Professional Documents
Culture Documents
Bargarh, Odisha
TECHNICAL SPECIFICATIONS FOR CIVIL AND
STRUCTURAL WORKS
.
Doc No TCE.12282A-CV-3000-3001
TCE.12282A-CV-3000-3001
For
26-07-
R0 Client: BHARAT PETROLEUM
2021 CORPORATION LTD
REVISION HISTORY
CHANGE LIST
2.
3.
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE. 12282A-CV-
TECHNICAL SPECIFICATIONS FOR CIVIL AND
3000-3001 STRUCTURAL WORKS
SHEET 1 OF 1
TECHNICAL SPECIFICATIONS
TECHNICAL SPECIFIATIONS
SEC- SUB - SPECIFICATION NO OF
ISSUE TITLE
TION SECTION NUMBER SHEETS
TCE.12282A-CV-3000-
A A1 P0 SCOPE OF ENQUIRY 2
3001-01
B B1 TCE.12282A-CV-3000-
P0 PROJECT GENERAL INFORMATION 2
3001-02
D3 TCE.M4-418-03 R3 DEWATERING 2
D5 TCE.M4-403-01-1 R5 GROUTING 6
D
D6 TCE.M4-405-01 SUPPLY AND FABRICATION OF
R9 28
STRUCTURAL STEEL
TCE.12282A-CV-3000-
D9 P0 RAINWATER DRAINAGE 1
3001-04
1.0 INTRODUCTION
3.1 The scope of this enquiry shall comprise of but not limited to excavation and
backfilling, reinforced concrete works, steel structure and allied works for
plant / non-plant and allied buildings/ structures, drainage of plant building
and other areas, utilities and other buildings, equipment foundations, etc as
listed in below para including supplying, providing and furnishing of all
materials, equipment, plant, labour, transport, tools & tackles and all other
services necessary for the complete execution of works, including all
surveying and setting out necessary works.
3.2 The list of major buildings / facilities / structures covered under this enquiry
are listed below but not limited to:
2. Sheds
FILE NAME: TCE.12282A-CV-3000-3001-01
Proprietary Notice and Version Control
This document contains confidential information for use only by the “Client”; for the Project under consideration, which is provided for the sole purpose of permitting the recipient to evaluate the information
submitted herewith. In consideration of receipt of this document; unless agreed to in contrary in the Contract; the recipient agrees to maintain such information in confidence and to not reproduce or otherwise
disclose this information to any person outside the recipient’s organisation; except that there is no obligation to maintain the confidentiality of any information which was known to the recipient prior to receipt of ISSUE
such information from Tata Consulting Engineers Limited, or becomes publicly known through no fault of recipient, or Tata Consulting Engineers Limited, or is received without obligation of confidentiality from a
third party owing no obligation of confidentiality to Tata Consulting Engineers Limited. All information given under this version over rides all and any kind of offers, assumptions, deliverables and contracts P0
submitted verbally (and subsequently communicated in writing) or in writing or otherwise given under any and all previous version/s.
2.1 Milling
2.1.A Civil Works & Structural works
2.2 Raw Water Tank Shed
2.2.A Civil Works & Structural works
2.3 Fire Water Tank Shed
2.3.A Civil Works & Structural works
3.3 It is not the intent to specify completely herein all details of construction
activities. However, the work executed shall conform in all respects to high
standards of engineering design and workmanship and be capable of
performing in continuous commercial operation in a manner acceptable to the
ENGINEER/OWNER who will interpret the meaning of drawings and
specifications and shall have the power to reject any work or materials which
in his judgement are not in full accordance therewith.
6.1 Railway
The BIDDER shall indicate below all deviations from the Technical Specifications.
SL.
SECTION SPECIFICATION NO. PARA NO. DEVIATION
NO.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
The BIDDER hereby certifies that the above mentioned are the only deviations from the
PURCHASER’s/CONSULTANT’s Technical Specifications for this Enquiry Document. The
BIDDER further confirms that in the event any other data and information presented in the
BIDDER’s proposal and accompanying documents including drawings and catalogues etc. are
at variance with the specific requirements laid out in the PURCHASER’s/CONSULTANT’s
Technical Specifications, the latter shall govern and shall be binding on the BIDDER without any
price implication.
ISSUE
R8
The BIDDER shall indicate below the equipment and erection machinery he has in his
possession and proposes to bring to the site, in case the work is awarded to him.
SL.
TYPE AND DESCRIPTION OF THE EQUIPMENT NUMBER IN NUMBER
NO.
AND ERECTION MACHINERY POSSESSION PROPOSED
TO BRING TO
THE SITE
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
The BIDDER hereby confirms that the quantity and type of equipment and erection machinery
he will employ for the site work will not be less than those listed above. The BIDDER also
agrees to bring more equipment and erection machinery, if so warranted, in the opinion of the
PURCHASER/ CONSULTANT to meet the construction norms and construction schedule.
ISSUE
R5
1. SCOPE
1.1. The specification covers the general requirements and the specific technical
requirements for the works, which are not covered by any of the other
component specifications of Section D but are required to be carried out for
the satisfactory completion of the work. This specification and the other
component technical specifications contained in Section D are mutually
dependent and essential for correct interpretation of the contract. If the
requirements of this section and the other technical specifications in Section
D conflict, those of this section shall govern. Bidder shall bring out such
variations to Owner / Engineer-in-charge's notice for seeking clarifications. It
shall be noted that all Codes of Practice and Standards shall be those of
latest issue.
1.2. It shall be very clearly understood that the specifications given in Section D
are brief and do not cover minute details. However, all works shall have to be
carried out in accordance with the relevant standards and codes of practices
or in their absence in accordance with the best accepted current engineering
practices or as directed by Engineer from time to time. Items for which
separate specifications have not been indicated shall be carried out in
consultation with and as directed/approved by Engineer. The decision of
Engineer as regards the specification to be adopted and their interpretation
and the mode of execution of work shall be final and binding on Contractor
and no claim whatsoever shall be entertained on this account.
2. SUB-SOIL DATA
2.1. The Geotechnical Investigation report will be made available to the successful
bidder at the time of mobilisation by Owner. However, Bidder is advised to
visit the site and get acquainted with the site conditions such as type of soil
etc.
3. SITE GRADING
Earthwork in filling with borrow earth or excavated earth for site grading over
areas, banking excavated earth in layers not exceeding 150 mm in depth to
lines, levels and profiles indicated by Engineer and compacting including all
leads and lifts and spreading to level, rolling at OMC using vibratory power
roller of 8-10 tonne static weight to achieve not less than 95% Modified
Proctor Density including dressing up the peripheral embankments of the area
to be filled up, lead up to 1 KM, in all types of soil except soft/decomposed
and hard rock for all lifts or depths up to 1 m above or below the average
ground level (The average ground level shall be fixed by Engineer prior to
start of work).
4. EXCAVATION
4.1. Excavation for foundations, substructures, trenches, sumps, tunnels, pits etc.
in all types of ordinary and hard soils including all types of murum, with
necessary shoring, strutting, stacking selected material for backfilling or
FILE NAME: TCE.12282A-CV-3000-3001-03
Proprietary Notice and Version Control
This document contains confidential information for use only by the “Client”; for the Project under consideration, which is provided for the sole purpose of permitting the recipient to evaluate the information
submitted herewith. In consideration of receipt of this document; unless agreed to in contrary in the Contract; the recipient agrees to maintain such information in confidence and to not reproduce or
otherwise disclose this information to any person outside the recipient’s organisation; except that there is no obligation to maintain the confidentiality of any information which was known to the recipient prior
ISSUE
to receipt of such information from Tata Consulting Engineers Limited, or becomes publicly known through no fault of recipient, or Tata Consulting Engineers Limited, or is received without obligation of
confidentiality from a third party owing no obligation of confidentiality to Tata Consulting Engineers Limited. All information given under this version over rides all and any kind of offers, assumptions,
P0
deliverables and contracts submitted verbally (and subsequently communicated in writing) or in writing or otherwise given under any and all previous version/s.
disposing excess excavated material anywhere in the plot area, for following
depths measured from the average ground level including dewatering etc
complete. (Excavation / removal of rubble fill shall be paid under this item)
(The average ground level shall be fixed by Engineer prior to start of work)
5. CONCRETE
5.2. Contractor shall make temporary arrangement for storage of the Cement at
his own cost. The location for this storage shall be as directed by
Engineer/Owner.
5.3. The structural grade of concrete shall be of minimum M25 Grade having
minimum cement content as per IS:456-2000 shall be used using 20mm
and downsize graded crushed stone aggregate with maximum water
cement ratio of 0.5. Water-reducing admixtures conforming to IS 9103
(Latest Edition) shall be used for all structures.
5.4. RCC to be used for grade slab inside enclosed buildings, paving area &
drainages shall be of grade M25.
5.5. Unless otherwise specified minimum grade of RCC to be used for Liquid
retaining structures and its foundations shall be M30 confirming to IS:456 shall
be used using 20mm and downsize graded crushed stone aggregate.
5.6. Unless otherwise specified 75mm thick PCC 1:2:4 of M7.5 grade by weight using
20mm and downsize graded crushed stone aggregate shall be provided under all
RCC foundations. The PCC concrete shall extend 75mm beyond foundations.
5.7. Unless otherwise specified plum concrete of grade M5 using 40mm and
downsize grade crushed stone aggregate shall be used as filler material wherever
loose subgrade exists by removing the loose soil/fill
5.8. Design mix for grade M7.5, M20, M25 & M30 shall be prepared by the
contractor in the beginning of the civil construction work at site. The design mix
shall be prepared for each grade with and without admixtures. Moreover, the
fresh design mix shall also be prepared at every change of sources of sand,
aggregates and cement.
5.9. Contractor shall take special care for concrete for liquid retaining structures,
underground structures and those others specifically called for to guarantee
the finish and water tightness. All such structures shall be hydro-tested.
Contractor shall include in his price hydro-testing of structure including all
arrangements for testing such as temporary bulk heads, pressure gauges,
pumps, pipe lines, etc. Any temporary arrangements that may have to be
made to ensure stability of the structure shall also be considered by the
bidder in his price while quoting the rates. Any leakage that may occur during
the hydro-test or subsequently during the defects liability period or the period
for which the structure is guaranteed shall be effectively stopped either by
cement/epoxy pressure grouting, geniting or such other method as may be
approved by Engineer. All such rectification shall be done by Contractor to the
entire satisfaction of Owner/Engineer at no extra cost to Owner.
5.10. Contractor shall design the mix for concrete for all the types of grades
required for civil works, with and without admixtures. The concrete mix
design report shall be got approved from the Engineer-in-charge / Owner,
prior to start of the work.
5.11. The contractor shall install and deploy the batching plant of adequate
capacity. Adequate nos. of diesel operated concrete pumps and adequate
numbers of transit mixers shall be deployed by the contractor at site.
5.12. Adequate arrangements shall be made to make the area clear from boring
muck / slushy / surplus earth.
5.13. All R.C.C. of designed grade shall be provided at all heights and levels on
well compacted / sound surfaces including dewatering, shuttering, vibrating,
curing and finishing as required. Integral water-proofing compound shall be
added @ 2% by weight of cement in the wet concrete for the specified area in
the drawings.
5.14. Concrete in contact with earth shall be given two coats of bituminous paint.
6. REINFORCEMENT
6.2. Contractor shall prepare detail bar bending schedule based on design
drawings furnished by Engineer.
7.2. Plates shall be E250 grade, Quality A/BR, killed, tested for impact resistance
and confirming to IS 2062 unless noted. Plates beyond 12mm and up to
40mm thickness shall be controlled rolling. Plates beyond 40mm thickness
FILE NAME: TCE.12282A-CV-3000-3001-03
Proprietary Notice and Version Control
This document contains confidential information for use only by the “Client”; for the Project under consideration, which is provided for the sole purpose of permitting the recipient to evaluate the information
submitted herewith. In consideration of receipt of this document; unless agreed to in contrary in the Contract; the recipient agrees to maintain such information in confidence and to not reproduce or
otherwise disclose this information to any person outside the recipient’s organisation; except that there is no obligation to maintain the confidentiality of any information which was known to the recipient prior
ISSUE
to receipt of such information from Tata Consulting Engineers Limited, or becomes publicly known through no fault of recipient, or Tata Consulting Engineers Limited, or is received without obligation of
confidentiality from a third party owing no obligation of confidentiality to Tata Consulting Engineers Limited. All information given under this version over rides all and any kind of offers, assumptions,
P0
deliverables and contracts submitted verbally (and subsequently communicated in writing) or in writing or otherwise given under any and all previous version/s.
7.3. Anchor Bolts shall be turned from M.S. rounds conforming to IS 2062 Grade-
A (Class-4.6).
7.5. Threading shall be coarse conforming to IS 1367 and IS 4218.f Sleeve shall
be M.S Tubes (Medium) as per IS 1239.
7.9. Mass of hot dipped galvanised grating should be min. 610gm/m2 conforming
to IS code 4759.
8.1. Concrete surfaces shall not be plastered unless otherwise shown on the
drawings or directed by Engineer. The concrete surfaces above ground shall
be of high-quality stain free, smooth and even with no shutter marks.
Approved shutter/mould release agents shall be used. However, Engineer's
approval shall not relieve Contractor of his contractual obligations and his
responsibilities for ensuring and providing the finish specified or removing/
rectifying defective work.
8.2. The grade slab in all buildings shall have even surface with all necessary
levelling. The concrete shall be finished with vacuum dewatering and
mechanical trowelling to render even surface.
8.3. Form-work (Straight or Curved) for concrete items shall include forming
chamfers, drip moulds, pockets, scaffolding, centring, finishing concrete
surface after striking the form-work etc.
8.4. Tubular staging (ACROW or equivalent) is to be used for all structural / RCC
work for all floors at all levels and heights. Aluminium / Wooden / Steel forms
shuttering shall be used for all surfaces. For beam sides, wooden shuttering
may be used. The rate quoted for formwork and shuttering shall remain
applicable irrespective of the material used. Contractor can use any material
to expedite the work. No extra cost will be paid.
8.5. Mould release agents shall be used for all shuttering. Approval of make/brand
of mould release agents shall be obtained from Engineer prior to use in
works.
9.1. Material for the finish layer of ring wall tank shall normally be hot bitumen -
sand mix in the following proportions by weight:
Above mixture shall have a good stability and a rational flow of bitumen
adopting the qualification of the layer to the profile of the tank (bottom). Low
percentage of voids in the mixture, after rolling, to be left and an adequate
guarantee on water tightness is provided.
10.1. Water-proofing treatment to RCC terrace slab shall be done applying two
coats of POLYALK WP of M/s Sunanda Specialty Coatings Pvt. Ltd. or
equivalent and cement in proportion as recommended by manufacturer. The
procedure for surface preparation and final application shall be as
recommended by manufacturer.
10.2. Brick bat Coba in cement mortar 1:3 shall be provided to proper level and
slope having average thick of 115 mm. Curing shall be done with filling of
water for 48 hrs. The top surface shall be finished with IPS flooring including
making rounding at corners and at the junction of wall and floor. Final
inspection shall be carried out to ensure that there are no damp patches,
leakages, seepages etc at lower slab. If any type of leakages, seepages,
damp patches are found, same shall be repaired to Owner / Engineer-in-
charge’s satisfaction at contractor’s own cost.
10.3. The waterproofing treatment is to be guaranteed for bone dry condition for a
period of 10 years.
11.2. The 4½” thick soaked brick bat coba shall be provided in C:M 1:3 to proper
level and slope. Curing shall be done by filling water for 48 hrs. Concrete
screed shall be laid over a brick bats with 10mm downgraded aggregates by
adding proportionate dosage “SUNPLEX” of M/s Sunanda Specialty Coatings
Pvt. Ltd. or equivalent as recommended by manufacturer. Surface shall be
kept rough for further tiling work. Curing shall be done for minimum 7 days by
filling water. Final inspection shall be carried out to ensure that there are no
damp patches, leakages, seepages etc. If any type of leakages, seepages
damp patches are found, same shall be repaired to Owner / Engineer-in-
charge’s satisfaction at contractor’s own cost.
11.3. The waterproofing treatment is to be guaranteed for bone dry condition for a
period of 10 years.
12.3. The waterproofing treatment is to be guaranteed for bone dry condition for a
period of 10 years.
13.3. Waterproofing of walls shall be done only after hydro testing of Vaults is
completed.
13.4. A working space of about 600 mm shall have to be provided in the excavation
separately for treatment of exterior faces of walls.
13.5. The waterproofing treatment is to be guaranteed for bone dry condition for a
period of 10 years.
14.1. Hydro-static test for water tightness shall be done at full storage level as
described below:
14.1.1. In case of structures whose external faces are exposed, such as water tanks,
the requirements of the test shall be deemed to be satisfied if the external
faces show no sign of leakage or sweating and remain completely dry during
the period of observation of seven days after allowing a seven (07) days
period for absorption after filling with water.
14.1.2. In the case of structures whose external faces are submerged and are not
accessible for inspection, such as underground tanks, the structures shall be
filled with water for seven (07) days. After the expiry of seven days, the level
of the surface of the water shall be recorded. The level of water shall be
recorded again at subsequent intervals of 24 hours over a period of seven
days. Backfilling shall be withheld till the tanks are tested. The total drop in
surface level over a period of seven days shall be taken as an indication of
the water tightness of the structure. Engineer shall decide on the actual
permissible nature of this drop in the surface level, taking into account
whether the structures are open or closed and the corresponding effect it has
on evaporation losses. Unless specified otherwise, a structure whose top is
covered shall be deemed to be water tight if the total drop in the surface level
over a period of seven days does not exceed 40 mm.
FILE NAME: TCE.12282A-CV-3000-3001-03
Proprietary Notice and Version Control
This document contains confidential information for use only by the “Client”; for the Project under consideration, which is provided for the sole purpose of permitting the recipient to evaluate the information
submitted herewith. In consideration of receipt of this document; unless agreed to in contrary in the Contract; the recipient agrees to maintain such information in confidence and to not reproduce or
otherwise disclose this information to any person outside the recipient’s organisation; except that there is no obligation to maintain the confidentiality of any information which was known to the recipient prior
ISSUE
to receipt of such information from Tata Consulting Engineers Limited, or becomes publicly known through no fault of recipient, or Tata Consulting Engineers Limited, or is received without obligation of
confidentiality from a third party owing no obligation of confidentiality to Tata Consulting Engineers Limited. All information given under this version over rides all and any kind of offers, assumptions,
P0
deliverables and contracts submitted verbally (and subsequently communicated in writing) or in writing or otherwise given under any and all previous version/s.
15.1. All chajjas, slab and sill projections shall be provided with drip mould and/or
throating.
16.1. All the expansion joints (except joints in concrete paving) shall be filled
"Shalitex" board of required thickness as per the drawings including sealing
with Two part pour grade type Poly-sulphide based sealant as per BS : 254
("PIDISEAL PS-42P" of Pidilite or approved equivalent) shall be used in
expansion joints or at places as indicated in drawings or as specified the
Engineer-in-charge including surface preparation, primer, masking tapes,
backer rod of polyethylene foam etc., as per manufacturer's specifications.
16.3. Sealant to be used in floor cracks etc. shall be "Sunexpoxy 358" of Sunanda
Speciality Coatings Pvt. Ltd. Or Ciba-Geigy Araldite GY257 with hardener
HY840 or equivalent. The application shall be as per manufacturer's
specifications and as directed by Engineer in places specified or as shown
on the drawings or as directed on the site.
17. PLUMBING
17.2. Based on design drawings indicating locations of floor drains, traps, sanitary
and water supply fixtures, Contractor shall prepare detailed working drawings
indicating the position of fittings, valves joints, supports, connection to main
lines, manholes, inspection chambers, sumps, septic tanks, etc. These
drawings shall be made by a licensed plumber in Contractor's employment or
otherwise and duly signed by him. The correctness of the drawings shall be
the responsibility of Contractor. No work shall be commenced unless the
drawings are approved by Engineer and / or statutory authorities.
18. FLOORING
18.1. Laying of tiles shall start from the centre of the room and proceed towards the
ends. Equal sizes of cut tiles shall be provided near the walls of each room.
Tiles shall be sorted before laying so that each area / room has only one
shade.
18.2. Kota stone tiles shall conform to IS:3622 - Specification for sand stone (slabs
and tiles).
19.1. Grading in the vicinity of excavation shall be such as to exclude rain / surface-
water draining into excavated areas. Excavation shall be kept clean of rain
and such water as the Contractor may be using for his work by suitably
pumping out the same at no extra cost to the owner. The scheme for pumping
and discharge of such water shall be approved by the Engineer.
19.2. Contractor shall ensure that the surface runoff outside the excavated pit
/working area shall be collected through a catch water drain excavated
around the working area and led away to a natural stream, at no extra cost to
the owner. Contractor shall maintain the catch water drains in proper
condition during the construction period at no extra cost to the owner.
19.3. The contractor shall be entirely responsible for the provision and the
maintenance of efficient drainage arrangements in the work site to lead off
all water whatever pumped from the excavation or on account of rains,
springs or any other source whatsoever. Flooding or ponding of water in
the work site shall not be permitted under any circumstances whatsoever and
the contractor shall take all precautions to prevent the same by
providing suitable pump and other dewatering arrangements. The cost
of repairing damages, if any to the work under execution or to any
Government property in and around the site shall be entirely borne by the
contractor, when such damages are due to his non-compliance with the above
conditions.
1.0 SCOPE
This specification covers the general requirements of earthwork in excavation for
different types of soil, site grading, filling in areas as shown in drawing, backfilling
around foundations and in plinths, conveyance and disposal of surplus soils or
stacking them properly as shown in the drawings and as directed by the ENGINEER
and all operations covered within the intent and purpose of this specification.
2.0 APPLICABLE CODES
The following Indian Standard Codes, unless otherwise specified herein, shall be
applicable. In all cases, the latest revision of the codes shall be referred to.
1. IS 456: 2000 - Code of practice for plain and reinforced
(Reaffirmed 2016) concrete.
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information.
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information.
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information.
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information.
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information.
sand under the basement floor. The water table shall not be allowed to rise above
base of raft level until completion of outer retaining walls including water proofing of
vertical surface of walls and back filling along the walls upto ground level and until
the structure attains such height to counter balance the uplift pressure. The
CONTRACTOR should inspect the site and make his own assessment about sub-
soil water level likely to be encountered at the time of execution and quote his rates
accordingly. Rate of all items are inclusive of pumping out or bailing out water, if
required. Nothing extra on this account whatsoever shall be paid to him. Only when
dewatering is performed by well point dewatering as agreed and approved by
Engineer, the work shall be considered extra and be treated as additional item to be
settled commercially. The CONTRACTOR shall obtain the ENGINEER’s approval
on the sequence of construction.
The CONTRACTOR shall take all necessary measures for the safety of traffic during
construction and provide, erect and maintain such barricades including signs,
markings, flags, lights and flagman, as necessary at either end of the excavation/
embankment and at such intermediate points as directed by the ENGINEER for the
proper identification of construction area. He shall be responsible for all damages
and accidents caused due to negligence on his part.
11.0 EXCAVATION IN HARD ROCK
11.1 GENERAL REQUIREMENTS
Unless otherwise stated herein, IS specification “IS: 4081 - Safety Code for Blasting
and related Drilling Operations” shall be followed. After removal of overburden, if
any, excavation shall be continued in rock to such widths, lengths, depths, and
profiles as are shown in the drawings or such other lines and grades as may be
specified by ENGINEER. As far as possible, all blasting shall be completed prior to
commencement of construction. At all stages of excavation, precautions shall be
taken to preserve the rock below and beyond the lines specified for the excavation,
in the soundest possible condition. The quantity and strength of explosives used
shall be such that it will neither damage nor crack the rock outside the limits of
excavation. All precautions, as directed by ENGINEER, shall be taken during the
blasting operations and care shall be taken that no damage is caused to adjoining
buildings or structures due to blasting operations. In case of damage to permanent
or temporary structures, CONTRACTOR shall repair the same to the satisfaction of
ENGINEER at his cost. As excavation approaches its final lines and levels, the depth
of the charge holes and amount of explosives used shall be progressively and
suitably reduced.
Specific permission of ENGINEER will have to be taken by CONTRACTOR for
blasting rock and he shall also obtain a valid Blasting License from the authorities
concerned. If permission for blasting is refused by ENGINEER, the rock shall be
removed by wedging, pick, barring, heating and quenching or other approved
means. All loose or loosened rock in the sides shall be removed by barring, wedging,
etc. The unit rates for excavation in hard rock shall include the cost of all these
operations.
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information.
CONTRACTOR shall obtain necessary license for storage of explosives, fuses and
detonators issued to him from OWNER’s stores or from supplier arranged by him,
from the authorities dealing with explosives. The fees, if any, required for obtaining
such license, shall be borne by CONTRACTOR. CONTRACTOR shall have to make
necessary storage facilities for the explosives, etc. as per rules of local, State and
Central Government authorities and statutory bodies/ regulations. Explosives shall
be kept dry and shall neither be exposed to direct rays of sun nor be stored in the
vicinity of fire, stoves, steam pipes or heated metal, etc. No explosives shall be
brought near the work in excess of the quantity actually required for a particular
amount of firing to be done; and the surplus left after filling the holes shall be
removed to the magazine. The magazine shall be built, as far as possible, from the
area to be blasted. ENGINEER’s prior approval shall be taken for the location
proposed for the magazine.
In no case shall blasting be allowed closer than 30 metres from any structure or at
locations where concrete has just been placed. In the latter case, the concrete must
be at least 7 days old.
11.2 SPECIFIC REQUIREMENTS
For blasting operations, the following points shall be observed.
CONTRACTOR shall employ a competent and experienced supervisor and licensed
blaster in-charge of each set of operation. These persons shall be held personally
responsible to ensure that all safety regulations are carried out.
Before any blasting is carried out, CONTRACTOR shall intimate ENGINEER and
obtain his approval in writing for resorting to such operations. He shall intimate the
hours of firing charges, the nature of explosive to be used and the precautions taken
for ensuring safety.
CONTRACTOR shall ensure that all workmen and the personnel at site are excluded
from an area within 200 m radius from the firing point, at least 5 minutes before firing
time by sounding warning whistle. The area shall also be given a warning by
sounding a distinguishing whistle.
The blasting of rock near any existing buildings, equipment or any other property
shall be done under cover and CONTRACTOR has to make all such necessary
muffling arrangements. Covering may preferably be done with small charges only
and where directed by ENGINEER, a trench shall have to be cut by chiselling prior
to the blasting operation, separating the area under blasting from the existing
structures.
The firing shall be supervised by a Supervisor and not more than 6 (six) holes at a
time shall be set off successively. If the blasts do not tally with the number fired, the
misfired holes shall be carefully located after half an hour and when located, shall
be exploded by drilling a fresh hole along the misfired hole (but not nearer than 600
mm from it) and by exploding a new charge.
A wooden tamping rod with a flat end shall be used to push cartridges home and
metal rod or hammer shall not be permitted. The charges shall be placed firmly into
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information.
place and not rammed or pounded. After a hole is filled to the required depth, the
balance of the hole shall be filled with stemming which may consist of sand or stone
dust or similar inert material.
CONTRACTOR shall preferably detonate the explosives electrically.
The explosives shall be exploded by means of a primer, which shall be fired by
detonating a Fuse Instantaneous Detonator (FID) or other approved cables. The
detonators with FID shall be connected by special nippers.
In dry weather and normal dry excavation, ordinary low explosive gunpowder may
be used. In damp rock, high explosive like gelatine with detonator and fuse wire may
be used. Underwater or for excavation in rock with substantial accumulated seepage
electric detonation shall be used.
Holes for charging explosives shall be drilled with pneumatic drills, the drilling pattern
being so planned that rock pieces after blasting will be suitable for handling without
secondary blasting.
When excavation has almost reached the desired level, hand trimming shall have to
be done for dressing the surface to the desired level. Any rock excavation beyond
an over-break limit of 75 mm shall be filled up as instructed by ENGINEER, with
concrete of strength not less than M10. The cost of filling such excess depth shall
be borne by CONTRACTOR and the excavation carried out beyond the limit
specified above will not be paid for. Stopping in rock excavation shall be done by
hand trimming.
CONTRACTOR shall be responsible for any accident to workmen, public or
OWNER’s property due to blasting operations. CONTRACTOR shall also be
responsible for strict observance of rules, laid by Inspector of explosives, or any
other Authority duly constituted under the State and/ or Union Government.
12.0 FILL, BACK FILLING AND SITE GRADING
12.1 GENERAL
All fill material will be subject to the ENGINEER's approval. If any material is rejected
by the ENGINEER, the CONTRACTOR shall remove the same forthwith from the
site at no extra cost to the OWNER. Surplus fill material shall be deposited/ disposed
of as directed by the ENGINEER after the fill work is completed.
No earthfill shall commence until surface water discharges and streams have been
properly intercepted or otherwise dealt with as directed by the ENGINEER.
In case of terrace grading, proper slope protection as specified in the drawing or as
approved by the ENGINEER to be ensured at the places of grade level change.
12.2 MATERIAL
To the extent available, selected surplus soils from excavated materials shall be
used as backfill. Fill material shall be free from clods, salts, sulphates, organic or
other foreign material. All clods of earth shall be broken or removed. Where
excavated material is mostly rock, the boulders shall be broken into pieces not larger
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information.
than 150 mm size, mixed with properly graded fine material consisting of murrum or
earth to fill up the voids and the mixture used for filling.
If any selected fill material is required to be borrowed, the CONTRACTOR shall
make arrangements for bringing such material from outside borrow pits. The material
and source shall be subject to prior approval of the ENGINEER. The approved
borrow pit area shall be cleared of all bushes, roots of trees, plants, rubbish, etc. Top
soil containing salts/ sulphates and other foreign material shall be removed. The
materials so removed shall be burnt or disposed off as directed by the ENGINEER.
The CONTRACTOR shall make necessary access road to the borrow areas and
maintain the same, if such access road does not exist, at his cost.
Filling with excavated earth shall be done in regular horizontal layers each not
exceeding 30 cm in depth. All lumps and clods exceeding 80mm in any direction
shall be broken. Each layer shall be watered and consolidated with steel rammer or
half (½) tonne roller. Where specified, every third and top most layer shall also be
consolidated with power roller of minimum 8 tonnes. Wherever depth of filling
exceeds 1.5 metres, vibratory power roller shall be used to consolidate the filling
unless otherwise directed by ENGINEER. The CONTRACTOR shall make good all
subsidence and shrinkage in earth fillings, embankments, traverses, etc. during
execution and till the completion of work unless otherwise specified. Field density
measurements shall be carried out one in each layer.
Any damage to the existing facilities in the site which is not intended as per Drawing,
nor instructed by the Engineer or Owner but is solely due to improper execution of
filling work, shall be restored and made good by the CONTRACTOR as was before
the excavation work started. The cost of such work shall be borne by
CONTRACTOR.
12.3 FILLING IN PITS AND TRENCHES AROUND FOUNDATIONS OF STRUCTURES,
WALLS, ETC.
As soon as the work in foundations has been accepted and measured, the spaces
around the foundations, structures, pits, trenches, etc. shall be cleared of all debris,
and filled with earth in layers not exceeding 150 mm, each layer being watered,
rammed and properly consolidated, before the succeeding one is laid. Each layer
shall be consolidated to the satisfaction of the ENGINEER. Earth shall be rammed
with approved mechanical compaction machines. Usually no manual compaction
shall be allowed unless the ENGINEER is satisfied that in some cases manual
compaction by tampers cannot be avoided. The final backfill surface shall be
trimmed and levelled to proper profile as directed by the ENGINEER or indicated on
the drawings.
12.4 PLINTH FILLING
Plinth filling shall be carried out with approved material as described herein before
in layers not exceeding compacted thickness of 150mm, watered and compacted
with mechanical compaction machines. The ENGINEER may however permit
manual compaction by hand tampers in case he is satisfied that mechanical
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information.
compaction is not possible. When filling reaches the finished level, the surface shall
be flooded with water, unless otherwise directed, for at least 24 hours, allowed to
dry and then again compacted as specified above to avoid settlements at a later
stage. The finished level of the filling shall be trimmed to the level/ slope specified.
Where specified in the schedule of works, compaction of the plinth fill shall be carried
out by means of 12 tonne rollers smooth wheeled, sheep-foot or wobbly wheeled
rollers. In case of compaction of granular material such as sands and gravel,
vibratory rollers shall be used. A smaller weight roller may be used only if permitted
by the ENGINEER. As rolling proceeds water sprinkling shall be done to assist
consolidation. Water shall not be sprinkled in case of sandy fill.
The thickness of each unconsolidated fill layer can in this case be upto a maximum
of 200 mm. The ENGINEER will determine the thickness of the layers in which fill
has to be consolidated depending on the fill material and equipment used.
Rolling shall commence from the outer edge and progress towards the centre and
continue until compaction is to the satisfaction of the ENGINEER, but in no case less
than 10 passes of the roller will be accepted for each layer.
The compacted surface shall be properly shaped, trimmed and consolidated to an
even and uniform gradient. All soft spots shall be excavated and filled and
consolidated.
At some locations/ areas it may not be possible to use rollers because of space
restrictions, etc. The CONTRACTOR shall then be permitted to use pneumatic
tampers, rammers, etc. and he shall ensure proper compaction.
12.5 SAND FILLING IN PLINTH AND OTHER PLACES
At places backfilling shall be carried out with local sand if directed by the ENGINEER.
The sand used shall be clean, medium grained and free from impurities. The filled-
in-sand shall be kept flooded with water for 24 hours to ensure maximum
consolidation. Any temporary work required to contain sand under flooded condition
shall be to the CONTRACTOR's account. The surface of the consolidated sand shall
be dressed to required level or slope. Construction of floors or other structures on
sand fill shall not be started until the ENGINEER has inspected and approved the
fill.
12.6 FILLING IN TRENCHES
Filling in trenches for pipes and drains shall be commenced as soon as the joints of
pipes and drains have been tested and passed. The backfilling material shall be
properly consolidated by watering and ramming, taking due care that no damage is
caused to the pipes.
Where the trenches are excavated in soil, the filling from the bottom of the trench to
the level of the centre line of the pipe shall be done by hand compaction with selected
approved earth in layers not exceeding 80mm; backfilling above the level of the
centre line of the pipe shall be done with selected earth by hand compaction or other
approved means in layers not exceeding 150mm.
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information.
In case of excavation of trenches in rock, the filling upto a level 300mm above the
top of the pipe shall be done with fine materials, such as earth, murrum, etc. The
filling upto the level of the centre line of the pipe shall be done by hand compaction
in layers not exceeding 80mm whereas the filling above the centre line of the pipe
shall be done by hand compaction or approved means in layers not exceeding
150mm. The filling from a level 300mm above the top of the pipe to the top of the
trench shall be done by hand or other approved mechanical methods with broken
rock filling of size not exceeding 150mm mixed with fine material as available to fill
up the voids.
Filling of the trenches shall be carried simultaneously on both sides of the pipe to
avoid unequal pressure on the pipe.
13.0 GENERAL SITE GRADING
Site grading shall be carried out as indicated in the drawings and as directed by the
ENGINEER. Excavation shall be carried out as specified in the specification. Filling
and compaction shall be carried out as specified under clause 12.0 and elsewhere
unless otherwise indicated below.
If no compaction is called for, the fill may be deposited to the full height in one
operation and levelled. If the fill has to be compacted, it shall be placed in layers not
exceeding 225 mm and levelled uniformly and compacted as indicated in clause 12.0
before the next layer is deposited.
To ensure that the fill has been compacted as specified, field and laboratory tests
shall be carried out by the CONTRACTOR at his cost.
Field compaction test shall be carried out at each of the different stages of filling and
at frequency of one test in each layer per 2000 sqm area and also after the fill to the
entire height has been completed. This shall hold good for embankments as well.
The CONTRACTOR shall protect the earthfill from being washed away by rain or
damaged in any other way. Should any slip occur, the CONTRACTOR shall remove
the affected material and make good the slip at his cost.
The fill shall be carried out to such dimensions and levels as indicated in the
drawings after the stipulated compaction. The fill will be considered as incomplete if
the desired compaction has not been achieved.
If specifically permitted by the ENGINEER, compaction can be achieved by allowing
loaded trucks conveying fill or other material or chain tracked vehicles to ply over the
fill area. Even if such a method is permitted, it will be for the CONTRACTOR to
demonstrate that the desired/ specified compaction has been achieved. In order that
the fill may be reasonably uniform throughout, the material should be dumped in
place in approximately uniform layers. Traffic over the fill shall then be so routed to
compact the area uniformly throughout.
If so specified, the rock as obtained from excavation may be used for filling and
levelling to required grades without further breaking. In such an event, filling shall be
done in layers not exceeding 50 cm approximately. After rock filling to the
approximate level indicated above, has been carried out, the void in the rocks shall
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information.
be filled with finer materials such as earth, broken stone, etc. and the area to be
flooded so that the finer materials fill up the voids. Care shall be taken to ensure that
the finer fill material does not get washed out. Over the layer so filled, a 100 mm
thick mixed layer of broken material and earth shall be laid, and consolidation carried
out by a 12 tonne roller. No less than twelve passes of the roller shall be accepted
before subsequent similar operations are taken up.
14.0 SITE FILLING
14.1 FILL MATERIAL
14.1.1 General
All fill material whether such material is brought from outside borrow areas or from
excavation from within the site, will be subject to the ENGINEER’s written approval.
Notwithstanding any approval given to the fill material of borrow areas from which fill
material is proposed to be brought, the ENGINEER/ OWNER reserves the right to
reject such material, which in his opinion either does not meet the specification
requirements or is unsuitable for the purpose for which it is intended.
14.1.2 Borrow Areas
It shall be CONTRACTOR’s responsibility to locate suitable borrow areas for
borrowing fill material. Such area will be inspected by the ENGINEER and approved
before the CONTRACTOR makes arrangements to borrow the fill material. The top
soil which may contain vegetation, rubbish, slush, etc. shall not be used. If
demanded by the ENGINEER, the CONTRACTOR shall arrange to have trial pits of
specified dimensions and numbers dug at locations specified, for the ENGINEER to
examine the nature and type of material likely to be obtained from the borrow area.
14.1.3 Lead, Lift and Transportation
Unless separately provided for, all lead, lift and transportation required for bringing
in the fill material from borrow areas or from excavation from within the site shall be
included in the CONTRACTOR’s quoted unit rates.
14.1.4 Quality
The borrowed soil shall be generally granular, and non-cohesive. It shall consist of
sand, silty sand, murrum, ordinary soil, gravel and shingle. Dredged material shall
also be free from sulphates, salts, organic, foreign and other harmful or objectionable
materials. Any material rejected by the ENGINEER shall be removed from the site
immediately.
14.2 ACCESS ROADS
Roads, whether of temporary or other nature, required to be constructed for access
and for movement of men, materials, equipment, transport vehicles, vehicles
carrying fill material, etc. to or over borrow areas and/ or to or over areas on which
fill has to be deposited shall be constructed by the CONTRACTOR at his cost. Such
costs shall be deemed to have been included in the unit rates quoted by the
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information.
CONTRACTOR. Such access roads shall be maintained in good condition during all
seasons to ensure completion of work according to time schedule.
14.3 CLEARING
Site clearing before filling shall be carried out as per clause 5.0 of this specification.
14.4 FILLING
14.4.1 Sand Fill
a) Sandy fill shall be deposited to bring the grade level to desired elevation after
compaction of fill. Sandy fill shall be carried out as per the method indicated
in the drawings.
b) Compaction of sandy fill by flooding the area shall be carried out where so
specified. In this case, CONTRACTOR should ensure that the fill material is
not washed away. This work should be carried out as directed by ENGINEER.
c) Sandy fill shall be compacted, where so specified, by 12 tonne vibratory
rollers. The fill material shall be compacted to the specified density.
d) If the density of fill or use of rollers for compaction is not specified, the
CONTRACTOR shall ensure necessary compaction by the passage of trucks,
carrying the fill material over the deposited fill in such a way that the entire fill
area is covered. This will reasonably compact the sand fill and will be accepted
by the ENGINEER. However, the CONTRACTOR shall ensure that every
layer is thus compacted before the succeeding layers are deposited. Each
layer shall not exceed 200 mm in thickness.
14.4.2 Soil Fill
a) Approved soil fill consisting of ordinary soil, murrum, soil containing gravel,
shingle, etc. shall be deposited in layers not exceeding 200 mm.
CONTRACTOR should ensure that all clods of earth are broken down to a
size not larger than 100 mm.
b) Where density of fill or use of rollers is not specified, the fill shall be carried
out as specified in this specification.
c) Where the fill material has to be compacted by use of rollers procedure as
specified in clause 12.4of this specification shall be followed.
d) Where specified, the required density of fill shall be obtained by proper
compaction.
15.0 FILL DENSITY
The compaction, where so called for, in the Schedule of Quantities/ Items shall
comply with the specified (Standard Proctor/ Modified Proctor) density at moisture
content differing not more than 2 percent from the optimum moisture content. The
CONTRACTOR shall demonstrate adequately at his cost, by field and laboratory
tests that the specified density has been obtained.
16.0 PROPERTIES OF FILLING MATERIAL
The soil selected for filling purpose shall comply with the following requirements:
a) Soil shall be free from swelling properties. Preferably, soil having free swelling
index less than 50 shall be used. However, soil having free swelling index up
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information.
to 100 may be used after carrying out necessary soil improvement and
approval by ENGINEER. Liquid Limit and Plasticity Index shall be as per Table
8 of IS: 1498 for low degree of expansion.
b) It shall be possible to compact the soil upto 97% of Proctor Density or Modified
Proctor Density as per the project requirement. Broad guidelines for selection
of various types of soil groups and their requirements for compaction are
indicated in Table 8 of IS: 1498.
c) Soil shall be free from chemical contamination. It shall have pH value,
sulphate and chloride content within the permissible values specified in IS:
456.
17.0 LEAD
Lead for deposition/ disposal of excavated material, shall be as specified in the
respective item of work. For the purpose of measurement of lead, the area to be
excavated or filled or area on which excavated material is to be deposited/ disposed
of shall be divided into suitable blocks and for each of the blocks, the distance
between centre lines shall be taken as the lead, which shall be measured by the
shortest straight line route on the plan and not the actual route taken by the
CONTRACTOR. No extra compensation shall be admissible on the grounds that the
lead including that for borrowed material had to be transported over marshy or
'kutcha' land/ route.
18.0 MEASUREMENT AND PAYMENT
All excavation shall be measured net. Dimensions for purpose of payment shall be
reckoned on the horizontal area of the excavation at the base for foundations of the
walls, columns, footings, tanks, rafts or other foundations/ structures to be built,
multiplied by the mean depth from the surface of the ground in accordance with the
foundation drawings. Excavation in side slopes will not be paid for. The
CONTRACTOR may make such allowance in his rates to provide for excavation in
side slopes keeping in mind the nature of the soil and safety or excavation. However,
if the concreting is proposed against the excavated sides, no such over excavation
will be permitted. In such cases, over excavation shall be made good by the
CONTRACTOR with concrete of the same class as in the foundations at his cost.
Dewatering by ordinary methods not requiring well point shall be included in the
quoted rates for excavation.
Unless otherwise specified, the unit rates quoted for excavation in different types of
material shall also account for a basic lead of 100 metres for disposal as specified
or directed. Only leads beyond the basic lead of 100 metres will be considered as
extra lead and paid for at the rates quoted in the schedules.
Backfilling, as per specification, the sides of foundations, columns, structures, walls,
tanks, rafts, trenches, etc. with excavated material will not be paid for separately. It
shall be clearly understood that the rate quoted for excavation including backfilling
shall include stacking of excavated material as directed, excavation/ packing of
selected stacked material, conveying it to the place of final backfill, compaction, etc.
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information.
END
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information.
1.0 SCOPE
This specification covers the general requirements of dewatering excavations in
general.
2.0 DEWATERING
All excavations shall be kept free of water. Grading and surface water drainage
scheme in the vicinity of excavation shall be properly closed to prevent surface water
from draining into excavated areas. CONTRACTOR shall remove by pumping or other
means approved by ENGINEER any water inclusive of rain water and subsoil water
accumulated in excavation and keep all excavations dewatered until the foundation
work is completed and backfilled. Sumps made for dewatering must be kept clear of
the excavation/ trench areas required for further work of foundation construction.
Method of pumping shall be approved by ENGINEER; but in any case, the pumping
arrangement shall be such that there shall be no movement of subsoil or blowing in or
excavation wall collapse due to differential head of water during pumping. Pumping
arrangements shall be adequate to ensure no delays in construction.
The CONTRACTOR shall take adequate measures for bailing and/ or pumping out
water from excavations and construct diversion channels, bunds, sumps, coffer dams,
etc. as may be required. Pumping shall be done directly from the foundation trenches
or from a sump outside the excavation in such a manner as to preclude the possibility
of movement of water through any fresh concrete or masonry and washing away parts
of concrete or mortar. During laying of concrete or masonry and for a period of at least
24 hours thereafter, pumping shall be done to ensure that the surface below the
concrete remains dry.
Capacity and number of pumps, location at which the pumps are to be installed,
pumping hours, etc. shall be reviewed by the CONTRACTOR from time to time. The
ENGINEER may direct the CONTRACTOR to make changes in his scheme if the
adopted scheme fails to achieve the desired results.
Pumping shall be done in such a way as not to cause damage to the work or adjoining
property by subsidence, etc. Disposal of water shall not cause inconvenience or
nuisance in the area or cause damage to the property and structures nearby or shall
not be a cause for environmental pollution of natural water bodies.
When there is a continuous inflow of water and quantum of water to be handled is
considered in the opinion of ENGINEER as large, well point system - Single stage or
multi stage, shall be adopted. CONTRACTOR shall submit to ENGINEER his scheme
of well point system including the stages, the spacing, number and diameter of well
points, headers, etc. and the numbers, capacity and location of pumps of approvals.
Normal dewatering using bailing arrangement, submersible pumps shall be included
in the item rate for excavation. Special dewatering system using well point system shall
be considered as separate item.
In case well point dewatering is required, the Indian Standard IS 9759: 1981
(Reaffirmed 2016) - Guidelines for De-Watering During Construction shall be used for
design of the dewatering system.
FILENAME: M4-418-03-REV-03.DOCX
Proprietary Notice and Version Control
This document contains confidential information for use only by the “Client”; for the Project under consideration, which is provided for the sole purpose of permitting the recipient to evaluate the information
submitted herewith. In consideration of receipt of this document; unless agreed to in contrary in the Contract; the recipient agrees to maintain such information in confidence and to not reproduce or otherwise
disclose this information to any person outside the recipient’s organisation; except that there is no obligation to maintain the confidentiality of any information which was known to the recipient prior to receipt of
ISSUE
such information from Tata Consulting Engineers Limited, or becomes publicly known through no fault of recipient, or Tata Consulting Engineers Limited, or is received without obligation of confidentiality from
a third party owing no obligation of confidentiality to Tata Consulting Engineers Limited. All information given under this version over rides all and any kind of offers, assumptions, deliverables and contracts
R3
submitted verbally (and subsequently communicated in writing) or in writing or otherwise given under any and all previous version/s.
3.0 MEASUREMENT
Normal dewatering using bailing arrangement, submersible pumps shall be included
in the item rate for excavation. Special dewatering system using well point system shall
be considered as separate item. If such special items are not included in the schedule
of quantities but required to be operated, it shall be treated as an extra item and
separate rate shall be obtained from contractor and agreed upon between Owner and
Contractor.
END
ISSUE
R3
1.0 SCOPE
1.1 This Specification covers the general requirements for ready mixed concrete and
for concrete using on-site production facilities including requirements with regard
to the quality, handling, storage of ingredients, proportioning, batching, mixing,
transporting, placing, curing, protecting, repairing, finishing and testing of concrete;
formwork; requirements with regard to the quality, storage, bending and fixing of
reinforcement; grouting as well as mode of measurement and payment for
completed works.
1.2 It shall be very clearly understood that the specifications given herein are brief and
do not cover minute details. However, all works shall have to be carried out in
accordance with the relevant standards and codes of practices or in their absence
in accordance with the best accepted current Engineering practices or as directed
by ENGINEER from time to time. The decision of ENGINEER about the
specification to be adopted and their interpretation and the mode of execution of
work shall be final and binding on CONTRACTOR and no claim whatsoever will be
entertained on this account.
2.0 APPLICABLE CODES AND SPECIFICATIONS
2.1 The pertinent clauses of the following Indian Codes, Standards and Specification
shall apply to the material and workmanship covered by this specification. In the
event of the conflict of certain requirements between this specification and the
codes referred herein, this specification shall govern.
2.2 The codes and standards mentioned herein shall be latest as on the day of award
of contract of the works unless otherwise specified. Contractor shall be responsible
to inform to the Consultant/ Owner in case of any revisions/re-affirm/amendment in
the relevant codes and standards after the date of award of contract within 30 days
of the issue of such revision/re-affirm/amendment of the code/ standard.
Consultant/ Owner may approve use of the earlier code/ standard if the revisions
do not materially affect the statutory requirements of the project or does not impact
safety practices. Any cost impact arising out of such revisions shall be mutually
agreed.
2.3 It is not the intent to specify herein all the codes and standards required for the
satisfactory completion of work. The list of codes and standards indicates certain
primary codes and standards and not all the codes required for the work under the
contract. It is understood that all the pertinent codes and standards shall form the
part of this specification whether explicitly indicated or not. Indian Standards shall
be supplemented by International Standards for clarity and coverage wherever felt
so.
FILE NAME:M4.403-01-Rev.R10
Proprietary Notice and Version Control
This document contains confidential information for use only by the “Client”; for the Project under consideration, which is provided for the sole purpose of permitting the recipient to evaluate the information submitted
herewith. In consideration of receipt of this document; unless agreed to in contrary in the Contract; the recipient agrees to maintain such information in confidence and to not reproduce or otherwise disclose this
ISSUE
information to any person outside the recipient’s organisation; except that there is no obligation to maintain the confidentiality of any information which was known to the recipient prior to receipt of such information
from Tata Consulting Engineers Limited, or becomes publicly known through no fault of recipient, or Tata Consulting Engineers Limited, or is received without obligation of confidentiality from a third party owing no
R11
obligation of confidentiality to Tata Consulting Engineers Limited. All information given under this version over rides all and any kind of offers, assumptions, deliverables and contracts submitted verbally (and
subsequently communicated in writing) or in writing or otherwise given under all previous version/s.
2.4 MATERIALS
IS 455:2015 Specification for Portland Slag Cement.
IS 1489: PART 1: Portland pozzolana cement - specification part 1 fly ash
2015 based
IS 1489: PART 2: Portland pozzolana cement - specification part 2 calcined
2015 clay based (fourth revision)
IS 8112:2013 Ordinary Portland Cement, 43 Grade
IS 12330: 1988
Specification for Sulphate Resisting Portland Cement
(Reaffirmed 2019)
Coarse and fine aggregate for concrete - specification (third
IS 383: 2016
revision)
Specification for Mild Steel and Medium Tensile Steel Bars
IS 432: 1982
and Hand Drawn Steel Wire for Concrete Reinforcement –
(Reaffirmed 2015)
Part 1 and 2
IS 1786: 2008 High strength deformed steel bars and wires for concrete
(Reaffirmed 2018) reinforcement - specification
IS 1566:1982 Specification for hard-drawn steel wire fabric for concrete
Reaffirmed 2015 reinforcement
IS 9103:1999
Concrete admixtures - specification
Reaffirmed 2018
IS 2645:2003 Integral waterproofing compounds for cement mortar and
Reaffirmed 2017 concrete - specification
IS 4990:2011
Plywood for concrete shuttering work - specification
Reaffirmed 2017
IS 4926:2003
Ready-mixed concrete - code of practice
Reaffirmed 2017
IS 12269: 2013 Ordinary Portland Cement, 53 Grade
IS 8041:1990
Specification for rapid hardening cement.
Reaffirmed 2019
IS 12600: 1989
–Specification for Low Heat Portland Cement
(Reaffirmed 2019)
IS 6909: 1990
Specification for super-sulphated cement
(reaffirmed 2016)
IS 12089:1987 Specification for granulated slag for manufacture of portland
Reaffirmed 2018 slag cement
ISSUE
R11
ISSUE
R11
IS 4014
Code of practice for steel tubular scaffolding Part 1
(Part 1):1967
Definitions and materials
Reaffirmed 2016
IS 4014 Code of practice for steel tubular scaffolding: Part 2 Safety
(Part 2):2013 regulations for scaffolding (first revision)
IS 2571:1970
Code of practice for laying in situ cement concrete flooring
Reaffirmed 2017
IS 7861
Code of practice for extreme weather concreting: Part
(Part 1):1975
1Recommended practice for hot weather concreting
Reaffirmed 2016
IS 7861
Code of practice for extreme weather concreting: Part
(Part 2):1981
2Recommended practice for cold weather concreting
Reaffirmed 2016
IS 3812 (Part 1): Pulverized fuel ash – Part 1 – For use as pozzolana in
2013 cement, cement mortar and concrete
3.0 GENERAL
3.1 ENGINEER shall always have the right to inspect all operations including the
sources of materials, procurement, layout and storage of materials, the
concrete batching and mixing equipment, and the quality control system. Such ISSUE
an inspection shall be arranged, and ENGINEER’s approval obtained, prior to R11
i. In a flight of stairs
Rise - 3 mm
Tread - 5 mm
Plus - 10 mm
Variation in the thickness of slabs, walls, arch sections and similar
vi.
members.
Minus - 5 mm
Plus - 50 mm
11.2.3 Footing for Columns, Piers, Walls, Buttresses and Similar Members
11.3 Tolerance for top of concrete of equipment and structural steel foundations
shall be as under unless more stringent requirements are specified by
equipment manufacturer:
(a) Where grout thickness is less than or equal to 25 mm: ±5 mm.
(b) Where grout thickness is more than 25 mm: ±5 mm.
11.4 EXECUTION AND REMOVAL OF FORMS
(a) Before placing concrete, the surface of all forms shall be coated with
suitable non-staining form releasing agents such as raw linseed oil to
prevent adhesion of concrete and to facilitate removal of forms.
(b) The form releasing agent shall cover the forms fully and evenly without
excess over drip. Care shall be taken to prevent form releasing agents
from getting on the surface of the construction joints and on
reinforcement bars. Special care shall be taken to thoroughly cover form
strips for narrow grooves, to prevent swelling of the forms and the
consequent damage to concrete prior to or during removal of forms.
(c) Immediately before concrete is placed care shall be taken to see that all
forms are in proper alignment and the supports and fixtures are properly
secured and tightened.
(d) Where forms for continuous surfaces are placed in successive units, the
forms shall lap and fit tightly over the completed surface to prevent
leakage of cement slurry from the fresh concrete and to maintain
accurate alignment of the surface.
(e) Forms shall be left in place until their removal is authorised and shall
then be removed with care to avoid injury to concrete.
(f) Removal of forms shall be started when the concrete has achieved
strength of at least twice the stress to which the concrete may be
subjected at the time of removal of formwork.
(g) In normal circumstances and where ordinary Portland cement is used
forms can be allowed to be struck asper the guideline given in clause
11.3 of IS 456.
Note: Time shall be measured from last batch concreted in respect to the
structural member under consideration. For other cement stripping time as
recommended above may be suitably decided by ENGINEER.
Re-propping shall be done to the below floor to carry the construction load
transferred through props/ equipment, etc. during construction of upper floor
and props left under till the period of removal of props supported to or any other
load due to construction load on the upper floor. Re-propping shall be part of
shuttering/ formwork for concrete without any claim for extra cost.
11.5 SETTLEMENT OF FORMWORK AND CAMBER
Due to various reasons such as closure of form joints, shrinkage of timber, dead
load deflections, elastic shortening of form members or formwork, deflections,
settlement may occur. The CONTRACTOR shall take precautions, including
using adequately rigid formwork, to prevent excessive settlement/ deflection;
the usual acceptable limit being 1/500 of the spans of the formwork.
ISSUE
R11
Table-2
Volume of Coarse Aggregate per unit of Volume of Concrete
Grade – A (Maximum Size 40 mm) Grade – B (Maximum Size 20 mm)
Volume of Dry-rodded Coarse Aggregate per Unit Volume of
Maximum Size
Aggregates of Concrete for different Fineness Moduli of sand
FMS = 2.40 FMS = 2.60 FMS = 2.80 FMS = 3.00
10 0.50 0.48 0.46 0.44
12.50 0.59 0.57 0.55 0.53
20 0.66 0.64 0.62 0.60
25 0.71 0.69 0.67 0.65
40 0.76 0.74 0.72 0.70
50 0.78 0.76 0.74 0.72
Notes:
1. Volumes are based on aggregates in dry-rodded condition.
2. These volumes are selected from empirical relationships to produce
concrete with a degree of workability suitable for usual reinforced
construction. When placement is to by pump, they shall be reduced by
about 10 percent.
3. FMS = Fineness Modulus of Sand.
14.8.2 Fine Normal Weight Aggregate
Fine aggregate shall consist of natural sand, manufactured sand or a
combination thereof and shall be graded within the following limits:
Sieve Size Percent passing by Weight
9.50 mm 100
4.75 mm 95 to 100
2.36 mm 80 to 100
1.18 mm 50 to 85
600 microns 25 to 60
300 microns 10 to 30
150 microns 2 to 10 ISSUE
R11
ISSUE
R11
ISSUE
R11
3. REINFORCEMENT CHECKED
4. COVER TO REINFORCEMENT CHECKED
VERIFIED TEST CERTIFICATE FOR
5. YES/ NO YES/ NO
CEMENT/ STEEL
ADEQUENCY OF MATERIALS/
6. YES/ NO YES/ NO
EQUIPMENT FOR POUR
EMBEDED PARTS CIVIL
CHECKED MECHANICAL
7.
(LOCATION AND
PLUMB) ELECTRICAL
POUR AUTHORISED SITE ENGINEER
SOFFIT(S) AND POUR TOP(T) LEVELS S(B) T(B)
CHECKED BEFORE (B) AND AFTER (A) FORM S(A) T(A)
8. REMOVAL (ONLY OF BEAMS OF OVER 10 M
SPAN AND IMPORTANT STRUCTURES LIKE
TG, ETC.)
CONSTRUCTION JOINT LOCATION AND TIME
9.
(IF NOT AS PER DRAWING)
10. CEMENT CONSUMPTION IN KG
NUMBER OF CUBES AND IDENTIFICATION
11.
MARK
12. TEST CUBE RESULTS (7 DAYS/ 28 DAYS) / / /
VERY GOOD/ GOOD/ FAIR/
13. CONCRETE CONDITION ON FORM REMOVAL
POOR
SITE-IN-CHARGE
NOTES:
1. EACH ITEM TO BE CHECKED AND SIGNED BY THE RESPECTIVE ENGINEERS.
2. ITEMS 8 TO 13 (BOTH INCLUSIVE) TO BE FILLED BY ONLY TCE ENGINEER.
3. EACH POUR TO HAVE SEPARATE CARDS, IN TRIPILCATE ONE EACH FOR CLIENT, TCE AND
SITE OFFICE.
UNDER REMARKS INDICATE DEVIATIONS FROM DRAWINGS AND SPECIFICATIONS,
CONGESTION IN REINFORCEMENT, IF ANY, UNUSUAL OCCURENCES, SUCH AS FAILURE OF
EQUIPMENT, SINKING OF SUPPORTS/ PROPS, HEAVY RAINS AFFECTING CONCRETEING,
POOR COMPACTION, IMPROPER CURING, OTHER DEFICIENCIES, OBSERVATIONS, ETC.
ISSUE
R11
1.0 SCOPE
2.0 MATERIALS
2.2.1 cement
Cement shall be ordinary Portland cement conforming to IS:8112/ ASTM
C150.
2.2.2 Aggregates
Sand shall be clean and well graded conforming to IS383. For fluid mix
grout, sand shall conform to zone-4 grade. Course aggregates wherever
used shall also conform to IS 383/ ASTM C33/ C144-11.
2.2.3 Water used for mixing of grout shall be clean and free from oils, acids,
alkalis, organics and other deleterious materials and conforming to the
requirements of IS:456
2.2.4 Admixtures
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE R5
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE R5
3.2 Anchor bolts, anchor bolt holes and the bottom of equipment and column
base plates shall be cleaned of all oil, grease, dirt and loose material.
3.3 The hardened concrete surfaces on which the cementitious grouts are to be
placed shall be saturated with water. All standing water shall be removed
from the concrete surface as well as from anchor bolt holes, just prior to
grouting. However, surface shall be absolutely dry before placing epoxy
grouts.
4.0 INSTALLATION
4.1 Ready mixed grouts shall be mixed in the manner and in accordance with
manufacturer’s recommendations and shall be used in the form of liquid/
fluid. In case of field proportioned mix it shall be prepared, mixed and placed
in accordance to ACI:351-1-12. Consistency of grout shall be such so that it
can maintain its flowability within the gap provided below the base plates,
during its entire period of placement. Grouts shall be placed from one end to
the other. Grouting, once started, shall be finished quickly and continuously
to prevent segregation, bleeding and starting of initial set. No water or
solvent shall be added to change the consistency, if the grout stiffens during
placement. The stiffened grouts along with other grout, in place but not
completed, shall be removed.
4.2 The bases of structures and equipment are levelled and aligned by other
vendors by using shims. Shims shall be positioned at the edges of bases to
permit easy subsequent removal.. In case of fliud /plastic mix, grout of
suitable mix shall be poured immediately after preparation into the
pockets/blockouts/bolt holes/space between the base & concrete either from
sides or through holes made in bases by using special equipment for
pressure grouting. dry pack grouts, if used, shall be placed by firmly
pressurizing or ramming into the place against fixed supports or rodding.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE R5
Extreme care shall be taken to see that alignment and levels of bases are
not disturbed during grouting.
It shall be ensured by rodding and tapping of bolts that the blackouts are
completely filled with grout without leaving voids
4.3 The grouts shall be prepared only to the extent it can be used within the
specific pot life by the manufacturer. Any leftover grout or grouts not
consumed within the pot life time shall not be used and shall be discarded.
The shelf life of the grout shall also be checked before they are used.
Grouts having expired date shall not be used under any circumstances.
4.5 Forms and shims shall not be removed and the anchor bolts shall not be
tightened for at least twenty four hours after placing the grout. After removal
of forms and peripheral shims, area occupied by shims shall be filled and
the area between the base and the edge of the foundation shall be finished
smooth to allow drainage away from the base. Interconnecting piping shall
not be attached to the machinery before anchor bolts are tightened. It is
desirable to make these connections at least after a minimum of seven
days from the date of grouting. During this period, the grout shall be
properly cured.
4.6 Grout shall be cured for a period of at least 7 days commencing 24 hours
after the completion of grouting. The curing shall be done by covering the
surfaces with wet gunny bags and flooding unless otherwise
specified/recommended by grout manufacturer.
5.0 INSPECTION
5.1 All materials, workmanship and finished construction shall be subject to the
continuous inspection and approval of ENGINEER.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE R5
5.4 All grouting shall be protected against damage until final acceptance by
OWNER or his representative.
5.5 Upon the completion of grouting work, all forms, equipment, construction
tools, protective coverings and any debris shall be removed from the area as
directed by the ENGINEER.
6.0 GENERAL
6.1 The thickness of standard dry pack grouts shall be minimum 75mm.
However,thickness of flow-able grout can be anywhere between 20 to 50mm
except in case of equipment bases where grout thickness shall be as per
equipment supplier’s recommendation.
6.2 Generally, the Crushing strength of grout shall be one grade higher than the
base concrete on which the grout is placed. However in case of large
equipment foundations like TG deck, wind mill pedestals, grout strength
shall be arrived based on actual bearing stress due to external loads via-a-
vis allowable bearing pressure on concrete unless otherwise specified by
the equipment supplier. Minimum crushing strength shall be 30N/mm2,
unless otherwise specified.
6.3 Full contact area between the grout and baseplate shall be ensured..
6.4 All materials shall be delivered to site in original unopened packages, clearly
labelled with the manufacturer’s identification and printed instructions. The
contractor must submit the manufacturer’s certified test data on the grout’s
constituents, 24 hour compressive strength and its flowability, from
approved test laboratory, prior to placement of order. Manufacturers shall
also give warranty saying that the non-shrink grout supplied shall never go
below its initial placement volume.
6.5 Forms around base plates shall be reasonably tight to prevent leakage of
the grout. When the base is to be flow grouted, forms shall be built and
securely anchored outside the base plate so as to completely confine and
withstand the pressure of liquid grout under working and rodding condition
without leaking and high enough to ensure the grout is in contact with the
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE R5
underside of the base plate, and provide a head of minimum 100 mm above
the underside of the base plate. Provisions of grout holes in base plates,
rodding, arrangements shall be checked prior to commencement of grouting.
6.6 Adequate clearances shall be provided between forms and base plate to
permit grout to be worked properly into place.
6.7 Grouting through holes in base plates shall be by pressure grouting. The
pressure to be used for grouting shall be as directed by the ENGINEER.
END
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE R5
1.0 SCOPE
1.1 This specification covers the general requirements for supply of all structural
steel items where specified, fabrication, inspection and testing of all fabricated
structural steel items. Volume III/SECTION C covers the specific requirements
for the project. The two parts are complementary and are to be read together
for a correct interpretation of the provisions of this specification. Where
requirements of the two parts conflict; those of Volume III/SECTION C shall
govern.
1.2 This specification also covers design of all connections and substituted
members, preparation of all shop fabrication drawings, inspection of fabricated
items.
1.3 The scope of work also includes but is not limited to supply (if the fabrication
shop is not within plant site), proper stacking and storage of fabricated
materials. All the works shall be carried as per approved QA procedures.
2.0 APPLICABLE CODES STANDARDS AND SPECIFICATIONS
It is not the intent to specify herein all the codes and standards required for the
satisfactory completion of work. The list of codes and standards indicates
certain primary codes and standards and not all the codes required for the work
under the contract. It is understood that all the pertinent codes and standards
shall form the part of this specification whether explicitly indicated or not.
IS 1239: 2011 Mild steel tubes, tubular and other wrought steel
(Reaffirmed 2016) fittings-Part 2: Mild steel tubular and other
wrought steel pipe fittings
IS 1363:2018
Part 3: Hexagon Nuts (Size range M5 to M64)
IS 1367:2017 Technical Supply Conditions for Threaded
Fasteners (All Parts)
Part-3: Technical supply conditions for threaded
steel fasteners: Part 3: Mechanical properties of
fasteners made of carbon steel and bolts, screws
and nuts.
The work covered in this specification, shall comply with all relevant
government and local laws, regulations and standards. For subjects not
covered by regulations, codes, standards or specifications, the materials and
construction shall be based on good engineering practice, subject to approval
by OWNER.
4.1.1. The CONTRACTOR shall use steel supplied by the OWNER judiciously and to
the best advantage so as to minimize splicing and wastage. All steel materials
remaining after completion of the work, whether in the form of balance pieces
or unutilized prime steel, shall be returned to the OWNER’s stores by the
CONTRACTOR at his own cost. Reconciliation of steel supplied and wastage
will be as specified in the Contract.
4.1.2. Structural steel materials will be issued in sizes as received from manufacturer
/ suppliers within the project area at the departmental stores free of cost or at
the rates specified in the Contract. The CONTRACTOR shall make necessary
arrangements for carriage, loading, unloading of all materials to work site at his
own cost within the rates quoted and agreed for the job.
4.1.3. OWNER shall furnish the mill / manufacturer’s test reports, along with the
materials and satisfactorily demonstrate the specific grade and quality.
4.1.4. All materials required for the work shall be correlated with manufactures test
certificates. In the absence of test certificates, CONTRACTOR shall test
materials through reputed laboratory approved by ENGINEER for establishing
quality, at OWNER’s cost and as directed by the ENGINEER. ISSUE
R9
4.1.5. On receiving each consignment of steel from the OWNER the CONTRACTOR
shall acknowledge in writing the receipt thereof giving full particulars of
sections, sizes, quantities, grade and quality. Should there be any damage or
distortion of the materials in transit, the CONTRACTOR shall immediately
report the matter to the ENGINEER in writing.
4.1.6. The CONTRACTOR shall take proper care of the steel supplied by the OWNER
and protect them from weathering and damage. Any such materials rendered
unserviceable or damaged while in the CONTRACTOR’s custody shall be
replaced by the CONTRACTOR at his own cost as determined by the
ENGINEER.
4.1.7. In cases where after receipt of visibly good tested quality steel from the
OWNER, defects such as laminations, seams, tears, fins etc., are discovered
during fabrication, the work on such sections shall be stopped immediately and
the matter shall be brought to the notice of OWNER who shall arrange for
replacing the affected sections, if necessary.
4.1.8. CONTRACTOR shall use the materials as issued by the OWNER to fabricate
the structures as required. No extra claim on account of extra welding and / or
cutting due to non-conformity of sizes with the drawings issued will be
entertained.
4.1.9. Steel required for the work will be issued to the CONTRACTOR on the basis of
approved fabrication drawings and drawings released for construction.
4.1.10. Steel will be issued to the CONTRACTOR on the basis of standard sectional
weights and measured lengths rounded off to nearest 5mm with Unit weights
given in BIS 808. For sections and weights not covered in IS: 808, unit weights
as given by the manufacturers shall be considered for calculation of weight.
The same unit weight shall be used in the BOM included in fabrication
drawings.
4.2.1 All steel and other material shall be procured and supplied by the
CONTRACTOR, from reputed manufacturers as mentioned in tender
document. Steel proposed to be procured from other manufacturers shall have
prior approval from the OWNER before placement of procurement order.
However, OWNER reserves the right to accept or reject material from other
manufacturers. Materials from re-rollers will not be accepted. Steel procured
shall conform to the applicable codes & standards mentioned in clause 2.0.
4.2.2 CONTRACTOR shall use materials for fabrication as specified in the approved
ISSUE
drawings. All materials supplied by the CONTRACTOR shall be in sound R9
condition, of recent manufacture, free from defects such as mill scales, slag
intrusions, laminations, pitting, flakes, rust etc. and be of full weight and
thickness as specified.
4.2.3 CONTRACTOR shall furnish the mill / manufacturer’s test reports, along with
the materials and satisfactorily demonstrate the specific grade and quality.
Material test certificate shall be in original.
4.2.4 All materials required for the work shall be correlated with manufactures test
certificates. In the absence of test certificates, CONTRACTOR shall test
materials through reputed laboratory approved by ENGINEER for establishing
quality, at CONTRACTOR’s cost and as directed by the ENGINEER.
4.2.5 Material supplied against each Test Certificates (TC) shall have identification
stamped or stencilled on them. All such identification markings shall be
authenticated by the inspection agency, which has inspected and approved
the material.
4.2.6 The CONTRACTOR shall furnish to the ENGINEER duplicate copies of all
purchase order copies covering the material ordered by him for the project
under reference and also test reports.
4.2.7 The OWNER/ ENGINEER shall have the right to test random samples to
prove authenticity of the test certificates produced by the CONTRACTOR at
OWNER’s cost. Any material found not meeting the required specification
would be rejected. The cost of testing, if material gets rejected shall also then
be borne by CONTRACTOR.
5.0 DRAWINGS.
5.1.1 Engineer will issue to CONTRACTOR such drawings and data as specified in
Contract which may include, depending on Contract:
a) Preliminary Drawings and Data along with Tender / Enquiry.
b) Interface particulars with other Contracts and
c) Detailed engineering design drawings in OWNER’s Scope.
ISSUE
R9
5.1.4 Engineer reserves the right to make changes; revisions to drawings, even after
release for preparation of shop drawings, to reflect additional data/details
received and updated requirements. Revisions to drawings and any new
drawings made to include additional work by the OWNER shall be considered
as part of this specification and contract without additional cost implication to
the OWNER. The OWNER shall not entertain any extra claims on this account.
5.1.6 Unless otherwise specified, the drawings and specifications are intended to
include everything obviously requisite and necessary for proper and entire
completion of the work and shall be carried out accordingly for completeness
as required.
Owner. All the drawings for the entire work shall be prepared in metric units.
The drawings shall preferably be of one standard size and the details shown
there in shall be clear and legible. Drawings shall be prepared in computer
tools and the details shall be drawn to the minimum scale as specified under.
5.2.3 Key plan prepared by the CONTRACTOR shall indicate the fabrication /
erection marking of each member and a table showing the corresponding
fabrication drawing number where these members are detailed. Also, each
drawing prepared by CONTRACTOR shall indicate corresponding
ENGINEER’s design drawing number with revisions.
5.2.4 Each member shall be detailed separately unless members are identical in all
respects with no deviation whatsoever. Shop detail drawings shall show all
shearing, punching, drilling, bevel cutting, bending, and all welding in complete
detail. All connections and splices shall be designed and detailed by the
CONTRACTOR and clearly shown on the drawings. Bill of material shall show
number, size, length, weight and assembly work of each erection piece. Bill of
material for each drawing shall include fasteners/bolts, nuts, washers and
other accessories complete with specification, size, length, numbers, etc., for
each erection mark and proper identification for each joint. Bill of material shall
be prepared erection mark wise, showing weight of each component part and
total weight of each erection mark. All revisions after initial issue of a drawing
shall be clearly indicated with issue number and date of revision.
5.2.5 Each drawing prepared by the CONTRACTOR shall clearly indicate Names of
OWNER, ENGINEER, CONTRACTOR, Project Title, Title of drawing, Scale,
Notes, Details of revisions carried out etc. All titles, noting, markings and
writings on the drawing shall be in English and all dimensions shall be in metric
units. Before the commencement of preparation of fabrication drawings,
CONTRACTOR shall discuss with the ENGINEER any specific requirement to
be followed for fabrication drawing preparation.
ISSUE
R9
5.2.6 No detailed shop drawings will be accepted by the ENGINEER unless they are
complete and checked and approved by CONTRACTOR’s qualified Structural
ENGINEER and accompanied by an erection plan showing the location of all
pieces detailed.
5.2.7 CONTRACTOR shall check for erection clearance and ensure that detailing of
connections is carefully planned to obtain ease in erection of structures
including field-welded connection and bolting. Field connections/splices may
be welded or bolted type as specified in design drawings.
5.2.8 CONTRACTOR shall submit design calculations for major connection detail as
advised by the ENGINEER, splices proposed by him and also for any
substitution members desired by him and approved by the ENGINEER.
Fabrication drawings not accompanied by calculation for such connection
details/ splices are liable for rejection.
5.2.9 Each lot of drawings sent by CONTRACTOR for approval shall contain a limited
number of drawings and shall be in an order and manner which follows erection
sequence or as required by ENGINEER based on priorities allocated.
ENGINEER will return copy of CONTRACTOR's drawing marked with
ENGINEER’s approval/comments. CONTRACTOR shall furnish the
ENGINEER the required number of prints and soft copy of all approved
drawings for field use and record purpose.
thicker plates shall be given a chamfer on both sides such that at the location
of butt welds, thickness of plate on either side will be equal.
g) Similarly, where the width of the flange plate changes, the wider plate shall be
tapered with a slope 1 horizontal to 5 vertical.
h) Site splicing may be by welding or by means of high tensile bolts.
i) In the case of built up framing beams, the weld between flange and web shall
be calculated based on standard formula considering the shear force as the full
shear capacity of the web. Continuous weld shall be provided keeping size of
weld uniform for the full length of girder. However, is no case the size of weld
shall be less than half the web thickness.
j) Weld between flanges and web both for column as well as beams, shall
preferably be made using automatic welding machines, with proper sequence
of welds to avoid warping. The processing of welding and the methodology
shall be got approved before welding is started.
k) Connection of bracings /tie beams to column shall follow the details given in
the design drawings. The maximum size of the weld shall be less than or equal
to the thickness of the rolled section at the location of connection.
l) Thickness of gusset plates if not specified on design drawings shall be at least
equal to the thickness of member connected and shall have adequate cross
section to transfer the force at the point. If the members are connected on either
side of gusset, thickness of gusset shall be more than sum of thickness of fillet
weld on either side of gusset. Layout of gusset plate shall be such that the
eccentricity between member c.g. and the c.g of connection gusset is a
minimum.
5.2.11 ENGINEER may review / approve some, all or none of the fabrication drawings
at his option. Wherever such review is carried out the same shall be restricted
to the following-
ISSUE
R9
5.2.12 It shall be clearly noted by the CONTRACTOR that even where review is done
by the ENGINEER, the following shall be the sole responsibility of the
CONTRACTOR.
a) Provision for erection.
b) Marking of members.
c) Cutting Lengths of members
d) Matching of Joints and holes
e) Provision kept in the member for all other interconnected members
f) Bill of materials.
g) Gusset sizes.
h) Connections
5.2.13 Approval by ENGINEER of any of the fabrication drawings shall not relieve the
CONTRACTOR from the responsibility for correctness of engineering, design
of connections, workmanship, and fit of parts, details, material, errors or
omissions of any and all work shown thereon. ENGINEER’s approval shall not
invalidate any claim by OWNER for damages of any kind for incorrectly
detailed / fabricated steel.
5.2.16 All fabrication drawings submitted by the CONTRACTOR will remain the
property of the OWNER. OWNER reserves the right to use them in any manner
whatsoever.
6.0 FABRICATION
6.1 GENERAL
6.1.1 Fabrication shall not be started until CONTRACTOR has received copies of
such drawings upon which ENGINEER has endorsed his approval. Any work
done prior to approval of CONTRACTOR’s fabrication drawings will be at the ISSUE
R9
6.1.2 All workmanship and finish shall be of the best quality and shall conform to
good engineering practice and the best-approved method of fabrication. All
materials shall be finished straight and shall be machined / ground smooth,
true and square where so specified.
6.1.3 All holes and edges shall be free of burrs. Shearing and chipping shall be
neatly and accurately done and all portions of work exposed to view shall be
neatly finished. Standard fabrication clearances as detailed in the American
Institute of Steel Construction Manual / BIS Codes shall generally be followed
unless otherwise directed / approved.
6.1.4 Materials at the shop shall be kept clean and protected from weather. Cutting,
punching, drilling, welding and fabrication tolerances shall be generally as per
relevant Codes and Standards. In addition, the CONTRACTOR shall strictly
adhere to the following.
6.2 CONNECTIONS
6.2.2 All connections shall be designed for forces indicated on the design drawings
or as specified elsewhere in the specification/standard drawing if not given in
the design drawings. The CONTRACTOR shall be responsible for selection of
standard connections from AISC Manual of Steel Construction or any other
standards approved by ENGINEER.
6.2.3 All connections shall be designed and detailed as per guidelines given in IS:
800:2007.
ISSUE
R9
6.2.4 In case of bolted connections, taper washers or flat washers or spring washers
shall be used with bolts as necessary. In case of high strength friction grip bolts,
hardened washers are used under the nuts or the bolt heads whichever are
turned to tighten the bolts. The length of the bolt shall be such that at least one
thread of the bolt projects beyond the nut, except in case of high strength
friction grip bolts where this projection shall be at least three times the pitch of
the thread.
6.2.5 In all cases where bearing is critical, the unthreaded portion of bolt shall bear
on the members assembled. A washer of adequate thickness may be provided
to exclude the threads from the bearing thickness, if a longer grip bolt has to
be used for this purpose.
6.2.6 Not more than one shop splice shall be provided to make up the full length of
a member. Shop splices to make the full member lengths shall be of full
penetration butt welded type and radiographically tested.
6.2.8 All bolts, nuts, screws, washers, electrodes, etc. shall be supplied / brought to
site 10% in excess of the requirement in each category and size. Rates shall
cover the cost of this extra quantity and no additional payment will be made for
this extra quantity supplied.
6.2.9 All members likely to collect rain water shall have drain holes provided.
6.3 STRAIGHTENING
6.3.1 Rolled material, before being worked, shall be straightened, unless otherwise
specified. If straightening or flattening is necessary, it shall be done by methods
that will not injure the material. Long plates shall be straightened by passing
through a mandrel or levelling rolls and structural shapes by the use of
mechanical or hydraulic bar/section straightening machines. Heating or forging
shall not be resorted to without the prior approval of the ENGINEER in writing.
In case of site fabrication, CONTRACTOR shall obtain ENGINEER’s approval
in writing on the straightening method proposed to be adopted before
commencing the work.
6.3.2 Checking of the straightness of the structural members like angles, channels,
beams etc. shall be done by using the thread. For checking of the straightness
ISSUE
of the column sections piano wire shall be used. The sections, which are R9
twisted beyond repairs, shall not be used for fabrication. Heating or hammering
shall not be permitted. After removal of bends structural members shall be
submitted for inspection and approval of ENGINEER.
6.4 CUTTING
6.4.1 Cutting may be done by shearing, cropping, sawing or machine flame cutting.
All re-entrant corners shall be shaped notch free to a radius of at least 12-mm.
Sheared or cropped edges shall be dressed to a neat workmanlike finish and
shall be free from distortion and burrs.
6.4.2 Hand flame cutting shall be undertaken, only if so permitted by the ENGINEER
and shall only be carried out by an expert in such work. Hand flame cut edges
shall be ground smooth and straight.
6.4.3 Edges of flange cover plates and plates used to form any sections shall be
ground smooth.
6.5.1 Holes in secondary members such as Purlins, girts, lacing bars etc. may be
punched full size through material not over 12 mm thick. Holes shall be clean
cut, without burr or ragged edges. Holes for all other connections shall be
drilled accurately and the burrs removed effectively. Where several parts are
to be connected to very close tolerances such parts shall be first assembled,
tightly clamped together and drilled through.
6.5.2 Sub-punching may be permitted before assembly, provided the holes are
punched 3 mm smaller in diameter than the required size and reamed after
assembly to the full diameter. The thickness of material punched shall not in
such cases exceed 16 mm.
6.5.3 When match drilling is carried out in one operation through two or more
separate parts, these parts shall be separated after drilling and the burrs
removed.
6.5.4 Holes for turned and fitted bolts shall be drilled with diameter equal to the
nominal diameter of the shank or barrel subject to tolerance specified in IS:
919.
6.5.5 Where reamed members are taken apart for transporting or handling, the
respective pieces reamed together shall be so marked that they may be
reassembled in the same position in the final setting up. No interchange of
reamed parts will be permitted. Poor matching, over drilling and ovality in holes
shall be a cause for rejection. Burning holes with gas is strictly prohibited.
6.6 ROLLING AND FORMING
ISSUE
R9
Plates, Channels, Rolled Steel joists etc., for circular bins, bunkers, hoppers,
gantry girders, etc., shall be accurately laid off and rolled or formed to required
profile/ shape as called for on the drawings. Adjacent sections shall be match-
marked to facilitate accurate assembly, welding and erection in the field.
6.7 GRINDING:
Column ends bearing on each other, resting on base plates, compression joints
designed for bearing, base plates coming in contact with column end and cap
plate shall be ground smooth to ensure 90% contact with local gap not
exceeding 0.10 mm (filler gauge shall be used to check this gap). Bottom edge
of knife edge support (bearing stiffener) for crane girder and top of cap plates
where the knife edge supports rest shall also be accurately ground as above.
All ground surfaces shall be protected from dirt and mechanical damages till
the assembly is completed. However, the underside of base plate bearing on
grout need not be machined.
6.8 WELDING
6.8.1 Before the start of the work, welding procedure shall be submitted to
ENGINEER for approval. Welding shall be entrusted to only qualified and
experienced welders who shall be periodically tested and graded as per
relevant standards. The CONTRACTOR shall maintain and update the
welder’s records as and when the tests are conducted.
.
6.8.2 Welding procedure specification (WPS) shall be established and Qualification
of weld procedure (QWP) shall be done as per approved standards. Welders
employed shall also be qualified as per above standards prior to taking up
fabrication. CONTRACTOR shall obtain approval from ENGINEER before the
start of the work.
6.8.4 All welds shall be free from defects like blowholes, lack of penetration,
undercutting, cracks etc. All welds shall be cleaned of slag or flux and show
sections, smoothness of weld metal, featheredges without overlap and freedom
from porosity.
ISSUE
R9
6.8.5 50mm on either side of the surfaces on which weld metal is to be deposited
shall be smooth, uniform, free from fins, tears, burrs, cracks and absolutely free
from grease, paint, loose scale, moisture or any other substance which would
adversely affect quality and strength of weld.
6.8.6 Machining, thermal cutting or grinding may be employed for joint preparation or
removal of unacceptable work or metal. The weld edges shall be smooth &
regular surface, free from cracks & notches. Flame cut material above 50mm
thick shall be pre-heated as per relevant standards prior to flame cutting and
shall be subjected to ENGINEER’s approval.
6.8.7 All weld fit-up shall comply with tolerances specified in the relevant standards.
The parts to be joined by fillet welds shall be brought into close contact as
practicable and within the tolerable limits as per relevant codes & standards.
6.8.8 All tack welds shall be made using qualified procedure and qualified welders.
Any preheat requirement specified in the welding procedure shall also apply to
tack welds. All tack welds shall be examined visually for defects and if found
defective, shall be removed and re-welded. Throat thickness, leg length and
length of tack weld shall be as per IS: 9595.
6.8.10 It is not allowed to turn over and carry over heavy assemblies in tacking
condition in order to control the geometric dimensions to the requirements of
the drawings. The work shall be positioned for flat welding wherever practicable
and overhead weld shall be avoided as far as possible.
6.8.11 In the joints of the parts with dissimilar thickness smooth transition of one part
to the other must be provided by way of the gradual decreasing of the thickness
of the thicker part with the slope of the surface not exceeding 15 degree or 1:5.
6.8.12 Welding shall not be done when the surface of the members are wet or exposed
to rain or high wind velocities unless the welding operator and the work are
properly protected.
6.8.13 In joints connected only by fillet welds, the minimum size of fillet weld to be
used shall be as per IS 9595-1996.
ISSUE
R9
6.8.14 Welds shall be defect free and surfaces shall be thoroughly cleaned to remove
all visible weld defects and extra material.
6.8.15 For all built up sections such as Columns/ girders/ beams, Crane Girders etc.,
welding between web and flange plates shall be carried out by SMAW / SAW
process. Welding shall be continuous and shall be on both sides of the
connecting member. One side fillet weld is not acceptable. Especially for butt
welds of Crane girders full penetration of weld between top of web plate and
top flange shall be ensured.
6.8.16 In general, all welding shall be performed as per the recommendation specified
in IS: 9595-1996.
6.8.17 Pre-heating and Post weld Heat treatment shall be carried out as per the
acceptable standards and procedure and shall have prior approval from the
ENGINEER. The pre-heat and inter pass temperature shall be checked just
prior to initiating the arc for each pass. The weld joint details and procedure for
Pre-heating and Post heating shall be submitted by the CONTRACTOR for
approval from ENGINEER.
6.9.1 Electrodes, filler wires and flux used for welding shall be from approved
manufacturers/Suppliers. CONTRACTOR shall submit the list of Electrode
manufacturers proposed to be procured to the ENGINEER for approval. The
CONTRACTOR shall furnish certification that electrode or electrode flux
combination will meet the requirements of classification. The classification and
size of electrode, arc length, voltage & amperage shall be suited to type and
thickness of material, type of groove, welding positions and other
circumstances attending work.
6.9.2 Only low hydrogen electrodes shall be used for welding 20mm and above thick
plates. All electrodes having low hydrogen covering shall conform to relevant
acceptable standards. These electrodes shall be purchased in hermetically
sealed containers or baked by the user as recommended by electrode
manufacturer. Electrode flux coating shall be sound and unbroken. Broken or
damaged coating shall cause the electrodes to be discarded. Before welding,
the electrodes shall de dried in a holding oven as per manufacturer’s
recommendations. Only limited quantity shall be issued to the welders. The
electrodes shall be kept in “carry ovens” and shall not be exposed to the
atmosphere.
6.9.3 Welding plants and accessories shall have capacity adequate for welding
procedure laid down and shall satisfy appropriate standards and be of
approved make and quality. CONTRACTOR shall furnish and obtain approval
ISSUE
from ENGINEER the details of equipment he proposes to deploy for the works. R9
All the electrical plant in connection with the welding operation shall be properly
and adequately earthed and adequate means of measuring the current shall
be provided. Proper safety rules shall be strictly followed.
7.1 GENERAL.
7.1.5 CONTRACTOR shall provide all the testing and inspection services
and facilities for shop work except where otherwise specified.
7.1.6 For fabrication work carried out in the field, the same standard of
supervision and quality control shall be maintained as in shop
fabricated work. The inspection and testing shall be conducted in a
manner satisfactory to ENGINEER. The inspection and testing on
structural steel members shall be as set forth below:
7.2.2 If mill test reports are not available for any steel materials, the same
shall be got tested by CONTRACTOR to ENGINEER’s satisfaction to
demonstrate conformity with the relevant specification at his own cost.
For materials supplied by OWNER, the cost of such tests will be
reimbursed to CONTRACTOR. Testing shall be conducted at NABL
accredited laboratories or Owner Approved labs.
7.2.3 Raw material with cracks, seams, laps, lamination and heavy pitting are
not acceptable. Ultrasonic testing of plates above 50 mm thick shall
be carried out for the soundness of material, the same shall be got
tested by CONTRACTOR to ENGINEER’s satisfaction to
demonstrate conformity with the relevant specification at his own cost.
For materials supplied by OWNER, the cost of such tests will be
reimbursed to CONTRACTOR.
7.2.5 The CONTRACTOR shall maintain records of all inspection and tests,
which shall be made freely available to the ENGINEER and shall be
submitted to the ENGINEER on completion of each stage of work.
7.3.1 All welds shall be tested for flaws by any of the methods described
under. The choice of the method adopted shall be determined by the
OWNER. Following methods are generally recommended for the
quality control of welded joints:
All fillet welds in general structural steel work shall have their final passes fully
tested by MPT. However, for fillet welds of size 10mm and above and /or critical
areas, the root and final passes shall be tested using MPT. The ENGINEER
shall however decide the requirements of this additional testing. For Complete
penetration butt welds, the root and final passes shall be tested using MPT. All
MPT shall be as per relevant acceptable standards. Defects if found, shall be
repaired and retested. MPT shall be carried out using alternating current only.
ISSUE
Direct current may be used with the permission of the ENGINEER. The cost of R9
All completed full penetration butt welds to a length of about 10% shall be radio-
graphed as per ENGINEER’s directive in accordance with the relevant
acceptable standards. In case of crane girders 100 per cent of the full strength
butt welds shall be inspected by RT. In the case of hoppers of coal bunkers at
least 10% of the circumferential as well as seam welds shall be inspected by
RT or as per mutual agreement in % between the OWNER and
CONTRACTOR.
.
7.3.5 Ultrasonic Testing (UT):
Wherever built up sections for crane runway girders are fabricated, the T-joints
of the sections shall be subjected to ultrasonic testing. 100 per cent length of
the seam as well as circumferential welds of hoppers of coal bunkers shall be
inspected by UT; OR as per mutual agreement between the OWNER and
CONTRACTOR.
.
7.3.6 Acceptance Standard:
The acceptable standards for various weld tests shall be as per ASME Sec IX
or relevant acceptable standards.
7.4.1 Welding shall be carried out as per approved WPS and QWS by
qualified welders.
7.4.2 All welds shall be inspected for flaws by any of the methods
described under clause 7.3; the choice of the method adopted shall
be determined by the ENGINEER.
portion of the weld shall not be allowed more than two (2) times. Portion of the
welding seams, which have been subjected to repair, must be indicated in the
weld inspection reports.
8.1 All the fabricated parts of Structural Steel members shall be inspected at all
stages of fabrication and assembly to verify that dimensions, tolerances,
alignment and surface finish are in accordance with the requirements shown
on the approved CONTRACTOR's shop drawings and/or ENGINEER’s
drawings.
8.2 Fit ups shall be examined by the quality surveyor as per the approved QA plan
prior to welding the joint. All welds shall be inspected for flaws by the method
described under the Clause 7.4 (Inspection Of welds).
8.3 The dimensions of the fit ups shall be maintained as specified in the fabrication
drawings.
8.5 TOLERANCES
9.1 In the event of any failure of welding, structural steel members to meet
inspection or test requirements, the CONTRACTOR shall notify the
ENGINEER or his authorised representative. A design concession request has
to be made and got approved from the ENGINEER or his representative before
repair is undertaken. The quality control procedures to be followed to ensure
satisfactory repair shall be subject to approval by ENGINEER.
ISSUE
R9
9.2 CONTRACTOR shall maintain records of all inspection and testing which shall
be made available to the ENGINEER or his authorised representative, for three
years from the date of completion of the contract.
9.3 The ENGINEER has the right to specify additional testing as he deems
necessary, and the additional cost of such testing shall be borne by the
OWNER only in case of successful testing.
For structures like bunkers, tanks, etc. shop assembly is essential. For other
steel work, such as columns along with the tie beams/bracings may have to be
shop assembled to ensure satisfactory fabrication, obtaining of adequate
bearing areas etc. if so desired by the ENGINEER. All these shop assemblies
shall be carried out by CONTRACTOR at no extra cost to the OWNER.
12.1 After checking and inspection, all members shall be marked for identification
during erection. This mark shall correspond to distinguishing marks on
approved erection drawings and shall be legibly painted and stamped on it.
The erection mark shall be stamped with a metal dye with figures at least 20
mm high and to such optimum depth as to be clearly visible.
12.2 All erection marks shall be on the outer surface of all sections and near one
end, but clear of bolt holes. The marking shall be so stamped that they are
easily discernible when sorting out members. The stamped marking shall be
encircled boldly by a distinguishable paint to facilitate easy location.
12.3 Erection marks on like pieces shall be in identical locations. Members having
lengths of 7.0 m or more shall have the erection mark at both ends.
13.0 ERRORS
Any error in shop fabrication which prevents proper assembling and fitting up
of parts in the field by moderate use of drift pins or moderate amount of
reaming will be classified by the ENGINEER as defective workmanship. In
case ENGINEER rejects such material or defective workmanship, the same
ISSUE
shall be replaced by the materials and workmanship conforming to the R9
15.1 GENERAL.
15.1.1 The ENGINEER shall subject all works and materials covered by this
specification to Inspection.
15.1.2 The CONTRACTOR shall provide free access in his shop during working hours
for the inspection staff, designated by the Engineer, at all phases of the work
and assist them where necessary in conducting the inspection. The
CONTRACTOR shall expeditiously furnish all gauges, instruments and other
necessary measuring equipment required for inspection of the work in the shop.
The shop inspection by the inspector is intended to ensure that the material
and workmanship are in accordance with this specification, but it will not relieve
the CONTRACTOR of any of his responsibilities for the product. The
inspector’s inspection will include, but not be limited to, the following:
15.2 MATERIAL
The inspector will ascertain that only materials conforming to the requirements
of this specification are used.
The ENGINEER will ensure and check that the structural members conform to
the dimensions and tolerances as set out on the drawings and as required by
the specification.
The ENGINEER will witness the welding and testing of any procedure
qualification tests that are required by this specification. The ENGINEER will
also check that welding procedure (including the electrode, flux, current, arc
voltage, speed of travel) used are in accordance with the approved welding
procedures.
The ENGINEER will check the welding equipment to be used for the work to
ensure that it is in such condition as to enable qualified welders to follow the
procedures.
15.6.1 The ENGINEER will permit welding to be performed only by welders and
welding operators who are qualified by tests in accordance with relevant
standards
15.6.2 When the quality of a welder or welding operators’ work, appears to be below
the requirements, the ENGINEER may require testing of his qualifications by
necessary tests.
15.7 WELDS
15.7.1 The ENGINEER will ascertain that the sizes, length and the location of all welds
conform to the requirements of this specification and the approved fabrication
drawings. Temporary welds used for the works shall be removed and ground
flush with the original surface.
15.7.2 The ENGINEER will identify with a distinguishing mark of all parts of the joints
that he has inspected and accepted.
15.7.3 The CONTRACTOR shall comply with all the demands of the ENGINEER to
correct improper workmanship and to remove and replace, or correct as
instructed, all welds found defective or deficient.
15.7.4 In the event of faulty welding or its removal for re-welding results in damage to
the base metal in the judgment of the Engineer, or its retention is not in
accordance with the intent of the plans and specification, the CONTRACTOR
shall remove and replace the damaged materials at his own cost.
16.1 For the purpose of payment, the weight of the actual completed structures
shall be calculated from the approved drawings for different finished structural
elements and for different items of work. The CONTRACTOR shall submit to
the OWNER relevant material list containing weight of each item.
16.2 No allowances will be permitted for bolts, nuts, washers, studs, screws etc.,
galvanizing, welding or for rolling margins. One tonne for the purpose of
payment shall mean ONE METRIC TONNE i.e. 1000 Kg. Permanent bolts,
however, will be considered for payment against the relevant item under
schedule of items.
ISSUE
R9
16.3 The weight of a member made out of standard rolled section such as beams,
channels, angles, etc., shall be based on the standard IS:808 without
deductions for holes, notches, bevel cuts, etc. Where a component consists
of a cut rolled sections, the full weight of the rolled section shall be considered
only if more than half the depth of the original section is used. Otherwise,
only half the section unit weight shall be considered for calculation of the
weight of the components. Deductions shall be made in the weight of
gussets/plates for cuts and notches of 900 sq. cm. or larger.
16.4 For gussets/plates used in trusses, bracings, columns, beams, etc., the area
shall be that of the minimum circumscribing rectangle except as stated in 16.3
above.
The weight of any built-up members shall be based on the weight of each
component.
E N D
ISSUE
R9
1 SCOPE
This specification covers the general requirements for erection of structural
steel. In addition to erection of steel, transportation of fabricated steel from
fabrication yard to storage yard, transportation of associated equipment are a
part of the scope of works. The scope of work also includes supply of tools
and tackles, consumables, materials, labour and supervision and shall also
cover the following:
1.1 Storing and stacking of all fabricated structural components/units/assemblies
at site storage yards till the time of erection.
1.2 Transportation of structures from storage yard to site of erection, including
multiple handling, if required.
1.3 All minor rectifications/ modifications such as:-
i) Removal of bends, kinks, twists etc., for parts damaged during
transportation and handling
ii) Reaming of holes which do not fit properly or which are damaged, for
use of next higher size bolt.
iii) Plug-welding and re-drilling of holes which do not register, and which
cannot be reamed for use of next higher size bolt.
iv) Drilling of holes which are either not drilled at all or are drilled in incorrect
position during fabrication.
1.4 Fabrication of minor missing items as directed by the OWNER.
1.5 Verification of the position of embedded anchor bolts and inserts w.r.t lines
and levels, installed by others based on Geodetic Scheme /Bench
Mark/Reference co-ordinates to be furnished by OWNER.
1.6 Verification of actual dimensions of structures (erected by others) which would
have bearing on the cutting lengths, end connections etc., of those members
which are to be erected under this scope of work.
1.7 Assembly at site of steel structural components wherever required, including
temporary supports and staging.
1.8 Making arrangements for providing all facilities for
i) Conducting Ultrasonic Testing (UT) by reputed testing laboratories
approved by OWNER.
ii) Making available test films / graphs, with reports / interpretation.
1.9 Rectifying at site; damaged portions of shop primer by cleaning and
application of touch-up paint.
1.10 Erection of structures including making connections by bolts/ High strength
Friction Grip bolts / welding as per drawing.
1.11 Alignment of all structures true to line, plumb and dimensions within
specified limits of tolerance.
1.12 Application at site after erection, required number of coats of primer and
finishing paint as per specification.
1.13 Rectification of structures as per preliminary acceptance report and Final
acceptance report.
1.14 All necessary items of work required for satisfactory completion of job on
schedule.
2 APPLICABLE CODES STANDARDS & SPECIFICATIONS
The pertinent clauses of the following Indian Codes, Standards and
Specification (latest editions including all applicable official amendments,
reaffirmations and revisions) shall apply to the material and workmanship
covered by this specification. In the event of conflict of certain requirements
between this specification and the codes referred herein, this specification
shall govern.
It is not the intent to specify herein all the codes and standards required for
the satisfactory completion of work. The list of codes and standards indicates
certain primary codes & standards and not all the codes required for the work
under the contract. It is understood that all the pertinent codes and standards
shall form the part of this specification whether explicitly indicated or not.
Reference codes and standards:
IS 800: 2007 General Construction in Steel –Code of Practice.
(Reaffirmed 2017)
IS 806:1968 Code of Practice For Use Of Steel Tubes In
(Reaffirmed 2017) General Building Construction
IS 808:1989
Dimensions for hot rolled steel beam, column,
(Reaffirmed 2019
channel and angle sections
IS 822:1970 Code of Procedure for Inspection of Welds.
(Reaffirmed 2019
IS1363:2002 Hexagonal Head Bolts, screw and nuts of
Product grade “C” (Parts 1 to 8)
IS 1367:2002 Technical Supply Conditions for threaded
fastener (all parts)
IS 4000:1992 Code of Practice High strength bolts in Steel
(Reaffirmed 2013) Structures.
IS 7205:1974 Safety code for erection of structural steel
(Reaffirmed 2016)
IS 7969: 1975 Safety code for handling and storage of building
(Reaffirmed 2012) Materials
IS:9595:-1996 Metal Arc Welding of Carbon and Carbon
(Reaffirmed 2019 manganese steel.
IS 1182: 1983 Recommended Practice for Radiographic
(Reaffirmed 2017) examination of Fusion Welded Butt Joints in Steel
Plates
ISSUE
R9
3 REGULATORY REQUIREMENTS
The work covered in this specification, shall comply with all relevant
government and local laws, regulations and standards. For subjects not
covered by regulations, codes, standards or specifications, the materials
and construction shall be based on good engineering practice, subject to
approval by OWNER.
4 ERECTION SCHEME
4.1 CONTRACTOR after the award of work shall submit a detailed erection
scheme covering the period of completion of all the works covered under the
specification for ENGINEER’s approval. The erection scheme shall include
but not limited to the following.
i) Methods proposed to be employed for transporting his equipment,
tools, tackles, gas cylinders, electrodes and all that is necessary to
site.
ii) Type, capacity and quantity of equipment that the CONTRACTOR
proposes to bring to site for unloading, transporting within the site,
handling, assembling, hoisting and erecting of the structural steel
components.
iii) Strength and trade wise composition of the work force and supervisory
personnel that will be deployed by the CONTRACTOR for the various
operations.
iv) Erection scheme being adopted for erection of special / complicated
structural elements such as coal bunkers, chimney flue can, main
process building roof trusses etc.
4.2 A brief write-up covering the above activities shall be submitted along with
the bid document by the bidder during submission of his bid.
4.3 Engineer reserves the right to direct the contractor either at the start or
during the contract period, to mobilize additional resources in terms of
labour, material ,equipment, tools and plant etc., at no cost to the owner if in
his opinion that the resources employed by the contractor does not meet the
schedule of completion.
ISSUE
R9
5 ERECTION PROGRAMME
5.1 Within two (2) weeks of acceptance of bid the CONTRACTOR shall submit
a detailed erection programme with dates and estimated completion time for
various parts of the work for ENGINEER’s approval. This programme shall
broadly comprise the following:
i) Layout plan identifying the areas proposed for unloading, main
storage, subsidiary storage and assembly
ii) Transportation of fabricated material between the storage and work
areas.
iii) Layout to indicate the points at which proposed erection begins,
direction in which it is proposed to progress, the deployment of
equipment, access route for cranes to reach work areas, etc.
iv) The locations and extent of site offices and stores, labour quarters if
any.
v) Layout of electrical cables and water pipes from the tap-off points.
vi) Details of the method of handling, transport, hoisting and erection
including false work/staging, temporary bracing, guying, etc. along
with complete details of the quantity and capacity of the various items
of erection equipment that will be used.
vii) Site organization chart showing the number of supervisory personnel,
and the number and composition of the various gangs.
viii) Safety measures to be adopted at site of erection and organization
chart showing safety personnel.
5.2 Any modifications to the erection programme directed by ENGINEER for the
reasons of inadequacy of
i) The quantity and/or capacity of the erection equipment.
ii) Erection personnel and supervisors, temporary bracing, guying etc.,
iii) Safety of the erection methods, or stability of the erected portions of
structures, or unsuitability of the erection sequence due to interference
with the work of other agencies.
iv) Any other unforeseen events which may delay the schedule.
v) Safety measures proposed.
shall be incorporated by CONTRACTOR and the work shall be carried out
in accordance with the revised programme. Approval by ENGINEER shall
not relieve the CONTRACTOR from the responsibility for the safe, sound,
accurate and timely erection of structural steel work as required by
ENGINEER/OWNER. CONTRACTOR shall also make no extra claims for
bringing additional equipment to site for erection, if so directed by
ENGINEER. CONTRACTOR shall be deemed to have visualized all erection
problems while bidding for the work and no additional compensation shall
be claimed on this account.
ISSUE
R9
6 SITE OPERATIONS
6.1 CONTRACTOR shall employ an experienced and qualified graduate
Engineer who shall be in full time charge of the job and responsible for all
site activities.
6.2 CONTRACTOR shall complete all preliminary works at site well before the
arrival of structural steel, such as establishment of a well-equipped and
adequately staffed site office, stores, unloading gantry, unloading and pre-
assembly yard, labour quarters if any, electrical and water connections,
electrical winches, derricks, cranes, compressors, all tools and tackles, rivet
guns, welding sets, torque wrenches, spud wrenches, staging, etc. as well
as experienced erection and supervisory personnel as part of this contract
and any other work that may be necessary so as to start erection
immediately after the arrival of fabricated steel at site.
6.3 CONTRACTOR shall furnish at his own expense, the necessary non-
inflammable staging and hoisting materials or equipment required for the
erection work and shall remove and take them away after completion of the
job. CONTRACTOR shall also provide necessary passageways, fences,
safety belts, helmets, lights and other fittings to the satisfaction of OWNER
/ ENGINEER and to meet the rules of local authorities and for protection to
his men and materials. A licensed electrician shall be kept on the job for the
entire duration of the work to maintain CONTRACTOR’s electrical
equipment and connections.
6.4 CONTRACTOR shall protect all existing plant, structures, piping, conduits,
equipment and facilities against damage during erection. Any damage
caused by CONTRACTOR shall be rectified entirely at CONTRACTOR’s
cost, to the satisfaction of OWNER / ENGINEER. If work has to be carried
out adjacent to existing switch yards or electrical installations which are live,
CONTRACTOR must ensure suitable safety precautions in consultation with
ENGINEER.
6.5 If a portion of the work of the project area cannot be made available to
CONTRACTOR for his activities due to operations being carried out by other
agencies, he shall suitably modify his sequence of operations so as to
continue work without interruption. CONTRACTOR shall work in
coordination with other agencies working on the project site and plan his
work suitably so as not to hinder the progress of construction at site.
6.6 The Suitability and capacity of all plant and equipment used for erection shall
be to the satisfaction of the OWNER/ENGINEER.
7 ACCEPTANCE, HANDLING AND STORAGE
7.1 The fabricated material received at erection site shall be verified with respect
of marking on the key plan / marking plan or shipping list.
7.2 Any material found damaged or defective shall be stacked separately and
the damaged or defective material shall be painted in distinct colour for
identification and the same shall be brought to the notice of ENGINEER.
7.3 No dragging of steel shall be permitted. All fabricated items shall be stored
300mm above ground on suitable packing to avoid damage. It shall be
stored in the order required for erection, with erection marks visible. All
storage areas shall be prepared and maintained by CONTRACTOR. Before ISSUE
R9
storing of Material, the Storage yard shall be marked on the plot plan and
CONTRACTOR shall get approval from OWNER/ ENGINEER.
7.4 Scratched or abraded steel shall be given a coat of primer in accordance with
TCE specification M4-405-04 (painting of structural steel) after unloading and
handling prior to erection. All milled and machined surfaces shall be properly
protected from rust/corrosion by suitable coating and from getting damaged.
8 ANCHOR BOLTS, EMBEDDED PARTS AND FOUNDATIONS
8.1 CONTRACTOR shall carefully check the location, level and layout of anchor
bolts embedded in foundations constructed by others, to ensure that the
structures can be properly erected as shown on the drawings. Any
discrepancy in the anchor bolts/foundation shall be reported to ENGINEER.
8.2 CONTRACTOR shall carefully check the actual dimensions of structures
and the location, level and sizes of embedded parts a) in the RC beam
/column and/ or b) cleats / plates provided in steel beam /column constructed
by others to receive structures covered under this scope of work.
CONTRACTOR shall take note of discrepancies if any and shall report to
ENGINEER and fabricate the structures covered under this contract suitably
before the commencement of erection.
8.3 Levelling of column bases to the required elevation may be done by
providing shims. All shim stock required for keeping the specified thickness
of grout and in connection with erection of structures on foundations, crane
brackets or at any other locations shall be of good M.S. plates and shall be
supplied by CONTRACTOR at his cost.
8.4 A certain amount of chipping/cleaning of foundations and preparing the area
is considered normal and shall be carried out by CONTRACTOR at no extra
cost.
8.5 Where beams bear in pockets or on walls, bearing plates shall be set and
levelled as part of the work. All grouting under column base plates or beam
bearing plates will be carried out by CONTRACTOR, unless the grouting is
specifically excluded from the CONTRACTOR’s scope.
9 ASSEMBLY AND CONNECTIONS
9.1 Field connections may be executed either by bolting, welding or by use of
high strength friction grip bolts as shown in the design and erection
drawings.
9.2 All bolts, nuts, washers, rivets, electrodes required for field connections shall
be supplied by CONTRACTOR free of cost. The materials shall have prior
approval from the OWNER /ENGINEER and necessary test certificates shall
be furnished for ENGINEER’s approval. Materials shall be procured from
reputed manufacturers with prior approval from OWNER /ENGINEER
9.3 All assembling shall be carried out on a level platform.
9.4 For frames especially in bolted construction, controlled assembly shall be
carried out in shop before material is sent to site to check the adequacy of
fit of the structural components.
9.5 Drifts shall be used only for drawing the work to proper position and must
not be used to such an extent as to damage the holes. Size of drifts larger
ISSUE
R9
than the nominal diameter of hole shall not be used. Any damaged holes or
burrs must be rectified to the satisfaction of ENGINEER.
9.6 Corrections of minor misfits and reasonable amount of reaming shall be
considered as a part of erection. Any error in the shop, which prevents
proper fit on a moderate amount of reaming and slight chipping or cutting,
shall be immediately reported to ENGINEER.
10.0 ERECTION
10.1 Erection work shall be taken up after receipt of clearance from the
ENGINEER.
10.2 All structural steel shall be erected as per approved Design / fabrication
drawings.
10.3 For safety requirements during erection, provisions of IS: 7205, IS: 7969, IS:
800 and other relevant codes shall be strictly followed. The safety plan to be
prepared by CONTRACTOR and any erection activities shall start only after
getting approval from Owner/ Engineer on the safety plan.
10.4 Erection shall be carried out with the help of maximum mechanization
possible.
10.5 Prior to commencement of erection, all the erection equipment, tools,
tackles, ropes etc., shall be tested for their load carrying capacity. Such tests
may be repeated at intermediate stages also if considered necessary.
Frequent visual inspection shall be done of all vulnerable areas and
components to detect damages or distress in the erection equipment, if any.
10.6 Temporary bracing, whenever required, shall be provided to sustain forces
due to erection loads, equipment etc. Erected parts of the structure shall
remain stable during all stages of erection when subjected to action of wind,
dead weight, erection forces etc. Such bracings shall be left in place as long
as may be required for safety and stability. Specified sequence of erection
of vertical and horizontal structural members shall be followed. After
completion of all permanent member erection and alignment, the temporary
bracing shall be removed.
10.7 Erected members shall be held securely in place by bolts to take care of
dead load, wind / seismic load and erection load.
10.8 All structural members shall be erected with erection marks in the same
relative position as shown in the appropriate erection and shop drawings.
10.9 All connections shall achieve free expansion and contraction of structures
wherever provided.
10.10 No final bolting or welding of joints shall be done until the structure has been
properly aligned and approved by ENGINEER.
10.11 For positioning beams, columns and other steel members, the use of steel
sledges is not permitted.
10.12 Instrumental checking of correctness of initial setting out of structures and
adjustment of alignment shall be carried out in sequence and at different
stages as required using precision survey instruments. The final levelling
and alignment shall be carried out immediately after completion of each
section of a building.
ISSUE
R9
10.13 The CONTRACTOR shall design, manufacture, erect and provide false
work, staging, temporary support, etc., required for safe and accurate
erection of structural steelwork and fully responsible for the adequacy of the
same.
10.14 The CONTRACTOR shall also provide facilities such as adequate temporary
access ladders, gangways, tools & tackles, instruments etc., to OWNER for
his inspection at any stage during erection.
10.15 Proper size steel cable slings, etc., shall be used for hoisting. Guys shall
not be anchored to existing structures, foundations, etc. unless so permitted
by ENGINEER in writing. Care shall be taken to see that ropes in use are
always in good condition.
10.16 Steel columns in the basement, if any, are to be lowered and erected
carefully with the help of a crane and/or derrick without damaging the
basement walls steel or floor.
10.17 Structural steel frames shall be erected plumb and true. Frames shall be
lifted at such points that they are not liable to buckle and deform. Trusses
shall be lifted only at node points. Trusses which are very slender in the
lateral direction shall be provided with temporary lateral supports till the
horizontal bracings are erected. All steel columns and beams shall be
checked for plumb and level individually before and after connections are
made.
10.18 Chequered plates shall be fixed to supporting members by welding or by
countersunk bolts as shown/specified in relevant drawings and/or as
directed by ENGINEER. The edges shall be made smooth and no burrs or
jagged ends shall be left. While splicing, care should be taken so that there
is continuity in pattern between the two portions. Care should also be taken
to avoid distortion of the plate while welding. The erection of chequered
plates shall include:
a. Welding of stiffening angles/vertical stiffening ribs as per drawings
b. Cutting to size and making holes to required shape wherever
necessary to allow service lines such as piping, cables etc., to pass
through
c. Splicing as shown in relevant drawings
d. Smoothening of edges
e. Fixing of chequered plates by welding and/or countersunk bolts
f. Providing lifting hooks for ease of lifting.
10.19 Cutting, heating or enlarging holes may be carried out only with prior written
approval from the ENGINEER.
11.0 FIELD CONNECTIONS:
11.1 ASSEMBLY BY PERMANENT BOLTS:
11.1.1 The number of washers on permanent bolts shall not be more than two (2)
and not less than one (1) for the nuts and one (1) for the bolt head.
ISSUE
R9
11.1.1 Only wooden rams or mallet shall be used in forcing members into position
in order to protect the metal from injury or shock.
11.1.2 Where bolting is specified on the drawing, the bolts shall be tightened to the
maximum limit. The threaded portion of each bolt shall project through the
nut by at least one thread. Tapered washers shall be provided for all heads
and nuts to achieve uniform bearing on sloping surface.
11.1.3 To prevent loosening of nuts, spring washers or lock-nuts shall be provided
as specified in the design / shop drawings.
11.1.4 All machine fitted bolts shall be perfectly tight and the ends shall be checked
to prevent nuts from becoming loose. No unfilled holes shall be left in any
part of the structure.
11.2 ASSEMBLY BY WELDING:
11.2.1 All field assembly by welding shall be executed in accordance with the
requirements for shop fabrication. Where the steel has been delivered
painted, the paint shall be removed before field welding for a distance of at
least 50 mm on either side of the joints to be welded.
11.2.2 All other requirements of welding and its acceptance standards shall be in
accordance with clauses specified in TCE.M4-405-01(Supply and
Fabrication of structural steel).
11.3 ASSEMBLY BY HIGH STRENGTH FRICTION GRIP BOLTS (HSFG
BOLTS)
11.3.1 Assembly of structures with HSFG bolts shall conform to IS:4000
11.3.2 The mating surface shall be prepared in accordance with the requirements
of design in order to achieve required properties to develop adequate friction
between the surfaces.
11.3.3 The mating surfaces shall be absolutely free from grease, Lubricant, dust,
rust etc., and shall be thoroughly cleaned before assembly.
11.3.4 The nuts shall be tightened up to the specific torque with the help of torque-
wrench or by half-turn method with the help of pneumatic wrench lever.
11.3.5 The direction of tightening of the nuts shall be from the middle towards the
periphery of assembly.
11.3.6 After desired tightening the bolt heads, nuts and edges of the mating
surfaces shall be sealed with a coat of paint to obviate entry of moisture.
12 INSPECTION
ENGINEER/OWNER or their authorised representatives shall have free
access to all parts of the job during erection and all erection shall be
subjected to their approval. In case of faulty erection, all dismantling and re-
erection required will be at CONTRACTOR's cost. No paint shall be applied
to rivet heads or field welds or bolts until these have been approved by
ENGINEER.
ISSUE
R9
13 TOLERANCES
Tolerances mentioned below shall be achieved after the entire structure or
part thereof is in line, level and plumb. The tolerances specified below do
not apply to steel structures where the deviations from true position are
intimately linked with and directly influence technological process. In such
cases, the tolerances on erected steel structures shall be as per
recommendations of process technologists/suppliers which will be indicated
in the drawings.
13.1 COLUMNS
13.1.1 Deviation of column axes at foundation top level with respect to true axes
ISSUE
R9
2 mm subject to grinding of
Relative shift of crane rail surfaces at a joint
13.3.8 surfaces for smooth
in plan and elevation
transition.
Relative shift in the location of crane stops 1/1000 of track gauge S in
13.3.9 (end buffers) along the crane tracks with mm subject to maximum of
track gauge S in mm 20 mm
13.4 CHIMNEYS AND TOWERS
Out of plumbness (verticality) from the true 1/1000 of the height of the
13.4.1
vertical axis chimney or tower in mm
13.5 BUNKERS
Deviation in length of bunker from true
13.5.1 ± 1/1000 of length in mm
length
13.5.2 Deviation in width of bunker from true width ± 1/1000 of width in mm
Deviation in height of bunker from true
13.5.3 ± 1/500 of height in mm
height
Deviation in diagonal length in any
± 1/500 of diagonal length in
13.5.4 horizontal cross section from the true
mm
diagonal length
14 PAINTING
14.1 After steel has been erected, all bare and abraded spots, field welds, bolt
heads and nuts shall be spot painted. Before paint is applied, the surface
shall be dry and free from dust, dirt, scale and grease. Surface preparation
and painting of steel surfaces shall be in accordance with painting
specification.
15 SAFETY
15.1 GENERAL REQUIREMENTS:
The Following general safety aspects shall be ensured by the
CONTRACTOR at his cost in addition requirements of IS800 section 17:-
a) As per Safety, Health and Environment (SHE) Plan all staff members
and workers are required to under-go medical check-up prior to their
induction to the plant to ensure fitness.
b) Ensure that all the workmen & supervisory staff engaged on the job are
authorised category wise by the competent authority.
c) Ensure that the persons to be deployed for working at height have
undergone height phobia check and are declared fit by Registered
Medical Practitioner.
d) Ensure that all the persons have undergone Safety Induction Training.
e) Ensure usage of personnel protective equipment / clothing by all as per
job requirement.
f) Ensure use and provision of Full Body Safety harness / safety belts with
double hooks, regular scaffoldings with minimum square floor grills or ISSUE
R9
chequered plates, proper toe guards, hand railing and minimum two
access / approach ladders, provision of lifeline where anchoring of
safety belts to permanent nearby structures is not feasible, fall arrestors,
safety nets etc. for working at height.
g) Ensure full compliance to the general safety requirement specified in
"Safety Manual” .
h) Ensure that workmen are briefed about the hazards involved and
precautions to be taken i.e. tool box talks are conducted.
i) Ensure the worthiness of all construction equipment, hand tools, power
tools, hardware, and all lifting tackles i.e. these are tested and certified
and the latest valid load test certificates are available for safe working
load by Government approved Competent Authority. The physical
condition certificate from Government approved Competent Authority
should also be available.
j) Ensure that all electrical installations have proper earthing of all non-
current carrying parts.
k) Ensure that all electrical installations are having devices like earth
leakage current breaker (ELCB) for cutting off the power supply in the
event of any leakage.
l) Ensure that all electrical power hand tools are regularly checked and
are equipped with Safety Guard to isolate moving parts and also to
inspect and ensure that the handles are having proper insulation without
any damage whatsoever.
m) Ensure that storage, handling and usage of Oxy – acetylene gas
cylinders are strictly as per safety requirements like; the Cylinders are
in trolleys duly chained and in upright condition, only regular keys,
handles and spanners are used for operating valves, regulators etc.,
that hood / canopy is provided and regular lighters are only used for
initial ignition.
n) Ensure no lifting Ropes are near electrical equipment or electrical wire.
The lifting ropes should be free from any contact of electrical
applications.
15.2 SPECIFIC REQUIREMENTS:
The following specific safety requirements shall be ensured by
CONTRACTOR at his cost:-
a) Ensure that complete methodology to the last details of assembly and
erection at site is prepared in advance, submitted for review and
approved by ENGINEER before start of erection.
b) Ensure that proper relevant work permit is obtained for working in
operational area.
c) Ensure 100 % supervision by competent & experienced Supervisor,
Engineer & Safety Officer.
d) Ensure that working at height is limited to daylight only.
e) Ensure proper barricading / cordoning of the erection work space to stop
unauthorised persons from entering the area. Display regular safety ISSUE
R9
ISSUE
R9
1.0 SCOPE
1.1. This specification covers the general requirements of materials, surface preparation,
application method, quality requirements and measurement requirements for shop and
field painting for Structural Steel works using hot/ cold rolled steel sections and tubular
members joined by using bolting and/ or welding. The term painting covers all types of
organic and inorganic coating for anti-corrosive protection of steel structures and
including floor plates.
1.2. Surfaces considered for paint application refer to carbon steel surfaces subjected to
atmospheric exposure or exposure to corrosive environment. Paint is to be applied
after specified surface treatment has been carried out. Steel surfaces in bond with
concrete shall not be painted.
1.3. Paint application shall ensure continuous adherent organic/ inorganic coating film of
specified thickness on the prepared surface to protect it from exposure to environment.
FILENAME: M4-405-04-REV-07.DOCX
Proprietary Notice and Version Control
This document contains confidential information for use only by the “Client”; for the Project under consideration, which is provided for the sole purpose of permitting the recipient to evaluate the information
submitted herewith. In consideration of receipt of this document; unless agreed to in contrary in the Contract; the recipient agrees to maintain such information in confidence and to not reproduce or otherwis e
disclose this information to any person outside the recipient’s organisation; except that there is no obligation to maintain the confidentiality of any information which was known to the recipient prior to receipt of
ISSUE
such information from Tata Consulting Engineers Limited, or becomes publicly known through no fault of recipient, or Tata Consulting Engineers Limited, or is received without obligation of confidentiality from
a third party owing no obligation of confidentiality to Tata Consulting Engineers Limited. All information given under this version over rides all and any kind of offers, assumptions, deliverables and contracts
R7
submitted verbally (and subsequently communicated in writing) or in writing or otherwise given under any and all previous versi on/s.
2.0 EXCLUSIONS
This specification shall cover all structural steel section either rolled, fabricated or
structural tubes and hollow sections. It excludes paintings of the following structures
/equipment.
i. Mechanical & electrical equipment and parts.
ii. Technological Structures
iii. Buried & Overhead piping works
iv. Storage tanks
v. Insulated parts
vi. Interior surfaces of structural tubes and hollow sections
vii. Electroplating of steel surfaces
viii. Any other items of work specifically excluded in the scope of works.
3.0 APPLICABLE CODES, STANDARDS
The pertinent clauses of the following Indian / International Codes, Standards and
Specification (latest editions including all applicable official amendments,
reaffirmations and revisions) shall apply to the material and workmanship covered by
this specification. In the event of the conflict of certain requirements between this
specification and the codes referred herein, this specification shall govern.
It is not the intent to specify herein all the codes and standards required for the
satisfactory completion of work. The list of codes and standards indicates certain
primary codes & standards and not all the codes required for the work under the
contract. It is understood that all the pertinent codes and standards shall form the part
of this specification whether explicitly indicated or not.
The codes and standards shall be latest as on the day of award of contract of the works
unless otherwise specified. Contractor shall be responsible to inform to the Consultant/
Owner in case of any revisions/re-affirm/amendment in the relevant codes and
standards after the date of award of contract within 30 days of the issue of such
revision/re-affirm/amendment of the code/ standard. Consultant/ Owner may approve
use of the earlier code/ standard if the revisions do not materially affect the statutory
requirements of the project or does not impact safety practices. Any cost impact arising
out of such revisions shall be mutually agreed.
ISSUE
R7
ISSUE
R7
4.1 The work covered in this specification, shall comply with all relevant government and
local laws, regulations and standards. For subjects not covered by regulations, codes,
standards or specifications, the materials and construction shall be based on good
engineering practice, subject to approval by Owner. Contractor shall submit Material
Safety Data Sheet (MSDS) of all materials proposed to be used in the project.
4.2 CONTRACTOR shall ensure that all health and safety regulations are adopted for the
erection of scaffolding and use of the selected paint material.
4.3 All necessary precautions shall be taken to ensure the safety of personal and property.
Extreme caution shall be used when working with oil or oil-based paints, cleaning fluids
etc., especially near oxygen piping or oxygen equipment. Heavy concentrations of
volatile or toxic fumes must be avoided and in confined areas, blowers or exhaust fans
shall be used.
4.4 The instructions of the paint manufacturer shall be followed regarding storage, surface
preparation, mixing and thinning of paints, paint application, timing between coats and
safety instructions.
4.5 Rags and other waste material soiled with paints, thinners or solvents shall be kept in
tightly closed metal containers while on the jobsite and when not in use. Legal disposal
of waste materials outside plant site premises is Contractor’s responsibility.
4.6 Lead being hazardous material it is recommended to use lead free paint as per
requirement of clause 3.6 of IS158.
ISSUE
R7
ISSUE
R7
descalers, needle guns and rotary descalers. The method is applied after cleaning of
oil and grease by solvent cleaning and removal of loose rust by hand tool cleaning.
The minimum acceptable standards in case of power tool cleaning shall be in
accordance with ISO 8501- St3 / SSPC-SP3.
The tools shall be used carefully to avoid formation of edges and burrs, excessive
roughening of surface and burnishing to smooth slick surface. This method will not
remove rust or firmly adherent mill-scales.
6.1 PROCUREMENT
All types of paints required for the work shall be as per the requirement of relevant
codes and procured from reputed manufacturers. Contractor shall obtain the detailed
list of approved paint manufacturers from the ENGINEER before initiating the
procurement action. The contractor shall also provide technical data sheet, material
ISSUE
R7
safety data sheet and test reports from manufacturer for the specific paints to be
selected. The data sheet shall indicate relevant standards, composition in weight per
cent of pigments, VOC, additives, drying time, viscosity, spreading rate, flash point,
method of application, quality of surface preparation required, corrosion resistance
properties and colour.
6.2 STORAGE
The Paint material shall be stored strictly in accordance with the instructions of the
paint manufacturer. In general painting materials should be stored in dry, cool, well
ventilated and frost-free area and free from source of electrical sparks. Containers at
time of use shall have legible labels showing paint identification, manufacturing date,
batch number, order number and special instructions. Containers shall only be opened
at the time of use. Paints which have livered, gelled or otherwise deteriorated during
storage shall not be used. Paints that have crossed the shelf life should not be used
without inspection and approval by Owner.
6.3 PACKING
All paints delivered to the fabrication shop / site shall be in original sealed container,
as packed by the manufacturer. Paint containers shall clearly be marked with paint
manufacturer’s name, batch number, date of manufacture, shelf life and a clear
indication of the type and colour of the product.
6.4 MIXING
Paint shall be thoroughly mixed prior to application. Mixing shall be done in a well-
ventilated, clean and dust -free area. Paint shall be mixed by non-sparking, low speed
paint mixer or rolling rigs except for containers smaller than 20 litres, until a uniform
consistency is achieved as recommended by manufacturer. Mixing by air bubbling is
not permitted.
Multiple pack paint materials shall be mixed in accordance with and under the
conditions as specified by the paint manufacturer. Pot life as specified by the paint
manufacturer shall be strictly followed.
ISSUE
R7
Engineer reserves the right to request CONTRACTOR for the following tests to be
carried out on samples of paint from standard laboratories identified by Owner.
Engineer reserves the right to test the paint material either before the commencement
of work or during the progress of work; if in his opinion the paints supplied are of inferior
quality and does not meet the code requirements.
i. Pull off test as per IS 101 Part 5 Sec 2: 1988 (R2019)
ii. Abrasion resistance test as per IS 101 Part 5 Sec 2: 1988 (R2019)
iii. Impact resistance test as per IS 101 Part 5 Sec 3: 2019
ISSUE
R7
ii. Round, Oval (IS:487) or Wide flat brushes (IS:384) shall be used depending
upon the surface irregularity, rough or pitted steel, large flat painting areas etc.
Width of brushes shall not in general exceed 125mm.
iii. Short strokes shall be used for paint application depositing uniform amount in
each stroke and the paint brushed into all surface irregularities, crevices,
corners. This shall be followed by long and light strokes at right angles to first
coat.
iv. There shall be a minimum of brush marks left in the applied paint.
v. Brush painting shall be done for edges, corners and weld joints as a stipe coat.
vi. Surfaces not accessible to brushes shall be painted by spray.
7.2 ROLLER APPLICATION
Roller coat will be used only when specifically authorised. Suitable rollers of different
nap length to suit varying surface roughness shall be used. Rollers are not generally
recommended for application of primers. Roller application shall only be used if the
first or priming coat of paint has been applied by brush or other means. Manufacturer’s
recommendation shall be strictly followed for roller applied paints.
7.3 SPRAY APPLICATION
7.3.1 Airless or pneumatic/ Air- spray application shall be in accordance with the following
i. Airless spray application shall be as per steel structure paint Manual Vol 1 &Vol 2
SSPC, USA.
ii. Spraying shall be carried out keeping the spray gun at the minimum suitable
distance from the work piece and consistently at 90 0 to the surface being painted.
iii. Correct spray tips, air pressures etc., as recommended by the equipment supplier
shall be adopted.
7.3.2 Air spray application shall be in accordance with the following:
i. The equipment used shall be suitable for the intended purpose, shall be capable
of properly atomizing the paint to be applied, and shall be equipped with suitable
pressure regulators and gauges.
ii. Appropriate pressure and nozzles shall be those recommended by the
manufacturer of the equipment for the material being sprayed. The equipment shall
be kept in satisfactory condition to permit proper paint application.
iii. Correct combination of air volume, air pressure and fluid flow to give good
atomization shall be ensured to get a defect free painted surface.
iv. Traps or separators shall be provided to remove oil and condensed water from the
air. These traps or separators must be of adequate size and must be drained
periodically during operations. The air from the spray gun impinging against the
surface shall show no condensed water or oil.
v. Ingredients shall be kept properly mixed in the spray pots or containers during
application by continuous mechanical agitation.
vi. Spray equipment shall be kept sufficiently clean so that dirt, dried paint and other
foreign materials are not deposited in the paint film. Any solvents left in the
ISSUE
R7
equipment shall be completely removed before applying paint to the surface being
painted.
7.3.3 Selection of type of spray application shall depend upon the type of paint coating being
used. At all times paint manufacturer’s recommendation shall be strictly followed.
8.0 COATING PROCEDURE
8.1 COMPATIBILITY
General Compatibility between primer, intermediate and top coats, as applicable for
individual painting system shall be established through the paint manufacturer
supplying the paints. Primer and finishing paint for the entire project shall be procured
from the same manufacturer. Mixing of material from different manufacturers is strictly
prohibited.
8.2 Surface shall not be coated in rain, high wind, when steel surface temperature is less
than 50 C, or when the relative humidity is greater than 85%.
8.3 Applied paint system shall be allowed to cure at ambient and surface temperatures
between 10 ° C and 60 ° C with relative humidity below 85%. All paint shall be air cured.
8.4 A suitable test area (approx.0.5 m2) shall be painted with agreed paint system. The
test area shall be fully coated with all coats of the agreed coating system using the
tools and equipment to be used for the actual coating work. The painted test area shall
be maintained for the duration of the project. Painting on test piece shall be carried out
such that all the coats shall be made visible for reference at all time.
8.5 Structural steel shall preferably have prime coat and intermediate coat applied at shop,
prime coat shall be applied immediately after surface preparation and preferably within
the time as specified elsewhere in the specification. Subsequent finish coats shall be
carried out at site after the alignment and erection is complete. Portions of structural
steel members to be embedded into the concrete shall not be painted.
8.6 Surfaces inaccessible after assembly shall receive full coating/painting system prior to
assembly.
8.7 Surfaces inaccessible after erection, including top surfaces of floor beams supporting
grating / chequered plate /RC Slabs shall receive one additional coat of finish paint
over and above the number of coats specified prior to erection.
8.8 Welding edges and joint zone shall be also shop painted except if the paint is harmful
to welding operator. In such case the zone shall be coated with epoxy based weldable
blast primer for 50mm wide patch and covered with adhesive tape before full coat of
shop paint is applied on the work piece and the tape removed.
8.9 Site paint shall be applied after assembly and erection of fabricated structures.
Defective shop coat shall be cleaned and touched up with same paint as applied in
shop. Damaged shop coat shall be repaired including paint removal, surface
preparation to St3 quality and painting to satisfaction of Engineer. The erected
structure shall then be painted with intermediate coat (if applicable) and finish coat.
8.10 Field welds and areas within 50mm of welds shall be cleaned to required surface
quality before painting. Welds shall be blast cleaned, power wire brushed, chemically
scrubbed or solvent cleaned depending on nature of weld deposits.
8.11 Each coat of paint material shall be applied as continuous film of uniform thickness;
free of holidays and pin holes. Any spot or areas missed in application shall be recoated
ISSUE
R7
and permitted to dry before the next coat is applied. Applied paint should have the
desired wet film thickness.
8.12 Each coat shall be in proper state of cure or dryness before the application of
succeeding coat. Material shall be considered dry for recoating when an additional coat
can be applied without development of any detrimental film irregularities, such as lifting
or loss of adhesion of the under coat. Manufacturer’s instruction shall be strictly
followed for intervals between successive coats.
8.13 No paint shall be force dried under conditions which will cause checking, wrinkling,
blistering and formation of pin holes or detrimentally affect the condition of the paint.
8.14 No drier shall be added to paint on the job unless specifically called for in the
manufacturer's specification for the paint.
8.15 Paint shall be protected from rain, condensation, contamination, snow and freezing
until dried to the extent practicable.
8.16 Blast cleaned surface shall be coated with one coat of primer before surface
degradation occurs but in no case later than 2hrs. Irrespective of the method of surface
preparation, the first coat of primer shall be applied not later than 2-3 hours after
preparation and on dry surface.
8.17 When the successive coat of the same colour is specified, alternate coat shall be tinted
as far as practicable; sufficient to produce enough contrast to indicate complete
coverage of the surface. The tinting material shall be compatible with the material and
not detrimental to its service life. However, it is always preferable to have multiple
colours instead of tinting.
8.18 All field welded areas on shop painted item shall be mechanically cleaned using power
tool (including the weld area proper, adjacent areas contaminated by weld spatter or
fumes and areas where existing primer, intermediate / finishing paint is burnt) so as to
expose bare metal. All areas close to welds shall then be solvent cleaned.
Subsequently, new primer and finishing coats of paint shall be applied as per painting
specification.
8.19 Care shall be taken to protect adjacent equipment, piping, structures etc., from spillage
and spatter during field painting by use of adequate temporary covers. If surfaces are
accidentally spattered or sprayed, the paint shall be immediately and thoroughly
removed. For cleaning of spillages an inert absorbent material shall be used
8.20 All structures shall receive appropriate number of primer, intermediate and finishing
coats in order to achieve overall DFT as per the drawings / specifications/ data sheets.
9.0 PAINTING SYSTEM
The types of paints to be used for primer, intermediate and finish coats are specified
in TABLE-1. The recommended painting system of all Structural Steel Works covering
surface preparation, application of Primer coats, Intermediate coats (if specified) and
Final coats to develop required minimum DFT shall be indicated separately. User shall
specify selected painting system for the various structures in Specific Technical
Requirement DATA SHEET A of tender document in prescribed format.
ISSUE
R7
12.1 As part of the Quality Assurance, a final inspection in the presence of the
representatives of OWNER and CONTRACTOR shall be conducted prior to the final
acceptance of the paintwork. Part of this final inspection checks shall be
i. Visual check of the appearance to ensure the painted surface is free from
sagging, holidays, cracking, blistering, pin holes etc.
ii. Checks on DFT’s of the total applied coating system
iii. Shade verification
iv. Holiday Testing
v. Scratch Test
ISSUE
R7
ISSUE
R7
i. For structures with surface area less than 30 sqm, each 10 sqm shall be
measured
ii. For structures less than 100 sqm in area, three 10 sqm areas randomly
selected
iii. For structures exceeding 100 sqm in area, first 100 sqm shall be measured as
in (ii) above and one 10 sqm selected randomly for each 100 sqm increment
iv. Additional measurements required when DFT value in any 10 sqm area does
not comply requirements.
13.0 DOCUMENTATION
Contractor shall keep records and furnish the following documents to the Owner
i. A written quality plan with procedure for qualification trials and for the actual
work.
ii. Daily progress report with details of weather conditions, particular of
applications, number of coats and type of material applied, anomalies, progress
of work versus program.
iii. Results of measurement of temperatures, relative humidity, surface profile, film
thickness, holiday detection, adhesion tests with signature of appropriate
authority.
iv. Particulars of surface preparation and paint application during trials and during
the work.
v. Details of non-compliance rejects and repairs.
vi. Type of testing equipment and calibration.
vii. Code and batch numbers of paint materials used, including shelf life.
viii. Visual examination of surface preparation compared with the standards.
ix. Profile check of the prepared surface with suitable “profilometer”.
x. Dry film thickness check of intermediate and final coating layers, in accordance
with the specification and/or paint manufacturer’s recommendation
xi. Checks/ tests carried out as per clauses above.
14.0 GUARANTEE
14.1 The paint system shall provide sufficient protection of the underlying steel surface
against the attack of the environment, other than mechanical damage, chemical
spillage as result of operational activities or other unusual occurrences from the outside
caused by others.
14.2 The CONTRACTOR is fully responsible for the quality of the work and for all related
QA/QC activities as indicated in the specification.
14.3 The CONTRACTOR shall guarantee quality of their coating works for the period
specified in Data Sheet-A and for the coating condition specified therein.
14.3.1 The guarantee period starts from the date of acceptance of CONTRACTOR’s paint
work.
ISSUE
R7
14.3.2 Initial acceptance of any new coating work by OWNER will not release the
CONTRACTOR of his obligation under this section until final inspection has been
carried out and acceptance of the completed work has been agreed in writing.
14.3.3 These guarantee clauses regarding coating specifications are prevailing and
supersede the warrantee requirements in General Conditions of Contract.
15.0 MEASUREMENT
15.1 Painting work shall not be measured separately, if primer painting and/or primer and
finish painting are already included in the scope of item of structural steel works which
include supply, fabrication, painting and erection of structural steel and work is
measured on the weight basis for payment.
15.2 In cases where primer and/or finish painting work as specified is carried out on erected
structural steel executed by a different agency, the method of measurement for
painting shall be on the basis of tonnage of the steel erected. For this purpose, the
tonnage of erected steel as certified for payment to the different erection agency shall
be considered as the basis and no measurement will be carried out separately.
ISSUE
R7
END
ISSUE
R7
1. SCOPE
Contractor shall ensure that the surface runoff outside the excavated pit
/working area shall be collected through a catch water drain excavated
around the working area and led away to a natural stream, at no extra cost
to the owner .Contractor shall maintain the catch water drains in proper
condition during the construction period at no extra cost to the owner.
ISSUE
R0
ISSUE
R0
1 SCOPE
1.1 This specification covers the general requirements for civil and architectural
works comprising of masonry, flooring, skirting, dado, plastering for wall and
ceilings, painting, doors, windows, ventilators, Builders hardware,
ironmongery, Glass and glazing, Partition works, False ceiling works, toilet
cubicles, sanitary fixtures and fittings, water proofing, Metal sheet cladding,
grills and railing works.
1.2 The works under this specification shall consist of furnishing of all tools,
plants, labour, materials, and everything necessary for execution.
2 MASONRY WORK
2.1 GENERAL
ISSUE
R4
IS:2185 - Specification for concrete masonry units (Parts 1,2 & 3).
2.3.1 MATERIALS
2.3.1.1 Stones for the works shall be of the type specified such as granite, trap,
ISSUE
sandstone, quartzite, etc. and shall be obtained from quarries, R4
2.3.1.3 Cement-sand mortar for stone masonry works shall be in the proportion
of 1:6 unless otherwise specified in the respective items of work. Sand
for masonry mortar shall conform to IS:2116. The sand shall be free
from clay, shale, loam, alkali and organic matter and shall be of sound,
hard, clean and durable particles. Sand shall be approved by
ENGINEER. If so directed by the ENGINEER, sand shall be screened
and washed till it satisfies the limits of deleterious materials.
2.3.1.4 For preparing cement mortar, the ingredients shall first be mixed
thoroughly in dry condition. Water shall then be added and mixing
continued to give a uniform mix of required consistency. Mixing shall
be done thoroughly in a mechanical mixer, unless hand mixing is
specifically permitted by the ENGINEER. The mortar thus mixed shall
be used as soon as possible, preferably within 30 minutes from the time
water is added to cement. In case, the mortar has stiffened due to
evaporation of water, this may be re-tempered by adding water as
required to restore consistency, but this will be permitted only upto 30
ISSUE
minutes from the time of initial mixing of water to cement. Any mortar R4
2.3.2 WORKMANSHIP
2.3.2.1 For all works below ground level the masonry shall be random rubble
un-coursed with ordinary quarry dressed stones for the hearting and
selected quarry dressed stones for the facing. Stones having sharp
corners or round surface shall not be used.
2.3.2.2 For all works above ground level and in superstructure the masonry
shall be random rubble un-coursed, well bonded, faced with hammer
dressed stones with squared quoins at corners. The bushings on the
face shall not be more than 40 mm on an exposed face and on the face
to be plastered it shall not project by more than 12 mm nor shall it have
depressions more than 10 mm from the average wall surface.
2.3.2.3 Face stones shall extend back sufficiently and bond well with the
masonry. The depth of stone from the face of the wall inwards shall not
be less than 2/3 the thickness of wall. The length of the stone shall not
exceed three times the height and the breadth on base shall not be
greater than three-fourths the thickness of wall nor less than 150 mm.
The height of stone may be upto a maximum of 300 mm. Hearting
stones shall not be less than 150 mm in any direction and shall be
bedded in mortar. Stones shall be laid with its grains horizontal.
2.3.2.4 Chips and spalls shall be used wherever necessary to avoid thick
mortar joints and to ensure that no hollow spaces are left in the
masonry. The use of chips and spalls in the hearting shall not exceed
20 percent of the quantity of stone masonry. Spalls & chips shall not be
ISSUE
R4
used on the face of the wall and below hearting stones to bring them to
the level of face stones.
2.3.2.5 The maximum thickness of joints shall not exceed 20 mm. All joints
shall be completely filled with mortar. When plastering or pointing is not
required to be done, the joints shall be struck flush and finished as the
work proceeds. Otherwise, the joints shall be raked to a minimum
depth of 20 mm by a raking tool during the progress of the work while
the mortar is still green.
comprising of one part of mortar as used for masonry and two parts of
graded stone aggregate of 20mm nominal size. The masonry in
structure shall be carried uniformly. Where the masonry of one part is to
be delayed, the work shall be racked back at an angle not steeper than
450. Height of wall raised in any one day shall not exceed one metre.
2.3.2.8 Green work shall be protected from rain by suitable covering. Masonry
work shall be kept constantly moist on all the faces for a minimum
period of seven days for proper curing of the joints.
2.3.2.10 CONTRACTOR shall note that the unit rates quoted for the
masonry work shall be deemed to include for the installation of
miscellaneous inserts such as pipe sleeves, bolts, steel sections with
anchors etc. and providing pockets, leaving openings, cutting chases
etc. in accordance with the construction drawings. Miscellaneous
inserts shall be either supplied FREE by the OWNER or to be furnished
by the CONTRACTOR. Any of the miscellaneous inserts which are
required to be fabricated and supplied by the CONTRACTOR and
cement concrete to be provided for fixing embedments, hold fasts of
door/window frames etc. shall however, be measured and paid
ISSUE
separately under the respective items of work. . R4
2.3.3 MEASUREMENT
2.3.3.2 No deductions shall be made for openings less than 0.1sq.m area or for
embedments upto 0.1 sq.m in section.
2.4.1 MATERIALS
2.4.1.1 The material specification for the work shall be as per clause 2.3.1
2.4.2 WORKMANSHIP
2.4.2.1 Face stones shall be hammer dressed on all beds, and joints so as to
give them approximately rectangular block shape. These shall be
squared on all joints and beds. The bed joint shall be rough chisel
dressed for at least 80 mm back from the face, and side joints for at
least 40 mm such that no portion of the dressed surface is more than 6
mm from a straight edge placed on it. The remaining unexposed portion
of the stone shall not project beyond the surface of bed and side joint.
The bushing on the face shall not project more than 40 mm as an
exposed face and 10 mm on a face to be plastered. The hammer
dressed stone shall also have a rough tooling for minimum width of 25
mm along the four edges of the face of the stone, when stone work is
exposed.
2.4.2.2 All stones shall be wetted before use. The walls shall be carried up truly
ISSUE
plumb or to specified batter. All courses shall not be less laid truly R4
horizontal and all vertical joints shall be truly vertical. The height of each
course shall not be less than 150mm or more than 300mm
2.4.2.3 Face stones shall be laid alternate headers and stretchers. No pinning
shall be allowed on the face. No face stone shall be less in breadth than
its height and at least one third of the stones shall tail into the work for
length not less than twice their height.
2.4.2.4 The hearting or the interior filling of the wall shall consist of stones
carefully laid on their proper beds in mortar; chips and spalls of stone
being used where necessary to avoid thick beds of joints of mortar and
at the same time ensuring that no hollow spaces are left anywhere in
the masonry. The chips shall not be used bellow the hearting stone to
bring these up to the level of face stones. The use of chips shall be
restricted to the filling of interstices between the adjacent stones in
hearting and these shall not exceed 10% of the quantity of stone
masonry.
2.4.2.6 Bond Stones shall be as specified in 3.1.2.6 except that a bond stone or
a set of bond stones shall be inserted 1.5 to 1.8 meters apart, in every
course.
2.4.2.7 The quoins shall be of the same height as the course in which these
occur. These shall be at least 450 mm long and shall be laid stretchers
and headers alternatively. These shall be laid square on the beds,
which shall be rough-chisel dressed to depth of at least 100 mm. In
case of exposed work, these stones shall have a minimum of 25 mm
wide chisel drafts at four edges, all the edges being in the same plane.
2.4.2.8 All bed joints shall be horizontal and all side joints vertical. All joints
shall be fully packed with mortar, ace joints shall not be more than one ISSUE
R4
2.4.3 MEASUREMENT
2.5.1 Bricks used in the works shall conform to the requirements laid down in
IS:1077 /IS:13757. The class of the bricks shall be as specifically indicated
in the respective items of work.
2.5.2 Standard modular size of common bricks shall be 190mm x 90mm x 90mm
as per IS:1077/ IS13757. The nominal thickness of one brick and half brick
walls using modular bricks shall be considered as 200 mm and 100 mm
respectively. In the event of use of non-modular bricks, standard size shall
be 230mm x ll0mm x 70mm. The nominal thickness of one brick and half
brick walls using non-modular bricks shall be considered as 230 mm and
115 mm respectively. The dimensional tolerances of modular and non-
modular sized bricks over the standard sizes shall be as per IS 1077. /
IS13757.
2.5.3 Normal Clay Bricks shall be sound, hard, and homogenous in texture, well
ISSUE
burnt in kiln without being vitrified, hand/machine moulded, deep red, cherry R4
or copper coloured, of regular shape and size & shall have sharp and
square edges with smooth rectangular faces. The bricks shall be free from
pores, cracks, flaws and nodules of free lime. Hand moulded bricks shall
be moulded with a frog and those made by extrusion process may not be
provided with a frog. Bricks shall give a clear ringing sound when struck
and shall have a minimum crushing strength of 5N/sq.mm unless otherwise
specified in the item.
2.5.4 Clay Fly ash bricks shall be hand/machine moulded and shall be made from
the admixture of suitable soils and fly ash in optimum proportioned as per
IS2117. Fly ash used for manufacture of bricks shall conforming to grade 1
or grade 2 as per IS3812. The bricks shall be free from pores, cracks, flaws
and nodules of free lime. Hand moulded bricks shall be moulded with a
frog and those made by extrusion process may not be provided with a frog.
Bricks shall give a clear ringing sound when struck and shall have a
minimum crushing strength of 5N/sq.mm unless otherwise specified in the
item.
2.5.5 The average water absorption shall not be more than 20 percentages by
weight up to class 12.5 and 15 percentages by weight for higher classes.
Bricks which do not conform to this requirement shall be rejected. Over or
under burnt bricks are not acceptable for use in the works.
2.5.6 Sample bricks shall be submitted to the ENGINEER for approval and bricks
supplied shall conform to approved samples. If demanded by ENGINEER,
brick samples shall be got tested as per IS: 3495 by CONTRACTOR at no
extra cost to OWNER. Bricks rejected by ENGINEER shall be removed
from the site of works within 24 hours.
2.5.7 Mortar for brick masonry shall consist of cement and sand and shall be
prepared as per IS:2250. Mix shall be in the proportion of 1:5 for all
brickworks, unless otherwise specified in the respective items of work.
Sand for masonry mortar shall conform to IS:2116. The sand shall be free
from clay, shale, loam, alkali and organic matter and shall be of sound,
ISSUE
hard, clean and durable particles. Sand shall be approved by ENGINEER. R4
2.5.8 For preparing cement mortar, the ingredients shall first be mixed thoroughly
in dry condition. Water shall then be added and mixing continued to give a
uniform mix of required consistency. Mixing shall be done thoroughly in a
mechanical mixer, unless hand mixing is specifically permitted by the
ENGINEER. The mortar thus mixed shall be used as soon as possible,
preferably within 30 minutes from the time water is added to cement. In
case, the mortar has stiffened due to evaporation of water, this may be re-
tempered by adding water as required to restore consistency, but this will
be permitted only upto 30 minutes from the time of initial mixing of water to
cement. Any mortar which is partially set shall be rejected and shall be
removed forthwith from the site. Droppings of mortar shall not be re-used
under any circumstances.
2.5.9 The CONTRACTOR shall arrange for test on mortar samples if so directed
by the ENGINEER.
2.5.10 WORKMANSHIP
2.5.10.1 Workmanship of brick work shall conform to IS: 2212. All bricks
shall be thoroughly soaked in clean water for at least one hour
immediately before being laid. The cement mortar for brick masonry
work shall be as specified in the respective item of work. Brick work
200mm/230mm thick and over shall be laid in English Bond unless
otherwise specified. 100mm/115mm thick brickwork shall be laid with
stretchers. For laying bricks, a layer of mortar shall be spread over the
full width of suitable length of the lower course. Each brick shall be
slightly pressed into the mortar and shoved into final position so as to
embed the brick fully in mortar. Only full size bricks shall be used for
the works and cut bricks utilised only to make up required wall length or
for bonding. Bricks shall be laid with frogs uppermost.
ISSUE
R4
2.5.10.3 Bricks shall be so laid that all joints are well filled with mortar. The
thickness of joints shall not be less than 6 mm and not more than 10
mm. The face joints shall be raked to a minimum depth of 10mm/15mm
by raking tools during the progress of work when the mortar is still
green, so as to provide a proper key for the plastering/pointing
respectively to be done later. When plastering or pointing is not
required to be done, the joints shall be uniform in thickness and be
struck flush and finished at the time of laying. The face of brickwork
shall be cleaned daily and all mortar droppings removed. The surface
of each course shall be thoroughly cleaned of all dirt before another
course is laid on top.
ISSUE
R4
2.5.10.5 Brickwork shall be kept constantly moist on all the faces for at
least seven days. The arrangement for curing shall be got approved
from the ENGINEER.
2.5.10.8 All brickwork shall be built tightly against columns, floor slabs or
other structural members.
2.5.10.10 The above items shall be measured and paid for separately under
the respective items of work.
2.5.10.11 Bricks for partition walls shall be stacked adjacent to the structural
member to pre-deflect the structural member before the wall is taken up
for execution. Further, the top most course of half or full brick walls
abutting against either a de-shuttered slab or beam shall be built only
after any proposed masonry wall above the structural member is
executed to cater for the deflection of the structural element.
2.5.10.14 CONTRACTOR shall note that the unit rates quoted for the
masonry work shall be deemed to include for the installation of
miscellaneous inserts such as pipe sleeves, bolts, steel sections with
anchors etc. and providing pockets, leaving openings, cutting chases
etc. in accordance with the construction drawings. Miscellaneous
ISSUE
inserts shall be either supplied FREE by the OWNER or to be furnished R4
2.5.10.18 Faced works shall be kept clean and free from damage,
discoloration etc., at all times.
2.5.10.19 Cutting of chases in 230 thick wall and above for routing GI pipes,
CI pipes or for any other services shall preferably be in the vertical
direction. Horizontal chases shall be avoided, as far as possible. The
depth of vertical chases and horizontal chases, if any, shall not exceed
one third and one sixth of the thickness of masonry respectively.
Vertical chases shall not be closer than 2m in any stretch. Not more
than 2 horizontal chases shall be permitted in a stretch of wall and
these should be located in upper or lower one-third of height of wall.
2.5.11 MEASUREMENT
2.5.11.2 No deductions shall be made for openings less than 0.1sq.m area
or for embedment upto 0.1 sq.m in section.
2.5.11.4 All concrete works shall he measured and paid for separately
under the respective items of work.
2.6.1 MATERIALS
2.6.1.1 Masonry units of hollow and solid concrete blocks shall conform to the
requirements of IS : 2185 (Part 1).
2.6.1.2 Masonry units of hollow and solid light-weight concrete blocks shall
conform to the requirements of IS: 2185 (Part 2).
2.6.1.6 The maximum variation in the length of the units shall not be more than
+ 5mm and maximum variation in height or width of the units shall not
be more than + 3mm.
2.6.1.7 Concrete blocks shall be either hollow blocks with open or closed
cavities or solid blocks.
2.6.1.9 The concrete mix for the hollow and solid concrete blocks/light weight
concrete blocks shall not be richer than one part of cement to six parts
of combined aggregates by volume i.e. (1:6).
2.6.2 WORKMANSHIP
2.6.2.1 The type of the concrete block, thickness and grade based on the
compressive strength for use in load bearing and/or non-load bearing ISSUE
walls shall be as specified in the respective items of work. The R4
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
WRITE UP
TCE.M4-419-01
GENERAL BUILDING WORKS SHEET 18 of 174
2.6.2.5 The thickness of both horizontal and vertical joints shall be 10 mm. The
first course shall he laid with greater care, ensuring that it is properly
aligned, levelled and plumb since this will facilitate in laying succeeding
courses to obtain a straight and truly vertical wall. For the horizontal
(bedding) joint, mortar shall be spread over the entire top surface of the
block including front and rear as well as the edges to a uniform layer of
10 mm. For vertical joints, the mortar shall be applied on the vertical
edges of the front and rear sides of the blocks. The mortar may be
applied either to the unit already placed on the wall or on the edges of
the succeeding unit when it is standing vertically and then placing it
horizontally, well pressed against the previously laid unit to produce a
compacted vertical joint. To assure satisfactory bond, mortar shall not
be spread too far ahead of actual laying of the block as the mortar will
stiffen and lose its plasticity. Mortar while hardening shrinks slightly
and thus pulls away from the edges of the block. The mortar shall be ISSUE
R4
pressed against the units with a jointing tool after it has stiffened to
effect intimate contact between the mortar and the unit to obtain a
weather tight joint. The mortar shall be raked to a depth of 10 mm as
each course is laid to ensure good bond for the plaster.
2.6.2.6 Only well dried blocks should be used for the construction. Blocks with
moisture content more than 25% of maximum water absorption
permissible shall not he used. The blocks should not be wetted before
or during laying in the walls. Blocks should be laid dry except slightly
moistening their surface on which mortar is to be applied to obviate
absorption of water from the mortar.
2.6.2.7 For jambs of doors, windows and openings, solid concrete blocks shall
he provided. If hollow units are used, the hollows shall be filled with
concrete of mix 1:3:6. Hold fasts of doors/windows should be arranged
so that they occur at block course level.
2.6.2.8 At intersection of walls, the courses shall be laid up at the same time
with a true masonry bond between at least 50% of the concrete blocks.
The sequence for construction of partition walls and treatment at the top
of load bearing walls for the RCC slab shall be as detailed under clause
3 for the brick work.
2.6.2.9 Curing of the mortar joints shall be carried out for atleast 7 days. The
walls should only be lightly moistened and shall not be allowed to
become excessively wet.
2.6.3 MEASUREMENT
ISSUE
R4
3.1 GENERAL
3.2.1 Work shall be carried out as per latest edition of Indian Standards and Code
of Practices. List given here shall not be considered as conclusive and is for
reference and guidance only. Any discrepancies/ conflict noticed shall be
brought to the notice of Architect/Engineer in charge for direction / approval.
However, as a general rule more stringent specification shall take
precedence.
IS: 383 Coarse and fine aggregates from natural sources for
concrete
IS:456 Plain And Reinforced Concrete - Code Of Practice
ISSUE
R4
3.3.1 MATERIALS
3.3.1.1 Stone used under grade slab for rubble soling on grade, foundations
etc., shall be clean, hard, durable rock free from veins, flaws,
weathering and other defects. Stones shall generally conform to the
requirements stipulated in IS:1597 (Part-I).
3.3.2 WORKMANSHIP
3.3.2.1 Stones shall be hand packed carefully and laid with their largest base
downwards resting flat on the prepared sub-grade and with their height
equal to the thickness of the packing. Stones shall be laid breaking
joints and in close contact with each other-. All interstices between the
stones shall be wedged-in by small stones of suitable size, well driven
in by crow bars and hammers to ensure tight packing and complete
filling-in of the interstices. The wedging shall be carried out
simultaneously with the placing in position of rubble packing and shall
not lag behind. After this, any interstices between the smaller wedged
stones shall be in-filled with clean hard sand by booming so as to fill the
joints completely.
3.3.2.2 The laid rubble packing shall be sprinkled with water and compacted by
using suitable rammers/rollers.
ISSUE
R4
3.3.3 MEASUREMENT
3.3.3.1 Measurement shall be in sq.m correct to two places of decimal for the
specified compacted thickness of rubble sub-base.
3.4.1 WORKMANSHIP
3.4.1.1 The thickness and grade of concrete shall be as specified in the item of
work.
3.4.1.2 Before placing the blinding concrete, 50/75mm thick as per the item of
work, the sub-base of rubble packing shall be properly wetted and
rammed. Concrete for the base shall then be deposited between the
forms, thoroughly tamped and the surface finished level with the top
edges of the forms. Two or three hours after the concrete has been laid
in position, the surface shall be roughened using steel wire brush to
remove any scum or laitance and swept clean so that the coarse
aggregates are exposed. The surface of the base concrete shall be left
rough to provide adequate bond for the floor finish to be provided later.
3.4.2 MEASUREMENT
3.5.1 Terrazzo tiles and cement tiles shall generally conform in all respects to
standards stipulated in IS:1237. Tiles shall be of the best quality
manufactured adopting hydraulic pressure of not less than 14N/mm 2.
3.5.2 The type, quality, size, thickness colour etc, of the tiles for flooring/dado/
skirting shall be as specified in the respective items of work.
ISSUE
R4
3.5.3 The aggregates for terrazzo topping shall consist of marble chips which are
hard, sound and dense. Cement to be used shall be either ordinary
Portland cement or white cement with or without colouring pigment. The
binder mix shall be with 3 parts of cement to 1 part of marble powder by
weight. The proportion of cement shall be inclusive of any pigments. For
every one part of cement-marble powder binder mix, the proportion of
aggregates shall be 1.75 parts by volume, if the chips are between l mm to
6mm and 1.50 parts by volume if the chips are between 6mm to 25mm.
3.5.4 The minimum thickness of wearing layer of plain cement and plain coloured
tiles for general purpose and terrazzo tiles with chips upto 6mm to 12mm
general purpose is 5mm thick tiles. Terrazo tiles with chips of size up to
20mm for heavy duty and general purpose and plain cement and plain
coloured tiles for heavy duty shall be 6mm thick tiles. Pigment used in the
wearing layer shall not exceed 10 percent of the weight of cement used in
the mix.
3.5.5 WORKMANSHIP
3.5.5.2 Tiling work shall be commenced only after the door and window frames
are fixed and plastering of the walls/ ceiling is completed. Wall
plastering shall not be carried out up to about 50mm above the level of
proposed skirting/dado.
3.5.5.4 A layer of 25mm average thickness of cement mortar consisting of one ISSUE
R4
part of cement to four parts of sand shall be provided as bedding for the
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
WRITE UP
TCE.M4-419-01
GENERAL BUILDING WORKS SHEET 27 of 174
tiles over the base concrete. The thickness of bedding mortar shall not
be less than l0mm at any place. The quantity of water to be added for
the mortar shall be just adequate to obtain the workability for laying.
Sand for the mortar shall conform to IS:2116 and shall have minimum
fineness modulus of 1.5. The surface shall be left rough to provide a
good bond for the tiles. The bedding shall be allowed to harden for a
day before laying of the tiles.
3.5.5.5 Neat cement slurry using 4.4 kg of cement per one sq.m of floor area
shall be spread over the hardened mortar bedding over such an area at
a time as would accommodate about 20 tiles. Tiles shall be fixed in this
slurry one after the other, each tile being gently tapped with a wooden
mallet till it is properly bedded and in level with the adjoining tiles. The
joints shall be in straight lines and shall normally be 1.5mm wide. On
completion of laying of the tiles in a room, all the Joints shall be cleaned
and washed fairly deep with a stiff broom/wire brush to a minimum
depth of 5mm. The day after the tiles have been laid, the joints shall be
filled with cement grout of the same shade on the colour of the matrix of
the tile. For this purpose white cement or grey cement with or without
pigments shall be used. The flooring should be kept moist and left
undisturbed for 7 days for the bedding/joints to set properly. Heavy
traffic shall not be allowed on the floor for at least 14 days after fixing of
the tiles.
3.5.5.6 About a week after laying the tiles, each and every tile shall be lightly
tapped with a small wooden mallet to find out if it gives a hollow sound;
if it does, such tiles along with any other cracked or broken tiles shall be
removed and replaced with new tiles to proper line and level. The same
procedure shall be followed again after grinding the tiles and all
damaged tiles replaced, properly jointed and finished to match. For the
purpose of ensuring that such replaced tiles match with those laid
earlier, it is necessary that the CONTRACTOR shall procure sufficient
quantity of extra tiles to meet this contingency. ISSUE
R4
3.5.5.7 Wherever a full tile cannot be provided, tiles shall be cut to size and
fixed. Floor tiles adjoining the wall shall go about 10mm under the
plaster, skirting or dado.
3.5.5.8 Tile skirting and dado work shall be executed only after laying tiles on
the floor. For dado and skirting work, the vertical wall surface shall be
thoroughly cleaned and wetted. Thereafter it shall be evenly and
uniformly covered with 12mm thick backing of 1:4 cement sand mortar.
For this work the tiles as obtained from the factory shall be of the size
required and practically full polished. The back of each tile to be fixed
shall be covered with a thin layer of neat cement paste and the tile shall
then be gently tapped against the wall with a wooden mallet. Fixing
shall be done from the bottom of the wall upwards. The joints shall be in
straight lines and shall normally be 1.5mm wide. Any difference in the
thickness of the tiles shall be evened out in the backing mortar or
cement paste so that the tile faces are in conformity & truly plumb. Tiles
for use at the corners shall be suitably cut with bevelled edges to obtain
a neat and true joint. After the work has set, hand polishing with
carborundum stones shall be done so that the surface matches with the
floor finish.
3.5.5.9 Wall plastering of the strip left out above the level of skirting/dado shall
be taken up after the tiles are fixed.
3.5.5.10 CONTRACTOR shall note that the unit rate quoted for skirting
shall also include for any chipping of the brick work required to be
carried out for this item.
3.5.5.11 Chequered terrazzo tiles for flooring and for stair treads shall be
delivered to site after the first machine grinding.
3.5.5.13 Tiles shall be laid to the levels specified. To ensure this, finished
floor levels should be marked at all door locations and also on the floor
at frequent intervals. Where large areas are to be tiled the level of the
central portion shall be kept l0mm higher than that at the walls to
overcome optical illusion of a depression in the central portion.
Localized deviation of 3mm in any 3m length is acceptable in a
nominally flat floor.
3.5.5.14 All corners shall be in perfect right angle matching up with the
corners of walls. If due to any misalignment during construction, the
corners of wall are not at right angle, adjustment shall be made in the
title portion lying below skirting.
3.5.5.15 Flooring in toilets, kitchen shall be taken up only after fixing water
closet, squatting pans & floor traps.
3.6.1 The aggregates for terrazzo topping shall consist of marble chips which are
hard, sound and dense.
3.6.3 The binder mix shall be with 3 parts of cement to 1 part of marble powder
by weight. The proportion of cement shall be inclusive of any pigments. For
every one part of cement-marble powder binder mix, the proportion of
aggregates shall be 1.75 parts by volume, if the chips are between l mm to
6mm and 1.50 parts by volume if the chips are between 6mm to 25mm.
3.6.4 WORKMANSHIP
ISSUE
R4
3.6.4.1 Cement shall first be mixed with the marble powder in dry state. The
mix thus obtained shall be mixed with the aggregates in the specified
proportions.
3.6.4.2 Care shall be taken not to get the materials into a heap which results in
the coarsest chips falling to the edges and cement working to the centre
at the bottom.
3.6.4.4 The mix shall be used in the works within 30 minutes of the addition of
water to the cement.
3.6.4.5 The thickness, type, quality, size and colour of chips etc. for the in-situ
terrazzo finish for flooring/dado skirting shall be as specified in the
respective items of work. Laying and finishing of in-situ work shall
conform to the requirements of workmanship stipulated in IS: 2114.
3.6.4.6 In-situ terrazzo finish shall be laid over hardened concrete base. The
finish layer consists of an under layer and terrazzo topping. The under
layer shall be of cement concrete of mix 1:2:4 using l0mm downgraded
coarse aggregates. The combined thickness of under layer and topping
shall not be less than 30 mm for flooring and 20mm for dado/skirting
work.
3.6.4.7 The minimum thickness of topping shall be 6mm if chips used are
between 1mm to 4mm, 9mm if chips are between 4mm to 7mm and
12mm if chips are between 7mm to l0mm. If chips larger than l0mm
size are used, the minimum thickness shall be one and one third the
maximum size of chips.
3.6.4.8 Both the under layer and later the topping shall be divided into panels ISSUE
not exceeding 2 Sq.m. for laying so as to reduce the possibility of R4
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
WRITE UP
TCE.M4-419-01
GENERAL BUILDING WORKS SHEET 31 of 174
3.6.4.11 Terrazzo topping shall be laid while the under-layer is still plastic
and normally between 18 to 24 hours after the under-layer is laid.
Cement slurry of the same colour as the topping shall be brushed on
the surface immediately before laying is commenced. The terrazzo mix
shall be laid to a uniform thickness and compacted thoroughly by
tamping and with a minimum of trowelling. Straight edge and steel
floats shall be used to bring the surface true to the required level in
such a manner that the maximum amount of marble chips come up and
spread uniformly all over the surface.
ISSUE
R4
3.6.4.12 The surface shall be left dry for air-curing for a period of 12 to 18
hours. Thereafter it shall be cured by allowing water to stand in pools
for a period of not less than 4 days.
3.6.4.14 Where the dampness from ground may find its way to the top of
floor, concrete floor on the ground or basement shall be provided with
an effective damp proof.
3.6.4.15 Flooring in toilet and kitchen shall be taken up after fixing water
closet, squatting pans and floor trap.
ISSUE
R4
3.7.1 The mix proportion for the in-situ concrete floor topping shall be
1:2.5:3.5(one part cement: two and half parts sand : three and half parts
coarse aggregates) by volume unless otherwise specified in the item of
work.
3.7.3 Coarse aggregates shall have high hardness surface texture and shall
consist of crushed rock of granite, basalt, trap or quartzite. The aggregate
crushing value shall not exceed 30 percent. The grading of the coarse
aggregates shall be of size 12.5mm and below and shall be as per IS:2571.
3.7.4 Grading of the sand shall be within the limits indicated in IS:2571.
3.7.5 WORKMANSHIP
3.7.5.1 The thickness of the floor topping shall be as specified in the item of
work. The minimum thickness of the floor topping shall be 25mm, if it is
laid separately. 15mm thick wearing course of cement concrete 1:2 (1
cement:2 stone) aggregate of size 4.75mm & below) by volume shall be
applied monolithically over floor topping, if called for in the schedule of
item. Wearing course shall be 20mm thick, if it is cast monolithically
over ground floor slab. Laying and finishing of in-situ topping shall
conform to the requirements of IS 2571.
3.7.5.2 The surface shall be rough to provide adequate bond for the topping. It
shall be finished to a level below the finished floor equal to the
thickness of topping and / or wearing courses, if specified.
3.7.5.4 Floor finish shall be laid in suitable panels to reduce the risk of cracking.
No dimension of a panel shall exceed 2 meters and the length of a
panel shall not exceed one and a half times its breadth. Topping shall
be laid in alternate panels, the intermediate panels being cast after a
gap of at least one day. Construction joints shall be plain vertical butt
joints.
3.7.5.5 Screed strips shall be fixed dividing the area into suitable panels.
Immediately before depositing the concrete topping, neat cement slurry
at 2.75 kg/sq.m of area shall be thoroughly brushed into the prepared
surface. Topping shall then be laid, very thoroughly tamped, struck off
level and floated with wooden float. The surface shall then be tested
with a straight edge and mason's spirit level to detect any inequalities
from that specified in the drawings and these shall be made good
immediately.
3.7.5.9 In severe condition, where dampness from ground may find its way on
the top of the floor, the floor slab shall be cast in two equal halves. The
top surface of bottom half shall be made plane and smooth after it is
cast. A coat of bitumen primer conforming to IS 3384 shall be applied
on the hard surface over which two coats of bitumen conforming to IS
1580 shall be applied @ 1.5 kg/m2 for each layer. After the bitumen
surface is dry, the top half of floor slab shall be cast.
3.8.2 The thickness of the floor topping shall be as specified in the item of work.
The minimum thickness of granolithic floor topping on hardened concrete
base shall be 40mm, if laid separately. It shall be 20mm, if the topping is
laid monolithically over the floor concrete.
3.9.1 Floor hardener topping shall be provided either as integrally finished over
the structural slab/grade slab or laid monolithically with the
concrete/granolithic floor finish on top of hardened concrete base.
3.9.2 Floor hardener of the metallic or non-metallic type suitable for the
performance of normal/medium/heavy duty function of the floor, the
ISSUE
R4
3.9.3 For monolithic application with the floor finish/slab, the thickness of the
layer shall be 15mm. It shall be 20mm if it is laid separately over floor slab.
The topping shall be laid within 2 to 3 hours after concrete is laid and it is
still plastic but stiffened enough for the workmen to tread over it by placing
planks. The surface of the concrete layer shall be kept rough for providing
adequate band for the topping. Laitance shall be removed before placing
the topping. The topping shall be screeded and thoroughly compacted to
the finished level. After the surface has hardened sufficiently, it shall be
kept continuously moist for at least 10 days.
3.9.4 The procedure for mixing the floor hardener topping shall be as per
manufacturer's instructions.
3.9.5 Floor hardener topping shall be prevented from any damages due to
subsequent building operations by covering with 75 mm thick layer of sand,
if it is laid monolithically with the slab.
3.10.1 The epoxy resin and hardener formulation for laying of Pointless lining work
in floors and walls of concrete tanks/trenches, floor toppings etc shall be as
per the requirements of IS:9197. Method of laying shall be as per the
requirements of IS 4631.
3.10.2 The epoxy composition shall have the chemical resistance to withstand the
conditions of exposure like Hydrochloric acid up to 30% concentration,
Sodium hydroxide up to 50% concentration, Liquid temperature up to 60"C,
Ultraviolet radiation, Alternate wetting and drying.
3.10.3 Epoxy resin shall be of liquid type of suitable grade and class as
recommended by the manufacturer.
3.10.4 The hardener shall be of the liquid type such as Aliphatic Amine or an
ISSUE
Aliphatic/Aromatic Amine Adduct or a polyamide or amido polyamine of R4
suitable characteristics. The hardener shall react with epoxy resin at normal
ambient temperature above 5oC.
3.10.6 Accelerator, plasticizer and coal tar may be added for the preparation of
epoxy composition, to the proportion as recommended in IS 9197.
3.10.7 CONTRACTOR shall furnish test certificates for satisfying the requirements
of the epoxy formulation if so directed by the ENGINEER.
3.10.8 WORKMANSHIP
3.10.8.2 The epoxy lining shall be of the trowel type to facilitate execution
of the required thickness for satisfactory performance.
3.10.8.4 Just adequate quantity of epoxy resin which can be applied within
the pot life as specified by the manufacturer shall be prepared at one
time for laying and jointing.
ISSUE
R4
3.10.8.7 For epoxy lining over the inside concrete surfaces of underground
tank or trenches, it should be ensured that they are leak proof against
water by conducting leakage test.
3.11.1 The slabs shall be of approved selected quality, hard, sound, dense and
homogenous in texture, free from cracks, decay, weathering and flaws. The
percentage of water absorption shall not exceed 5 percent as per test
conducted in accordance with IS:1124.
3.11.2 The slabs shall be hand or machine cut to the required thickness. Tolerance
in thickness for dimensions of tile more than 100 mm shall be ±5mm. This
shall be + 2mm on dimensions less than l00mm.
3.11.3 Slabs shall be supplied to the specified size with machine cut edges or fine
chisel dressed to the full depth. All angles and edges of the slabs shall be
true and square, free from any chipping giving a plane surface. Slabs shall
have the top surface machine polished (first grinding) before being brought
to site. The slabs shall be washed clean before laying.
3.11.4 WORKMANSHIP
3.11.4.1 The type, size, thickness and colour/shade etc. of the slabs for
flooring/dado/ skirting shall be as specified in the respective items of the
work.
ISSUE
R4
3.11.4.2 Concrete base shall be prepared and finished below the finished
floor level equal to the thickness of stone slab and cement mortar
below.
3.11.4.3 The thickness of the slabs for dado/skirting work shall not be more
than 25mm. Slabs shall be so placed that the back surface is at a
distance of 12mm from the wall. If necessary, slabs shall be held in
position temporarily by suitable method. After checking for verticality,
the gap shall be filled and packed with cement sand mortar of
proportion 1:3. After the mortar has acquired sufficient strength, the
temporary arrangement holding the slab shall be removed. The
recommended mortar mix for joints and beddings for stone blocks shall
be two parts of white cement and seven parts of stone dust. The
thickness of joints shall be 5 mm. For fixing of stones to the walls, fixing
clamps of non-ferrous metal should be used.
3.11.4.4 Grinding and polishing shall be as per clause 3.6.4.13 except that
first grinding with coarse grade carborundum shall not be done and
cement slurry with or without pigment shall not be applied before
polishing.
3.12.2 Each tile shall bear on its back, permanent and legible trade mark of the
manufacturer. All angles of the tiles shall be right angle, all edges sharp and
true, colour and texture of the wearing face uniform throughout. Maximum
tolerance/allowance for length and breadth shall be +1 mm and thickness
+3mm along the wearing surface of the tile and the wearing surface shall be
planed free from pin-holes and other blemishes.
ISSUE
R4
3.12.3 The backing shall be composed of 1 part ordinary grey cement, 2 parts
sand and 4 parts of stone chips by volume and mixed with water.
3.12.4 The topping shall be uniform and of thickness not less than 6mm. The
quantity of carborundum grit shall be not less than 1.35 kg/sq.m used with
cement with or without pigment. The carborundum grit shall pass through
1.18mm mesh and shall be retained on 0.60mm mesh. The total
thickness of tiles including the topping shall be not less than 20 mm.
3.12.5 The tile shall be cured at the shop for at least 14 days before delivery to
site. Tiles shall be packed properly to prevent damage during transit and
storage. The tiles must be stored carefully to prevent staining by damp,
rust, oil and grease or other chemicals. Tiles made in each batch shall be
kept and used separately so that the colour of each area of floor may
remain uniform.
3.12.6 The manufacturer shall supply along with the tiles the grout mix containing
cement and pigment in exact proportions as used in topping of tiles. The
containers of the grout mix shall be suitably marked to relate it to the
particular type and batch of tiles
3.12.7 The size, thickness, colour and plain or chequered etc. of the tiles for
flooring/skirting shall be as specified in the respective items of work. The
under bed for floors shall be 1 part cement: 2 parts coarse sand: 4 parts
stone aggregate by volume mix with sufficient water to form a stiff workable
mass. For skirting and dado, it shall be 1 part cement: 3 parts coarse sand
by volume.
3.12.8 The total average thickness shall be minimum 50 mm for floors and 30 mm
for walls.
3.12.9 WORKMANSHIP
3.13.1 Tiles shall be of the best quality from an approved manufacturer. The tiles
shall be flat, true to shape and free from flaws such as crazing, blisters,
pinholes, specks or welts. Edges and underside of the tiles shall be free
from glaze and shall have ribs or indentations for a better anchorage with
the bedding mortar. Dimensional tolerances shall be as specified in IS:
13756.
3.13.2 WORKMANSHIP
3.13.2.1 The size, thickness, colour, with or without designs etc of the tiles
for flooring/dado/skirting shall be as specified in the respective items of
work.
3.13.2.2 The total thickness of glazed tile finish including the bedding
mortar shall be maximum 20 mm in flooring/dado/skirting. The minimum
thickness of bedding mortar shall be 12mm for flooring and l0mm for
dado/skirting work.
3.13.2.4 Tiles shall be soaked in water for about 10 minutes just before
laying. Where full size tiles cannot be fixed, tiles shall be cut to the
required size using special cutting device and the edges rubbed smooth
to ensure straight and true joints.
3.13.2.5 Coloured tiles with or without designs shall be uniform and shall be
preferably procured from the same batch of manufacture to avoid any
differences in the shade.
3.13.2.6 Tiles for the flooring shall be laid over hardened concrete base.
The surface of the concrete base shall be cleaned of all loose materials,
mortar droppings etc well wetted without allowing any water pools on
ISSUE
the surface. The bedding mortar shall then be laid evenly over the R4
surface, tamped to the desired level and allowed to harden for a day.
The top surface shall be left rough to provide a good band for the tiles.
For skirting and dado work, the brick walls shall be raked to a depth of
15mm. In case of concrete walls, the surfaces shall be hacked. The
raked / hacked masonry surfaces shall be cleared, wet and then the
bedding mortar to specified thickness shall be applied. The mortar
surfaces shall be roughened using wire brush and allowed to harden.
3.13.2.7 Neat cement slurry using 3.3 kg cement per one sq.m of floor area
shall be spread over the hardened mortar bed over such an area as
would accommodate about 20 tiles. Tiles shall be fixed in this slurry one
after the other, each tile being gently tapped with a wooden mallet till it
is properly bedded and in level with the adjoining tiles. For skirting and
dado work, the back of the tiles shall be smeared with cement slurry for
setting on the backing mortar.
3.13.2.8 Fixing of tiles shall be done from the bottom of the wall upwards.
The joints shall be in perfect straight lines and as thin as possible but
shall not be more than l mm wide. Tiles used for corners shall be
suitably beveled to obtain a true and neat joint. The surface shall be
checked frequently to ensure correct level/required slope. Floor tiles
near the walls shall enter skirting/dado to a minimum depth of 10mm.
Tiles shall not sound hollow when tapped.
3.13.2.9 All the joints shall be cleaned of grey cement with wire brush to a
depth of at least 3mm and all dust, loose mortar etc. shall be removed.
White cement with or without pigment shall then be used for flush
pointing the joints. Curing shall then be carried out for a minimum
period of 7 days for the bedding and joints to set properly. The surface
shall then be cleaned using a suitable detergent, fully washed and
wiped dry.
ISSUE
R4
3.14.2 The surface of the sheets/tiles shall be free from any physical defects such
as pores, blisters, cracks etc. which affects the appearance and
serviceability. Tiles/sheets shall meet with the tolerance limits in dimensions
specified in the IS codes. CONTRACTOR shall submit the test certificates,
if so desired by the ENGINEER.
3.14.3 Each tile/sheet shall be legibly and indelibly marked with the name of the
manufacturer or his trade mark, IS certificate mark and batch number.
3.14.4 The adhesive to be used for laying the PVC/VINYL flooring shall be rubber
based conforming to IS 12830 and of the make as recommended and
approved by the manufacturer of PVC/VINYL sheets/tiles.
3.14.5 The type, size, thickness, colour, plain or mottled and the pattern shall be
as specified in the respective items of work.
3.14.6 WORKMANSHIP
3.14.6.1 Laying of PVC / VINYL sheets / tiles shall conform IS 5318. PVC /
VINYL floor covering shall be provided over an under bed of cement
concrete floor finish over the base concrete or structural slab. It is
essential that the sub-floor and the under bed are perfectly dry before
laying the PVC / VINYL flooring. This shall be ensured by methods of
testing as stipulated in Appendix-A of IS:5318. Concrete floor on the
ground / basement shall be treated with an effective damp proof course.
ISSUE
R4
3.14.6.2 The surface of the under bed shall have trowelled finish without
any irregularities which creates poor adhesion. Surface shall be free of
oil or grease and thoroughly cleaned of all dust, dirt and wiped with a
dry cloth.
3.14.6.6 PVC / VINYL sheet shall be carefully taken and placed in position
from one end onwards slowly so that the air will be completely
squeezed out between the sheet and the background surface and no
air pockets are formed. It shall then be pressed with a suitable roller to
develop proper contact. The next sheet shall be laid edge to edge with
the sheet already laid, so that there is minimum gap between joints.
ISSUE
R4
3.14.6.7 Tiles shall be laid in the same manner as sheets and preferably,
commencing from the centre of the area. Tiles should be lowered in
position and pressed firmly on to the adhesive with minimum gap
between the joints. Tiles shall not be slided on the surface. Tiles shall
be rolled with a light wooden roller of about 5kg to ensure full contact
with the underlay. Work should be constantly checked to ensure that all
four edges of adjacent tiles meet accurately.
3.14.6.9 A minimum period of 24 hours shall be given after laying for the
development of proper bond of the adhesive. When the flooring in thus
completed, it shall be cleaned with a wet cloth soaked in warm soap
solution.
3.14.6.10 Metallic edge strips shall be used to protect the edges of PVC /
VINYL sheets/tiles which are exposed as in doorways/ stair treads.
3.14.6.11 Hot sealing of joints between adjacent PVC / VINYL sheet flooring
to prevent creeping of water through the Joints shall be carried out, if
specified in the item of work, using special equipment as per
manufacturer's instructions.
3.14.6.12 It is desirable that the PVC / VINYL flooring are taken up after
completing all other works in the area so as to avoid any accidental
damage to the flooring.
ISSUE
R4
3.15.1 The ceramic unglazed vitreous acid resisting tiles shall conform to the
requirements of IS: 4457.
3.15.2 The finished tile when fractured shall appear fine grained in texture, dense
and homogeneous. Tile shall be sound, true to shape, flat, free from flaws
and any manufacturing defects affecting their utility. Tolerance in the
dimensions shall be within the limits specified in the respective IS code.
3.15.3 The tiles shall be bedded and jointed using chemical resistant mortar
prepared from resin type conforming to IS: 4832 (Part II) filter, accelerator
and catalyst mixed in proportion as recommended by manufacturers.
Method of usage shall generally be as per the requirements of IS: 4443.
3.15.4 WORKMANSHIP
3.15.4.1 The size and thickness of tiles for use in the flooring/skirting/dado
shall be as specified in the respective items of work.
3.15.4.2 The base concrete surface shall be free from dirt and thoroughly
dried. The surface shall be applied with a coat of bitumen primer
conforming to IS: 3384. The primed surface shall then be applied with a
uniform coat of bitumen conforming to IS: 1580. Tiles shall be laid
directly without the application of bitumen, if epoxy or polyester resin is
used for the mortar.
3.15.4.3 Just adequate quantity of mortar which can be applied within the
pot life as specified by the manufacturer shall be prepared at one time
for bedding and jointing. Rigid PVC/Stainless steel/chromium plated
tools shall be used for mixing and laying.
3.15.4.4 For laying the floor 6 to 8 mm thick mortar shall be spread on the
back of the tile. Two adjacent sides of the tile shall be smeared with 4 to
6 mm thick mortar. Tile shall be pressed into the bed and pushed
against the floor and with the adjacent tile, until the joint in each case is ISSUE
2 to 3 mm thick. Excess mortar shall then be trimmed off and allowed to R4
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
WRITE UP
TCE.M4-419-01
GENERAL BUILDING WORKS SHEET 47 of 174
harden fully. Similar procedure shall be adopted for the work on walls
by pressing the tile/brick against the prepared wall surfaces and only
one course shall be laid at a time until the initial setting period.
3.15.4.5 The mortar joints shall be cured for a minimum period of 72 hours
with 20 to 25% hydrochloric acid or 30 to 40% sulphuric acid. After acid
curing, the joints shall be washed with water and allowed to thoroughly
dry. The joints shall then be filled with mortar to make them smooth and
plane. Acid curing is not required to be carried out if epoxy or polyester
resin is used for the mortar.
3.15.4.6 Resin mortars are normally self curing. The area tiled shall not be
put to use before 48 hours in case epoxy, polyester and furane type of
resin is used for the mortar. If phenol or cashew nut shell liquid resin is
used for the mortar, the area tiled shall not be put to use for 7 to 28
days respectively, without heat treatment. This period shall be 2 to 6
days respectively if heat treatment is given with infrared lamp.
3.15.4.8 It is necessary that the concrete slab / wall shall be made leak
proof against water, if necessary by pressure grouting etc. before taking
up any titling works. Cost of such works shall be deemed to have
included in the cost of tiling works, whether same is specifically
mentioned or not.
3.16.1 Concrete Mix Design - The concrete shall have a minimum compressive
strength of 3,000 psi in non-freeze areas, 3,500 psi in moderate freeze-
thaw areas and 4,000 psi in severe freeze-thaw areas. Portland cement &
Aggregates shall conform to IS. Mixing water shall be fresh, clean and
potable. No admixtures containing calcium chloride shall be permitted. ISSUE
R4
3.16.3 Low VOC Liquid Release Agent - Colourless, odourless liquid formulated to
break the bond between imprinting tools and surface of colour-hardened
concrete. Evaporates completely, leaving no residue. VOC content less
than 450 g/L (3.75lb/gal).
3.16.5.2 The area to receive imprinted concrete shall have the sub-grade
prepared as required as for any concrete slab on grade.Sub grade to
receive stamped concrete paving work must be well drained and have
adequate, uniform load bearing characteristics.
3.16.5.4 Place and spread concrete to completely fill all space inside forms.
Move concrete into place with square-tipped shovels or concrete rakes.
Consolidate concrete by tamping or vibrating to provide a suitable
surface for finishing. Prior to appearance of excess moisture or bleed
water, screed concrete with wood or magnesium straight edge or
mechanical vibrating screed. Continue concrete surface leveling and
consolidation with highway magnesium straight edge and (or)
magnesium bull float. Mechanically float concrete surfaces to required
flatness and levelness as soon as concrete surface has taken its initial
set and will support weight of a power float machine equipped with float
shoes or combination blades and operator. Completed concrete
ISSUE
R4
3.16.5.7 Sealing
3.16.5.10 Moisture content of concrete is low enough that alkali and other
salts do not become trapped beneath sealer. This will require a
minimum of 28 days subsequent to concrete placement, or longer if
required. ISSUE
R4
3.16.5.12 Seal imprinted concrete with liquid membrane curing and sealing
compounds as recommended by manufacturer. Apply two coats of
specified curing and sealing compound according to manufacturer‘s
written instructions.
3.16.6.3 Imprinting tools must be stored flat, textured face up, with no
objects resting on top. Handle products according to manufacturer‘s
printed instructions.
3.16.6.4 Care must be taken to ensure that the products are not damaged
while loading / unloading and transporting. Cartons must always be
stored with designated side upwards.
ISSUE
3.16.7 MEASUREMENT R4
3.16.7.2 This will include the materials, labour, tools, equipment, and
execution.
3.17.3 Sealing compound for filling the joints above the preformed bitumen filler
shall conform to Grade 'B' as per IS:1834.
3.17.4 WORKMANSHIP
3.17.4.2 The concrete/masonry surface shall be cleaned free from dust and
any loose particles. When the surface is dry, one coat of bitumen
primer conforming to IS 3384 to be applied over which one coat of
industrial blown type bitumen of grade 85/25 conforming to IS:702 shall
be applied hot by brushing at the rate of 1.20 kg/sq.m. When the
bitumen is still hot, the preformed bitumen filler shall be pressed and
held in position till it completely adheres.
The surface of the filler ISSUE
against which further concreting/masonry work is to be done shall R4
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
WRITE UP
TCE.M4-419-01
GENERAL BUILDING WORKS SHEET 52 of 174
similarly be applied with one coat of hot bitumen at the rate of 1.20
kg/sq.m.
3.17.5 MEASUREMENT
3.17.5.1 Measurement for the preformed joint filler shal1 be in sq.m correct
to two places of decimal for the specified thickness as per the items of
work. Measurement for applying the bitumen coat to concrete/masonry
surfaces shall be in sq.m correct to two places of decimal.
Measurement for the joint sealing compound shall be in running metres
correct to two places of decimal for the specified width and thickness as
per the items of work. Measurement for the mild steel corner angle and
plate shall be by weight as per the item of work.
3.18.1 MATERIAL
3.18.2 WORKMANSHIP
3.18.2.1 For flooring, the base Reinforced cement concrete slab or the
grade slab shall be cleaned of all dirt with water and hard brush. If
required the base surface shall be backed or otherwise roughened to
obtain a good bond. The surface shall be clean, free from grease, oil,
dust, loose particles, etc. and thoroughly soaked with water to prevent
absorption of mixing water from the base course. Before placing the
under bed, any excess standing water shall be mopped out. Before
laying the flooring approval of the Engineer-in-charge shall be obtained
as to the acceptability of the base. No extra payment is admissible for
the preparation of base and the unit rate of flooring shall be inclusive of
preparation of the base. Wherever the level is down, the contractor may
have to fill it up with the base concrete to achieve the specified top level
of the flooring surface. Wherever the level is higher, the contractor may
have to chip/break the concrete to achieve the specified thickness of
the floor topping. The rate quoted for the floor topping shall be firm for
the variation in level of the existing surface upto ±12mm. No extra rate
will be paid for chipping the specified floor topping thickness. Similarly
no extra payment will be made for the extra concrete to be laid for
achieving the top specified level in flooring.
3.18.2.2 The Indian patent stone floor unless otherwise stated, shall have a
total thickness of 50 mm laid in two layers. The under-bed shall consist
of 25mm thick cement concrete with 10 mm to 6mm size stones.The
proportion of the mix shall be 1 part cement, 2 parts sand and 4 parts
stone chips by volume. Second layer 15mm shall be with 6mm down
aggregates of above proportion
commencement of laying the under bed, thick cement slurry (cement &
water) shall be given on clean surface and then the under bed layer
shall be laid.
3.18.2.4 The floor shall be cast in panels not exceeding 5 sq.m. in area and
no side more than 2.5 m long. The casting sequence shall be in a
chequered board fashion, no two adjacent panels being cast before the
contraction of the previous one has taken place. The edge of each
panel into which the floor is divided shall be supported by flat bars of
steel or glass strips duly oiled to prevent sticking. The bars shall be
removed before filling in adjoining panels. At least 48 hours shall elapse
before the concreting in the adjacent bay is commenced. After laying,
the underbed shall be leveled, compacted and brought to proper grade
with a screed or float. PVC/Glass floor separator of approved make
shall be used between the panels with the approval of Engineer. Unit
rate quoted shall be inclusive of preparation of base, cement slurry
application, underbed and the topping coat and the finishing including
cost of all labour, tools and materials and the PVC/GLASS separators
between adjacent panels.
3.18.3.1 Measurement shall be for the plan area of flooring and for the
finished work.
3.19.1 The contractor shall submit full details of the system with catalogues etc. he
proposes to adopt for this work. The contractor shall ensure strict
adherence to all the steps given therein to ensure good quality work.
However, it shall be the contractor's entire responsibility to complete the
works to the satisfaction of the Engineer. The contractor shall mobilize to
the site adequate manpower and all the equipment necessary for this work.
Standby arrangement of equipment and power shall also be made to
ensure uninterrupted work.
3.19.2 WORKMANSHIP
3.19.2.2 The mat and pump shall then be removed and mechanically
operated power floats shall be rotated on the wet concrete surface. The
process shall be repeated and the surface shall be finally finished with
minimum two passes of power trowel.
3.19.2.3 The finished surface shall then be covered with a polythene sheet
the following day after sprinkling water on the surface. Ponding of water
shall be carried out after 2-3 days and the surface shall be kept wet
continuously for at least 21 days. ISSUE
R4
3.19.3 MEASUREMENT
ISSUE
R4
4.1 GENERAL
4.1.1 This specification covers the general requirements for finishing the
plastered brick / concrete surfaces with Plaster of Paris and other related
works forming a part of this job, which may be required to be carried out
though not specifically mentioned above. The work under this specification
shall consist of furnishing of all tools, plants, labour, materials and
everything necessary for carrying out the work.
4.2.1 Work shall be carried out as per latest edition of Indian Standards and Code
of Practices. List given here shall not be considered as conclusive and is for
reference and guidance only. Any discrepancies/ conflict noticed shall be
brought to the notice of Architect/Engineer in charge for direction / approval.
However, as a general rule more stringent specification shall take
precedence.
ISSUE
R4
4.3.1 MATERIALS
4.3.1.1 The plaster of Paris powder shall conform to the requirements of IS:
2333.
4.3.2 WORKMANSHIP
4.3.2.1 The plaster on masonry surface shall be allowed to dry before the POP
punning is applied.
4.3.2.3 The POP shall be laid and rubbed and finally trowelled to a fine uniform
smooth finish. All unevenness shall be rubbed down from top to bottom
in one operation to eliminate joint marks.
4.4.1 MATERIALS
4.4.1.1 Water resistant white cement based putty ideal for use on concrete /
mortar walls (internal and external) and ceiling.
4.4.2 WORKMANSHIP
4.4.2.2 Mixing of putty:Putty shall be mixed with 30-35% clean water slowly to
make a paste. Mixing shall be continued for 10-15 minutes till a uniform
paste is formed. ISSUE
R4
4.4.2.4 Marks if any shall be removed with the help of moist sponge or the
surface shall be rubbed very gently with putty blade. The surface shall
be allowed to dry completely.
4.4.2.5 Only the required quantity of putty shall be prepared at a time and shall
be used within 2-3 hours of mixing of water. The total thickness of the
coats should be limited to maximum 1.5 mm. If required, to remove
unevenness of surface before applying any kind of paint/ distemper,
walls / ceiling surface shall be leveled gently with very fine water proof
emery paper of not less than 5900 number to get a glossy white
surface.
4.4.3.1 Material received at site shall be with original packing and labels. It
ISSUE
shall be intact till issued for use of site. R4
4.4.3.2 Material shall be stored at properly covered dry location and shall be
safe from damage.
4.4.4 MEASUREMENT
4.4.4.1 Measurement for white cement based putty work shall be in sq. m
correct to two places of decimal. Unless a separate item is provided for
grooves, mouldings etc., these works are deemed to be included in the
unit rates quoted for putty work.
4.4.4.2 The quantity of work to be paid for under these items shall be
calculated by taking the projected surface of the areas plastered after
making necessary deductions for openings for doors, windows, exhaust
fan openings etc. The actual plaster work carried out on jambs/sills of
windows, openings, etc. shall be measured for payment.
4.5.1 The proportions of the cement mortar for plastering shall be 1:4 (one part of
cement to four parts of sand) unless otherwise specified under the
respective item of work. Cement and sand shall be mixed thoroughly in dry
condition and then water added to obtain a workable consistency. The
quality of water and cement shall be as per relevant IS. The quality and
grading of sand for plastering shall conform to IS:1542. The mixing shall be
done thoroughly in a mechanical mixer unless hand mixing is specifically
permitted by the ENGINEER. If so desired by the ENGINEER sand shall
be screened and washed to meet the specification requirements. The
mortar thus mixed shall be used as soon as possible preferably within 30
minutes from the time water is added to cement. In case the mortar has
stiffened due to evaporation of water this may be re-tempered by adding
water as required to restore consistency but this will be permitted only upto
30 minutes from the time of initial mixing of water to cement. Any mortar
which is partially set shall be rejected and removed forthwith from the site. ISSUE
R4
Droppings of plaster shall not be re-used under any circumstances.
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
WRITE UP
TCE.M4-419-01
GENERAL BUILDING WORKS SHEET 61 of 174
4.5.2 WORKMANSHIP
4.5.2.3 All joints in masonry shall be raked as the work proceeds to a depth of
l0mm/20mm for brick/stone masonry respectively with a tool made for
the purpose when the mortar is still green. The masonry surface to be
rendered shall be washed with clean-water to remove all dirt, loose
materials, etc., Concrete surfaces to be rendered shall be roughened
suitably by hacking or bush hammering for proper adhesion of plaster
and the surface shall be evenly wetted to provide the correct suction.
The masonry surfaces should not be too wet but only damp at the time
of plastering. The dampness shall be uniform to get uniform bond
between the plaster and the masonry surface.
4.5.3 Interior plain faced plaster - This plaster shall be laid in a single coat of
13mm thickness. The mortar shall be dashed against the prepared surface
with a trowel. The dashing of the coat shall be done using a strong
whipping motion at right angles to the face of the wall or it may be applied
with a plaster machine. The coat shall be trowelled hard and tight forcing it
to surface depressions to obtain a permanent bond and finished to smooth
surface. Interior plaster shall be carried out on jambs, lintel and sill faces,
etc. as shown in the drawing and as directed by the ENGINEER. Rate
quoted for plaster work shall be deemed to include for plastering of all these
surfaces.
4.5.4 Plain Faced Ceiling plaster - This plaster shall be applied in a single coat of
6mm thickness. The proportion of cement mortar shall be 1:3.
4.5.5 Exterior plain faced plaster - This plaster shall be applied in 2 coats. The ISSUE
first coat or the rendering coat shall be approximately 14mm thick. The R4
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
WRITE UP
TCE.M4-419-01
GENERAL BUILDING WORKS SHEET 62 of 174
4.5.6 Interior plain faced plaster 20mm thick if specified for uneven faces of brick
walls or for random/coursed rubble masonry walls shall be executed in 2
coats.
4.5.7 Exterior Sand Faced Plaster - This plaster shall be applied in 2 coats. The
first coat shall be 14mm thick and the second coat shall be 6mm thick.
However, only approved quality white sand shall be used for the second
coat and for the finishing work. Sand for the finishing work shall be coarse
and of even size and shall be dashed against the surface and sponged.
4.5.7.1 The mortar proportions for the first and second coats shall be as
specified in the respective items of work.
4.5.7.2 Wherever more than 20mm thick plaster has been specified, which is
intended for purposes of providing beading, bands, etc. this work shall
be carried out in two or three coats as directed by the ENGINEER duly
satisfying the requirements of curing each coat (rendering/floating) for a
minimum period of 2 days and curing the finished work for atleast 7
days.
4.5.7.3 In the case of pebble faced finish plaster, pebbles of approved size and
quality shall be dashed against the final coat while it is still green to
ISSUE
R4
4.5.7.5 Curing of plaster shall be started as soon as the applied plaster has
hardened sufficiently so as not to be damaged when watered. Curing
shall be done by continuously applying water in a fine spray and shall
be carried out for atleast 7 days.
4.5.7.6 When the specification items of work calls for waterproofing plaster the
CONTRACTOR shall provide the waterproofing compound as specified
while preparing the cement mortar. Payment for water-proofing
compound will be made separately if it is not included as a combined
item of work.
4.5.7.7 Where lath plastering is specified, it shall be paid for at the same rate
as for plaster work except that separate payment for metal lath will be
made.
4.5.7.9 The finished plaster surface shall not show any deviation more than
4mm when checked with a straight edge of 2m length placed against
the surface.To overcome the possibility of development of cracks in the
plastering work following measures shall be adapted. ISSUE
R4
4.5.8 MEASUREMENT
4.5.8.1 Measurement for plastering work shall be in sq.m correct to two places
of decimal. Unless a separate item is provided for grooves, mouldings,
etc., these works are deemed to be included in the unit rates quoted for
plastering work. The quantity of work to be paid for under these items
shall be calculated by taking the projected surface of the areas
plastered after making necessary deductions for openings for doors,
windows, fan openings etc. The actual plaster work carried out on
jambs/sills of windows, openings, etc. shall be measured for payment.
4.6.1 The cement mortar for pointing shall be in the proportion of 1:3 (one part of
cement to three parts of fine sand) unless otherwise specified in the
respective items of work. Sand shall conform to IS:1542 and shall be free
from clay, shale, loam, alkali and organic matter and shall be of sound,
hard, clean and durable particles. Sand shall be approved by ENGINEER
and if so directed it shall be washed/screened to meet specification
requirements.
4.6.2 WORKMANSHIP
4.7 Any dust/dirt in the raked joints shall be brushed out clean and the joints shall
be washed with water. The joints shall be damp at the time of pointing.
Mortar shall be filled into joints and well pressed with special steel trowels.
The joints shall not be disturbed after it has once begun to set. The joints of
the pointed work shall be neat. The lines shall be regular and uniform in
breadth and the joints shall be raised, flat, sunk or 'V' as may be specified in
the respective items of work. No false joints shall be allowed.
4.7.1.1 The work shall be kept moist for atleast 7 days after the pointing is
completed. Whenever coloured pointing is to be done, the colouring
pigment of the colour required shall be added to cement in such
proportions as recommended by the manufacturer and as approved by
the ENGINEER.
4.7.2 MEASUREMENT
4.7.2.1 The quantity of work to be paid for under this Item shall be measured in
sq.m correct to two places of decimal by taking the projected surface of
the area pointed after making necessary deductions for openings, etc.
ISSUE
R4
5 PAINTING WORKS
5.1 GENERAL
5.1.1 This specification covers the general requirements for painting of interior
and exterior plastered brick / concrete surfaces and partition walls with
suitable paints and other related works forming a part of this job, which may
be required to be carried out though not specifically mentioned above. The
work under this specification shall consist of furnishing of all tools, labour,
materials and everything necessary for carrying out the work.
5.2.1 Work shall be carried out as per latest edition of Indian Standards and Code
of Practices. List given here shall not be considered as conclusive and is for
reference and guidance only. Any discrepancies/ conflict noticed shall be
brought to the notice of Architect/Engineer in charge for direction / approval.
However, as a general rule more stringent specification shall take
precedence.
ISSUE
R4
5.3.1 MATERIALS
5.3.1.1 All paint products shall have no added lead, mercury, chromium,
arsenic and antimony content.
5.3.1.2 Oil bound distemper shall conform to IS: 428. The primer shall be alkali
resistant primer of the same manufacture as that of the distemper.
5.3.1.3 Cement paint shall conform to IS: 5410. The primer shall be a thinned
coat of cement paint.
5.3.1.6 Lead free acid, alkali and chlorine resisting paint shall conform to IS:
9862.
5.3.1.7 All paints shall have low VOC with VOC for non flat (gloss finish) paints
shall be 150g/l and VOC for flat (mat finish) paint shall be 50 g/l.
5.3.1.8 White wash shall be made from good quality fat lime conforming to IS:
712. It shall be slaked at site and mixed with water in the proportion of 5
litres of water to 1 kg of un-slaked lime stirred well to make a thin
cream. This shall be allowed to stand for a minimum period of one day
and strained through a clean coarse cloth. Four kg of gum dissolved in
hot water shall be added to each cu.m of cream. 1.30 kg of sodium
chloride dissolved in hot water shall then be added per 10 kg of lime
used for the white wash to be ready for application.
5.3.1.10 All the materials shall be of the best quality from an approved
manufacturer. CONTRACTOR shall obtain prior approval of the
ENGINEER for the brand of manufacture and the colour/shade. All
materials shall be brought to the site of works in sealed containers.
5.3.2 WORKMANSHIP
5.3.3 WHITE WASH - The prepared surfaces shall be wetted and the finish
applied by brushing. The operation for each coat shall consist of a stroke of
the brush first given horizontally from the right and the other from the left
and similarly, the subsequent stroke from bottom upwards and the other
from top downwards, before the first coat dries. Each coat shall be allowed
to dry before the next coat is applied. Minimum of 2 coats shall be applied
unless otherwise specified in the item of work. The dry surface shall present
a uniform finish without any brush marks.
5.3.4 COLOUR WASH - Colour wash shall be applied in the same way as for
white wash. A minimum of 2 coats shall be applied unless otherwise
ISSUE
specified in the item of work. The surface shall present a smooth and R4
uniform finish without any streaks. The finished dry surface shall not show
any signs of peeling/powdery and come off readily on the hand when
rubbed.
5.3.5 CEMENT PAINT - The prepared surfaces shall be wetted to control surface
suction and to provide moisture to aid in proper curing of the paint. Cement
paint shall be applied with a brush with stiff bristles. The primer coat shall
be a thinned coat of cement paint. The quantity of thinner shall be as per
manufacturer's instructions. The coats shall be vigorously scrubbed to work
the paint into any voids for providing a continuous paint film free from
pinholes for effective water- proofing in addition to decoration. Cement paint
shall be brushed in uniform thickness and the covering capacity for two
coats on plastered surfaces shall be 3 to 4 kg/sq.m. A minimum of 2 coats
of the same colour shall be applied unless otherwise specified in the item of
work. At least 24 hours shall be left after the first coat to become sufficiently
hard before the second coat is applied. The painted surfaces shall be
thoroughly cured by sprinkling with water using a fog spray at least 2 to 3
times a day. Curing shall commence after about 12 hours when the paint
hardens. Curing shall be continued for at least 2 days after the application
of final coat. Paint may also be applied using rollers.
5.3.6 OIL BOUND DISTEMPER - The prepared surfaces shall be dry and
provided with one coat of alkali resistant primer by brushing. The surface
shall be finished uniformly without leaving any brush marks and allowed to
dry for at least 48 hours. A minimum of two coats of oil bound distemper
shall be applied unless otherwise specified in the item of work. The first
coat shall be of a lighter tint. At least 24 hours shall be left after the first coat
to become completely dry before the application of the second coat. Broad,
stiff, double bristled distemper brushes shall be used for the work. Paint
may also be applied using rollers.
5.3.7 PLASTIC EMULSION PAINT - The prepared surface shall be dry and
provided with one coat of primer which shall be a thinned coat of emulsion
paint. The quantity of thinner shall be as per manufacturer's instructions. ISSUE
R4
The paint shall be laid an evenly and smoothly by means of crossing and
laying off. The crossing and laying off consists of covering the area with
paint, brushing the surface hard for the first time over and then brushing
alternately in opposite directions two or three times and then finally
brushing lightly in a direction at right angles. In this process, no brush
marks shall be left after the laying off is finished. The full process of
crossing and laying off constitutes one coat. The next coat shall be applied
only after the first coat has dried and sufficiently become hard which
normally takes about 2 to 3 hours. A minimum of 2 finishing coats of the
same colour shall be applied unless otherwise specified in the item of work.
Paint may also be applied using rollers. The surface on finishing shall
present a flat velvety smooth finish and uniform in shade without any
patches. Paint may also be applied using rollers.
5.3.8 ACRYLIC EMULSION PAINT - Acrylic emulsion paint shall be applied in the
same way as for plastic emulsion paint. A minimum of 2 finishing coats over
one coat of primer shall be provided unless otherwise specified in the item
of work. Paint may also be applied using rollers.
5.3.10 SYNTHETIC ENAMEL PAINT - The prepared surface shall be dry and
provided with one coat of primer which shall be a thinned coat of enamel
paint. The quantity of thinner shall be as per manufacturer's instructions.
The paint shall be laid on evenly and smoothly by means of crossing and
laying off. The crossing and laying off consists of covering the area with
paint, brushing the surface hard for the first time over and then brushing
alternately in opposite directions two or three times and then finally
brushing lightly in a direction at right angles. In this process, no brush
marks shall be left after the laying off is finished. The full process of
crossing and laying off constitutes one coat. The next coat shall be applied
only after the first coat has dried and sufficiently become hard which ISSUE
R4
5.3.11 ACRYLIC DISTEMPER - The prepared surfaces shall be dry and provided
with one coat of alkali resistant primer by brushing. The surface shall be
finished uniformly without leaving any brush marks and allowed to dry for at
least 48 hours. A minimum of two coats of acrylic distemper shall be
applied, unless otherwise specified. The first coat shall be of a lighter tint. At
least 24 hours shall be left after the first coat to become completely dry
before the application of the second coat. Broad, stiff, double bristled
distemper brushes shall be used for the work. The operations for brushing
each coat shall be as detailed above.
5.4.1 MATERIALS
5.4.6 All the materials shall be of the best quality from an approved manufacturer.
CONTRACTCOR shall obtain prior approval of the ENGINEER for the
brand of manufacture and the colour/shade. All materials shall be brought
to the site of works in sealed containers.
5.4.7 WORKMANSHIP
5.4.7.1 The type of finish to be provided for woodwork, either for painting or
polishing, the number of coats, etc. shall be as specified in the
respective items of work.
ISSUE
R4
5.4.7.2 Primer and finish paint shall be compatible with each other to avoid,
cracking and wrinkling. Primer and finish paint shall be from the same
manufacturer.
5.4.7.4 All the wood surfaces to be painted shall be thoroughly dry and free
from any foreign matter. Surfaces shall be smoothened with abrasive
paper using it across the grains and dusted off. Wood primer coat shall
then be applied uniformly by brushing. The number of primer coats shall
be as specified in the item of work. Stopping as per IS 426 shall be
used to fill up large holes & cracks on the surface. For small holes or
minor cracks, fillers as per IS 110 should be used. Any slight
irregularities of the surface shall then be made up by applying an
optimum coat of filler conforming to IS: 110 and rubbed down with an
abrasive paper for obtaining a smooth surface for the undercoat of
synthetic enamel paint conforming to IS: 2932.
5.4.7.6 All the wood surfaces to be provided with clear finishes shall be
thoroughly dry and free from any foreign matter. Surfaces shall be
smoothened with abrasive paper using it in the direction of the grains
and dusted off. ISSUE
R4
5.4.7.8 After the surface is dry, a suitable sealer shall be applied to prevent
bleeding of stain and filler into the finish coat. The surface shall be
rubbed down lightly, wiped off and allowed to dry.
5.4.7.9 Over this prepared surface, varnish conforming to IS: 337 shall be
applied by brushing. Varnish should not be retouched once it has begun
to set. Staining if required shall be provided as directed by the
ENGINEER. When two coats of varnish is specified, the first coat
should be a hard-drying undercoat or flatting varnish which shall be
allowed to dry hard before applying the finishing coat. The number of
coats to be applied shall be as per the item of work.
5.4.7.10 For works where clear finish of French polish is specified the
prepared surfaces of wood shall be applied with the polish using a pad
of woollen cloth covered by a fine cloth. The pad shall be moistened
with polish and rubbed hard on the surface in a series of overlapping
circles to give an even finish over the entire area. The surface shall be
allowed to dry before applying the next coat.
5.4.7.11 Finishing shall be carried out using a fresh clean cloth over the
pad, slight dampening with methylated spirit and rubbing lightly and
quickly in circular motions. The finished surface shall have a uniform
texture and high gloss. The number of coats to be applied shall be as
per the item of work.
5.4.8 MOCK-UP
5.4.8.1 The contractor shall prepare and install mock-up samples as per
approved shop drawings. ISSUE
R4
5.4.8.2 Mock-up samples shall be of full size and shall be true representation of
actual works to be carried out at site. Mock-ups may be part of
completed work if undisturbed.
5.4.9.1 Material received at site shall be with original packing and labels. It
shall be intact till issued for use of site.
5.4.9.2 Material shall be stored at properly covered dry location and shall be
safe from damage.
5.4.9.3 Paints shall be kept covered at all times and mixing shall be done in
suitable containers.
5.4.10 MEASUREMENT
5.4.10.3 For openings exceeding 0.5 sq.m. but not exceeding 3.0 sq.m.,
deductions shall be made for half the area of openings and no additions
shall be made for jambs, sills etc.
5.4.10.4 For openings exceeding 3.0 sq.m., deductions shall be made for
the whole area and additions shall be made for jambs, sills, soffits etc.
5.4.10.5 No extra payment shall be made for painting etc. done around
openings, wall features like grooves, projections, cornices etc.
ISSUE
R4
5.4.10.6 Rate quoted shall take into account the provision of necessary
enabling works such as scaffolding, painter's cradle etc.
ISSUE
R4
6.1 GENERAL
6.1.1 This specification covers the general requirements for doors, windows and
ventilators and other related works forming a part of this job, which may be
required to be carried out though not specifically mentioned above. The
work under this specification shall consist of furnishing of all tools and
tackles, plants, labour, materials and everything necessary for carrying out
the work.
6.2.1 Work shall be carried out as per latest edition of Indian Standards and Code
of Practices. List given here shall not be considered as conclusive and is for
reference and guidance only. Any discrepancies/ conflict noticed shall be
brought to the notice of Architect/Engineer in charge for direction / approval.
However, as a general rule more stringent specification shall take
precedence.
6.3.1 MATERIALS
6.3.1.1 Timber to be used shall be first class Teak wood as per IS: 4021.
Timber shall be of the best quality and well seasoned by a suitable
process before being planed to the required sizes. The maximum
permissible moisture content shall be from 10 to 16 percent for timber
50mm and above in thickness and 9 to 14 percent of timber less than
50mm in thickness for different regions of the country as stipulated In
IS: 287. Timber shall be close grained, of uniform colour and free from
decay, fungal growth, boxed heart, pitch pockets or streaks on the
exposed edges, borer holes, splits and cracks.
6.3.1.2 Flush door shutters of the solid core type with plywood face panels shall
conform to IS: 2202 (Part 1) and with particle board/hard board face
panels shall conform to IS: 2202 (Part 2).
6.3.1.3 Transparent sheet glass shall conform to the requirements of IS: 2835.
Wired and figured glass shall be as per IS: 5437.
6.3.1.4 Builder's hardware of fittings and fixtures shall be of the best quality
from approved manufacturers.
6.3.2 WORKMANSHIP
6.3.2.2 All works shall be executed as per the detailed drawings and/or as
directed by the ENGINEER.
6.3.2.3 All members of the door, window, and ventilator shall be straight without
ISSUE
any warp or bow and shall have smooth well planed faces. The right R4
6.3.2.4 Frames shall have mortise and tenon joints which shall be treated with
an approved adhesive and provided with metal or wood pins. The
vertical members of the door frame shall project 50 mm below the
finished floor level with a spacer bar. The finished dimension of frames
shall be rebated on the solid for keying with the plaster and for receiving
the shutters. The depth of rebate for housing the shutter shall be 15
mm. The size of the frames shall be as specified in the respective items
of work. The workmanship shall generally conform to the requirements
specified in IS: 4021.
6.3.2.5 The face of the frames abutting the masonry or concrete shall be
provided with a coat of coal tar.
6.3.2.7 Timber panelled shutters for doors, windows and ventilators shall be
constructed in the form of framework of stiles and rails with panel
insertion. The panels shall be fixed by either providing grooves in the
stiles and rails or by beading. Glazing bars shall be as detailed in the
drawings. The stiles and rails shall be joined by mortise and tenon joints
at right angles. All members of the shutter shall be straight without any
warp or bow and shall have smooth, well planed faces at right angles to
each other. The right angle for the shutter shall be checked by
measuring the diagonals and the difference shall not be more than + 3
mm. Timber panels made from more than one piece shall be jointed
with a continuous tongued and grooved joint, glued together and ISSUE
R4
6.3.2.8 Details of the wooden flush door shutters, solid core type with specific
requirement of the thickness, core, face panels, viewing glazed panel,
Venetian louver opening, teak wood lipping etc. shall be as indicated in
the respective items of work. Panels of shutter shall be of marine
plywood conforming to IS: 710, if so specified in the item of work. Flush
door shutters shall be from reputed manufacturers and CONTRACTOR
shall submit test results as per IS: 4020, if so desired by the
ENGINEER.
6.3.2.9 The material of the fittings and fixtures either of chromium plated steel,
cast brass, copper oxidized or anodized aluminum shall be as specified
in the item of work. The number, size and type of the fittings and
fixtures shall be as indicated in the drawings/item of work.
6.3.2.10 Wood work shall not be provided with the finishes of painting,
galvanizing etc. unless it has been approved by the ENGINEER. The
type of finish and the number of coats shall be as stipulated in the
respective items of work. Preparation of the wood surface and
application of the finishes shall be as per Painting and Polishing of
wood works.
6.4.1.1 Hot rolled steel sections for the fabrication of steel doors, windows and
ventilators shall conform to IS: 7452, which are suitable for single
glazing.
6.4.1.2 Pressed steel door frames for steel flush doors shall be out of 1.25 mm
thick mild steel sheets of profiles as per IS:4351.
6.4.1.3 Transparent sheet glass shall conform to the requirements of IS: 2835.
Wired and figured glass shall be as per IS: 5437.
6.4.1.4 Builder's hardware of fittings and fixtures shall be of the best quality
from approved manufacturers.
6.4.2 WORKMANSHIP
6.4.2.1 All steel doors, windows and ventilators shall be of the type as specified
in the respective items of work and of sizes as indicated in the
drawings. Steel doors, windows and ventilators shall conform to the
requirements as stipulated in IS: 1038. Steel windows shall conform to
IS: 1361, if so specified.
6.4.2.4 For windows with fly proof mesh as per the item of work, rotor operator
arrangement, for the operation of the glazed shutters from the inside
shall be provided.
6.4.2.5 Pressed steel door frames shall be provided with fixing lugs at each
jamb, hinges, lock-strike plate, mortar guards, angle threshold, shock-
absorbers of rubber or similar material as per the requirements of
IS:4351. Pressed steel door frames shall be fixed as 'built-in', as the
masonry work proceeds. After placing it plumb at the specified location,
masonry walls shall be built up solid on either side or each course
grouted with mortar to ensure solid contact with the door frame, without
leaving any voids. Temporary struts across the width shall be fixed,
during erection to prevent bow/sag of the frame.
6.4.2.7 Doors, windows and ventilators shall be fixed into the prepared
openings. They shall not be 'built-in' as the masonry work proceeds, to
avoid distortion and damage of the units. The dimensions of the
masonry opening shall have l0mm clearance all-round the overall
dimensions of the frame for this purpose. Any support of scaffolding
members on the frames/glazing bars is prohibited.
ISSUE
R4
6.4.2.8 Glazing of the units shall be either with flat transparent glass or
wired/figured glass of the thickness as specified in the item of work. All
glass panels shall have properly squared corner and straight edges.
Glazing shall be provided on the outside of the frames.
6.4.2.9 Fixing of the glazing shall be either with spring glazing clips and putty
conforming to IS: 419 or with metal beads. Pre-formed PVC / VINYL or
rubber gasket shall be provided for fixing the beads with concealed
screws. The type of fixing the glazing shall be as indicated in the item of
work and/or in drawings.
6.4.2.10 Steel doors, windows and ventilators shall be provided with finish
of either painting as specified or shall be hot dip galvanized with
thickness of zinc coating as stipulated all as described in the respective
items of work.
6.4.2.12 Installation of the units with fixing lugs, screws, mastic caulking
compound at the specified locations shall generally conform to the
requirements of IS:1081. Necessary holes etc required for fixing shall
be made by the CONTRACTOR and made good after installation.
Workmanship expected is of a high order for efficient and smooth
operation of the units.
ISSUE
R4
6.5.1 MATERIALS
6.5.1.1 Aluminum alloy used in the manufacture of extruded sections for the
fabrication of doors, windows, ventilators shall conform to designation
63400 WP of IS:733.
6.5.1.2 Transparent sheet glass shall conform to the requirements of IS: 2835.
Wired and figured glass shall be as per IS: 5437.
6.5.1.3 Builder's hardware of fittings & fixtures shall be of the best quality from
approved manufacturers.
6.5.2 WORKMANSHIP
6.5.2.1 All aluminum doors, windows, and ventilators shall be of the type as
specified in the respective items of work and of sizes as indicated in the
drawings. The doors, windows, ventilators shall conform to the
requirements of IS: 1948. Aluminum windows, shall conform to IS:
1949, if so specified.
6.5.2.4 Aluminum swing type doors, aluminum sliding windows, partitions shall
be as described in the item of work and/or bid drawings which indicates
ISSUE
generally the arrangement along with the overall size of the various R4
6.5.2.6 The framework of the partitions with mullions and transoms shall be
with anodized/powder coated aluminum box sections of dimensions as
per the item of work. Anodized/powder coated Aluminum box sections
shall be in-filled with timber of class 3 (silver oak or any other
equivalent) as per IS:4021. Panels of double/single glazing/plywood
shall be fixed as per details indicated in the drawing. Partitions shall be
fixed rigidly between the floor and the structural columns/beams
including provision of necessary shims for wedging etc. Finished work
shall be of rigid construction, erected truly plumb to the lines and levels,
at locations as per the construction drawings.
6.6.1 MATERIALS
6.6.1.2 The type viz. self coiling type (manual) for clear areas up to 12 sq.m,
gear operated type (mechanical) for clear areas up to 35 sq.m and
electrically operated type for areas up to 50 sq.m shall be as specified
in the IS Code 6248. Mechanical type shall be suitable for operation
from both inside and outside with the crank handle or chain gear
operating mechanism duly considering the size of wall/column.
Electrical type shall also be provided with a facility for emergency
mechanical operation.
6.6.2 WORKMANSHIP
6.6.2.1 Rolling shutters / grill shall be supplied duly considering the type,
specified clear width/height of the opening and the location of fixing as
indicated in the drawings.
6.6.2.2 Rolling Shutter curtain shall be built-up of interlocking laths 75mm width
between rolling centers formed from cold rolled steel strips. The
thickness of the steel strip shall not be less than 0.90 mm for shutters
up to 3.50m width and not less than 1.20 mm for shutters above 3.50 m
width. Each lath section shall be continuous single piece without any
welded joint.
6.6.2.3 Fabrication and assembly of rolling grill curtain shall have the type of
links and other additional requirements as specified in the item of
works.
6.6.2.4 The guide channels out of mild steel sheets of thickness not less than
3.15 mm shall be of either rolled, pressed or built up construction. The
channel shall be of size as stipulated in IS: 6248 for various clear width
of the shutters / grill.
ISSUE
R4
6.6.2.5 Hood covers shall be of mild steel sheets not less than 0.90mm thick
and of approved shape.
6.6.2.6 Rolling shutters / grill shall be provided with a central hasp and staple
safety device in addition to one pair of lever locks and sliding locks at
the ends.
6.6.2.7 Where a rolling shutter is combined with rolling grill, height of rolling grill
shall be 500mm maximum.
6.6.2.8 All steel components (excepting springs and insides of guide channels)
shall be provided with one coat of zinc chrome primer conforming to IS:
2074 at the time of work.
6.6.2.9 Where galvanizing is called for, the curtain sections, guides, lock plate,
bracket plates, suspension shaft and the hood cover shall be hot dip
galvanized with a zinc coating containing not less than 97.5 percent
pure zinc. The weight of the zinc coating per sq.m shall be as specified
in the item of work.
ISSUE
R4
6.7.1.3 Size of the frame and material for frames will be decided as per project
requirement.
6.7.1.5 The module should be provided with short circuit proof power supply
unit for power rating of 220/240 V, 50/60 Hz. A power point will be
made available at a suitable location by electrical contractor.
6.7.1.6 The door shall have facilities for activation by infrared movement
detector on both sides.
6.7.1.10 Both the fixed and sliding panels shall be made of 12 mm thick
toughened glass with or without etching. It should be provided with all
required fittings and fixtures, digital entry – exit function on the top and
electro- mechanical locking system.
ISSUE
R4
6.8.1 MATERIALS
6.8.1.1 The UPVC windows shall be made of high quality UPVC profile section
and GI/Aluminum reinforcement.
6.8.1.2 Generally, the UPVC windows shall comprise of main profiles for outer
frames and shutters, beads, coupling mullions, bays and reinforcement.
6.8.1.3 The windows shall be non combustible, non corrosive, shall have good
sound and heat insulation properties, shall withstand harsh weather
conditions and desert conditions and shall not form stains, blisters or
corrosion in salty conditions.
6.8.2 WORKMANSHIP
6.8.2.1 Fabrication and erection of windows shall be done as per the approved
fabrication drawings.
6.8.2.4 Drainage slots shall be provided in the outer chamber of the profile. All
horizontal members, except heads of the outer frame, shall have
drainage slots of min 5mm wide and 30mm long.
6.8.2.5 EPDM weather seals shall be fitted in the continuous lengths, inserted
in the weather seal grooves. Joints in the vent weather seals shall be
placed at the bottom and at top in the outer frame.
6.8.2.6 Friction stays shall be of high quality stainless steel and nylon
component for improved durability.
ISSUE
R4
6.8.2.11 Contractor shall provide warranty for installed hand railing system
for the period described herein, starting from date of completion of
installation work. When notified in writing from Owner,
contractor/installer shall promptly correct the said deficiencies, without
inconvenience and extra cost to owner.
6.8.3 MOCK-UP
6.8.3.1 The contractor shall prepare and install mock-up samples as per
approved shop drawings.
6.8.3.2 Mock-up samples shall be of full size and shall be true representation of
actual works to be carried out at site. Mock-ups may be part of
completed work if undisturbed.
ISSUE
R4
6.8.4.3 Finished shop work shall not be installed in any room or space where
concrete, masonry, or plaster work is not completed and dry.
6.8.4.4 Contractor shall use all means necessary to protect doors, windows
and associated fittings from damage prior to, during, and after
installation. All damaged items shall be repaired or replaced by the
contractor at no cost to the owner.
6.8.5 MEASUREMENT
6.8.5.3 Rate quoted shall be for all the works including glazing, painting,
builder's hardware of fittings and fixtures as specifically described in the
respective items of work.
ISSUE
R4
7.1 GENERAL
7.1.1 This specification covers the general requirements for hardware such as
hinges, locks, stays, stoppers, handles etc. for doors, windows, and
ventilators and other related works forming a part of this job, which may be
required to be carried out though not specifically mentioned above. The
work under this specification shall consist of furnishing of all tools, labour,
materials and everything necessary for carrying out the work.
7.2.1 Work shall be carried out as per latest edition of Indian Standards and Code
of Practices. List given here shall not be considered as conclusive and is for
reference and guidance only. Any discrepancies/ conflict noticed shall be
brought to the notice of Architect/Engineer in charge for direction / approval.
However, as a general rule more stringent specification shall take
precedence.
IS: 7197 Double action floor springs (without oil check for
heavy doors)
IS: 7534 Mild steel bolts with holders for pad locks
IS: 7881 Glossary of items relating to building hardware
ISSUE
R4
7.3.1 All ironmongery shall be of first quality and shall be obtained from an
approved manufacturer. Butt hinges shall be aluminum alloy, stainless steel
or brass as specified with double stainless steel washers.
7.3.2 The size, materials, finishes, type and quality of ironmongery shall be as
described in the schedule of ironmongery.
7.3.3 Unless otherwise shown and/or scheduled in the drawings, the contractor
shall supply and fix all ironmongery as listed in the Schedule of
Ironmongery attached in the project document, complete with fixing screws
of the same material and finish.
7.3.4 Proper sockets shall be provided for all bolts to fix flush in floors, cills and
door/window/ventilator frames. Each lock shall be provided with minimum
two keys and no two locks shall have identical keys, unless specifically
required.
7.3.5 The use of nails for fixing ironmongery will not be permitted. The Contractor
shall hand over all work in a finished state and to the satisfaction of owner.
7.3.6 On completion of all locks, catches and similar items of ironmongery they
are to be properly cleaned, tested and oiled, and all keys are to be clearly
labeled. All locks provided shall be anti theft.
7.4 MOCK-UP
7.4.1 Contractor shall prepare full size mock-up after sample approval for typical
Doors and Windows and install at location approved by owner for final
approval at no extra cost as specified in the Special Conditions of the
Contract.
7.5.1 The material shall be supplied in the manufacturer‘s original packages and
containers with labels intact and legible, including installation instructions,
templates and maintenance manuals, if any.
7.5.3 Any items or parts which are damaged or defaced or found to be defective
shall be replaced at the Contractor‘s expense before handing over.
7.6 IRONMONGERY
7.6.2 The contractor shall submit a schedule of ironmongery for the approval of
the Engineer before placing any supply order. The Engineer‘s approval of
such schedule shall not relieve the contractor from furnishing all items of
hardware required under the contract.
MEASUREMENT
7.7.1 The contractor shall set up the locks for a system of master- keying. Two
change keys shall be furnished for each lockset.
ISSUE
R4
8.1 GENERAL
8.1.1 This part of the specification covers the requirement of providing fitting and
fixing in position of glazing of different thickness comprising of clear float
glass, wired glass, tinted glass, including curtain glass and hermetically
sealed composite double glazing complete with all clips, putty, mastic, etc.
8.2.1 Work shall be carried out as per latest edition of Indian Standards and Code
of Practices. List given here shall not be considered as conclusive and is for
reference and guidance only. Any discrepancies/ conflict noticed shall be
brought to the notice of Architect/Engineer in charge for direction / approval.
However, as a general rule more stringent specification shall take
precedence.
ISSUE
R4
8.3 MATERIALS
8.3.1 All glass and glazing shall have uniform reflective index and free form flaws,
specs and bubbles.
8.3.2 The glass shall be brought to site in the original packing from the
manufacturer and cut to size at site. The cut edges shall be straight and
free from hips, spells or any other damages.
8.3.3 Clear glass shall be float glass and shall be of thickness as specified in the
schedule of items. Properties of float glass shall generally meet the
requirements of IS: 14900.
8.3.4 Wired glass shall be thick rolled glass with centrally embedded wire mesh
of Georgian type conforming to IS: 5437
8.3.5 Composite double glazing shall be made of two 6mm thick clear float glass
on either sides and separated by 12mm air gap. The trapped air shall be
kept dry by means of suitable desiccant. The glass shall be hermetically
sealed. The composite double glazing shall be procured as finished
product.
8.3.6 The curtain glazing shall consist of minimum 8mm thick heat strengthened
glass fixed with framework made of aluminum sections designed as per
structural requirements.
8.3.7 The silicone sealant shall be of best quality and shall be brought to site in
manufacturer's original packing.
8.4 WORKMANSHIP
8.4.1 All glazing clips, putty, mastic etc. shall be provided as required.
8.4.2 All glasses shall be thoroughly cleaned before setting in position. Wherever
required, glass pane shall be held in place by special glazing clips of
approved type. Minimum four glazing clips shall be provided per glass pane
except for large panes where six or more clips shall be used. All holes that
may be necessary on doors/windows/ventilators etc. for holding the clips, ISSUE
R4
glazing beads and all other attachments shall be drilled in position. Glass
panes shall be set without springing, and shall be bedded in putty and back
puttied, except where moulding or gasket are provided.. Putty, mastic etc.
shall be smoothly finished to a true even line.
8.4.3 After completing the glazing work, contractor shall remove all dirt, stains,
excess sealants and clean the glass panes and leave the work in perfectly
acceptable condition. All broken, cracked or damaged glass shall be
replaced by new ones without any extra cost to the owner.
8.4.4 The glass must be protected during installation period so that they will not
be damaged by splashing of cement, welding, grinding etc.
8.4.5 Labels, tapes, adhesives, writing with chalk or any other tool shall never be
done on the coating of glazing.
8.4.7 When assembling and installing the glazing, the coating shall be positioned
as indicated in the drawing.
8.4.8 Glazing shall be carefully done to avoid the contact with metal frames.
8.5 MOCK-UP
8.5.1 The contractor shall prepare and install mock-up samples as per approved
shop drawings.
8.5.2 Mock-up samples shall be of full size and shall be true representation of
actual works to be carried out at site. Mock-ups may be part of completed
work if undisturbed.
8.5.3.1 Material received at site shall be with original packing and labels. It
shall be intact till issued for use of site.
ISSUE
R4
8.5.3.2 Material shall be stored at properly covered dry location and shall be
safe from damage.
8.5.3.3 All items shall be protected from dampness both during and after
delivery to site.
8.5.3.4 Partition shall not be installed in any room or space where concrete,
masonry, or plaster work is not completed and dry.
8.5.3.5 Care must be taken to ensure that the frames and panels of partition
works are not damaged while transporting/erection.
8.5.4 MEASUREMENT
ISSUE
R4
9 PARTITION WORKS
9.1 GENERAL
9.1.1 This specification covers the general requirements for fabrication and
erection of wooden / aluminum / gypsum board partitions and other related
works forming a part of this job, which may be required to be carried out
though not specifically mentioned above. The work under this specification
shall consist of furnishing of all tools, labour, materials and everything
necessary for carrying out the work.
9.2.1 Work shall be carried out as per latest edition of Indian Standards and Code
of Practices. List given here shall not be considered as conclusive and is for
reference and guidance only. Any discrepancies/ conflict noticed shall be
brought to the notice of Architect/Engineer in charge for direction / approval.
However, as a general rule more stringent specification shall take
precedence.
IS: 287 Permissible moisture content for timber used for different
purposes.
IS: 303 Plywood for general purpose
IS: 710 Marine plywood
IS: 733 Wrought aluminum and aluminum alloys, bars, rods
and sections for general engineering purposes.
IS: 848 Synthetic resin adhesive for plywood
IS: 1200 Method of measurement of building and civil
engineering works.
IS: 1328 Veneered decorative plywood
IS: 1868 Anodic coating on aluminum and its alloys.
IS: 1948 Aluminum doors, windows and ventilators
IS: 1949 Aluminum windows for industrial buildings
IS: 2095 Gypsum plaster boards ISSUE
R4
ISSUE
R4
9.3.1 MATERIALS
9.3.1.1 Timber to be used shall be first class Teak wood as per IS: 4021.
Timber shall be of the best quality and well seasoned by a suitable
process before being planed to the required sizes. The maximum
permissible moisture content shall be from 10 to 16 percent for timber
50mm and above in thickness and 9 to 14 percent for timber less than
50mm in thickness for different regions of the country as stipulated In
IS: 287.
9.3.1.2 Timber shall be close grained, of uniform colour and free from decay,
fungal growth, boxed heart, pitch pockets or streaks on the exposed
edges, borer holes, splits and cracks.
9.3.1.3 Transparent sheet glass shall conform to the requirements of IS: 2835.
Wired and figured glass shall be as per IS: 5437.
9.3.1.4 Builder's hardware of fittings and fixtures shall be of the best quality
from approved manufacturers.
9.3.2 WORKMANSHIP
9.3.2.2 All works shall be executed as per the detailed drawings and/or as
directed by the ENGINEER.
9.3.2.3 The framework of the partitions with mullions and transoms shall be
with the sections of dimensions as per the item at work. Panels of
double/single glazing/ plywood shall be fixed as per details indicated in
ISSUE
the drawings. R4
9.3.2.4 Partitions shall be fixed rigidly between the floor and structural
columns/beams including provision of necessary shims for wedging etc.
Finished work shall be of rigid construction, erected truly plumb to the
lines and levels, at locations as per the construction drawings.
9.3.2.5 The face of the frames abutting the masonry or concrete shall be
provided with a coat of coal tar.
9.3.2.6 Glazing of partitions shall be with either flat transparent sheet glass or
figured glass. Transparent sheet glass shall be of 'B' quality as per IS:
2835. The thickness and type of glazing to be provided shall be as
specified in the item of work.
9.3.2.7 The material of the fittings and fixtures either of chromium plated steel,
cast brass, copper oxidized or anodized aluminum shall be as specified
in the item of work. The number, size and type of the fittings and
fixtures shall be as indicated in the drawings/item of work.
9.3.2.8 Wood work shall not be provided with the finishes of painting,
galvanizing etc. unless it has been approved by the ENGINEER. The
type of finish and the number of coats shall be as stipulated in the
respective items of work.
9.3.2.9 Any carpentry work which shows defects due to inadequate seasoning
of the timber or bad workmanship shall be removed and replaced by
CONTRACTOR with work as per specification requirements, at no extra
cost to the OWNER.
9.4.1 MATERIALS
9.4.1.1 Aluminum alloy used in the manufacture of extruded sections for the
fabrication of doors, windows, ventilators shall conform to designation
63400 WP of IS:733. ISSUE
R4
9.4.1.2 Transparent sheet glass shall conform to the requirements of IS: 2835.
Wired and figured glass shall be as per IS: 5437.
9.4.1.3 Builder's hardware of fittings & fixtures shall be of the best quality from
approved manufacturers.
9.4.2 WORKMANSHIP
9.4.2.3 Aluminum partitions shall be as described in the item of work and/or bid
drawings which indicates generally the arrangement along with the
overall size of the various components and weight per running meter of
the extruded sections to be adopted.
9.4.2.4 IS:1948 and IS:1949 are referred to incorporate the sizes, shapes,
thicknesses and weight per running meter of extruded sections for the
various components of the units. However, new sizes, shapes,
thicknesses with modifications to suit snap-fit glazing clips etc. are
continuously being added by various leading manufacturers of extruded
sections, which are available in the market. As such, the sections of the
various components of the unit proposed by the CONTRACTOR, will be
reviewed by the ENGINEER and will be accepted only if they are equal
to or marginally more than that specified in the codes/ item of works.
9.4.2.5 The framework of the partitions with mullions and transoms shall be
with anodized/powder coated aluminum extruded sections of
dimensions as per the item of work. Anodized/powder coated Aluminum
extruded sections shall be in-filled with timber of class 3 (silver oak or
any other equivalent) as per IS:4021. Panels of double/single
ISSUE
glazing/plywood shall be fixed as per details indicated in the drawing. R4
Partitions shall be fixed rigidly between the floor and the structural
columns/beams including provision of necessary shims for wedging etc.
Finished work shall be of rigid construction, erected truly plumb to the
lines and levels, at locations as per the construction drawings.
9.5.1 MATERIALS
9.5.1.2 GI frame shall include 48mm studs (0.55mm thick having one flange of
34mm and another flange of 36mm made of GI steel) placed at 610mm
c/c vertically, in 50mm thick floor and ceiling channel (0.55m,m thick
having equal flanges of 32mm made of GI steel).
9.5.1.3 Glass wool of density 24Kg/cum shall comply with BS: 476 Part 4,
1970.
9.5.2 WORKMANSHIP
9.5.2.1 Single Skin Partition shall consist of 13mm thick plaster board screw
fixed with 25mm dry wall screw at 300mm c/c to either side of stud
framework. Necessary cut-outs shall be provided in the partition to
receive cable raceways, electrical/HVAC fittings and fixtures, which
shall be neatly finished after fixing the fixtures thereby leaving no gaps. ISSUE
R4
Square and tapered edges of the boards shall be jointed and finished to
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
TATA CONSULTING ENGINEERS LIMITED
SPEC. NO. WRITE UP
TCE.M4-419-01 SHEET 107 of
GENERAL BUILDING WORKS
174
9.5.2.2 Double Skin Partition shall include first skin consist of 13mm thick
tapered edge plaster board screw fixed with 25mm dry wall screw at
300mm c/c to either side of stud framework. Necessary cut-outs shall
be provided in the partition to receive cable raceways, electrical/HVAC
fittings and fixtures, which shall be neatly finished after fixing the
fixtures thereby leaving no gaps. The layer shall be finished to take on
second skin in gypsum board/Plywood/ MDF directly. The first skin of
the partition shall be continued up to true ceiling. Second skin shall
consist of 13mm thick tapered edge plaster board screw fixed with
35mm dry wall screw at 300mm c/c to existing first skin of partition.
Care shall be taken that the joints are staggered to avoid leakage.
Finally square and tapered edges of the boards shall be joined and
finished to have a flush look including filling and finishing with jointing
compound, joint paper tape and two coats of drywall top coat suitable
for gypsum board. The second skin of partition shall be stopped 100mm
above false ceiling. Necessary cut-outs shall be provided in the partition
to receive cable raceways, electrical/HVAC fittings and fixtures, which
shall be neatly finished after fixing the fixtures thereby leaving no gaps.
The partition shall be finished to take on wall paper / paint directly by
applying suitable base coats, prime coats etc. complete.Skirting shall
be provided with 100mm high and 12mm thick commercial plywood
backing fixed to gypsum backing and finished with 1.5mm laminate. ISSUE
R4
The skirting shall be flushed to the surface of partition in line and level
and 6mm wide groove to be made in the partition at the junction and
inclusive of SS/Aluminum inserted between the groove formed. The
strip shall be glued to the surface with instant glue of approved make.
The stone/tile shall be fixed to the ply by means of approved
adhesive.50mm thick glass wool insulation of density 24 Kg/cum shall
be wrapped in RP tissues as per manufacturer's specifications. Glass
wool shall be non- combustible and shall be chemically inert.
Application shall not cause or accelerate corrosion.
9.5.3.1 Material received at site shall be with original packing and labels. It
shall be intact till issued for use of site.
9.5.3.2 Material shall be stored at properly covered dry location and shall be
safe from damage.
9.5.3.3 All items shall be protected from dampness both during and after
delivery to site.
9.5.3.4 Partition shall not be installed in any room or space where concrete,
masonry, or plaster work is not completed and dry.
9.5.3.5 Care must be taken to ensure that the frames and panels of partition
works are not damaged while transporting/erection.
9.5.4 MASUREMENT
9.5.4.2 Measurement shall be from out to out of the frames. Rate quoted shall
be for all the works including glazing, painting, builder's hardware of
fittings and fixtures as specifically described in the respective items of
ISSUE
work. R4
10.1 GENERAL
10.1.1 This specification covers the general requirements for fabrication and
erection of aluminum / gypsum board false ceilings and other related works
forming a part of this job, which may be required to be carried out though
not specifically mentioned above. The work under this specification shall
consist of furnishing of all tools, labour, materials and everything necessary
for carrying out the work.
10.2.1 Work shall be carried out as per latest edition of Indian Standards and Code
of Practices. List given here shall not be considered as conclusive and is for
reference and guidance only. Any discrepancies/ conflict noticed shall be
brought to the notice of Architect/Engineer in charge for direction / approval.
However, as a general rule more stringent specification shall take
precedence.
10.3.1 MATERIALS
10.3.1.3 The fiber boards shall be fire resistant, termite and insect resistant,
weather resistant, acoustically satisfactory, dimensionally stable, warp-
free, easily workable, treated with anti-fungus chemicals, heat insulated
and of adequate structural strength and should have good surface finish
as approved by the Owner.
10.3.1.4 The size of fiber board ceiling tile shall generally be 600 x 600 x 12
mm thick. All types of boards and ceiling tiles shall be stored flat under
cover at a clean dry place on firm ground. The Contractor should
ensure that boards are not stacked on termite infected, wet or loose
ground. The boards should be always carried on edges.
10.3.1.5 The metal frame work shall be interlocking type and made of
sections of light metal, such as extruded anodized aluminum. The
shape and cross section shall be such as to facilitate proper suspension
and proper fixing of the ceiling boards covering them and shall be
structurally sound and rigid.
10.3.2 WORKMANSHIP
10.3.2.1 The Contractor shall ensure that the frame to support the ceiling is
designed for its structural strength to withstand the weight of ceiling
boards to be fixed, live load of 75 kg/m2, and other loads such as that
of air- conditioning ducts, grills, electrical wiring and lighting fixtures,
thermal insulation, etc. as shown on the drawings. The Contractor shall
also submit a detailed drawing to show the grid work, sizes of grid
members, method of suspension, position of openings for air-
conditioning and lighting, access doors, etc.
10.3.2.2 The metal frame work of extruded anodized aluminum false ceiling
grid system shall consist of aluminum main members of special T- ISSUE
R4
profile of 32 mm x 32 mm interlocking with each other and run both
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
TATA CONSULTING ENGINEERS LIMITED
SPEC. NO. WRITE UP
TCE.M4-419-01 SHEET 111 of
GENERAL BUILDING WORKS
174
10.3.2.3 In the case of aluminum grid system, boards are just placed into
the frames formed by the main `T' members and the cross members
fitted with the clips for locking the boards. Contractor should take
utmost care so as not to force the boards in position, and a very little
gap is preferable to a tight joint. Fixing fiber boards by adhesives shall
not be permitted unless approved by the Owner. The fiber boards
should be cut with a fine toothed saw, if required.
10.3.2.5 As the work of false ceiling may be interconnected with the work of
air-conditioning ducts and lighting, the Contractor shall fully cooperate
with other agencies entrusted with the above works and who may be
working simultaneously. The Contractor shall provide necessary
openings, in the false ceiling work for air- conditioning, lighting and
other fixtures. Additional framing, if required, for the above openings
shall also be provided at no extra cost to the Owner. Removable or
hinged type inspection or access trap doors shall be provided at
locations specified by the Owner.
10.4.1.1 Thermal Insulation material consisting of boards slabs and rolls of ISSUE
R4
approved manufacturer, shall be of approved thermal conductivity for
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
TATA CONSULTING ENGINEERS LIMITED
SPEC. NO. WRITE UP
TCE.M4-419-01 SHEET 112 of
GENERAL BUILDING WORKS
174
10.4.1.2 The quoted rate shall include supply, delivery, cutting and fixing of
all materials for covering the roof with thermal insulation material,
including wood pegs, slotted angle, G.I rawl plugs, wood/coach screws,
lacing wire, G.I washers, wire mesh, any covering as stipulated in
schedule of prices and quantities, finishing at all levels and elevation
etc., complete.
10.4.2.1 Material received at site shall be with original packing and labels. It
shall be intact till issued for use of site.
10.4.2.2 Material shall be stored at properly covered dry location and shall
be safe from damage.
10.4.2.3 Care must be taken to ensure that the floor tiles are not damaged
while loading / unloading and transporting. Tile packages shall not be
stacked higher than 2m.
10.4.3 MEASUREMENT
10.4.3.1 The superficial area of false ceiling shall be measured and paid for
at the unit rate less deductions, if any. Openings in false ceiling which
are less than 0.4 sq. m in area shall not be deducted for the purpose of
payment.
10.4.3.2 The quoted rates shall include supply, delivery and erection of all
materials for covering the ceiling, frame work suspenders or hangers,
anti-termite treatment making openings in false ceiling, extra frame
ISSUE
R4
10.4.3.4 Where fire barriers are specified, they shall be as per details
shown in drawings and as directed and shall be measured in square
meters and paid for separately.
ISSUE
R4
11 TOILET CUBICLES
11.1 GENERAL
11.1.1 Specification applies to steel toilet partitions / cubicles with doors and
hardware for fixing and mounting of the panels as per architect's design,
plans and schedules. The scope of work includes design, supply,
installation and handling except civil works.
11.2.1 Work shall be carried out as per latest edition of Indian Standards and Code
of Practices. List given here shall not be considered as conclusive and is for
reference and guidance only. Any discrepancies/ conflict noticed shall be
brought to the notice of Architect/Engineer in charge for direction / approval.
However, as a general rule more stringent specification shall take
precedence.
ISSUE
R4
11.3 MATERIALS
11.3.1 All clamps, fittings, accessories should be made out of first grade quality
galvanized steel conforming to IS 316. All products should be made out of
0.6mm (24g) galvanized sheet.
11.3.4 The panels and doors should be constructed out of 12mm thick merino
laminate or any other optional material as specified by the architect.
11.3.5 All panels should have a built in feature to be totally sight proof on all four
corners for better privacy. Standard gap of 150mm on sides and on moving
element has to be provided unless otherwise specified or scheduled in the
drawing or layout.
11.3.6 Cubicles should have a provision for mounting of the toilet hardware like
handrails, hinges, locks with indicator, coat hooks, tissue holders and taps
as per scheduled and specified. All panels should be fully protected with the
self adhesive film and to be removed at the handing over of the cubicles
11.4.2 The Urinal partition screens shall also be measured in numbers of the
standard sizes as approved.
ISSUE
R4
12.1 GENERAL
12.1.1 The scope of this section consists of but is not necessarily limited to
installation, testing and commissioning of Sanitary appliances and fixtures
for toilets, Steel, Chromium plated, brass fittings, Stainless steel sinks,
Accessories e.g. towel rods, toilet paper holders, soap dish, towel rails, coat
hooks, hand dryers, mirrors, liquid soap dispensers etc.
12.1.2 Whether specifically mentioned or not the Contractor shall provide for all
appliances and fixtures, all fixing devices, nuts, bolts, screws, hangers as
required.
12.1.3 All exposed pipes within toilets and near appliances/fixtures shall be of
chromium plated brass or copper unless otherwise specified.
12.2.1 Work shall be carried out as per latest edition of Indian Standards and Code
of Practices. List given here shall not be considered as conclusive and is for
reference and guidance only. Any discrepancies/ conflict noticed shall be
brought to the notice of Architect/Engineer in charge for direction / approval.
However, as a general rule more stringent specification shall take
precedence.
ISSUE
R4
12.3 MATERIALS
12.3.1.1 Water Closet shall be wash down or symphonic wash down type
floor or wall mounted set, as shown in the drawings, designed for low
volume flushing from 2-6 liters of water to be flushed by means of a
porcelain flushing cistern or an exposed or concealed type (as detailed
in the drawings or as directed by the Owner‘s Site Representative) 32
mm size CP, brass flush valve with regulator valve.
12.3.1.5 Each WC shall be provided with 110 mm dia (OD) PVC Pan
Connector connecting the ceramic outlet of WC to CI pipe.
ISSUE
R4
12.3.3.3 Each basin shall be provided with 32mm dia CP waste with
overflow, pop-up waste or rubber plug and CP brass chain as specified
in the Schedule of Quantities.
12.3.3.4 Each basin shall be provided with hot and cold water mixing fitting
or as specified in the Schedule of Quantities. Wash Faucets shall be
sensor controlled and shall have an added aerator to reduce flow to 2.0
LPM.
12.3.3.5 Flow Rate = 2 Liters per minute @ 58 PSI, all others except
private applications. (as per LEED requirement)
12.3.4 Sinks
12.3.4.3 Sanitary fittings for sinks shall be deck mounted or wall mounted
CP swivel faucets with or without hot and cold water mixing fittings as
specified in the Schedule of Quantities. Installation of fittings shall be
measured and paid for separately.
12.3.4.4 Flow Rate = 2 Liters per minute @ 58 PSI, all others except
private applications. (as per LEED requirement)
12.3.5.1 Janitor's sink shall be stainless steel, single bowl type of size as
called for in the Schedule of Quantities, provided with painted R.S. or CI
brackets and clips and securely fixed. Each sink shall be provided with
40mm dia CP waste. Fixing shall be as directed by the Owner‘s Site
Representative. The supply fittings for Janitor's sink shall be wall
mounted type of size as mentioned in Schedule of Quantities.
ISSUE
R4
12.3.8.1 The hand drier shall be no touch operating type with solid state
time delay to allow user to keep hand in any position. The hand drier
shall be fully hygienic, rated for continuous repeat use (CRU). The
rating of hand drier shall be such that time required to dry a pair of
hands up to wrists is approximately 30 seconds. The hand drier shall be
of wall mounting type suitable for 230 V, single phase, 50 Hz, AC power
supply.
12.3.9.1 Shower set shall comprise of two CP brass concealed stop cocks,
four/five way auto-diverter, adjustable type over-head shower with CP
shower arm, all with CP wall flanges of approved quality all as specified
in the Schedule of Quantities. Bath spout, hand showers and pop up
wastes shall also be provided wherever, specified. Wall flanges shall be
kept clear off the finished wall. Wall flanges embedded in the finishing
shall not be accepted.
12.3.9.2 Flow Rate = < 6.1 Liters per minute @ 58 PSI (as per LEED
requirement)
12.3.9.4 Approved / rated flow control fitment in brass body, chrome outer
cover, rated for flow / discharge of the fixture.
12.3.10.1 Toilet paper holder shall be white glazed vitreous china or chrome
plated of size, shape and type specified in the Schedule of Quantities.
12.3.10.2 Porcelain toilet paper holder shall be fixed in walls and set in
cement mortar 1:2 (1 cement: 2 coarse sand) and fixed in relation to the
tiling work.
12.3.11.2 Towel rail shall be fixed with screws/capping having finish similar
to the towel rail in wall with rawl plugs or nylon sleeves and shall
include cutting and making good as required or directed by the Owner‘s
Site Representative.
12.3.12 Urinals
12.3.12.1 Urinals shall be lipped type half stall with glazed vitreous China of
size as called for in the Bill of Quantities.
12.3.12.2 Half stall urinals shall be provided with 15mm dia CP spreader,
32mm dia CP domical waste and CP cast brass bottle trap with pipe ISSUE
R4
and wall flange and shall be fixed to wall by CI brackets, CI wall clips
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
TATA CONSULTING ENGINEERS LIMITED
SPEC. NO. WRITE UP
TCE.M4-419-01 SHEET 125 of
GENERAL BUILDING WORKS
174
12.3.12.4 Flush pipes shall be GI pipes concealed in wall chase but with
chromium plated bends at inlet and outlet.
12.3.12.5 Flow Rate = 4.0 Litres per Flush. 8.5 Liters per minute @ 4 Bar 58
PSI, private applications only (as per LEED requirement)
12.3.13.2 The contractor shall provide all the necessary supporting and
fixing devices to install the sanitary fixtures and fittings securely in
position. The fixing devices shall be rigidly anchored into the building
structure. The devices shall be rust resistant and shall be so fixed that
they do not present an unsightly appearance in the final assembly.
Where the location demands, the Architect may instruct the contractor
to provide chromium plated or other similarly finished fixing devices. In
such circumstances the contractor shall arrange to supply the fixing
devices and shall be installed complete with appropriate vibration ISSUE
R4
isolating pads, washers and gaskets.
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
TATA CONSULTING ENGINEERS LIMITED
SPEC. NO. WRITE UP
TCE.M4-419-01 SHEET 126 of
GENERAL BUILDING WORKS
174
12.4.1 All appliances, fixtures and fittings shall be provided with all such
accessories as are required to complete the item in working condition
whether specifically mentioned or not in the Schedule of Quantities,
specifications, and drawings. Accessories shall include proper fixing
arrangements, brackets, nuts, bolts, washers, screws and required
connection pieces.
12.4.2 The sanitary fixtures and fittings shall be installed at the correct assigned
position as shown on the drawings and as directed by the Architect /
Owner‘s Site Representative and shall fully meet with the aesthetic and
symmetrical requirements as demanded by the Architect / Interior Designer
12.4.3 All fixtures and accessories shall be fixed in accordance with a set pattern
matching the tiles or interior finish as per Architect requirements. Wherever
necessary, the fittings shall be centered to dimensions and pattern as called
for.
12.4.4 Fixing screws shall be half round head chromium plated (CP) brass screws,
with CP brass washers unless otherwise specified.
12.4.6 All appliances, fittings and fixtures shall be fixed in a neat workmanlike
manner true to level and to heights shown on the drawings and in
accordance with the manufacturers‘ recommendations. Care shall be taken
to fix all inlet and outlet pipes at correct positions. Faulty locations shall be
made good and any damage to the finished floor, tiling, plaster, paint,
insulation or terrace shall be made good by the Contractor at his own cost.
Fixtures shall be mounted rigid, plumb and true to alignment.
12.4.7 All materials shall be rust proofed; materials in direct or indirect contact
shall be compatible to prevent electrolytic or chemical (bimetallic) corrosion.
ISSUE
R4
12.4.8 Wall flanges shall be provided on all walls, floors, columns etc. wherever
supply and disposal pipes pierce through them. These wall caps shall be or
chromium plated brass fittings and the receiving pipes and shall be large
enough to cover the punctures properly.
12.4.10 Contractor shall, during the entire period of installation and afterwards
protect the appliances by providing suitable cover or any other protection so
as to absolutely prevent any damage to the appliances until handing over
(The original protective wrapping shall be left in position for as long as
possible)
12.4.11 The appliances shall be placed in correct position or marked out in order
that pipe work can be fixed or partially fixed first.
12.4.12 The appliance shall be fixed in a manner such that it will facilitate
subsequent removal if necessary.
12.4.13 The appliance shall be securely fixed. Manufacturer's brackets and fixing
methods shall be used wherever possible. Compatible rust-proofed fixings
shall be used. Fixing shall be done in manners that minimize noise
transmission.
12.4.14 Appliances shall not be bedded (e.g. WC pans, pedestal units) in thick
strong mortar that could crack the unit (e.g. ceramic unit)
12.4.15 Pipe connections shall be made with demountable unions. Pipe work shall
not be fixed in a manner that it supports or partially supports and appliance.
12.4.16 Appliances shall be fixed true to level firmly fixed to anchor or supports
provided by the manufacturer and additional anchors or supports where
necessary.
ISSUE
R4
12.4.18 The contractor shall fix all plumbing fittings such as water faucets, shower
fittings, mixing valves etc. in accordance with manufacturer‘s instructions
and connect to piping system. The contractor shall supply all fixing
materials such as screws, rawl plugs, unions, collars, compression fittings
etc., as required.
12.4.19 Joints / gaps between all sanitary appliances / fixtures and the floor / walls
shall be caulked with an approved mildew resistant sealant, having
antifungal properties, of colour and shade to match that of the appliances /
fixture and the floor / wall to the extent possible.
12.4.20 The contractor shall install all sanitary fixtures and fittings in their final
position in accordance with approved trial assemblies and as shown on
drawings. The installation shall be complete with all supply and waste
connections. The connection between building and piping system and the
sanitary fixtures shall be through proper unions and flanges to facilitate
removal/replacement of sanitary fixtures without disturbing the built in piping
system. All unions and flanges shall match in appearance with other
exposed fittings.
12.4.21 Fixtures shall be mounted rigid, plumb and to alignment. The outlets of
water closet pans and similar appliances shall be examined to ensure that
outlet ends are butting on the receiving pipes before making the joints. It
shall be ensured that the receiving pipes are clear of obstruction. When
fixtures are being mounted, attention shall be paid to the possibility of
movement and settlement by other causes. Overflows shall be made to
ensure that necessary anchoring devices have been provided for
ISSUE
supporting water closets, wash basins, sinks and other appliances. R4
12.5.1 The contractor shall provide all the necessary supporting and fixing devices
to install the sanitary fixtures and fittings securely in position. The fixing
devices shall be rigidly anchored into the building structure. The devices
shall be rust resistant and shall be so fixed that they do not present an
unsightly appearance in the final assembly. Where the location demands,
the Architect may instruct the contractor to provide chromium plated or
other similarly finished fixing devices. In such circumstances the contractor
shall arrange to supply the fixing devices and shall be installed complete
with appropriate vibration isolating pads, washers and gaskets.
FINAL INSTALLATION
12.5.2 The contractor shall install all sanitary fixtures and fittings in their final
position in accordance with approved trial assemblies and as shown on
drawings. The installation shall be complete with all supply and waste
connections. The connection between building and piping system and the
sanitary fixtures shall be through proper unions and flanges to facilitate
removal/replacement of sanitary fixtures without disturbing the built in piping
system. All unions and flanges shall match in appearance with other
exposed fittings.
12.5.3 Fixtures shall be mounted rigid, plumb and to alignment. The outlets of
water closet pans and similar appliances shall be examined to ensure that
outlet ends are butting on the receiving pipes before making the joints. It
shall be ensured that the receiving pipes are clear of obstruction. When
fixtures are being mounted, attention shall be paid to the possibility of
movement and settlement by other causes. Overflows shall be made to
ensure that necessary anchoring devices have been provided for
supporting water closets, wash basins, sinks and other appliance.
ISSUE
R4
12.6.1 Material received at site shall be with original packing and labels. It shall be
intact till issued for use of site. Material shall be stored at properly covered
dry location and shall be safe from damage.
12.6.2 Care must be taken to ensure that the sanitary fixtures are not damaged
while loading / unloading and transporting. Cartons must always be stored
with designated side upwards.
12.6.3 The contractor shall take every precaution to protect all sanitary fixtures
against damage, misuse, cracking, staining, breakage and pilferage by
providing proper wrapping and locking arrangement till the completion of
the installation.
12.6.4 At the time of handing over, the contractor shall clean, disinfect and polish
all the fixtures and fittings. Any fixtures and fittings found damaged, cracked
chipped stained or scratched shall be removed and new fixtures and fittings
free from defects shall be installed at his own cost to complete the work.
12.7 MEASUREMENTS
12.7.1 Rate for fixing only of sanitary fixtures accessories, CP fittings shall etc.
include all items, and operations stated in the respective specifications and
bill of quantities and nothing extra is payable.
12.7.2 Rates for all items shall be inclusive of cutting holes and chases and
making good the same, CP screws, nuts, bolts and any fixing arrangements
required and recommended by manufacturers, testing and commissioning
and making good to the satisfaction of the Owner‘s Site Representative.
ISSUE
R4
13.1 GENERAL
13.1.1 Specification applies to water proofing of terrace, basement and toilet slabs
with elastomeric membrane, waterstops, swellable sealant water bars and
water proofing admixtures.
13.3.1.1 All the walls in a building shall be provided with damp-proof course
to prevent water from rising up the wall. The damp-proof course shall
run without a break throughout the length of the wall, even under the
door or other openings. Damp-proof course shall consist of 50 mm
thick cement concrete of 1:2:4 nominal mix with approved water-
proofing compound admixture conforming to IS: 2645 in proportion as
directed by the manufacturer. Concrete shall be with 10 mm
downgraded coarse aggregates The surface of brick or stone masonry
work shall be levelled and prepared before laying the cement concrete.
Edge of damp proof course shall be straight, even and vertical. Side
shuttering shall consist of steel forms and shall be strong and properly
fixed so that it does not get disturbed during compaction and the mortar
does not leak through. The concrete mix shall be of workable
consistency and shall be tamped thoroughly to make a dense mass.
When the sides are removed, the surface should come out smooth
without honeycoming. Continuity shall be maintained while laying the
cement concrete layer and laying shall be terminated only at the
predetermined location where damp proof course is to be discontinued.
There shall be no construction joints in the Damp Proof Course.
13.3.1.3 Damp-proof course shall be cured properly for at least seven days
after which it shall be allowed to dry for taking up further work.
ISSUE
R4
13.4.1 MATERIALS
13.4.1.2 The material shall not be diluted. The coating shall have physical
features like high viscosity, minimum 80% solids, high resistance to
impact, abrasion and cracking, superior tensile strength, 500%
elongation and forming a perfectly smooth permanently flexible
seamless membrane which should have good adhesion to roof surface.
It should also be resistant to acid (mild concentrated), alkalis and have
a very low water absorption rate (0.5% max) at ambient temperature
after 7 days. The material shall not be older than 9 months.
13.4.2 WORKMANSHIP
13.4.2.1 The roof shall be sloped with mortar or concrete (M20 grade with
12mm down size aggregates) screed to achieve the specified slope as
per drawing and shall be properly cured before taking up water-proofing
treatment.
13.4.2.2 The roof surface shall be cleaned of all foreign matters by wire
brushing, dusting etc. and shall be made thoroughly dry. All cracks and
voids on the surface shall be filled with mastic sealant, if required. A V-
groove shall be made along the crack line and shall be filled with mastic
sealant.
ISSUE
R4
13.4.2.5 After the first coat is touched dry, second coat @ 0.50 kg/sq.mm
and minimum average thickness of 0.50mm shall be applied. After the
second coat is dry, third coat shall be applied to result in an overall
thickness of 1.5mm.
13.4.2.8 Water proofing treatment shall be taken on the brick masonry wall
/ parapet / column projection by a minimum of 150 mm along its height.
Groove 75mm wide and 65mm deep in masonry shall be left for tucking
the water proofing treatment. The groove shall be filled with 1:4 cement
mortar for securing the water proofing treatment firmly.
13.4.3 All completed works shall be cleaned to remove any spillage from
chemicals.
13.4.4 For finishing on top, machine made burnt clay flat terracing tiles conforming
to IS 2690 (Part-1) or cement concrete flooring tiles conforming to IS 1237
shall be used and shall be of the size and thickness as specified in the item
of work. Tiles shall be soaked in water for at least one hour before laying.
Bedding for the tiles shall be 12mm thick in cement mortar 1:3. Tiles shall
ISSUE
be laid, open jointed with 4 to 6 mm wide joints, flat on the mortar and lightly R4
pressed and set to plane surface true to slope, using a trowel and wooden
straight edge. They shall be laid with their longitudinal lines of joints truly
parallel and generally at right angles to the direction of run-off gradient.
Transverse joints in alternate rows shall come directly in line with each
other. Transverse joints in adjacent courses shall break joints by atleast 50
mm. The joints shall be completely filled and flush pointed with cement
mortar l:2 mixed with water proofing compound as per manufacturer's
instructions. Curing shall be carried out for a minimum period of seven
days.
13.4.4.1 After completing all the water proofing works over the roof surface
and curing, the works shall be tested against any leakage / soaking of
water below the roof. For this, arrangement shall be made by
Contractor to store minimum 50mm height of water over the roof
surface and shall be maintained for a period of 7 days. If any wet patch
is observed on the ceiling, rectification of water proofing works should
be attended immediately by the contractor. The test should be repeated
till the leakage / soaking through the ceiling completely stops.
ISSUE
R4
13.4.5 MEASUREMENT
13.4.5.1 Measurement shall be for the plan area of treatment and for the
finished work. No separate payment shall be made for the fillets and
work as specified on the vertical faces. Cement concrete tiling works or
machine pressed clay tile works shall be paid separately, unless they
are specifically included in the item of works.
13.5.1 MATERIAL
13.5.2 WORKMANSHIP
13.5.2.1 Base slab or raft shall be provided over the lean concrete/PCC.
The membrane shall be applied in the similar manner as mentioned in
clause 13.4.2. The top surface of elastomeric memberane shall be
protected by providing 20mm thick mortar ratio 1:4. Protective coating
shall be cured for 3days.
13.5.2.2 The elastomeric membrane for the vertical wall shall be provided
on the outer face exposed to water pressure/earth pressure. The
membrane shall be applied as explained in clause 13.4.2. There shall
be proper continuation of membrane provided below the base slab /raft
and over the outer face of wall. The exposed membrane shall be
protected by providing extruded high density dimpled polyurethane
board.
13.5.3 MEASUREMENT
13.5.3.1 Measurement shall be for the plan area of treatment and for the
finished work. No separate payment shall be made for providing and
ISSUE
laying the lapping of membrane/ protective mortar/board/any other type. R4
13.6.1 MATERIAL
13.6.2 WORKMANSHIP
13.6.2.1 After casting the concrete slab, the surface shall be cured for
required period.
13.6.2.2 The inner surface shall be prepared and membrane coating shall
be applied as described above clause 14.2.2. Provisions of IS13182
shall be adopted for making the wet areas watertight.
13.6.2.3 The prepared surface shall be plastered with cement mortar 1:3 –
15 mm thick admixed with – Normal Setting Integral Waterproofing
Compound conforming to IS: 2645, or approved equivalent at 2% by
weight of cement. Surface shall be cured for minimum 7 days.
13.7 WATERSTOPS
13.7.1 MATERIAL
13.7.1.1 The material for the PVC water stops shall be a plastic compound
with the basic resin of polyvinyl chloride and additional resins,
plasticizers, inhibitors, which satisfies the performance characteristics
specified below as per IS:15058. Testing shall be in accordance with
IS:8543 (Part 4/sec1), IS 13360 (Part 5/sec11) and IS 9766..
Tensile strength : 13.8 MPa minimum
Accelerated extraction
13.7.1.2 PVC water stops shall be either of the bar type, serrated with
centre bulb and end grips for use within the concrete elements or of the
surface (kicker) type for external use. The width, type, minimum
thickness and safe hydraulic head requirements shall be as specified in
the individual items of work.
13.7.2 WORKMANSHIP
13.7.3 MEASUREMENT
13.8.1 MATERIAL
13.8.2 WORKMANSHIP
13.8.2.1 Construction joint surface shall be cleaned and swellable water ISSUE
bar shall be placed in the grove or fixed with adhesive and cured as R4
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
TATA CONSULTING ENGINEERS LIMITED
SPEC. NO. WRITE UP
TCE.M4-419-01 SHEET 141 of
GENERAL BUILDING WORKS
174
13.8.3 MEASUREMENT
13.10.1 General: Before taking up the water proofing work the construction of
parapet walls, including finishing should be completed. Similarly, the
ancillary items like haunches, khurras, grooves to tack the fibre cloth layer,
fixing up of all down take pipes, water pipes and electric conduits etc.
should be completed and no such work should be allowed on the area to be
treated during the progress of water proofing treatment or even later.
13.10.1.1 Preparing the Surface: The surface of the slab should be roughened
by scrapping when the slab concrete is still green, however, the
surface need not be hacked. In case the slab is already cast and
surface fairly finished, the same shall be cleaned neatly of all mortar
droppings, loose materials etc with brooms/cloth.
ISSUE
R4
13.10.1.2 Providing and Laying of Slurry under Base Coat The quantity of
water required to prepare the slurry with 2.75 kg. of blended cement
to be painted over an area of 1 sq m. Depending upon the area of
surface that has to be covered, the required quantity of slurry should
be prepared using 2.75 kg. blended cement + water per sq m. area
to be covered, taking particular care to see that only that much
quantity of slurry shall be prepared which can be used within half an
hour of preparation i.e. before the initial setting time of cement. Page
15 of 42 The prepared slurry shall be applied over the dampened
surface with brushes very carefully, including the joints between the
floor slab and the parapet wall, holes on the surfaces, joints of pipes,
masonry/concrete etc. The application of the slurry should continue
upto a height of 300 mm on the parapet wall. Slurry should also be
applied upto a height of 150 mm over pipe projections etc.
13.10.1.4 Laying Brick Bat Coba: Brick bat of size 25 mm to 115 mm out of well
burnt bricks shall be used for the purpose of brick bat coba. The brick
bats shall be properly dampened for six hours before laying. Brick
bats shall be laid to required slope/gradient over the base coat of
mortar leaving 15-25 mm gap between two bats. Cement mortar 1:5
(1 blended cement: 5 coarse sand) shall be poured over the brick
bats and joints filled properly. Under no circumstances dry brick bats
should be laid over the base coat. The haunches/gola at the junction
of parapet wall and the roof shall be formed only with brick bat coba. ISSUE
In case the brick bat coba is laid on the base coat immediately on R4
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
TATA CONSULTING ENGINEERS LIMITED
SPEC. NO. WRITE UP
TCE.M4-419-01 SHEET 143 of
GENERAL BUILDING WORKS
174
initial set there will be no necessity of applying cement slurry over the
base coat before laying the brick bat coba. However, if the brick bat
coba is to be laid on the subsequent day, cement slurry prepared as
described in clause 5.2.2 shall be applied over the top surface of the
base coat, then only the brick bat coba shall be laid.
13.10.1.5 Application of Slurry over Brick Bat Coba: After two days of curing of
brick bat coba cement slurry shall be applied on the surface of brick
bat coba The application of slurry shall cover the haunches/gola, and
the remaining small portion of parapet wall and also inside the
groove .
13.10.1.7 Providing and Laying of Fibre Glass Cloth The fiber glass cloth shall
be of approved brand and shall be thin, flexible uniformly bonded mat
composed of chemically resistant borosilicate glass fibre distributed
ISSUE
in random open porous structure bonded together with a R4
13.10.1.8 Curing and Testing the Treatment The entire surface thus treated
shall be flooded with water by making kiaries with weak cement
mortar, for a minimum period of two weeks.
ISSUE
R4
13.11.1.1 Hessian based tar felt is the most common product for water proofing
on the new Roofs. These felts use hessian as the barrier medium for
bitumen and bituminous Compound. Bitumen felts are classsified as
Type 1, 2 or 3 depending on type of base used in their manufacture
and the uses for which the felts are suited. Grades refer to minimum
weight of bitumen felt. The bitumen felt should be laid over finished
roof surface of slope not flatter than 1 in 120.
13.11.1.3 In the laying of 4 or 6 courses of bitumen felt, as the case may be,
over the last course of hot bitumen, stone grit or gravel of 6 mm and
down size shall be spread uniformly on horizontal surfaces. Bitumen
felts suffer from following deficiencies:
ISSUE
R4
14.1 GENERAL
IS:901
Code Of - Practice For Use Of Cold-Formed Light Gauge Steel
Structural Members In General Building Construction
ISSUE
R4
14.3 MATERIAL
14.3.1.2 Troughed permanently colour coated metal sheet for roofing, side
cladding, ridges, hips, flashings, trimmings, closure for vertical &
horizontal joints,capping etc., shall be
14.3.1.3 With sheet having minimum 0.6mm (bare metal thickness) thickness
galvanised to grade 275 as per IS277, of minimum yield strength of
250Mpa of drawing grade as per IS513.
14.3.1.4 With sheet having minimum 0.5mm (bare metal thickness) thickness
coated with zinc aluminum alloy at 150gm/m2 of minimum yield
strength of 350 as per AS1397.
14.3.1.5 Steel sheet shall be colour coated as per clause 15.2.1 and shall be
of approved profile, sectional properties, colour and shade.
14.4.1.1 For metal decking the sectional properties shall be calculated as per
IS801 for satisfying deflection and strength requirements. Deflection
shall be limited to span/250 under critical load combinations.
ISSUE
R4
14.4.1.4 Sealant used for cladding shall be butyl based, two parts poly
sulphide or equivalent approved, non stainless material and be
flexible enough not to interface with fit of the sheets.
14.4.1.5 Filler blocks as a trough filler shall be used to seal cavities formed
between the profiled sheet and the support or flashing. Filler block
shall be manufacturer from black synthetic rubber or any other
material approved by ENGINEER.
14.4.1.8 Percentage elongation of the mild steel sheet having minimum yield
strength of 250Mpa shall be 23% as per IS: 2062.
14.5 WORKMANSHIP
14.5.1.1 The sheeting shall be fixed as per the working drawings. Sheets shall
be supplied in required sizes (based on the secondary beams ISSUE
spacing/ purlins) according to the cutting schedule. Generally cutting R4
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
TATA CONSULTING ENGINEERS LIMITED
SPEC. NO. WRITE UP
TCE.M4-419-01 SHEET 150 of
GENERAL BUILDING WORKS
174
14.5.1.3 Side and end laps of the sheets shall be made weather proof by
securing them with the fasteners not less than 4mm dis with 2mm
thick neoprene washer. Maximum spacing of the fasteners not to
exceed 500mm.
14.5.1.4 Length of the sheet shall be such as to cover minimum 3 span purlin
spacings. The roof decking sheets shall be fixed to the purlins with
the help of self drilling and tapping type fasteners and neoprene
washers.
14.5.1.5 Sheets shall be laid over the supporting purlins with a minimum
bearing of 50mm and end projection of 75mm at lap joints. End and
side laps between the sheets shall be sufficiently large to ensure the
weather tightness. In no case, the end laps shall be less than 150mm
and side laps less than one trough length with proper weather tight
arrangement.
14.5.1.6 Cladding erection for each elevation shall commence at the bottom
and proceed towards the top, in order to ensure tight fittings laps.
ISSUE
R4
14.5.1.7 In case double skin cladding, inner sheet and outer sheet can be
directly fixed to the opposite faces of the sheeting runner totally
concealing the supporting steel structure.
ISSUE
R4
15.1 GENERAL
15.1.1 This specification covers the general requirements regarding materials and
details of fabrication and erection of Stainless Steel (SS) Handrails. The
contractor shall design, engineer, document, test, manufacture, deliver,
install, protect and commission SS Railing complete with all necessary
accessories, fixings, finishes, flashings, sealants and the like in accordance
with the Contract Documents. The scope of this Section is performance
based, and shall be developed, tested and warranted to comply with:
15.2.1 Work shall be carried out as per latest edition of Indian Standards and Code
of Practices. List given here shall not be considered as conclusive and is for
reference and guidance only. Any discrepancies/ conflict noticed shall be
brought to the notice of Architect/Engineer in charge for direction / approval.
However, as a general rule more stringent specification shall take
precedence.
INDIAN STANDARDS:
NBC 2005 Bureau of Indian Standards, the National Building
Code of India,
IS: 806 Code of Practice for Use of Steel Tubes in
General Building Construction.
IS: 2835 Specification for flat transparent sheet glass(third
revision)
IS: 4912 Safety Requirements for Floor and Wall Openings,
ISSUE
Railings and Toe Boards R4
AMERICAN STANDARDS
ASTM A554–13: Standard Specification for Welded Stainless Steel
Mechanical Tubing
ASTM E985: Standard Specification for Permanent Metal
Railing Systems and Rails for Buildings
ASTM E488: Standard Test Methods for Strength of Anchors in
Concrete and Masonry Elements
ASTM E894–88: Standard Test Method for Anchorage of Permanent
Metal Railing Systems and Rails for Buildings
ASTM E935–00: Standard Test Methods for Performance of
Permanent Metal Railing Systems and Rails for
buildings
BRITISH STANDARDS
CP 3012: Code of Practice for Cleaning and
Preparation of Metal Surfaces
IBC 2407: Glass in Handrails and Guards
BS EN 14179-2: Glass in building. Heat-soaked thermally-
toughened soda lime silicate safety glass
Evaluation of conformity/product standard
BS EN 1096-1: Glass in building. Coated glass Definitions
and classification
ISSUE
R4
15.3.1 MATERIALS
15.3.1.2 All rails and other horizontal / inclined tubular components shall be
constructed using the following:
15.3.1.7 Stainless steel grade AISI type 316, surface to be 320 grain/grit
finish/ polish / matte/ bead blasted for component fittings including
handrail attachment support and post attachment components Stainless
Perforated, Woven Or Welded Metal Infill Panels: As per Custom
pattern as specified herein.
15.3.1.8 Fasteners:
15.3.2.6 When stainless steel items are joined to carbon steel structural
elements the carbon steel element must be well protected by suitable
painting.
15.3.2.7 Stainless steel rivets, screws and bolts must be used and the
carbon steel element must be suitably insulated from the stainless steel
element using EPDM/ neoprene/Teflon
15.3.3 WORKMANSHIP
15.3.3.1 Installation work shall not be carried out until substrates have been
properly prepared.
15.3.3.3 All works shown or inferred from the Specifications and Drawings
are intended to be the design criteria for the subcontract work. The
detailed design development shall be submitted by the Contractor for
Acceptance and Endorsement.
ISSUE
R4
15.3.3.15 Stainless steel tubing cuts shall be square, without burrs and
where exposed, rounded to produce smooth rigid and hairline joints
15.3.3.18 Perform cutting, drilling and fitting required for installation. Set
accurately in location, alignment and elevation, plumb, level and true,
measured from established lines and levels.
15.3.3.26 Maximum offset from true alignment for every 50-foot of railing
shall be 1/4", non-accumulative.
15.3.4.6 Upon delivery railing will have protective wrapping over cap only.
Immediately upon completion of installation of railing, remove cap cover
and clean all work for inspection and approval.
15.3.4.7 When cleaning surfaces use plain water containing a mild soap or
detergent. No abrasive agents or harsh chemicals shall be used.
15.3.5 WARRANTY
15.3.6 MEASUREMENT
15.3.6.1 Horizontal plan length of top rail only will be measured as handrail
length in Running Unit. Verticals will not be measured. Rate shall
include all labour and materials including balustrades (vertical pipes) all
necessary infill details (as shown in drawing), welding (if necessary),
tools, plants & buffing charges fixing arrangements etc complete as
directed.
15.4.1 MATERIALS
15.4.1.1 Guardrails And Handrail System - All rails and other horizontal /
inclined tubular components shall be constructed using the following:
15.4.1.3 All posts and other vertical components shall be constructed using
the following:
15.4.1.7 Provide 1.0mm radius at all corners with ‗v-cut‘ where necessary.
15.4.1.9 Stainless steel grade AISI type 316, surface to be 320 grain/grit
finish/ polish / matte/ bead blasted for component fittings including
handrail attachment support and post attachment components
15.4.1.13 Tinted glass: Class 2 (tinted heat absorbing and light reducing).
Manufacturer‘s standard tint color or custom color as indicated below:
15.4.1.16 Glass shall be Fully Tempered and 100% Heat Soak Tested to EN
14179 part 1.
15.4.1.18 Opacifier coatings and films are required to be suitable for the
proposed temperature and exposure conditions and are required to
function without bubbling, blistering or colour shift for the design life of
the Building.
15.4.1.22 Glass for laminating is to be cut into individual panels prior to the
laminating process.
15.4.1.24 Heat treated glass is to be orientated so that warp, bow and roller
wave between successive panels are matched. Two stage convection
tempering ovens are to be used to ensure glass distortions are
minimized. Edge clamping of glass is forbidden.
15.4.1.28 When stainless steel items are joined to carbon steel structural
elements the carbon steel element must be well protected by suitable
painting. Stainless steel rivets, screws and bolts must be used and the
ISSUE
R4
carbon steel element must be suitably insulated from the stainless steel
element using EPDM/ neoprene/Teflon
15.4.1.30 All laminated glass shall have clean cut edges, or polished edges
if required to eliminate thermal stress breakage risk. Laminated glass
units shall be fabricated with autoclaved edges on all four sides.
15.4.1.35 Perform cutting, drilling and fitting required for installation. Set
accurately in location, alignment and elevation, plumb, level and true,
measured from established lines and levels.
15.4.1.42 Maximum offset from true alignment for every 50-foot of railing
shall be 1/4", non-accumulative.
15.4.3 WORKMANSHIP
15.4.3.3 All works shown or inferred from the Specifications and Drawings
are intended to be the design criteria for the subcontract work. The
detailed design development shall be submitted by the Contractor for
Acceptance and Endorsement.
15.4.3.15 Stainless steel tubing cuts shall be square, without burrs and
where exposed, rounded to produce smooth rigid and hairline joints
15.4.4.1 Submit (within the One month of the award of contract) the
Comprehensive, detailed and dimensioned shop drawings to indicate all
set-out and construction/ installation details to include and not limited to
ISSUE
R4
15.4.6.5 Defective works log to be kept up to date for the duration of the
warranty period outlining each defect type location and corrective action
to rectify each defect.
15.4.8 Glass
15.4.8.2 Bow Distortion: ‗bow‘ and ‗warp‘ shall have the same meaning.
Overall bow across the shorter glass dimension (‗the gauge length‘)
shall not exceed 0.00342 times gauge length for gauge length less than
900mm, and 0.00258 times gauge length for gauge length greater than
900mm.
15.4.8.3 100% heat soak testing will be required for all glass with edge
stress exceeding 50mpA (7500 psi). Submit Heat Soak method,
temperature, and duration for review and Acceptance, prior to
commencement.
15.4.9 MOCK-UP
ISSUE
R4
15.4.9.1 Contractor shall install a full scale mock up for a length of 7.5m of
typical detailing treatment at locations to be confirmed by the Architect.
15.4.10.5 Upon delivery railing will have protective wrapping over cap only.
Immediately upon completion of installation of railing, remove cap cover
and clean all work for inspection and approval.
15.4.10.7 When cleaning surfaces use plain water containing a mild soap or
detergent. No abrasive agents or harsh chemicals shall be used.
ISSUE
R4
15.4.11 WARRANTY
15.4.12 MEASUREMENT
15.4.12.1 The mode of measurement will be length of railing and not length
of individual pipes/bars i.e. Horizontal plan length of top rail only will be
measured as handrail length in Running Unit. Verticals will not be
measured.
15.4.12.2 Rate shall include all labour and materials including balustrades
(vertical pipes) all necessary infill details / Glass Panels (as shown in
drg), welding (if necessary), tools, plants & buffing charges fixing
arrangements etc complete as directed.
ISSUE
R4
15.5.1 MATERIALS
15.5.1.1 Mild steel tubular sections should be used for hand railing; design
should be as per drawing.
15.5.2 WORKMANSHIP
15.5.2.1 The hand railings will be fitted in staircase and other areas without
tampering the finishing material of the stair/area. The fixing will be done
as per details shown in drawing.
15.5.3 MOCK-UP
15.5.3.1 Contractor shall install a full scale mock up for a length of 7.5m of
typical detailing treatment at locations to be confirmed by the Architect.
15.5.4 MEASUREMENT
15.5.4.2 Rate shall include all labour and materials including balustrades
(vertical pipes) welding, tools, scaffoldings, buffing charges, fixing
arrangements etc complete as directed.
ISSUE
R4
16 MISCELLANEOUS
16.1 GENERAL
16.1.1 This part of the specification covers miscellaneous items such as Inserts,
bolts, cutouts, metal lath and wire fabric.
IS:4948 - Specification for welded steel wire fabric for general use.
16.3.1 WORKMANSHIP
16.3.1.2 The rate quoted by the Bidder for concrete works shall hold good
for accurately fixing the inserts at the correct levels/alignment and shall
include the cost of any temporary supports/anchors such as bars
including cutting, bending, welding, etc. as required.
16.3.1.4 The Contractor shall ensure proper protection of all bolts, inserts,
etc. from weather by greasing or other approved means such as
applying white lead putty and wrapping them with gunny bags or
canvas or by other means as directed by the Engineer to avoid damage
due to movement of his labourers, materials, equipment, etc. No extra
claim from the Contractor on this account shall be entertained. The
Contractor shall be solely responsible for all damage caused to bolts,
inserts, etc. due to his negligence and in case damage does occur, they
shall be rectified to the satisfaction of the Engineer at the Contractor's
cost.
16.3.1.5 Cut outs, chamfers, pockets, etc. shall be left as indicated in the
drawings and no extra cost shall be payable for providing these at their
correct locations. The Contractor shall take all necessary precautions to
protect the cut outs from accidentally getting filled up or the edges
getting broken.
16.3.2 MEASUREMENT
16.4.1 MATERIALS
16.4.2 WORKMANSHIP
16.4.2.1 The type and details of the steel material to be used for metal lath
plastering work and at the junctions of brick masonry/concrete before
wall plastering shall be as specified in the respective items of work.
16.4.2.2 For metal lath plastering work, the weight of steel material shall be
not less than 1.6 kg/sq m.
16.4.2.3 Steel material for use at the Junction of brick masonry/ concrete
shall have the mesh dimensions not greater than 50 mm.
16.4.3 MEASUREMENT
ISSUE
R4
1.0 SCOPE
3.0 MATERIALS
3.1.1 Submit shop drawings for reflected ceiling plans (RCP’s), drawn to scale,
The detailed drawings shall be based on those of other services and
shall be prepared in close co-ordination with the other vendors/agencies.
The aluminium ceiling panels to be used in the false ceiling shall be
made of aluminium alloy sheets of 19000 or 31000 of IS:737 and shall be
of a make , type and brand as approved by the ENGINEER/Architect.
Panel type :
1) Perforated
2) Non Perforated – plain, Square, Rectangular and/or strips.
3) Non Perforated - patterned
4) Non Perforated - textured
5) Mesh
3.1.3 The aluminium panels shall be light weight, strong, flat, dimensionally
stable, free from sag, warp, sharp edges and shall be easy to install. The
surface shall be chemically treated to provide micro-etched surface to
promote tenacious bonding of the protective and decorative paint to be
finally applied.
3.1.4 The aluminium panels supplied by the CONTRACTOR shall be made out
of aluminium sheet of appropriate thickness as per size of panels
approved by the ENGINEER/ARCHITECT to suit grid and/or design
pattern of the false ceiling. The CONTRACTOR shall get a sample of the
panel duly approved by the ENGINEER/ARCHITECT before procuring
the panels for the entire ceiling.
3.2.1 The metal frame work shall be made out of rugged galvanised steel
conforming to IS: 2062 or extruded anodised aluminium sections
confirming to grade 63400 WP of IS: 737 as shown on the drawings. The
shape of cross-section of the members shall be such as to facilitate
proper suspension and proper fixing of the ceiling panels. The framework
shall also be structurally sound and rigid and of make, type and brand as
approved by the ENGINEER/ARCHITECT.
3.3. HANGERS
3.3.1 M.S. bars or flats confirming to IS: 2062 shall be used for the hangers.
Diameter or size of the hangers should be approved by the
ENGINEER/ARCHITECT to provide adequate structural strength to hold
framework on which aluminium are to be fixed.
4.0 WORKMANSHIP
4.1 Prior to installation, the entire execution team to have a briefing by the
supervisor on safe working practices using safety gear like helmets,
safety belts etc. Safety measures with regards to erection of scaffolding ,
working at heights, using of tools & emergency evacuation procedures to
be strictly followed to avoid any accidents. TCE.M10-PCS-10 to be
followed for Safety in Design.
4.2 The CONTRACTOR shall ensure that the frame to support the ceiling is
designed for structural strength and the sizes, weight and strength of
aluminium panels to be fixed and other loads due to live load at
75kg/sqm ( where human access is intended at particular locations, with
proper cat walks), air conditioning, grills, electrical cables /wiring and
lighting fixtures, thermal insulation etc. as shown on the drawings. The
false ceiling grid work shall be carried out as per the approved drawings
and approved load considerations as directed by the
ENGINEER/ARCHITECT.
4.3 The metal framework of extruded aluminium false ceiling grid system
shall consist of aluminium main member of special T-profile of 38 mm x
38mm x 1.5 mm interlocking with each other to form frames of various
sizes as shown on the drawing. The main members shall be suspended
from the roof structures by means of steel hangers and supported at the
walls by means of extruded aluminium wall angles 25 mm x 25 mm x 1.5
mm. In case of aluminium T-grid system, the panels shall be
manufactured a little undersized so as to be accommodated in the
standard `T` sections. ISSUE
R4
TATA Consulting Engineers Limited SECTION: WRITE
UP
TCE-M4-419-08 SHEET 4 OF 6 OF
ALUMINIUM PANEL FALSE CEILING
4.4 In the case of grid work made out of galvanised steel, these shall be of
such profile so that panels can be snapped into the suspension runners
with ease. Wall mound or section shall be fixed all along the perimeter of
the wall, wherever necessary.
4.5 The main grid member shall be suspended with the help of steel hangers
at 1.2 m centre to centre in both the directions. The hangers shall be
fabricated from mild steel / galvanised flats of 35 mm x 6 mm size or bar
of 10 mm diameter (or as designed by the engineer for higher loads),
threaded at the lower end and anchored securely in the roof concrete
using expansion bolts or welded to inserts provided on the underside of
slabs, beams etc. In case the roof work is of AC sheeting supported on
purlins and trusses, the hangers shall be suspended from the roof steel
work. The arrangement of metal hangers shall be such that the level of
false ceiling can be adjusted during fixing of the ceiling frame work. The
hangers shall be given two coats of red oxide zinc chromate paint
primer.
5.3 Store components in fully enclosed dry space. Carefully place on skids,
to avoid damage from moisture and other construction activities. Follow
IS: 4082:1996 guidelines for stacking and storage at site.
6.0 FINISHING
6.1 It is essential that the false ceiling work should be firm and in perfect
lines and levels and free from distortion, warp, bulge and other
defects. All defective sheets and other materials shall be removed from
site immediately and replaced, and ceiling restored to original finish
to the satisfaction of the ENGINEER/ARCHITECT.
ISSUE
R4
TATA Consulting Engineers Limited SECTION: WRITE
UP
TCE-M4-419-08 SHEET 5 OF 6 OF
ALUMINIUM PANEL FALSE CEILING
6.2 The workmanship is expected to be of highest quality. The joints for the
frame work shall be of interlocking type so that when the cross member is
in place, it cannot be lifted out.
6.3 All aluminium ceiling panels, tees etc. shall have a natural satin anodised
finish of grade AC 10 of IS: 1868 or approved powder coated shade If
anodised, the anodised surface shall finally be sealed for life –long finish.
6.4 Align joints in adjacent courses to form uniform, straight joints parallel to
room axis in both directions, unless otherwise indicated. Install
directionally patterned or textured panels in directions indicated on
approved shop drawings. Panel-joints shall flow smoothly and in a
straight line within 1 in 1000. Intersections shall be continuous.
6.5 Fit adjoining units to form flush, tight joints. Scribe and cut units for
accurate fit at borders and around construction penetrating ceiling.
6.6 Remove protective film from panels only when space is completely clean
and free of airborne particles. Use white cotton gloves for final
installation of panels into grid system.
7.0 WARRANTY
7.3 This warranty shall remain in effect for a minimum period of five (5) years
from date of initial acceptance.
8.0 SUBMITTALS
ISSUE
R4
TATA Consulting Engineers Limited SECTION: WRITE
UP
TCE-M4-419-08 SHEET 6 OF 6 OF
ALUMINIUM PANEL FALSE CEILING
8.3.1 Submit shop drawings for reflected ceiling plans (RCP’s), drawn to scale,
the detailed drawings shall be based on those of other services and shall
be prepared in close co-ordination with the other vendors/agencies.
8.3.2 Reflected Ceiling Plan(s): Indicating metal ceiling layout, the grid work,
sizes of grid members, method of suspension, position of openings for
air-conditioning and lighting, access doors, other penetrations and ceiling
mounted items etc.
8.3.5 Samples for Verification: Full-size units (or as specified below) of each
type of ceiling assembly indicated; in sets for each colour, texture, and
pattern specified, showing the full range of variations expected in these
characteristics. samples for each type specified of product to be
submitted.
9.0 MEASUREMENT
9.1 The flat plan area of false ceiling shall be measured and paid at the unit
rate less deductions, if any. Openings in false ceiling which are less than
0.2 sq.m. in area shall not be deducted for the purpose of payment.
9.2 The quoted rates shall include supply, delivery and erection of all
materials for covering the ceiling, frame work, suspenders or hangers
and their anchoring system, making openings, supporting the main
members on masonry walls, beams, levelling and painting, including
preparing of detailed false ceiling drawings. Nothing extra shall be
payable for modification accounting to 5% of area, that may be required
at site.
9.3 All the rates shall be inclusive of all the level differences as per design
and supply-installation of full system with necessary fixtures and
fasteners when made to merge with different type of ceiling. Scaffolding
is to be included in the rate and will not be paid separately.
END
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M4-419-11 SPECIFICATION FOR ANTI-TERMITE PRECONSTRUCTIONAL
SHEET 1 OF 1
CHEMICAL TREATMENT IN BUILDINGS
1.0 SCOPE
This specification covers the general requirements for Anti-termite Constructional
Measures, chemical treatment of soils for the protection of buildings from attack by
subterranean termites, chemicals to be used with their minimum rates of application
and procedure to be followed while the building is under construction.
2.0 APPLICABLE CODES AND SPECIFICATIONS
The following codes, standards and specifications are made a part of this specification.
In case of discrepancy between this specification and those referred to herein, this
specification shall govern.
The codes and standards mentioned below shall be latest as on the day of award of
contract of the works unless otherwise specified. Contractor shall be responsible to
inform to the Consultant/ Owner in case of any revisions/re-affirm/amendment in the
relevant codes and standards after the date of award of contract within 30 days of the
issue of such revision/re-affirm/amendment of the code/ standard. Consultant/ Owner
may approve use of the earlier code/ standard if the revisions do not materially affect
the statutory requirements of the project or does not impact safety practices. Any cost
impact arising out of such revisions shall be mutually agreed.
3.0 GENERAL
Contractor shall furnish all tools, plants, instruments, qualified supervisory personnel,
labour, materials, any temporary works, consumables, any and everything necessary
whether such items are specifically stated herein for completion of the job in
accordance with specification requirements or not.
All work shall be done in the order of progress required by Owner's construction
programme. Contractor shall take all necessary precautions to prevent any accident in
connection with the performance of the work.
On completion of all work, Contractor shall leave the entire premises within the site of
his operation clean and free from all rubbish resulting from his operation.
FILENAME: M4-419-11-REV-05.DOCX
Proprietary Notice and Version Control
This document contains confidential information for use only by the “Client”; for the Project under consideration, which is provided for the sole purpose of permitting the recipient to evaluate the information
submitted herewith. In consideration of receipt of this document; unless agreed to in contrary in the Contract; the recipient agrees to maintain such information in confidence and to not reproduce or otherwise
disclose this information to any person outside the recipient’s organisation; except that there is no obligation to maintain the confidentiality of any information which was known to the recipient prior to receipt of
ISSUE
such information from Tata Consulting Engineers Limited, or becomes publicly known through no fault of recipient, or Tata Consulting Engineers Limited, or is received without obligation of confidentiality from
a third party owing no obligation of confidentiality to Tata Consulting Engineers Limited. All information given under this version over rides all and any kind of offers, assumptions, deliverables and contracts
R5
submitted verbally (and subsequently communicated in writing) or in writing or otherwise given under any and all previous version/s.
Owner reserves the right to inspect, check and direct any or all operations at any stage
of the work and to require unsatisfactory work to be remedied at Contractor's expense.
No work shall be carried out under unsuitable weather conditions viz. when raining or
when the soil is wet due to rain or sub-soil water.
Chemicals shall be brought to site of work in sealed original containers. The materials
shall be brought in, at a time, in adequate quantity to suffice for the work. The material
shall be kept in cool and locked stores. The empties shall not be removed from the
work site till the relevant item of work has been completed and permission granted by
Owner/ Engineer.
Chemicals available in concentrated forms with concentration indicated on the sealed
containers only shall be used. Chemicals shall be diluted with water in required quantity
before use, using graduated containers to achieve the desired percentage of
concentration:
Examples:
Chlorpyriphos 20% EC 250 ml is diluted to 5 litres to give 1.0% emulsion.
Imidacloprid 30.50% SC 10.5 ml is diluted to 5 litres to give 0.075% emulsion
4.1.1 Application
Hand operated pressure pump with graduated containers shall be used to ensure
uniform spraying of the chemical. Continuous check shall be kept ensuring that the
specified quantity of chemical is used for the required area during the operation. On
large projects, a power sprayer may be used to save time and labour.
4.1.4 Disturbance
The treated soil barriers shall not be disturbed after they are formed. If by chance,
treated soil barriers are disturbed, immediate steps shall be taken to restore the
continuity and completeness of the barrier system.
ISSUE
R5
ISSUE
R5
ISSUE
R5
Particular care shall be taken to prevent skin contact with concentrates. Prolonged
exposure to dilute emulsions shall also be avoided. Workers shall wear clean clothing
and wash thoroughly with soap and water, especially before eating and smoking. In
the event of severe contamination, clothing shall be removed at once and the skin
washed with soap and water. If chemicals splash into eyes they shall be flushed with
plenty of soap and water and immediate medical attention shall be sought.
The concentrates are oil solutions and present a fire hazard owing to the use of
petroleum solvents. Flames shall not be allowed during mixing.
Care shall be taken in the application of chemicals to see that they are not allowed to
contaminate wells or springs which serve as source of drinking water.
In case of poisoning suitable measure shall be taken for protection in accordance with
IS 4015.
6.0 MEASUREMENTS
The measurements shall be made in sq.m on the basis of plinth area of the building at
ground floor only for all operations described above. Nothing extra shall be measured.
7.0 RATE
The rate shall include the cost of all materials and labour involved in all the operations
described above including making holes and refilling and making good the same.
END
ISSUE
R5
TCE.M4-419-12
FALSE OR CAVITY FLOOR SHEET 1 of 9
1. SCOPE
1.1 This specification covers the requirements of false or cavity floor constructed
over reinforced concrete floor slabs for control rooms, computer rooms, data
centers, office areas and other similar structures
2.1 The following specifications, standards and codes, including all official
amendments and revisions and other specifications referred to therein shall
be considered as a part of this specification. In all cases the latest
issue/edition/revision shall apply. In case of discrepancy between this
specification and those referred to herein, this specification shall govern.
ISSUE
R5
TCE.M4-419-12
FALSE OR CAVITY FLOOR SHEET 2 of 9
3.1 PEDESTALS
3.1.1 The false floor shall consist of a framework of suitable structural member
designed to carry the loads specified. This frame work shall be supported on
suitably designed pedestals placed at 600 mm centre to centre in both
directions.
3.1.3 The base plate shall be fixed to the reinforced concrete floor with an approved
adhesive compound or with 4 nos. 6 mm dia. anchor fasteners. Bedding of 1:2
or richer cement sand mortar shall be provided locally under the base plates of
pedestals to provide a level surface.
3.1.4 The prop head shall be provided with mild steel lugs welded on top and each
placed perpendicular to the other for proper positioning and supporting the
main and cross members.
3.1.6 All steel framework including steel pedestals shall be hot dip galvanized.
3.2.1.1 Floor panels shall be welded construction made out of high-grade cold rolled
steel sheets top and bottom plates, joined with 100 spot welding. The
thickness of top sheet shall be minimum 0.6mm and bottom sheet shall be
minimum 0.7mm.
ISSUE
R5
TCE.M4-419-12
FALSE OR CAVITY FLOOR SHEET 3 of 9
3.2.1.2 The sides of the panels shall be coated with epoxy powder coating of
minimum DFT 60 microns. Hollow core of the panel shall be filled with light
weight, fire retardant, non-combustible cementitious compound to support not
less than 90% of the top surface area of the panel. The core material must
contain recycled content. The panel core shall be filled with zero void to
eliminate weak spots.
3.2.1.3 Top surface of the panel shall be finished with any of the finishing materials
with anti-static properties such as high pressure laminate (HPL), PVC sheet,
carpet or hard surface such as natural stone or ceramic tiles. The floor finishes
shall conform to the requirements of relevant IS codes.
3.2.1.4 All edges of the panels shall be covered with PVC edge trim 5mm wide and of
colour matching with the floor finish. The edge trim shall be mechanically
locked and sealed in place to avoid detachment.
3.2.1.5 The panel size may be modified suitably near electrical panels/equipments
and also to suit room dimensions, however, the panel size shall not be more
than 600mm and less than 150mm (near wall edge) unless specified
otherwise.
3.2.1.6 In case the bigger and/or non-standard panel size needs to be provided due to
services requirement, same shall be clearly mentioned in the drawing and
designed accordingly.
3.2.2.1 The floor panels shall be made of calcium sulphate core of minimum thickness
30mm and having high density natural Gypsum. The core shall be
manufactured by compressing multiple layers of gypsum for homogenous
density across the panel and low moisture absorption.
3.2.2.2 The top surface of the core shall be bonded and laminated with anti-static high
pressure laminate (HPL) or static dissipative/conductive vinyl sheet. Bottom
surface of the core shall be bonded with aluminum of galvanized steel sheet.
3.2.2.3 The panel edges shall be provided with total encapsulation of PVC/ABS edge
band for entire panel depth.
ISSUE
R5
TCE.M4-419-12
FALSE OR CAVITY FLOOR SHEET 4 of 9
3.2.3.1 The floor panel shall consist of high density chipboard / particle board core
strengthened with high performance thermosetting resin and encapsulated on
all sides including edges with corrosion resistant galvanized steel sheet. The
panel thickness shall be 35-40mm.
3.2.3.2 The particle board shall be fire resistant, termite resistant, moisture proof
quality and shall generally conform to the requirements of IS:3087 –
Specification for wood particle boards (medium density) for general purposes.
3.2.3.3 The top surface of the particle board panel shall be factory laminated with anti-
static/ESD high pressure laminate (HPL) or anti-static/ conductive / dissipative
vinyl sheet ensuring maximum bonding to steel surface. The panel edges shall
be protected with conductive PVC edge band on all sides.
3.2.4.1 The panel shall comprise of a high strength di-casting aluminum structure. The
floor panel shall be formed / machined to the size, shape and squareness
within the tolerance range as specified.
3.2.4.2 The panel surface shall be coated with epoxy coating / anodizing / nickel-
chromium coating or bare metal finish.
3.2.4.3 The floor panel shall be capable of receiving the floor finishes such as carpet,
high pressure laminate (HPL), vinyl sheet or any other hard surface such as
natural stone or ceramic tile.
3.3 ACCESSORIES
3.3.1 Manufacturer’s listed access floor outlet boxes shall be provided in locations
as detailed on the contract drawings. Large capacity 11 ¼ inch (285.75 mm)
square service outlet boxes shall be capable of accommodating four duplex
receptacles, six individual voice/data termination points and one grommet port.
Standard capacity 7-5/16 (185.67 mm) by 6-15/16 (176.02 mm) inch service
outlet boxes shall be capable of accommodating two duplex receptacles, two
ISSUE
R5
TCE.M4-419-12
FALSE OR CAVITY FLOOR SHEET 5 of 9
individual voice data/termination points and one grommet port. The service
outlet box shall be a drop-in design having a hinged lid with carpet insert and
frame with tapered edge. Service outlet box shall be capable of withstanding
without failure an 800 lb. (3.55 Kn).
3.3.2 Steps, ramps, fascia plate, perimeter support, and grommets shall be as per
manufacturer's standards and shall be provided where indicated on the
contract drawings.
4 WORKMANSHIP
4.1.1 Structural sub floor for shall be examined for unevenness, irregularities and
dampness that would affect the quality and execution of the work. Installation
work shall not be carried out until structural floor surfaces are level, clean, and
dry as completed by others.
4.1.2 Concrete sealers, if used, shall be identified and proven to be compatible with
pedestal adhesive. If other than manufacturer’s recommended adhesives or
sealers are used, verify that adhesive achieves bond to slab before
commencing work.
4.2 INSTALLATION
4.2.1 Pedestal locations shall be established from approved shop drawings so that
mechanical and electrical work can be installed without interfering with
pedestal installation.
4.2.2 In case of expansion joint in the sub floor, expansion joint shall be provided in
the false floor. The flooring shall be separated at expansion joint and separate
pedestals and floor panels shall be provided on either side of the expansion
joint with suitable joint cover.
4.2.3 Installation of access floor shall be coordinated with other trades to maintain
the integrity of the installed system. Traffic shall not be permitted on any floor
area for 24 hours to allow the pedestal adhesive to set.
ISSUE
R5
TCE.M4-419-12
FALSE OR CAVITY FLOOR SHEET 6 of 9
4.2.4 Floor system and accessories shall be installed under the supervision of the
manufacturer’s authorized representative and according to manufacturer’s
recommendations.
4.2.6 Partially complete floors shall be braced against shifting to maintain the
integrity of the installed system where required.
4.2.7 Additional pedestals as needed shall support panels where floor is disrupted
by columns, walls, and cut-outs.
4.2.8 Under structure shall be aligned such that all uncut panels are
interchangeable and fit snugly but do not bind when placed in alternate
positions.
Table 1:
Description Tolerance / Limit
Panel size ± 0.25mm
Panel Squareness ± 0.25mm - ± 0.38mm
Panel Flatness ±0.50mm - ± 0.75mm
Installed False Floor Level 1.5 mm in 3.0m or 2.5 mm overall
Height Variation between adjoining
± 0.50mm
panels
5 PERFORMANCE
5.1 LOADING
5.1.1 The floor system shall meet or exceed the specific performance requirements
under loading conditions as mentioned in the below table:
ISSUE
R5
TCE.M4-419-12
FALSE OR CAVITY FLOOR SHEET 7 of 9
Table 2:
Load Type Loadin value
Concentrated Load over 25mm x
350 – 1500 Kg
25mm area
Uniformly Distributed Load (UDL) 900 – 1650 Kg/m²
Rolling Load 360 Kg for 10 passes
50 kg from 1.0m height above floor
Impact Load
over 50mm dia surface
Axial Load 22.5 KN for individual pedestal
5.2.1 The panels shall conform to class 0 and class 1 fire ratings tested as per BS
476 (Part 6 & 7).
5.2.2 The surface and bulk electrostatic resistance shall fall in the range of 2.5x104 -
1x10² Ohms (Conductive range), 1x106 - 1x109 Ohms (Static Dissipative range)
and 1x109 – 2x1010 Ohms (Anti-static range).
5.3.1 Humidity resistance for the entire system including hardware and accessories
shall be up to 100%.
6.1 Material received at site shall be with original packing, labels, batch dates. It
shall be untouched/ intact till issued for use of site.
6.2 Material shall be stored at properly covered dry location and shall be safe from
any sort of physical damage.
7.1 Vendor shall prepare and submit a layout drawing for false floor giving all
details including supporting system for approval. If so called for, vendor shall
ISSUE
R5
TCE.M4-419-12
FALSE OR CAVITY FLOOR SHEET 8 of 9
also submit his calculations for the supporting system with all relevant data
assumed, to the ENGINEER for his approval. Work shall be carried out on
approved drawings only.
8 MOCK-UPS
8.1 The contractor shall prepare and install mock-up samples as per approved
shop drawings.
8.2 Mock-up samples shall be of full size and shall be true representation of actual
works to be carried out at site. Mock-ups may be part of completed work if
undisturbed.
8.3 In case of expansion joint in the floor, the mock-up shall contain expansion
joint with necessary joint cover.
9 MEASUREMENTS
9.1 Mode of measurement will be in sqm. The Mode of measurement will be same
as flooring as mentioned in IS-1200. The superficial area of false floor shall be
measured and paid for at the quoted unit rate.
9.2 The quoted rate shall include supply, delivery at site, preparation of surface,
Ramps/steps ,cutting for supply/return Air Grills etc and for Grommet of
required size, wastages, lead & lift, grouting the system with anchor fastener,
removing all debris from the premises etc. complete, as directed and for
providing subfloor insulation (only in air conditioned areas ) with adhesives to
the entire area of existing (Below false flooring) as per manufacturer's
specifications labour, Overheads and Profits, transport, all taxes if applicable.
Rate shall also include to produce a test certificate for the specified load of
approved laboratory.
ISSUE
R5
TCE.M4-419-12
FALSE OR CAVITY FLOOR SHEET 9 of 9
10 GUARANTEE
10.1 Contractor shall provide one (1) year guarantee, in format approved by
Owner/Engineer, against any defects caused by faulty materials and or
workmanship or non-compliance with this specification.
10.2 The installed false or cavity flooring system shall be capable of withstanding
the day to day operating load and conditions of the general office and/or
equipment room environment. The acceptable overall design life shall be 25
years.
END
ISSUE
R5
1. SCOPE
1.1. This specification covers the design, supply of materials, manufacture and
installation of factory made type fire rated steel doors with 2 (two) Hours fire
rating of approved make with rating as per the requirements with all
accessories, hard wares, iron mongery, fastening materials and including
installation of door with hard wares in position.
1.2. All metal work shall be free from defects, impairing strength, durability and
appearance and shall be of the best quality for purposes specified made with
structural properties to withstand safety strains, stresses to which they shall
normally be subjected to. All Hard ware fittings and Accessories shall be of
high quality and as specified and as approved by the Engineer-In-Charge.
1.3. The Contractor shall furnish all materials, labour, operations, equipment, tools
and plant, scaffolding and incidentals necessary and required for the
completion of metal work in connection with steel doors, as called for in the
drawings, specifications and bill of quantities which cover the major
requirements only. Anything called for in the tender documents shall be
considered as applicable to the items of work concerned. The supply and
installation of additional fastenings (Metal expansion Shields), accessory
features and other items not specifically mentioned, but which are necessary
to make a complete functioning installation shall form a part of this contract.
1.4. The Contractor shall strictly follow, at all stages of work, the stipulations
contained in the Indian Standard Safety Code and the provisions of the safety
code and the provision of the safety rules as specified in the General
Conditions of the Contract for ensuring safety of men and materials.
1.5. Any approval, instructions, permission, checking, review, etc. whatsoever by
the Engineer-In-Charge, shall not relieve the Contractor of his responsibility
and obligation regarding adequacy, correctness, completeness, Safety,
strength, quality, workmanship, etc. The Contractor shall submit the Shop
drawing for all works including all details, and after check by his own
Engineer. They shall not commence the work before obtaining prior and final
approval for shop drawings incorporating the changes, if any, instructed by
Engineer-In-Charge. Such prior approval shall not relieve the Contractor from
his responsibility of correctness of design, workmanship and material errors
and omissions, if any.
ISSUE
R4
2.1. All standards, specifications, acts, and codes of practice referred to herein
shall be the latest editions including all applicable official amendments and
revisions.
2.2. List of certain important Indian Standards, Acts and Codes applicable to this
work is given below. However, the applicable standards and codes shall be as
per this but not limited to the list given below:
IS : 277 Galvanized steel sheet (plain and
corrugated) of GPL Grade Z 120
coating.
IS: 3614 Part 1 and 2/ BS 476 Metallic and non-metallic fire check
Part 20 and 22 doors -Resistance test and
Performance criteria.
BS 7352 /BS EN 1935 Specification of Hinges
NBC 2016
2.3. The Fire Doors shall be Underwriters Laboratories (UL) listed/ Factory mutual
(FM) approved/ CBRI Roorkee /BIS accredited body or approved by any other
National or International standardization Bureau /Organization accredited test
laboratory.
3. MATERIALS
3.1. Following materials as per available size with the manufacturer and as
approved by the consultant should be used -
3.2. All materials, items, hardware etc. shall be subjected to approval by
Engineer-In-Charge. Necessary documentation/ test certificates shall be
furnished by the Contractor for such approval. Fire doors shall be fabricated
only after approval of materials etc., by Engineer-In-Charge.
3.3. Each Fire door shall be provided with a small metal identification plate in
suitable location indicating Fire rating, name of the Manufacturer, date of
installation and approval of approved test house.
3.4. Each vision panel shall carry a stamp of the manufacturer unless otherwise
mentioned elsewhere; all Fire Check Doors shall be of two hours (120 Min.)
fire integrity.
ISSUE
R4
DOOR FRAME:
4.1. Material: Frame shall be manufactured by using Galvanized steel sheets
complying with latest IS 277. Galvanized coating shall be GPL grade Z 120
coating.
4.2. Profile: Fire Door - 2 Hour rating: Double rebate profile of size 143 x 57 mm
(+/- 0.3) with bending radius of 1.4 mm. For any variation in size, which will be
as per manufacturer’s sizes, approval to be obtained from Engineer-in charge.
4.3. Frame shall be fabricated to the thickness specified below: 16 Gauge or 1.6
mm thick.
4.3.1. Frames fabricated at factory shall be in knock down form with butt joints for
bolted assembly at site or as per manufacturer’s Specification.
4.3.2. Frames shall be provided with 3 mm thick back plates on all jambs with
provision for anchor bolt fixing to wall openings.
4.3.3. Frames shall be provided with hinge plates 3 mm thick pre-drilled to receive
approved type and make of hinges for screw mounted fixing.
4.3.4. Frames shall have factory finish-pre-punched cut outs to receive specified type
and make of hardware and iron Mongery. All cut outs including hinge plates,
strike plates to have mortar guard covers from inside to prevent cement, dust
ingress into cut outs at the time of grouting of the frame.
4.3.5. Frames shall have reinforcement pads for fixing of door closer, locks and
handles at appropriate location as per manufacturer’s details.
4.3.6. Frames shall have plug-in type rubber silencer not less than 2 mm dia on the
strike jambs for single shutter frames and on the head jambs for double
shutter frames.
4.4. The total door assembly shall ensure fire and smoke integrity as per the fire
rating.
DOOR SHUTTER:
4.5. Material: Shutter shall be manufactured with double skins press formed by
using Galvanized steel sheets complying with latest IS 277. Galvanized
coating shall be GPL grade Z 120 coating.
4.6. Profile: Shutters should be press formed with double skins in such a way to
get 46 mm thick double skin hollow door with lock seam joints at stile edges.
ISSUE
R4
4.7. Fire Door shutter profile shall be as given below: Fire Door - 2 Hour rating: 18
Gauge or 1.25 mm thick.
4.7.1. Shutters shall have no visible screws or fasteners on both face and internal
reinforcement shall be provided at top, bottom and stile edges for desired fire
rating.
4.7.2. In Fill Material: Shutters shall be provided with honeycomb paper core as infill
material and to be bounded to the inner faces of the shutter or as per
Manufacturer’s specification. Door should have been tested with Infill material
proposed by the manufacturer and the same should have been approved by
CBRI.
4.7.3. Preparation: Shutters shall be provided with factory prepared and with pre-
punched cut-outs and reinforcement pads to receive the approved type and
make of Hardware and Iron Mongery. The shutter should have an interlocking
arrangement at this stile edges for flat surface on either side.
4.7.4. Shutters shall have pre-drilled hinge plates with hinge guard covers.
4.7.5. Shutters with locks shall have concealed lock box with lock fixing brackets with
pre-tapped holes and screws.
4.7.6. Shutter shall have reinforcement pad at appropriate location to receive the
locks, Door closer, Panic Bar, etc as per the approved type and make of
Hardware and all as per manufacturer’s design and conforming to Standards.
4.7.7. Necessary provision / fixing arrangements shall be provided in the shutter as
well as in the frame to receive / fix the Electromagnetic latch, Electromagnetic
contact for hooters with reinforcement pads and in such a way to connect the
same to the card access control system / IBMS. Fixing Details of the above
latches shall be provided in coordination with IBMS agency.
4.7.8. Vision panel shall be of 120 minutes fire rated (conforming to BS 476 part 22),
6mm thick borosilicate or other special substrate clear, non-wired, toughened
float glass of approved manufacturer. The Glass shall be compliant to Class A
Category of Impact Resistance to BS 6206:1981 Safety Glazing Material.
Glass shall be fixed with necessary beading. The integrity should be tested for
required fire rating.
4.8. Surface of the frame and shutter shall be cleaned suitably and thoroughly
with solvents as per manufacturer’s specification.
ISSUE
R4
4.9. Zinc etch primer coating shall be applied as shop coat to receive additional
coat of primer and top coats.
4.10. Stove zinc phosphate primer (35 microns DFT) shall be applied as additional
coat.
4.11. The surface shall be neatly finished with thermo setting polyurethane paint
(35 microns DFT) of approved colour and make.
5. PACKING
5.1. Individual frames members and individual shutters shall be wrapped and
protected with self-adhesive Peel-off Polythene sheets or Co extruded PE film
to a minimum thickness of 60 Microns, with low tack adhesive and with
abrasion resistant for a minimum period of 6 months and UV resistant
capability.
5.2. Individual frames members and individual shutters shall be packed in an
individual card board boxes and to be sealed with Identification numbers.
5.3. All frames and shutters shall be marked with identification number in such a
way install the door according to the door schedule.
6. STORAGE
6.1. Frames shall be stacked flat and shutters shall be stacked vertically on
wooden runners and suitably covered as per the manufacturer’s instructions
to prevent rust and damage.
7. INSTALLATION
FRAME:
7.1. Door frames shall be assembled adjacent to the place of installation as per
the Manufacturer’s specification. Frames are not allowed for transporting in an
assembled condition. If the manufacturer is desired to transport the frames in
an assembled condition, the frames should be designed suitably and
adequate packing to be given prior to transport in order to avoid any damage,
bending etc. during transport. If any defects found during the installation, such
frames will be summarily rejected and will not be allowed to use.
7.2. After assembly it is to be ensured that all threaded preparations / joints shall
be covered by using 15 x 10 self-adhesive sponge strips at the back of the
frame to prevent penetration of grouting mortar into screw threads. The head
member of assembled frame shall be positioned against jambs ensuring ISSUE
R4
7.6.12. The frames shall be back filled through holes provided and nylon plugs shall
be inserted after cleaning the surface. Nylon plugs shall be provided to suit the
frame finish and colour.
7.6.13. The Gaps between the frame and masonry surface shall be grouted with
cement slurry and sealed with Intumescent sealant of approved make, if called
for in the Bills of quantities.
SHUTTER:
7.7. All the hardware shall be fixed to the door shutter like hinges, flush bolts,
bolts, Mortise locks, Dead lock, handle, Push plate, Door closer, Door
stoppers, etc. with the appropriate SS screws and bolts supplied.
7.8. The shutter shall be fixed in to the installed frame and the shutter is aligned to
match the hardware cut-outs in the frame. The hinge screws shall also be
tightened.
7.9. The door jamb rebate surfaces shall be cleaned of all dust, oil etc.
7.10. Self-adhesive ‘FLAT’ seal shall be affixed on the door frame rebates, on hinge
jambs, strike jambs, head member, sill etc. and ‘FLAT’ seal in the shutter shall
also be affixed by using self-adhesive EPDM smoke seal ‘FLAT’ type
(Polyethylene cross linked foam of size 2 mm thick and 12.5 mm width) as
indicated by the manufacturer and if specifically called for in the bills of
quantities.
8. HARDWARE :
8.1. Fire proof doors of all type shall be provided with Hardware required for
complete stability and integrity of the door for the proposed fire rating and
vision panel (wherever applicable). All fire doors shall be fitted with an
automatic self-closing device of same fire rating as of the door which is
capable of closing the door from any angle and against any latch fitted to the
door. The fire door shall be capable of being opened manually, not be held
open by any means other than by an electromagnetic or electro-mechanical
device which can be activated by presence of smoke and/or the fire system,
provided that this shall not apply to fire doors opening into pressurised exit
staircases.
ISSUE
R4
9. PERFORMANCE REQUIREMENTS
9.1. In case of proprietary design of the manufacturers, the doors should have
valid fire test certificate from UL/FM/VDS/CBRI ROORKEE or from any other
national or international standardization Bureau/Organization, accredited
testing laboratory.
10. EXECUTION:
10.1. Shop drawings of the doors in accordance to the prototype door profile shall
be used to obtain fire test certificate. The shop drawings shall include all
details of construction, anchoring, connections, fastenings, accessories etc.
Any suitable modification in fittings, fixtures as required for project specific
installations shall have to be incorporated in door profile and approval
obtained prior to the installation of the door.
11. TESTING
11.1. Along with all material tests the complete system along with the framing shall
be tested in accordance with the criteria of BS 476: Part 22 1987 and Report
212 (1)/FR/2003; insulation at door leaf only. The door system shall be tested
using a steel Mortise latch set with a steel knob set. The ACRYLIC sealant
and the Intumescent door strip shall be tested in accordance with BS 476:
Part 20 and AS 1530: Part 4 and AS 4072: Part1
12. GUARANTEE
12.1. The doors including all hardware (excepting door closer) shall be guaranteed
for a period of 12 months from the date of installation against any
manufacturing defect.
12.2. Guarantee period for Door Closer shall be 10 years. In case of any such
defect within the guarantee period, the defected part shall be replaced by the
Contractor.
13. MEASUREMENT
13.1. The measurement for Fire Check doors shall be in numbers of different types
of doors supplied, fixed and approved by the Engineer. Different sizes of
doors shall be counted separately.
It shall include:
ISSUE
R4
13.1.1. Supply of all requisite materials, manufacturing and fixing in position with the
required standard of workmanship including supply-and-fixing of fixtures,
straps, bolts, hold-fasts, spikes, nails, screws, etc. applying contractors glue
or other jointing materials, coal tarring embedded parts, glazing and
supplying and fixing of all specified fittings painting as specified.
13.1.2. All material, labour, scaffolding, use of equipment etc. for framing, fixing and
completing the item as specified.
13.1.3. Measurement shall be in square metre for clear area over one face inclusive
of exposed frame. Portions embedded in masonry/concrete/ flooring shall not
be measured.
14. SUBMITTALS
14.1. Following documentation/ drawings shall be furnished along with the Doors
14.2.2. Certificate should indicate all clauses laid down by BIS & sustainability of
assembly and integrity for required fire rating.
ISSUE
R4
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 1 OF 54
1.0 SCOPE
1.1 This specification covers the general requirements of providing and laying
water mains and water supply piping, providing and fixing sanitary fixtures
and piping and providing and laying drainage lines.
1.2 For specifications, mode of measurements and scope of work covered under
the respective items for the work included under this contract, following
documents shall be referred to in the order of precedence as given below:
b) Drawings
c) Specifications.
In the event of any discrepancy among the documents referred above, the
document in the higher order of precedence shall prevail.
1.3 In the event of any element of specification not being available in any of the
documents mentioned above, the instructions of the Engineer-in-Charge in
writing shall be followed by the Contractor.
1.4 The Work shall be carried out in accordance with the drawings and designs
as would be issued to the Contractor by the Engineer-in-Charge duly signed
and stamped by him. The Contractor shall not take cognisance of any
drawings, designs, specifications, etc. not bearing Engineer-in-Charge's
signature and stamp. Similarly the Contractor shall not take cognisance of
instructions given by any other Authority except the instructions given by the
Engineer-in-Charge in writing.
1.5 The Work shall be executed and measured as per metric dimensions given in
the Schedule of Quantities, drawings etc.
1.6 The Contractor shall acquaint himself fully with the partial provisions for
supports that may be available in the structure and utilise them to the extent
possible. In any case the Contractor shall provide all the supports regardless
of provisions that have been already made. Nothing extra shall be payable for
situations where bed plates (for supports) are not available or are not useful.
The contents of this document are proprietary and confidential to Tata Consulting
Engineers Limited (TCE) and the disclosure of the contents to anyone outside TCE
is strictly prohibited except with the prior written consent from TCE.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 2 OF 54
1.8 Shop coats of paint that may be damaged during shipment or erection shall
be cleaned off with mineral spirits, wire brushed and spot primed over the
affected areas, then coated with paint to match the finish over the adjoining
shop painted surface.
1.9 In addition to the sectional testing carried out during the construction, the
Contractor shall test the entire installation after connections to the overhead
tanks or pumping system or mains. He shall rectify all leakage and shall
replace all defective materials in the system. Any consequential damage
done, on account of Contractors carelessness, open or burst pipes or failure
of fittings, during testing and commissioning to the building, furniture and
fixtures shall be made good by the Contractor.
2.0 SCAFFOLDING
2.1 Only steel tube scaffolding of approved design shall be used for all works.
The scaffold structure shall comply with the requirements of IS: 4014 and IS:
3696. An independent tied scaffold (double scaffold), which has two lines of
standards, shall be provided with the inner line kept at least one board clear
of the finished face with extended transoms, or hop up baskets to carry an
inside board. Diagonal braces shall not prevent the material being moved
along the scaffold run. The scaffolding shall be suitably packed at the ends to
prevent damage to the finished work.
3.0 PROTECTION
3.1 Protection against damage: Care shall be taken to avoid damage from any
cause at all stages. Packing pieces used for protection shall not disfigure or
otherwise permanently mark the Works.
3.2 Surface protection shall be afforded by careful handling and the avoidance of
the use of hooks, crowbars, or other implements that are likely to damage the
works.
3.3 During installation of piping, open end of pipe shall be protected with
temporary cover to prevent dust or other materials entering in it.
3.5 Protection of finished work: At all stages of the Contract it is essential that all
works are properly protected.
3.6 Suitable packing shall be used to ensure that scaffolding does not damage
erected stone, marble, granite or other finished works.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 3 OF 54
4.0 GUARANTEE
4.1 The Contractor shall guarantee and undertake to maintain and rectify the
various components of the Plumbing work installed by him for successful
performance for a period as indicated in the Datasheet-A. The Contractor
shall indemnify the Engineer-in-Charge for a similar period against any
damage to property and injury to persons on account of any defective work or
maintenance carried out by the Contractor. The format and text of the
Guarantee and the Indemnity Bond shall be given by the Engineer-in-Charge.
5.1 All equipment, supply, erection, testing and commissioning shall comply with
the requirements of Indian Standards and code of practices given below as
amended till date. All equipment and material being supplied by the contractor
shall meet the requirements of IS, and other Codes/ Publications as given
below.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 4 OF 54
IS:1554 (Part 2) PVC insulated (heavy duty) electric cables: Part 2 For
working voltages from3.3 kV up to and including 11 kV.
IS:1726 Specification for cast iron man hole covers and frames
IS:2527 Code of practice for fixing rain water gutters and down
pipes for roof drainage
IS:5329 Code of practice for sanitary pipe work above ground for
buildings
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 5 OF 54
IS:9912 Coal tar based coating materials and suitable primers for
protecting iron and steel pipe lines
BSEN274 Sanitary tap ware, waste fittings for basins, bidets and
baths. General technical specifications
IS:1538 Cast iron fittings for pressure pipes for water, gas and
sewage
IS:1729 Sand cast iron spigot and socket soil, waste and
ventilating pipes, fitting sand accessories
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 6 OF 54
IS:2643 (Part 3) Dimensions for pipe threads for fastening purposes: Part
3 Limits of sizes
IS:4346 Specifications for washers for use with fittings for water
services
IS:6418 Cast iron and malleable cast iron flanges for general
engineering purposes.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 7 OF 54
IS:775 Specification for cast iron brackets and supports for wash
basins and sinks
IS:781 Specification for cast copper alloy screw down bib taps
and stop valves for water services
IS:2548 (Part 1) Specification for plastic seats and covers for water
closets: Part 1:Thermoset seats and covers
IS: 2548(Part 2) Specification for plastic seats and covers for water
closets: Part 2:Thermoplastic seats and covers
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 8 OF 54
IS:3311 Specification for waste plug and its accessories for sinks
and wash basins.
IS:6249 Specification for flush valves and fittings for marine use
6.1 The Work shall conform to high standards of design and workmanship, shall
be structurally sound and aesthetically pleasing. Quality standards prescribed
shall form the backbone for the quality assurance and quality control system.
6.2 At the site level the Contractor shall arrange the materials, their stacking/
storage in appropriate manner to ensure the quality. Contractor shall provide
equipment and manpower to test continuously the quality of materials,
assemblies etc. as directed by the Engineer-in-Charge. The test shall be
conducted continuously and the result of tests maintained. In addition the
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 9 OF 54
6.3 The Engineer-in-Charge shall be free to carry out tests as may be considered
necessary by him at his sole discretion, from time to time, in addition to those
specified in this document. The Contractor shall provide the samples and
labour for collecting the samples. Nothing extra shall be payable to the
Contractor for samples or for the collection of the samples.
6.4 The test shall be conducted at the site laboratory that may be established by
Engineer-in-Charge or at any other Standard Laboratory selected by
Engineer-in-Charge.
6.5 The Contractor shall transport the samples to the laboratory for which nothing
extra shall be payable. In the event of Contractor failing to arrange
transportation of the samples in proper time Engineer-in-Charge shall have
them transported and recover two times the actual cost from the Contractor's
bills.
7.1.1 Without restricting to the generality of the foregoing, sanitary and other
appliances shall inter-alia include the following:-
7.1.2 Whether specifically mentioned or not the Contractor shall provide for all
appliances and fixtures all fixing devices, nuts, washers, teflon tape, sealant,
cement, brackets, supports, paints, connectors, cp riser pipes, adopters,
bolts, screws, hangers etc as required.
7.1.3 All exposed pipes within toilets and near appliances/ fixtures shall be of
chromium plated brass or copper unless otherwise specified.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 10 OF 54
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 11 OF 54
7.2.1 All materials shall be new and of quality conforming to specifications and
subject to the approval of the Engineer-in-Charge. Wherever particular makes
are mentioned, the choice of selection shall remain with the Engineer-in-
Charge.
7.2.2 All appliances, fixtures and fittings shall be provided with all such accessories
as are required to complete the item in working condition whether specifically
mentioned or not in the Schedule of Quantities, specifications, and drawings.
Accessories shall include proper fixing arrangement, brackets, nuts, bolts,
washers, screws and required connection pieces.
7.2.3 Fixing screws shall be half round head chromium plated (CP) brass screws,
with CP brass washers unless otherwise specified.
7.2.4 Porcelain sanitary ware shall be glazed vitreous china of first quality free from
warps, cracks and glazing defects conforming to IS: 2556. The choice of the
colour of the Sanitary ware shall be that of the Engineer-in-Charge and
nothing extra shall be payable to the Contractor for fixing of Sanitary ware of
any colour.
7.2.5 Sinks for kitchen shall be of stainless steel or as specified in the Schedule of
Quantities.
7.2.6 Chromium plated fittings shall be cast brass chromium plated of the best
quality approved by the Engineer-in-Charge.
7.2.7 If supply of sanitary appliances, fixtures & fittings are in client’s scope, no
damages shall occur to the same during shifting, transportation, installation till
successful handing over. If any damage occurs, the same shall be replaced
by the contractor at his own cost.
7.2.8 All appliances, fittings and fixtures shall be fixed in a neat workmanlike
manner true to level and to heights shown on the drawings and in accordance
with the manufacturer recommendations. Care shall be taken to fix all inlet
and outlet pipes at correct positions. Faulty locations shall be made good and
any damage to the finished floor, tiling, plaster, paint, insulation or terrace
shall be made good by the Contractor at his own cost.
7.2.9 All materials shall be rust proofed; materials in direct or indirect contact shall
be compatible to prevent electrolytic or chemical (bimetallic) corrosion.
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 12 OF 54
7.3.1 Squatting type water closet (WC) pan shall be of Orissa pattern of size as
specified in Schedule of Quantities. Each WC pan shall be provided with a
100mm dia cast iron or porcelain P or S trap with or without vent horn as
directed by the Engineer-in-Charge.
7.3.2 WC shall be flushed by means of concealed type or exposed type (as detailed
in the drawings or as directed by the Engineer-in-Charge) 32mm size CP
brass flush valve with regulator valve or cistern.
7.3.3 WC shall be fixed securely with trap by rich cement mortar & supported
properly with brickwork.
7.4.1 WC shall be wash down or siphonic wash down type floor or wall mounted
set, as shown in the drawings, designed for low volume flushing from 3-6
litres of water, flushed by means of a flushing cistern or an exposed or
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 13 OF 54
7.4.2 Each WC set shall be provided with a solid plastic seat, rubber buffers and
chromium plated brass hinges. Plastic seat shall be so fixed that it remains
absolutely stationary in vertical position without falling down on the WC.
7.4.3 Each WC set shall be provided with a fixed type CP brass ablution jet, if
called for in schedule of quantities, complete with CP/ plastic piping,
concealed type CP brass angle cock etc. all of approved make and brand.
The nozzle of the ablution jet and its holding down plate shall have smooth
and rounded edges and shall not be capable of causing any injury to a user or
cleaner.
7.5.1 Universal type water closet shall be wash down or siphonic type floor
mounted porcelain ware flushed by means of a porcelain flushing cistern or
an exposed or concealed type (as detailed in the drawings or as directed by
the Engineer-in-Charge) 32mm size CP brass flush valve with regulator valve.
Flush pipe/ bend shall be connected to the WC by means of a suitable rubber
adaptor.
7.5.2 Each WC set shall be provided with a solid plastic seat, rubber buffers and
chromium plated brass hinges. Plastic seat shall be so fixed that it remains
absolutely stationary in vertical position without falling down on the WC.
7.6 URINALS
7.6.1 Urinals shall be lipped type half stall white glazed vitreous china of size as
called for in the Schedule of Quantities.
7.6.2 Half stall urinals shall be provided with 15mm dia CP spreader, 32mm dia CP
domical waste and CP cast brass bottle/”P” trap with pipe and wall flange and
shall be fixed to wall by CI brackets, CI wall clips and CP brass screws as
recommended by manufacturer complete as directed by the Engineer-in-
Charge.
7.6.3 Flushing for urinals shall be by means of no hand operation, PVC or ceramic
flushing cistern / electronic auto flush valve with all internal fittings, mounted
on a C.I. brackets, and painted with two coats of approved paint of approved
shade and confirming to IS: 2326.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 14 OF 54
7.6.4 Flush pipes shall be PVC pipes concealed in wall chase but with chromium
plated bends at inlet and outlet or as given in Schedule of Quantities. These
shall be measured and paid for separately.
7.6.5 PVC waste pipes shall be provided for urinals. Waste pipes may be exposed
on wall or concealed in chase as directed by the Engineer-in-Charge. These
shall be measured and paid for separately.
7.7.1 Urinal partitions shall be white glazed vitreous china of size specified in the
Schedule of Quantities.
7.7.2 Porcelain partitions shall be fixed at proper heights with CP brass bolts,
anchor fasteners and MS clips as recommended by the manufacturer and
directed by the Engineer-in-Charge.
7.8.1 Wash basins shall be white glazed vitreous china of size, shape and type
specified in the Schedule of Quantities.
7.8.2 Each basin shall be provided with painted MS angle or C.I. brackets and clips
and the basin securely fixed to wall. Placing of basins over the brackets
without secure fixing shall not be accepted. The MS angle shall be provided
with two coats of red oxide primer and two coats of synthetic enamel paint of
make, brand and colour as approved by the Engineer-in-Charge.
7.8.3 Each basin shall be provided with 32mm dia CP waste with overflow, pop-up
waste or rubber plug, CP angle valve, CP riser pipe with connectors /
adoptors and CP brass chain as specified in the Schedule of Quantities,
32mm dia CP brass bottle trap with CP pipe to wall flange.
7.8.4 Wash basin shall be provided with hot and cold water mixing fitting or as
specified in the Schedule of Quantities.
7.8.5 Basins shall be fixed at proper heights as shown on drawings. If height is not
specified, the rim level shall be 790mm from finished floor level or as directed
by the Engineer-in-Charge.
7.9 SINKS
7.9.1 Sinks shall be stainless steel or any other material as specified in the
Schedule of Quantities.
7.9.2 Each sink shall be provided with painted MS or CI brackets and clips and
securely fixed. Counter top sinks shall be fixed with suitable painted angle
iron brackets or clips as recommended by the manufacturer. Each sink shall
be provided with 40mm dia CP waste, CP angle valve, CP riser pipe with
connectors / adoptors and rubber plug with CP brass chain as given in the
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 15 OF 54
Schedule of Quantities. The MS angle shall be provided with two coats of red
oxide primer and two coats of synthetic enamel paint of make, brand and
colour as approved by the Engineer-in-Charge.
7.9.3 Supply fittings for sinks shall be deck mounted CP swivel faucets with or
without hot and cold water mixing fittings as specified in the Schedule of
Quantities. These shall be measured and paid for separately.
7.10 MIRRORS
7.10.1 Mirrors shall be electro coated, 6.0 mm thick glass of approved make, plane
or bevelled edge. The size shall be as specified in the Schedule of Quantities
or as shown on the drawings. The image shall be clear and without waviness
at all angles of vision.
7.10.2 Mirrors shall be provided with backing of 12mm thick marine plywood, fixed
with CP brass semi-round headed screws and cup washers or CP brass
clamps as specified or instructed by Engineer-in-Charge.
7.11.1 Shower set shall comprise of two CP brass concealed stop cocks, four/ five
way auto-diverter, adjustable type overhead shower, all with CP wall flanges
of approved quality all as specified in the Schedule of Quantities. Bath spout,
shower head / rose, hand showers and pop up wastes shall also be provided
wherever specified.
7.11.2 Wall flange shall be kept clear off the finished wall. Wall flanges embedded in
the finishing shall not be accepted.
7.12.1 Toilet paper holder shall be white glazed vitreous china of size, shape and
type specified in the Schedule of Quantities or of stainless steel/powder
coated brass.
7.12.2 Porcelain toilet paper holder shall be fixed in walls and set in cement mortar
1:2 (1 cement: 2coarse sand) and fixed in relation to the tiling work.
7.12.3 The latter shall be fixed by means of crews/capping having finish similar to
the toilet paper holder in wall/ timber partitions with rawl plugs or nylon
sleeves. When fixed on timber partition, it shall be fixed on a solid wooden
base ember provided by the Engineer-in-Charge through another agency.
7.13.1 Towel rail shall be chromium plated brass or of stainless steel or powder
coated brass of size, shape and type specified in the Schedule of Quantities.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 16 OF 54
7.13.2 Towel rail shall be fixed with screws/capping having finish similar to the towel
rail in wall with rawl plugs or nylon sleeves and shall include cutting and
making good as required or directed by the Engineer-in-Charge.
7.14.1 Liquid Soap dispenser shall be wall/ counter mounted suitable for dispensing
liquid soaps, lotions, detergents as specified in schedule of quantities.
7.14.2 Liquid soap dispenser shall be with C.P. brass bracket, caps etc. fixed to wall
with C.P. brass screws, and screwed onto wooden rawl plug. The container
shall be of C.P. brass.
7.15.2 Drinking water fountain shall be wall mounting type made of stainless steel or
any other material as given in the Schedule of Quantities.
7.15.3 The drinking water fountain shall be with anti-squirt bubble less, self closing
valve type with automatic volume regulator.
7.15.4 The drinking water fountain shall be provided with an anti-splash back and
integral strainer with 32mm or 40mm cast brass trap.
7.16.1 The hand drier shall be no touch operating type with solid state time delay to
allow user to keep hand in any position.
7.16.2 The hand drier shall be fully hygienic, rated for continuous repeat use (CRU).
7.16.3 The rating of hand drier shall be such that time required to dry a pair of hands
up to wrists is approximately 30 seconds.
7.16.4 The hand drier shall be of wall mounting type suitable for 230 V, single phase,
50 Hz, ac power supply.
7.17.2 Rate for providing and fixing of sanitary fixtures, accessories, shall include all
items, and operations stated in the respective specifications and Schedule of
Quantities and nothing extra is payable.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 17 OF 54
7.17.3 Rates for all items under specification Clauses above shall be inclusive of
cutting holes and chases and making good the same, CP brass screws, nuts,
bolts and any other fixing arrangements required and recommended by
manufacturers, testing and commissioning etc. complete.
Soil, waste, vent and rain water disposal scope shall includes Supply,
Installation, testing, commissioning and successful handing over to client as
per the drawings, specifications and schedule of quantities.
All soil, waste and storm water disposal for the portion above ground level to
the public sewers shall be by gravity, whereas from the basements it shall be
by pumping. Without restricting to the generality of the foregoing, the soil,
waste, vent and rain water pipes system shall inter-alia include the following:
a) Vertical and horizontal soil, waste, vent and rainwater pipes and
fittings, joints, supports, paints and connections to fixtures.
c) Floor and urinal traps, clean out plugs, inlet fittings and rainwater
(roof) outlets.
8.2.1 Pipes and fittings shall be fixed truly vertical, horizontal or in slopes as
required in a neat workmanlike manner.
8.2.2 Pipes shall be fixed in a manner so as to provide easy accessibility for repair
and maintenance and shall not cause obstruction in shafts, passages etc.
8.2.3 Pipes shall be securely fixed to walls, and ceilings by suitable clamps at
intervals specified. Only approved type of anchor fasteners shall be used for
fixing pipes on RCC ceilings and RCC/ masonry walls.
8.2.4 Access doors for fittings and clean outs shall be so located that they are
easily accessible for repair and maintenance.
8.2.5 Long bends shall be used on all main pipelines as far as possible. Use of
elbows shall be restricted for short connections.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 18 OF 54
8.3.1 Soil, waste, vent and anti-siphon pipes, fittings and accessories shall be cast
iron pipes. All pipes shall be straight and smooth and their inside free from
irregular bore, blow holes, crack sand other manufacturing defects. Pipes
shall be centrifugally cast (spun) iron soil pipes conforming to IS: 3989 or
sand cast to IS: 1729.
8.3.2 Drip seal PJS-43 shall be used for jointing CI pipes & fittings as per
manufacturer’s specifications.
8.3.3 Fittings
c) Access door shall be made up with 3mm thick insertion rubber washer
and white lead. The bolts shall be lubricated with grease or white lead
for easy removal later. The fixing shall be air and water tight.
8.3.4 Fixing
a) All vertical pipes shall be fixed by GI clamps truly vertical. Branch pipes
shall be connected to the stack at the same angle as that of the fittings.
No collars shall be used on vertical stacks. Each stack shall be terminated
at top with a cowl (terminal guard).
c) Contractor shall provide all sleeves, openings, hangers, inserts during the
construction. He shall provide all necessary information to the building
Contractor for making such provisions in the structure as necessary. All
damages shall be made good by the Contractor at his own cost to restore
the surfaces.
d) GI Pipe sleeve one size higher than pipe diameter shall be provided in
wall / floor, wherever pipe crossing wall / floor. Annular space between
pipe and sleeve shall be filled with glass wool and approved sealant as
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 19 OF 54
8.3.5 Clamps
8.3.6 Traps
Cast iron "P" siphon traps shall be cast iron trap of self cleaning
design. The trap and waste pipes shall be set in cement concrete
blocks of size 300mm x 300mm and of required depth, firmly
supported on the structural floor. The blocks shall be in 1:2:4 mix (1
cement:2 coarse sand : 4 stone aggregate 20mm nominal size) and
extended to 40mm below finished floor level. Contractor shall provide
all necessary shuttering and centering for the blocks at no extra cost.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 20 OF 54
b) Urinal traps
Urinal traps shall be cast iron P or S traps with or without vent and set
in cement concrete block specified under clause 8.3.6 a)
Floor trap shall be C.I. floor trap as per IS: 3989. Bath room traps and
connections shall ensure free and silent flow of discharging water.
Where specified, Contractor shall provide a special type cast iron/GI
inlet hopper without or with one or two or three inlet sockets to receive
the waste pipe. Joint between waste and hopper inlet socket shall be
lead caulked. Hopper shall be connected to a CI P or S trap with at
least 50mm seal (hopper and traps shall be paid for separately). Floor
trap inlet hoppers and the traps shall be set in cement concrete blocks
as specified under clause 8.3.6 above without extra charge.
Soil, waste, vent, anti-siphonand & rain water pipes shall be jointed with
dripseal PJS-43. Sufficient skein of jute rope shall be caulked to leave a
minimum space for the drip seal to be applied in.
The following minimum procedures shall be complied with while making the
pipe joints:
8.4.1 All drainage lines passing under building, floors, in exposed position above
ground e.g. basement ceiling shall be Cast Iron LA pipes. Position of such
pipes shall generally be shown on the drawings.
8.4.2 Cast Iron LA pipes & fittings shall conforming to IS: 1536 & IS: 1538
respectively. Quality certificates shall be furnished.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 21 OF 54
8.4.3 Wherever possible junction from branch pipes shall be made by a “Y” tee.
8.4.4 Clean out plugs shall be provided on head of each drain and at location
indicated on plans or directed by the Engineer-in-Charge. Clean out plugs
shall be of size matching the full bore of the pipe. Plugs shall be made out
with GI coupling caulked into the socket of the pipe or fittings. The end shall
be provided with a brass screwed plug with suitable key for opening.
8.5.1 Laying
a) All cast iron pipes and fittings shall be jointed with drip seal PJS-43
which shall be free from impurities. In wet trenches joints shall be
made from lead wool. Nothing extra shall be paid for lead wool joints.
Depth of dripseal and weight for joints shall be as per the relevant IS
code or recommended by manufacturer, whichever is on higher side.
c) For lead wool joints the socket shall be caulked with tarred gaskin, as
explained above. The lead wool shall be inserted into the sockets and
tightly caulked home, skein by skein, with suitable tools and hammers
of not less than 2 kg weight until joint is filled.
d) Instead of drip seal joints, Rubber ring joints can also be provided. In
case of CI pipes of spigot-socket with rubber ring joints as specified in
BOQ, the rubber rings shall conform to IS-5382.
a) Cast iron soil and waste pipes under floor finish in sunken slabs and in
wall chases (when cut specially for the pipe) shall be encased in
cement concrete 1:2:4 mix (1 cement :2 coarse sand :4stone
aggregate 12mm size) 75mm in bed and all around. When pipes are
running well above the structural slab, the encased pipes shall be
supported with suitable cement concrete pillars, the details of which
shall be furnished by the Engineer-in-Charge of required height at
intervals of 1.8m. Rate for concrete all around pipes shall be inclusive
of pillars, supports, shuttering and centering.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 22 OF 54
8.5.3 Painting
a) Soil, waste, vent, anti-siphonage and rain water pipes in any exposed
location in shafts, pipe spaces etc. shall be painted with one coats of
zinc / red oxide primer and two or more coats of synthetic enamel
paint of colour as specified to give an even shade.
d) CI soil and waste pipes below ground and those covered in cement
concrete shall not be painted.
Pipes shall be fixed and tested as the building work proceeds. Contractor
shall provide all necessary holes, cut outs and chases in structural members
as the building work proceeds. Wherever holes are cut or left originally, they
shall be made good with cement concrete 1:1:2 (1 cement: 1coarse sand :2
stone aggregate 20mm nominal size) or cement mortar 1:2 (1 cement :2
coarse sand) as directed by the Engineer-in-Charge and the surface restored
as in original condition to the entire satisfaction of the Engineer-in-Charge at
no extra cost.
8.5.5 Testing
a) Testing shall be done in accordance with IS: 1172 and IS: 5329
except as may be modified herein under.
b) Before use at site all CI pipes shall be tested by filling up with water
for at least 30 minutes. After filling, pipes shall be struck with a
hammer and inspected for blow holes and cracks. All defective pipes
shall be rejected and removed from the site within 48 hours. Pipes
with minor sweating may be accepted at the discretion of the
Engineer-in-Charge.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 23 OF 54
d) The Contractor shall test all vent pipes by a smoke testing machine.
Smoke shall be pumped into the stack after plugging all inlets and
connections and filling water in all trap seals. The test shall be
conducted under a pressure of 25mm of water and shall be
maintained for 15 minutes. The stack shall then be observed for
leakages and all defective pipes and fittings removed or repaired as
directed by the Engineer-in-Charge.
e) A test register shall be maintained and all entries signed and dated by
Contractor and Engineer-in-Charge. A proforma of the proposed test
register shall be submitted to the Engineer-in-Charge for approval.
UPVC SWR pipework shall be provided for above ground soil, waste, vent &
rain water pipework as shown in drawings. UPVC SWR pipes & fittings shall
confirm to IS: 13592 & IS : 14735 respectively. Pipes shall be of Type - B,
pressure rating 6kgs/cm2. The pipes shall be supplied in nominal lengths of
2,3,4 or 6 meters, tolerance on specified lengths shall be +10mm and – 0mm.
Any physical test requirements shall be as per IS13592-1992.
8.6.1 Handling
Because of their lightweight, there may be a tendency for the UPVC pipes to
be thrown often during installation. Reasonable care should be taken in
handling and storage to prevent damage to the pipes. The pipes shall be
stored as per manufacturer’s recommendation. The contractor shall be fully
responsible in this case. In no case, pipes should be dragged on the
ground. Pipes should be given adequate supports at all times.
UPVC pipes shall be laid under the flooring or hanging below slab or fixed on
walls either buried or exposed as the case may be, as shown in the drawings.
The minimum thickness of fittings shall be of 3.2 mm. the fittings shall be of
injection mould type with solvent cement joint (for exposed piping) or rubber
ring joint (for concealed piping). The pipes and fittings shall be capable of
withstanding sun’s rays. UPVC pipes laid below slab or suspended from
ceiling shall be supported by GI angle brackets / supports as detailed in the
drawings.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 24 OF 54
8.6.3 Jointing
UPVC pipes & fittings shall be joined as per the manufacturer’s instructions /
recommendations. UPVC pipes and fittings shall be joined with Solvent
Cement and jointing shall be carried out as follows
b) All burrs from the internal and external surfaces should be removed.
e) Insert the pipe end into the socket of the fitting and push it in upto the
mark.
f) The pipe work should be assembled in a manner such that it does not
entail making of joints in restricted area.
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 25 OF 54
b) The Contractor shall test all vent pipes by a smoke testing machine.
Smoke shall be pumped into the stack after plugging all inlets and
connections and filling water in all trap seals. The test shall be
conducted under a pressure of 25 mm of water and shall be
maintained for 15 minutes. The stack shall then be observed for
leakages and all defective pipes and fittings removed or repaired as
directed by the Engineer-in-Charge.
c) A test register shall be maintained and all entries signed and dated by
Contractor and Engineer-in-Charge. A pro-forma of the proposed test
register shall be submitted to the Engineer-in-Charge for approval.
8.7.1 Waste pipe from appliances e.g. washbasins, baths, sinks and urinals etc.
shall be of UPVC confirming IS 4985 as given in the Schedule of Quantities.
8.7.2 The internal diameter sizes of outlet branch waste pipes for different fittings
shall be as follows :
Urinals - 50 dia
Sink - 50 dia
8.7.3 All pipes shall be fixed in gradient towards the outfalls of drains. Pipes inside
a toilet room shall be in chase unless otherwise shown on drawings. Where
required pipes may be run at ceiling level in suitable gradient and supported
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 26 OF 54
8.7.4 Pipes shall be UPVC tubes conforming to IS: 4985 and quality certificates
shall be furnished. Pipes shall be provided with all required fittings conforming
to IS: 4985 e.g. tees, couplings, bends, elbows, unions, reducers, nipples,
plugs etc. All UPVC waste pipes shall be terminated at the point of connection
with the appliance with an outlet of suitable diameter. Pipes shall be painted
as specified under Clause c).
b) Floor Cleanout
c) Ceiling Cleanout
All rainwater pipes shall be of UPVC / HDPE as shown in drawing & specified
in specification. UPVC piping shall conforming to IS: 4985 and 6 kg/sq.cm
minimum pressure rating or as specified in the schedule of quantities.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 27 OF 54
HDPE shall be used for above ground rain water pipework as shown in
drawing & specified in specification. HDPE pipes shall confirm to IS 14333 PE
80 grade, pressure rating shall be as indicated in schedule of quantities.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 28 OF 54
j) All HDPE fabricated fittings shall be manufactured from the pipe itself
made out of same raw material & dimensions as specified above. Fitting
shall be strictly fabricated in factory at pipe manufacturing facility.
Necessary certificate to be provided by the manufacturer. No fabrication
or moulding will be allowed at site, unless specifically permitted by the
Engineer.
a) Rain water out shall be preferably scupper type drain with cast iron
body & cast aluminium grating with stainless steel screws. Suitable
adopter / connector shall be used to match the pipe. Wherever shafts
are not available near rain water outlet, dome type rain water outlet
shall be installed.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 29 OF 54
8.12.1 General
a) Rates for all items shall be inclusive of all work and items called for in
the specifications given above and the Schedule of Quantities as
applicable for the work under floors, in shafts or at ceiling level at all
heights and depths.
b) All rates are inclusive of cutting holes and chases in RCC and
masonry work and making good the same.
c) All rates are inclusive of shop testing, pre-testing at site and final
testing of the installations, materials and commissioning.
8.12.2 Pipes
b) All CI / UPVC / HDPE soil, waste, vent, anti-siphonage and rain water
pipes shall be measured net, correct to a centimetre, including all
fittings along their length after fixing. The length shall be taken along
centre line of the pipes and fittings. No allowance shall be made for
the portions of pipe lengths entering the sockets of the adjacent pipes
or fittings. The above shall apply to all cases i.e. whether pipes are
fixed on wall face or pillars or embedded in masonry or pipes running
at ceiling level. The quoted rate shall include lead jointing.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 30 OF 54
8.12.4 GI Supports
8.12.5 Traps
8.12.6 Painting
b) Leaf and gravel grates along with the perforated ring shall be
measured in kgs.
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 31 OF 54
The term water supply is used as indicative of all water supply work required
and necessary for the building including such external work as may be
necessary to make the system functional.
9.3.1 All pipes inside the buildings and where specified, outside the building shall
be M.S. galvanized steel tubes conforming to IS: 1239 of Class specified.
When Class is not specified they shall be Heavy Class. All embedded /
concealed pipes shall be of heavy duty.
9.3.2 Fittings shall be of malleable cast iron galvanized, of approved make. Each
fitting shall have manufacturer's trade mark stamped on it. Fittings for GI
pipes shall include couplings, bends, tees, reducers, nipples, unions, bushes
etc. Fittings etc. shall conform to IS: 1879.
9.3.3 Pipes and fittings shall be jointed with screwed joints using Teflon tape
suitable for water pipes. Care shall be taken to remove burr from the end of
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 32 OF 54
the pipe after cutting by a round file. All pipes shall be fixed in accordance
with layout and alignment shown on the drawings. Care shall be taken to
avoid air pockets. Necessary vents and drains shall be provided at all high
and low points respectively. GI pipes inside toilets shall be fixed in wall
chases well above the floor. No pipes shall be run inside a sunken floor as far
as possible. Pipes may be run under the ceiling or floors and other areas as
shown on drawings. All pipe joints after testing of the line shall be seal welded
and the weld plus the adjoining portion shall be given two coats of zinc rich
primer.
All bib cocks and stop cocks shall be of C.P. brass conforming to IS: 781 of
tested quality and approved make and design, of diameter as specified in
schedule of quantities.
9.3.5 Clamps
9.3.6 Unions
9.3.7 Flanges
9.3.8 Trenches
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 33 OF 54
All GI pipes below ground shall be laid in trenches with a minimum cover of
600mm. The width and depth of the trenches shall be as follows except at
places where welding/ jointing etc. needs larger width of trench. Additional
width/ depth shall be provided as necessary for welding/ jointing etc. at no
additional cost:
GI pipes in trenches shall be protected with fine sand 150mm all around
before filling in the trenches.
9.3.10 Painting
a) All pipes above ground shall be painted with one coat of red lead and
two coats of synthetic enamel paint of approved shade and quality to
give an even shade, or as specified by the Engineer-in-Charge.
All hot water pipes fixed in wall chase shall be properly insulated by
elastomeric tape as per manufacturer’s recommendation.
Where specified, pipes below floor or below ground shall be protected against
corrosion by the application of two or more coats of solvent based rubberised
asphaltic primer to give a uniform coat covered with 'Pipecoat Hiper', a
puncture resistant non woven polyester mat. The application of pipecoat
primer and "Hiper" membrane shall be as specified by the manufacturer.
Ductile iron pipes & fittings spigot & socket type shall be used for external
buried cold water supply piping work. Ductile iron pressure pipes and fittings
shall be Class K7 unless otherwise shown on the drawings and shall comply
with IS: 8329 and IS: 9523. All fittings shall be socketed unless specified
otherwise.
9.4.1 The following standards, specifications and codes are part of this
specification. In all cases, the latest revision of the codes including all
applicable official amendments and revisions shall be referred to. In case
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 34 OF 54
9.4.2 Materials
The materials used in the manufacture of pipes and fittings shall comply with
IS: 8329 and IS: 9523. All fittings shall be socketed unless otherwise
specified.
9.4.3 Manufacturing
General
a) DI pipes (Class K7) and DI fittings (Class K7) with internal Cement
Mortar lining shall be in accordance with IS 8329 and IS 9523. Pipes
shall be ISI marked.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 35 OF 54
c) The pipes will be centrifugally cast (spun) Ductile Iron pipes for Water
and Sewage as per relevant ISO (amended up to date) having
specifications / properties equal to or superior to the IS 8329: 2000
(amended up to date). The pipes used will be with push on joints
(Rubber Gasket Joints).
d) The flange connection shall be used only in cases of fittings or
specials or under special circumferences as directed by Engineer. The
pipes shall be externally coated with bitumen as per appendix C of the
IS 8329: 2000 and have factory provided cement mortar lining in the
inside as per the provisions of Appendix B of the IS 8329: 2000.
e) The pipes shall be supplied in standard length of 5.50 and 6.00 meters
length with suitably rounded or chamfered ends. Each pipe of the push
on joint variety shall also be supplied with a rubber ring (EPDM/SBR)
gasket. Any change in the stipulated lengths will be approved by the
Engineer. The gaskets will confirm to the IS 5382:1985 and IS:12820.
f) The manufacturer of the pipes should also supply the specials and
gaskets. The manufacturer of the pipes should preferably manufacture
them. In case they are not, it will be the responsibility of the
manufacturer of the pipes to have them manufactured from a suitable
manufacturer under its own supervision and have it tested at his/sub
contractor’s premises as per the contract. The pipe manufacturer will
however be responsible for the compatibility and quality of the
products.
g) The flanged joints will confirm to the Clause 6.2 of IS 8329. The pipe
supply will also include one rubber gaskets for each flange.
h) All tests specified either in this specification or in the relevant Indian
Standards specified above shall be performed by the
supplier/contractor at his own cost and in presence of Engineer if
desired. For this, sufficient notice before testing of the pipes and
fittings shall be given to Engineer.
i) If the test is found unsatisfactory, Engineer may reject any or all pipes
and fittings of that lot. The decision of Engineer in this matter shall be
final and binding on the contractor and not subject to any arbitration or
appeal.
j) The pipes and fittings shall be stripped, with all precautions necessary
to avoid warping or shrinking defects. The pipes and fittings shall be
free from defects. Any defect in pipes and fittings in the opinion of
Engineer shall be rejected and shall be replaced by new one.
k) In the case of spigot and socket pipes and fittings the socket shall be
without the centering ring.
l) In the case of flanged pipes the flanges shall be at the right angles to
the axis of the pipe and machined on face. The bolt holes shall be
drilled and located symmetrically off the centre line. The bolt hole
circle shall be concentric with the bore and bolt holes equally spaced.
The flanges shall be integrally cast with the pipes and fittings and the
two flanges of the pipe shall be correctly aligned.
m) All the DI fittings shall be supplied with one rubber ring for each
socket.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 36 OF 54
The internal diameter, thickness and length of barrel, dimensions of pipes and
fittings shall be as per the relevant tables of IS 8329/IS 9523 for different
class of pipes and fittings. Standard length of 6m of pipe is recommended and
other properties for pipes and fittings shall be as per IS 8329 / IS 9523. Each
pipe supplied shall be of uniform thickness throughout its length. The
tolerances for pipes and fittings regarding dimensions, mass, ovality and
deviations from straight line in case of pipes shall be as per IS 8329/IS 9523.
9.4.5 Testing
Tests on pipes and fittings shall be carried out in accordance with IS 8329
and IS 9523. The Engineer shall be permitted free access to the place of
manufacture for the purpose of examining and witnessing the testing of pipes
and fittings.
All pipes or joints which are proved to be in any way defective shall be
replaced or remade and re-tested as often as may be necessary until a
satisfactory test shall have been obtained. Any work which fails or is proved
by test to the unsatisfactory in any way shall be redone by the Contractor.
General
This section covers the requirements for lubricant for the assembly of Ductile
Iron pipes and specials suitable for Tyton push-on rubber ring joints.
Specification
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 37 OF 54
They shall be conducted in line with the provisions of the IS: 9523.
9.4.9 Joints
Jointing of DI pipes and fittings shall be done as per IS: 12288 and
manufacturer’s recommendations. After jointing, extraneous material, if any,
shall be removed from the inside of the pipe. Rubber sealing rings/gaskets
used for jointing shall conform to IS: 638, IS: 12820 and IS: 5382.
These shall have sockets which are integral with the pipe and incorporate an
elastomeric rubber ring gasket conforming to IS: 12820 and rubber rings shall
be as per IS: 5382.
In jointing DI pipes and fittings, the Contractor shall take into account the
manufacturer’s recommendations as to the methods and equipment to be
used in assembling the joints. In particular the Contractor shall ensure that
the spigot end of the pipe to be jointed is smooth and has been properly
chamfered, so that the rubber ring as per IS 12820 and IS 5382 is correctly
positioned in line, before the joint is made. The rubber rings and any
recommended lubricant shall be obtained only through the pipe supplier or as
otherwise directed by the Engineer.
These shall comply with dimensions and drilling details in IS 8329 for PN 10
flanges. All flanged joints between steel and ductile iron pipe work shall be
electrically isolated joints. These shall have isolation gaskets between the
flanges, isolation sleeves around all bolts and isolation washers under all bolt
heads and nuts. All materials shall be supplied by a specialist manufacturer
and be to the approval of the Engineer.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 38 OF 54
All pipes and fittings shall be internally lined with cement mortar in
accordance with ISO: 4179 / IS: 11906. Cement mortar lining shall be applied
at the factory in conformance with the above mentioned standards. No
admixtures in the mortar shall be used without the approval of the Engineer.
Pipe linings shall be inspected on site and any damage or defective areas
shall be made good to the satisfaction of the Engineer. The Contractor may
use specialist mortars, mortar additives or curing agents only with the
approval of the Engineer.
Lining shall be uniform in thickness all along the pipe. The minimum thickness
of factory applied cement mortar lining shall be 3 mm for DN 300 mm pipe; 5
mm for DN 350 to 600 mm pipe; and 6mm for DN 800 mm pipes.
b) The minimum thickness of the lining at one point shall not be less than
4 mm.
9.4.11 Specials
9.4.12 Coatings
a) General
Ductile iron pipes and fittings shall be zinc coated with bitumen over coating,
all in accordance with the following Specifications. Buried pipes and fittings
shall also have a site or factory applied polythene sleeving. Coating shall not
be applied to pipe and fittings unless its surface is clean, dry and free from
rust. Pipe coatings shall be inspected on site and any damage or defective
areas made good to the satisfaction of the Engineer.
b) Zinc Coating
Zinc coating shall comply with ISO 8179 and shall be applied as a
spray coating. The mass of sprayed metal shall not be less than 130
g/m2 as described in Clause 5.2 of ISO 8179.
c) Bitumen Coating
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 39 OF 54
CPVC pipes & fittings solvent welded type shall be used for internal cold &
hot water supply piping work. CPVC pipes from 15mm to 50 mm shall be
Class - 1, SDR-11 confirm to the requirements of IS 15778. CPVC pipes from
65mm to 300 mm shall be schedule 40 / schedule 80 class confirm to the
requirements of ASTM-F441 & as described in the BOQ/SOQ.
CPVC fittings i.e sockets, tees, bends, reducers, brass threaded male/female
connectors, brass threaded male/female adopters unions, bushings etc shall
comply to the requirements of ASTM F438 & ASTM F439 for schedule 40 &
schedule 80 class respectively. Solvent cement for CPVC pipe shall comply
as per ASTM F493.
Upon successful testing of entire piping system, it shall be painted with one
coat of approved primer & two coats of approved synthetic enamel paint, as
per direction of engineer-in-charge / client.
b) Remove burr (shaving) & clean the cut portion with dry cloth. Ensure
that jointing portion is free from any dirt, grease or any other foreign
material.
c) Install dry fit out, by inserting pipe inside the sockets upto 1/3rd to
2/3rd penetration depth. Ensure that pipe inserts to the bottom of the
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 40 OF 54
d) Apply a thin coat of solvent cement to the inner side of socket upto it's
bottom & full coat to the outer side of pipe.
e) Insert pipe in to the socket, till the solvent is in fluid state. Twist the
pipe turn to cover any dry spots.
f) Hold the pipe for atleat 30 seconds, to ensure proper jointing. Wipe
out excess solvent cement with clean dry cloth.
Nominal Size Pipe Size Support Spacing (Meter) Respectively with Pipe Size
0 0 0 0
23 C 38 C 60 C 80 C
15 mm SDR 11 / SDR 13.5 1.22 / 1.22 1.22 / 1.22 1.07 / 1.07 0.92 / 0.92
65 mm SCH 40 / SCH 80 2.13 / 2.86 2.13 / 2.86 1.82 / 1.98 1.06 / 1.22
SCH 40 / SCH 80
80 mm 2.13 / 2.59 2.13 / 2.59 1.82 / 2.13 1.06 / 1.22
SCH 40 / SCH 80
100 mm 2.86 / 2.74 2.86 / 2.74 1.98 / 2.86 1.22 / 1.37
SCH 40 / SCH 80
150 mm 2.59 / 3.04 2.59 / 2.89 2.13 / 2.59 1.37 / 1.52
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 41 OF 54
9.6.1.1 Valves 65mm dia and below shall be heavy gunmetal full way valves or
globe valves conforming to Class I of IS: 778. Valves shall be tested at
manufacturer's works and the same stamped on it.
9.6.1.2 All valves shall be approved by the Engineer-in-Charge before they are
allowed to be used in the Work.
9.6.2.1 Unless otherwise specified all valves 80mm dia and above shall be CI
double flanged sluice valves with non rising spindle. Sluice valves shall be
provided with wheel when they are in exposed positions and with a cap top
when they are located underground. Contractor shall provide suitable
operating keys for sluice valves with cap tops.
9.6.2.2 Sluice valves shall be of approved makes conforming to IS: 780 of Class as
specified.
9.6.3.1 Where specified Valves 80mm dia and above shall be cast iron butterfly
valve to be used for isolation and/ or flow regulation as directed by the
Engineer-in-Charge. The valves shall be tight shutoff/ regulatory type with
resilient seat suitable for flow in either direction and seal in both directions.
9.6.4.1 Where specified non return valve (swing check type) shall be provided
through which flow can occur in one direction only. It shall be single door
swing check type of best quality conforming to IS: 5312.
9.6.5.1 Valves of size 50mm dia and below shall be full bore quarter turn lever
operated female threaded forged brass hard chrome plated ball valves
conforming to IS: 554. Valve shall have PTFE body seat rings & gland
packing, forged brass ball, stem & bonnet, carbon steel nut washer & lever
and finished in chrome. Valves shall have minimum working pressure of 16
bar. Valves shall be tested at manufacturer's works and the same stamped
on it.
9.6.6.1 Ball type NRV shall be used in water treatment plants & sewage sump pump
piping. NRV shall be constructed in cast iron body with epoxy coating,
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 42 OF 54
phenolic resin and NBR(Nitrile) seal. NRV shall have flanged ends & can be
installed in horizontal as well as vertical position. NRV shall have minimum
working pressure of 10 bar or as per system requirements. Valves shall be
tested at manufacturer's works and the same stamped on it.
9.6.7.1 Pressurized water supply lines shall be provided with air release valve at
heighest point to release accumulated air for piping system. Air release
valve shall be automatic float operated, the diameter shall be as specified in
the BOQ. Air release valve shall be provided with ball valve for ease in
operation & maintenance. Valve body shall be in cast iron stainless steel,
brss & EPDM internal components. Valves shall have minimum working
pressure of 10 Kgs.
9.7 TESTING
9.7.1 All pipes, fittings and valves shall be tested in accordance with IS: 2065
except as may be modified herein under. All pipes, fittings and valves, after
fixing at site, shall be tested to a hydrostatic pressure of 10 kg/cm2 or 1.5
times the shut off head of the pump whichever is greater.
9.7.2 The test pressure shall be maintained for a period of at least thirty minutes
without any drop in pressure.
9.7.3 A test register shall be maintained and all entries shall be signed and dated
by Contractor(s) and the Engineer-in-Charge.
9.7.4 After commissioning of the water supply system, the Contractor shall test
each valve by closing and opening it a number of times to observe if it is
working efficiently and effectively. Valves which do not operate efficiently and
effectively shall be replaced by new ones at no extra cost and the same shall
be tested as above.
9.7.5 All pipes in wall chase or meant to be encased or buried shall be hydro tested
before the chase is plastered or the pipe encased or buried.
9.8 INSULATION
9.8.1 All open hot water flow and return pipes shall be insulated with preformed
fibrous pipe sections conforming to IS: 9842.
9.8.2 Insulation to pipes shall be with pre-moulded pipe sections, thickness for
sections shall be:
9.8.3 Application:
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 43 OF 54
All hot water pipes in chase shall be insulated with 3 mm elastomeric tape as
per manufacturer’s recommendations.
d) When the installation is filled all bib cocks (taps) shall be opened
progressively and each allowed to run until the water smells of
chlorine.
f) The installation shall then be left for three hours and shall then be
tested for residual chlorine; if none is found, the installation shall be
drained and the process repeated.
g) The installation shall be finally drained and flushed with potable water
before use.
a) GI pipes above ground shall be measured per linear metre (to the
nearest cm) along the centre line of the pipe and shall be inclusive of
all fittings e.g. couplings, tees, bends, elbows, unions, flanges, etc.
Deduction for valves shall be made. Rates quoted shall be inclusive of
all fittings, clamps, cutting holes chases and making good the same
and all other items mentioned in the specifications and Schedule of
Quantities.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 44 OF 54
b) GI pipes below ground shall be measured per linear metre (to the
nearest cm) along the centre line of the pipe and shall be inclusive of
all fittings e.g. couplings, tees, bends, elbows, unions and flanges, etc.
Deduction for valves shall be made. Rates quoted shall be inclusive of
all fittings, cutting holes and chases and making good the same and
all other items mentioned in the specifications and Schedule of
Quantities. Excavation, filling, back filling with selected excavated
earth, compaction and disposal of surplus earth, fine sand filling
around GI pipes, in external work shall be measured separately, as
per respective items.
9.10.3 Gunmetal and cast iron valves, Bib cocks and stop cocks shall be measured
by numbers.
10.0 DRAINAGE
10.1.1 The scope shall include supply, installation, testing, commissioning and
satisfactory handing over of the complete water supply system to client as per
drawings, specifications and schedule of quantities.
10.1.3 Without restricting to the generality of the foregoing, the drainage system
shall inter-alia include:
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 45 OF 54
10.2.2 Drainage lines and open drains shall be laid to the required gradients and
profiles.
10.2.3 All drainage work shall be done in accordance with the Local municipal bye-
laws.
10.2.4 Contractor shall obtain necessary approval and permission for the drainage
system from the municipal or any other competent Authority.
10.2.5 Location of all manholes, etc. shall be got confirmed by the Engineer-in-
Charge before the actual execution of work at site. As far as possible, no
drains or sewers shall be laid in the middle of road unless otherwise
specifically shown on the drawings or directed by the Engineer-in-Charge in
writing.
10.3 EXCAVATION
The sewer pipes shall be laid to alignment and gradient shown on the
drawings but subject to such modifications as shall be ordered by the
Engineer-in- Charge from time to time to meet the requirements of the Works.
No deviations from the lines, depths of cutting or gradients of sewers shown
on the plans and sections shall be permitted except by the express direction
in writing of the Engineer-in-Charge.
Excavation for sewer works shall be open cutting unless the permission of the
Engineer-in-Charge for the ground to be tunnelled is obtained in writing.
Where sewers have to be constructed along narrow passages, the Engineer-
in-Charge may order the excavation to be made partly in tunnel and in such
cases the excavated soil shall be brought back later on for refilling.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 46 OF 54
trees in the line of the proposed works but shall tunnel under them,
unless the Engineer-in-Charge shall order to the contrary.
b) The Contractor shall grub up and clear the surface over the trenches
and other excavations of all trees, stumps roots and all other
encumbrances affecting execution of the work and shall remove them
from the site.
The Contractor shall not occupy or obstruct by his operation more than one
half of the width of any road or street and sufficient space shall then be left
for public and private transit. He shall remove the materials excavated and
bring them back again when the trench is required to be refilled. The
Contractor shall obtain the consent of the concerned authority in writing
before closing any road to vehicular traffic. The foot walks must be clear at
all times.
All night soil, filth or any other offensive matter met with during the execution
of the works, shall not be deposited on to the surface of any street or where it
is likely to be a nuisance or passed into any sewer or drain but shall be
immediately, after it is taken out of any trench, sewer or cess pool, put into
the carts and removed to a suitable place to be provided by the Contractor.
The trenches shall be excavated to such a depth that the sewer shall rest on
concrete as specified in the clauses relating thereto, so that the inverts may
be at the levels given in the sections. In bad ground, the Engineer-in-Charge
may order the Contractor to excavate to a greater depth than that shown on
the drawings and to fill up the excavation to the level of the sewers with
concrete, broken stone, gravel or other materials as directed by the
Engineer-in-Charge. Such extra excavation, concrete, broken stone, gravel
or other materials, shall be measured and paid for separately if the extra
work was ordered by the Engineer-in-Charge in writing, but if the Contractor
should excavate the trench to a greater depth than is required without a
specific order to that effect in writing of the Engineer-in-Charge, the extra
depth shall have to be filled up with cement concrete 1:4:8 (1 cement:
4coarse sand 8: stone aggregate 20mm nominal size) at the Contractor's
own costs and charges, as directed by and to the satisfaction of the
Engineer-in-Charge.
10.3.7 Refilling
After the sewer or other work has been laid and proved to be water tight, the
trench or other excavations shall be back filled with selected excavated earth
and compacted. Utmost care shall be taken in doing this, so that no damage
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 47 OF 54
shall be caused to the sewer and other permanent work. The filling in the
haunches and up to 75mm above the crown of the sewer shall consist of the
finest selected materials, as directed by the Engineer-in-Charge, placed
carefully in 150mm layers, then flooded and consolidated. After this has been
laid, the trench and other excavation shall be refilled carefully in 150mm
layers with materials taken from the excavation, each layer being watered to
assist in the consolidation unless the Engineer-in-Charge shall otherwise
direct.
The Contractor shall, at his own costs and charges, make good promptly any
settlement that may occur in the surfaces of roads, berms, footpaths,
gardens, open spaces etc. whether public or private caused by his trenches
or by his other excavations and he shall be liable for any accidents caused
thereby. He shall also, at his own expense and charges, repair and make
good any damage done to buildings and other property. If in the opinion of
the Engineer-in-Charge he fails to make good such works with all practicable
despatch, the Engineer-in-Charge shall be at liberty to get the work done by
other means and the expenses thereof shall be paid by the Contractor or
deducted from any money that may be or become due to the Contractor or
recovered from the Contractor in any other manner according to the law of
the land.
The Contractor shall at his own costs and charges provide places for
disposal of all surplus materials not required to be used on the works. As
each trench is refilled the surplus soil shall be immediately removed, the
surface properly restored and the site cleared.
a) The Contractor shall at all times support efficiently and effectively the
sides of all the trenches and other excavations by suitable timbering,
piling and sheeting and they shall be close timbered in loose or sandy
strata and below the surface of the sub soil water level.
b) All timbering, sheeting and piling with their wallings and supports shall
be of adequate dimensions and strength and fully braced and strutted
so that no risk of collapse or subsidence of the walls of the trench
shall take place.
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 48 OF 54
The Contractor shall shore up all buildings, walls and other structures, the
stability of which is liable to be endangered by the execution of the work
and shall be fully responsible for all damages to persons or property
resulting from any accident.
The Contractor shall at all times during the progress of the work keep the
trenches and excavations free from water which shall be disposed of by
him in a manner as shall neither cause injury to the public health nor to the
public or private property nor to the work completed or in progress nor to
the surface of any roads or streets nor cause any interference with the use
of the same by the public at no extra cost.
10.4.1 Stoneware pipes shall be new and of first Class quality salt glazed and free
from rough texture inside and outside and straight. All pipes shall comply with
IS: 651 and have the manufacturers name marked on them.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 49 OF 54
with a wooden hammer or mallet and those that do not ring true and
clear shall be rejected. Sound pipes shall be carefully stacked to
prevent damage. All defective pipes shall be segregated, marked in a
conspicuous manner and their use in the works prevented by
expeditiously removing them from the work site.
b) The pipes shall be laid with sockets leading uphill and should rest on
solid and even foundations for the full length of the barrel. Socket
holes shall be formed in the foundation sufficiently deep to allow the
pipe jointer room to work right round the pipe and as short as
practicable to admit the socket and allow the joint to be made.
c) Where pipes are not bedded on concrete the trench bottom shall be
left slightly high and carefully bottomed up as pipe laying proceeds so
that the pipe barrels rest on firm ground. If excavation has been
carried too low it shall be made up with cement concrete 1:4:8 (1
cement: 4coarse sand: 8 stone aggregate 20mm nominal size) at the
Contractor's cost and charges.
a) Tarred gaskin shall first be wrapped round the spigot of each pipe and
the spigot shall then be placed into the socket of the pipe previously
laid, the pipe shall then be adjusted and fixed in its correct position
and the gaskin caulked tightly home so as to fill not more than one
quarter of the total length of the socket.
b) The remainder of the socket shall be filled with stiff mix of cement
mortar (1 cement: 1 clear sharp washed sand). When the socket is
filled, a fillet shall be formed round the joint with a trowel forming an
angle of 45 degrees with the barrel of that pipe. The mortar shall be
mixed as needed for immediate use and no mortar shall be beaten up
and used after it has begun to set.
c) After the joint has been made any extraneous materials shall be
removed from the inside of the joint with a suitable scraper of
"badger". The newly made joints shall be protected until set, from the
sun, drying winds, rain or dust. Sacking or other materials which can
be kept damp shall be used. The joints shall be exposed and space
left all around the pipes for inspection by the Engineer-in-Charge. The
inside of the sewer must be left absolutely clear in bore and free from
cement mortar or other obstructions throughout its entire length, and
shall efficiently drain and discharge.
d) In case Glazed Stoneware pipes are jointed with rubber rings as per
BOQ, the rubber ring shall confirm to IS-5382.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 50 OF 54
10.5.1 All underground storm water drainage pipes and sewer lines where specified
(other than those specified as cast iron) shall be centrifugally spun S&S RCC
pipes of specified Class conforming to IS: 458. Pipes shall be true and
straight with uniform bore, throughout. Cracked, warped pipes shall not be
used on the work. All pipes shall be tested by the manufacturer and the
Contractor shall produce a certificate to that effect from the manufacturer.
10.5.2 Laying
RCC S&S spun pipes shall be laid on cement concrete bed or cradles as
specified and shown on the detailed drawings. The cradles may be pre cast
and sufficiently cured to prevent cracks and breakage in handling. The invert
of the cradles shall be left 12mm below the invert level of the pipe properly
placed on the soil to prevent any disturbance. The pipe shall then be placed
on the bed concrete or cradles and set for the line and gradient by means of
sight rails and bonding rods etc. Cradles or concrete bed may be omitted, if
directed by the Engineer-in-Charge.
Jointing of RCC pipes with collar joint shall be with CM (1:1) after inserting
bitumen gasket in between groove of pipes as per the details given in cl.
10.4.3. In case of spigot-socket RCC pipes jointed with rubber rings as
specified in BOQ, the rubber rings shall conform to IS: 5382.
10.6.1 Materials
All materials used in cement concrete and masonry works e.g., water, coarse
aggregates, sand, cement, reinforcement bars, bricks etc. shall conform to
relevant Indian Standards and the Specifications of the Central Public Works
Department.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 51 OF 54
Classification
Upto 1.5m Upto 3m Beyond 3m
of Pipe
Depth Depth Depth
support
Stoneware
pipes in open All round In haunches In haunches
ground (no sub (1:5:10) (1:5:10) (1:5:10)
soil water)
RCC Pipes or
All round All round All round
CI pipes under
(1:3:6) (1:3:6) (1:3:6)
building
RCC / CI
/Stoneware All round All round All round
Pipes under (1:3:6) (1:3:6) (1:3:6)
road
10.7.1 All manholes, chambers and other such works as specified shall be
constructed in brick masonry in cement mortar 1:4 (1 cement: 4 coarse sand)
or as specified in the Schedule of Quantities.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 52 OF 54
10.7.2 All manholes and chambers, etc. shall be supported on base of cement
concrete of such thickness and mix as given in the Schedule of Quantities or
shown on the drawings.
Size / type of 900x450 900x600 900 dia 1200 dia 1500 dia
manhole Rect. Rect. Conical Conical Conical
Note - All dimensions are clear internal dimensions in mm. In case of SFRC
frame and cover is specified / mentioned in BOQ, it shall conform to
IS: 12592.
10.7.4 All manholes shall be provided with cement concrete benching in 1:2:4
nominal mix. (1 cement: 2 coarse sand: 4 stone aggregate 20mm nominal
size). The benching shall have slope of 1:12 towards the channel. The depth
of the channel shall be full diameter of the pipe. Benching shall be finished
with a floating coat of neat cement with water proofing compound.
10.7.5 All manholes shall be plastered with 12/15mm thick cement mortar 1:3 (1
cement: 3 coarse sand) and finished with a floating coat of neat cement
inside. Manhole shall be plastered outside as above but with rough plaster
with waterproofing compound.
10.7.6 All manholes with depths greater than 1 m. shall be provided with 20mm
square or 25mm round CI/Polypropylene footrests set in cement concrete
blocks 250x100x100m min 1:2:4 mix (1 cement: 2 coarse sand: 4 stone
aggregate 20mm nominal size), at 300mm centre to centre vertically and
staggered. Footrests shall be coated with coal tar before embedding.
10.7.7 All manholes shall be provided with cast iron covers and frames and
embedded in reinforced cement concrete slab. Weight of cover, frame and
thickness of slab shall be given above.
10.8.1 Contractor shall connect the new sewer line to the existing manhole by cutting
the walls, benching and restoring them to the original condition. A new
channel shall be cut in the benching of the existing manhole for the new
connection. Contractor shall remove all sewage and water if encountered in
making the connection without additional cost. Back filling and compaction
shall be done carefully in layers, simultaneously on both sides so as to
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 53 OF 54
prevent unequal earth pressure. Back filling shall not be taken up till testing
has been successfully completed.
10.9 TESTING
10.9.1 All testing shall be done in accordance with IS: 1172 and IS: 5329 except as
may be modified herein under.
10.9.2 All lengths of the sewer/ drain/ pipelines shall be fully tested for water
tightness by means of water pressure. Testing shall be carried out from
manhole to manhole. All pipes shall be subjected to a test pressure of at least
2.5m head of water. The test pressure shall, however, not exceed 6m head at
any point. The pipes shall be plugged preferably with standard design rubber
plugs on both ends. The upper end shall, however, be connected to a pipe for
filling with water and getting the required head. The sewer/ drain/ pipeline
shall be filled with water and left to stand for 2 hours and topped up. The
leakage over 30 minutes shall then be measured and the loss in water shall
not exceed 2 litres/cm. of diameter/km of pipeline measured during the last 10
minutes of the period of test.
a) Inserting a smooth ball 12mm less than the internal diameter of the
pipe. In the absence of obstructions such as yarn or mortar projecting
at the joints the ball should roll down the invert of the pipe and emerge
at the lower end,
b) Means of a mirror at one end and a lamp at the other end. If the pipe
line is straight the full circle of light shall be seen otherwise obstruction
or deviation shall be apparent.
10.9.4 A test register shall be maintained which shall be signed and dated by the
Contractor and the Engineer-in-Charge.
10.9.5 The pipeline shall be covered only after the testing is successfully completed.
10.10.1 Excavation
i) Ordinary soil
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 54 OF 54
c) Payment for trenches more than 1.5m in depth shall be made for extra
depth as given in the Schedule of Quantities over and above the rate
for depth upto1.5m.
Rate quoted for excavation shall be inclusive of pumping and bailing out of
water encountered from any source whatsoever.
Stoneware/ RCC/ CI pipes shall be measured for the finished length of the
pipeline per linear meter to the nearest centimetre i.e.
Gully traps shall be measured by the number and rate shall include all
excavation, back filling, foundation, concrete brick masonry, cement plaster
inside and outside, CI grating and sealed cover and frame etc. complete.
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITEUP
TCE.M4-435-06
WATER SUPPLY, SANITARY & DRAINAGE WORKS PAGE 55 OF 54
10.10.8 Manholes
b) Manholes with depths greater than that specified under the main item
shall be paid for under "extra depth" and shall include all items as
given for manholes. Measurement shall be done to the nearest
centimetre. Depth of the manholes shall be measured from top of the
manhole cover to invert level of channel.
Item for making connection to municipal sewer shall be paid for by number
and shall include all items given in the Schedule of Quantities and
specifications.
END
ISSUE
R4
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M4-403-06 SPECIFICATIONS FOR SHOTCRETING AND GUNITING SHEET 1 OF 7
1. SCOPE
1.1. This Specification covers the general requirements of materials, mixing,
placing, curing, constructional and other performance related requirements of
encasing the structural steel members for fire proofing (thickness less than
75mm) as well as strengthening & rehabilitation of concrete structures using
Shotcreting and Guniting. Any other special requirement specified by
ENGINEER or OWNER or as indicated on the drawings shall supersede the
requirements given in this document.
1.2. In addition to this specification, guniting shall be carried out in accordance
with IS: 9012 and other relevant codes mentioned therein. In case of any
conflict between this document and IS codes, the requirements given in this
document shall govern.
2. MATERIALS
All materials to be used for shotcreting shall conform to the requirements of
IS codes. Samples and test results of all materials shall be submitted to
ENGINEER or OWNER for approval. The source of materials shall be kept
same during the execution of the project.
2.1. Cement shall conform to IS 269 or IS 455 or IS 1489, IS 8041 or IS 8112.
2.2. Sand shall comply with the requirements of IS 383 and graded evenly from
fine to coarse as per Zone II and III. Sand of Zone IV shall not be used.
2.3. Coarse aggregates when used shall comply with the requirement of IS 383.
Maximum size of aggregates shall be 10mm. The grading of aggregate shall
be as per IS 9012.
2.4. Water – It shall comply with the requirements of IS 456.
2.5. Admixture – It shall comply with requirements of IS 9103. This shall be mixed
with concrete strictly as per manufacturer’s recommendations and shall meet
the requirements of IS 456.
2.6. Welded wire fabric to be used as reinforcement, shall conform to IS: 1566
and shall be of approved type. Welded wire mesh size shall be 50mmx50mm
and diameter of wire shall not be more than 3mm.
2.7. Reinforcement bars, wherever required shall conform to IS 1786 and
maximum dis meter of reinforcement bar shall not be more than 16mm.
2.8. Air used, shall be dry and free from chemical or hydrocarbon or acid fumes
and smoke.
3. SHOTCRETE PROCESS
Shotcreting shall be done by any of the following two processes.
3.1. Dry Mix Process
Moist sand / coarse aggregates with optimum moisture content of 3% to 6%
shall be thoroughly mixed with cement in a mixing chamber and further fed in
to a special mechanical feeder / dispensing gun. The mixture shall be forced
in to the delivery hose by a feeder week / distributor. The mixed material
shall be kept in suspension by compressed air. The gun shall be connected
FILE NAME:
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information ISSUE
and any claim arising thereof, cost and consequence will be on the party misusing the information. R0
FILE NAME:
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information ISSUE
and any claim arising thereof, cost and consequence will be on the party misusing the information. R0
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information ISSUE
and any claim arising thereof, cost and consequence will be on the party misusing the information. R0
satisfactory construction joint is built up. The remaining area between the
shooting strips is then filled to the level and line of the shooting strips.
5.4. Mix to be used shall conform to the strength requirement as specified in IS
456. Contractor shall submit mix design to ENGINEER or OWNER for
approval. The minimum crushing strength of 24N/mm2 at 28 days shall be
ensured prior to start of the work. Admixtures can be added with prior
approval of ENGINEER or OWNER in the design mix to achieve required
design parameters.
5.5. The water cement ratio of dry mix guniting shall be in the range of 0.3 to 0.5
by weight and 0.4 to m to 0.55 for wet mix.
5.6. The air pressure at the gun outlet shall not be less than 3 kg/cm2.The air and
water pressure shall be uniform and steady. However, the pressure may be
slightly adjusted depending upon the location of the surface, Nozzle size and
orientation etc. to ensure proper deposition and consolidation of the materials
with minimum wastage.
5.7. The application of gunite mortar shall be governed by uniform delivery,
consistent proportion and grading of mix, control of water to assure minimum
of dusting and rebound as well as maximum bonding to present concrete. The
critical part of the total application is nozzle operation and spraying technique.
The proper method of application is to begin at the lowest point, filling in the
corners and recesses first and then to fill the main body of the section in
layers by systematic movement of the nozzle is the ideal spraying method.
Care must be taken to avoid sand pockets behind reinforcement bars. Initially,
the coarse sand particles rebound from the surface and a grout of fine sand
and cement which is also very rich in cement (1:1.5 cement: sand) is built up
on the surface of concrete. This grout helps bonding of gunite to concrete and
also forms a soft cushion for receiving the gunite spray from the nozzle. The
rebound reduces considerably and gunite is built up on the surface in layers.
Any humps in the last layer of gunite should be cut by the edge of a steel
trowel to level the gunite. Finally, a spray coat of gunite with fine sand and
cement is applied to ensure good surface density an impervious to gunite.
5.8. Shotcreting or Guniting shall be laid to a maximum thickness of 50mm in one
operation. Where a layer of shotcreting is to be covered by succeeding layers,
the successive layer shall be laid only after the initial set of previous layer. All
loose materials shall be removed by brooming or hacking and surface e be
cleaned with water jet. The surface shall be thoroughly checked by a hammer
for hollow areas resulting for rebound pockets in poor bond. Such areas shall
be cut and replaced during the second layer deposition.
5.9. When shotcrete consists of several layers, concrete delivery shall be so
scheduled so that each layer is placed while the preceding one is still plastic
to avoid cold joints. If the underlying layer has stiffened just beyond the point
where it can be penetrated by the vibrator, bond can still be obtained by
thoroughly and systematically vibrating the new concrete into contact with the
previously placed concrete; however, an unavoidable layer line will show on
the surface when the form is removed.
FILE NAME:
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information ISSUE
and any claim arising thereof, cost and consequence will be on the party misusing the information. R0
5.10. When multiple layers of wire fabric are required, the first layer is covered with
shotcrete prior to placing the next layer, with ties extending from the first layer
to the next. At least one layer of fabric is used for each 2 inches of shotcrete.
5.11. When applying more than one layer of shotcrete, use a cutting rod, brush with
a stiff bristle, or other suitable equipment to remove all loose material,
overspray, laitance, or other material that may compromise the bond of the
subsequent layer of shotcrete. If shotcrete has hardened, clean the surface of
all loose material, laitance, overspray, or other material that may compromise
the bond of subsequent layers. Bring the surface to a saturated surface-dry
condition at the time of application of the next layer of shotcrete.”
5.12. The nozzle shall be held in optimum position usually between 0.5 to 1.5m
from and at the right angle to the surface.
5.13. The thickness of coating established by providing ground wires both in
vertical and horizontal directions. Ground wires shall be tight and true to line
and placed in such a manner that they can be further tightened if required.
5.14. During application of shotcrete, cement mortar which rebounds off the surface
shall not be used again.
5.15. Construction joints shall be provided at the end of each day’s work or on
stopping work for any reason by tapering the mortar coating to a thin edge
within a length of 300mm. Work shall commence only after cleaning and
wetting of the surface.
5.16. The coating shall be cured by keeping it moist for a period of eight hours and
for a period of at least 7 days or else surface shall be coated with membrane
curing compound. Membrane curing compound shall be from approved
manufacturer.
6. FINISHING AND JOINT SEALING
6.1. The final flush coat 3 to 6mm thick shall be applied to the fresh screeded
lightly wetted surface of the shotcrete and shall be troweled smooth.
6.2. If sufficient cover (at least 25 mm.) is provided on the outer layer of
reinforcement, then gunite does not need any additional protection. However,
the natural finish of gunite is equivalent to rough cast plaster. If smooth
finished surface is required, then additional plaster shall be provided as per
the drawings or directed by an ENGINEER. Plaster shall be applied only after
seven days curing of gunite.
7. APPROACH, WORKING PLATFORM, SCAFFOLDING & FORMWORK
7.1. The contractor shall arrange all approaches, Accesses, scaffoldings,
stairways, ladders, working platform etc. for carrying out the shotcreting /
Guniting process safely. The working area shall be neatly maintained and all
the facilities required by the ENGINEER or OWNER for supervision shall be
provided by the contractor. All temporary works shall be removed by
contractor after satisfactory completion of work and after approval of
ENGINEER or OWNER.
7.2. Formwork, wherever required shall be of plywood. It shall be adequately
supported and braced to protect against deformation on account of vibration
FILE NAME:
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information ISSUE
and any claim arising thereof, cost and consequence will be on the party misusing the information. R0
during the application. Forms shall be oiled, dampened and cleaned before
use.
8. PRECONSTRUCTION AND QUALITY CONTROL
8.1. Test panels simulating actual working conditions shall be fabricated by the
operating staff, using the equipment, material and mix proportion, water
cement ration, etc. as proposed for the main job. These panels shall be
fabricated by gunning on to a back form of plywood. Separate panels shall be
fabricated for different mix proportions being proposed and also for each
gunning position to be encountered during the actual working. The size of
panel shall not be less than 750mm x 750mm and the thickness of guniting /
shotcreting shall be 75mm. Part of the panel shall contain the same
reinforcement as proposed to ascertain soundness of concrete behind the
reinforcement. Panel size shall be large enough to ensure quality and
uniformity of the operation.
8.2. Cubes or cores shall be taken from the panel for testing. The core shall have
a minimum diameter of 75mm. The specimen shall be tested at the end of 7
and 28 days as per relevant IS code of testing cores. Only 28 days strength
shall be considered as strength acceptance criteria.
8.3. The cut surface of the core shall be carefully examined and additional surface
shall be exposed by sawing or breaking the panel to check the soundness
and uniformity of the material. All cut or broken surfaces shall be dense and
free from laminations and sand pockets.
8.4. Small un-reinforced test panels, at least 300 mm x 300 mm x 75 mm thick
shall be periodically gunned and cores or cubes extracted for compressive
tests and visual examination.
8.5. Test core shall also be taken from the completed work at regular periods as
decided by the ENGINEER or OWNER to ensure that control tests reflect the
actual quality.
8.6. Cubes, by directly gunning in to 150mm cube moulds shall be taken from day-
to-day quality tests. The results of core tests shall be co-related to the results
of cubes made from the panels. Frequency of sampling of shotcrete and
acceptance criteria shall be as decided by the ENGINEER.
9. PAYMENT
9.1. Payment for encasing structural steel members for fire proofing shall be
regulated as per the payment clauses given specification M4-405-06.
9.2. Payment for strengthening and rehabilitation of concrete structures shall be
made as mentioned below.
a) Payment shall be made on cubic metre (m3) basis of actually finished
work as certified by ENGINEER.
b) The rate quoted shall be inclusive of all labour
c) The rate quoted shall be inclusive of all labour, material, form work,
plant & tools etc. required for the successful and satisfactory completion
of work including curing, curing compound, all cleaning operations
FILE NAME:
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information ISSUE
and any claim arising thereof, cost and consequence will be on the party misusing the information. R0
END
FILE NAME:
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information ISSUE
and any claim arising thereof, cost and consequence will be on the party misusing the information. R0
1. SCOPE
1.1. This specification covers the general requirements of materials and the
method of application for external fire protection of structural steel
members, vessel/column skirts, saddles and supports against fire by
shotcreting, in-situ concrete or vermiculite cementitious coating.
1.2. This specification does not cover the general requirements of materials
and the method of application for external fire protection of structural steel
members, using intumescent paint. Intumescent paint, if applied, shall
conform to the requirements of IS 17044.
2. MATERIALS
2.1. All materials to be used shall conform to the requirements of respective latest
BIS codes. Samples and test results for all materials shall be submitted to the
ENGINEER or OWNER and got approved from him in writing before
execution of work. Acceptance criteria of commonly used materials are given
below.
2.1.1. Cement - The cement used shall conform to either of the following BIS codes:
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE
R0
2.1.2. Fine Aggregates (Sand) - Sand shall comply with the requirements of IS 383
and graded evenly from fine to coarse as per Zone II and Zone III. Sand of
Zone IV shall not be used.
2.1.3. Coarse Aggregates – Coarse aggregates shall comply with the requirements
of IS 383. Maximum size of aggregates shall be 10mm for shorcrete
application. For cast in situ application, higher size of aggregates as per IS
9102 may be used.
2.1.5. Admixture – It shall comply with requirements of IS 9103. This shall be mixed
with concrete strictly as per manufacturer’s recommendations and shall meet
the requirements of IS 456.
2.1.7. Expanded Metal Steel Sheet - Expanded metal steel sheets shall conform to
IS: 412 and shall be of an approved type. Size of the mesh shall be
10mmx40mm with strands of 2.5mm width and 1mm thickness.
2.1.9. Accessories
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE
R0
Nuts of M16 bolts shall be welded with all the steel members to be fire
proofed. Maximum spacing of nuts shall be 400mm centre to centre in both
directions. Nuts shall not be welded to the vessel supports/skirts (to be
welded by vessel fabricator); unless directed by ENGINEER or OWNER.
Primer paint shall be applied to the MS nuts and affected surfaces of
the members due to welding after proper cleaning. Primer paint shall
be compatible with the primer already applied to the steel members.
3.3. Fixing of expanded metal steel sheet
Expanded metal steel sheet shall only be used for built up sections,
consisting of two members spaced apart. This shall be kept in position
true to line and face, and shall be attached firmly to structural steel
member by tack welding or with the help of clips and 16 SWG tying wire at
300mm centre to centre. Minimum lap of 75mm shall be provided wherever
required, however laps shall be avoided at bends. Strands of the expanded
metal steel sheet shall slope inwards & downwards.
3.4. Placement of reinforcement
Reinforcement shall be placed in the middle of coated material thickness. It
shall be bent confirming with outlines of finished encasement and rigidly
secured in place by tie wire with all the nuts. Minimum lap at ends and sides
shall be 100mm and lapped wire fabric shall be tied firmly.
3.5. Cover plate
Cover plates shall be welded to the top flange of the beams if top edges of
fire proofing are not protected with bitumen mastic flashing
4. APPLICATION
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE
R0
5.1. The Contractor shall arrange all approaches, scaffolding, stair ways, ladder,
working platform etc., for carrying out the entire works s af e l y . The working
area shall be neatly maintained and all the facilities required by ENGINEER
or OWNER for proper supervision of the work shall be provided. In case,
any special precaution is needed for the safety of the structure till the
completion of application, the Contractor shall make and provide all such
arrangement to the complete satisfaction of the ENGINEER or OWNER and
shall remove the same after completion of works.
5.2. Form work wherever required shall be of Plywood Sheeting. It shall be
adequately supported and braced to protect against deformation on account
of vibration during the application. Forms shall be oiled, dampened and
cleaned before use. All other specifications pertaining to the f o r m work
shall be as per specification M4-403-01.
6. SPECIFIC REQUIREMENT
Concrete for fireproofing shall be of M20 grade design mix. Mixing and
placing shall be done as per TCE specification no. M4-403-01. Thickness of
concrete coating over the steel shall be minimum 50mm.
Concrete shall be poured into well-made forms properly oiled and made
to correct dimensions. . Concrete shall be vibrated as necessary to
ensure smooth surface, free from voids and irregularities. Any defects,
honeycomb etc. shall be made good by contractor at his own cost.
6.3.1. Design
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE
R0
b) The coating shall be non-corrosive to the steel members & shall not
be affected by environmental conditions, whether natural or from
local leaks, spillage or pollution. It shall also be asbestos free.
c) The coating shall be able to withstand both thermal shock and
impingement of water from fire hoses and/or monitors.
d) The coating material shall be durable and easily repairable.
e) Application procedure of the coating shall be easy, non- hazardous
and also shall not interfere with the working of the adjoining areas.
f) The contractor shall submit calculations of coating thickness for all
structural steel sections to be fire proofed; for review/approval of the
ENGINEER or OWNER for the branded product but in no case
thickness of coating shall be less than 40mm.
6.3.2. Application
7.1. Fire proof coating shall be finished with 2 coats of micro-porous exterior top
coat, compatible to cement surfaces, of approved make & colour
conforming to IS specifications.
7.2. All exposed joints between fire proofing material coating & steel shall be
sealed with min. 1 Omm thick bitumen mastic flashing, when not otherwise
shielded.
8. TEST
9. PAYMENT
9.1. Payment for fire proofing by shorcreting or guniting, shall be made on cubic
metre (m3) basis of actually finished work or as calculated from the
construction drawings, whichever is less.
9.2. Payment of fire proofing using intumescent paint shall be made based on the
square meter (m2) basis of finished surface area or as calculated from the
drawings, whichever is less.
9.3. The rate quoted shall be inclusive of all labour, material, form work, plant &
tools etc. required for the successful and satisfactory completion of work
including curing, curing compound, all cleaning operations before and after
the work, preparation of the surface as specified, applying the primer coat
compatible with the primer already applied over nuts and effected surface of
steel surfaces due to welding , finishing the surface smooth, painting the
surface with 2 coats of micro-porous exterior top coats & sealing the joints
with sealing compounds, providing required access, working platforms,
props, scaffolding and other safety measures including their removal after
completion.
9.4. The rate shall also be inclusive of supplying and fixing of reinforcement with
nuts by using tying wire ( ex c l u di n g the cost of expanded metal steel sheets,
cover plates, which shall be paid extra) and other required accessories for
satisfactory completion of the work as specified and directed.
9.5. The rates quoted shall be inclusive of the tests specified and directed to
establish the quality and strength of materials.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE
R0