft. (0.57
Load Load cu.m).
30 Washing:-
31 Hoisting and placing sleepers for centring, including Each 90.75 - Each 90.75 -
carriage within one chain. No. No.
32 Dismantling sleepers from centring, including stacking Each 103.15 - Each 103.15 -
within one chain. No. No.
33 Dredging Sumps. Per 3,712.50 - Per 3,712.50 - Not less than five gangmen to be
Shift Shift employed for each shift to ensure
effective dredging.
34 Fixing `U' bolt in masonry or concrete, including levelling Each 302.50 - Each 302.50 -
and tying for fixing angle iron post.
a) by hand 1000 Cft. 2,970.00 - cu.m 104.90 - Rate includes cost of providing
b) by pump 1000 Cft. 360.95 572.70 ditto 12.75 20.25 pump, POL and operation charges,
etc.
36 Drilling holes in R.C. Trough. Per Nos. 192.50 - Per Nos. 192.50 -
37 Supplying and laying polythene sheet over D.P.C. under The rate includes overlaps.
floors and on roofs, etc.
i) 300 gauge (.003" thick) Per Sft. 2.00 3.85 sq.m 21.30 41.65
ii) 500 gauge (.005" thick) Per Sft. 3.95 5.55 sq.m 42.60 59.65
38 Laying 2" (50 mm) thick sand and bitumen carpet, on top 100Sft. 2,049.10 8,093.10 sq.m 220.50 870.80
of foundation of oil tank.
39 Cutting hole 4"x6" (100x150 mm) in stone masonry or Per 330.00 - Per 330.00 - Same rate to be paid for other type
brick wall with chisel, repairing masonry and removing Hole Hole of masonry and R.C.C. work.
debris within one chain lead.
Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
40 Making 1½"x1½" (40x40 mm) groove in wall of stone or Per 288.75 - Per 288.75 -
brick masonry in cement for fixing planks upto 9" (225 Plank Plank
mm) deep.
41 Drilling holes in stone or brick masonry upto 2" (50 mm) Per hole 99.00 Per hole 39.60
dia, per inch (25 mm) depth. per inch per c.m
depth depth
42 Spraying anti-termite liquid mixed with water in the ratio of 100Sft. of 132.00 270.35 sq.m of 14.20 29.10
1:40. each each
spray spray
i) without cement concrete base. 100Rft. 11,986.95 35,111.65 Per Metre 393.15 1,151.65
ii) in cement concrete 1:4:8 base of size 12"x12"x21" 100Rft. 13,142.50 38,238.35 Per Metre 431.05 1,254.20
(300x300x525 mm).
4 Supply & Installation of foil faced round flexible duct made of PET
(Polyethelene Terephthalate) of specified size i/c the cost of insulation
and supports as per drawings with all accessories and fittings complete
in all respect as approved and directed by Engineer Incharge.
(i) 6" dia Per Rft 28.80 351.90 P.Mtr 94.46 1154.23
(ii) 8" dia Per Rft 28.80 415.86 P.Mtr 94.46 1364.02
(iii) 10" Dia Per Rft 28.80 536.52 P.Mtr 94.46 1759.79
(iv) 12" Dia Per Rft 28.80 619.38 P.Mtr 94.46 2031.57
(v) 14" Dia Per Rft 28.80 707.58 P.Mtr 94.46 2320.86
(vi) 16" Dia Per Rft 28.80 898.50 P.Mtr 94.46 2947.08
5 Supply, wrapping of 3" thick foil-faced Rockwool thermal Insulation of
nominal density with built in GI wire mesh as per specifications and
drawings conforming to BS 5422:2009 complete in all respect as
approved and directed by the Engineer Incharge.
(i) 30-40 kg/m3 Per Sft 6.00 65.40 Sq.m 64.56 703.70
(ii) 45-50 kg/m3 Per Sft 6.00 91.80 Sq.m 64.58 988.14
(iii) 55-60 kg/m3 Per Sft 6.00 362.40 Sq.m 64.58 3900.87
(iv) 65-80 kg/m3 Per Sft 6.00 118.20 Sq.m 64.58 1272.30
(a) 12 kg/m3
(i)1" thick Per Sft 12.00 56.17 Sq.m 129.12 604.41
(ii)2" thick Per Sft 12.00 71.29 Sq.m 129.12 767.10
(b) 16 kg/m3
(i)1" thick Per Sft 12.00 57.43 Sq.m 129.12 617.97
(ii)2" thick Per Sft 12.00 73.81 Sq.m 129.12 794.22
(c) 24 kg/m3
(i)1" thick Per Sft 12.00 58.69 Sq.m 129.12 631.53
(ii)2" thick Per Sft 12.00 75.07 Sq.m 129.12 807.77
7 Providing and fixing 1" thick bonded fiberglass Blanket sound liner Per Sft 6.00 77.30 Sq.m 64.56 831.75
(Acoustic Liner) having density of 24 kg/m3 with NRC (Noise
Reduction Coefficient of 0.6 ) in ducts, fire retardant type with 100%
surface applied with adhesive as well as mechanical fasteners (
Gripnails) complete in all respect as aprroved and directed by
Engineer Incharge,
8 Providing and installation extruded anodized/Powder coated aluminum Per Sft 132.00 2052.00 Sq.m 1420.32 22079.52
Supply Air registers have horizontal and vertical adjustable deflecting
bars and opposed blade volume control dampers adjustable from face
with a removable key with minimum of 75% free area complete in all
respects as approved and directed by the Engineer Incharge.
(i) 0.3 mm Thick Per Sft 6.70 58.70 Sq.m 72.20 631.70
(ii) 0.4 mm Thick Per Sft 6.71 74.84 Sq.m 72.19 805.32
(iii) 0.5 mm Thick Per Sft 6.71 90.98 Sq.m 72.19 978.92
(iv) 0.6 mm Thick Per Sft 6.71 107.11 Sq.m 72.19 1152.52
(v) 0.8 mm Thick Per Sft 6.71 139.38 Sq.m 72.19 1499.71
(vi) 1.00 mm Thick Per Sft 6.71 171.65 Sq.m 72.19 1846.91
(vii) 1.20 mm Thick Per Sft 6.71 198.27 Sq.m 72.19 2133.43
(a) 25 mm thick
(i) 3/4"dia Per Rft 21.00 134.75 Meter 68.90 442.00
(ii) 1" dia Per Rft 21.00 140.85 Meter 68.90 462.05
(iii) 1-1/4" dia Per Rft 21.00 158.15 Meter 68.90 518.80
(iv) 1-1/2" dia Per Rft 21.00 168.05 Meter 68.90 551.25
(v) 2" dia Per Rft 31.50 190.90 Meter 103.30 626.20
(vi) 2-1/2" dia Per Rft 31.50 203.30 Meter 103.30 666.75
(vii) 3"dia Per Rft 31.50 228.00 Meter 103.30 747.85
(b) 50 mm thick
(i) 4" dia Per Rft 42.00 427.70 Meter 137.75 1402.80
(ii) 5" dia Per Rft 42.00 479.50 Meter 137.75 1572.85
(iii) 6" dia Per Rft 42.00 541.30 Meter 137.75 1775.55
(iv) 8" dia Per Rft 42.00 746.50 Meter 137.75 2448.50
(v) 10" dia Per Rft 52.50 793.05 Meter 172.20 2601.20
(vi) 12" dia Per Rft 52.50 978.45 Meter 172.20 3209.30
17 Supply & Installation built in Microban Elastomeric closed cell FM
approved Foam type insulation of 40-65 kg/m3 density and thermal
condcutivity of 0.035 W/M at 25 degree centigrade of fire performance
closely woven fiberglass cloth conforming to UK building regulation of
clause - 0 rating as specified, complete including the cost of adhesives
and sealers as approved and directed by Engineer Incharge.
(i)3/4 " dia pipe Per Rft 10.50 47.75 Meter 34.45 156.60
(ii)1 " dia pipe Per Rft 10.50 99.25 Meter 34.45 325.55
(iii)1-1/4" dia pipe Per Rft 21.00 140.65 Meter 68.90 461.35
(iv)1-1/2 " dia pipe Per Rft 21.00 171.55 Meter 68.90 562.70
(v)2 " dia pipe Per Rft 21.00 181.85 Meter 68.90 596.45
(i) 1" Thick Per Sft 52.50 1087.50 Sq.m 564.90 11701.50
(ii) 2" Thick Per Sft 52.50 1087.50 Sq.m 564.90 11701.50
(iii) 3" Thick Per Sft 52.50 1087.50 Sq.m 564.90 11701.50
20 Supply & Installation of Powder coated/extruded anodized Per Sft 26.25 1091.25 Sq.m 282.45 11741.85
rectangular/Squar aluminium louver duly fixed in frame of specified
thickness for intake/Exhaust air with fine finishing as approved and
directed by Engineer Incharge.
21 Supply & installation closed cell type polyolefin pipe insulation tube
with factory applied Aluminium foil of density 40-65 Kg/m³ of
specified thickness & thermal conductivity 0.035 w/m °C and fire
retardent of Class "o" rating as specified for refrigerant copper piping
as approved by the Engineer Incharge
(a) 19mm thick
(i) 1/4"dia Per Rft 4.20 75.80 Meter 13.80 248.55
(ii) 3/8" dia Per Rft 4.20 88.15 Meter 13.80 289.10
(iii) 1/2" dia Per Rft 4.20 94.30 Meter 13.80 309.35
(iv) 5/8" dia Per Rft 8.40 103.45 Meter 27.55 339.35
(v) 3/4" dia Per Rft 8.40 107.15 Meter 27.55 351.50
(vi) 7/8" dia Per Rft 8.40 110.90 Meter 27.55 363.70
(vii) 1"dia Per Rft 16.80 125.45 Meter 55.10 411.50
(viii) 1-1/8" dia Per Rft 16.80 139.05 Meter 55.10 456.10
(ix) 1-1/4" dia Per Rft 21.00 150.65 Meter 68.90 494.20
(x) 1-1/2" dia Per Rft 31.50 171.05 Meter 103.30 561.10
(xi) 1-5/8" dia Per Rft 31.50 179.70 Meter 103.30 589.45
(xii) 1-3/4" dia Per Rft 31.50 187.15 Meter 103.30 613.80
(xiii) 2" dia Per Rft 42.00 206.30 Meter 137.75 676.60
(xiv) 2-1/2" dia Per Rft 42.00 212.45 Meter 137.75 696.85
(xv) 3" dia Per Rft 42.00 213.60 Meter 137.75 700.60
(i) 2- Gal Capacity, Size 12-1/2"x8" Each 525.00 18515.00 Each 525.00 18515.00
(ii) 3.2 Gal Capacity, Size 12-1/2"x11" Each 525.00 23465.00 Each 525.00 23465.00
(iii) 4.5 Gal Capacity, Size 15"x11" Each 525.00 30115.00 Each 525.00 30115.00
(iv) 7.0 Gal Capacity, Size 11"x21-3/8" Each 525.00 32965.00 Each 525.00 32965.00
(v)14 Gal Capacity, Size 20"x15-1/2" Each 525.00 37065.00 Each 525.00 37065.00
(vi) 20 Gal Capacity, Size 27"x15-1/2" Each 525.00 65965.00 Each 525.00 65965.00