You are on page 1of 1

LARSEN & TOUBRO LIMITED

CONSTRUCTION OF FOUR LANE BRIDGE FROM DHUBRI TO PHULBARI OVER


BRAHMAPUTRA RIVER
Format No.: L&T/DPBP/QF 07 Rev 1, Rev Date: 30.07.2021
Client : National Highways & Infrastructure Development Corporation Limited (NHIDCL)
Authority Engineer : AECOM Asia Company Limited In Association with PADECO Co.Ltd
EPC Contractor : Larsen & Toubro Ltd.

CONCRETE DELIVERY SHEET


TRANSIT MIXER DELIVERY CHALLAN
Plant Location Date
Transit Mixer No. Time of Despatch
Concrete Grade Location of Pour
Structure Details
Slump at batching plant Mix. Temperature at BP
Batch Start Time Batching Finish Time
Quantity (Cum) Cumulative Quantity (Cum)
Remarks:

FOR L&T FOR CLIENT/AE

LARSEN & TOUBRO LIMITED


CONSTRUCTION OF FOUR LANE BRIDGE FROM DHUBRI TO PHULBARI OVER
BRAHMAPUTRA RIVER
Format No.: L&T/DPBP/QF 07 Rev 1, Rev Date: 30.07.2021
Client : National Highways & Infrastructure Development Corporation Limited (NHIDCL)
Authority Engineer : AECOM Asia Company Limited In Association with PADECO Co.Ltd
EPC Contractor : Larsen & Toubro Ltd.

CONCRETE DELIVERY SHEET


TRANSIT MIXER DELIVERY CHALLAN
Plant Location Date
Transit Mixer No. Time of Despatch
Concrete Grade Location of Pour
Structure Details
Slump at batching plant Mix. Temperature at BP
Batch Start Time Batching Finish Time
Quantity (Cum) Cumulative Quantity (Cum)
Remarks: