Professional Documents
Culture Documents
Document Holds
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 2 of 43
TABLE OF CONTENTS
1. INTRODUCTION ………………………………………………………………… 4
1.1. Overview …………………………………………………………………… 4
1.2. Scope ……………………………………………………………………… 5
1.3. References ………………………………………………………………… 5
1.4. Unit of Measurement …………………………………………………… 6
1.5. Quality of Materials ……………………………………………………… 6
2. DESIGN ANALYSIS …………………………………………………………… 7
2.1. Design Life ………………………………………………………………… 7
2.2. Design Criteria …………………………………………………………… 8
2.3. Structural Design ………………………………………………………… 8
3. TRACK PAVEMENT DESIGN CONCLUSION ……………………………… 9
Attachment A - Track Pavement Calculation with Subgrade CBR = 3 %
Attachment B - Track Pavement Calculation with Subgrade CBR = 6 %
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 3 of 43
1. INTRODUCTION
1.1. Overview
PT Chevron Pacific Indonesia is presently working on development phase for North
Corridor Project (NCP). The NCP is a project which has been established for the
purpose of improving safety, security and future operability & maintainability of
pipeline, powerline and communication infrastructure within the main shipping
corridors of Chevron’s Sumatra Operations. Figure-1 below shows the project
location.
Presently, COMPANY is utilizing two parallel main export pipelines 36” and 30”
diameter to transport Sumatra Light Crude (SLC) and Duri Crude (DC) from Duri to
Dumai respectively. SLC pipeline conveys SLC oil from Duri CPS to SLC tanks at
Dumai Tank Farm, and DC pipeline transports DC oil from Duri field to DC tanks at
Dumai Tank Farm. There is also SLC export pipeline (20” and 30” diameter) which
carries SLC oil from Bangko GS and other gathering stations to Dumai. All the above
pipelines are near to the end of their useful life.
COMPANY plans to replace the above pipelines with two new 24” pipelines (SLC and
DC) from Duri to Dumai via Batang, and another new 16” pipeline from Bangko GS to
Batang as shown in Figure-1. The 16” SLC pipeline from Bangko will be tied-in with
SLC pipeline from Duri CPS at Batang. The pipelines will be installed underground
with minimum 1.0 m depth and vary in different location. The approximate length is
63,400 m (Duri – Dumai) and 45,000 m (Bangko – Batang). Shipping line from Benar
GS will be replaced with a new 6” above ground pipeline (about 9,600 m) and will be
tied-in to the 16” SLC pipeline at Bangko Tie-in area.
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 4 of 43
COMPANY also plans to replace Duri – Dumai 44 kV transmission line with a new 44
kV line and to install new Duri Cogen – Bangko 115 kV transmission line, and to
install fiber optic cable too. The new 44 kV transmission line will be tied-in to new 115
kV / 44 kV Sub Station (S/S) at Batang and connect to the existing 44 kV Dumai S/S.
The new 115 kV transmission line will be connected to the existing Cogen S/S,
Sintong S/S, Bangko S/S and new Batang S/S. The unused facilities will be
demolished after new facilities put in service.
1.2. Scope
This document presents calculation of track pavement design for North Corridor
Project. The scope include: maintenance access track, public access track and track
crossing.
1.3. References
The subject facilities will be designed in accordance with, but not limited to the
following codes, standards and project document.
1) Chevron Engineering Standard for Specifications
a) AIP-GEN-CIV-SPC-TPE-00004-00 Project Addendum for SP-CI-
RL-002 Pavement
Specification.
2) International Codes and Standards
a) AASHTO Guide for Design of Pavement Structure, 1993.
3) Project Documents
a) AIP-NCP-CIV-BOD-TPE-00001-00 Civil and Structure Basis of
Design NCP.
4) Sukirman, Silvia, "Perencanaan Tebal Struktur Perkerasan Lentur", Nova,
2000.
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 5 of 43
1.5. Quality of Materials
1) Track Subgrade
a) Material
The subgrade material shall be free of organic or vegetation matter and
lumps or ball of clay. The subgrade surface shall be compacted to not
less than ninety percent (95 %) of maximum dry density modified proctor
test at optimum moisture content as determined by ASTM D1557.
b) Strength
Track subgrade can be of fill (embankment) or cut (excavation) material.
The strength of subgrade for the track design shall be expressed as CBR
value. The CBR value for fill material or excavated soil shall not be less
than six percent (6 %) when compacted to not less than ninety-five
percent (95 %) of maximum dry density modified proctor test.
c) Width
The track subgrade shall be extended on both sides of the track sub base
layer by a minimum of two hundred (200) mm.
d) There are two types of subgrade in this project, namely:
1) Subgrade type A
Subgrade which is built on top of peat soil. For this kind of
subgrade, it is assumed that the CBR is 3 %. This CBR value is
adopted to maximize the possibility of acceptance for existing
borrow pit soil in the remote area condition.
2) Subgrade type B
Subgrade which is non peat soil (usually the subgrade will not be
soaked, by the surrounding water because non peat soil is usually
at an elevation which is higher).
For this kind of subgrade, it is assumed that the CBR is 6 %. This
CBR value is adopted to maximize the possibility of acceptance for
existing ground surface soil.
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 6 of 43
b) Strength
Track sub base CBR value shall be not less than twenty percent (20 %)
when compacted to not less than ninety-five percent (95 %) of maximum
dry density modified proctor test at optimum moisture content as
determined by ASTM D1557. Loose lift thickness of fill material spread in
horizontal layers shall not be thicker than two hundred (200) mm for each
layer (for clayey soils). For sandy soils, the prescribed loose lift thickness
is between three hundred (300) to five hundred (500) mm for each layer.
2. DESIGN ANALYSIS
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 7 of 43
2.2. Design Criteria
According to Project Addendum for SP-CI-RL-002 Pavement Specification, access
track to minor operating/process facilities (pig launcher/receiver) and maintenance
access for pipe corridor, canal and power line use Class C road. Class C road is for
light traffic that has less than 200 ESAL/day.
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 8 of 43
3. TRACK PAVEMENT DESIGN CONCLUSION
Track pavement design for subgrade type A (minimum CBR = 3 %) is presented
below. Please refer to Attachment A for detailed calculation.
Figure 3.1 Design Sketch for Track Pavement with Subgrade CBR = 3 %
Figure 3.2 Design Sketch for Track Pavement with Subgrade CBR = 6 %
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 9 of 43
Attachment A - Track Pavement Calculation with Subgrade CBR = 3 %
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 10 of 43
1. DESIGN DATA
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 11 of 43
1.3. Assumed Design Traffic Data
= 73000 ESAL/year
Using traffic growth factor of two percent (2 %) per year (ref. 1a chapter 2.1.), equivalent
traffic load forecasting shall be:
Traffic load forecasting also can use table below (ref. 2a Appendix D page D-24):
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 12 of 43
Analysis Period Years (n) = 5
Traffic load during analysis period = Traffic Growth Factors * Equivalent Traffic Load
= 379600 ESAL
2. DESIGN VARIABLES
2.1. Traffic
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 13 of 43
b) DL, a lane distribution factor, expressed
as a ratio, that accounts for distribution of
traffic when two or more lanes are
available in one direction (ref. 2a).
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 14 of 43
2.2. Realiability
Functional classification for this track is local and rural condition exists.
Reliability level, according to table below (ref. 2a part II chapter 2 section 2.1.3
page II-9), track with local functional classification, recommend to use middle
value:
Reliability (R) = 75 %
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 15 of 43
2.3. Overall Standard Deviation
3. PERFORMANCE CRITERIA
3.1. Serviceability
The serviceability of a pavement is defined as its ability to serve the type of traffic which
use the facility. The primary measure of serviceability is the Present Serviceability Index
(PSI), which ranges from 0 (impossible road) to 5 (perfect road). The basic design
philosophy is the serviceability-performance concept, which provides a means of
designing a pavement based on a specific total traffic volume and a minimum level of
serviceability desired at the end of the performance period (ref. 2a).
The initial serviceability (pi) is an estimate by the user of what the PSI will be immediately
after construction (ref. 2a).
The terminal serviceability index (pt) is the lowest acceptable level before resurfacing or
reconstruction becomes necessary for the particular class of highway (ref. 2a).
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 16 of 43
Once pi and pt are established, the following equation should be applied to define the
total change in serviceability index (ref. 2a).
∆PSI = pi - pt (ref. 2a part II chapter 2
section 2.2.1 page II-10)
The equation is applicable to flexible, rigid, and aggregate-surfaced roads (ref. 2a).
∆PSI = 2.2
The definitive material property used to characterize roadbed soil for pavement design is
the resilient modulus (MR) (ref. 2a).
The resilient modulus is a measure of the elastic property of soil recognizing certain
nonlinear characteristics. The resilient modulus can be used directly for the design of
flexible pavements (ref. 2a).
Heukelom and Klomp have reported correlations between the Corps of Engineers CBR
value, using dynamic compaction, and the in situ modulus of soil. The correlation is given
by the following relationship (ref. 2a).
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 17 of 43
This relationship has been used extensively by design agencies and researchers an is
considered reasonable for finegrained soil with a soaked CBR of 10 or less (ref. 2a).
A method for estimating the AASHTO structural layer coefficients (ai values) required for
standard flexible pavement structural design shall be described. A value for this
coefficient is assigned to each layer material in the pavement structure on order to
convert actual layer thicknesses into structural number (SN). This layer coefficient
expresses the empirical relationship between SN and thickness and is a measure of the
relative ability of the material to function as as structural component of the pavement.
The following general equation for structural number reflects the relative impact of the
layer coefficients (ai) and thickness (Di) (ref. 2a).
SN =
1) Layer Design
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 18 of 43
2) Base Course
Hence using nomograph (ref. 2a) Figure 2.6 Variation in Granular Base Layer
Coefficient (a2) with CBR value, 25 %.
a2 = 0.083
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 19 of 43
3) Sub Base Course
Hence using nomograph (ref. 2a) Figure 2.7 Variation in Granular Sub Base Layer
Coefficient (a3) with CBR value, 20 %.
a3 = 0.094
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 20 of 43
5. PAVEMENT STRUCTURAL CHARACTERISTICS
5.1. Drainage
Level (or quality) of drainage is achieved under a specific set of drainage conditions. Below are
the general definitions corresponding to different drainage levels from the pavement structure
(ref. 2a).
For comparison purposes, the drainage conditions at the AASHO Road Test are considered to
be fair, i.e., free water was removed within 1 week (ref. 2a).
The treatment for the expected level of drainage for a flexible pavement is through the use of
modified layer coefficients (e.g., a higher effective layer coefficient would be used for improved
drainge conditions). The factor for modifying the layer coefficient is referred to as an mi value
and has been integrated into the structural number (SN) equation along with layer coefficient
(ai) and thickness (Di), thus
The possible effect of drainage on the asphalt concrete surface course is not considered (ref.
2a).
According to Table 2.4 (ref. 2a part I chapter 2 section 2.4 page II-25) the recommended mi
values as a function of the quality of drainage and the percent of time during the year the
pavement structure would normally be exposed to moisture levels approaching saturation.
It is important to note that these values apply only to the effects of drainage on untreated base
and su base layers. Although improved drainage is certainly beneficial to stabilized or treated
materials, the effects on performance of flexible pavements are not as profound as those
quantified in Table 2.4 (ref. 2a).
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 21 of 43
Assumed rain fall duration = 24 hours, base layer almost never in submerged condition (less
than 1 %).
Possibility, sub base layer in submerged condition, assumed rain fall duration = 24 hours.
For 1 week (168 hours): 24
* 100 % = 14%
168
Determined the design structural number (SN) required for specific condition using
nomograph or equation (ref. 2a part II chapter 3 section 3.1.1 page II-32):
log (w18) = ZR * So + (9,36 * log (SN+1)) - 0,2 + [ log (∆PSI/2,7) /
(0,4+1094/(SN+1)5,19) ] + (2,32 * log (MR)) - 8,07
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 22 of 43
Design structural number (SN) using nomograph below for
w18 = 379895 ESAL
R = 75 %
So = 0.49
MR = 4500 psi
ΔPSI = 2.2
Figure 6.1 Nomograph for SN
check :
log (W 18) = ZR * So + 9,36 * log (SN+1) - 0,2 + log (∆PSI/2,7) /
(0,4+1094/(SN+1)5,19) + 2,32 * log (MR) - 8,07
5.58 = 5.58 OK
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 23 of 43
6.2. Selection of Layer Thicknesses
The following equation provides the basis for converting SN into actual thickness of
surfacing, base and sub base:
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 24 of 43
SN2 = structural number for base layer
SN2 = 0.80 (determined the assumed design)
D*2 = actual structural number for base layer
SN3 = structural number for sub base layer (design structural number)
SN3 = 3.153
D*3 = actual structural number for sub base layer
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 25 of 43
Based on the calculation above, the adopted thickness are:
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 26 of 43
Attachment B - Track Pavement Calculation with Subgrade CBR = 6 %
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 27 of 43
1. DESIGN DATA
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 28 of 43
1.3. Assumed Design Traffic Data
= 73000 ESAL/year
Using traffic growth factor of two percent (2 %) per year (ref. 1a chapter 2.1.), equivalent
traffic load forecasting shall be:
Traffic load forecasting also can use table below (ref. 2a Appendix D page D-24):
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 29 of 43
Analysis Period Years (n) = 5
Traffic load during analysis period = Traffic Growth Factors * Equivalent Traffic Load
= 379600 ESAL
2. DESIGN VARIABLES
2.1. Traffic
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 30 of 43
b) DL, a lane distribution factor, expressed
as a ratio, that accounts for distribution of
traffic when two or more lanes are
available in one direction (ref. 2a).
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 31 of 43
2.2. Realiability
Functional classification for this track is local and rural condition exists.
Reliability level, according to table below (ref. 2a part II chapter 2 section 2.1.3
page II-9), track with local functional classification, recommend to use middle
value:
Reliability (R) = 75 %
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 32 of 43
2.3. Overall Standard Deviation
3. PERFORMANCE CRITERIA
3.1. Serviceability
The serviceability of a pavement is defined as its ability to serve the type of traffic which
use the facility. The primary measure of serviceability is the Present Serviceability Index
(PSI), which ranges from 0 (impossible road) to 5 (perfect road). The basic design
philosophy is the serviceability-performance concept, which provides a means of
designing a pavement based on a specific total traffic volume and a minimum level of
serviceability desired at the end of the performance period (ref. 2a).
The initial serviceability (pi) is an estimate by the user of what the PSI will be immediately
after construction (ref. 2a).
The terminal serviceability index (pt) is the lowest acceptable level before resurfacing or
reconstruction becomes necessary for the particular class of highway (ref. 2a).
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 33 of 43
Once pi and pt are established, the following equation should be applied to define the
total change in serviceability index (ref. 2a).
∆PSI = pi - pt (ref. 2a part II chapter 2
section 2.2.1 page II-10)
The equation is applicable to flexible, rigid, and aggregate-surfaced roads (ref. 2a).
∆PSI = 2.2
The definitive material property used to characterize roadbed soil for pavement design is
the resilient modulus (MR) (ref. 2a).
The resilient modulus is a measure of the elastic property of soil recognizing certain
nonlinear characteristics. The resilient modulus can be used directly for the design of
flexible pavements (ref. 2a).
Heukelom and Klomp have reported correlations between the Corps of Engineers CBR
value, using dynamic compaction, and the in situ modulus of soil. The correlation is given
by the following relationship (ref. 2a).
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 34 of 43
This relationship has been used extensively by design agencies and researchers an is
considered reasonable for finegrained soil with a soaked CBR of 10 or less (ref. 2a).
A method for estimating the AASHTO structural layer coefficients (ai values) required for
standard flexible pavement structural design shall be described. A value for this
coefficient is assigned to each layer material in the pavement structure on order to
convert actual layer thicknesses into structural number (SN). This layer coefficient
expresses the empirical relationship between SN and thickness and is a measure of the
relative ability of the material to function as as structural component of the pavement.
The following general equation for structural number reflects the relative impact of the
layer coefficients (ai) and thickness (Di) (ref. 2a).
SN =
1) Layer Design
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 35 of 43
2) Base Course
Hence using nomograph (ref. 2a) Figure 2.6 Variation in Granular Base Layer
Coefficient (a2) with CBR value, 25 %.
a2 = 0.083
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 36 of 43
3) Sub Base Course
Hence using nomograph (ref. 2a) Figure 2.7 Variation in Granular Sub Base Layer
Coefficient (a3) with CBR value, 20 %.
a3 = 0.094
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 37 of 43
5. PAVEMENT STRUCTURAL CHARACTERISTICS
5.1. Drainage
Level (or quality) of drainage is achieved under a specific set of drainage conditions. Below are
the general definitions corresponding to different drainage levels from the pavement structure
(ref. 2a).
For comparison purposes, the drainage conditions at the AASHO Road Test are considered to
be fair, i.e., free water was removed within 1 week (ref. 2a).
The treatment for the expected level of drainage for a flexible pavement is through the use of
modified layer coefficients (e.g., a higher effective layer coefficient would be used for improved
drainge conditions). The factor for modifying the layer coefficient is referred to as an mi value
and has been integrated into the structural number (SN) equation along with layer coefficient
(ai) and thickness (Di), thus
The possible effect of drainage on the asphalt concrete surface course is not considered (ref.
2a).
According to Table 2.4 (ref. 2a part I chapter 2 section 2.4 page II-25) the recommended mi
values as a function of the quality of drainage and the percent of time during the year the
pavement structure would normally be exposed to moisture levels approaching saturation.
It is important to note that these values apply only to the effects of drainage on untreated base
and su base layers. Although improved drainage is certainly beneficial to stabilized or treated
materials, the effects on performance of flexible pavements are not as profound as those
quantified in Table 2.4 (ref. 2a).
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 38 of 43
Assumed rain fall duration = 24 hours, base layer almost never in submerged condition (less
than 1 %).
Possibility, sub base layer in submerged condition, assumed rain fall duration = 24 hours.
For 1 week (168 hours): 24
* 100 % = 14%
168
Determined the design structural number (SN) required for specific condition using
nomograph or equation (ref. 2a part II chapter 3 section 3.1.1 page II-32):
log (w18) = ZR * So + (9,36 * log (SN+1)) - 0,2 + [ log (∆PSI/2,7) /
(0,4+1094/(SN+1)5,19) ] + (2,32 * log (MR)) - 8,07
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 39 of 43
Design structural number (SN) using nomograph below for
w18 = 379895 ESAL
R = 75 %
So = 0.49
MR = 9000 psi
ΔPSI = 2.2
Figure 6.1 Nomograph for SN
check :
log (W 18) = ZR * So + 9,36 * log (SN+1) - 0,2 + log (∆PSI/2,7) /
(0,4+1094/(SN+1)5,19) + 2,32 * log (MR) - 8,07
5.58 = 5.58 OK
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 40 of 43
6.2. Selection of Layer Thicknesses
The following equation provides the basis for converting SN into actual thickness of
surfacing, base and sub base:
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 41 of 43
SN2 = structural number for base layer
SN2 = 0.80 (determined the assumed design)
D*2 = actual structural number for base layer
SN3 = structural number for sub base layer (design structural number)
SN3 = 2.465
D*3 = actual structural number for sub base layer
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 42 of 43
Based on the calculation above, the adopted thickness are:
__________________________________________________________________________________________________
Track Pavement Design Calculation
AIP-NCP-CIV-CAL-TPE-00006-00 Page 43 of 43