Inspection and

Rework FY21

NMEX PQE
Aug 2021

Nissan Stricly Confidential B 1


FY21 NMEX PQE Supplier Improvement Strategy
Workload Balance
NMEX PQE Must activites
FY20 FY21
Reactive Hot Items Solution – Speed Up Workload Workload
Internal – [Plant Concerns] External [Market Concerns]

Reactive
- Line Attendance - Parts Inspection - DC Room Alerts - Dealer Action

- Vehicle Analysis - Supplier FB (PIR) - CAR Wty Reply - TFT New Model

- Parts Metrology - PIR Solving (8DS) - Long Tail Attack - IQS Improvement
Fire Fighters

NMEX PQE New Preventive Strategy


Preventive Improve Worst Suppliers [L3 + L4] Control Good Suppliers [L1 + L2]
Quality System Improvement Assure Process Robustnness

Preventive
- Supplier Health Check - 4Ms Deployment
- Top Management Escalation - Horizontal Deployment
- Supplier War Room - Supplier Training (ITESM)
- Firewall Implementation - Key Parts Control System
Fire Preventers - Improvement Monitoring - Know How Sheet New Model
NMEX PQE One Team Preventive Activity
Need to reinforce during
ractive –> preventive transition!

Reactive PQE New Model PQE


Full Change Development
Internal Line Attendance Incoming Insp.
External
DC Room/TFT
Vehicle Analysis PIR/8Ds CAR/8Ds Minor Changes Development
O. Aguilar
QA SD A1 A2 CIVAC VPRENG
Senior Supervisor Senior Supervisor
Senior Supervisor Senior Supervisor
1. Felix Castro 1. J. Reyes 4. Juan Carranza
1. A. Concha 1. Marvin Macias
2. E. Rivera 5. E. Penaloza
2. E. Dominguez
3. V. Mora
L. Díaz STAFF
PQE Sr. Mgr
STAFF STAFF STAFF 1. G. Pardo 12. I. Moran.
1. Christian Muñoz 1. Daniel Tavares 1. Erivan Massiel 2. A. Rosales 13. Perez
2. Cesar Atla 2. Maria Valdez 2. Blanca Albavera 3. A. Rodriguez 14. J. Beltran
3. Fernando Ibarra 3. Daniela Muñoz 3. Claudia Garcia 4. A. Jimenez 15. J. Marin
M. Ahuactzin M. Hdz C. Roque E. Canseco 4. Jorge Morales 4. Rodrigo Muñoz 4. Enrique Arteaga 5. A. Aguilar 16. F. Gonzalez
New Mod Mgr A1 PQE Mgr PQE A2 Mgr PQE CIV Mgr 5. Araceli Gomez 5. Elpidio Garcia 5. Rebeca Perez 6. C. Rodriguez 17. F. Garcia
6. Karen Martinez 6. Juan Velasco 6. Jacob Miranda 7. C. Macias 18. J. Lira
PQE One Team Preventive Group 7. Gerardo Martinez 8. E. Luna 19. J. Ventura
Romero
8. Daniel Alegria 7. Ivan Ricardez 9. E. Becerra 20. O. Soto
9. Aaron Sanchez 10. E. Ortiz 21. O. De Leon
Muñoz 10. Mario Nafarrate 11. G. Barcenas 22. V. Ramirez
Leader
1. A1 D. Alegria 4. CIVAC J. Miranda SSV 2 SSV 1 SSV 1 SSV 5
2. A1 C. Atla STAFF: 10 -> 7 STAFF: 6 -> 5 STAFF: 6 -> 5 STAFF: 22 -> 21
3. A2 D. Tavares 5. VPRENG Barcenas
Inspection Chargeback Scheme Improvement
Current Condition
Basic Inspection Worklfow Highlights
• Inspection Starts until get part supplier
NG Part
Detection Request Selected Company approval (risk to market ouflow)
Request
Inspection Part Supplier Inspection to • Direct agreement between part supplier
NMEX PQE Sorting Company
and sorting Company.
Issue PIR to Analysis & agree Direct fee Material Inspection
responsabilty
• Supplier skips key information to
Supplier agreement at NISSAN Plant
NISSAN (quality alerts, clean points, etc)
• Sorting Administration Cost is not
considered in the PIR charge.

Improved Condition
Basic Inspection Worklfow Highlights
Sorting Companies • Inmediate inspection deployment, no
NG Part Request inspection
(2 at least)
Detection (preferent fee)
need supplier approval. Market protected
Inspect Material • NISSAN direct Communication with
NMEX PQE @NISSAN
Sorting Company
Issue PIR to Send Inspection Bill (NISSAN standard fee) Part Supplier
Supplier • NISSAN controls the complete operation.
Define CM
• All Sorting expenses are now considered
in the PIR charge.
CAMPAÑA DE REGULARIZACION DE RESIDENTES DE PROVEEDURIA PLANTA A1 Y A2

Objetivo: Regular la estadía y operación de los Residentes de calidad de la proveeduría dentro de las instalaciones de
NMEX.

Requisito para actualización de Anexo 1:

1. Certificado que de estudios que acredite una escolaridad mínima de Bachillerato


2. Anexo 1 de control de entrada a planta de proveedores. Original
3. SUA que certifique al proveedor de las partes como patrón del asegurado.
4. Constancia de trabajo, que incluya puesto y antigüedad laboral emitida por el área de RH de la compañía proveedora
de partes

Se estará recibiendo documentación a partir del 21 de septiembre hasta el 5 de octubre posterior a esta fecha se le negará
el acceso a las instalaciones de NISSAN A1