Professional Documents
Culture Documents
Abstract: Investigation of the background of the 610 mm (24 in.) spacing of stud shear connectors showed that this limit was set on the basis
of a small amount of testing of beams with spacing greater than this limit. The literature search showed that some attempts have been recently
made to extend this limit. One of the objectives of the NCHRP 12-65 research project was to investigate the possibility of extending this limit
to 1,220 mm (48 in.) for cluster of studs used for precast concrete panels made composite with steel I-beams. The experimental investigation
included testing of push-off specimens and full-scale composite beams. Results of the push-off specimens have shown that the fatigue loading
has no detrimental effect on the load-slip relationship when the number of studs is doubled per cluster. This paper covers the second part of the
experimental investigation, which is fatigue and ultimate testing of full-scale composite beams. The full-scale testing has proven that full-
composite action between precast concrete panels and steel girders can be achieved when the spacing between the stud clusters is extended up
to 1,220 mm (48 in.). DOI: 10.1061/(ASCE)BE.1943-5592.0000215. © 2011 American Society of Civil Engineers.
CE Database subject headings: Shear; Studs; Slabs; Steel beams; Girder bridges; Panels; Spacing; Full-scale tests.
Author keywords: Shear; Connector; Studs; Composite; Precast; Panel; Bridges; Girders.
N Beam #1 S
A B
2 ft 7 spacings @ 4 ft 2 ft
A B
N Beam #2 S
A B
31'-0"
6" 6"
No. 6 Closed Ties Confinment HSS 13x9x5/16 Tube Confinment
Fig. 1. Arrangement of the stud clusters of beams 1 and 2 (X = location of the clusters; N = north side; S = south side)
2"
3"
1/2" 1/2"
5"
1"
1"
3 closed ties 5" HSS 9x7x0.188 5" 6"x6"-W14xW14
6"x6"-W14xW14
with 1 in. 9" 9"
clear spacing
11 1/4"
11 1/4"
Downloaded from ascelibrary.org by NIRMA INSTITUTE OF TECHNOLOGY on 01/31/17. Copyright ASCE. For personal use only; all rights reserved.
W18x119 W18x119
7"
3/4"
#4 closed ties
2 in. grouting hole HSS 9x7x0.188 2 in. grouting hole
Plan view of 4-stud Cluster with Closed Ties Plan view of 4-stud Cluster with HSS Tube
1 in. vent
1 in. vent
1'-3 1/2"
1'-1"
1'-1"
where A1 = net loaded area = (bc xt s ); A2 = maximum area of Table 1 gives the values of the splitting force, T split , the required
the supporting surface that is geometrically similar to and con- area of transverse reinforcement, As , and the bearing stresses of
centric with the loaded area = (effective flange width of the both beams by using Eq. 6.10.10.4.3-1 or Eq. 5.8.4.1-3 of the
slab xt s ); ts = slab thickness, and ϕ = bearing strength reduction AASHTO LRFD Specifications (AASHTO 2007). Table 1 shows
factor = 0.65. that the provided transverse reinforcement in the precast slab was
and tested in tension, which showed that the yield strength was ap-
proximately 352 MPa (51 ksi).
The composite beams were built by supporting the steel beam
on two end supports. Then the precast concrete slabs were installed
and their elevation was adjusted to provide for a 25-mm (1-in.)
haunch. Polystyrene packer rods were used as grout dams, as
shown in Fig. 2, then the nonshrink grout was cast to fill the shear
Fig. 3. Fatigue fracture failure of composite beam 2 (images by S. S.
pockets and the haunch through the 51-mm (2-in.) diameter holes Badie and M. K. Tadros)
that were provide in the shear pocket. As a result of this construc-
tion scenario, the weight of the steel beam and the concrete slab did
not provide any horizontal shear tresses on the studs.
because the steel beam was exposed to a very high number of
fatigue cycles (over 20 million cycles) in other research projects
Fatigue Test before it was used in building Beam 2 for this research project.
As a result of the unexpected fracture failure, a 13-mm (.5-in.)
The composite beams were exposed to 2 million cycles of fatigue
separation between the slab and the steel beam was developed over
load, by applying a concentrated load at the midspan section of
a distance of approximately 610 mm (24 in.) around the failure lo-
each beam. This setup put all stud clusters under a uniform hori-
cation. The composite beam was thoroughly inspected and no other
zontal shear force produced only by the applied load. The upper
limit of the fatigue concentrated load at midspan was set to cracks or signs of distress were detected.
384.3 kN (86.4 kips). This value was determined by using the stud Fig. 4 shows the pre- and postfatigue stress distribution at mid-
fatigue resistance given by Eq. 6.10.10.2-1 of the AASHTO LRFD span of both beams and compares them with the stresses calculated
Specifications (AASHTO 2007) and the section properties. A mini- by using the elastic stress theory assuming full-composite action.
mum load of 7.1 kN (1.6 kips) was used as the lower limit of the Table 2 gives the deflection of the composite beams at the quarter
fatigue load to maintain stability of the test setup. Normal stresses points and midspan before and after applying the fatigue load and
in the concrete slab and the steel beam were checked and found to compares them with the elastic theory values. Also, Fig. 5 gives the
be within the elastic limit of both materials. load-displacement relationship at midspan before and after apply-
A series of strain gauges and linear voltage displacement ing the fatigue load. Examining Figs. 4 and 5 and Table 2 showed
transducers (LVDT) were installed at the quarter points and the following:
midspan sections of each beam to measure strains and vertical • Regardless of the stud cluster spacing and the type of confine-
displacements, respectively, at these locations. These locations ment (1) pre- and postfatigue stress distributions showed almost
were selected because they were at the middistance between two a linear distribution, (2) pre- and postfatigue stresses at extreme
adjacent clusters of studs, where partial composite action and/or tension and compression fibers of the composite beams were
separation between the slab and the beam might occur. The test within the elastic range of the material, and (3) pre- and post-
was conducted by applying the upper limit of the fatigue load fatigue stresses and deflection were almost the same;
as a static load and the measurements were collected (prefatigue • Pre- and postfatigue deflection was in agreement with the
measurements), then the composite beams were exposed to deflection calculated by using the elastic stress theory;
2 million cycles of the fatigue load at 2 Hz. Finally, the composite • Regardless of the type of confinement provided around the stud
beams were loaded statically with the upper limit of the fatigue clusters, the stress distribution and deflection measurements of
load, and the strain and displacement measurements were collected Beam 1 and 2 were almost identical;
(postfatigue measurements). • Regardless of the spacing between the clusters, the stress
Testing went smoothly with no problems for Beam 1. For distribution and deflection measurements of the north side of
Beam 2, the prefatigue measurements were successfully collected the each beam, where closed ties were used for confinement,
before applying the fatigue load and at 1 million cycles. Then the were almost identical to the stress distribution and deflection
test was put on hold to run the annual maintenance of the hydraulic measurements of the south side of the same beam, where steel
system of the actuator. The test was resumed after 2 weeks. During tubes were used; and
this period, no load was applied to the beam. The postfatigue mea- • Visual inspection of the composite beams before, during, and
surements that were planned to be taken at 2 million cycles could after applying the 2 million cycles of fatigue load, showed that
not be collected because the steel beam fractured close to the mid- (1) no cracks on the top surface of the concrete slab were ob-
span section at approximately 1.95 million cycles, as shown in served; (2) no separation between the concrete haunch and the
Fig. 3. The fatigue fracture started at the bottom flange of the steel steel beams occurred, except the separation that occurred in
beam, propagated through the web and stopped at the web-top Beam 2 locally around the location of the fatigue fracture fail-
flange junction. The writers believed that this failure occurred ure; (3) no cracks or signs of distress were observed in the
4 Concrete 4
Slab
Beam 2:
Post-fatigue
8 8
Elastic
Depth (in.)
Strain
Depth (in.)
12 Theory gauge 12
locations Elastic
Steel Theory
16 16
Beam
Downloaded from ascelibrary.org by NIRMA INSTITUTE OF TECHNOLOGY on 01/31/17. Copyright ASCE. For personal use only; all rights reserved.
20 Beam 1: 20
Beam 1: Pre-fatigue Beam 2:
Post-fatigue Pre-fatigue
24 24
28 28
Fig. 4. Composite section stresses at midspan owing to fatigue load (postfatigue distribution is measured at 2 × 106 cycles for beam 1 and at 1 × 106
cycles for beam 2)
Table 2. Composite Section Deflection Owing to Fatigue Load haunch; and (4) no residual deflection was observed after
Quarter point Quarter point removing the load.
of north side of south side On the basis of these observations, the following conclusions
(confinement: (confinement: were drawn:
closed ties) Midspan steel tubes) 1. It is safe to use Eq. 6.10.10.2-1 of the AASHTO LRFD
Measurement type [mm (in.)] [mm (in.)] [mm (in.)]
Specifications (AASHTO 2007) to determine the fatigue
Beam 1: 610-mm (24-in.) cluster spacing capacity for studs set on clusters and spaced as long as
Elastic theorya 7.52 (0.296) 10.95 (0.431) 7.52 (0.296) 1,220 mm (48 in.);
Prefatigue measurements 6.63 (0.261) 11.43 (0.450) 6.81 (0.268) 2. Full-composite action between precast concrete panels and
Postfatigue measurementsb 7.24 (0.285) 11.10 (0.437) 7.44 (0.293) steel beams can be maintained up to 1,220 mm (48 in.) of
Beam 2: 1,220-mm (48-in.) cluster spacing
spacing between clusters of studs; and
3. Stud clusters confined with closed ties or steel tubes, provide
Elastic theorya 7.52 (0.296) 10.95 (0.431) 7.52 (0.296)
similar behavior when the system is exposed to fatigue load.
Prefatigue measurements 7.77 (0.306) 11.94 (0.470) 7.65 (0.301)
Postfatigue measurementsb 7.65 (0.301) 12.19 (0.480) 7.70 (0.303)
0.5 0.5
Elastic Theory 0.45 Elastic Theory
0.45
Beam 1: pre fatigue Beam 2: pre fatigue
0.4 Beam 1: post fatigue 0.4 Beam 2: post fatigue
0.35 0.35
Deflection (in.)
Deflection (in.)
0.3 0.3
0.25 0.25
0.2 0.2
0.15 0.15
0.1 0.1
0.05 0.05
0 0
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90
Load (kips) Load (kips)
Fig. 5. Load-displacement relationship at midspan (postfatigue distribution is measured at 2 × 106 cycles for beam 1 and at 1 × 106 cycles for
beam 2)
N Beam #1 SS
N Beam #1 S
Downloaded from ascelibrary.org by NIRMA INSTITUTE OF TECHNOLOGY on 01/31/17. Copyright ASCE. For personal use only; all rights reserved.
exactly at midspan. Each half of the beam was tested as a simply Two hydraulic rams, 1,334 kN (300 kip) each, were used to pro-
supported beam under a concentrated load “F”. This was achieved vide for the load “F”. The hydraulic rams were supported on a short
by removing the external support of the far end of the beam, as spreader beam to apply the load as a single concentrated load.
shown in Fig. 6. Therefore, the applied concentrated load provided Before conducting the ultimate test, two modes of failure were
horizontal shear force at the slab/beam interface only on the stud investigated to determine the possible mode of failure of each
clusters located on the simply supported span being tested. beam and the corresponding load “F” required to cause failure
For Beam 2, one intermediate support was added off the fatigue of the composite beam. These modes were (1) flexural failure of
fraction location to create a two-span continuous beam system, as the composite beam, in which the flexural capacity at the full plastic
shown in Fig. 6. This arrangement resulted in two unequal spans, stage was determined in accordance with Article 6.10.7 of the
3.35-m (11-ft) and 6.10-m (20-ft) long. The concentrated load was AASHTO LRFD Specifications (AASHTO 2007); and (2) horizon-
applied on the short span. To guarantee that the horizontal shear tal shear failure, in which Eqs. 6.10.10.4.3-1 and 5.8.4.1-3 of the
force developed by the concentrated load acted only on the stud AASHTO LRFD Specifications (AASHTO 2007) were used to de-
clusters located on the short span, the concrete slab was jack ham- termine the horizontal shear force generated by the shear connec-
mered above the location where the steel beam was fractured to tors and the corresponding flexural capacity was calculated. The
create a real hinge. Also, the external support of the far end was flexural capacity and corresponding concentrated force, “F”, are
provided with a frictionless surface to allow sliding of the support. given in Table 3. According to this investigation, it was expected
Table 3. Mode of Failures and the Corresponding Flexural Capacity, M n , and Applied Load, F
Possible failure modes
Flexural failure at full plastic stage Horizontal shear failure
Mode of failure and corresponding
a
M n and F LRFD article 6.10.7 LRFD Eq. 6.10.10.4.3-1a LRFD Eq. 5.8.4.1-3a applied load reported from testing
Beam 1: 610-mm (24-in.) cluster spacing
Mn N: 2,311.3 k-ft N: 2,120.0 k-ft N: 1,836.6 k-ft N & S: Flexural failure;
S: 2,311.3 k-ft S: 2,120.0 k-ft S: 1,836.6 k-ft slab concrete crushing
F N: 2,722 KN (611.9 kips) N: 2,498 KN (561.6 kips) N: 2,166 KN (487.0 kips) N: 2,615 KN (588 kips)
S: 2,722 KN (611.9 kips) S: 2,498 KN (561.6 kips) S: 2,166 KN (487.0 kips) S: 2,669 KN (600 kips)
Beam 2: 1,220-mm (48-in.) cluster spacing
Mn N: 2,311.3 k-ft N: 1,758.2 k-ft N: 1,554.6 k-ft N: No failure was reached
S: 2,311.3 k-ft S: 1,758.2 k-ft S: 1,554.6 k-ft S: No failure was reached
F N: 3,988 KN (896.7 kips) N: 3,038 KN (683.0 kips) N: 2,688 KN (604.4 kips) N: 2,669 KN (600 kips)
S: 3,981 KN (895.0 kips) S: 3,030 KN (681.3 kips) S: 2,681 KN (602.6 kips) S: 2,669 KN (600 kips)
Note: 1 k-ft ¼ 1;356 N · m; 1 kip ¼ 4:448 KN; 1 in: ¼ 25:4 mm; N = north side of the beam; S = south side of the beam.
a
AASHTO LRFD Specifications (AASHTO 2007)
100%
Beam 1: LRFD EQ 6.10.10.4.3-1
90%
50% Beam 1:
Steel Tubes
40%
30%
20% Beam 2:
Closed Ties
10%
Beam 2:
Steel Tubes
0%
0.00 0.30 0.60 0.90 1.20 1.50
Displacement (in.)
90% Beam 1:
Steel Tubes
80% Beam 1:
Closed Ties
70%
50% Beam 2:
Closed Ties
Downloaded from ascelibrary.org by NIRMA INSTITUTE OF TECHNOLOGY on 01/31/17. Copyright ASCE. For personal use only; all rights reserved.
40% Beam 2:
Steel Tubes
30%
20%
10%
0%
0 0.02 0.04 0.06 0.08 0.1 0.12 0.14 0.16 0.18
Relative Displacement (in.)
Concrete Slab
4 M applied / Mp =
94% for Beam 1
68% for Beam 2
8
12
Steel Beam
m
Deptth (in.)
16 Beam 1:
Closed Ties
20 Beam 1:
Beam 2: Steel Tubes
Stee Tubes
Steel ubes
24
Beam 2:
Closed Ties
28
-2.00 -1.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00
Stress (ksi)
Fig. 9. Stress distribution of the full-scale beams 1 and 2 at midspan
5. The beams made with 1,220-mm (48-in.) cluster spacing in which the two sides of Beam 2 did not show any horizontal
showed an approximately 25% increase in deflection and hor- slip during the first period of applying the load (from zero to
izontal slip compared to the beams made with 610-mm (24-in.) approximately 10%).
cluster spacing. The researchers believe that this increase was 6. At the same ratio of applied moment-to-plastic flexural capa-
because of the fracture fatigue failure that occurred at midspan city, Beams 1 and 2 showed almost the same amount of stresses
of Beam 2 during the fatigue test. This can be confirmed in the concrete slab and steel beam.
from Fig. 7, in which the north and south sides of Beam 2 7. The sides, where steel tube confinement was used, showed
showed a 2.54-mm (0.1-in.) instantaneous deflection once a almost that same amount of normal stresses as the sides where
small amount of load was applied. Also, it can be seen in Fig. 8 closed ties confinement was used.
which shows that hidden shear pockets can be successfully grouted. and the volume of grout needed to fill them, which will reduce
the cost of the deck system; and (3) facilitate deck removal in
the future. The 31.8-mm (1.25-in.) large size stud is currently avail-
Conclusion able in the U.S. market. Also, it has been used successfully used in
Experimental and theoretical investigation conducted in the the Midwest area on composite slab/I-beam bridges.
NCHRP 12-65 project have proven that satisfactory composite ac-
tion between precast concrete panels and steel girders can be
achieved when the spacing between the stud clusters is extended Acknowledgments
up to 1,220 mm (48 in.). The new spacing limit is 200% of the
The research activities reported in this paper have been performed
current limit given by the LRFD Specifications, which reduces
under the National Cooperative Highway Research Program
the number of shear pockets by 50% simplifying fabrication of
projects, under Contract No. NCHRP 12-65 “Full-depth, precast
the precast deck panels. To make this extension possible, the design
concrete bridge deck panel systems.” Special thanks are extended
engineer should consider for the following issues: (1) check for the
to David Beal of the Transportation Research Board (TRB) and
adequacy and anchorage of the transverse reinforcement of the slab
all individuals who have participated in various activities of this
to resist the transverse splitting forces, (2) provide confinement
research project.
around the shear studs to effectively distribute the shear force
among the studs in each cluster of studs, and to protect the grout
at the base of each stud against crushing (In this research, two types
References
of confinement were envisioned and tested, steel tubes and closed
ties. Both types of confinement have been proven effective in AASHTO. (2007). AASHTO LRFD bridge design specifications, 4th Ed.,
achieving these goals. When closed ties are used, it is recom- with the 2008 interim, Washington, DC.
mended to install the lower tie as close as possible to the bottom Badie, S. S., Girgis, F. A., Tadros, M. K., and Nguyen, N. T. (2010).
surface of the panel.), and (3) check bearing stresses in the slab in “Relaxing the stud spacing limit for full-depth precast concrete deck
front of the shear pockets to prevent crushing of the slab concrete. panels supported on steel girders (phase I).” J. Bridge Eng., 15(5),
The experimental investigation has proven that Eq. 6.10.10.2-1 482–492.
of the AASHTO LRFD Specifications (AASHTO 2007) currently Badie, S. S., and Tadros, M. K. (2008). “Full-depth, precast-concrete bridge
deck panel systems.” National Cooperative Highway Research
used to estimate the fatigue capacity does not require modification
Program (NCHRP) Rep. No. 584, Project No. 12-65, Transportation
for design of stud clusters at 1,220 mm (48 in.) spacing. Research Board, Washington, DC.
Eq. 6.10.10.4.3-1, that is currently used to estimate the ultimate Badie, S. S., Tadros, M. K., Kakish, H. K., Splittgerber, D. L., and Baishya,
capacity, should not be used for stud clusters at spacing greater than M. C. (2002). “Large studs for composite action in steel bridge girders.”
610 mm (24 in.). Instead, Eq. 5.8.4.1-3 of the AASHTO LRFD J. Bridge Eng., 7(3), 195–203.
Specifications (AASHTO 2007) should be used to estimate the ul- Wire Reinforcement Institute (WRI) (2010). Manual of standard practice—
timate capacity of stud clusters at spacing up to 1,220 mm (48 in.). Structural welded wire reinforcement, 8th Ed., Hartford, CT.