SIMPLEX INFRASTRUCTURES LIMITED

Brigade Metropolis Site, Bangalore


11-Jul-09

Rate Anlaysis for Grinding the concrete surface at FHC Duct for fixing of Door

Item :- Grinding the concrete surface(10mm thk, i.e. Modification of duct opening from standard size of 900mm width to as per
requirement of 910mm width) at FHC Ducts.

COST / 1 NO
SL.NO DESCRIPTION
DUCT

a Labour Charges

Labour charges for Grinding to required dimensions - 1 Skilled Labour / 2 No Ducts @ Rs 250 per 8 Hours 125.00 Rs

b Material Charges

Grinding Machine ( Including Spare Parts) @ Rs 1200 / 30 No Ducts 40.00 Rs

Grinding Wheel - 1No / 8 No Ducts @ Rs 620 /- inclusive of VAT @ 12.5% 77.50 Rs

c Electricity consumption @ 6.5 Units / 8 Hours @ Rs 10.5 / Unit 34.13 Rs

d TOTAL (Labour + Material + Electrical Charges) 276.63 Rs

e Add 15% for Overheads 41.49 Rs

f Total Cost for Grinding 1 No opening of FHC Duct ( d + e) 318.00 Rs