Tampa Office Building - Change order Gantt chart showing activities organised by responsibility - ordered by TF 01-Jun-21 12:23 AM

Apr 25 May 02 May 09 May 16 May 23 May 30 Jun 06 Jun 13 Jun 20 Jun 27 Jul 04 Jul 11 Jul 18 Jul 25 Aug 01 Aug 08 Aug 15 Aug 22 Aug 29 Sep 05 Sep 12 Sep 19 Sep 26 Oct 03 Oct 10 Oct 17 Oct 24 Oct 31 Nov 07 Nov 14
S S T T F S S T T F S S T T FS S T T FS S T T FS S T T FS S T T F S S T T F S S T T F S S T T F S S T T F SS T T F SS T T F SS T T F S S T T FS S T T FS S T T FS S T T FS S T T F S S T T F S S T T F S S T T F S S T T F S S T T F S S T T F S S T T F S S T T FS S T T FS S T T FS S
20-Oct-21 07:00 PM, GC General contractor

NTP
Mobilization
Clear and Grub
Excavation
Foundation
Fill, compact and treat soil
SOG
2nd floor suspended slab
Building dry-in
Building clean up
Final check/CO
2nd floor columns
FRP vault walls
1st floor columns
01-Oct-21 07:00 PM,ACAL All season AC & heating
HVAC thermostat test
2nd floor HVAC air handler
HVAC : install equipment
1st floor HVAC air handler
2nd floor HVAC ductwork/rough-in
1st floor HVAC ductwork/rough-in
01-Oct-21 07:00 PM, WALL Wall to wall
1st floor drywall
2nd floor drywall
2nd floor suspended ceiling
2nd floor paint/wall covering
1st floor suspended ceiling
1st floor paint/wall covering
Stucco and paint to external walls
06-Sep-21 07:00 PM, WINT Windows & Doors NT
1st floor door and window frames
2nd floor door and window frames
1st floor : hang doors and windows
2nd floor : hang doors and windows
Vault door
25-Aug-21 07:00 PM, ROSS Ross carpentry & framing
Roof trusses
Roof sheathing
Internal partition framing
Roof insulation
Soffit and facia
17-Aug-21 07:00 PM, RABT Rabbit-the-Roofer
Roof felt
Roof shingles
07-Oct-21 07:00 PM, ZAPP ZAPP electric co.
2nd floor electrical finish
Electric final
1st floor electrical finish
1st floor electrical rough-in
2nd floor electrical rough-in
24-Jul-21 07:00 PM, MASE Mase and Company
1st floor internal CMU walls
2nd floor internal CMU walls
1st floor external CMU walls
2nd floor external CMU walls
18-Sep-21 07:00 PM, PLMX Plumbing expert
1st floor plumbing rough -in
2nd floor plumbing install fixtures
Plumbing finish
1st floor plumbing install fixtures
2nd floor plumbing rough-in
16-Oct-21 07:00 PM, TACO Tile & Carpet inc co
2nd floor flooring
1st floor flooring
07-Jul-21 07:00 PM, MART Master art landscape
Site work

Actual Work Critical Remaining Work Summary Page 1 of 1 TASK filter: All Activities