LOADER PRODUCTION
STEP 1: BUCKET SIZE
Loaders can
usually be
equipped with
several different
size and type
buckets.

19SC703 Course material - Dr.K.B.Anand 4

2
4/29/2021

STEP 1: BUCKET SIZE

Buckets are rated in both Heaped


and Struck capacities.

Heaped Capacity is the


rating of interest for
Production Estimating.
19SC703 Course material - Dr.K.B.Anand 5

STEP 2: FILL FACTOR

Heaped Capacity is based on the


SAE standard of a 2:1 material
repose angle.
The Fill Factor adjusts Heaped
Capacity (in loose measure)
based on the type of material
being handled.
19SC703 Course material - Dr.K.B.Anand 6

3
4/29/2021

STEP 2: FILL FACTOR


The Fill Factors for wheel and
track loaders are different because
of differences in the breakout force
that can be developed.

19SC703 Course material - Dr.K.B.Anand 7

19SC703 Course material - Dr.K.B.Anand 8

4
4/29/2021

STEP 2: FILL FACTOR

HEAPED BUCKET CAPACITY


 FILL FACTOR
= VOLUME (lcy)

19SC703 Course material - Dr.K.B.Anand 9

LOADER CAPACITY

A loader must maneuver and travel


with the load
19SC703 Course material - Dr.K.B.Anand 10

5
4/29/2021

CHECK TIPPING
Wheel Loader OPERATING WEIGHT is limited
to 50% of full-turn static tipping load.

Track Loader
OPERATING WEIGHT
is limited to 35% of
static tipping load.
19SC703 Course material - Dr.K.B.Anand 11

CHECK TIPPING
WHEEL LOADER:
Volume X Material Unit Wt
< 0.50 Static Tipping Load full-turn

19SC703 Course material - Dr.K.B.Anand 12

6
4/29/2021

CHECK TIPPING
TRACK LOADER:
Volume X Material Unit Wt
< 0.35 Static Tipping Load

19SC703 Course material - Dr.K.B.Anand 13

STEP 3: CYCLE TIME

LOADER CYCLE TIME has three


components :
(1) Fixed Time to load,
Maneuver with four reversals of direction
(min. travel), and Dump.

(2) Travel Time


(3) Return Time

19SC703 Course material - Dr.K.B.Anand 14

7
4/29/2021

LOADER PRODUCTION

19SC703 Course material - Dr.K.B.Anand 15

STEP 3: FIXED CYCLE TIME


(1) Fixed Time
 Time to load
 Maneuver with four reversals of
direction (min. travel)
 Dump

19SC703 Course material - Dr.K.B.Anand 16

8
4/29/2021

LOADER PRODUCTION
Fixed time plus travel

19SC703 Course material - Dr.K.B.Anand 17

STEP 3: CYCLE TIME

(2) Travel Speed


(3) Return Speed
Check Manufactures’ data for
gear speeds.

19SC703 Course material - Dr.K.B.Anand 18

9
4/29/2021

STEP 3: CYCLE TIME

Travel Speed with a loaded


bucket - Average speed should
be about 80% of maximum in
low range.

19SC703 Course material - Dr.K.B.Anand 19

STEP 3: CYCLE TIME

Return Speed with an empty


bucket - Average speed should
be about 60% (upto 30m) or
80% (over 30m) of maximum
in intermediate range.

19SC703 Course material - Dr.K.B.Anand 20

10
4/29/2021

STEP 4: EFFICIENCY
FACTOR

When selecting a minutes per hour


efficiency factor visualize the work site
and consider:
• Materials being handled, bank or
broken
• Size of the loader’s dumping target,
(large or small)

19SC703 Course material - Dr.K.B.Anand 21

STEP 5: CLASS of
MATERIAL

The bucket load is in loose state.


It may be necessary to converted
to bank measure or tons.

19SC703 Course material - Dr.K.B.Anand 22

11
4/29/2021

STEP 6: PRODUCTION

Working mins / hr
Total cycle time (min)
X Heaped Capacity (lcy)
X Fill Factor
= Production (lcy/hr)
19SC703 Course material - Dr.K.B.Anand 23

Loader-backhoe / Backhoe-loader / Digger-loader

• Backhoe attachment and loader attachment


• Outriggers are provided for stability
• Bucket sizes are smaller
• Medium size unit (multipurpose equipment, not very expensive)
• Ideal for medium range contractors
• Escorts JCB made it popular in India

19SC703 Course material - Dr.K.B.Anand 24

12
4/29/2021

Wheel-type trenching machine

19SC703 Course material - Dr.K.B.Anand 25

Ladder-type trenching machine

19SC703 Course material - Dr.K.B.Anand 26