Planning for Earthwork

Construction

19SC703 Course material - 1


Dr.K.B.Anand

Planning for Earthwork


Construction

Every construction project is a


unique undertaking. Therefore,
planning is undertaken to
understand the problems and to
develop courses of action.
19SC703 Course material - 2
Dr.K.B.Anand
Planning Earthwork
Construction
• Review the Contract Documents
• Study the plans
• Plan the Work
• Perform quantity take-off
• Determine costs

19SC703 Course material - 3


Dr.K.B.Anand

Planning Earthwork
Construction
A site visit is strongly recommended
to relate the physical site
characteristics to the work details.

19SC703 Course material - 4


Dr.K.B.Anand
Planning Earthwork
Construction
After the site visit is completed, the
planner determines the quantity of
materials – either to furnish or move.
The takeoff or
"quantity survey."
19SC703 Course material - 5
Dr.K.B.Anand

Planning Earthwork
Construction
During the takeoff, the planner
must make decisions concerning:
– equipment needs
– sequence of operations
– and crew size
19SC703 Course material - 6
Dr.K.B.Anand
Graphical Presentation
of Earthwork
Three kinds of views are presented in
the contract documents to show
earthwork construction features:
– Plan view
– Profile view
– Cross section view
19SC703 Course material - 7
Dr.K.B.Anand

Plan View
The plan view is looking down on the
proposed work and presents the
horizontal alignment of features

19SC703 Course material - 8


Dr.K.B.Anand
Profile View
The profile view is a cut view typically
along the centerline of the work.
It presents
the vertical
alignment of
features.

19SC703 Course material - 9


Dr.K.B.Anand

Cross Section View


A view formed by a plane cutting the
work at a right angle to its long axis
– When the ground surface is regular,
sections are typically taken at every
full station (30m)
– When the ground is irregular,
sections must be taken at closer
intervals & at points of change
19SC703 Course material - 10
Dr.K.B.Anand
19SC703 Course material - 11
Dr.K.B.Anand

Earthwork Quantities
Earthwork computations involve:
• Calculation of earthwork
volumes
• Balancing of cuts and fills
• Planning of the most
economical material hauls.
19SC703 Course material - 12
Dr.K.B.Anand
Average End Area

19SC703 Course material - 13


Dr.K.B.Anand

Average End Area

19SC703 Course material - 14


Dr.K.B.Anand
Net Volume
• Bank cubic metres (bcm)
• Loose cubic metres (lcm)
• Compacted cubic metres (ccm)

bcm lcm
19SC703 Course material - ccm 15
Dr.K.B.Anand

Station End End Vol. of Vol. of


(m) area cut area fill cut (bcm) fill (bcm)
(m2) (m2)
100 0 73 -- --
130 60 0 900 1095
160 200 0 3900 0
190 299 0 7485 0
220 117 14 6240 210
250 9 73 1890 1305
280 0 341 135 6210
19SC703 Course material - 16
Dr.K.B.Anand
STRIPPING

For cut sections subtract the stripping.

19SC703 Course material - 17


Dr.K.B.Anand

STRIPPING
For fill sections the stripping is a cut
quantity; plus an equal amount must
be added to the embankment
quantity.

19SC703 Course material - 18


Dr.K.B.Anand
Earthwork Volume
Calculation Sheet

19SC703 Course material - 19


Dr.K.B.Anand

Mass Diagram
The mass diagram is an excellent
method of analyzing linear
earthmoving operations.
It is a graphical means for
measuring haul distance (stations)
in terms of earthwork volume
(cubic metres).
19SC703 Course material - 20
Dr.K.B.Anand
Mass Diagram
Aids in identifying:
• Where to utilize specific types
of equipment,
• Where quantities of material
are required,
• Average haul distance,
• Haul grades.
19SC703 Course material -
Dr.K.B.Anand
21

Earthwork Volume
Calculation Sheet

19SC703 Course material - 22


Dr.K.B.Anand
MASS DIAGRAM PLOTTING

1000 CONNECT THE


POINTS
500

- 500

- 1000

0 + 00 1 + 00 2 + 00 3 + 00 4 +00 5 + 00 6 + 00

19SC703 Course material - 23


Dr.K.B.Anand

MASS DIAGRAM
1000
Embankment requirements
500
exceeds excavation quantity.
0

-500

- 1000

Descending lines
0 + 00 1 + 00 2 + 00 3 + 00 4 +00 5 + 00 6 + 00

19SC703 Course material - 24


Dr.K.B.Anand
MASS DIAGRAM
1000

500 Ascending lines


0

-500

- 1000
Excavation exceeds embankment
requirements
0 + 00 1 + 00 2 + 00 3 + 00 4 +00 5 + 00 6 + 00

19SC703 Course material - 25


Dr.K.B.Anand

MASS DIAGRAM
1500 MASS DIAGRAM
1000

CUT FILL
500
V
O C
L C
U Y 0
M
E

-500 FILL CUT

-1000

1+00 2+00 3+00 4+00 5+00 6+00 7+00 8+00 9+


19SC703 Course material - 26
STATIONS
Dr.K.B.Anand
MASS DIAGRAM
1000

500

Zero balance line


0

-500

Excavation quantity equals


- 1000

0 + 00
embankment requirement.
1 + 00 2 + 00 3 + 00 4 +00 5 + 00 6 + 00

19SC703 Course material - 27


Dr.K.B.Anand

MASS DIAGRAM
Maximum and minimum points
 Maximum is where the cut
transitions into fill.
 Minimum is where the fill
transitions into cut.
19SC703 Course material - 28
Dr.K.B.Anand
MASS DIAGRAM
1000

Maximum and minimum points


500

-500

- 1000

Transition point
0 + 00 1 + 00 2 + 00 3 + 00 4 +00 5 + 00 6 + 00

19SC703 Course material - 29


Dr.K.B.Anand

MASS DIAGRAM
Final position
500 410 cm
waste
cm
0
0 1 2 3 4 5 6 7 90 cm
Stations borrow
Above the zero line indicates waste.
Below the zero line indicates borrow. 19SC703 Course material - 30
Dr.K.B.Anand
19SC703 Course material - 31
Dr.K.B.Anand

Economical Haul Distances


Machine type Economical
haul distance
Large dozers, Up to 100 m
pushing material
Push-loaded scrapers 100 to 1500 m
Trucks > than 1500 m

19SC703 Course material - 32


Dr.K.B.Anand
Mass Diagram With a Balance Line

19SC703 Course material - 33


Dr.K.B.Anand

Haul Distances

19SC703 Course material - 34


Dr.K.B.Anand
Haul Distances
Average haul = area / quantity (cy)

Haul No. 3 quantity -17,080


Haul No. 1 quantity?
19SC703 Course material - 35
Dr.K.B.Anand

Consolidated Average Hauls

Stations
Haul 1 11,459 bcy 3+51 40,221 sta-cy
Haul 2 5,590 bcy 3+35 18,727 sta-cy
Haul 3 17,080 bcy 12+51 213,654 sta-cy
34,129 bcy 272,602 sta-cy

272,602 sta-cy = 8.0 stations


34,129 bcy
19SC703 Course material - 36
Dr.K.B.Anand
Pricing Earthwork
Operations
The cost of earthwork operations
will vary with the kind of soil or
rock encountered and the methods
used to excavate, haul, and place
the material in its final deposition.

19SC703 Course material - 37


Dr.K.B.Anand

Spreading Dumped
Embankment
Material with a Dozer

19SC703 Course material - 38


Dr.K.B.Anand
Water Truck and Roller used to
Compaction Embankment
Material

19SC703 Course material - 39


Dr.K.B.Anand

Three-link Earthwork
System
Spread &
Excavate & load compact

Haul, dump, return


19SC703 Course material - 40