1 Marketing Dept will provide style information alocng with tech pack, quantity, approximate fabric in house date & shipment date.
2 IE depertment will preapare approximate SMV based on techpack & Sample.
3 Plannining dept will provide factory allocation along with no of line & approximate uninterrapted feeding quantity in line.
4 IE depertment will provide approximate average productiovity along with average efficiency
5 Per day approximate production may also need to circular on demand basis.
6 Productivity will be produced based on product criticality, no of day allocation by planning, no of manpower allocation / budgeted manpower per line.
7 Based on criticality product will classified as Easy (SMV 12-16) , Basic (SMV 16.01-20) , Semi Critical (SMV 20.01-27) , Critical ( 27.01- upper)
8 Based on criticality per day approximate expected efficiency is likely bellow :
Day 1 Easy -> efficiency 40 % Basic -> efficiency 30 % Semi critical -> efficiency 20 % Critical -> efficiency 15 %
Day 2 Easy -> efficiency 50 % Basic -> efficiency 40 % Semi critical -> efficiency 25 % Critical -> efficiency 15 %
Day 3 Easy -> efficiency 65 % Basic -> efficiency 55 % Semi critical -> efficiency 25 % Critical -> efficiency 20 %
Day 4 Easy -> efficiency 68 % Basic -> efficiency 60 % Semi critical -> efficiency 30 % Critical -> efficiency 20 %
Day 5 Easy -> efficiency 70 % Basic -> efficiency 60 % Semi critical -> efficiency 30 % Critical -> efficiency 25 %
Day 6 Easy -> efficiency 70 % Basic -> efficiency 60 % Semi critical -> efficiency 40 % Critical -> efficiency 25 %
Day 7 Easy -> efficiency 70 % Basic -> efficiency 65 % Semi critical -> efficiency 40 % Critical -> efficiency 35 %
Day 8 Easy -> efficiency 70 % Basic -> efficiency 65 % Semi critical -> efficiency 40 % Critical -> efficiency 35 %
Day 9 Easy -> efficiency 72 % Basic -> efficiency 65 % Semi critical -> efficiency 45 % Critical -> efficiency 40 %
Day 10 Easy -> efficiency 72 % Basic -> efficiency 65 % Semi critical -> efficiency 45 % Critical -> efficiency 40 %
Day 11 Easy -> efficiency 72 % Basic -> efficiency 65 % Semi critical -> efficiency 45 % Critical -> efficiency 45 %
Day 12 Easy -> efficiency 72 % Basic -> efficiency 68 % Semi critical -> efficiency 50 % Critical -> efficiency 45 %
Day 13 Easy -> efficiency 72 % Basic -> efficiency 68 % Semi critical -> efficiency 50 % Critical -> efficiency 45 %
Day 14 Easy -> efficiency 75 % Basic -> efficiency 68 % Semi critical -> efficiency 50 % Critical -> efficiency 45 %
Day 15 Easy -> efficiency 75 % Basic -> efficiency 68 % Semi critical -> efficiency 50 % Critical -> efficiency 45 %
Day 16 Easy -> efficiency 75 % Basic -> efficiency 68 % Semi critical -> efficiency 50 % Critical -> efficiency 45 %
Day 17 Easy -> efficiency 75 % Basic -> efficiency 70 % Semi critical -> efficiency 55 % Critical -> efficiency 45 %
Day 18 Easy -> efficiency 75 % Basic -> efficiency 70 % Semi critical -> efficiency 55 % Critical -> efficiency 45 %
Day 19 Easy -> efficiency 75 % Basic -> efficiency 70 % Semi critical -> efficiency 55 % Critical -> efficiency 50 %
Day 20 Easy -> efficiency 75 % Basic -> efficiency 70 % Semi critical -> efficiency 55 % Critical -> efficiency 50 %
Day 21 Easy -> efficiency 75 % Basic -> efficiency 70 % Semi critical -> efficiency 55 % Critical -> efficiency 50 %
Day 22 Easy -> efficiency 75 % Basic -> efficiency 72 % Semi critical -> efficiency 60 % Critical -> efficiency 50 %
Day 23 Easy -> efficiency 75 % Basic -> efficiency 72 % Semi critical -> efficiency 60 % Critical -> efficiency 50 %
Day 24 Easy -> efficiency 75 % Basic -> efficiency 72 % Semi critical -> efficiency 60 % Critical -> efficiency 50 %
Day 25 Easy -> efficiency 75 % Basic -> efficiency 72 % Semi critical -> efficiency 60 % Critical -> efficiency 50 %
Day 26 Easy -> efficiency 75 % Basic -> efficiency 72 % Semi critical -> efficiency 60 % Critical -> efficiency 50 %
Day 27 Easy -> efficiency 75 % Basic -> efficiency 72 % Semi critical -> efficiency 60 % Critical -> efficiency 50 %
Day 28 Easy -> efficiency 75 % Basic -> efficiency 72 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 29 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 30 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 31 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 32 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 33 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 34 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 35 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 36 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 37 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 38 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 39 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 40 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 41 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 42 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 43 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 44 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 45 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 46 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 47 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 48 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 49 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 50 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Day 51 Easy -> efficiency 78 % Basic -> efficiency 75 % Semi critical -> efficiency 65 % Critical -> efficiency 55 %
Sewing Productivity
Date:5/1/2022 MOMO FASHION LTD Factory: