Tampa Office Building - Updation 31-May-21 09:15 PM

Report of Updated Activities with Negative Total Float only

Activity ID Activity Title Original Duration Start Finish Total Float

1040 Foundation 15 08-May-21 08:00 AM A 31-May-21 07:00 PM -7


1050 Fill, compact and treat soil 3 01-Jun-21 08:00 AM 03-Jun-21 07:00 PM -7
1060 1st floor plumbing rough -in 3 04-Jun-21 08:00 AM 07-Jun-21 07:00 PM -7
1070 SOG 4 08-Jun-21 08:00 AM 11-Jun-21 07:00 PM -7
1090 1st floor external CMU walls 10 12-Jun-21 08:00 AM 23-Jun-21 07:00 PM -3
1100 1st floor internal CMU walls 14 12-Jun-21 08:00 AM 28-Jun-21 07:00 PM -7
1110 2nd floor suspended slab 10 29-Jun-21 08:00 AM 10-Jul-21 07:00 PM -7
1170 2nd floor external CMU walls 12 12-Jul-21 08:00 AM 24-Jul-21 07:00 PM -1
1180 2nd floor internal CMU walls 16 14-Jul-21 08:00 AM 31-Jul-21 07:00 PM -7
1190 Roof trusses 8 02-Aug-21 08:00 AM 10-Aug-21 07:00 PM -7
1230 Roof sheathing 5 11-Aug-21 08:00 AM 16-Aug-21 07:00 PM -7
1240 Roof felt 1 17-Aug-21 08:00 AM 17-Aug-21 07:00 PM -7
1250 Building dry-in 0 18-Aug-21 08:00 AM 18-Aug-21 08:00 AM -7
1280 Internal partition framing 12 18-Aug-21 08:00 AM 01-Sep-21 07:00 PM -7
1300 1st floor drywall 8 02-Sep-21 08:00 AM 10-Sep-21 07:00 PM -7
1380 2nd floor drywall 8 11-Sep-21 08:00 AM 21-Sep-21 07:00 PM -7
1400 2nd floor suspended ceiling 8 22-Sep-21 08:00 AM 30-Sep-21 07:00 PM -7
1410 2nd floor plumbing install fixtures 2 22-Sep-21 08:00 AM 23-Sep-21 07:00 PM -5
1420 2nd floor paint/wall covering 11 27-Sep-21 08:00 AM 09-Oct-21 07:00 PM -7
1430 2nd floor electrical finish 6 01-Oct-21 08:00 AM 08-Oct-21 07:00 PM -6
1450 2nd floor flooring 10 13-Oct-21 08:00 AM 23-Oct-21 07:00 PM -7
1500 Electric final 4 13-Oct-21 08:00 AM 16-Oct-21 07:00 PM -1
1510 Building clean up 2 25-Oct-21 08:00 AM 26-Oct-21 07:00 PM -7
1520 Final check/CO 1 27-Oct-21 08:00 AM 27-Oct-21 07:00 PM -7

Total 142 08-May-21 08:00 AM A 27-Oct-21 07:00 PM -7