You are on page 1of 9

Full-Scale Testing for Composite Slab/Beam

Systems Made with Extended Stud Spacing


Sameh S. Badie, Ph.D., P.E., M.ASCE1; Amgad F. Morgan Girgis, Ph.D., P.E.2;
Maher K. Tadros, Ph.D., P.E., M.ASCE3; and Krissachai Sriboonma, D.Sc.4
Downloaded from ascelibrary.org by NIRMA INSTITUTE OF TECHNOLOGY on 01/31/17. Copyright ASCE. For personal use only; all rights reserved.

Abstract: Investigation of the background of the 610 mm (24 in.) spacing of stud shear connectors showed that this limit was set on the basis
of a small amount of testing of beams with spacing greater than this limit. The literature search showed that some attempts have been recently
made to extend this limit. One of the objectives of the NCHRP 12-65 research project was to investigate the possibility of extending this limit
to 1,220 mm (48 in.) for cluster of studs used for precast concrete panels made composite with steel I-beams. The experimental investigation
included testing of push-off specimens and full-scale composite beams. Results of the push-off specimens have shown that the fatigue loading
has no detrimental effect on the load-slip relationship when the number of studs is doubled per cluster. This paper covers the second part of the
experimental investigation, which is fatigue and ultimate testing of full-scale composite beams. The full-scale testing has proven that full-
composite action between precast concrete panels and steel girders can be achieved when the spacing between the stud clusters is extended up
to 1,220 mm (48 in.). DOI: 10.1061/(ASCE)BE.1943-5592.0000215. © 2011 American Society of Civil Engineers.
CE Database subject headings: Shear; Studs; Slabs; Steel beams; Girder bridges; Panels; Spacing; Full-scale tests.
Author keywords: Shear; Connector; Studs; Composite; Precast; Panel; Bridges; Girders.

Introduction AASHTO LRFD Bridge Design Specifications, 4th Edition


(AASHTO 2007) state that spacing between the shear connectors
Headed steel studs are used to create composite action between should not exceed 610 mm (24 in.). Background check of this limit
concrete deck slabs and steel girders. The studs are welded to showed that it was set on the basis of a small amount of testing of
the top flange of the girders and embedded in the deck slab for composite beams with spacing greater than this limit (Badie
an adequate height to provide for full anchorage. In bridges built et al. 2010).
with full-depth precast concrete deck systems, the studs are set in One of the objectives of the NCHRP 12-65 research project
clusters and embedded in shear pockets created in the panels during (Badie and Tadros 2008) was to investigate the possibility of ex-
fabrication. After the precast panels are installed on the bridge and tending this limit to 1,220 mm (48 in.). The experimental investi-
their elevation is adjusted, the shear pockets and the haunch be- gation included testing of push-off specimens and full-scale
tween the steel girders and the panels are filled with flowable non- composite beams. The experimental results of the push-off speci-
shrink grout. mens has shown that fatigue load has no detrimental effect on the
For bridge owners, it is advantageous to extend the spacing be- load-slip relationship when the number of studs is doubled per clus-
ter (Badie et al. 2010). Another goal of the push-off specimens test
tween the stud clusters, even beyond what the specifications cur-
was to investigate the validity of the current AASHTO LRFD
rently permit, for the following reasons (Badie et al. 2010): (1) to
Specifications (AASHTO 2007) provisions for design of stud clus-
simplify and speed up the fabrication process of the panels; (2) to
ters with the proposed extended spacing. The design provisions are
reduce the cost of the deck system by reducing the volume of the given in Article 6.10.10 of Section 6 and Article 5.8.4 of Section 5
grout filling the shear pockets; (3) to reduce the possibility of water of the AASHTO LRFD Specifications (AASHTO 2007), as
leakage at the interface between the shear pockets and the grout follows:
filling them; and (4) to give the design engineer more flexibility • Fatigue resistance, Z r :
in laying out the transverse reinforcement of the panel. The
5:5 2
Z r ðkipsÞ ¼ αd 2s ≥ d ðLRFD; Eq: 6:10:10:2-1Þ ð1Þ
1
Associate Professor, Civil & Environmental Engineering Dept., The 2 s
George Washington Univ., 801 22nd St., Washington, D.C. 20052 (corre-
sponding author). E-mail: badies@gwu.edu where
2
Design Engineer, e-Construct, 2111 South 67th St., Suite 200, Omaha, αðksiÞ ¼ 34:5  4:28 logðNÞ ðLRFD; Eq:6:10:10:2-2Þ
NE 68106. E-mail: AGirgis@econstruct.us
3
Leslie D. Martin Professor, Dept. of Civil Engineering, Univ. of ð2Þ
Nebraska–Lincoln, Lincoln, NE. E-mail: mtadros@mail.unomaha.edu and N = number of cycles
4
Consultant, Baker Engineering and Risk Consultants, Inc., San • Nominal shear resistance, Qn (kips):
Antonio, TX. E-mail: KSriboonma@BakerRisk.com
pffiffiffiffiffiffiffiffiffi
Note. This manuscript was submitted on March 25, 2010; approved on Qn ðkipsÞ ¼ 0:5Asc f 0c E c ≤ Asc F u
December 29, 2010; published online on August 15, 2011. Discussion per- ð3Þ
iod open until February 1, 2012; separate discussions must be submitted for ðLRFD; Eq:6:10:10:4:3-1Þ
individual papers. This paper is part of the Journal of Bridge Engineering,
Vol. 16, No. 5, September 1, 2011. ©ASCE, ISSN 1084-0702/2011/5-653– where Asc = cross-sectional area of a stud shear connector (in2 );
661/$25.00. E c = modulus of elasticity of the concrete (ksi); f 0c = specified

JOURNAL OF BRIDGE ENGINEERING © ASCE / SEPTEMBER/OCTOBER 2011 / 653

J. Bridge Eng., 2011, 16(5): 653-661


compressive strength of the concrete (ksi); and F u = specified chance of any possible separation between the slab and the
minimum tensile strength of a stud shear connector (ksi). steel beam.
• Nominal shear resistance, V ni (kips), using the shear friction
theory:
Full-Scale Beam Specimens
V ni ðkipsÞ ¼ cAcv þ μAvf f y ðLRFD; Eq:5:8:4:1-3Þ ð4Þ
Two full-scale composite beams, 9,754-mm (32-ft) long, were fab-
ricated. Each beam consisted of a 203-mm (8-in.) thick, 1,220-mm
V ni ≤ 0:2f 0c Acv or ðLRFD; Eq:5:8:4:1-4Þ ð5a Þ
(48-in.) wide, precast concrete slab supported on a W18 × 119 steel
beam, Grade 50 steel. The slab and the steel beam were made
V ni ≤ 0:8Acv ðLRFD; Eq:5:8:4:1-5Þ ð5b Þ composite by using 64 31.8-mm (1.25-in.) studs over the full span
Downloaded from ascelibrary.org by NIRMA INSTITUTE OF TECHNOLOGY on 01/31/17. Copyright ASCE. For personal use only; all rights reserved.

length of beam. The studs on Beam 1 were set in 16 clusters spaced


where c = cohesion factor, 0.025 ksi for concrete anchored to as- at 610 mm (24 in.), with four studs per cluster. The studs on Beam 2
rolled structural steel by headed studs; μ = friction factor, 0.7 for were set in eight clusters spaced at 1,220 mm (48 in.), with eight
concrete anchored to as-rolled structural steel by headed studs; studs per cluster. In each cluster, two studs, spaced at 5 in. in the
Acv = area of concrete considered to be engaged in interface transverse direction, were provided per row, and the spacing be-
shear transfer (in2 ); Avf = area of shear reinforcement crossing tween the studs in the longitudinal direction was 76 mm (3 in.).
the shear plane (in2 ); and f y = yield stress of horizontal shear The stud clusters on the north side of each composite beam were
reinforcement (ksi). confined with individual closed ties, whereas the stud clusters on
The first phase of the experimental program of the NCHRP 12- the south side were confined with hollow structural steel tubes
65 project, conducted on push-off specimens (Badie et al. 2010), (HSS). Figs. 1 and 2 show the details of the full-scale beams.
concluded that (1) Eq. 6.10.10.2-1 of the AASHTO LRFD Spec- The concrete slab was made of one precast panel reinforced
ifications (AASHTO 2007) can be used to estimate the fatigue with two welded wire reinforcement (WWR) meshes. The top mesh
capacity regardless of the number of studs provided in the cluster; was 152 × 152 mm-MW65 × MW65 (6 × 6 in:-W10 × W10),
(2) confinement of the grout surrounding the stud cluster was able and the bottom mesh was 152 × 152 mm-MW90 × MW90
to protect the grout from early crushing and to allow the studs to (6 × 6 in:-W14 × W14). This amount of reinforcement was pro-
develop their maximum fatigue strength even if the limits given by vided in accordance with the minimum reinforcement requirements
Eqs. (5a) and (5b) are violated; and (3) Eq. 6.10.10.4.3-1 of the of the Empirical Design Method given in Article 9.7.2 of the
AASHTO LRFD Specifications (AASHTO 2007) overestimates AASHTO LRFD Specifications (AASHTO 2007). The amount
the ultimate capacity, whereas Eq. 5.8.4.1-3 of the AASHTO LRFD of transverse reinforcement, As , and bearing stresses in front of
Specifications (AASHTO 2007) correlates very well with the test the stud clusters were checked to protect the slab from longitudinal
results. Because some of the push-off specimens failed in bearing splitting cracking and/or crushing, by using Eqs. (6) and (7), re-
or the slab around the shear pockets cracked before the studs de- spectively (Badie et al. 2010)
veloped their design shear strength, Badie et al. (2010) concluded  
that the push-off specimens are not accurate in modeling interface T split bc
As ¼ ; T split ¼ 0:25P 1  ð6Þ
shear behavior in beams, especially for investigating the ultimate S fy b
capacity. This is because the loading arrangement and the limited
specimen size do not provide the true shear/flexure interaction or where b = effective slab width of the composite slab-beam system;
the redundancy that exists in the more expensive beam testing. As a bc = width of the stud cluster; f y = minimum specified yield
result, Badie et al. (2010) recommended testing of full-scale strength of the transverse reinforcement used in the slab; P = hori-
composite beams to investigate the ultimate capacity of studs zontal force generated by a cluster of studs; and S = spacing be-
grouped in clusters spaced at 1,220 mm (48 in.). tween the clusters. P is taken as the capacity of the studs in the
This paper covers the second phase of the experimental inves- cluster as determined by Eq. 6.10.10.4.3-1 or Eq. 5.8.4.1-3 of
tigation, which is fatigue and ultimate testing of two full-scale the AASHTO LRFD Specifications (AASHTO 2007).
composite beams. A precast concrete slab made composite with
sffiffiffiffiffi sffiffiffiffiffi
a steel beam configuration was used. The 31.8 mm (1.25 in.) large A2 A2
0
size studs, recently developed (Badie et al. 2002), were used in this f allowable bearing ¼ 0:85ϕf c ; ≤ 2:0 ð7Þ
research to maximize the spacing between clusters and increase the A1 A1

1'-0" 15 spacings @ 2 ft = 30 ft 1'-0"


A B

N Beam #1 S
A B
2 ft 7 spacings @ 4 ft 2 ft
A B

N Beam #2 S
A B
31'-0"
6" 6"
No. 6 Closed Ties Confinment HSS 13x9x5/16 Tube Confinment

Fig. 1. Arrangement of the stud clusters of beams 1 and 2 (X = location of the clusters; N = north side; S = south side)

654 / JOURNAL OF BRIDGE ENGINEERING © ASCE / SEPTEMBER/OCTOBER 2011

J. Bridge Eng., 2011, 16(5): 653-661


4'-0" 4'-0"
11 1/2" 6"x6"-W10xW10 2 in. grouting hole 6"x6"-W10xW10

2"
3"
1/2" 1/2"
5"
1"
1"
3 closed ties 5" HSS 9x7x0.188 5" 6"x6"-W14xW14
6"x6"-W14xW14
with 1 in. 9" 9"
clear spacing
11 1/4"
11 1/4"
Downloaded from ascelibrary.org by NIRMA INSTITUTE OF TECHNOLOGY on 01/31/17. Copyright ASCE. For personal use only; all rights reserved.

W18x119 W18x119

Section A-A Section B-B


1 in. vent 3/4"
1 in. vent
1'-1 3/4"

2" 3" 2"

2" 3" 2"


9 1/2"
7"

7"
3/4"
#4 closed ties
2 in. grouting hole HSS 9x7x0.188 2 in. grouting hole
Plan view of 4-stud Cluster with Closed Ties Plan view of 4-stud Cluster with HSS Tube

1 in. vent
1 in. vent

2" 3" 3" 3" 2"


2" 3" 3" 3" 2"

1'-3 1/2"

1'-1"
1'-1"

#6 closed ties HSS 13x9x5/16


1 in. vent 2 in. grouting hole
1 in. vent 2 in. grouting hole
Plan view of 8-stud Cluster with Closed Ties Plan view of 8-stud Cluster with HSS Tube

Fig. 2. Sections A-A and B-B of beams 1 and 2

where A1 = net loaded area = (bc xt s ); A2 = maximum area of Table 1 gives the values of the splitting force, T split , the required
the supporting surface that is geometrically similar to and con- area of transverse reinforcement, As , and the bearing stresses of
centric with the loaded area = (effective flange width of the both beams by using Eq. 6.10.10.4.3-1 or Eq. 5.8.4.1-3 of the
slab xt s ); ts = slab thickness, and ϕ = bearing strength reduction AASHTO LRFD Specifications (AASHTO 2007). Table 1 shows
factor = 0.65. that the provided transverse reinforcement in the precast slab was

Table 1. Check for As and Bearing Stresses of the Full-Scale Beams


As and bearing stresses using As and bearing stresses using Provided As and
LRFD Eq. 6.10.10.4.3-1a LRFD Eq. 5.8.4.1-3a allowable bearing stresses
Beam 1: 610-mm (24-in.) cluster spacing (bc ¼ 9 in: and b ¼ 48 in:, S ¼ 4 ft, and f y ¼ 65 ksib)
P ¼ 314:8 kips=cluster (LRFD Eq. 6.10.10.4.3-1a) P ¼ 187:1 kips=cluster (LRFD Eq. 5.8.4.1-3a) Provided As ¼ 0:48 in:2 =ft,
T split ¼ 31:97 kips=ft, As ¼ 0:48 in:2 =ft T split ¼ 19:00 kips=ft, As ¼ 0:29 in:2 =ft allowable bearing
[derived from Eq. (6)] [derived from Eq. (6)] stress = 9.06 ksi
Bearing stress = 314:8 kips=9 x 8 in: ¼ 4:37 ksi Bearing stress = 187:1 kips=9 x 8 in: ¼ 2:60 ksi
[derived from Eq. (7)] [derived from Eq. (7)]
Beam 2: 1,220-mm (48-in.) cluster spacing (bc ¼ 9 in: and b ¼ 48 in:, S ¼ 8 ft, and f y ¼ 65 ksia)
P ¼ 629:6 kips=cluster (LRFD Eq. 6.10.10.4.3-1a) P ¼ 372:6 kips=cluster (LRFD Eq. 5.8.4.1-3a) Provided As ¼ 0:48 in:2 =ft,
T split ¼ 31:97 kips=ft, As ¼ 0:49 in:2 =ft T split ¼ 19:00 kips=ft, As ¼ 0:29 in:2 =ft allowable bearing
[derived from Eq. (6)] [derived from Eq. (6)] stress = 9.06 ksi
Bearing stress = 629:6 kips=9 x 8 in: ¼ 8:74 ksi Bearing stress = 372:6 kips=9 x 8 in: ¼ 5:18 ksi
[derived from Eq. (7)] [derived from Eq. (7)]
Note: 1 ksi ¼ 6:895 MPa; 1 kip ¼ 4:448 KN; 1 in: ¼ 25:4 mm.
a
AASHTO LRFD Specifications (AASHTO 2007).
b
According to the Wire Reinforcement Institute manual (2010).

JOURNAL OF BRIDGE ENGINEERING © ASCE / SEPTEMBER/OCTOBER 2011 / 655

J. Bridge Eng., 2011, 16(5): 653-661


sufficient to resist the splitting force. As per Article 5.11.2.5.2 of
the AASHTO LRFD Specifications (AASHTO 2007), the trans-
verse reinforcement of the slab was considered fully developed
as more than two cross wires were embedded, with the closer wire
at a distance greater than 50 mm (2 in.) from the critical section. A
41.4 MP (6 ksi) standard concrete mix was used for the precast slab.
The concrete strength measured at time of testing the beams was
56.5 MP (8.2 ksi). The shear pockets were filled with a commercial
nonshrink grout, SS Mortar, extended with 13 mm (.5 in.) of pea
gravel. Compressive strength of the grout measured at time of test-
ing was 66.2 MPa (9.6 ksi). Coupons of the steel beams were taken
Downloaded from ascelibrary.org by NIRMA INSTITUTE OF TECHNOLOGY on 01/31/17. Copyright ASCE. For personal use only; all rights reserved.

and tested in tension, which showed that the yield strength was ap-
proximately 352 MPa (51 ksi).
The composite beams were built by supporting the steel beam
on two end supports. Then the precast concrete slabs were installed
and their elevation was adjusted to provide for a 25-mm (1-in.)
haunch. Polystyrene packer rods were used as grout dams, as
shown in Fig. 2, then the nonshrink grout was cast to fill the shear
Fig. 3. Fatigue fracture failure of composite beam 2 (images by S. S.
pockets and the haunch through the 51-mm (2-in.) diameter holes Badie and M. K. Tadros)
that were provide in the shear pocket. As a result of this construc-
tion scenario, the weight of the steel beam and the concrete slab did
not provide any horizontal shear tresses on the studs.
because the steel beam was exposed to a very high number of
fatigue cycles (over 20 million cycles) in other research projects
Fatigue Test before it was used in building Beam 2 for this research project.
As a result of the unexpected fracture failure, a 13-mm (.5-in.)
The composite beams were exposed to 2 million cycles of fatigue
separation between the slab and the steel beam was developed over
load, by applying a concentrated load at the midspan section of
a distance of approximately 610 mm (24 in.) around the failure lo-
each beam. This setup put all stud clusters under a uniform hori-
cation. The composite beam was thoroughly inspected and no other
zontal shear force produced only by the applied load. The upper
limit of the fatigue concentrated load at midspan was set to cracks or signs of distress were detected.
384.3 kN (86.4 kips). This value was determined by using the stud Fig. 4 shows the pre- and postfatigue stress distribution at mid-
fatigue resistance given by Eq. 6.10.10.2-1 of the AASHTO LRFD span of both beams and compares them with the stresses calculated
Specifications (AASHTO 2007) and the section properties. A mini- by using the elastic stress theory assuming full-composite action.
mum load of 7.1 kN (1.6 kips) was used as the lower limit of the Table 2 gives the deflection of the composite beams at the quarter
fatigue load to maintain stability of the test setup. Normal stresses points and midspan before and after applying the fatigue load and
in the concrete slab and the steel beam were checked and found to compares them with the elastic theory values. Also, Fig. 5 gives the
be within the elastic limit of both materials. load-displacement relationship at midspan before and after apply-
A series of strain gauges and linear voltage displacement ing the fatigue load. Examining Figs. 4 and 5 and Table 2 showed
transducers (LVDT) were installed at the quarter points and the following:
midspan sections of each beam to measure strains and vertical • Regardless of the stud cluster spacing and the type of confine-
displacements, respectively, at these locations. These locations ment (1) pre- and postfatigue stress distributions showed almost
were selected because they were at the middistance between two a linear distribution, (2) pre- and postfatigue stresses at extreme
adjacent clusters of studs, where partial composite action and/or tension and compression fibers of the composite beams were
separation between the slab and the beam might occur. The test within the elastic range of the material, and (3) pre- and post-
was conducted by applying the upper limit of the fatigue load fatigue stresses and deflection were almost the same;
as a static load and the measurements were collected (prefatigue • Pre- and postfatigue deflection was in agreement with the
measurements), then the composite beams were exposed to deflection calculated by using the elastic stress theory;
2 million cycles of the fatigue load at 2 Hz. Finally, the composite • Regardless of the type of confinement provided around the stud
beams were loaded statically with the upper limit of the fatigue clusters, the stress distribution and deflection measurements of
load, and the strain and displacement measurements were collected Beam 1 and 2 were almost identical;
(postfatigue measurements). • Regardless of the spacing between the clusters, the stress
Testing went smoothly with no problems for Beam 1. For distribution and deflection measurements of the north side of
Beam 2, the prefatigue measurements were successfully collected the each beam, where closed ties were used for confinement,
before applying the fatigue load and at 1 million cycles. Then the were almost identical to the stress distribution and deflection
test was put on hold to run the annual maintenance of the hydraulic measurements of the south side of the same beam, where steel
system of the actuator. The test was resumed after 2 weeks. During tubes were used; and
this period, no load was applied to the beam. The postfatigue mea- • Visual inspection of the composite beams before, during, and
surements that were planned to be taken at 2 million cycles could after applying the 2 million cycles of fatigue load, showed that
not be collected because the steel beam fractured close to the mid- (1) no cracks on the top surface of the concrete slab were ob-
span section at approximately 1.95 million cycles, as shown in served; (2) no separation between the concrete haunch and the
Fig. 3. The fatigue fracture started at the bottom flange of the steel steel beams occurred, except the separation that occurred in
beam, propagated through the web and stopped at the web-top Beam 2 locally around the location of the fatigue fracture fail-
flange junction. The writers believed that this failure occurred ure; (3) no cracks or signs of distress were observed in the

656 / JOURNAL OF BRIDGE ENGINEERING © ASCE / SEPTEMBER/OCTOBER 2011

J. Bridge Eng., 2011, 16(5): 653-661


Stress (ksi) Stress (ksi)
-5.000 0.000 5.000 10.000 15.000 20.000 25.000 30.000 -5 0 5 10 15 20 25
0 0

4 Concrete 4
Slab
Beam 2:
Post-fatigue
8 8

Elastic
Depth (in.)

Strain

Depth (in.)
12 Theory gauge 12
locations Elastic
Steel Theory
16 16
Beam
Downloaded from ascelibrary.org by NIRMA INSTITUTE OF TECHNOLOGY on 01/31/17. Copyright ASCE. For personal use only; all rights reserved.

20 Beam 1: 20
Beam 1: Pre-fatigue Beam 2:
Post-fatigue Pre-fatigue
24 24

28 28

Fig. 4. Composite section stresses at midspan owing to fatigue load (postfatigue distribution is measured at 2 × 106 cycles for beam 1 and at 1 × 106
cycles for beam 2)

Table 2. Composite Section Deflection Owing to Fatigue Load haunch; and (4) no residual deflection was observed after
Quarter point Quarter point removing the load.
of north side of south side On the basis of these observations, the following conclusions
(confinement: (confinement: were drawn:
closed ties) Midspan steel tubes) 1. It is safe to use Eq. 6.10.10.2-1 of the AASHTO LRFD
Measurement type [mm (in.)] [mm (in.)] [mm (in.)]
Specifications (AASHTO 2007) to determine the fatigue
Beam 1: 610-mm (24-in.) cluster spacing capacity for studs set on clusters and spaced as long as
Elastic theorya 7.52 (0.296) 10.95 (0.431) 7.52 (0.296) 1,220 mm (48 in.);
Prefatigue measurements 6.63 (0.261) 11.43 (0.450) 6.81 (0.268) 2. Full-composite action between precast concrete panels and
Postfatigue measurementsb 7.24 (0.285) 11.10 (0.437) 7.44 (0.293) steel beams can be maintained up to 1,220 mm (48 in.) of
Beam 2: 1,220-mm (48-in.) cluster spacing
spacing between clusters of studs; and
3. Stud clusters confined with closed ties or steel tubes, provide
Elastic theorya 7.52 (0.296) 10.95 (0.431) 7.52 (0.296)
similar behavior when the system is exposed to fatigue load.
Prefatigue measurements 7.77 (0.306) 11.94 (0.470) 7.65 (0.301)
Postfatigue measurementsb 7.65 (0.301) 12.19 (0.480) 7.70 (0.303)

Note: 1 in. = 25.4 mm. Ultimate Testing


a
Neutral axis depth = 221.49 mm (8.72 in.) from top slab fiber; moment of
inertia of composite section = 3:143 × 109 ð7; 551 in4 Þ. To investigate the horizontal shear capacity of the stud clusters, the
b
Postfatigue measurements are measured at 2 × 106 cycles for Beam 1 and 9.75-m (32-ft) span of each beam was divided into two spans, as
at 1 × 106 cycles for Beam 2. shown in Fig. 6. For Beam 1, an intermediate support was installed

0.5 0.5
Elastic Theory 0.45 Elastic Theory
0.45
Beam 1: pre fatigue Beam 2: pre fatigue
0.4 Beam 1: post fatigue 0.4 Beam 2: post fatigue

0.35 0.35
Deflection (in.)
Deflection (in.)

0.3 0.3

0.25 0.25

0.2 0.2

0.15 0.15

0.1 0.1

0.05 0.05

0 0
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90
Load (kips) Load (kips)

Fig. 5. Load-displacement relationship at midspan (postfatigue distribution is measured at 2 × 106 cycles for beam 1 and at 1 × 106 cycles for
beam 2)

JOURNAL OF BRIDGE ENGINEERING © ASCE / SEPTEMBER/OCTOBER 2011 / 657

J. Bridge Eng., 2011, 16(5): 653-661


4 3/4" 5'-4" F 7'-0 3/4" 12'-9 5/8"

N Beam #1 SS

12'-9 5/8" 7'-0 3/4" F 5'-4" 4 3/4"

N Beam #1 S
Downloaded from ascelibrary.org by NIRMA INSTITUTE OF TECHNOLOGY on 01/31/17. Copyright ASCE. For personal use only; all rights reserved.

4 3/4" 5'-5 5/8" F 3'-4" 4'-1 5/8" 11'-10 3/8" 4 3/4"

N Beam #2 Fatigue fracture location S

4 3/4" 12'-11 1/4" 3'-0 3/4" 3'-4" F 5'-5 5/8" 4 3/4"

N Beam #2 Fatigue fracture location S

Fig. 6. Ultimate test arrangements of beams 1 and 2

exactly at midspan. Each half of the beam was tested as a simply Two hydraulic rams, 1,334 kN (300 kip) each, were used to pro-
supported beam under a concentrated load “F”. This was achieved vide for the load “F”. The hydraulic rams were supported on a short
by removing the external support of the far end of the beam, as spreader beam to apply the load as a single concentrated load.
shown in Fig. 6. Therefore, the applied concentrated load provided Before conducting the ultimate test, two modes of failure were
horizontal shear force at the slab/beam interface only on the stud investigated to determine the possible mode of failure of each
clusters located on the simply supported span being tested. beam and the corresponding load “F” required to cause failure
For Beam 2, one intermediate support was added off the fatigue of the composite beam. These modes were (1) flexural failure of
fraction location to create a two-span continuous beam system, as the composite beam, in which the flexural capacity at the full plastic
shown in Fig. 6. This arrangement resulted in two unequal spans, stage was determined in accordance with Article 6.10.7 of the
3.35-m (11-ft) and 6.10-m (20-ft) long. The concentrated load was AASHTO LRFD Specifications (AASHTO 2007); and (2) horizon-
applied on the short span. To guarantee that the horizontal shear tal shear failure, in which Eqs. 6.10.10.4.3-1 and 5.8.4.1-3 of the
force developed by the concentrated load acted only on the stud AASHTO LRFD Specifications (AASHTO 2007) were used to de-
clusters located on the short span, the concrete slab was jack ham- termine the horizontal shear force generated by the shear connec-
mered above the location where the steel beam was fractured to tors and the corresponding flexural capacity was calculated. The
create a real hinge. Also, the external support of the far end was flexural capacity and corresponding concentrated force, “F”, are
provided with a frictionless surface to allow sliding of the support. given in Table 3. According to this investigation, it was expected

Table 3. Mode of Failures and the Corresponding Flexural Capacity, M n , and Applied Load, F
Possible failure modes
Flexural failure at full plastic stage Horizontal shear failure
Mode of failure and corresponding
a
M n and F LRFD article 6.10.7 LRFD Eq. 6.10.10.4.3-1a LRFD Eq. 5.8.4.1-3a applied load reported from testing
Beam 1: 610-mm (24-in.) cluster spacing
Mn N: 2,311.3 k-ft N: 2,120.0 k-ft N: 1,836.6 k-ft N & S: Flexural failure;
S: 2,311.3 k-ft S: 2,120.0 k-ft S: 1,836.6 k-ft slab concrete crushing
F N: 2,722 KN (611.9 kips) N: 2,498 KN (561.6 kips) N: 2,166 KN (487.0 kips) N: 2,615 KN (588 kips)
S: 2,722 KN (611.9 kips) S: 2,498 KN (561.6 kips) S: 2,166 KN (487.0 kips) S: 2,669 KN (600 kips)
Beam 2: 1,220-mm (48-in.) cluster spacing
Mn N: 2,311.3 k-ft N: 1,758.2 k-ft N: 1,554.6 k-ft N: No failure was reached
S: 2,311.3 k-ft S: 1,758.2 k-ft S: 1,554.6 k-ft S: No failure was reached
F N: 3,988 KN (896.7 kips) N: 3,038 KN (683.0 kips) N: 2,688 KN (604.4 kips) N: 2,669 KN (600 kips)
S: 3,981 KN (895.0 kips) S: 3,030 KN (681.3 kips) S: 2,681 KN (602.6 kips) S: 2,669 KN (600 kips)
Note: 1 k-ft ¼ 1;356 N · m; 1 kip ¼ 4:448 KN; 1 in: ¼ 25:4 mm; N = north side of the beam; S = south side of the beam.
a
AASHTO LRFD Specifications (AASHTO 2007)

658 / JOURNAL OF BRIDGE ENGINEERING © ASCE / SEPTEMBER/OCTOBER 2011

J. Bridge Eng., 2011, 16(5): 653-661


that the four beams would fail in horizontal shear before failing in Figs. 7 and 8 show the load-deflection and load-horizontal slip
flexure. relationships of the north and south sides of both beams, respec-
Each simply supported beam was provided with one set of six tively. To maintain consistency when comparing the structural
strain gauges and a deflection measurement device installed at the behavior of the four sides, the load axis in both figures was
location of the applied concentrated load. Three gauges were normalized as the ratio between the testing applied moment and
provided over the slab thickness and three gauges were provided the plastic moment capacity of the composite section. Fig. 9 shows
over the steel beam height, as shown in Fig. 4. Also, the relative the strain distribution at various levels of applied load of the north
horizontal displacement between the concrete slab and the steel
and south sides of Beams 1 and 2, respectively. Analyzing Figs. 7
beam was recorded at the free ends of each composite beam.
through 9, the following conclusions were drawn:
The load was applied at a steady rate of 44.5 kN (10 kips)
1. Regardless the spacing of the stud clusters and the type of
per second until failure occurred or the 2,669 kN (600 kip) maxi-
Downloaded from ascelibrary.org by NIRMA INSTITUTE OF TECHNOLOGY on 01/31/17. Copyright ASCE. For personal use only; all rights reserved.

confinement, all beams were able to develop the stud ultimate


mum capacity of the hydraulic jacks was reached, whichever
capacity given by Eq. 5.8.4.1-3 of the AASHTO LRFD
occurred first.
Specifications (AASHTO 2007).
2. The north and south sides of Beam 1, made with 310-mm
Discussion of Test Results (24-in.) cluster spacing, were able to develop the stud ultimate
capacity given by Eq. 6.10.10.4.3-1 of the AASHTO LRFD
The north and south sides of Beam 1 failed in flexure where the top Specifications (AASHTO 2007). However, it was not possible
fiber of the concrete slab was crushed in compression (see Table 3). to check if the north and south sides of Beam 2, made with
The applied load at failure was approximately 2,669 kN (600 kips) 1,220-mm (48-in.) cluster spacing, could satisfy the capacity
that was equal to maximum capacity of the hydraulic jacks com- given by this equation. The writers believe that Beam 2 would
bined. Vertical and sloped cracks were observed in the concrete be able to satisfy the design capacity of this equation if it did
haunch between the slab and the steel beam, on both sides of not fail in fatigue. The fatigue failure forced the writers to test a
the beam, close to the end support. shorter span of the two sides of this beam, which required a
The north and south sides of Beam 2 were loaded up to the very high applied load that was beyond the capacity of the test
maximum capacity of the hydraulic jacks, 2,669 kN (600 kips), setup.
but they did not show any signs of failure either in horizontal shear 3. The slope of the load-deflection relationship, which is a
at the slab/beam interface or in flexure (see Table 3). measure of the composite beam stiffness, of the four beams
Inspection of the top surface of the concrete slab, of the north is almost the same. This means that extending the stud cluster
and south sides of both beams, showed that a longitudinal splitting spacing to 1,220 mm (48 in.) does not reduce the composite
hairline cracks were formed exactly over the web location of the beam stiffness.
steel beam. The hairline cracks covered almost the full length of 4. Regardless of the cluster spacing, confinement provided by
Beam 1, whereas in Beam 2 the crack covered only the midspan steel tubes or closed ties did not negatively affect either the
area of the north and south sides. The width of the crack of Beams 1 ultimate capacity of the studs or the deflection of the composite
and 2 was 1 mm (0.04 in.) and 0.76 mm (0.03 in.), respectively. beams.

100%
Beam 1: LRFD EQ 6.10.10.4.3-1
90%

Beam 1: LRFD EQ 5.8.4.1-3


80%

Beam 2: LRFD EQ 6.10.10.4.3-1


70%

Beam 1: Beam 2: LRFD EQ 5.8.4.1-3


60% Closed Ties
M applied / Mp (%)

50% Beam 1:
Steel Tubes
40%

30%

20% Beam 2:
Closed Ties
10%
Beam 2:
Steel Tubes
0%
0.00 0.30 0.60 0.90 1.20 1.50
Displacement (in.)

Fig. 7. Load-deflection relationship of beams 1 and 2

JOURNAL OF BRIDGE ENGINEERING © ASCE / SEPTEMBER/OCTOBER 2011 / 659

J. Bridge Eng., 2011, 16(5): 653-661


100%

90% Beam 1:
Steel Tubes
80% Beam 1:
Closed Ties
70%

M applied / Mp (%) 60%

50% Beam 2:
Closed Ties
Downloaded from ascelibrary.org by NIRMA INSTITUTE OF TECHNOLOGY on 01/31/17. Copyright ASCE. For personal use only; all rights reserved.

40% Beam 2:
Steel Tubes
30%

20%

10%

0%
0 0.02 0.04 0.06 0.08 0.1 0.12 0.14 0.16 0.18
Relative Displacement (in.)

Fig. 8. Load-horizontal slip relationship of beams 1 and 2

Concrete Slab
4 M applied / Mp =
94% for Beam 1
68% for Beam 2
8

12

Steel Beam
m
Deptth (in.)

16 Beam 1:
Closed Ties

20 Beam 1:
Beam 2: Steel Tubes
Stee Tubes
Steel ubes
24
Beam 2:
Closed Ties
28
-2.00 -1.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00
Stress (ksi)
Fig. 9. Stress distribution of the full-scale beams 1 and 2 at midspan

5. The beams made with 1,220-mm (48-in.) cluster spacing in which the two sides of Beam 2 did not show any horizontal
showed an approximately 25% increase in deflection and hor- slip during the first period of applying the load (from zero to
izontal slip compared to the beams made with 610-mm (24-in.) approximately 10%).
cluster spacing. The researchers believe that this increase was 6. At the same ratio of applied moment-to-plastic flexural capa-
because of the fracture fatigue failure that occurred at midspan city, Beams 1 and 2 showed almost the same amount of stresses
of Beam 2 during the fatigue test. This can be confirmed in the concrete slab and steel beam.
from Fig. 7, in which the north and south sides of Beam 2 7. The sides, where steel tube confinement was used, showed
showed a 2.54-mm (0.1-in.) instantaneous deflection once a almost that same amount of normal stresses as the sides where
small amount of load was applied. Also, it can be seen in Fig. 8 closed ties confinement was used.

660 / JOURNAL OF BRIDGE ENGINEERING © ASCE / SEPTEMBER/OCTOBER 2011

J. Bridge Eng., 2011, 16(5): 653-661


Removal of the Precast Panel This recommendation is expected to result in approximately a 25%
increase in the required number of studs. Although this conclusion
The precast slabs were removed by jack hammering the concrete may be conservative, the writers believe that it does not signifi-
around the studs. Then the grout around the studs was manually cantly impact the overall economy of bridges. It should be used
removed by using a chisel. The following observations were re- until more testing of full-scale composite beams is conducted.
corded on the condition of the shear studs and the grout surround- The writers encourage the design engineers to use the 31.8-mm
ing them: (1) no grout crushing was detected at the base of the studs (1.25-in.) large studs with precast concrete deck panel systems in-
and the grout was fully bonded to the studs; (2) no cracks were stead of the common 22.2-mm (0.875-in.) studs. Using the large
detected in the welding at the base of the studs; (3) no bearing fail- size studs will (1) reduce the number of studs that need to be
ure was observed in the slab in front of the shear pockets; and (4) no welded by 50%, which will increase the construction speed and
air pockets were detected in the shear pockets or in the haunch, reduce the labor cost; (2) reduce the size of the shear pockets
Downloaded from ascelibrary.org by NIRMA INSTITUTE OF TECHNOLOGY on 01/31/17. Copyright ASCE. For personal use only; all rights reserved.

which shows that hidden shear pockets can be successfully grouted. and the volume of grout needed to fill them, which will reduce
the cost of the deck system; and (3) facilitate deck removal in
the future. The 31.8-mm (1.25-in.) large size stud is currently avail-
Conclusion able in the U.S. market. Also, it has been used successfully used in
Experimental and theoretical investigation conducted in the the Midwest area on composite slab/I-beam bridges.
NCHRP 12-65 project have proven that satisfactory composite ac-
tion between precast concrete panels and steel girders can be
achieved when the spacing between the stud clusters is extended Acknowledgments
up to 1,220 mm (48 in.). The new spacing limit is 200% of the
The research activities reported in this paper have been performed
current limit given by the LRFD Specifications, which reduces
under the National Cooperative Highway Research Program
the number of shear pockets by 50% simplifying fabrication of
projects, under Contract No. NCHRP 12-65 “Full-depth, precast
the precast deck panels. To make this extension possible, the design
concrete bridge deck panel systems.” Special thanks are extended
engineer should consider for the following issues: (1) check for the
to David Beal of the Transportation Research Board (TRB) and
adequacy and anchorage of the transverse reinforcement of the slab
all individuals who have participated in various activities of this
to resist the transverse splitting forces, (2) provide confinement
research project.
around the shear studs to effectively distribute the shear force
among the studs in each cluster of studs, and to protect the grout
at the base of each stud against crushing (In this research, two types
References
of confinement were envisioned and tested, steel tubes and closed
ties. Both types of confinement have been proven effective in AASHTO. (2007). AASHTO LRFD bridge design specifications, 4th Ed.,
achieving these goals. When closed ties are used, it is recom- with the 2008 interim, Washington, DC.
mended to install the lower tie as close as possible to the bottom Badie, S. S., Girgis, F. A., Tadros, M. K., and Nguyen, N. T. (2010).
surface of the panel.), and (3) check bearing stresses in the slab in “Relaxing the stud spacing limit for full-depth precast concrete deck
front of the shear pockets to prevent crushing of the slab concrete. panels supported on steel girders (phase I).” J. Bridge Eng., 15(5),
The experimental investigation has proven that Eq. 6.10.10.2-1 482–492.
of the AASHTO LRFD Specifications (AASHTO 2007) currently Badie, S. S., and Tadros, M. K. (2008). “Full-depth, precast-concrete bridge
deck panel systems.” National Cooperative Highway Research
used to estimate the fatigue capacity does not require modification
Program (NCHRP) Rep. No. 584, Project No. 12-65, Transportation
for design of stud clusters at 1,220 mm (48 in.) spacing. Research Board, Washington, DC.
Eq. 6.10.10.4.3-1, that is currently used to estimate the ultimate Badie, S. S., Tadros, M. K., Kakish, H. K., Splittgerber, D. L., and Baishya,
capacity, should not be used for stud clusters at spacing greater than M. C. (2002). “Large studs for composite action in steel bridge girders.”
610 mm (24 in.). Instead, Eq. 5.8.4.1-3 of the AASHTO LRFD J. Bridge Eng., 7(3), 195–203.
Specifications (AASHTO 2007) should be used to estimate the ul- Wire Reinforcement Institute (WRI) (2010). Manual of standard practice—
timate capacity of stud clusters at spacing up to 1,220 mm (48 in.). Structural welded wire reinforcement, 8th Ed., Hartford, CT.

JOURNAL OF BRIDGE ENGINEERING © ASCE / SEPTEMBER/OCTOBER 2011 / 661

J. Bridge Eng., 2011, 16(5): 653-661

You might also like