You are on page 1of 5

(contactor's Logo)

(Project name) Sp(16)


R.F.I
TANT OFFICE - PROJECT MANAGER :

RE BY TO REQUEST INFORMATION CONCERNING THE FOLLOWING MATTER , PLEASE ADVICE US FOR :

DATE :
(Owner's Logo)

(clinet)

R.F.I
TO CONSULTANT OFFICE - PROJECT MANAGER :

WE ARE HERE BY TO REQUEST INFORMATION CONCERNING THE FOLLOWING MATTER , PLEASE ADVICE

CONTRACTOR PM :

COMMENTS :

CONSULTANT PM :
Submittal Ref.: HBZ1-QSS-AR-000
Project Name: Revision 00
Supervision Active Brains
Consultant: ABCG
Hacienda Bay Date 23/Dec/20
Phase/Package 1
Zone 1
United Engineering Attachments xx Pages
Contractor: for Construction Client: Palm Hills
Co. Size A3/A4
Soft Copy CD

Quantity Survey Submittal (QSS)


To: ABCG Contract no.: Contractor Project no.: HB00021
From: UECC Scope of Work: Consultant Project no.:

Discipline: Architectural Structural Electrical Mechanical Infra Survey Roads Other

Copy to: Employer - Palm Hills SD Ref.: - IR Ref.:-

Location: Villa / Chalet no. Spec. Ref.:-

Action
Item No. Description Document ref. Rev.
Code

Received by: Consultant's Stamp Approval Status:


Main Contractor
Authorized Representative Code A ( Work may proceed )

PM Name : Eng. Code B ( Approved As Noted work may proceed )

PM Signature : Code C ( Revise and Resubmit Work may not proceed )

Date : Code D ( For Information Only - Rejected )

Consultant Review Comments :

Consultant Received by: Contractor's Stamp Received by: Employer's Stamp


Authorized Representative

RE Name : Eng.

Signature :

Date :

Employer's Representative Comments (if Required): -

Employer Rep.
Authorized Representative
Legends:
AR = Architectural ST = Structural EL = Electrical ME = Mechanical IN = Infra SU = Survey
FF = Fire Fighting PL = Plumbing OT = Other drawings