You are on page 1of 6

ITC-311: IT Project Management

BS(IT) 5-A
Fall-2021
Syed Mohammad Ali Rizvi
02-235192-034

ASSIGNMENT 01
Marks: 10

Read Carefully:

• The deadline for this assignment is before or on Tuesday Nov 30, 2021.

WARNING: This is an individual assignment; you must solve it by yourself. Any form of
plagiarism will result in receiving zero in the assignment.

WARNING: Late submission will not be accepted. Any assignment submitted after the cutoff
time will get zero.

• Assignment will be sumitted in the form of Soft Copy.

Syed Mohammad Ali Rizvi 02-235192-034 assignment 1


ITC-311: IT Project Management
BS(IT) 5-A
Fall-2021
Syed Mohammad Ali Rizvi
02-235192-034

Question:
A project manager has to do a project of coloring of a house. The project manager has to give the
precise cost and time estimate to the owner of the house. The house has 4 rooms, the owner has to
leave the country within 2 days and he has budget of Rs. 100,000 only.
Following activies are involved in the coloring of house:

Activity ID Activitity Description Preceding Activities Estimate in hours


Start Start of project 0
A Hiring of all labour Start 2
B Smoothing of all rooms’ walls A 16
by a single labour
C Purchase of all color A 2
D Mixing of all rooms’ color by a C 1
single labour
E Paint of all rooms’ ceiling by a B,D 4
single labour
F Paint of all rooms’ walls by a E 16
single labour
End End of Project F 0

The cost of a color bucket is Rs. 3500 and 2 color buckets are required for a single room’s walls and
1 color bucket is required for a room’s ceiling. A single labour can work only for 9 hours daily from
8:00am to 5:00pm and his salary for 8 hours is Rs. 2000. If 8 labour workers can be hired for the
project and 2 labour can be assigned for each room, then :

i. How much cost and time is required for the project using WBS? (Marks 2)
ii. Find the critical path of the project. (Marks 2)
iii. Create a scope statement of the project. (Marks 3)
iv. Create a project charter of the project. (Marks 3)

Syed Mohammad Ali Rizvi 02-235192-034 assignment 1


ITC-311: IT Project Management
BS(IT) 5-A
Fall-2021
Syed Mohammad Ali Rizvi
02-235192-034

WBS DIAGRAM AND CALCULATION:

GIVEN:
Owner has budget of Rs. 100,000 only
The owner has to leave the country within 2 days
The house has 4 rooms
Cost of a color bucket is Rs. 3500
1 color bucket is required for a room’s ceiling
2 color buckets are required for a single room’s walls
Single labor can work only for 9 hours daily 8 hour for work and 1 hour for food and tea
His salary for 9 hours is Rs. 2000
Total 8 worker, 2 for each room

REQURIED:
Cost and time

SOLUTION:
Duration = 2 days
Working hours = 9 (8 hour for work and 1 hour for food and tea)
Total working hours available = 2 x 9 = 18 hours

Color bucket cost = 3500


Each room wall req. = 2 buckets
Each room ceiling req. = 1 bucket
Each room req. total = 3 buckets
Total rooms = 4
Total coloring cost = color bucket cost x total buckets require for each room x no. of rooms
Total coloring cost = 3 x 4 x 3500
Total coloring cost = Rs. 42,000/-
Syed Mohammad Ali Rizvi 02-235192-034 assignment 1
ITC-311: IT Project Management
BS(IT) 5-A
Fall-2021
Syed Mohammad Ali Rizvi
02-235192-034

no. of labors could be hired = 8


Cost of each labor = Rs. 2000/-
Labor cost for 1 day = Days x Labor x salary (1 x 8 x 2000) =16000
Labor cost for 2 day = Rs.32000
Miscellaneous cost = 10000

Total work expense(2 days) = coloring cost + labor cost + miscellaneous cost
= 32000+42000+10000
Total work expense(2 days) = Rs. 84,000/-

10% risk cost = 84000 x 0.1 = Rs. 8400/-


9% profit = 84000 x 0.1 = Rs. 7560/-

Total project cost = total work expense+ Risk cost + Profit


= 84000 + 8400 + 7560

Total project cost = Rs. 99,960/-

Network diagram:

FLOAT=0 0

0 A 2 2 B 18
0 2 2 2 16 18

13 0 0
2 C 4 18 E 22 22 F 38
15 2 17 18 4 22 22 16 38

13
4 D 5
17 1 18

CRITICAL PATH: A-B-E-F

Syed Mohammad Ali Rizvi 02-235192-034 assignment 1


ITC-311: IT Project Management
BS(IT) 5-A
Fall-2021
Syed Mohammad Ali Rizvi
02-235192-034

Scope Statement:

Project Scope Statement

Project name House Painting


sponser House owner Project manager Mohammad Ali
Approval date 30-11-2021 Last revision date 30-11-2021

Scope Description IN SCOPE:


interior house painting 4 rooms with their
ceiling,hiring labors, purchasing color for
painting, labor salary/cost, smoothing, painting
,miscellaneous material and things requires
cotton, brush, thread, etc
OUT OF SCOPE:
exterior house painting
windows, doors, doorway, doorsill
any room, wall and ceiling other than 4 rooms
Project Deliverables Painted rooms with ceiling .
Acceptance criteria the agreement will be done if painter ready to
work under given constraints. And done work in 2
days in given cost but no out of scope work will be
accepteded
constraints Only 2 days are available for work
Only 9 hours of a day labor can work from 8AM -
5pm
house is not available other than mentioned day
hours
assumptions there is no other to work in rooms
there is no furniture in rooms
furniture in rooms are covered
other things are covered

Syed Mohammad Ali Rizvi 02-235192-034 assignment 1


ITC-311: IT Project Management
BS(IT) 5-A
Fall-2021
Syed Mohammad Ali Rizvi
02-235192-034

Project Charter:

OPPORTUNITY CONSTRAINTS ASSUMPTION

The manager had much experience of these -Only 2 days are -there is no other to
short timeline projects so she does not try new available for work work in rooms
worker they go for most experience labors of -Only 9 hours of a day -there is no furniture
their company. labor can work from in rooms
8AM - 5pm - furniture in rooms
-house is not are covered
available other than -other things are
mentioned day hours covered

SPONSORAPPROVAL DATE
OWNER 30-11-2021
GOAL STAKEHOLDERS ROLES

Done With In 2 Day And 9 Hours Each Day Owner Release payment
Manager Lead the labors
Labors painting
OBJECTIVES MILESTONES STATUS

Painting 4 rooms’ walls and ceiling • hired labors ✓


• purchased color ✓

SCOPE • purchased miscellaneous
materials
IN SCOPE: • walls smoothed ✓
interior house painting (4 rooms with their • painted ceiling ✓
ceiling),hiring labors, purchasing color for • painted walls ✓
painting, labor salary/cost, smoothing, ✓
• completed painting
painting ,miscellaneous material and things
requires (cotton, brush, thread, etc.) CORE TEAMMEMBERS ROLE
OUT OF SCOPE: Syed Mohammad Ali Rizvi Project
exterior house painting Manager
windows, doors, doorway, doorsill
any room, wall and ceiling other than 4 rooms
DELIVERABLES SUMMARY STATUS
Painted rooms with ceiling . Project start date: 30-11-2021
Est-completion:2-12-2021