Professional Documents
Culture Documents
Solved Problems
1. Given below are the cash flows of a project:
Solution:
(a) NPV @ 12%:
Year Cash Flow PVIF @ 12% Present Value
0 (100,000) 1.0000 (100,000)
1 20,000 0.8929 17,857
2 30,000 0.7972 23,916
3 40,000 0.7118 28,471
4 50,000 0.6355 31,776
5 30,000 0.5674 17,023
NPV @ 12% 19,043
(b) IRR:
In order to find the IRR, we need to find the discount rate at which the NPV at that rate is
zero. As the NPV @ 12% is positive, we need to increase the discounting rate, say to 19%.
NPV @ 19%:
Year Cash Flows PVIF @ 19% Present Value
0 (100,000) 1.0000 (100,000)
1 20,000 0.8403 16,807
2 30,000 0.7062 21,185
3 40,000 0.5934 23,737
4 50,000 0.4987 24,933
5 30,000 0.4190 12,571
NPV @ 19% (767)
At 18%, the NPV is positive, which means that the IRR falls between 18% and 19%. By
interpolation, we can find the IRR as follows:
18% +x
18% + (1743/(1743+767)
18% + (1743/2510)
18%+0.69% = 18.69%
The IRR is 18.69% which is greater than the hurdle rate (discount rate), hence we may
accept the project.
2. Premium Manufacturing Company is evaluating two forklift systems to use in its plant
that produces the towers for a windmill power farm. The costs and the cash flows
from these systems are as follows:
(Rs.)
Year 0 Year 1 Year 2 Year 3
Otis Forklifts −3,123,450 979,225 1,358,886 2,111,497
Craigmore Forklifts −4,137,410 875,236 1,765,225 2,865,110
If the company uses a 12 percent discount rate for all projects, determine which
forklift system should be purchased using the net present value (NPV) approach.
Compute the IRR for each of the two systems. Is the choice different from the one
determined by NPV?
Otis Forklifts:
As NPV (Otis) @ 12% Rs. 337,075 > 0, we need to use a higher discount rate to get NPV
= 0.
At r = 15%, the NPV (Otis) is as follows:
979,225 1,358,886 2,111,497
NPV= -3,123,450 + 1
+ 2
+
(1+0.15) (1.15) (1.15)3
= -3,123,450 + 851,500 + 1,027,513 + 1,388,344
= Rs.143,907/-
Craigmore Forklifts:
Similarly, we can find the IRR for Craigmore forklifts which is 13.06 %.
Based on the IRR, we would still pick Otis over Craigmore forklift systems.
(100.00 (100.00
0 (100) 1.0000 (100.00) 1.0000 ) 1.0000 )
50.00
40.00
30.00
20.00 Project A
NPV
10.00 Project B
0.00 Increment
-10.00
-20.00
-30.00
0% 10% 20%
Discount Rate
The company should accept Project A if its NPV is positive and higher than that of Project
B; that is, the company should accept Project A if the discount rate is greater than 10.7%
(the intersection of NPVA and NPVB on the graph below) and less than 13.1%.
The cash flows for Project B – Project A & NPV are as follows:
Project B - Project A:
IRRB-A = 10.7%
The company should accept Project A if the discount rate is greater than 10.7% and less
than 13.1%. As shown in the graph, for these discount rates, the IRR for the incremental
investment is less than the opportunity cost of capital.
Because the IRR for the incremental cash flows exceeds the cost of capital, the
additional investment in A is worthwhile.
250 300
NPVA = - 400+ + =Rs.81.86
1.09 (1.09)2
140 179
NPVB = -200+ + =Rs. 79.10
1.09 (1.09)2
5. Pipli Pharma has Rs. 1 million allocated for Capital expenditures. Which of the
following projects should the company accept to stay within the budget? How
much does the limit of budget cost the company in terms of its market value?
The opportunity cost of capital for each project is 11%.
(In Rs’000s)
Project Investment NPV IRR (%)
1 300 66 17.2
2 200 -4 10.7
3 250 43 16.6
4 100 14 12.1
5 100 7 11.8
6 350 63 18.0
7 400 48 13.5
Thus, given the budget of Rs. 1 million, the best the company can do is to accept
Projects 1, 3, 4, and 6.
If the company accepted all positive NPV projects, the market value (compared to
the market value under the budget limitation) would increase by the NPV of
Project 5 plus the NPV of Project 7: Rs. 7,000 + Rs. 48,000 = Rs. 55,000
Thus, the budget limit costs the company Rs. 55,000 in terms of its market value.
209794/(1+r*)^5 =
100000
1+ r* =
(209794/100000)^(1/5)
r* = 1.15973 - 1
r* = 0.15973 = 15.97%
*****
Dr Pankaj Varshney Page 7 of 7