BHG COMITTED DATES ACTUAL DURATION DEVIATION WRT COMITTED BHG DATES

S.No DESCRIPTION AS PER AS PER AS PER 27/12/2019 AS PER COMPLETION WRT WRT WRT WRT
07/09/2019 MAIL 31/10/2019 MAIL DOCUMENT 28/02/2020 MAIL DATE 07/09/2019 MAIL 31/10/2019 MAIL 27/12/2019 DOC. 28/02/2020 MAIL
DRIVE SIDE
1 FIRST SLAB CASTING @ +6.50 MTS 11/15/2019
2 SECOND SLAB CASTING @ +6.50 MTS 10/31/2019 11/22/2019 22 22
3 THIRD SLAB CASTING @ +6.50 MTS 11/30/2019 12/5/2019 12/16/2019 16 11 16
4 FIRST SLAB CASTING @ +12.00 MTS 2/10/2020 -24 -30
5 SECOND SLAB CASTING @ +12.00 MTS 3/5/2020 3/11/2020 2/21/2020 -13 -19
6 THIRD SLAB CASTING @ +12.00 MTS 3/12/2020 7 1
7 SLAB CASTING @ +16.00 MTS 3/5/2020 2/26/2020 -8
NON - DRIVE SIDE
8 FIRST SLAB CASTING @ +6.50 MTS 11/25/2019 12/5/2019 1/11/2020 47 37 -20 -56
9 SECOND SLAB CASTING @ +6.50 MTS 12/25/2019 1/31/2020 3/7/2020 3/11/2020 77 40 4
10 THIRD SLAB CASTING @ +6.50 MTS 1/30/2020 4/5/2020 66 65 29
11 FIRST SLAB CASTING @ +12.00 MTS 5/3/2020 65 46
3/18/2020
12 SECOND SLAB CASTING @ +12.00 MTS 2/28/2020 5/6/2020 68 60
13 THIRD SLAB CASTING @ +12.00 MTS 3/28/2020 6/12/2020 105 97
DRIVE & NON-DRIVE SIDE
14 MACHINE SEAL BEAM - WIRE PART 11/30/2019 2/22/2020 84 28
15 MACHINE SEAL BEAM - DRYER PART 1/25/2020 2/23/2020 29
16 MACHINE SEAL BEAM - REEL PART 2/24/2020 30
EOT CRANE BRACKETS & TRUSS COLUMNS
14 1ST SPAN 3/31/2020
ND
15 2 SPAN
4/30/2020
16 3RD SPAN

You might also like