Professional Documents
Culture Documents
Mohammad Ali (034) Assign1 Ipm
Mohammad Ali (034) Assign1 Ipm
BS(IT) 5-A
Fall-2021
Syed Mohammad Ali Rizvi
02-235192-034
ASSIGNMENT 01
Marks: 10
Read Carefully:
• The deadline for this assignment is before or on Tuesday Nov 30, 2021.
WARNING: This is an individual assignment; you must solve it by yourself. Any form of
plagiarism will result in receiving zero in the assignment.
WARNING: Late submission will not be accepted. Any assignment submitted after the cutoff
time will get zero.
Question:
A project manager has to do a project of coloring of a house. The project manager has to give the
precise cost and time estimate to the owner of the house. The house has 4 rooms, the owner has to
leave the country within 2 days and he has budget of Rs. 100,000 only.
Following activies are involved in the coloring of house:
The cost of a color bucket is Rs. 3500 and 2 color buckets are required for a single room’s walls and
1 color bucket is required for a room’s ceiling. A single labour can work only for 9 hours daily from
8:00am to 5:00pm and his salary for 8 hours is Rs. 2000. If 8 labour workers can be hired for the
project and 2 labour can be assigned for each room, then :
i. How much cost and time is required for the project using WBS? (Marks 2)
ii. Find the critical path of the project. (Marks 2)
iii. Create a scope statement of the project. (Marks 3)
iv. Create a project charter of the project. (Marks 3)
GIVEN:
Owner has budget of Rs. 100,000 only
The owner has to leave the country within 2 days
The house has 4 rooms
Cost of a color bucket is Rs. 3500
1 color bucket is required for a room’s ceiling
2 color buckets are required for a single room’s walls
Single labor can work only for 9 hours daily 8 hour for work and 1 hour for food and tea
His salary for 9 hours is Rs. 2000
Total 8 worker, 2 for each room
REQURIED:
Cost and time
SOLUTION:
Duration = 2 days
Working hours = 9 (8 hour for work and 1 hour for food and tea)
Total working hours available = 2 x 9 = 18 hours
Total work expense(2 days) = coloring cost + labor cost + miscellaneous cost
= 32000+42000+10000
Total work expense(2 days) = Rs. 84,000/-
Network diagram:
FLOAT=0 0
0 A 2 2 B 18
0 2 2 2 16 18
13 0 0
2 C 4 18 E 22 22 F 38
15 2 17 18 4 22 22 16 38
13
4 D 5
17 1 18
Scope Statement:
Project Charter:
The manager had much experience of these -Only 2 days are -there is no other to
short timeline projects so she does not try new available for work work in rooms
worker they go for most experience labors of -Only 9 hours of a day -there is no furniture
their company. labor can work from in rooms
8AM - 5pm - furniture in rooms
-house is not are covered
available other than -other things are
mentioned day hours covered
SPONSORAPPROVAL DATE
OWNER 30-11-2021
GOAL STAKEHOLDERS ROLES
Done With In 2 Day And 9 Hours Each Day Owner Release payment
Manager Lead the labors
Labors painting
OBJECTIVES MILESTONES STATUS
----------------------XXXXXXXX------------------------